Performance Index is created to establish a uniform measure of performance for all projects as some schedules were
conservative and some were aggressive in their plans.
Timelines for
Parameter Unit Average PI 1 PI 2 PI 3 PI 4 PI 5
Typical Slab Cycle – Avg Days 18 12 10 8 7 6
Start to Terrace (G+23) Months 20 13.5 12 10.5 9 8
Terrace to OC application Months 20 10.5 10 9.5 9 8
Start to OC application Months 40 24 22 20 18 16
Degree of Difficulty
1) Best Performance of GPL Start to OC application – 21.5 months at Hillside would lead to PI 2.5
Benefits of PI Index
1. Has become common yardstick to gauge performance among Ops teams
2. It helps identify gaps in progress (eg superlative performance in RCC but lower in finishing)
3. Healthy competition among Ops teams as they are rated on common rules
4. Acts as a North star for teams to surpass existing benchmarks
5. High motivation levels among project teams to achieve Superlative Performance
Need for Performance Index for Operations
Contents
• Substructure
• Superstructure – Aluminum and Conventional formwork
• Superstructure – Tunnel, Pre cast and Hybrid formwork
• Finishing
• Finishing and Parking structure
• Terrace to OC
• Handover
• Annexure
• OC efficiency factor
• Excavation
• Vendor on board milestones
• Fastest achievements in GPL
Excavation and Substructure timelines
SL.
NO.
HEAD ACTIVITY UNIT
PI timelines REMARKS
PI 1 PI 2 PI 3 PI 4 PI 5
1
PILING &
EXCAVATION
Shore piles (300 mm dia ) (avg 15 m depth) NOS/DAY 9 12 15 18 20
Soil (project avg) cum/day 880 1000 1125 1250 1365
Soft rock (project avg) (which can be
excavated with bucket)
cum/day 770 870 970 1070 1170
Hard rock with breaker (project avg) cum/day 550 620 690 760 830
Excavation for buildings with no basement days 36 31 26 21 15
2 FOUNDATION
Regular raft / footing days 36 31 26 21 15
Complicated raft (pit parking) days 60 53 46 39 30
3
FOUNDATION
TO PLINTH
Foundation to plinth days 30 26 22 18 15
Durations are for avg of 3 to 4.5 m
depth. For 6 m depth consider
1.25 times the duration
4
BASEMENT /
PODIUM RCC
SLABS
Basement slab cycle (up to 4.5 M) days 35 30 25 20 15
For 6 m height consider 1.25 times
the duration
Podium slab cycle(up to 4.5 M) days 35 30 25 20 14
For 6 m height consider 1.25 times
the duration
Superstructure timelines
SL.
NO.
ACTIVITY UNIT
REVISED PI 14 Jun 22 REMARKS
PI 1 PI 2 PI 3 PI 4 PI 5
5
ALUMINIUM
FORMWORK
TECHNOLOGY
1st slab (in case of combo of aluform +
conventional) or (100% conventional)
days 30 27 24 21 19
2nd slab (in case of combo of aluform +
conventional) (in case of combo of aluform +
conventional) or (100% conventional
days 21 20 19 18 15
NEW ALUFORM MATERIAL - 1st setup of aluminum
formwork
days 30 25 21 17 12
REFURBISHED ALUFORM MATERIAL - 1st setup of
aluminum formwork
days 51 43 36 29 20
2nd slab after 1st set up (100% mivan) days 21 18 15 12 9
Typical Slab
Cycle - (Level 3
to terrace)
except service
floor, refuge
floor , change
of shuttering
Tower up to 18 floor height days 13 11 9 8 7
Consider 1 day extra for towers with RCC
elevation features (like grooves) as
observed in RKS
Tower (19 to 30 floor height) days 12 10 8 7 6
Tower (31 to 40 floor height) days 14 12 10 8 7
for towers above Level 30, consider the
duration on level basis. E.g. PI 3 : consider
from Level 3 to Level 18 as 9 days.
From Level 19 to Level 30 - 8 days.
From level 31 to 40 - 10 days ,
level 41 to 50 - 12 days.
Level 51 to L65 (except terrace) - 16 days
Tower (41 to 50 floor height) days 15.5 14 12 10 8
Tower (51 to 65 floor height) days 19.5 18 16 14 12.5
6
CONVENTIONAL/
FLOOR CHANGE
CONVENTIONAL FLOOR including any service floor,
refuge floor , change of shuttering, terrace etc
days 18 15 12 9 6
Superstructure timelines
SL.
NO.
HEAD ACTIVITY UNIT
REVISED PI 14 Jun 22 REMARKS
PI 1 PI 2 PI 3 PI 4 PI 5
7
JUMPFORM +
ALUFORM (51 to 65
floors height)
Set up of jump form + min. 4 floors jumping of core days 95 86 77 68 60 for towers above Level 30, consider
the duration on floor basis. E.g. PI 3
: consider from Level 3 to Level 18
as 8.5 days.
From Level 19 to Level 30 - 7.5
days.
From level 31 to 40 - 9.5 days ,
level 41 to 50 - 10.5 days. Level 51
to L65 (except terrace) - 13 days
(Terrace to be treated as
conventional)
Typical slab cycle (Level 3 to 18 floor ) days 10.5 9.5 8.5 7.5 7
Typical slab cycle (Level 19 to 30 floor ) days 9.5 8.5 7.5 6.5 6
Typical slab cycle (Level 31 to 40 floor ) days 11.5 10.5 9.5 8.5 7
Typical slab cycle (Level 41 to 50 floor ) days 13 11.5 10.5 9.5 8
Typical slab cycle (Level 51 to 65 floor excluding terrace ) days 17 15 13 11 9.5
8
TUNNEL FORMWORK
TECH
Set up for first 3 floors of tunnel form days 63 60 57 55 54
Typical floor up to terrace
Tunnel (Full set) days 5.5 4.5 3.5 2.5 2
Tunnel (Half set) days 11 9.5 8 6.5 5
Secondary RCC works (Staircase, upstands, façade walls etc)
gap (no
of floors )
7 6 5 4 3
9 PRECAST All floors days 8 7.5 7 6 5
10
HYBRID PRECAST
(VERTICALS CAST IN
SITU ALUFORM, SLAB
PRECAST)
for 18-30 floor tower ( 6000 to 7000 sqft floor plate)
1st set up Days 33 29 25 21 18
2nd slab days 21 19 17 15 14
Typical floor days 11 9.5 8 6.5 5
Terrace or any change in design floor days 11 9.5 8.5 7.5 6
Finishing timelines
SL.N
O.
HEAD ACTIVITY UNIT
REVISED PI 14 Jun 22 REMARKS
PI 1 PI 2 PI 3 PI 4 PI 5
11
TYPICAL FLOORS
FINISHING SLAB
CYCLE (applicable up
to tile flooring)
Block work & handrail days 10 9 8 7 6
Waterproofing days 14 13 12 11 10
MEP Works days 7 6 5 5 3
Plaster days 14 13 12 11 10
IPS Flooring days 10 9 8 7 6
Stone flooring days 7 6 5 4 3
Flat/ Toilet Tile flooring days 10 9 8 7 6
counters days 10 9 8 7 6
Tile cladding and skirting days 10 9 8 7 6
Temp Door fixinfg & skirting repair days 6 5 4 5 2
TOTAL DURATION days 98 88 78 71 58
12
INTERMEDIATE
FINISHING ACTIVITIES
(GAP FROM RCC
CASTING SLAB )
Blockwork & railing completion
no of
floors
7 6 5 4 3
Internal Plaster completion
no of
floors
8 7 6 5 4
Flat / Toilet Flooring/ Dado completion till temporary door
fixing
no of
floors
10 9 8 7 6
13 WINDOW FIXING Window fixing (Gap from Flat flooring)
no of
floors
8 6 4 3 2
Exceptional case with
external plaster to be
discussed
14
LIFT COMPLETION
FROM TERRACE
Lift completion (lift NOC) (lag from terrace completion to lift
installation)
days 160 135 120 105 90
Finishing and parking structure timelines
SL.N
O
HEAD ACTIVITY UNIT
REVISED PI 14 Jun 22 REMARKS
PI 1 PI 2 PI 3 PI 4 PI 5
15
FINISHING ACTIVITIES
COMPLETION TIMELINE
(From Terrace
completion)
Blockwork & railing completion
lag
(days)
80 60 40 30 20
Internal Plaster completion
lag
(days)
120 90 70 55 40
Flat / Toilet Flooring/ Dado completion
lag
(days)
170 155 135 120 100
Window fixing
lag
(days)
200 185 165 150 130
External Paint
lag
(days)
285 255 225 200 175
Common area flooring completion
lag
(days)
230 210 190 170 150
16
NTA works/ Podium/
MLCP tower completion
100 % RCC work completion slab area.
Inclusion of NTA/ Podium progress
along with tower works. It will have
weightage of 25 % for a given projects.
Rest all towers shall be distributed
within 75 %
NTA
Area
within
three
months of
last tower
RCC
completion
within one
month of
last tower
RCC
completion
Along with
last tower
RCC
completion
Before one
month of
last tower
RCC
completion
Before three
months of
last tower
RCC
completion
1. All measurement to be
done with Terrace
completion of last tower
of first phase. .
2. NTA to be done to the
extent of OC requirement
3. Tower height less than
13 floors to be discussed
separately.
Terrace to OC application timelines
O.C.
