SlideShare a Scribd company logo
1
Definition of estimating
‘To form an approximate notion of the
amount, number, magnitude or position
of anything, without actual enumeration
or measurement.’
2
What estimates are made in projects
1. Time estimates are used in scheduling
work, assigning resources and determining
delivery dates.
2. Cost estimates are used for budgeting.
3. Cost and benefit estimates are used in
cost/benefit analysis to determine the
overall viability of a project.
3
Importance of accurate estimates
1. Inaccurate time estimates can result in inefficient
use of resources and late delivery.
2. Inaccurate cost estimates can result in insufficient
budget being allocated, or excess budget being set
aside for the project when it could be used for other
projects.
3. If the cost or benefits estimates are inaccurate this
can lead to incorrect decisions about proceeding
with the project being made.
When estimates are required
Project phase Estimates required
Initiation Time, cost and benefit estimates in
project definition.
Planning Time estimates in project schedule.
Cost estimates in project budget.
Cost and benefit estimates in business
case.
Start of project
stages
Time and cost estimates reconfirmed for
the stage.
5
Effort and duration
 Effort is the amount of work required to complete a
task – used to estimate cost of resources.
 Duration is the time that elapses between the start
and end of the task – used to estimate timeframe.
In estimating it is essential to know whether the
estimate is an effort or duration based estimate.
For example, the estimate for painting a room may be 10 hours
for two people (20 hours effort), over 3 days (duration) allowing for
other tasks and for the drying time of the paint.
6
Accuracy
Information Available (%)
0
100
50
Estimating accuracy
50 100
Estimating accuracy increases during the life of the
project as more knowledge is gained about the project.
7
Types of estimates
1. Order of magnitude: obtained in the initiation
phase of a project for the whole project
2. 2. Budget estimate: an estimate derived during
the planning phase for the whole project
3. Definitive estimate: an estimate derived at the
start of each project stage
Different types of estimates reflect the range of
accuracy expected from the estimate.
Three types of project estimates* are:
8
Estimating methods
1. Top down estimating
2. Bottom up estimating
3. Parametric estimating
Three commonly used methods of estimating are:
9
Top-down method
The top-down method is also known as the analogous method.
It is used to determine order of magnitude estimates in the initiation
phase of the project.
The method uses the actual durations, effort or costs from previous
projects as a basis for estimating the effort or costs for the current
project.
1. Identify a previous project or section of a previous project
that is similar to the current project.
2. Assess the extent to which the current project is similar to
the previous project
3. Compute the estimate for the current project based on the
actual durations, effort or costs from the previous project and
the comparison factor.
10
Bottom-up method
The bottom-up method is considered to be the most accurate method
for generating project estimates.
It is used to determine budget or definitive estimates during the
planning phase and at the start of each project stage.
The method uses the Work Breakdown Structure (WBS) developed
during the planning stage of the project. Estimates are created for all
tasks at the lowest level of the WBS and then these are accumulated
to determine the estimates for the whole project.
The consensus technique* is usually used to obtain task estimates for
the low level tasks on the WBS it also builds active involvement,
cooperation and commitment. Experts with the skills required to
perform the work should be included in the estimating process.
One disadvantage of the bottom-up method is that it is much more
time-consuming than other methods.
11
Parametric method
The parametric method is also known as the object
based method.
It is used to obtain definitive estimates and to confirm
bottom up estimates where possible.
A simple concept is used, namely:
If the amount of effort needed to carry out a particular
activity for a particular object is known, and the number
of objects is known, the effort required to perform the
activity for all the objects can be determined.
The amount of effort for the single activity can be
determined either from a standard, which has been
established from previous experience, or by executing a
sample activity if no standard exists.
12
1. Identify an item to be estimated.
2. Estimate the number of items.
3. Estimate the effort per item.
4. Multiply effort per item by number of items to
determine the total effort.
Parametric method (Cont.)
For example, if the assembly of one library shelving
stack takes an hour and a half and there are 40 stacks
to assemble then the total effort is 60 hours.
Steps in deriving the estimate:
13
Estimating techniques
1. Weighted average estimating
