SlideShare a Scribd company logo
EMPLOYER
NWSDB CENTRAL PROVINCE
SRI LANKA
NATIONAL WATER SUPPLY AND
DRAINAGE BOARD
MAIN CONTRACTOR
OTV
VEOLIA WATER TECHNOLOGIES
GREATER MATALE WATER SUPPLY SCHEME
SRI LANKA
METHOD STATEMENT FOR TWT BASE CONCRETE POURING
A 2018/09/18 BHARATHA LK NJ
REV DATE PREPARED CHECKED APPROVED DESCRIPTION
Format :
A4
This document is the intellectual property of
the relevant issuer. It shall not be
reproduced, used or disclosed other than
with the document issuer’s acceptance.
For Employer Approval :
□ Approved □ Comment □ Rejected
Date:
Name:
Signature:
Page 1 of
Sub-Contractor
Document Reference :
GREATER MATALE WATER SUPPLY SCHEME
SRI LANKA
METHOD STATEMENT FOR TWT BASE CONCRETE POURING
Page: 2 of 9
Date: 18/09/2018
Rev: 1
TABLE OF CONTENTS
Section Description
1. PURPOSE
2. SCOPE
3. DEFINITIONS
4. REFERENCES
5. MATERIALS
5.1 Ready mix concrete
6. MOBILIZATION OF WORKFORCE & EQUIPMENT
6.1 Construction Plant & Equipment
6.2 Manpower
7. WORKING METHODS / PROCEDURES
7.1 Number of truck mixtures & delivery
7.2 Placing ofconcrete
7.3 Maintaining the finish level ofconcrete
7.4 Pouring sequence and layer thickness
7.5 Concrete consolidation
7.6 Curing of concrete
8. INSPECTION, TESTING & QUALITY CONTROL
9. SAFETY & SECURITY
9.1 General Provisions
9.2 Safety Action Plan
10. ATTACHMENTS
GREATER MATALE WATER SUPPLY SCHEME
SRI LANKA
METHOD STATEMENT FOR TWT BASE CONCRETE POURING
Page: 3 of 9
Date: 18/09/2018
Rev: 1
1. PURPOSE
The purpose of this Method Statement is to create awareness of common tasks involved in TWT base
concrete pouring and ensure the execution is in full compliance with Project Specifications & Standards,
Drawings and other related international Standards & Specifications including HSE requirements. This
Method Statement shall be communicated and be understood by all personnel associated with the task
before commencing the activity.
2. SCOPE
This document enumerates the plan activities and execution activities for the concrete pouring in TWT.
Concrete pouring procedure shall be in accordancewith this Method Statement. Supply, placing finishing
and curing for all applications in line with project requirements
3. DEFINITIONS
NWSDB : National Water Supply and Drainage Board
CONTRACTOR : OTV Veolia
SUB-CONTRACTOR : China Eleventh Chemical Construction Co. Ltd.( ELECO)
PROJECT : Greater Malate Water Supply Scheme
CMS : Construction Method Statement
QA / QC : Quality Assurance & Quality Control
HSE : Health Safety & Environment
PPE : Personnel Protective Equipment
RA : Risk Assessment
GREATER MATALE WATER SUPPLY SCHEME
SRI LANKA
METHOD STATEMENT FOR TWT BASE CONCRETE POURING
Page: 4 of 9
Date: 18/09/2018
Rev: 1
4. REFERENCES
- Specification for civil engineering works – NWSDB/SBD/Plant & Design – Build: Specification
- TWT Detail Drawings
- ITP & Check lists for concrete works
5. RESPONSIBILITIES
- Responsibilities for ensuring that the steps in this procedure shall be carried out are specified at
relevant steps in the procedure:
 Site Manager
 Construction manager
 QA/QC Engineer
 Site Engineer
 HSE officer
 SK
6. MATERIALS
All Material listed below shall be approved and inspected by NWSDB prior to use at site.
6.1 READY MIX CONCRETE
Grade 35A ready mix concrete will use for the whole structure.
7. MOBILIZATION OF WORKFORCE AND EQUIPMENT
7.1 CONSTRUCTION PLANT & EQUIPMENT
 Mobile crane
 Pump car
 Poker vibrators
 Carpentry / Masonry Tools
 Wooden level pegs
GREATER MATALE WATER SUPPLY SCHEME
SRI LANKA
METHOD STATEMENT FOR TWT BASE CONCRETE POURING
Page: 5 of 9
Date: 18/09/2018
Rev: 1
7.2 MAN POWER
 Site / QC Engineer
 HSE officer
 Foramens
 Carpenters
 Masons
 Helpers
8. WORKING METHODS / PROCEDURES
8.1 Number of truck mixtures & delivery
Total arrange concrete for the pouring process(approximately) = 225 m3
Capacity of one truck mixture = 5.0 m3
Number of trips required = 225 / 5
= 45 Nos
Time assumed for placement of one truck (5.0 m3
) = 15 min
Numbers of truck mixtures per hour = 60 / 15 = 4 truck mixtures
Travel / Loading time for one truck mixtures = 45 mins
Therefore to have continuous supply of concrete at pouring area shall be 5 truck mixtures, 6 truck
mixtures shall be provided keeping one standby
8.2 Placing of concrete
- For placing concrete, pumping car and crane with skip bucket will use. Pumping car having 38