READINESS
FROM
COMPLETION
OF TERRACE
(MONTHS)
No of floors UNIT
PI 1 PI 2 PI 3 PI 4 PI 5
Bare
shell
Typical
High
end
Bare
shell
Typical
High
end
Bare
shell
Typical
High
end
Bare
shell
Typical
High
end
Bare
shell
Typical
High
end
up to 8 floors months 7.5 8.5 10.5 6.5 7.5 9.5 5.5 6.5 8.5 4.5 5.5 7.5 3.0 4.5 6.5
9 to 18 floors months 8.5 9.5 11.5 7.5 8.5 10.5 6.5 7.5 9.5 5.5 6.5 8.5 4.0 5.5 7.5
19-30 floors months 9.5 10.5 12.5 8.5 9.5 11.5 7.5 8.5 10.5 6.5 7.5 9.5 5.0 6.5 8.5
30-50 floors months 10.5 11.5 13.5 9.5 10.5 12.5 8.5 9.5 11.5 7.5 8.5 10.5 6.0 7.5 9.5
more than 50 floors months 11.5 12.5 14.5 10.5 11.5 13.5 9.5 10.5 12.5 8.5 9.5 11.5 7.0 8.5 10.5
Handover
Handover PI PI1 PI2 PI3 PI4 PI5
Start from OC receipt ( 1st Flat ) 7 months 6 months 5 months 4 months 3 months
Finish from OC Receipt 13 months 11 months 9 months 7.5 months 6 months
Notes
The above cases is where OC receipt is within 3 months of application. Otherwise above duration shall be
measured from OC application + 3 months
In case OC is stuck after application, handover to CQRA team shall be considered
Annexure Slides
OC led projects - Efficiency factor
Overall efficiency factor to be applied once if OC is received basis major work completion. This is being done to ensure faster work turnaround to handover post
OC receipt. Enumeration done below for a sample:
Activity UOM Target Actual achieved Completion % Weightage Final Factor
A B C = B/A D E = C*D
Flat flooring ( Except wooden flooring) No. of flats 1000 900 90% 25% 23%
Common area finishes (flooring, cladding, false ceiling) Floor 22 11 50% 15% 8%
Window fixing No. of windows 5000 3500 70% 15% 11%
Lift Nos. 3 3 100% 20% 20%
External paint 1st coat Sqm 13941 10000 72% 25% 18%
Net factor 78%
Net PI calculation
= OC PI X Net factor ( E)
= 3 0.8
Net PI = 2.4
Notes :
Grey cells to be filled as per actual progress
In case some activity are not required as per OC rule for the given geography; same will be exempted from calculation
Excavation timelines Enumeration
STRATA
volume as per geotech
report (cum)
swell (voids) total volume (cum) output (cum/day) Days
SOIL 18000 1.3 23400 880 27
WEATHERED ROCK 23000 1.35 31050 770 40
HARD ROCK 30000 1.4 42000 550 76
TOTAL 71000 96450 143
PILING LAG in case shore piling is to be done. In case shore piling is not required then this lag to be 0 45
TOTAL DAYS 188
P.I. REMARKS
BASE
DURATION
(WORKING
DAYS)
MONSOON
DAYS
LOSS DUE TO
MONSOON
(monsoon
days x
efficiency loss)
LOSS DUE TO
BASEMENT
DEPTH
FACTOR
DURATION OF
EXCAVATION +
SHORE PILING
FOR BI
WORKING
PILING
DURATION
EXCAVATION
LAG POST
PILING
PILES/DAY NO OF PILES
A B
D=B *
MONSOON
FACTOR
E=A * B A+D+E
1 BASE 188 120 36 9 234 120 113 7
842
2 10% REDUCTION 210 105 105 8
3 20% REDUCTION 187 94 93 9
4 30% REDUCTION 164 77 87 11
5 40% REDUCTION 140 70 70 12
Excavation timelines Enumeration (efficiency factors)
MONSOON FACTOR : EFFICIENCY LOSS DUE TO MONSOON
LOCATION SEASON EFFICIENCY LOSS DUE TO MONSOON
MUMBAI MONSOON 30%
PUNE MONSOON 25%
NCR / BANGALORE MONSOON 20%
BASEMENT DEPTH FACTOR (INCLUDES PARKING PITS)
1 BASEMENT 0%
Depth of 3.5 m
2 BASEMENT 5%
3 BASEMENT 10%
4 BASEMENT 15%
Note: in case basement depth is more than 4.2 m then an additional 2% to be considered
Vendor onboarding milestones
PACKAGE
3B+G+14 (Foundation + 3 basement
slabs+15 superstructure slabs)
G+23 (Foundation + 25 slabs) B+P+27 (Foundation + 29 slabs)
Piling 15 Days before start of construction 15 Days before start of construction
Excavation 15 Days before start of construction 15 Days before start of construction 15 Days before start of construction
Shell and Core
(Including electrical embedment/WP of foundation)
15 days before start of PCC 2 Week after excavation start 03 week after start of excavation
Aluform Basement 2 completion 15 Days Before start of construction At completion of excavation
Railing Level 5 Level 5 Level 4
Plumbing Including CP Sanitry Level 5 Level 5 Level 4
Fire Fighting Level 5 Level 5 Level 4
Electrical work Level 5 Level 5 Level 4
WP (toilet/ balcony/ terrace) Level 5 Level 5 Level 4
Flooring (Supplier) Level 3 Level 3 Level 2
Flooring (Vendor) Level 5 Level 5 Level 4
Window Level 6 Level 6 Level 7
Internal painting Level 12 Level 12 Level 12
Ext painting Terrace Terrace Terrace
Readymade door Level 12 Level 19 Level 23
Vendor onboarding milestones
PACKAGE
3B+G+14 (Foundation + 3
basement slabs+15
superstructure slabs)
G+23 (Foundation + 25 slabs) B+P+27 (Foundation + 29 slabs)
Lift (Domestic) Level 7 Level 13 Level 17
Lift (International) Level 3 Level 8 Level 12
EXTERNAL
External MEP Level 13 Level 20 Level 24
Solar system Level 9 Level 16 Level 20
STP Level 3 Level 10 Level 12
DG System Level 9 Level 16 Level 20
Mechanical car park
(with 2 basement and Piling)
Excavation completion
Wooden flooring level 12 Level 19 Level 23
Hard scape Level 13 Level 20 Level 24
Softscape Level 13 Level 20 Level 24
External development (Road, Compound wall, SWD) Level 14 level 21 Level 26
Fastest achievements in GPL - Substructure
HEAD ACTIVITY ACHIEVEMENT PROJECT - TOWER ZONE FREQUENCY
PILING &
EXCAVATION
Shore piles (300 mm dia ) (avg 15 m depth) 18 piles/day RK STUDIO MMR Overall
Excavation hard rock with blasting (project avg) 439 cum/day RK STUDIO MMR Overall
Excavation for buildings with no basement 13 days INFINITY – T5 WEST - PUNE
FOUNDATION
Regular raft/ footing 15 days WOODS Sec 43 – T4 NCR 1 slab
Complicated raft (pit parking) 16 days URBAN PARK – T7 MMR 1 tower
FOUNDATION TO
PLINTH
Foundation to Plinth 30 days EMERALD – T6 MMR 1 tower
BASEMENT Basement slab cycle (up to 4.5 m)
16 days RKS - TA MMR 1 slab
16 days AIRNXT - TJ SOUTH 1 slab
PODIUM Podium slab cycle(up to 4.5 m) 11 days REJUVE – T11 B WEST - PUNE 1 slab
Fastest achievements in GPL - Superstructure
HEAD ACTIVITY ACHIEVEMENT PROJECT - TOWER ZONE FREQUENCY
ALUMINIUM
FORM TECH
NEW ALUFORM MATERIAL - 1st setup of aluminium
formwork
15 days WOODS SEC 43 – T2 NCR 1 tower
2nd slab after 1st set up (100% Aluform) 8 days WOODS SEC 43 – T6 NCR 1 tower
Tower (19 to 30 floor height) (Level 3 to terrace)
except service floor, refuge floor , change of shuttering
4 days NURTURE – T2, T3, T7 SOUTH 3 slabs
4 days REJUVE – T10A, T7A WEST- PUNE 4 slabs
4 days SOUTH ESTATE – SB2 NCR 2 slabs
4 days HILLSIDE 1 – T1 WEST- PUNE 1 slab
4 days AIR – A5 NCR 1 slab
Average slab cycle (typical floors) (3rd
floor to Terrace) 8.35, 8.45 days NURTURE – TD, TC SOUTH 2 towers
Maximum no. of slabs cast in a tower in a month 7 slabs in 30 days NURTURE – TC (L16 to terrace) SOUTH 1 tower
Maximum no. of slabs cast in a tower in a calendar
month
6 slabs (Mar-22) AIR – A5 (L21 to L26) NCR 1 tower
Fastest achievements in GPL – Lift, Finishing, NTA, OC Readiness
HEAD ACTIVITY ACHIEVEMENT PROJECT - TOWER ZONE FREQUENCY
LIFT COMPLETION
Lift completion (lift NOC) (lag from terrace
completion to lift installation)
36 days AVENUES – TD SOUTH 1 tower
FINISHING
ACTIVITIES
COMPLETION
Blockwork completion (from Terrace) 10 days AVENUES - TA SOUTH 1 tower
Internal Plaster completion (from Terrace) 63 days NURTURE – TD SOUTH 1 tower
Flat Flooring completion (lag from terrace) 68 days NURTURE – TA SOUTH 1 tower
Common area flooring completion (from Terrace) 121 days AVENUES PH1 - TA SOUTH 1 tower
O.C. READINESS
FROM COMPLETION
OF TERRACE
OC Application from completion of Terrace 90 days 24 – E3 WEST - PUNE 1 tower
CONSTRUCTION
START TO OCA
Construction start to OC Application
21.4 months (651
days)
HILLSIDE 2 (T1, T2, T3) WEST - PUNE 3 towers