2. Consensus estimating
3. Phase ratios
Three commonly used techniques for obtaining
estimates are:
14
Weighted average estimates
Estimated effort = (O + 4M + P ) / 6
Weighted average estimating is also known as sensitivity
analysis estimating.
With this technique three estimates are obtained for each
item rather than one. This provides a more accurate
estimate than when only one estimate value is provided.
The three estimates are known as the best case (O =
Optimistic), worst case (P = Pessimistic) and most likely
(M = Median).
These are then used in the following formula to determine
the estimated effort:
15
Consensus estimating
 A briefing is provided to the estimating team on the project.
 Each person is provided with a list of work components to
estimate.
 Each person independently estimates O, M and P for each
work component.
 The estimates are written up on the whiteboard.
 Each person discusses the basis and assumptions for their
estimates.
 A revised set of estimates is produced.
 Averages for the O, M and P values are calculated.
 These averages are then used in the weighted averages
formula to calculate the estimated effort.
Steps in conducting a consensus estimating session:
16
Phase ratios
Project phase ratios provide a means of generating a top-down
order of magnitude duration estimate for a project, or they can be
used as a sense check of bottom-up duration estimates of the time
allocated to each project phase.
Phase ratio estimating uses an estimate for one phase of a project
to derive the likely size of the other phases, and hence an overall
estimate for the project.
For example, if analysis takes 5 weeks, and this represents 10% of
the project, then the project is likely to take 50 weeks.
The concept behind this method is that similar types of projects
would normally spend the same percentage of time in each phase.
Phase ratios are not accurate enough to be used as a budget or
definitive estimates.
17
Phase ratio percentages
Initiation 5%
Planning 20%
Analysis 10%
Design 10%
Construction 20%
Testing 20%
Implementation 10%
Closure 5%
Phase Ratio
The phase ratio technique is based on studies that average the
proportion of time that a large sample of projects has spent on standard
project phases. An initial set of project phase ratios is provided below.
These should be refined based on results from completed projects.
18
Estimating assumptions
An estimate is a qualified guess.
Every estimate is based on assumptions.
An estimate assumption is a statement which has been
considered to be true in deriving the estimate.
These estimate assumptions need to be specified so that
the basis of the estimate is known and validity of the
assumptions can be assessed.
For example, a work effort estimate is usually based on a
level of skill and expertise. If a lower level of skill and
expertise is utilised then it is likely that the task will
require more effort.
19
Applying contingency to estimates
 Can be applied to each project stage or to each task. It provides
a buffer to absorb the impact of dealing with unforeseen issues or
complexities in completing the task or stage.
 Assess the uncertainty of the estimate and the level of risk.
 Assess the length of time between when the estimate is produced
and when the estimated task or stage is likely to be executed.
For example, if there are four sequential stages to a project, then
there is more uncertainty about the last stage than the first and
hence the contingency for the last stage should be greater.
 Apply an increase to the estimate as a contingency in line with the
uncertainty, risk and the length of time to execution. Apply the
contingency as a percentage of the estimate, 10% is often used
as an average.
20
Recommended estimating principles
 Always obtain at least two estimates.
 Involve the people who will be doing the work (or with the skills to do
the work if resources have not yet been allocated) in the estimating
process and the people who require the work done where possible.
 Use more than one estimating method.
 Each estimate must be independently derived.
 Review the estimates and rationalise the differences.
 Document assumptions made
 Add contingency based on the level of uncertainty and risk.
 Get agreement and commitment from the project team for their task
estimates and also from the project sponsor for the overall project
estimate.
 Review and refine the estimates as the project proceeds
based on progress.
21
Estimates need to be reviewed to check they are realistic.
Using more than one method of estimating and/or two or
more independent estimators to produce estimates, then
comparing these provides a very effective verification of
the estimates.
For example, phase ratios is a useful technique for
checking estimates derived by other means.
As tasks progress, regularly obtain updated estimates of
effort, and time to complete the tasks from the resources
performing the tasks. These are called “revised
estimates” and should be used to keep project
schedules continually up to date.
Verification of estimates

