SlideShare a Scribd company logo
PROJECT QUALITY
MANAGEMENT
FINAL PRESENTATION
VERTEX ENGINEERING QUALITY PLAN
GROUP MEMBERS: MUHAMMAD MOHSIN 10506
SYED ZIYAD BIN HASAN 11091
INTRODUCTION
 Vertex engineers are professionals who specialize in the design, analysis,
and optimization of geometric shapes and structures. They use their
knowledge of mathematics, physics, and engineering principles to create
designs that are both structurally sound and efficient. They are also
involved in the construction, maintenance and repair of buildings, bridges,
and other structures. They often work closely with architects, designers,
and other engineers to ensure that the final product meets the needs of
the client and adheres to relevant safety and building codes.
QUALITY MANAGEMENT OBJECTIVES
The Quality Plan to be instituted by Vertex Engineering for the construction of
the 1000 sq. yd. in precinct 36 sports city villa’s bahria town karachi.
The plan is Vertex Engineering project team’s documentation of the organizational
structure, functional responsibility, levels of authority, and lines of communications
for the activities that affect quality.
 1) Verify that all provisions have been made to provide required control testing.
 2) Monitor the design, and contractor’s daily work progress.
 3) Check dimensional requirements.
 4) Visually inspects materials received on site for proper documentation,
completeness, and condition.
 5) Observe all required tests such as mechanical and electrical to verify that they are in
compliance with the specifications.
 6) Ensure the completion of all deficiencies in materials and workmanship in a timely
manner.
 7) Maintain a document control file.
 8) Work closely with all testing agencies to verify that all required tests are able to be
performed.
QUALITY MANAGEMENT PROCESS
 Vertex Engineering will review drawings at each of the above stages of
completion to ensure constructibility and functionality. These reviews will also be
used to ensure that schedule and budget remain in compliance.
 Vertex Engineering will provide contract document timeline requirements to the
consultants to ensure that the overall project schedule is maintained.
QUALITY CHARACTERISTICS
Vertex Engineering Quality Plan will ensure a uniform high quality level of
workmanship through all phases of construction, including planning, construction,
and turnover. To meet this goal, the following principles will be observed:
1) Ensure the highest level of quality by maintaining supervised controls and written
instructions governing Quality Control procedures and practices.
2) Establish clearly defined responsibility and authority for compliance.
3) Meet contractual requirements by conformance to Contract Documents and
applicable standards.
The techniques that will be used for quality planning are the following ones:
  Cost-benefit analysis;
  Cost of Quality (CoQ);
  Benchmarking;
  Statistical sampling;
  Quality Requirements Prioritisation (MoSCoW – Must have, Should have,
Could have, or Won't have).
PERFORM QUALITY ASSURANCE
Quality assurance will be performed by evaluating:
 the design of the project controls, by confirming that they are implemented, and
by assessing their operational effectiveness. These activities will consider the
project quality objectives along with the project risks.
 compliance with the organisation’s rules and regulations, as well as with relevant
governmental and industry rules, regulations and legislation.
PERFORM QUALITY CONTROL
The purpose of this step is to monitor and consolidate results from the quality
assurance activities in The CQCP will be implemented in order to ensure compliance
with the specifications for building construction as detailed in the contract
specifications.
The QCM will be responsible for implementing the CQC Plan by ensuring
that quality materials and supplies are providedfor the proposed project, and that
good workmanship is provided in all aspects of this contract. The QCM will report
directly to the CM and/or On-site Project Manager and will complete daily site
inspections to ensure compliance with the quality control specifications.
PERFORM DELIVERABLES ACCEPTANCE
The purpose of this step is to obtain formal approval from the Project Owner (PO) for
each project deliverable. It comprises the verification if deliverables meet the
predefined objectives and set of criteria defined in the Deliverables Acceptance Plan,
so that the Project Owner (PO) can formally accept them, in the Deliverables
Acceptance Note.
The Deliverables Acceptance Checklist supports the monitoring of the status of all
activities that are pre-condition to the delivery of project outputs to the Project Owner
(PO) and the formal acceptance from him/her.
PERFORM FINAL ACCEPTANCE
The purpose of this step is to manage the final acceptance of the project, including the
accepted deliverables and to perform the administrative closure of the project. The
final acceptance is obtained from the Project Owner (PO), through a formal Project
Acceptance Note.
Before the formal project sign-off, the Project Manager (PM) should report on project
performance in the Project-End Review Meeting, discuss lessons learned and develop
the Project-End Report.
QUALITY MANAGEMENT ROLES &
RESPONSIBILITIES
The following RASCI table defines the responsibilities of those involved in quality
management:
TOOLS & TECHNIQUES
The following techniques will be used for project quality management:
 Audits;
 Walkthroughs;
 Benchmarking;
 Questionnaires;
 Peer reviews;
 Acceptance testing;
 Project Review Meetings;
The following tools will be used for project quality management:
 PM Quality Management Plan;
 PM Deliverables Acceptance Plan;
 PM Quality Review Checklist;
 PM Deliverables Acceptance Checklist;
 PM Phase-exit Review Checklist;
 PM Quality Review Report;
 PM Project-End Report;
 Deliverables Acceptance Note;
 Project Acceptance Note;
FIELD INSPECTION
 Pre-Work Coordination Meeting’s
 Follow-Up Inspection.
 Completion Inspection
MATERIAL TEST PROCEDURES
A. Testing
 The appropriate Consultant will take random samples and test them for
conformance with the contract documents. These results will be distributed to all
parties. The Quality Control Coordinator will review all test results and follow up
as appropriate.
B. Samples
 Approved samples of materials to be incorporated into the job will be maintained
in the site office for use in comparing to installed material. Site mock-ups, as
required, will bemaintained during construction at a designated location on site.
 Testing samples will be individually identified by The appropriate Consultant.
QUALITY REPORTS
The quality records (evidence that quality management activities have been performed) are archived
in the project repository, under the "Monitor & Control" folder. The different versions of the project
artefacts (created at each artefact update) will provide evidence of the performance of these
activities.
 1. Inspection reports: Inspection reports should be kept for all quality control activities,
including material inspections, workmanship inspections, and final inspections. These reports
should include details on the items inspected, any issues or non-compliances found, and the
actions taken to address them.
 2. Test and commissioning reports: Reports detailing the results of all tests and commissioning
activities should be kept on file. This includes information on the systems and
equipment tested, the test results, and any issues that were identified and addressed.
 3. Maintenance records: Records of all maintenance activities should be kept, including the date
of the maintenance, the equipment or systems that were maintained, and any issues that were
identified and addressed.
THANK YOU