More Related Content

Similar to Setting BI for ultimate performance for Site

P25
P25P25
Labour Productivity for construction projects
Labour Productivity for construction projectsLabour Productivity for construction projects
Labour Productivity for construction projects
Kapugantikapuganti Gupta
 
Design and analasys of a g+3 residential building using staad
Design and analasys of a g+3 residential building using staadDesign and analasys of a g+3 residential building using staad
Design and analasys of a g+3 residential building using staadgopichand's
 
Design and analasys of a g+3 residential building using staad
Design and analasys of a g+3 residential building using staadDesign and analasys of a g+3 residential building using staad
Design and analasys of a g+3 residential building using staad
gopichand's
 
Etabs BY Subash Pathak
Etabs BY Subash PathakEtabs BY Subash Pathak
Etabs BY Subash Pathak
Subash Pathak
 
Presentation - 1240 Villas
Presentation - 1240 VillasPresentation - 1240 Villas
Presentation - 1240 VillasIssam M. Faqir
 
PDR Presentation
PDR PresentationPDR Presentation
PDR PresentationNate Pham
 
EarthQuake Reistant Building
EarthQuake Reistant BuildingEarthQuake Reistant Building
EarthQuake Reistant Building
Hemant Srivastava
 
GBI: Role of BS
GBI: Role of BSGBI: Role of BS
GBI: Role of BS
Adiirfan Che-ani
 
practical training ppt
practical training pptpractical training ppt
practical training pptSagar Shah
 
kuku.pptx
kuku.pptxkuku.pptx
kuku.pptx
JaiminTandel1
 
Civil Works Site Construction Guidelines for Haris & Co Civil Team.pdf
Civil Works Site Construction Guidelines for  Haris & Co Civil Team.pdfCivil Works Site Construction Guidelines for  Haris & Co Civil Team.pdf
Civil Works Site Construction Guidelines for Haris & Co Civil Team.pdf
usamazahoor159
 
IRJET- Comparative Study of Top down & Bottom up Method Construction Schedule...
IRJET- Comparative Study of Top down & Bottom up Method Construction Schedule...IRJET- Comparative Study of Top down & Bottom up Method Construction Schedule...
IRJET- Comparative Study of Top down & Bottom up Method Construction Schedule...
IRJET Journal
 
151111 Exploring the challenges of underground construction in urban areas_Be...
151111 Exploring the challenges of underground construction in urban areas_Be...151111 Exploring the challenges of underground construction in urban areas_Be...
151111 Exploring the challenges of underground construction in urban areas_Be...Benoit Latapie
 