More Related Content

What's hot

Introduction to MS project
Introduction to MS projectIntroduction to MS project
Introduction to MS project
Samir Paralikar
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentationNithin Dev
 
Integrated Project Management
Integrated Project ManagementIntegrated Project Management
Integrated Project Management
Inam Khosa
 
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptx
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptxCONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptx
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptx
surekha1287
 
Lecture 8 monitoring & controlling (1)
Lecture 8  monitoring & controlling (1)Lecture 8  monitoring & controlling (1)
Lecture 8 monitoring & controlling (1)Nur Azwin
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling
akashpadole
 
Project planning and Scheduling
Project planning and SchedulingProject planning and Scheduling
Project planning and Schedulingsaurabmi2
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
Soe Naing Win
 
6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing
DavidMcLachlan1
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
Saqib Raza
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
Imran Jamil
 
Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management
A Makwana
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project managementRahul Dubey
 
Key Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionKey Components of Cost Estimation in construction
Key Components of Cost Estimation in construction
Waleed Liaqat
 
RESOURCE LEVELLING (MS PROJECT)
RESOURCE LEVELLING (MS PROJECT)RESOURCE LEVELLING (MS PROJECT)
RESOURCE LEVELLING (MS PROJECT)
Mayur Rahangdale
 
07. Project Integration Management
07. Project Integration Management07. Project Integration Management
07. Project Integration Management
BhuWan Khadka
 
Project Scope Management -
Project Scope Management - Project Scope Management -
Project Scope Management -
dyaksa hanindito
 
Project Resource Management - PMBOK6
Project Resource Management - PMBOK6Project Resource Management - PMBOK6
Project Resource Management - PMBOK6
Agus Suhanto
 
Project stakeholders
Project stakeholdersProject stakeholders

What's hot (20)

Introduction to MS project
Introduction to MS projectIntroduction to MS project
Introduction to MS project
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentation
 
Integrated Project Management
Integrated Project ManagementIntegrated Project Management
Integrated Project Management
 
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptx
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptxCONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptx
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptx
 
Lecture 8 monitoring & controlling (1)
Lecture 8  monitoring & controlling (1)Lecture 8  monitoring & controlling (1)
Lecture 8 monitoring & controlling (1)
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling
 
ppt for primevera
ppt for primeverappt for primevera
ppt for primevera
 
Project planning and Scheduling
Project planning and SchedulingProject planning and Scheduling
Project planning and Scheduling
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
 
6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
 
Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 
Key Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionKey Components of Cost Estimation in construction
Key Components of Cost Estimation in construction
 
RESOURCE LEVELLING (MS PROJECT)
RESOURCE LEVELLING (MS PROJECT)RESOURCE LEVELLING (MS PROJECT)
RESOURCE LEVELLING (MS PROJECT)
 
07. Project Integration Management
07. Project Integration Management07. Project Integration Management
07. Project Integration Management
 
Project Scope Management -
Project Scope Management - Project Scope Management -
Project Scope Management -
 
Project Resource Management - PMBOK6
Project Resource Management - PMBOK6Project Resource Management - PMBOK6
Project Resource Management - PMBOK6
 
Project stakeholders
Project stakeholdersProject stakeholders
Project stakeholders
 

Similar to PM Estimation techniques

Project selection and estimating technique spencer o’briencpmgt303
Project selection and estimating technique spencer o’briencpmgt303Project selection and estimating technique spencer o’briencpmgt303
Project selection and estimating technique spencer o’briencpmgt303
MARK547399
 
