SlideShare a Scribd company logo
0
ICE Coasts, Marine Structures and Breakwaters 2013
19 September 2013
Laure Herbert
Senior Engineer, Mouchel Maritime
Puerto Caucedo Multimodal Terminal,
– Increased Terminal Capacity Through
Modification of Existing Breakwater
1
Contents
1. Introduction
2. Phase 2 Project Overview
3. Concept Stage Marine/Onshore Works
4. Risk Management
5. Conclusion
2
1. Introduction - Location
Puerto Caucedo
3
1. Introduction – Existing, Terminal Phase 1
• 600m Berth for Post Panamax
• 40 Hectares Container Yard
• 900m Breakwater
• Water Depths up to 20m
• 10m Design Wave Height
100m
Football Pitch
4
2. Phase 2 – Overview
Phase 2 Works:
• US$30m
• 300m Berth for Panamax
• Tug Berth
• RoRo Berth
• Access & Stacking Area
5
3. Concept Stage – Marine & Onshore Works
• Key Activity;
• Development Workshop;
• Operational Requirements;
• Design Constraints & Considerations;
• Procurement Strategy & Risk Register;
6
3. Concept – Marine Works
Navigation Review:
• Vessel Manoeuvring;
• Dredged Depth.
Design Vessel Criteria: LOA = 220m; Draft = 11m
-14.5mDRD
EXISTING DEPTH
-12.5mDRD
-13.5mDRD
DREDGED BOX
-15.0mDRD
N
MINIMUM
PERMISSIBLE
EXISTING BERTH
NEW BERTH
NEW RORO
NEW TUG BERTH
7
3. Concept – Marine Works
Quay Wall Considerations
i - Structure & Maintenance:
• Disturbance to existing breakwater;
• Backfill Requirements;
• Ground Conditions;
• Maintenance;
ii – Construction:
• Speed of Construction;
• Constructability;
• Materials;
8
3. Concept – Marine Works
- Combi Wall Concept Design
• Front wall: anchored tubular piles, tubular piles & sheet piles
• Anchor wall: sheet piles anchored within rubble mound breakwater
Basin
Seaward
Anchor Wall
Front Wall
Tug
Berth
RoRo Ramp
APPROX 50mAPPROX 26m
NEW BERTH
APPROX 40m
PORT SIDE SEA SIDE
DREDGED
LEVEL
-12.5mDRD
MATERIAL
FROM
DREDGING
-19.0mDRD
16m3 ACCROPODES
BREAKWATER
9
3. Concept - Onshore Works
- Operational Requirements;
- Conversion of existing breakwater crest:
i. Container Stacking Area
ii. Handling Operations
iii. Services/Welfare
iv. Access
- Separate Contracts
10
4. Risk & Key Issue Management in Contract
FEASIBILITY
IN OPERATION
CONSTRUCTION
Navigation
Access
Container Traffic
Hurricane
(Wave and Wind)
Interface with operations
Ground Conditions
Operational Requirements Programme
Quality
11
4. Risk Management – Ground Conditions
Feasibility Stage:
i. Constraints: Highly Variable/Voided/Brittle Ground, High seismic design loading;
ii. Design Approach: Extensive sensitivity testing/Robust design;
iii. Recommendations:
- Additional ground investigation;
- Seismic hazard study update;
- Rigorous design requirements in D&B documents;
In Contract:
i. Independent Design Analysis;
ii. Localised variability of bed material;
iii. Design adjusted.
12
4. Impact on Operations: Hurricane: Overtopping & Wind
Manage risk during construction and operations
i. Shut Down Risk Assessment;
ii. Mitigation Measures;
iii. Physical Modelling Review;
iv. Emergency Plan
OPERATING
AREA
1.2m
1.5m
13
4. Risk Management – Interface with operations
Constraints:
i. Port operates 24/7 and continuously;
ii. Disruptions to be fundamentally avoided;
iii. 4 contracts occurring simultaneously during construction period;
Mitigation Measures:
i. Close working relationships;
ii. Weekly lookahead liaison meetings;
iii. Barge manoeuvres controlled by Harbour Master;
iv. Programme reviewed frequently and included extensive contingency
planning to accommodate the threat of hurricanes;
14
5. Lessons Learnt
i. The project benefited from the Phase 1 experience in terms of:
• Design practicalities and knowledge of the local environment and port operations;
• Well established communication channels between the port’s staff and Mouchel.
ii. Concept/Feasibility Stages:
• Define operational requirements,
• Understand existing port operations,
• Identify key issues.
iii. Early Contractor Involvement and Contractor’s design independent analysis;
iv. Clear lines of communication between all parties
15
THANK YOU
16