DESIGN OF G+20 MULTISTOREY BUILDING
DESIGN OF G+20 MULTISTOREY BUILDINGDESIGN OF G+20 MULTISTOREY BUILDING
DESIGN OF G+20 MULTISTOREY BUILDING
Anjneya Srivastava
 
IT TOWER DESIGN CHANDAKA BHUBANESWAR ODISHA
IT TOWER DESIGN CHANDAKA BHUBANESWAR ODISHAIT TOWER DESIGN CHANDAKA BHUBANESWAR ODISHA
IT TOWER DESIGN CHANDAKA BHUBANESWAR ODISHA
alwayslogo
 
11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx
11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx
11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx
ssuser2ec079
 
G+3 APARTMENT BUILDING PROJECT REPORT
G+3 APARTMENT BUILDING  PROJECT  REPORTG+3 APARTMENT BUILDING  PROJECT  REPORT
G+3 APARTMENT BUILDING PROJECT REPORT
Fresher Thinking
 

Similar to Setting BI for ultimate performance for Site (20)

P25
P25P25
P25
 
CE236_Final_2007
CE236_Final_2007CE236_Final_2007
CE236_Final_2007
 
Labour Productivity for construction projects
Labour Productivity for construction projectsLabour Productivity for construction projects
Labour Productivity for construction projects
 
Design and analasys of a g+3 residential building using staad
Design and analasys of a g+3 residential building using staadDesign and analasys of a g+3 residential building using staad
Design and analasys of a g+3 residential building using staad
 
Design and analasys of a g+3 residential building using staad
Design and analasys of a g+3 residential building using staadDesign and analasys of a g+3 residential building using staad
Design and analasys of a g+3 residential building using staad
 
Etabs BY Subash Pathak
Etabs BY Subash PathakEtabs BY Subash Pathak
Etabs BY Subash Pathak
 
Presentation - 1240 Villas
Presentation - 1240 VillasPresentation - 1240 Villas
Presentation - 1240 Villas
 
PDR Presentation
PDR PresentationPDR Presentation
PDR Presentation
 
EarthQuake Reistant Building
EarthQuake Reistant BuildingEarthQuake Reistant Building
EarthQuake Reistant Building
 
GBI: Role of BS
GBI: Role of BSGBI: Role of BS
GBI: Role of BS
 
practical training ppt
practical training pptpractical training ppt
practical training ppt
 
kuku.pptx
kuku.pptxkuku.pptx
kuku.pptx
 
Civil Works Site Construction Guidelines for Haris & Co Civil Team.pdf
Civil Works Site Construction Guidelines for  Haris & Co Civil Team.pdfCivil Works Site Construction Guidelines for  Haris & Co Civil Team.pdf
Civil Works Site Construction Guidelines for Haris & Co Civil Team.pdf
 
IRJET- Comparative Study of Top down & Bottom up Method Construction Schedule...
IRJET- Comparative Study of Top down & Bottom up Method Construction Schedule...IRJET- Comparative Study of Top down & Bottom up Method Construction Schedule...
IRJET- Comparative Study of Top down & Bottom up Method Construction Schedule...
 
151111 Exploring the challenges of underground construction in urban areas_Be...
151111 Exploring the challenges of underground construction in urban areas_Be...151111 Exploring the challenges of underground construction in urban areas_Be...
151111 Exploring the challenges of underground construction in urban areas_Be...
 
DESIGN OF G+20 MULTISTOREY BUILDING
DESIGN OF G+20 MULTISTOREY BUILDINGDESIGN OF G+20 MULTISTOREY BUILDING
DESIGN OF G+20 MULTISTOREY BUILDING
 
IT TOWER DESIGN CHANDAKA BHUBANESWAR ODISHA
IT TOWER DESIGN CHANDAKA BHUBANESWAR ODISHAIT TOWER DESIGN CHANDAKA BHUBANESWAR ODISHA
IT TOWER DESIGN CHANDAKA BHUBANESWAR ODISHA
 
11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx
11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx
11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx
 
G+3 APARTMENT BUILDING PROJECT REPORT
G+3 APARTMENT BUILDING  PROJECT  REPORTG+3 APARTMENT BUILDING  PROJECT  REPORT
G+3 APARTMENT BUILDING PROJECT REPORT
 
SMHB
SMHBSMHB
SMHB
 

Recently uploaded

一比一原版(UofS毕业证书)萨省大学毕业证如何办理
一比一原版(UofS毕业证书)萨省大学毕业证如何办理一比一原版(UofS毕业证书)萨省大学毕业证如何办理
一比一原版(UofS毕业证书)萨省大学毕业证如何办理
v3tuleee
 
Enhanced Enterprise Intelligence with your personal AI Data Copilot.pdf
Enhanced Enterprise Intelligence with your personal AI Data Copilot.pdfEnhanced Enterprise Intelligence with your personal AI Data Copilot.pdf
Enhanced Enterprise Intelligence with your personal AI Data Copilot.pdf
GetInData
 
一比一原版(Dalhousie毕业证书)达尔豪斯大学毕业证如何办理
一比一原版(Dalhousie毕业证书)达尔豪斯大学毕业证如何办理一比一原版(Dalhousie毕业证书)达尔豪斯大学毕业证如何办理
一比一原版(Dalhousie毕业证书)达尔豪斯大学毕业证如何办理
mzpolocfi
 
My burning issue is homelessness K.C.M.O.
My burning issue is homelessness K.C.M.O.My burning issue is homelessness K.C.M.O.
My burning issue is homelessness K.C.M.O.
rwarrenll
 
原版制作(swinburne毕业证书)斯威本科技大学毕业证毕业完成信一模一样
原版制作(swinburne毕业证书)斯威本科技大学毕业证毕业完成信一模一样原版制作(swinburne毕业证书)斯威本科技大学毕业证毕业完成信一模一样
原版制作(swinburne毕业证书)斯威本科技大学毕业证毕业完成信一模一样
u86oixdj
 
Influence of Marketing Strategy and Market Competition on Business Plan
Influence of Marketing Strategy and Market Competition on Business PlanInfluence of Marketing Strategy and Market Competition on Business Plan
Influence of Marketing Strategy and Market Competition on Business Plan
jerlynmaetalle
 
哪里卖(usq毕业证书)南昆士兰大学毕业证研究生文凭证书托福证书原版一模一样
哪里卖(usq毕业证书)南昆士兰大学毕业证研究生文凭证书托福证书原版一模一样哪里卖(usq毕业证书)南昆士兰大学毕业证研究生文凭证书托福证书原版一模一样
哪里卖(usq毕业证书)南昆士兰大学毕业证研究生文凭证书托福证书原版一模一样
axoqas
 
Malana- Gimlet Market Analysis (Portfolio 2)
Malana- Gimlet Market Analysis (Portfolio 2)Malana- Gimlet Market Analysis (Portfolio 2)
Malana- Gimlet Market Analysis (Portfolio 2)
TravisMalana
 
一比一原版(Coventry毕业证书)考文垂大学毕业证如何办理
一比一原版(Coventry毕业证书)考文垂大学毕业证如何办理一比一原版(Coventry毕业证书)考文垂大学毕业证如何办理
一比一原版(Coventry毕业证书)考文垂大学毕业证如何办理
74nqk8xf
 