Estimation guidelines and templates
Estimation guidelines and templatesEstimation guidelines and templates
Estimation guidelines and templates
Hoa PN Thaycacac
 
Project Duration Estimation
Project Duration EstimationProject Duration Estimation
Project Duration Estimation
Harsh Behl
 
Term paper spm
Term paper spmTerm paper spm
Term paper spm
UDAY SHARMA
 
Baseline Compliance Analysis
Baseline Compliance AnalysisBaseline Compliance Analysis
Baseline Compliance Analysis
Acumen
 
Preparing cost estimation
Preparing cost estimationPreparing cost estimation
Preparing cost estimation
Somashekar S.M
 
Project Analysis and Methods of project evaluation
Project Analysis and Methods of project evaluationProject Analysis and Methods of project evaluation
Project Analysis and Methods of project evaluation
Yousuf Razzaq
 
Cost management
Cost managementCost management
Cost managementshkadry
 
Project Estimation Project Estimation Project Estimation
Project Estimation Project Estimation Project EstimationProject Estimation Project Estimation Project Estimation
Project Estimation Project Estimation Project Estimation
VandalRay
 
Project Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & TricksProject Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & Tricks
SHAZEBALIKHAN1
 
Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?
Acumen
 
Top Pillars | Cost & Time Management by Salameh Mahasneh
Top Pillars | Cost & Time Management by Salameh MahasnehTop Pillars | Cost & Time Management by Salameh Mahasneh
Top Pillars | Cost & Time Management by Salameh Mahasneh
Top Pillars
 
WHAT IS COST ESTIMATION IN PROJECT MANAGEMENT AND THEIR TYPES?
 WHAT IS COST ESTIMATION IN PROJECT MANAGEMENT AND THEIR TYPES? WHAT IS COST ESTIMATION IN PROJECT MANAGEMENT AND THEIR TYPES?
WHAT IS COST ESTIMATION IN PROJECT MANAGEMENT AND THEIR TYPES?
MirzaNuman1
 
Software Test Estimation
Software Test EstimationSoftware Test Estimation
Software Test Estimation
Jatin Kochhar
 
Chap 5 Estimating Project Times
Chap 5 Estimating Project TimesChap 5 Estimating Project Times
Chap 5 Estimating Project Times
project management
 
abate and h.pptx
abate and h.pptxabate and h.pptx
abate and h.pptx
BetshaTizazu1
 
Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)
Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)
Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)
danieljohn810
 
4. project cost management
4. project cost management4. project cost management
4. project cost management
Mohamed Salah Eldien Mohamed Ali
 

Similar to PM Estimation techniques (20)

Project selection and estimating technique spencer o’briencpmgt303
Project selection and estimating technique spencer o’briencpmgt303Project selection and estimating technique spencer o’briencpmgt303
Project selection and estimating technique spencer o’briencpmgt303
 
Estimation guidelines and templates
Estimation guidelines and templatesEstimation guidelines and templates
Estimation guidelines and templates
 
Project Duration Estimation
Project Duration EstimationProject Duration Estimation
Project Duration Estimation
 
Term paper spm
Term paper spmTerm paper spm
Term paper spm
 
Baseline Compliance Analysis
Baseline Compliance AnalysisBaseline Compliance Analysis
Baseline Compliance Analysis
 
Preparing cost estimation
Preparing cost estimationPreparing cost estimation
Preparing cost estimation
 
Project Analysis and Methods of project evaluation
Project Analysis and Methods of project evaluationProject Analysis and Methods of project evaluation
Project Analysis and Methods of project evaluation
 
Cost management
Cost managementCost management
Cost management
 
Project mgt
Project mgtProject mgt
Project mgt
 
Project Estimation Project Estimation Project Estimation
Project Estimation Project Estimation Project EstimationProject Estimation Project Estimation Project Estimation
Project Estimation Project Estimation Project Estimation
 
Project Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & TricksProject Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & Tricks
 
Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?
 