m boom length shall be provided. Concrete will pour with pump car and crane in same time form
the two banks of treated water tank. As per the sketch: 1
8.3 Maintaining the finish level of concrete
- Level pegs(wooden) shall be provided at about 2m intervals to keep top level uniform and
level instrument to be used for verification.
GREATER MATALE WATER SUPPLY SCHEME
SRI LANKA
METHOD STATEMENT FOR TWT BASE CONCRETE POURING
Page: 6 of 9
Date: 18/09/2018
Rev: 1
8.4 pouring sequence and layer thickness
- First the perimeter wall of the sump shall be complete having not more than 500mm layer
thickness. Free falling height shall not exceeded 1.5m
- For base pouring continue with 2m layer wise from a side of base, as per the Sketch: 2
8.5 Concrete consolidation
- All concrete shall be thoroughly consolidated by suitable means during placement and shall
be thoroughly worked around reinforcement and embedded fixtures and into corners of forms.
Concrete consolidation shall be executed with vibrators without displacing the steel reinforcement,
and ensuring that all parts are filled and compacted until grout floats to the surface. Pouring shall be
continuous and fill the whole section, both vertically and horizontally. Vibrators shall be inserted and
removed slowly, at a speed between 80 mm to 100 mm per second, to prevent the formation of voids
inside the concrete.
- Contact between vibrators and any reinforcing rods will be avoided.
8.6 Curing of concrete
Protect freshly placed concrete from premature drying and excessive cold or hot temperature and
maintain without drying at a relatively constant temperature for the period of time necessary for
hydration of the cement and proper hardening of the concrete.
Start initial curing as soon as free moisture has disappeared from the concrete surface after placing
and furnishing of concrete.
Water for curing shall be portable water which shall meet the requirements of NWSDB specification.
Proper water curing shall be achieved by covering the concrete with specified absorptive cover (such
as burlaps) and keeping the cover continuously wet.
Moisture cover (plastic sheet) shall be overlaid on top of absorptive cover with 75mm overlap in
order to retain moisture by reducing the evaporation.
Water curing shall be continued until the compressive strength has reached 70 % of the specified
strength, but not be less than 7 days after placement.
Casting dates will be noted down and 7 days curing period will be assured by construction
supervisors and continuously monitored by QC Engineers.
GREATER MATALE WATER SUPPLY SCHEME
SRI LANKA
METHOD STATEMENT FOR TWT BASE CONCRETE POURING
Page: 7 of 9
Date: 18/09/2018
Rev: 1
9. INSPECTION, TESTING & QUALITY CONTROL (QA/ QC)
- Inspection shall be accordance with approved ITP & Checklist
- Temperature and slump shall be maintained at NWSDB specification limits
- An RFI shall be raised 24 hrs. in advance prior to executing the activity
10. SAFETY & SECURITY
10.1 General Provisions
Protection and safety shall be in accordance with Project Safety Manual and ELECO Safety Manual
approved by OTV / NWSDB. ELECO shall provide temporary fence, barricades, lights and any other
preventive measure according to the approved Safety Manual for personnel safety during
construction. Directions given in manufacture’s MSDS shall strictly followed.
10.2 Safety Action Plan
Where applicable, Permit to Work will be obtained prior to starting the works.
Workforce and supervisors shall be aware of common risks that could be encountered during the
activities associated with masonry works. Necessary warnings, suitable barricades, proper access,
shall be established. PPE for workers are mandatory.
Site Engineer and General Foreman shall arrange all necessarysafety requirements at site and they
will ensure workplace is safe.
Safety Inspector shall ensure that all safety measures are implemented at workplace and
workers/staff are aware of safety risks.
11. ATTACHMENT
Sketch : 1 , 2
Annex 1: Risk Assessment
GREATER MATALE WATER SUPPLY SCHEME
SRI LANKA
METHOD STATEMENT FOR TWT BASE CONCRETE POURING
Page: 8 of 9
Date: 18/09/2018
Rev: 1
SKETCHES
SKETCH: 01
GREATER MATALE WATER SUPPLY SCHEME
SRI LANKA
METHOD STATEMENT FOR TWT BASE CONCRETE POURING
Page: 9 of 9
Date: 18/09/2018
Rev: 1
SKETCH: 02