More Related Content

What's hot

Evaluating logistical challenges of offshore module transportation
Evaluating logistical challenges of offshore module transportationEvaluating logistical challenges of offshore module transportation
Evaluating logistical challenges of offshore module transportation
Merrylyn Yeo
 
Beau M Wallace Curriculum Vitae
Beau M Wallace Curriculum VitaeBeau M Wallace Curriculum Vitae
Beau M Wallace Curriculum VitaeBeau Wallace
 
Selected Projects Portfolio Jorge Cabaco
Selected Projects Portfolio Jorge CabacoSelected Projects Portfolio Jorge Cabaco
Selected Projects Portfolio Jorge CabacoJorge Cabaco
 
Bert Savoie Resume
Bert Savoie ResumeBert Savoie Resume
Bert Savoie ResumeBert Savoie
 
Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012Richard Turnbull
 
East Java Gas Pipeline
East Java Gas PipelineEast Java Gas Pipeline
East Java Gas PipelineBoudewijn Baan
 
Sal offshore brochure_2016-05-03_web
Sal offshore brochure_2016-05-03_webSal offshore brochure_2016-05-03_web
Sal offshore brochure_2016-05-03_web
Nora Kohlhase
 
Royal Canadian Mounted Police: Mari-Tech 2017 Presentation
Royal Canadian Mounted Police: Mari-Tech 2017 PresentationRoyal Canadian Mounted Police: Mari-Tech 2017 Presentation
Royal Canadian Mounted Police: Mari-Tech 2017 Presentation
Rebecca Barton
 
Company Profile Jan De Nul Group (EN) - V2015-3
Company Profile Jan De Nul Group (EN) - V2015-3Company Profile Jan De Nul Group (EN) - V2015-3
Company Profile Jan De Nul Group (EN) - V2015-3Séamus Day
 
Premier Oil - Decommissioning Oil Projects In The North Sea Case Study
Premier Oil - Decommissioning Oil Projects In The North Sea Case StudyPremier Oil - Decommissioning Oil Projects In The North Sea Case Study
Premier Oil - Decommissioning Oil Projects In The North Sea Case Study
Thorne & Derrick International
 
Subsea field development
Subsea field developmentSubsea field development
Subsea field development
Hamid S
 
Lugo Marine - Barge Presentation 2011
Lugo Marine - Barge Presentation 2011Lugo Marine - Barge Presentation 2011
Lugo Marine - Barge Presentation 2011lugomarine
 
Preparing Trinidad and Tobago for Deepwater Developments
Preparing Trinidad and Tobago for Deepwater DevelopmentsPreparing Trinidad and Tobago for Deepwater Developments
Preparing Trinidad and Tobago for Deepwater Developments
Dylan Roberts
 

What's hot (18)

Evaluating logistical challenges of offshore module transportation
Evaluating logistical challenges of offshore module transportationEvaluating logistical challenges of offshore module transportation
Evaluating logistical challenges of offshore module transportation
 
Beau M Wallace Curriculum Vitae
Beau M Wallace Curriculum VitaeBeau M Wallace Curriculum Vitae
Beau M Wallace Curriculum Vitae
 
Selected Projects Portfolio Jorge Cabaco
Selected Projects Portfolio Jorge CabacoSelected Projects Portfolio Jorge Cabaco
Selected Projects Portfolio Jorge Cabaco
 