More Related Content

What's hot

Project manager-roles and responsibilities
Project manager-roles and responsibilitiesProject manager-roles and responsibilities
Project manager-roles and responsibilitiescollege
 
PMI Project Management Principles
PMI Project Management PrinciplesPMI Project Management Principles
PMI Project Management Principles
tltiede
 
Project integration management
Project integration managementProject integration management
Project integration management
Prabudh Dhingra
 
Chap 9.1 Pan Resource Management
Chap 9.1   Pan Resource ManagementChap 9.1   Pan Resource Management
Chap 9.1 Pan Resource Management
Anand Bobade
 
Pmp study-notes
Pmp study-notesPmp study-notes
Pmp study-notes
Krishna Murthy RVN
 
7 Steps Project Execution Process
7 Steps Project Execution Process7 Steps Project Execution Process
7 Steps Project Execution Process
C K Vishwakarma
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
Procept Associates
 
Project scope management
Project scope managementProject scope management
Project scope management
Anit Roy
 
PMP Chap 2- Org. Influence and Project Life Cycle
PMP Chap 2- Org. Influence and Project Life CyclePMP Chap 2- Org. Influence and Project Life Cycle
PMP Chap 2- Org. Influence and Project Life Cycle
Anand Bobade
 
Project Management - PMI Approach
Project Management - PMI ApproachProject Management - PMI Approach
Project Management - PMI Approach
Zaur Ahmadov, PMP
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
Mauro Jasse
 
7.3 Determine Budget
7.3 Determine Budget7.3 Determine Budget
7.3 Determine Budget
DavidMcLachlan1
 
P3O
P3O P3O
Chap 8.0 Quality Management Overview
Chap 8.0 Quality Management OverviewChap 8.0 Quality Management Overview
Chap 8.0 Quality Management Overview
Anand Bobade
 
Lecture 05:Advanced Project Management PM Processes and Framework
Lecture 05:Advanced Project Management   PM Processes and FrameworkLecture 05:Advanced Project Management   PM Processes and Framework
Lecture 05:Advanced Project Management PM Processes and Framework
Fida Karim 🇵🇰
 