More Related Content

What's hot

Construction Methods & Sequence
Construction  Methods & SequenceConstruction  Methods & Sequence
Construction Methods & Sequence
David H Moloney
 
Method painting works emulsion paint
Method painting works   emulsion paintMethod painting works   emulsion paint
Method painting works emulsion paintMinh Bui Si
 
Ms 12.doc 7.6.13.
Ms 12.doc 7.6.13.Ms 12.doc 7.6.13.
Ms 12.doc 7.6.13.maqsood1459
 
Diaphragm wall construction
Diaphragm wall constructionDiaphragm wall construction
Diaphragm wall construction
ANILKUMARMUCHINTALA
 
Method statement honycomb repairing
Method statement  honycomb repairingMethod statement  honycomb repairing
Method statement honycomb repairing
Bharatha Rathnayke
 
Supervision of piling works, ACES, 2011, Singapore
Supervision of piling works, ACES, 2011, SingaporeSupervision of piling works, ACES, 2011, Singapore
Supervision of piling works, ACES, 2011, SingaporeTong Seng Chua
 
Demolition methods and its sequence
Demolition methods and its sequenceDemolition methods and its sequence
Demolition methods and its sequenceRanjith Kumar
 
Method of statement piping works
Method of statement piping works Method of statement piping works
Method of statement piping works
Shaik Mohsin
 
Piling work method statement cm- ms- bw - 002
Piling work method statement   cm- ms- bw - 002Piling work method statement   cm- ms- bw - 002
Piling work method statement cm- ms- bw - 002Minh Bui Si
 
Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Ankit Singh
 
Slipform
SlipformSlipform
Slipform
Rahul Razz
 
Method statement for expansion joint
Method statement for expansion jointMethod statement for expansion joint
Method statement for expansion joint
akash yadav
 
Diaphragm wall construction
Diaphragm wall constructionDiaphragm wall construction
Diaphragm wall construction
ABHISHEK THAKKAE
 
ERECTION/LAUNCHING OF PRECAST SEGMENT USING GROUND SUPPORT SYSTEM (UNDER SLUNG)
ERECTION/LAUNCHING OF PRECAST SEGMENT USING GROUND SUPPORT SYSTEM (UNDER SLUNG)ERECTION/LAUNCHING OF PRECAST SEGMENT USING GROUND SUPPORT SYSTEM (UNDER SLUNG)
ERECTION/LAUNCHING OF PRECAST SEGMENT USING GROUND SUPPORT SYSTEM (UNDER SLUNG)
Rakesh Kumar Choubey
 
Metro rail segments
Metro rail segmentsMetro rail segments
Metro rail segments
Axay Sharma
 
Bs 1881-part-116-83
Bs 1881-part-116-83Bs 1881-part-116-83
Bs 1881-part-116-83
adrianafarniza
 
BLASTING and its type
BLASTING and its typeBLASTING and its type
BLASTING and its type
jaimin1702
 
Building work method statement cm - ms- bw - 001
Building work method statement  cm - ms- bw - 001Building work method statement  cm - ms- bw - 001
Building work method statement cm - ms- bw - 001Minh Bui Si
 
Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavement
pradip dangar
 

What's hot (20)

Construction Methods & Sequence
Construction  Methods & SequenceConstruction  Methods & Sequence
Construction Methods & Sequence
 
Method painting works emulsion paint
Method painting works   emulsion paintMethod painting works   emulsion paint
Method painting works emulsion paint
 
Ms 12.doc 7.6.13.
Ms 12.doc 7.6.13.Ms 12.doc 7.6.13.
Ms 12.doc 7.6.13.
 
