David Cammock - Trinidad Projects Highlights
Positions:
Project Delivery Manager
Project Campaign Manager
Facilities:
Hibiscus & Poinsettia Platforms
Central Block & Beachfield On-Shore
Gas Facilities
• Hibiscus Platform
Relocation and thereafter removal of Temporary Accommodation module.
Addition of new Permanent Accommodation module and helideck and associated
utilities upgrades.
Installation of Compression module.
• Poinsettia Platform
Installation of 65 x man temporary accommodation module.
Removal of 85 x man Temporary Accommodation module and helideck.
Addition of new Permanent Accommodation module and helideck and associated
utilities upgrades.
Control Room relocation and upgrade.
• Beachfield
Flare system replacement
VRU Compressor overhaul
Condensate Tank Bund Replacement
Opens Drains Upgrade
• Central Block
Relief and Blowdown system upgrade
Hot Oil Package upgrade
Three Phase Separator Upgrade
• As Project Delivery Manager I was responsible for
all Brownfield modification to the Hibiscus and
Poinsettia platforms as well as the Central Block
and Beachfield Gas processing facilities. I was
responsible for Projects in the SELECT, DEFINE and
EXECUTE phases.
• As Project Campaign Manager I was responsible
for integration and delivery of three major projects
on the Hibiscus and Poinsettia Platforms. These
being the Brownfield programme, installation and
integration of the Accommodation modules and
installation of the Hibiscus compression module.
• In both of these roles I managed a project team
comprising the following functions: HSSE, Quality,
Project Controls, Project Engineering, Engineering,
Contracts & Procurement, Operations Assurance,
Logistics, Community Liaison, Completions,
Construction and Commissioning.
• In both of these roles I was accountable for
delivery from EPCM contractors such as Fluor and
McDermott and numerous smaller contractors and
fabricators based in Trinidad and overseas.
• I managed 10 major shutdowns in these roles.
Project: Beachfield Flare Replacement
1. Existing Flare prior to removal 2. New Flare Stack off-loading
3. New Flare Tip installation 4. New Flare installed 5. New Flare commissioned
Project: Hibiscus & Poinsettia Projects
1. Helideck Removal from Poinsettia 2. Temporary Accommodation Module removal from Poinsettia Platform
3. Temporary Accommodation Module
removal from Poinsettia Platform
4. DB50 Installing Compression Module on Hibiscus Platform
Project: Hibiscus Platform (Compression & Accommodation Modules Installed)
5. Hibiscus Platform after installation of Compression and Accommodation Modules
Project:
Starfish - Dolphin Platform
Position:
Project Delivery Manager
Topsides:
HIPPS Module Fabrication & Installation
Platform and Jacket strengthening
Riser & I-tube clamps
Piping, Structural and E&I Upgrades / Stair towers / Deck Extensions
Hydraulic Power Unit
Topsides Umbilical Termination Assembly
Sub-surface Control Centre
Subs-sea - Installation by Dive Support Vessel or Pipelay vessel:
Flowlines & Metrology Spools
Riser & I-Tube Clamps
Riser
I-tube
Umbilical
Manifold
SSIV
Hydraulic Flying Leads
Electrical Flying Leads
Flexible Jumpers
• Starfish project was a sub-sea tieback to
Dolphin platform.
• As Project Delivery Manager I was responsible
for all Brownfield modification to Dolphin
platform, as well as the greenfield Subsea
scope. I managed the Execute phase of the
project on a day to day basis. I reported
directly to the Senior Project Manager.
• In this role I managed the project team
comprising the following functions: HSSE,
Quality, Project Controls, Project Engineering,
Engineering, Contracts & Procurement,
Operations Assurance, Logistics, Community
Liaison, Completions, Construction and
Commissioning.
• In this role I was accountable for delivery from
EPCM contractors Fluor and Technip and
numerous smaller contractors and fabricators
based in Trinidad and overseas.
• I managed 3 shutdowns in this role.
Project: Starfish
1. G1200 Preparing to Lift HIPPS Module 2. HIPPS Module Installation 3. HIPPS Module Installed
4. East side of Dolphin Platform after HIPPS Module Installation 6. Riser installation by G1200
5. Winches for Riser, I-Tube and Umbilical Installation
Project: Starfish
1. Dive Support Vessel ‘Norman Commander’ at Dolphin Platform
3. Subsea Clamp Installation
2. Clamps being closed after
Riser Installation
Project: Starfish
1. Dolphin Platform after Starfish Project
Position:
Project Delivery Manager
Facilities:
Dolphin Accommodation Project
(Fabrication, Installation & Integration)
• It should be noted that in 2010 I was the
Engineering Manager for this project.
• As Project Delivery Manager I was responsible
for fabrication, on-shore completions and
commissioning, transport & installation, off-
shore hook-up and commissioning.
• In this role I was the client management
representative on site for the fabrication of
the accommodation module at Bay’s facility in
Corpus Christi, Texas, USA.
• I was also responsible for managing the
Brownfield Team for on-shore commissioning
as well as off-shore installation, hook-up and
commissioning.
2. Helideck Installation
1. Preparing for Helideck Installation
3. HVAC Ducting & VAV boxes 4. Wet Units Installation
& Framing of Sleeping Quarters
5. Switchgear Installation
Project: Dolphin Accommodations
1. Accommodation Module with Helideck Installed

Project Overview - D.Cammock

  • 1.