Pmbok6 to 7 transformation
Pmbok6 to 7 transformationPmbok6 to 7 transformation
Pmbok6 to 7 transformation
Zaur Ahmadov, PMP
 
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo
 
Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7
Saad Merie
 
Cost Management PMBOK
Cost Management PMBOKCost Management PMBOK
Cost Management PMBOK
Wasis Witjaksono
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of scheduling
jmd2011
 

What's hot (20)

Project manager-roles and responsibilities
Project manager-roles and responsibilitiesProject manager-roles and responsibilities
Project manager-roles and responsibilities
 
PMI Project Management Principles
PMI Project Management PrinciplesPMI Project Management Principles
PMI Project Management Principles
 
Project integration management
Project integration managementProject integration management
Project integration management
 
Chap 9.1 Pan Resource Management
Chap 9.1   Pan Resource ManagementChap 9.1   Pan Resource Management
Chap 9.1 Pan Resource Management
 
Pmp study-notes
Pmp study-notesPmp study-notes
Pmp study-notes
 
7 Steps Project Execution Process
7 Steps Project Execution Process7 Steps Project Execution Process
7 Steps Project Execution Process
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 
Project scope management
Project scope managementProject scope management
Project scope management
 
PMP Chap 2- Org. Influence and Project Life Cycle
PMP Chap 2- Org. Influence and Project Life CyclePMP Chap 2- Org. Influence and Project Life Cycle
PMP Chap 2- Org. Influence and Project Life Cycle
 
Project Management - PMI Approach
Project Management - PMI ApproachProject Management - PMI Approach
Project Management - PMI Approach
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
7.3 Determine Budget
7.3 Determine Budget7.3 Determine Budget
7.3 Determine Budget
 
P3O
P3O P3O
P3O
 
Chap 8.0 Quality Management Overview
Chap 8.0 Quality Management OverviewChap 8.0 Quality Management Overview
Chap 8.0 Quality Management Overview
 
Lecture 05:Advanced Project Management PM Processes and Framework
Lecture 05:Advanced Project Management   PM Processes and FrameworkLecture 05:Advanced Project Management   PM Processes and Framework
Lecture 05:Advanced Project Management PM Processes and Framework
 
Pmbok6 to 7 transformation
Pmbok6 to 7 transformationPmbok6 to 7 transformation
Pmbok6 to 7 transformation
 
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
 
Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7
 
Cost Management PMBOK
Cost Management PMBOKCost Management PMBOK
Cost Management PMBOK
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of scheduling
 

Similar to Project Quality Management PPT.pptx

Project Quality Management Final Report.docx
Project Quality Management  Final Report.docxProject Quality Management  Final Report.docx
Project Quality Management Final Report.docx
Ziyad Zaidi
 
Quality control inspection reports and outcomes wrt contract management
Quality control inspection reports and outcomes wrt contract managementQuality control inspection reports and outcomes wrt contract management
Quality control inspection reports and outcomes wrt contract management
EdwinJacob5
 
Quality management
Quality managementQuality management
Quality management
charliesleopanadan
 
Quality Assurance & Quality Control
Quality Assurance & Quality ControlQuality Assurance & Quality Control
Quality Assurance & Quality Control
Pintu Badatiya
 
Quality_Management_Plan Template.docx
Quality_Management_Plan Template.docxQuality_Management_Plan Template.docx
Quality_Management_Plan Template.docx
Ziyad Zaidi
 
Quality plan
Quality planQuality plan
www.FASTProjectPlans.comQuality Management Plan Template· .docx
www.FASTProjectPlans.comQuality Management Plan Template· .docxwww.FASTProjectPlans.comQuality Management Plan Template· .docx
www.FASTProjectPlans.comQuality Management Plan Template· .docx
ericbrooks84875
 
Pradeep ramakrishnan cv 2018
Pradeep ramakrishnan   cv 2018Pradeep ramakrishnan   cv 2018
Pradeep ramakrishnan cv 2018
Pradeep Ramakrishnan
 
Module 6 qaqc training
Module 6 qaqc trainingModule 6 qaqc training
Module 6 qaqc training
Diaz Susetyo
 