Diaphragm wall construction
Diaphragm wall constructionDiaphragm wall construction
Diaphragm wall construction
 
Method statement honycomb repairing
Method statement  honycomb repairingMethod statement  honycomb repairing
Method statement honycomb repairing
 
Supervision of piling works, ACES, 2011, Singapore
Supervision of piling works, ACES, 2011, SingaporeSupervision of piling works, ACES, 2011, Singapore
Supervision of piling works, ACES, 2011, Singapore
 
Demolition methods and its sequence
Demolition methods and its sequenceDemolition methods and its sequence
Demolition methods and its sequence
 
Method of statement piping works
Method of statement piping works Method of statement piping works
Method of statement piping works
 
Piling work method statement cm- ms- bw - 002
Piling work method statement   cm- ms- bw - 002Piling work method statement   cm- ms- bw - 002
Piling work method statement cm- ms- bw - 002
 
PPT OF LG
PPT OF LGPPT OF LG
PPT OF LG
 
Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)
 
Slipform
SlipformSlipform
Slipform
 
Method statement for expansion joint
Method statement for expansion jointMethod statement for expansion joint
Method statement for expansion joint
 
Diaphragm wall construction
Diaphragm wall constructionDiaphragm wall construction
Diaphragm wall construction
 
ERECTION/LAUNCHING OF PRECAST SEGMENT USING GROUND SUPPORT SYSTEM (UNDER SLUNG)
ERECTION/LAUNCHING OF PRECAST SEGMENT USING GROUND SUPPORT SYSTEM (UNDER SLUNG)ERECTION/LAUNCHING OF PRECAST SEGMENT USING GROUND SUPPORT SYSTEM (UNDER SLUNG)
ERECTION/LAUNCHING OF PRECAST SEGMENT USING GROUND SUPPORT SYSTEM (UNDER SLUNG)
 
Metro rail segments
Metro rail segmentsMetro rail segments
Metro rail segments
 
Bs 1881-part-116-83
Bs 1881-part-116-83Bs 1881-part-116-83
Bs 1881-part-116-83
 
BLASTING and its type
BLASTING and its typeBLASTING and its type
BLASTING and its type
 
Building work method statement cm - ms- bw - 001
Building work method statement  cm - ms- bw - 001Building work method statement  cm - ms- bw - 001
Building work method statement cm - ms- bw - 001
 
Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavement
 

Similar to Method statement tank base concrete pouring

QP_Safety_executive_procedure_final
QP_Safety_executive_procedure_finalQP_Safety_executive_procedure_final
QP_Safety_executive_procedure_finalIan Kelly
 
CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016Ali Issa
 
Civil-Report on industrial training at URCC
Civil-Report on industrial training at URCCCivil-Report on industrial training at URCC
Civil-Report on industrial training at URCC
Rakshita Raghunath
 
CV Abd. Hadi Ahmad
CV Abd. Hadi AhmadCV Abd. Hadi Ahmad
CV Abd. Hadi AhmadAhmad Hadi
 
Concreting of super structure
Concreting of super structureConcreting of super structure
Concreting of super structureMinh Bui Si
 
Civil Engineering Measurment
Civil Engineering MeasurmentCivil Engineering Measurment
Civil Engineering Measurment
Sultan M Muzahir
 
Excavation method rectified 13-11-2010
Excavation method   rectified 13-11-2010Excavation method   rectified 13-11-2010
Excavation method rectified 13-11-2010Minh Bui Si
 
Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)
Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)
Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)
Krm Chari
 
A.youssef_c.v.2014.doc-2(3)
A.youssef_c.v.2014.doc-2(3)A.youssef_c.v.2014.doc-2(3)
A.youssef_c.v.2014.doc-2(3)Ahmed Youssef
 