Top Pillars | Cost & Time Management by Salameh Mahasneh
Top Pillars | Cost & Time Management by Salameh MahasnehTop Pillars | Cost & Time Management by Salameh Mahasneh
Top Pillars | Cost & Time Management by Salameh Mahasneh
 
Chap005
Chap005Chap005
Chap005
 
WHAT IS COST ESTIMATION IN PROJECT MANAGEMENT AND THEIR TYPES?
 WHAT IS COST ESTIMATION IN PROJECT MANAGEMENT AND THEIR TYPES? WHAT IS COST ESTIMATION IN PROJECT MANAGEMENT AND THEIR TYPES?
WHAT IS COST ESTIMATION IN PROJECT MANAGEMENT AND THEIR TYPES?
 
Software Test Estimation
Software Test EstimationSoftware Test Estimation
Software Test Estimation
 
Chap 5 Estimating Project Times
Chap 5 Estimating Project TimesChap 5 Estimating Project Times
Chap 5 Estimating Project Times
 
abate and h.pptx
abate and h.pptxabate and h.pptx
abate and h.pptx
 
Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)
Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)
Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)
 
4. project cost management
4. project cost management4. project cost management
4. project cost management
 

Recently uploaded

How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
Celine George
 
The geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideasThe geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideas
GeoBlogs
 
PART A. Introduction to Costumer Service
PART A. Introduction to Costumer ServicePART A. Introduction to Costumer Service
PART A. Introduction to Costumer Service
PedroFerreira53928
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
Atul Kumar Singh
 
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCECLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
BhavyaRajput3
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
Tamralipta Mahavidyalaya
 
Overview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with MechanismOverview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with Mechanism
DeeptiGupta154
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
JosvitaDsouza2
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
siemaillard
 
Introduction to Quality Improvement Essentials
Introduction to Quality Improvement EssentialsIntroduction to Quality Improvement Essentials
Introduction to Quality Improvement Essentials
Excellence Foundation for South Sudan
 
Thesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.pptThesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.ppt
EverAndrsGuerraGuerr
 
How to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS ModuleHow to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS Module
Celine George
 
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptxMARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
bennyroshan06
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
Vivekanand Anglo Vedic Academy
 
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXXPhrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
MIRIAMSALINAS13
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
Jisc
 
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptxStudents, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
EduSkills OECD
 
The Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdfThe Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdf
kaushalkr1407
 
special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
Special education needs
 
Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)
rosedainty
 

Recently uploaded (20)

How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
 
The geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideasThe geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideas
 
PART A. Introduction to Costumer Service
PART A. Introduction to Costumer ServicePART A. Introduction to Costumer Service
PART A. Introduction to Costumer Service
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
 
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCECLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
 
Overview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with MechanismOverview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with Mechanism
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
 
Introduction to Quality Improvement Essentials
Introduction to Quality Improvement EssentialsIntroduction to Quality Improvement Essentials
Introduction to Quality Improvement Essentials
 
Thesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.pptThesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.ppt
 
How to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS ModuleHow to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS Module
 
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptxMARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
 
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXXPhrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
 
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptxStudents, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
 
The Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdfThe Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdf
 
special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
 
Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)
 