QA/QC Manager-Civil
QA/QC Manager-Civil QA/QC Manager-Civil
QA/QC Manager-Civil
Seshadhri balakrishnan
 
Implementation of quality management concepts in managing Engineering Project...
Implementation of quality management concepts in managing Engineering Project...Implementation of quality management concepts in managing Engineering Project...
Implementation of quality management concepts in managing Engineering Project...
SIBENDU SURAJEET JENA
 
1661351047Unit 8 1060-V1 Quality Control during Construction.pdf
1661351047Unit 8 1060-V1 Quality Control during Construction.pdf1661351047Unit 8 1060-V1 Quality Control during Construction.pdf
1661351047Unit 8 1060-V1 Quality Control during Construction.pdf
ahsansaeed78
 
Raguram palnichamy jun 2019
Raguram palnichamy jun 2019Raguram palnichamy jun 2019
Raguram palnichamy jun 2019
RaguramPalanichamy
 
ECSS-Q-ST-20C Supplier Responsibilities
ECSS-Q-ST-20C Supplier ResponsibilitiesECSS-Q-ST-20C Supplier Responsibilities
ECSS-Q-ST-20C Supplier ResponsibilitiesAndrew Whittaker
 
10 me667 chap6 performance measures
10 me667 chap6 performance measures10 me667 chap6 performance measures
10 me667 chap6 performance measuresPavan Kumar
 
Adnan Resume revised
Adnan Resume revisedAdnan Resume revised
Adnan Resume revisedAdnan Rehmat
 

Similar to Project Quality Management PPT.pptx (20)

Project Quality Management Final Report.docx
Project Quality Management  Final Report.docxProject Quality Management  Final Report.docx
Project Quality Management Final Report.docx
 
Quality control inspection reports and outcomes wrt contract management
Quality control inspection reports and outcomes wrt contract managementQuality control inspection reports and outcomes wrt contract management
Quality control inspection reports and outcomes wrt contract management
 
Quality management
Quality managementQuality management
Quality management
 
MUHAMMAD ZEESHAN
MUHAMMAD ZEESHANMUHAMMAD ZEESHAN
MUHAMMAD ZEESHAN
 
Quality Assurance & Quality Control
Quality Assurance & Quality ControlQuality Assurance & Quality Control
Quality Assurance & Quality Control
 
Quality_Management_Plan Template.docx
Quality_Management_Plan Template.docxQuality_Management_Plan Template.docx
Quality_Management_Plan Template.docx
 
UPDATED RESUME 2016
UPDATED RESUME 2016UPDATED RESUME 2016
UPDATED RESUME 2016
 
Quality plan
Quality planQuality plan
Quality plan
 
CV Pholapatra Latest Rev 05
CV Pholapatra Latest Rev 05CV Pholapatra Latest Rev 05
CV Pholapatra Latest Rev 05
 
www.FASTProjectPlans.comQuality Management Plan Template· .docx
www.FASTProjectPlans.comQuality Management Plan Template· .docxwww.FASTProjectPlans.comQuality Management Plan Template· .docx
www.FASTProjectPlans.comQuality Management Plan Template· .docx
 
Pradeep ramakrishnan cv 2018
Pradeep ramakrishnan   cv 2018Pradeep ramakrishnan   cv 2018
Pradeep ramakrishnan cv 2018
 
Module 6 qaqc training
Module 6 qaqc trainingModule 6 qaqc training
Module 6 qaqc training
 
QA/QC Manager-Civil
QA/QC Manager-Civil QA/QC Manager-Civil
QA/QC Manager-Civil
 
Implementation of quality management concepts in managing Engineering Project...
Implementation of quality management concepts in managing Engineering Project...Implementation of quality management concepts in managing Engineering Project...
Implementation of quality management concepts in managing Engineering Project...
 