Bert Savoie Resume
Bert Savoie ResumeBert Savoie Resume
Bert Savoie Resume
 
WSR Resume
WSR ResumeWSR Resume
WSR Resume
 
Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012
 
CV2015
CV2015CV2015
CV2015
 
CV 2015 RAN
CV 2015 RANCV 2015 RAN
CV 2015 RAN
 
East Java Gas Pipeline
East Java Gas PipelineEast Java Gas Pipeline
East Java Gas Pipeline
 
Sal offshore brochure_2016-05-03_web
Sal offshore brochure_2016-05-03_webSal offshore brochure_2016-05-03_web
Sal offshore brochure_2016-05-03_web
 
Royal Canadian Mounted Police: Mari-Tech 2017 Presentation
Royal Canadian Mounted Police: Mari-Tech 2017 PresentationRoyal Canadian Mounted Police: Mari-Tech 2017 Presentation
Royal Canadian Mounted Police: Mari-Tech 2017 Presentation
 
Company Profile Jan De Nul Group (EN) - V2015-3
Company Profile Jan De Nul Group (EN) - V2015-3Company Profile Jan De Nul Group (EN) - V2015-3
Company Profile Jan De Nul Group (EN) - V2015-3
 
Premier Oil - Decommissioning Oil Projects In The North Sea Case Study
Premier Oil - Decommissioning Oil Projects In The North Sea Case StudyPremier Oil - Decommissioning Oil Projects In The North Sea Case Study
Premier Oil - Decommissioning Oil Projects In The North Sea Case Study
 
YH profile (E)
YH profile (E)YH profile (E)
YH profile (E)
 
Subsea field development
Subsea field developmentSubsea field development
Subsea field development
 
Lugo Marine - Barge Presentation 2011
Lugo Marine - Barge Presentation 2011Lugo Marine - Barge Presentation 2011
Lugo Marine - Barge Presentation 2011
 
Preparing Trinidad and Tobago for Deepwater Developments
Preparing Trinidad and Tobago for Deepwater DevelopmentsPreparing Trinidad and Tobago for Deepwater Developments
Preparing Trinidad and Tobago for Deepwater Developments
 
Presentation AC2_EN
Presentation AC2_ENPresentation AC2_EN
Presentation AC2_EN
 

Similar to Herbert, laure

DEEP SEA MINING – SHIP DESIGN FOR OPERABILITY IN GLOBAL ENVIRONMENTS
DEEP SEA MINING – SHIP DESIGN FOR OPERABILITY IN GLOBAL ENVIRONMENTSDEEP SEA MINING – SHIP DESIGN FOR OPERABILITY IN GLOBAL ENVIRONMENTS
DEEP SEA MINING – SHIP DESIGN FOR OPERABILITY IN GLOBAL ENVIRONMENTS
iQHub
 
David Goodwin Resume 2015 LP
David Goodwin Resume 2015 LPDavid Goodwin Resume 2015 LP
David Goodwin Resume 2015 LPDavid Goodwin
 
Nivaldo Curcio CV Feb 2015
Nivaldo Curcio CV Feb 2015Nivaldo Curcio CV Feb 2015
Nivaldo Curcio CV Feb 2015NIVALDO CURCIO
 
Modularization the-key-to-success
Modularization the-key-to-successModularization the-key-to-success
Modularization the-key-to-successMerrylyn Yeo
 
How are sea ports constructed?
How are sea ports constructed?How are sea ports constructed?
How are sea ports constructed?
Joyville Shapoorji Housing Pvt. Ltd
 
930DickWardTetraTechnologies.pdf
930DickWardTetraTechnologies.pdf930DickWardTetraTechnologies.pdf
930DickWardTetraTechnologies.pdf
RaviNobleseas
 
Bert Savoie Resume
Bert Savoie ResumeBert Savoie Resume
Bert Savoie ResumeBert Savoie
 
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South Australia
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South AustraliaMine Haul Road Upgrade Project OZ Minerals Prominent Hill South Australia
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South Australia
Stephen McKnight
 
Preparing Trinidad and Tobago for deepwater developments
Preparing Trinidad and Tobago for deepwater developmentsPreparing Trinidad and Tobago for deepwater developments
Preparing Trinidad and Tobago for deepwater developments
Advisian
 