CIVIL SUPERVISOR-CV-abdul shukoor
CIVIL SUPERVISOR-CV-abdul shukoorCIVIL SUPERVISOR-CV-abdul shukoor
CIVIL SUPERVISOR-CV-abdul shukoorabdul shukoor
 
Trevor Kemp CV - January 2015
Trevor Kemp CV - January 2015Trevor Kemp CV - January 2015
Trevor Kemp CV - January 2015TREVOR KEMP
 
CV. Mechincal Engineer
CV. Mechincal EngineerCV. Mechincal Engineer
CV. Mechincal EngineerAhmad Hassan
 

Similar to Method statement tank base concrete pouring (20)

Resume UAE
Resume UAEResume UAE
Resume UAE
 
QP_Safety_executive_procedure_final
QP_Safety_executive_procedure_finalQP_Safety_executive_procedure_final
QP_Safety_executive_procedure_final
 
CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016
 
Civil-Report on industrial training at URCC
Civil-Report on industrial training at URCCCivil-Report on industrial training at URCC
Civil-Report on industrial training at URCC
 
CV of broosto -7-2016
CV of broosto -7-2016CV of broosto -7-2016
CV of broosto -7-2016
 
03 Mohamed_fathi
03 Mohamed_fathi03 Mohamed_fathi
03 Mohamed_fathi
 
Column & beam
Column & beamColumn & beam
Column & beam
 
CV Abd. Hadi Ahmad
CV Abd. Hadi AhmadCV Abd. Hadi Ahmad
CV Abd. Hadi Ahmad
 
Husam CV updated (1)
Husam CV updated (1)Husam CV updated (1)
Husam CV updated (1)
 
SCC WITH KIM.PPTX
SCC WITH KIM.PPTXSCC WITH KIM.PPTX
SCC WITH KIM.PPTX
 
Concreting of super structure
Concreting of super structureConcreting of super structure
Concreting of super structure
 
Civil Engineering Measurment
Civil Engineering MeasurmentCivil Engineering Measurment
Civil Engineering Measurment
 
Excavation method rectified 13-11-2010
Excavation method   rectified 13-11-2010Excavation method   rectified 13-11-2010
Excavation method rectified 13-11-2010
 
Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)
Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)
Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)
 
my_cv_WP
my_cv_WPmy_cv_WP
my_cv_WP
 
Mahmoud Ahmed ElbadawyCV
Mahmoud Ahmed ElbadawyCVMahmoud Ahmed ElbadawyCV
Mahmoud Ahmed ElbadawyCV
 
A.youssef_c.v.2014.doc-2(3)
A.youssef_c.v.2014.doc-2(3)A.youssef_c.v.2014.doc-2(3)
A.youssef_c.v.2014.doc-2(3)
 
CIVIL SUPERVISOR-CV-abdul shukoor
CIVIL SUPERVISOR-CV-abdul shukoorCIVIL SUPERVISOR-CV-abdul shukoor
CIVIL SUPERVISOR-CV-abdul shukoor
 
Trevor Kemp CV - January 2015
Trevor Kemp CV - January 2015Trevor Kemp CV - January 2015
Trevor Kemp CV - January 2015
 
CV. Mechincal Engineer
CV. Mechincal EngineerCV. Mechincal Engineer
CV. Mechincal Engineer
 

Recently uploaded

weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
abh.arya
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
Kamal Acharya
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
MuhammadTufail242431
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
PrashantGoswami42
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 

Recently uploaded (20)

weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 

Method statement tank base concrete pouring

  • 1. EMPLOYER NWSDB CENTRAL PROVINCE SRI LANKA NATIONAL WATER SUPPLY AND DRAINAGE BOARD MAIN CONTRACTOR OTV VEOLIA WATER TECHNOLOGIES GREATER MATALE WATER SUPPLY SCHEME SRI LANKA METHOD STATEMENT FOR TWT BASE CONCRETE POURING A 2018/09/18 BHARATHA LK NJ REV DATE PREPARED CHECKED APPROVED DESCRIPTION Format : A4 This document is the intellectual property of the relevant issuer. It shall not be reproduced, used or disclosed other than with the document issuer’s acceptance. For Employer Approval : □ Approved □ Comment □ Rejected Date: Name: Signature: Page 1 of Sub-Contractor Document Reference :
  • 2. GREATER MATALE WATER SUPPLY SCHEME SRI LANKA METHOD STATEMENT FOR TWT BASE CONCRETE POURING Page: 2 of 9 Date: 18/09/2018 Rev: 1 TABLE OF CONTENTS Section Description 1. PURPOSE 2. SCOPE 3. DEFINITIONS 4. REFERENCES 5. MATERIALS 5.1 Ready mix concrete 6. MOBILIZATION OF WORKFORCE & EQUIPMENT 6.1 Construction Plant & Equipment 6.2 Manpower 7. WORKING METHODS / PROCEDURES 7.1 Number of truck mixtures & delivery 7.2 Placing ofconcrete 7.3 Maintaining the finish level ofconcrete 7.4 Pouring sequence and layer thickness 7.5 Concrete consolidation 7.6 Curing of concrete 8. INSPECTION, TESTING & QUALITY CONTROL 9. SAFETY & SECURITY 9.1 General Provisions 9.2 Safety Action Plan 10. ATTACHMENTS
  • 3. GREATER MATALE WATER SUPPLY SCHEME SRI LANKA METHOD STATEMENT FOR TWT BASE CONCRETE POURING Page: 3 of 9 Date: 18/09/2018 Rev: 1 1. PURPOSE The purpose of this Method Statement is to create awareness of common tasks involved in TWT base concrete pouring and ensure the execution is in full compliance with Project Specifications & Standards, Drawings and other related international Standards & Specifications including HSE requirements. This Method Statement shall be communicated and be understood by all personnel associated with the task before commencing the activity. 2. SCOPE This document enumerates the plan activities and execution activities for the concrete pouring in TWT. Concrete pouring procedure shall be in accordancewith this Method Statement. Supply, placing finishing and curing for all applications in line with project requirements 3. DEFINITIONS NWSDB : National Water Supply and Drainage Board CONTRACTOR : OTV Veolia SUB-CONTRACTOR : China Eleventh Chemical Construction Co. Ltd.( ELECO) PROJECT : Greater Malate Water Supply Scheme CMS : Construction Method Statement QA / QC : Quality Assurance & Quality Control HSE : Health Safety & Environment PPE : Personnel Protective Equipment RA : Risk Assessment
  • 4. GREATER MATALE WATER SUPPLY SCHEME SRI LANKA METHOD STATEMENT FOR TWT BASE CONCRETE POURING Page: 4 of 9 Date: 18/09/2018 Rev: 1 4. REFERENCES - Specification for civil engineering works – NWSDB/SBD/Plant & Design – Build: Specification - TWT Detail Drawings - ITP & Check lists for concrete works 5. RESPONSIBILITIES - Responsibilities for ensuring that the steps in this procedure shall be carried out are specified at relevant steps in the procedure:  Site Manager  Construction manager  QA/QC Engineer  Site Engineer  HSE officer  SK 6. MATERIALS All Material listed below shall be approved and inspected by NWSDB prior to use at site. 6.1 READY MIX CONCRETE Grade 35A ready mix concrete will use for the whole structure. 7. MOBILIZATION OF WORKFORCE AND EQUIPMENT 7.1 CONSTRUCTION PLANT & EQUIPMENT  Mobile crane  Pump car  Poker vibrators  Carpentry / Masonry Tools  Wooden level pegs
  • 5. GREATER MATALE WATER SUPPLY SCHEME SRI LANKA METHOD STATEMENT FOR TWT BASE CONCRETE POURING Page: 5 of 9 Date: 18/09/2018 Rev: 1 7.2 MAN POWER  Site / QC Engineer  HSE officer  Foramens  Carpenters  Masons  Helpers 8. WORKING METHODS / PROCEDURES 8.1 Number of truck mixtures & delivery Total arrange concrete for the pouring process(approximately) = 225 m3 Capacity of one truck mixture = 5.0 m3 Number of trips required = 225 / 5 = 45 Nos Time assumed for placement of one truck (5.0 m3 ) = 15 min Numbers of truck mixtures per hour = 60 / 15 = 4 truck mixtures Travel / Loading time for one truck mixtures = 45 mins Therefore to have continuous supply of concrete at pouring area shall be 5 truck mixtures, 6 truck mixtures shall be provided keeping one standby 8.2 Placing of concrete - For placing concrete, pumping car and crane with skip bucket will use. Pumping car having 38 m boom length shall be provided. Concrete will pour with pump car and crane in same time form the two banks of treated water tank. As per the sketch: 1 8.3 Maintaining the finish level of concrete - Level pegs(wooden) shall be provided at about 2m intervals to keep top level uniform and level instrument to be used for verification.