1661351047Unit 8 1060-V1 Quality Control during Construction.pdf
1661351047Unit 8 1060-V1 Quality Control during Construction.pdf1661351047Unit 8 1060-V1 Quality Control during Construction.pdf
1661351047Unit 8 1060-V1 Quality Control during Construction.pdf
 
Raguram palnichamy jun 2019
Raguram palnichamy jun 2019Raguram palnichamy jun 2019
Raguram palnichamy jun 2019
 
ECSS-Q-ST-20C Supplier Responsibilities
ECSS-Q-ST-20C Supplier ResponsibilitiesECSS-Q-ST-20C Supplier Responsibilities
ECSS-Q-ST-20C Supplier Responsibilities
 
10 me667 chap6 performance measures
10 me667 chap6 performance measures10 me667 chap6 performance measures
10 me667 chap6 performance measures
 
Quality Management Policy
Quality Management PolicyQuality Management Policy
Quality Management Policy
 
Adnan Resume revised
Adnan Resume revisedAdnan Resume revised
Adnan Resume revised
 

More from Ziyad Zaidi

IMPLEMENTATION AND CHALLENGES OF THE ICAO SAFETY MANAGEMENT SYSTEM IN AIRPORTS
IMPLEMENTATION AND CHALLENGES OF THE ICAO SAFETY MANAGEMENT SYSTEM IN AIRPORTSIMPLEMENTATION AND CHALLENGES OF THE ICAO SAFETY MANAGEMENT SYSTEM IN AIRPORTS
IMPLEMENTATION AND CHALLENGES OF THE ICAO SAFETY MANAGEMENT SYSTEM IN AIRPORTS
Ziyad Zaidi
 
Risk Management Final Ppt (Mobile App Development).pptx
Risk Management Final Ppt (Mobile App Development).pptxRisk Management Final Ppt (Mobile App Development).pptx
Risk Management Final Ppt (Mobile App Development).pptx
Ziyad Zaidi
 
Project Stakeholder Management (Risk Assignment).docx
Project Stakeholder Management (Risk Assignment).docxProject Stakeholder Management (Risk Assignment).docx
Project Stakeholder Management (Risk Assignment).docx
Ziyad Zaidi
 
Project Risk Management Report (Mobile App)
Project Risk Management Report (Mobile App)Project Risk Management Report (Mobile App)
Project Risk Management Report (Mobile App)
Ziyad Zaidi
 
DEMOCRACY IN PAKISTAN BALANCING HOPES AND OVERCOMING HURDLES.pptx
DEMOCRACY IN PAKISTAN BALANCING HOPES AND OVERCOMING HURDLES.pptxDEMOCRACY IN PAKISTAN BALANCING HOPES AND OVERCOMING HURDLES.pptx
DEMOCRACY IN PAKISTAN BALANCING HOPES AND OVERCOMING HURDLES.pptx
Ziyad Zaidi
 
Charlie Chaplin and the silent movie era.pptx
Charlie Chaplin and the silent movie era.pptxCharlie Chaplin and the silent movie era.pptx
Charlie Chaplin and the silent movie era.pptx
Ziyad Zaidi
 
Monetary Policy ppt.pptx
Monetary Policy ppt.pptxMonetary Policy ppt.pptx
Monetary Policy ppt.pptx
Ziyad Zaidi
 
Project Procurement Management .pptx
Project Procurement Management .pptxProject Procurement Management .pptx
Project Procurement Management .pptx
Ziyad Zaidi
 
Project Cost and Scheduling Management.pptx
Project Cost and Scheduling Management.pptxProject Cost and Scheduling Management.pptx
Project Cost and Scheduling Management.pptx
Ziyad Zaidi
 
Project Cost and Scheduling Management.docx
Project Cost and Scheduling Management.docxProject Cost and Scheduling Management.docx
Project Cost and Scheduling Management.docx
Ziyad Zaidi
 
Project procurement Management final report.docx
Project procurement Management final report.docxProject procurement Management final report.docx
Project procurement Management final report.docx
Ziyad Zaidi
 
Agriautos Industries Ltd.pptx
Agriautos Industries Ltd.pptxAgriautos Industries Ltd.pptx
Agriautos Industries Ltd.pptx
Ziyad Zaidi
 
ERP Report on Agri Autos.docx
ERP Report on Agri Autos.docxERP Report on Agri Autos.docx
ERP Report on Agri Autos.docx
Ziyad Zaidi
 
PMP Presentation of Failed project of HAL HF-24 Marut.ppt
PMP Presentation of Failed project of HAL HF-24 Marut.pptPMP Presentation of Failed project of HAL HF-24 Marut.ppt
PMP Presentation of Failed project of HAL HF-24 Marut.ppt
Ziyad Zaidi
 
PMP Presentation of Failed project of HAL HF-24 Marut.docx
PMP Presentation of Failed project of HAL HF-24 Marut.docxPMP Presentation of Failed project of HAL HF-24 Marut.docx
PMP Presentation of Failed project of HAL HF-24 Marut.docx
Ziyad Zaidi
 