Connecting offshore platforms to a subsea cable system
Connecting offshore platforms to a subsea cable system Connecting offshore platforms to a subsea cable system
Connecting offshore platforms to a subsea cable system
Jerry Brown
 
4 Cofferdams (Temporary Works) Risk Assessment Templates.docx
4 Cofferdams (Temporary Works) Risk Assessment Templates.docx4 Cofferdams (Temporary Works) Risk Assessment Templates.docx
4 Cofferdams (Temporary Works) Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
4 cofferdams (temporary works) risk assessment templates
4 cofferdams (temporary works) risk assessment templates4 cofferdams (temporary works) risk assessment templates
4 cofferdams (temporary works) risk assessment templates
Dwarika Bhushan Sharma
 
Khalid Khan-Geo (5-10-16)
Khalid Khan-Geo (5-10-16)Khalid Khan-Geo (5-10-16)
Khalid Khan-Geo (5-10-16)Khalid Khan
 
PetroSync - Deepwater Drilling Optimisation
PetroSync - Deepwater Drilling OptimisationPetroSync - Deepwater Drilling Optimisation
PetroSync - Deepwater Drilling Optimisation
PetroSync
 
DeesideSeaways MPSS Presentation Ver 3
DeesideSeaways MPSS  Presentation Ver 3DeesideSeaways MPSS  Presentation Ver 3
DeesideSeaways MPSS Presentation Ver 3Craig Lang
 
CV MECHANICAL ENGR-2000
CV MECHANICAL ENGR-2000CV MECHANICAL ENGR-2000
CV MECHANICAL ENGR-2000daniel cobar
 
Amjad survey inspector
Amjad survey inspectorAmjad survey inspector
Amjad survey inspector
Muhammad Amjad
 

Similar to Herbert, laure (20)

DEEP SEA MINING – SHIP DESIGN FOR OPERABILITY IN GLOBAL ENVIRONMENTS
DEEP SEA MINING – SHIP DESIGN FOR OPERABILITY IN GLOBAL ENVIRONMENTSDEEP SEA MINING – SHIP DESIGN FOR OPERABILITY IN GLOBAL ENVIRONMENTS
DEEP SEA MINING – SHIP DESIGN FOR OPERABILITY IN GLOBAL ENVIRONMENTS
 
David Goodwin Resume 2015 LP
David Goodwin Resume 2015 LPDavid Goodwin Resume 2015 LP
David Goodwin Resume 2015 LP
 
Nivaldo Curcio CV Feb 2015
Nivaldo Curcio CV Feb 2015Nivaldo Curcio CV Feb 2015
Nivaldo Curcio CV Feb 2015
 
Modularization the-key-to-success
Modularization the-key-to-successModularization the-key-to-success
Modularization the-key-to-success
 
How are sea ports constructed?
How are sea ports constructed?How are sea ports constructed?
How are sea ports constructed?
 
930DickWardTetraTechnologies.pdf
930DickWardTetraTechnologies.pdf930DickWardTetraTechnologies.pdf
930DickWardTetraTechnologies.pdf
 
Bert Savoie Resume
Bert Savoie ResumeBert Savoie Resume
Bert Savoie Resume
 
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South Australia
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South AustraliaMine Haul Road Upgrade Project OZ Minerals Prominent Hill South Australia
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South Australia
 
Preparing Trinidad and Tobago for deepwater developments
Preparing Trinidad and Tobago for deepwater developmentsPreparing Trinidad and Tobago for deepwater developments
Preparing Trinidad and Tobago for deepwater developments
 
Connecting offshore platforms to a subsea cable system
Connecting offshore platforms to a subsea cable system Connecting offshore platforms to a subsea cable system
Connecting offshore platforms to a subsea cable system
 
John Nelson CV 29 Oct 2015
John Nelson CV 29 Oct 2015John Nelson CV 29 Oct 2015
John Nelson CV 29 Oct 2015
 
Ravi's CV
Ravi's CVRavi's CV
Ravi's CV
 
4 Cofferdams (Temporary Works) Risk Assessment Templates.docx
4 Cofferdams (Temporary Works) Risk Assessment Templates.docx4 Cofferdams (Temporary Works) Risk Assessment Templates.docx
4 Cofferdams (Temporary Works) Risk Assessment Templates.docx
 