Nanandann Nilekani's ppt On India's .pdf
Nanandann Nilekani's ppt On India's .pdfNanandann Nilekani's ppt On India's .pdf
Nanandann Nilekani's ppt On India's .pdf
eddie19851
 
Unleashing the Power of Data_ Choosing a Trusted Analytics Platform.pdf
Unleashing the Power of Data_ Choosing a Trusted Analytics Platform.pdfUnleashing the Power of Data_ Choosing a Trusted Analytics Platform.pdf
Unleashing the Power of Data_ Choosing a Trusted Analytics Platform.pdf
Enterprise Wired
 
Levelwise PageRank with Loop-Based Dead End Handling Strategy : SHORT REPORT ...
Levelwise PageRank with Loop-Based Dead End Handling Strategy : SHORT REPORT ...Levelwise PageRank with Loop-Based Dead End Handling Strategy : SHORT REPORT ...
Levelwise PageRank with Loop-Based Dead End Handling Strategy : SHORT REPORT ...
Subhajit Sahu
 
Adjusting primitives for graph : SHORT REPORT / NOTES
Adjusting primitives for graph : SHORT REPORT / NOTESAdjusting primitives for graph : SHORT REPORT / NOTES
Adjusting primitives for graph : SHORT REPORT / NOTES
Subhajit Sahu
 
一比一原版(Adelaide毕业证书)阿德莱德大学毕业证如何办理
一比一原版(Adelaide毕业证书)阿德莱德大学毕业证如何办理一比一原版(Adelaide毕业证书)阿德莱德大学毕业证如何办理
一比一原版(Adelaide毕业证书)阿德莱德大学毕业证如何办理
slg6lamcq
 
06-04-2024 - NYC Tech Week - Discussion on Vector Databases, Unstructured Dat...
06-04-2024 - NYC Tech Week - Discussion on Vector Databases, Unstructured Dat...06-04-2024 - NYC Tech Week - Discussion on Vector Databases, Unstructured Dat...
06-04-2024 - NYC Tech Week - Discussion on Vector Databases, Unstructured Dat...
Timothy Spann
 
Machine learning and optimization techniques for electrical drives.pptx
Machine learning and optimization techniques for electrical drives.pptxMachine learning and optimization techniques for electrical drives.pptx
Machine learning and optimization techniques for electrical drives.pptx
balafet
 
06-04-2024 - NYC Tech Week - Discussion on Vector Databases, Unstructured Dat...
06-04-2024 - NYC Tech Week - Discussion on Vector Databases, Unstructured Dat...06-04-2024 - NYC Tech Week - Discussion on Vector Databases, Unstructured Dat...
06-04-2024 - NYC Tech Week - Discussion on Vector Databases, Unstructured Dat...
Timothy Spann
 
Adjusting OpenMP PageRank : SHORT REPORT / NOTES
Adjusting OpenMP PageRank : SHORT REPORT / NOTESAdjusting OpenMP PageRank : SHORT REPORT / NOTES
Adjusting OpenMP PageRank : SHORT REPORT / NOTES
Subhajit Sahu
 
办(uts毕业证书)悉尼科技大学毕业证学历证书原版一模一样
办(uts毕业证书)悉尼科技大学毕业证学历证书原版一模一样办(uts毕业证书)悉尼科技大学毕业证学历证书原版一模一样
办(uts毕业证书)悉尼科技大学毕业证学历证书原版一模一样
apvysm8
 
STATATHON: Unleashing the Power of Statistics in a 48-Hour Knowledge Extravag...
STATATHON: Unleashing the Power of Statistics in a 48-Hour Knowledge Extravag...STATATHON: Unleashing the Power of Statistics in a 48-Hour Knowledge Extravag...
STATATHON: Unleashing the Power of Statistics in a 48-Hour Knowledge Extravag...
sameer shah
 

Recently uploaded (20)

一比一原版(UofS毕业证书)萨省大学毕业证如何办理
一比一原版(UofS毕业证书)萨省大学毕业证如何办理一比一原版(UofS毕业证书)萨省大学毕业证如何办理
一比一原版(UofS毕业证书)萨省大学毕业证如何办理
 
Enhanced Enterprise Intelligence with your personal AI Data Copilot.pdf
Enhanced Enterprise Intelligence with your personal AI Data Copilot.pdfEnhanced Enterprise Intelligence with your personal AI Data Copilot.pdf
Enhanced Enterprise Intelligence with your personal AI Data Copilot.pdf
 
一比一原版(Dalhousie毕业证书)达尔豪斯大学毕业证如何办理
一比一原版(Dalhousie毕业证书)达尔豪斯大学毕业证如何办理一比一原版(Dalhousie毕业证书)达尔豪斯大学毕业证如何办理
一比一原版(Dalhousie毕业证书)达尔豪斯大学毕业证如何办理
 
My burning issue is homelessness K.C.M.O.
My burning issue is homelessness K.C.M.O.My burning issue is homelessness K.C.M.O.
My burning issue is homelessness K.C.M.O.
 
原版制作(swinburne毕业证书)斯威本科技大学毕业证毕业完成信一模一样
原版制作(swinburne毕业证书)斯威本科技大学毕业证毕业完成信一模一样原版制作(swinburne毕业证书)斯威本科技大学毕业证毕业完成信一模一样
原版制作(swinburne毕业证书)斯威本科技大学毕业证毕业完成信一模一样
 
Influence of Marketing Strategy and Market Competition on Business Plan
Influence of Marketing Strategy and Market Competition on Business PlanInfluence of Marketing Strategy and Market Competition on Business Plan
Influence of Marketing Strategy and Market Competition on Business Plan
 
哪里卖(usq毕业证书)南昆士兰大学毕业证研究生文凭证书托福证书原版一模一样
哪里卖(usq毕业证书)南昆士兰大学毕业证研究生文凭证书托福证书原版一模一样哪里卖(usq毕业证书)南昆士兰大学毕业证研究生文凭证书托福证书原版一模一样
哪里卖(usq毕业证书)南昆士兰大学毕业证研究生文凭证书托福证书原版一模一样
 
Malana- Gimlet Market Analysis (Portfolio 2)
Malana- Gimlet Market Analysis (Portfolio 2)Malana- Gimlet Market Analysis (Portfolio 2)
Malana- Gimlet Market Analysis (Portfolio 2)
 
一比一原版(Coventry毕业证书)考文垂大学毕业证如何办理
一比一原版(Coventry毕业证书)考文垂大学毕业证如何办理一比一原版(Coventry毕业证书)考文垂大学毕业证如何办理
一比一原版(Coventry毕业证书)考文垂大学毕业证如何办理
 
Nanandann Nilekani's ppt On India's .pdf
Nanandann Nilekani's ppt On India's .pdfNanandann Nilekani's ppt On India's .pdf
Nanandann Nilekani's ppt On India's .pdf
 
Unleashing the Power of Data_ Choosing a Trusted Analytics Platform.pdf
Unleashing the Power of Data_ Choosing a Trusted Analytics Platform.pdfUnleashing the Power of Data_ Choosing a Trusted Analytics Platform.pdf
Unleashing the Power of Data_ Choosing a Trusted Analytics Platform.pdf
 
Levelwise PageRank with Loop-Based Dead End Handling Strategy : SHORT REPORT ...
Levelwise PageRank with Loop-Based Dead End Handling Strategy : SHORT REPORT ...Levelwise PageRank with Loop-Based Dead End Handling Strategy : SHORT REPORT ...
Levelwise PageRank with Loop-Based Dead End Handling Strategy : SHORT REPORT ...
 