    David Cammock -Trinidad Projects Highlights
  • 2.
    Positions: Project Delivery Manager ProjectCampaign Manager Facilities: Hibiscus & Poinsettia Platforms Central Block & Beachfield On-Shore Gas Facilities • Hibiscus Platform Relocation and thereafter removal of Temporary Accommodation module. Addition of new Permanent Accommodation module and helideck and associated utilities upgrades. Installation of Compression module. • Poinsettia Platform Installation of 65 x man temporary accommodation module. Removal of 85 x man Temporary Accommodation module and helideck. Addition of new Permanent Accommodation module and helideck and associated utilities upgrades. Control Room relocation and upgrade. • Beachfield Flare system replacement VRU Compressor overhaul Condensate Tank Bund Replacement Opens Drains Upgrade • Central Block Relief and Blowdown system upgrade Hot Oil Package upgrade Three Phase Separator Upgrade • As Project Delivery Manager I was responsible for all Brownfield modification to the Hibiscus and Poinsettia platforms as well as the Central Block and Beachfield Gas processing facilities. I was responsible for Projects in the SELECT, DEFINE and EXECUTE phases. • As Project Campaign Manager I was responsible for integration and delivery of three major projects on the Hibiscus and Poinsettia Platforms. These being the Brownfield programme, installation and integration of the Accommodation modules and installation of the Hibiscus compression module. • In both of these roles I managed a project team comprising the following functions: HSSE, Quality, Project Controls, Project Engineering, Engineering, Contracts & Procurement, Operations Assurance, Logistics, Community Liaison, Completions, Construction and Commissioning. • In both of these roles I was accountable for delivery from EPCM contractors such as Fluor and McDermott and numerous smaller contractors and fabricators based in Trinidad and overseas. • I managed 10 major shutdowns in these roles.
  • 3.
    Project: Beachfield FlareReplacement 1. Existing Flare prior to removal 2. New Flare Stack off-loading 3. New Flare Tip installation 4. New Flare installed 5. New Flare commissioned
  • 4.
    Project: Hibiscus &Poinsettia Projects 1. Helideck Removal from Poinsettia 2. Temporary Accommodation Module removal from Poinsettia Platform 3. Temporary Accommodation Module removal from Poinsettia Platform 4. DB50 Installing Compression Module on Hibiscus Platform
  • 5.
    Project: Hibiscus Platform(Compression & Accommodation Modules Installed) 5. Hibiscus Platform after installation of Compression and Accommodation Modules
  • 6.
    Project: Starfish - DolphinPlatform Position: Project Delivery Manager Topsides: HIPPS Module Fabrication & Installation Platform and Jacket strengthening Riser & I-tube clamps Piping, Structural and E&I Upgrades / Stair towers / Deck Extensions Hydraulic Power Unit Topsides Umbilical Termination Assembly Sub-surface Control Centre Subs-sea - Installation by Dive Support Vessel or Pipelay vessel: Flowlines & Metrology Spools Riser & I-Tube Clamps Riser I-tube Umbilical Manifold SSIV Hydraulic Flying Leads Electrical Flying Leads Flexible Jumpers • Starfish project was a sub-sea tieback to Dolphin platform. • As Project Delivery Manager I was responsible for all Brownfield modification to Dolphin platform, as well as the greenfield Subsea scope. I managed the Execute phase of the project on a day to day basis. I reported directly to the Senior Project Manager. • In this role I managed the project team comprising the following functions: HSSE, Quality, Project Controls, Project Engineering, Engineering, Contracts & Procurement, Operations Assurance, Logistics, Community Liaison, Completions, Construction and Commissioning. • In this role I was accountable for delivery from EPCM contractors Fluor and Technip and numerous smaller contractors and fabricators based in Trinidad and overseas. • I managed 3 shutdowns in this role.
  • 7.
    Project: Starfish 1. G1200Preparing to Lift HIPPS Module 2. HIPPS Module Installation 3. HIPPS Module Installed 4. East side of Dolphin Platform after HIPPS Module Installation 6. Riser installation by G1200 5. Winches for Riser, I-Tube and Umbilical Installation
  • 8.
    Project: Starfish 1. DiveSupport Vessel ‘Norman Commander’ at Dolphin Platform 3. Subsea Clamp Installation 2. Clamps being closed after Riser Installation
  • 9.
    Project: Starfish 1. DolphinPlatform after Starfish Project
  • 10.
    Position: Project Delivery Manager Facilities: DolphinAccommodation Project (Fabrication, Installation & Integration) • It should be noted that in 2010 I was the Engineering Manager for this project. • As Project Delivery Manager I was responsible for fabrication, on-shore completions and commissioning, transport & installation, off- shore hook-up and commissioning. • In this role I was the client management representative on site for the fabrication of the accommodation module at Bay’s facility in Corpus Christi, Texas, USA. • I was also responsible for managing the Brownfield Team for on-shore commissioning as well as off-shore installation, hook-up and commissioning. 2. Helideck Installation 1. Preparing for Helideck Installation 3. HVAC Ducting & VAV boxes 4. Wet Units Installation & Framing of Sleeping Quarters 5. Switchgear Installation
  • 11.
    Project: Dolphin Accommodations 1.Accommodation Module with Helideck Installed