HUSSIEN CV 24-12-2012
HUSSIEN CV 24-12-2012HUSSIEN CV 24-12-2012
HUSSIEN CV 24-12-2012
 
4 cofferdams (temporary works) risk assessment templates
4 cofferdams (temporary works) risk assessment templates4 cofferdams (temporary works) risk assessment templates
4 cofferdams (temporary works) risk assessment templates
 
Khalid Khan-Geo (5-10-16)
Khalid Khan-Geo (5-10-16)Khalid Khan-Geo (5-10-16)
Khalid Khan-Geo (5-10-16)
 
PetroSync - Deepwater Drilling Optimisation
PetroSync - Deepwater Drilling OptimisationPetroSync - Deepwater Drilling Optimisation
PetroSync - Deepwater Drilling Optimisation
 
DeesideSeaways MPSS Presentation Ver 3
DeesideSeaways MPSS  Presentation Ver 3DeesideSeaways MPSS  Presentation Ver 3
DeesideSeaways MPSS Presentation Ver 3
 
CV MECHANICAL ENGR-2000
CV MECHANICAL ENGR-2000CV MECHANICAL ENGR-2000
CV MECHANICAL ENGR-2000
 
Amjad survey inspector
Amjad survey inspectorAmjad survey inspector
Amjad survey inspector
 

Recently uploaded

Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
Kamal Acharya
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
Online aptitude test management system project report.pdf
Online aptitude test management system project report.pdfOnline aptitude test management system project report.pdf
Online aptitude test management system project report.pdf
Kamal Acharya
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
Dr Ramhari Poudyal
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
symbo111
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
Rahul
 
AIR POLLUTION lecture EnE203 updated.pdf
AIR POLLUTION lecture EnE203 updated.pdfAIR POLLUTION lecture EnE203 updated.pdf
AIR POLLUTION lecture EnE203 updated.pdf
RicletoEspinosa1
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
gestioneergodomus
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Self-Control of Emotions by Slidesgo.pptx
Self-Control of Emotions by Slidesgo.pptxSelf-Control of Emotions by Slidesgo.pptx
Self-Control of Emotions by Slidesgo.pptx
iemerc2024
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
TOP 10 B TECH COLLEGES IN JAIPUR 2024.pptx
TOP 10 B TECH COLLEGES IN JAIPUR 2024.pptxTOP 10 B TECH COLLEGES IN JAIPUR 2024.pptx
TOP 10 B TECH COLLEGES IN JAIPUR 2024.pptx
nikitacareer3
 
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
obonagu
 
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
awadeshbabu
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 

Recently uploaded (20)

Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
Online aptitude test management system project report.pdf
Online aptitude test management system project report.pdfOnline aptitude test management system project report.pdf
Online aptitude test management system project report.pdf
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
 
AIR POLLUTION lecture EnE203 updated.pdf
AIR POLLUTION lecture EnE203 updated.pdfAIR POLLUTION lecture EnE203 updated.pdf
AIR POLLUTION lecture EnE203 updated.pdf
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Self-Control of Emotions by Slidesgo.pptx
Self-Control of Emotions by Slidesgo.pptxSelf-Control of Emotions by Slidesgo.pptx
Self-Control of Emotions by Slidesgo.pptx
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
TOP 10 B TECH COLLEGES IN JAIPUR 2024.pptx
TOP 10 B TECH COLLEGES IN JAIPUR 2024.pptxTOP 10 B TECH COLLEGES IN JAIPUR 2024.pptx
TOP 10 B TECH COLLEGES IN JAIPUR 2024.pptx
 