Adjusting primitives for graph : SHORT REPORT / NOTES
Adjusting primitives for graph : SHORT REPORT / NOTESAdjusting primitives for graph : SHORT REPORT / NOTES
Adjusting primitives for graph : SHORT REPORT / NOTES
 
一比一原版(Adelaide毕业证书)阿德莱德大学毕业证如何办理
一比一原版(Adelaide毕业证书)阿德莱德大学毕业证如何办理一比一原版(Adelaide毕业证书)阿德莱德大学毕业证如何办理
一比一原版(Adelaide毕业证书)阿德莱德大学毕业证如何办理
 
06-04-2024 - NYC Tech Week - Discussion on Vector Databases, Unstructured Dat...
06-04-2024 - NYC Tech Week - Discussion on Vector Databases, Unstructured Dat...06-04-2024 - NYC Tech Week - Discussion on Vector Databases, Unstructured Dat...
06-04-2024 - NYC Tech Week - Discussion on Vector Databases, Unstructured Dat...
 
Machine learning and optimization techniques for electrical drives.pptx
Machine learning and optimization techniques for electrical drives.pptxMachine learning and optimization techniques for electrical drives.pptx
Machine learning and optimization techniques for electrical drives.pptx
 
06-04-2024 - NYC Tech Week - Discussion on Vector Databases, Unstructured Dat...
06-04-2024 - NYC Tech Week - Discussion on Vector Databases, Unstructured Dat...06-04-2024 - NYC Tech Week - Discussion on Vector Databases, Unstructured Dat...
06-04-2024 - NYC Tech Week - Discussion on Vector Databases, Unstructured Dat...
 
Adjusting OpenMP PageRank : SHORT REPORT / NOTES
Adjusting OpenMP PageRank : SHORT REPORT / NOTESAdjusting OpenMP PageRank : SHORT REPORT / NOTES
Adjusting OpenMP PageRank : SHORT REPORT / NOTES
 
办(uts毕业证书)悉尼科技大学毕业证学历证书原版一模一样
办(uts毕业证书)悉尼科技大学毕业证学历证书原版一模一样办(uts毕业证书)悉尼科技大学毕业证学历证书原版一模一样
办(uts毕业证书)悉尼科技大学毕业证学历证书原版一模一样
 
STATATHON: Unleashing the Power of Statistics in a 48-Hour Knowledge Extravag...
STATATHON: Unleashing the Power of Statistics in a 48-Hour Knowledge Extravag...STATATHON: Unleashing the Power of Statistics in a 48-Hour Knowledge Extravag...
STATATHON: Unleashing the Power of Statistics in a 48-Hour Knowledge Extravag...
 