  • 6. GREATER MATALE WATER SUPPLY SCHEME SRI LANKA METHOD STATEMENT FOR TWT BASE CONCRETE POURING Page: 6 of 9 Date: 18/09/2018 Rev: 1 8.4 pouring sequence and layer thickness - First the perimeter wall of the sump shall be complete having not more than 500mm layer thickness. Free falling height shall not exceeded 1.5m - For base pouring continue with 2m layer wise from a side of base, as per the Sketch: 2 8.5 Concrete consolidation - All concrete shall be thoroughly consolidated by suitable means during placement and shall be thoroughly worked around reinforcement and embedded fixtures and into corners of forms. Concrete consolidation shall be executed with vibrators without displacing the steel reinforcement, and ensuring that all parts are filled and compacted until grout floats to the surface. Pouring shall be continuous and fill the whole section, both vertically and horizontally. Vibrators shall be inserted and removed slowly, at a speed between 80 mm to 100 mm per second, to prevent the formation of voids inside the concrete. - Contact between vibrators and any reinforcing rods will be avoided. 8.6 Curing of concrete Protect freshly placed concrete from premature drying and excessive cold or hot temperature and maintain without drying at a relatively constant temperature for the period of time necessary for hydration of the cement and proper hardening of the concrete. Start initial curing as soon as free moisture has disappeared from the concrete surface after placing and furnishing of concrete. Water for curing shall be portable water which shall meet the requirements of NWSDB specification. Proper water curing shall be achieved by covering the concrete with specified absorptive cover (such as burlaps) and keeping the cover continuously wet. Moisture cover (plastic sheet) shall be overlaid on top of absorptive cover with 75mm overlap in order to retain moisture by reducing the evaporation. Water curing shall be continued until the compressive strength has reached 70 % of the specified strength, but not be less than 7 days after placement. Casting dates will be noted down and 7 days curing period will be assured by construction supervisors and continuously monitored by QC Engineers.
  • 7. GREATER MATALE WATER SUPPLY SCHEME SRI LANKA METHOD STATEMENT FOR TWT BASE CONCRETE POURING Page: 7 of 9 Date: 18/09/2018 Rev: 1 9. INSPECTION, TESTING & QUALITY CONTROL (QA/ QC) - Inspection shall be accordance with approved ITP & Checklist - Temperature and slump shall be maintained at NWSDB specification limits - An RFI shall be raised 24 hrs. in advance prior to executing the activity 10. SAFETY & SECURITY 10.1 General Provisions Protection and safety shall be in accordance with Project Safety Manual and ELECO Safety Manual approved by OTV / NWSDB. ELECO shall provide temporary fence, barricades, lights and any other preventive measure according to the approved Safety Manual for personnel safety during construction. Directions given in manufacture’s MSDS shall strictly followed. 10.2 Safety Action Plan Where applicable, Permit to Work will be obtained prior to starting the works. Workforce and supervisors shall be aware of common risks that could be encountered during the activities associated with masonry works. Necessary warnings, suitable barricades, proper access, shall be established. PPE for workers are mandatory. Site Engineer and General Foreman shall arrange all necessarysafety requirements at site and they will ensure workplace is safe. Safety Inspector shall ensure that all safety measures are implemented at workplace and workers/staff are aware of safety risks. 11. ATTACHMENT Sketch : 1 , 2 Annex 1: Risk Assessment
  • 8. GREATER MATALE WATER SUPPLY SCHEME SRI LANKA METHOD STATEMENT FOR TWT BASE CONCRETE POURING Page: 8 of 9 Date: 18/09/2018 Rev: 1 SKETCHES SKETCH: 01
  • 9. GREATER MATALE WATER SUPPLY SCHEME SRI LANKA METHOD STATEMENT FOR TWT BASE CONCRETE POURING Page: 9 of 9 Date: 18/09/2018 Rev: 1 SKETCH: 02