Project Governance
Project Governance Project Governance
Project Governance
Ziyad Zaidi
 
Project Governance Intro
Project Governance  IntroProject Governance  Intro
Project Governance Intro
Ziyad Zaidi
 
Project Governance
Project Governance Project Governance
Project Governance
Ziyad Zaidi
 
Project Governance
Project Governance Project Governance
Project Governance
Ziyad Zaidi
 
GRC.docx
GRC.docxGRC.docx
GRC.docx
Ziyad Zaidi
 

More from Ziyad Zaidi (20)

IMPLEMENTATION AND CHALLENGES OF THE ICAO SAFETY MANAGEMENT SYSTEM IN AIRPORTS
IMPLEMENTATION AND CHALLENGES OF THE ICAO SAFETY MANAGEMENT SYSTEM IN AIRPORTSIMPLEMENTATION AND CHALLENGES OF THE ICAO SAFETY MANAGEMENT SYSTEM IN AIRPORTS
IMPLEMENTATION AND CHALLENGES OF THE ICAO SAFETY MANAGEMENT SYSTEM IN AIRPORTS
 
Risk Management Final Ppt (Mobile App Development).pptx
Risk Management Final Ppt (Mobile App Development).pptxRisk Management Final Ppt (Mobile App Development).pptx
Risk Management Final Ppt (Mobile App Development).pptx
 
Project Stakeholder Management (Risk Assignment).docx
Project Stakeholder Management (Risk Assignment).docxProject Stakeholder Management (Risk Assignment).docx
Project Stakeholder Management (Risk Assignment).docx
 
Project Risk Management Report (Mobile App)
Project Risk Management Report (Mobile App)Project Risk Management Report (Mobile App)
Project Risk Management Report (Mobile App)
 
DEMOCRACY IN PAKISTAN BALANCING HOPES AND OVERCOMING HURDLES.pptx
DEMOCRACY IN PAKISTAN BALANCING HOPES AND OVERCOMING HURDLES.pptxDEMOCRACY IN PAKISTAN BALANCING HOPES AND OVERCOMING HURDLES.pptx
DEMOCRACY IN PAKISTAN BALANCING HOPES AND OVERCOMING HURDLES.pptx
 
Charlie Chaplin and the silent movie era.pptx
Charlie Chaplin and the silent movie era.pptxCharlie Chaplin and the silent movie era.pptx
Charlie Chaplin and the silent movie era.pptx
 
Monetary Policy ppt.pptx
Monetary Policy ppt.pptxMonetary Policy ppt.pptx
Monetary Policy ppt.pptx
 
Project Procurement Management .pptx
Project Procurement Management .pptxProject Procurement Management .pptx
Project Procurement Management .pptx
 
Project Cost and Scheduling Management.pptx
Project Cost and Scheduling Management.pptxProject Cost and Scheduling Management.pptx
Project Cost and Scheduling Management.pptx
 
Project Cost and Scheduling Management.docx
Project Cost and Scheduling Management.docxProject Cost and Scheduling Management.docx
Project Cost and Scheduling Management.docx
 
Project procurement Management final report.docx
Project procurement Management final report.docxProject procurement Management final report.docx
Project procurement Management final report.docx
 
Agriautos Industries Ltd.pptx
Agriautos Industries Ltd.pptxAgriautos Industries Ltd.pptx
Agriautos Industries Ltd.pptx
 
ERP Report on Agri Autos.docx
ERP Report on Agri Autos.docxERP Report on Agri Autos.docx
ERP Report on Agri Autos.docx
 
PMP Presentation of Failed project of HAL HF-24 Marut.ppt
PMP Presentation of Failed project of HAL HF-24 Marut.pptPMP Presentation of Failed project of HAL HF-24 Marut.ppt
PMP Presentation of Failed project of HAL HF-24 Marut.ppt
 
PMP Presentation of Failed project of HAL HF-24 Marut.docx
PMP Presentation of Failed project of HAL HF-24 Marut.docxPMP Presentation of Failed project of HAL HF-24 Marut.docx
PMP Presentation of Failed project of HAL HF-24 Marut.docx
 
Project Governance
Project Governance Project Governance
Project Governance
 
Project Governance Intro
Project Governance  IntroProject Governance  Intro
Project Governance Intro
 