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
 
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 

Herbert, laure

  • 1. 0 ICE Coasts, Marine Structures and Breakwaters 2013 19 September 2013 Laure Herbert Senior Engineer, Mouchel Maritime Puerto Caucedo Multimodal Terminal, – Increased Terminal Capacity Through Modification of Existing Breakwater
  • 2. 1 Contents 1. Introduction 2. Phase 2 Project Overview 3. Concept Stage Marine/Onshore Works 4. Risk Management 5. Conclusion
  • 3. 2 1. Introduction - Location Puerto Caucedo
  • 4. 3 1. Introduction – Existing, Terminal Phase 1 • 600m Berth for Post Panamax • 40 Hectares Container Yard • 900m Breakwater • Water Depths up to 20m • 10m Design Wave Height 100m Football Pitch
  • 5. 4 2. Phase 2 – Overview Phase 2 Works: • US$30m • 300m Berth for Panamax • Tug Berth • RoRo Berth • Access & Stacking Area
  • 6. 5 3. Concept Stage – Marine & Onshore Works • Key Activity; • Development Workshop; • Operational Requirements; • Design Constraints & Considerations; • Procurement Strategy & Risk Register;
  • 7. 6 3. Concept – Marine Works Navigation Review: • Vessel Manoeuvring; • Dredged Depth. Design Vessel Criteria: LOA = 220m; Draft = 11m -14.5mDRD EXISTING DEPTH -12.5mDRD -13.5mDRD DREDGED BOX -15.0mDRD N MINIMUM PERMISSIBLE EXISTING BERTH NEW BERTH NEW RORO NEW TUG BERTH
  • 8. 7 3. Concept – Marine Works Quay Wall Considerations i - Structure & Maintenance: • Disturbance to existing breakwater; • Backfill Requirements; • Ground Conditions; • Maintenance; ii – Construction: • Speed of Construction; • Constructability; • Materials;
  • 9. 8 3. Concept – Marine Works - Combi Wall Concept Design • Front wall: anchored tubular piles, tubular piles & sheet piles • Anchor wall: sheet piles anchored within rubble mound breakwater Basin Seaward Anchor Wall Front Wall Tug Berth RoRo Ramp APPROX 50mAPPROX 26m NEW BERTH APPROX 40m PORT SIDE SEA SIDE DREDGED LEVEL -12.5mDRD MATERIAL FROM DREDGING -19.0mDRD 16m3 ACCROPODES BREAKWATER
  • 10. 9 3. Concept - Onshore Works - Operational Requirements; - Conversion of existing breakwater crest: i. Container Stacking Area ii. Handling Operations iii. Services/Welfare iv. Access - Separate Contracts
  • 11. 10 4. Risk & Key Issue Management in Contract FEASIBILITY IN OPERATION CONSTRUCTION Navigation Access Container Traffic Hurricane (Wave and Wind) Interface with operations Ground Conditions Operational Requirements Programme Quality
  • 12. 11 4. Risk Management – Ground Conditions Feasibility Stage: i. Constraints: Highly Variable/Voided/Brittle Ground, High seismic design loading; ii. Design Approach: Extensive sensitivity testing/Robust design; iii. Recommendations: - Additional ground investigation; - Seismic hazard study update; - Rigorous design requirements in D&B documents; In Contract: i. Independent Design Analysis; ii. Localised variability of bed material; iii. Design adjusted.
  • 13. 12 4. Impact on Operations: Hurricane: Overtopping & Wind Manage risk during construction and operations i. Shut Down Risk Assessment; ii. Mitigation Measures; iii. Physical Modelling Review; iv. Emergency Plan OPERATING AREA 1.2m 1.5m
  • 14. 13 4. Risk Management – Interface with operations Constraints: i. Port operates 24/7 and continuously; ii. Disruptions to be fundamentally avoided; iii. 4 contracts occurring simultaneously during construction period; Mitigation Measures: i. Close working relationships; ii. Weekly lookahead liaison meetings; iii. Barge manoeuvres controlled by Harbour Master; iv. Programme reviewed frequently and included extensive contingency planning to accommodate the threat of hurricanes;
  • 15. 14 5. Lessons Learnt i. The project benefited from the Phase 1 experience in terms of: • Design practicalities and knowledge of the local environment and port operations; • Well established communication channels between the port’s staff and Mouchel. ii. Concept/Feasibility Stages: • Define operational requirements, • Understand existing port operations, • Identify key issues. iii. Early Contractor Involvement and Contractor’s design independent analysis; iv. Clear lines of communication between all parties
  • 17. 16