Setting BI for ultimate performance for Site

  • 2. Performance Index is created to establish a uniform measure of performance for all projects as some schedules were conservative and some were aggressive in their plans. Timelines for Parameter Unit Average PI 1 PI 2 PI 3 PI 4 PI 5 Typical Slab Cycle – Avg Days 18 12 10 8 7 6 Start to Terrace (G+23) Months 20 13.5 12 10.5 9 8 Terrace to OC application Months 20 10.5 10 9.5 9 8 Start to OC application Months 40 24 22 20 18 16 Degree of Difficulty 1) Best Performance of GPL Start to OC application – 21.5 months at Hillside would lead to PI 2.5 Benefits of PI Index 1. Has become common yardstick to gauge performance among Ops teams 2. It helps identify gaps in progress (eg superlative performance in RCC but lower in finishing) 3. Healthy competition among Ops teams as they are rated on common rules 4. Acts as a North star for teams to surpass existing benchmarks 5. High motivation levels among project teams to achieve Superlative Performance Need for Performance Index for Operations
  • 3. Contents • Substructure • Superstructure – Aluminum and Conventional formwork • Superstructure – Tunnel, Pre cast and Hybrid formwork • Finishing • Finishing and Parking structure • Terrace to OC • Handover • Annexure • OC efficiency factor • Excavation • Vendor on board milestones • Fastest achievements in GPL
  • 4. Excavation and Substructure timelines SL. NO. HEAD ACTIVITY UNIT PI timelines REMARKS PI 1 PI 2 PI 3 PI 4 PI 5 1 PILING & EXCAVATION Shore piles (300 mm dia ) (avg 15 m depth) NOS/DAY 9 12 15 18 20 Soil (project avg) cum/day 880 1000 1125 1250 1365 Soft rock (project avg) (which can be excavated with bucket) cum/day 770 870 970 1070 1170 Hard rock with breaker (project avg) cum/day 550 620 690 760 830 Excavation for buildings with no basement days 36 31 26 21 15 2 FOUNDATION Regular raft / footing days 36 31 26 21 15 Complicated raft (pit parking) days 60 53 46 39 30 3 FOUNDATION TO PLINTH Foundation to plinth days 30 26 22 18 15 Durations are for avg of 3 to 4.5 m depth. For 6 m depth consider 1.25 times the duration 4 BASEMENT / PODIUM RCC SLABS Basement slab cycle (up to 4.5 M) days 35 30 25 20 15 For 6 m height consider 1.25 times the duration Podium slab cycle(up to 4.5 M) days 35 30 25 20 14 For 6 m height consider 1.25 times the duration
  • 5. Superstructure timelines SL. NO. ACTIVITY UNIT REVISED PI 14 Jun 22 REMARKS PI 1 PI 2 PI 3 PI 4 PI 5 5 ALUMINIUM FORMWORK TECHNOLOGY 1st slab (in case of combo of aluform + conventional) or (100% conventional) days 30 27 24 21 19 2nd slab (in case of combo of aluform + conventional) (in case of combo of aluform + conventional) or (100% conventional days 21 20 19 18 15 NEW ALUFORM MATERIAL - 1st setup of aluminum formwork days 30 25 21 17 12 REFURBISHED ALUFORM MATERIAL - 1st setup of aluminum formwork days 51 43 36 29 20 2nd slab after 1st set up (100% mivan) days 21 18 15 12 9 Typical Slab Cycle - (Level 3 to terrace) except service floor, refuge floor , change of shuttering Tower up to 18 floor height days 13 11 9 8 7 Consider 1 day extra for towers with RCC elevation features (like grooves) as observed in RKS Tower (19 to 30 floor height) days 12 10 8 7 6 Tower (31 to 40 floor height) days 14 12 10 8 7 for towers above Level 30, consider the duration on level basis. E.g. PI 3 : consider from Level 3 to Level 18 as 9 days. From Level 19 to Level 30 - 8 days. From level 31 to 40 - 10 days , level 41 to 50 - 12 days. Level 51 to L65 (except terrace) - 16 days Tower (41 to 50 floor height) days 15.5 14 12 10 8 Tower (51 to 65 floor height) days 19.5 18 16 14 12.5 6 CONVENTIONAL/ FLOOR CHANGE CONVENTIONAL FLOOR including any service floor, refuge floor , change of shuttering, terrace etc days 18 15 12 9 6
  • 6. Superstructure timelines SL. NO. HEAD ACTIVITY UNIT REVISED PI 14 Jun 22 REMARKS PI 1 PI 2 PI 3 PI 4 PI 5 7 JUMPFORM + ALUFORM (51 to 65 floors height) Set up of jump form + min. 4 floors jumping of core days 95 86 77 68 60 for towers above Level 30, consider the duration on floor basis. E.g. PI 3 : consider from Level 3 to Level 18 as 8.5 days. From Level 19 to Level 30 - 7.5 days. From level 31 to 40 - 9.5 days , level 41 to 50 - 10.5 days. Level 51 to L65 (except terrace) - 13 days (Terrace to be treated as conventional) Typical slab cycle (Level 3 to 18 floor ) days 10.5 9.5 8.5 7.5 7 Typical slab cycle (Level 19 to 30 floor ) days 9.5 8.5 7.5 6.5 6 Typical slab cycle (Level 31 to 40 floor ) days 11.5 10.5 9.5 8.5 7 Typical slab cycle (Level 41 to 50 floor ) days 13 11.5 10.5 9.5 8 Typical slab cycle (Level 51 to 65 floor excluding terrace ) days 17 15 13 11 9.5 8 TUNNEL FORMWORK TECH Set up for first 3 floors of tunnel form days 63 60 57 55 54 Typical floor up to terrace Tunnel (Full set) days 5.5 4.5 3.5 2.5 2 Tunnel (Half set) days 11 9.5 8 6.5 5 Secondary RCC works (Staircase, upstands, façade walls etc) gap (no of floors ) 7 6 5 4 3 9 PRECAST All floors days 8 7.5 7 6 5 10 HYBRID PRECAST (VERTICALS CAST IN SITU ALUFORM, SLAB PRECAST) for 18-30 floor tower ( 6000 to 7000 sqft floor plate) 1st set up Days 33 29 25 21 18 2nd slab days 21 19 17 15 14 Typical floor days 11 9.5 8 6.5 5 Terrace or any change in design floor days 11 9.5 8.5 7.5 6
  • 7. Finishing timelines SL.N O. HEAD ACTIVITY UNIT REVISED PI 14 Jun 22 REMARKS PI 1 PI 2 PI 3 PI 4 PI 5 11 TYPICAL FLOORS FINISHING SLAB CYCLE (applicable up to tile flooring) Block work & handrail days 10 9 8 7 6 Waterproofing days 14 13 12 11 10 MEP Works days 7 6 5 5 3 Plaster days 14 13 12 11 10 IPS Flooring days 10 9 8 7 6 Stone flooring days 7 6 5 4 3 Flat/ Toilet Tile flooring days 10 9 8 7 6 counters days 10 9 8 7 6 Tile cladding and skirting days 10 9 8 7 6 Temp Door fixinfg & skirting repair days 6 5 4 5 2 TOTAL DURATION days 98 88 78 71 58 12 INTERMEDIATE FINISHING ACTIVITIES (GAP FROM RCC CASTING SLAB ) Blockwork & railing completion no of floors 7 6 5 4 3 Internal Plaster completion no of floors 8 7 6 5 4 Flat / Toilet Flooring/ Dado completion till temporary door fixing no of floors 10 9 8 7 6 13 WINDOW FIXING Window fixing (Gap from Flat flooring) no of floors 8 6 4 3 2 Exceptional case with external plaster to be discussed 14 LIFT COMPLETION FROM TERRACE Lift completion (lift NOC) (lag from terrace completion to lift installation) days 160 135 120 105 90
  • 8. Finishing and parking structure timelines SL.N O HEAD ACTIVITY UNIT REVISED PI 14 Jun 22 REMARKS PI 1 PI 2 PI 3 PI 4 PI 5 15 FINISHING ACTIVITIES COMPLETION TIMELINE (From Terrace completion) Blockwork & railing completion lag (days) 80 60 40 30 20 Internal Plaster completion lag (days) 120 90 70 55 40 Flat / Toilet Flooring/ Dado completion lag (days) 170 155 135 120 100 Window fixing lag (days) 200 185 165 150 130 External Paint lag (days) 285 255 225 200 175 Common area flooring completion lag (days) 230 210 190 170 150 16 NTA works/ Podium/ MLCP tower completion 100 % RCC work completion slab area. Inclusion of NTA/ Podium progress along with tower works. It will have weightage of 25 % for a given projects. Rest all towers shall be distributed within 75 % NTA Area within three months of last tower RCC completion within one month of last tower RCC completion Along with last tower RCC completion Before one month of last tower RCC completion Before three months of last tower RCC completion 1. All measurement to be done with Terrace completion of last tower of first phase. . 2. NTA to be done to the extent of OC requirement 3. Tower height less than 13 floors to be discussed separately.