Project Governance
Project Governance Project Governance
Project Governance
 
Project Governance
Project Governance Project Governance
Project Governance
 
GRC.docx
GRC.docxGRC.docx
GRC.docx
 

Recently uploaded

aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
siemaillard
 
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
MysoreMuleSoftMeetup
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
EugeneSaldivar
 
Chapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptxChapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptx
Mohd Adib Abd Muin, Senior Lecturer at Universiti Utara Malaysia
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
Vivekanand Anglo Vedic Academy
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
TechSoup
 
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
Levi Shapiro
 
Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.
Ashokrao Mane college of Pharmacy Peth-Vadgaon
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
RaedMohamed3
 
"Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe..."Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe...
SACHIN R KONDAGURI
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
Delapenabediema
 
678020731-Sumas-y-Restas-Para-Colorear.pdf
678020731-Sumas-y-Restas-Para-Colorear.pdf678020731-Sumas-y-Restas-Para-Colorear.pdf
678020731-Sumas-y-Restas-Para-Colorear.pdf
CarlosHernanMontoyab2
 
Instructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptxInstructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptx
Jheel Barad
 
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCECLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
BhavyaRajput3
 
Thesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.pptThesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.ppt
EverAndrsGuerraGuerr
 
Overview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with MechanismOverview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with Mechanism
DeeptiGupta154
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
camakaiclarkmusic
 
Unit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdfUnit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdf
Thiyagu K
 
Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345
beazzy04
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
Celine George
 

Recently uploaded (20)

aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
 
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
 
Chapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptxChapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptx
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
 
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
 
Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
 
"Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe..."Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe...
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
 
678020731-Sumas-y-Restas-Para-Colorear.pdf
678020731-Sumas-y-Restas-Para-Colorear.pdf678020731-Sumas-y-Restas-Para-Colorear.pdf
678020731-Sumas-y-Restas-Para-Colorear.pdf
 
Instructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptxInstructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptx
 
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCECLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
 
Thesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.pptThesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.ppt
 
Overview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with MechanismOverview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with Mechanism
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
 
Unit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdfUnit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdf
 
Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
 

Project Quality Management PPT.pptx

  • 2. VERTEX ENGINEERING QUALITY PLAN GROUP MEMBERS: MUHAMMAD MOHSIN 10506 SYED ZIYAD BIN HASAN 11091
  • 3. INTRODUCTION  Vertex engineers are professionals who specialize in the design, analysis, and optimization of geometric shapes and structures. They use their knowledge of mathematics, physics, and engineering principles to create designs that are both structurally sound and efficient. They are also involved in the construction, maintenance and repair of buildings, bridges, and other structures. They often work closely with architects, designers, and other engineers to ensure that the final product meets the needs of the client and adheres to relevant safety and building codes.
  • 4. QUALITY MANAGEMENT OBJECTIVES The Quality Plan to be instituted by Vertex Engineering for the construction of the 1000 sq. yd. in precinct 36 sports city villa’s bahria town karachi. The plan is Vertex Engineering project team’s documentation of the organizational structure, functional responsibility, levels of authority, and lines of communications for the activities that affect quality.
  • 5.  1) Verify that all provisions have been made to provide required control testing.  2) Monitor the design, and contractor’s daily work progress.  3) Check dimensional requirements.  4) Visually inspects materials received on site for proper documentation, completeness, and condition.  5) Observe all required tests such as mechanical and electrical to verify that they are in compliance with the specifications.  6) Ensure the completion of all deficiencies in materials and workmanship in a timely manner.  7) Maintain a document control file.  8) Work closely with all testing agencies to verify that all required tests are able to be performed.
  • 6. QUALITY MANAGEMENT PROCESS  Vertex Engineering will review drawings at each of the above stages of completion to ensure constructibility and functionality. These reviews will also be used to ensure that schedule and budget remain in compliance.  Vertex Engineering will provide contract document timeline requirements to the consultants to ensure that the overall project schedule is maintained.
  • 7. QUALITY CHARACTERISTICS Vertex Engineering Quality Plan will ensure a uniform high quality level of workmanship through all phases of construction, including planning, construction, and turnover. To meet this goal, the following principles will be observed: 1) Ensure the highest level of quality by maintaining supervised controls and written instructions governing Quality Control procedures and practices. 2) Establish clearly defined responsibility and authority for compliance. 3) Meet contractual requirements by conformance to Contract Documents and applicable standards.
  • 8. The techniques that will be used for quality planning are the following ones:   Cost-benefit analysis;   Cost of Quality (CoQ);   Benchmarking;   Statistical sampling;   Quality Requirements Prioritisation (MoSCoW – Must have, Should have, Could have, or Won't have).
  • 9. PERFORM QUALITY ASSURANCE Quality assurance will be performed by evaluating:  the design of the project controls, by confirming that they are implemented, and by assessing their operational effectiveness. These activities will consider the project quality objectives along with the project risks.  compliance with the organisation’s rules and regulations, as well as with relevant governmental and industry rules, regulations and legislation.
  • 10. PERFORM QUALITY CONTROL The purpose of this step is to monitor and consolidate results from the quality assurance activities in The CQCP will be implemented in order to ensure compliance with the specifications for building construction as detailed in the contract specifications. The QCM will be responsible for implementing the CQC Plan by ensuring that quality materials and supplies are providedfor the proposed project, and that good workmanship is provided in all aspects of this contract. The QCM will report directly to the CM and/or On-site Project Manager and will complete daily site inspections to ensure compliance with the quality control specifications.
  • 11. PERFORM DELIVERABLES ACCEPTANCE The purpose of this step is to obtain formal approval from the Project Owner (PO) for each project deliverable. It comprises the verification if deliverables meet the predefined objectives and set of criteria defined in the Deliverables Acceptance Plan, so that the Project Owner (PO) can formally accept them, in the Deliverables Acceptance Note. The Deliverables Acceptance Checklist supports the monitoring of the status of all activities that are pre-condition to the delivery of project outputs to the Project Owner (PO) and the formal acceptance from him/her.
  • 12. PERFORM FINAL ACCEPTANCE The purpose of this step is to manage the final acceptance of the project, including the accepted deliverables and to perform the administrative closure of the project. The final acceptance is obtained from the Project Owner (PO), through a formal Project Acceptance Note. Before the formal project sign-off, the Project Manager (PM) should report on project performance in the Project-End Review Meeting, discuss lessons learned and develop the Project-End Report.
  • 13.
  • 14. QUALITY MANAGEMENT ROLES & RESPONSIBILITIES The following RASCI table defines the responsibilities of those involved in quality management:
  • 15. TOOLS & TECHNIQUES The following techniques will be used for project quality management:  Audits;  Walkthroughs;  Benchmarking;  Questionnaires;  Peer reviews;  Acceptance testing;  Project Review Meetings;
  • 16. The following tools will be used for project quality management:  PM Quality Management Plan;  PM Deliverables Acceptance Plan;  PM Quality Review Checklist;  PM Deliverables Acceptance Checklist;  PM Phase-exit Review Checklist;  PM Quality Review Report;  PM Project-End Report;  Deliverables Acceptance Note;  Project Acceptance Note;
  • 17. FIELD INSPECTION  Pre-Work Coordination Meeting’s  Follow-Up Inspection.  Completion Inspection
  • 18. MATERIAL TEST PROCEDURES A. Testing  The appropriate Consultant will take random samples and test them for conformance with the contract documents. These results will be distributed to all parties. The Quality Control Coordinator will review all test results and follow up as appropriate. B. Samples  Approved samples of materials to be incorporated into the job will be maintained in the site office for use in comparing to installed material. Site mock-ups, as required, will bemaintained during construction at a designated location on site.  Testing samples will be individually identified by The appropriate Consultant.
  • 19. QUALITY REPORTS The quality records (evidence that quality management activities have been performed) are archived in the project repository, under the "Monitor & Control" folder. The different versions of the project artefacts (created at each artefact update) will provide evidence of the performance of these activities.  1. Inspection reports: Inspection reports should be kept for all quality control activities, including material inspections, workmanship inspections, and final inspections. These reports should include details on the items inspected, any issues or non-compliances found, and the actions taken to address them.  2. Test and commissioning reports: Reports detailing the results of all tests and commissioning activities should be kept on file. This includes information on the systems and equipment tested, the test results, and any issues that were identified and addressed.  3. Maintenance records: Records of all maintenance activities should be kept, including the date of the maintenance, the equipment or systems that were maintained, and any issues that were identified and addressed.