  • 9. Terrace to OC application timelines O.C. READINESS FROM COMPLETION OF TERRACE (MONTHS) No of floors UNIT PI 1 PI 2 PI 3 PI 4 PI 5 Bare shell Typical High end Bare shell Typical High end Bare shell Typical High end Bare shell Typical High end Bare shell Typical High end up to 8 floors months 7.5 8.5 10.5 6.5 7.5 9.5 5.5 6.5 8.5 4.5 5.5 7.5 3.0 4.5 6.5 9 to 18 floors months 8.5 9.5 11.5 7.5 8.5 10.5 6.5 7.5 9.5 5.5 6.5 8.5 4.0 5.5 7.5 19-30 floors months 9.5 10.5 12.5 8.5 9.5 11.5 7.5 8.5 10.5 6.5 7.5 9.5 5.0 6.5 8.5 30-50 floors months 10.5 11.5 13.5 9.5 10.5 12.5 8.5 9.5 11.5 7.5 8.5 10.5 6.0 7.5 9.5 more than 50 floors months 11.5 12.5 14.5 10.5 11.5 13.5 9.5 10.5 12.5 8.5 9.5 11.5 7.0 8.5 10.5
  • 10. Handover Handover PI PI1 PI2 PI3 PI4 PI5 Start from OC receipt ( 1st Flat ) 7 months 6 months 5 months 4 months 3 months Finish from OC Receipt 13 months 11 months 9 months 7.5 months 6 months Notes The above cases is where OC receipt is within 3 months of application. Otherwise above duration shall be measured from OC application + 3 months In case OC is stuck after application, handover to CQRA team shall be considered
  • 12. OC led projects - Efficiency factor Overall efficiency factor to be applied once if OC is received basis major work completion. This is being done to ensure faster work turnaround to handover post OC receipt. Enumeration done below for a sample: Activity UOM Target Actual achieved Completion % Weightage Final Factor A B C = B/A D E = C*D Flat flooring ( Except wooden flooring) No. of flats 1000 900 90% 25% 23% Common area finishes (flooring, cladding, false ceiling) Floor 22 11 50% 15% 8% Window fixing No. of windows 5000 3500 70% 15% 11% Lift Nos. 3 3 100% 20% 20% External paint 1st coat Sqm 13941 10000 72% 25% 18% Net factor 78% Net PI calculation = OC PI X Net factor ( E) = 3 0.8 Net PI = 2.4 Notes : Grey cells to be filled as per actual progress In case some activity are not required as per OC rule for the given geography; same will be exempted from calculation
  • 13. Excavation timelines Enumeration STRATA volume as per geotech report (cum) swell (voids) total volume (cum) output (cum/day) Days SOIL 18000 1.3 23400 880 27 WEATHERED ROCK 23000 1.35 31050 770 40 HARD ROCK 30000 1.4 42000 550 76 TOTAL 71000 96450 143 PILING LAG in case shore piling is to be done. In case shore piling is not required then this lag to be 0 45 TOTAL DAYS 188 P.I. REMARKS BASE DURATION (WORKING DAYS) MONSOON DAYS LOSS DUE TO MONSOON (monsoon days x efficiency loss) LOSS DUE TO BASEMENT DEPTH FACTOR DURATION OF EXCAVATION + SHORE PILING FOR BI WORKING PILING DURATION EXCAVATION LAG POST PILING PILES/DAY NO OF PILES A B D=B * MONSOON FACTOR E=A * B A+D+E 1 BASE 188 120 36 9 234 120 113 7 842 2 10% REDUCTION 210 105 105 8 3 20% REDUCTION 187 94 93 9 4 30% REDUCTION 164 77 87 11 5 40% REDUCTION 140 70 70 12
  • 14. Excavation timelines Enumeration (efficiency factors) MONSOON FACTOR : EFFICIENCY LOSS DUE TO MONSOON LOCATION SEASON EFFICIENCY LOSS DUE TO MONSOON MUMBAI MONSOON 30% PUNE MONSOON 25% NCR / BANGALORE MONSOON 20% BASEMENT DEPTH FACTOR (INCLUDES PARKING PITS) 1 BASEMENT 0% Depth of 3.5 m 2 BASEMENT 5% 3 BASEMENT 10% 4 BASEMENT 15% Note: in case basement depth is more than 4.2 m then an additional 2% to be considered
  • 15. Vendor onboarding milestones PACKAGE 3B+G+14 (Foundation + 3 basement slabs+15 superstructure slabs) G+23 (Foundation + 25 slabs) B+P+27 (Foundation + 29 slabs) Piling 15 Days before start of construction 15 Days before start of construction Excavation 15 Days before start of construction 15 Days before start of construction 15 Days before start of construction Shell and Core (Including electrical embedment/WP of foundation) 15 days before start of PCC 2 Week after excavation start 03 week after start of excavation Aluform Basement 2 completion 15 Days Before start of construction At completion of excavation Railing Level 5 Level 5 Level 4 Plumbing Including CP Sanitry Level 5 Level 5 Level 4 Fire Fighting Level 5 Level 5 Level 4 Electrical work Level 5 Level 5 Level 4 WP (toilet/ balcony/ terrace) Level 5 Level 5 Level 4 Flooring (Supplier) Level 3 Level 3 Level 2 Flooring (Vendor) Level 5 Level 5 Level 4 Window Level 6 Level 6 Level 7 Internal painting Level 12 Level 12 Level 12 Ext painting Terrace Terrace Terrace Readymade door Level 12 Level 19 Level 23
  • 16. Vendor onboarding milestones PACKAGE 3B+G+14 (Foundation + 3 basement slabs+15 superstructure slabs) G+23 (Foundation + 25 slabs) B+P+27 (Foundation + 29 slabs) Lift (Domestic) Level 7 Level 13 Level 17 Lift (International) Level 3 Level 8 Level 12 EXTERNAL External MEP Level 13 Level 20 Level 24 Solar system Level 9 Level 16 Level 20 STP Level 3 Level 10 Level 12 DG System Level 9 Level 16 Level 20 Mechanical car park (with 2 basement and Piling) Excavation completion Wooden flooring level 12 Level 19 Level 23 Hard scape Level 13 Level 20 Level 24 Softscape Level 13 Level 20 Level 24 External development (Road, Compound wall, SWD) Level 14 level 21 Level 26
  • 17. Fastest achievements in GPL - Substructure HEAD ACTIVITY ACHIEVEMENT PROJECT - TOWER ZONE FREQUENCY PILING & EXCAVATION Shore piles (300 mm dia ) (avg 15 m depth) 18 piles/day RK STUDIO MMR Overall Excavation hard rock with blasting (project avg) 439 cum/day RK STUDIO MMR Overall Excavation for buildings with no basement 13 days INFINITY – T5 WEST - PUNE FOUNDATION Regular raft/ footing 15 days WOODS Sec 43 – T4 NCR 1 slab Complicated raft (pit parking) 16 days URBAN PARK – T7 MMR 1 tower FOUNDATION TO PLINTH Foundation to Plinth 30 days EMERALD – T6 MMR 1 tower BASEMENT Basement slab cycle (up to 4.5 m) 16 days RKS - TA MMR 1 slab 16 days AIRNXT - TJ SOUTH 1 slab PODIUM Podium slab cycle(up to 4.5 m) 11 days REJUVE – T11 B WEST - PUNE 1 slab
  • 18. Fastest achievements in GPL - Superstructure HEAD ACTIVITY ACHIEVEMENT PROJECT - TOWER ZONE FREQUENCY ALUMINIUM FORM TECH NEW ALUFORM MATERIAL - 1st setup of aluminium formwork 15 days WOODS SEC 43 – T2 NCR 1 tower 2nd slab after 1st set up (100% Aluform) 8 days WOODS SEC 43 – T6 NCR 1 tower Tower (19 to 30 floor height) (Level 3 to terrace) except service floor, refuge floor , change of shuttering 4 days NURTURE – T2, T3, T7 SOUTH 3 slabs 4 days REJUVE – T10A, T7A WEST- PUNE 4 slabs 4 days SOUTH ESTATE – SB2 NCR 2 slabs 4 days HILLSIDE 1 – T1 WEST- PUNE 1 slab 4 days AIR – A5 NCR 1 slab Average slab cycle (typical floors) (3rd floor to Terrace) 8.35, 8.45 days NURTURE – TD, TC SOUTH 2 towers Maximum no. of slabs cast in a tower in a month 7 slabs in 30 days NURTURE – TC (L16 to terrace) SOUTH 1 tower Maximum no. of slabs cast in a tower in a calendar month 6 slabs (Mar-22) AIR – A5 (L21 to L26) NCR 1 tower
  • 19. Fastest achievements in GPL – Lift, Finishing, NTA, OC Readiness HEAD ACTIVITY ACHIEVEMENT PROJECT - TOWER ZONE FREQUENCY LIFT COMPLETION Lift completion (lift NOC) (lag from terrace completion to lift installation) 36 days AVENUES – TD SOUTH 1 tower FINISHING ACTIVITIES COMPLETION Blockwork completion (from Terrace) 10 days AVENUES - TA SOUTH 1 tower Internal Plaster completion (from Terrace) 63 days NURTURE – TD SOUTH 1 tower Flat Flooring completion (lag from terrace) 68 days NURTURE – TA SOUTH 1 tower Common area flooring completion (from Terrace) 121 days AVENUES PH1 - TA SOUTH 1 tower O.C. READINESS FROM COMPLETION OF TERRACE OC Application from completion of Terrace 90 days 24 – E3 WEST - PUNE 1 tower CONSTRUCTION START TO OCA Construction start to OC Application 21.4 months (651 days) HILLSIDE 2 (T1, T2, T3) WEST - PUNE 3 towers