PM Estimation techniques

  • 1. 1 Definition of estimating ‘To form an approximate notion of the amount, number, magnitude or position of anything, without actual enumeration or measurement.’
  • 2. 2 What estimates are made in projects 1. Time estimates are used in scheduling work, assigning resources and determining delivery dates. 2. Cost estimates are used for budgeting. 3. Cost and benefit estimates are used in cost/benefit analysis to determine the overall viability of a project.
  • 3. 3 Importance of accurate estimates 1. Inaccurate time estimates can result in inefficient use of resources and late delivery. 2. Inaccurate cost estimates can result in insufficient budget being allocated, or excess budget being set aside for the project when it could be used for other projects. 3. If the cost or benefits estimates are inaccurate this can lead to incorrect decisions about proceeding with the project being made.
  • 4. When estimates are required Project phase Estimates required Initiation Time, cost and benefit estimates in project definition. Planning Time estimates in project schedule. Cost estimates in project budget. Cost and benefit estimates in business case. Start of project stages Time and cost estimates reconfirmed for the stage.
  • 5. 5 Effort and duration  Effort is the amount of work required to complete a task – used to estimate cost of resources.  Duration is the time that elapses between the start and end of the task – used to estimate timeframe. In estimating it is essential to know whether the estimate is an effort or duration based estimate. For example, the estimate for painting a room may be 10 hours for two people (20 hours effort), over 3 days (duration) allowing for other tasks and for the drying time of the paint.
  • 6. 6 Accuracy Information Available (%) 0 100 50 Estimating accuracy 50 100 Estimating accuracy increases during the life of the project as more knowledge is gained about the project.
  • 7. 7 Types of estimates 1. Order of magnitude: obtained in the initiation phase of a project for the whole project 2. 2. Budget estimate: an estimate derived during the planning phase for the whole project 3. Definitive estimate: an estimate derived at the start of each project stage Different types of estimates reflect the range of accuracy expected from the estimate. Three types of project estimates* are:
  • 8. 8 Estimating methods 1. Top down estimating 2. Bottom up estimating 3. Parametric estimating Three commonly used methods of estimating are:
  • 9. 9 Top-down method The top-down method is also known as the analogous method. It is used to determine order of magnitude estimates in the initiation phase of the project. The method uses the actual durations, effort or costs from previous projects as a basis for estimating the effort or costs for the current project. 1. Identify a previous project or section of a previous project that is similar to the current project. 2. Assess the extent to which the current project is similar to the previous project 3. Compute the estimate for the current project based on the actual durations, effort or costs from the previous project and the comparison factor.
  • 10. 10 Bottom-up method The bottom-up method is considered to be the most accurate method for generating project estimates. It is used to determine budget or definitive estimates during the planning phase and at the start of each project stage. The method uses the Work Breakdown Structure (WBS) developed during the planning stage of the project. Estimates are created for all tasks at the lowest level of the WBS and then these are accumulated to determine the estimates for the whole project. The consensus technique* is usually used to obtain task estimates for the low level tasks on the WBS it also builds active involvement, cooperation and commitment. Experts with the skills required to perform the work should be included in the estimating process. One disadvantage of the bottom-up method is that it is much more time-consuming than other methods.
  • 11. 11 Parametric method The parametric method is also known as the object based method. It is used to obtain definitive estimates and to confirm bottom up estimates where possible. A simple concept is used, namely: If the amount of effort needed to carry out a particular activity for a particular object is known, and the number of objects is known, the effort required to perform the activity for all the objects can be determined. The amount of effort for the single activity can be determined either from a standard, which has been established from previous experience, or by executing a sample activity if no standard exists.
  • 12. 12 1. Identify an item to be estimated. 2. Estimate the number of items. 3. Estimate the effort per item. 4. Multiply effort per item by number of items to determine the total effort. Parametric method (Cont.) For example, if the assembly of one library shelving stack takes an hour and a half and there are 40 stacks to assemble then the total effort is 60 hours. Steps in deriving the estimate:
  • 13. 13 Estimating techniques 1. Weighted average estimating 2. Consensus estimating 3. Phase ratios Three commonly used techniques for obtaining estimates are:
  • 14. 14 Weighted average estimates Estimated effort = (O + 4M + P ) / 6 Weighted average estimating is also known as sensitivity analysis estimating. With this technique three estimates are obtained for each item rather than one. This provides a more accurate estimate than when only one estimate value is provided. The three estimates are known as the best case (O = Optimistic), worst case (P = Pessimistic) and most likely (M = Median). These are then used in the following formula to determine the estimated effort:
  • 15. 15 Consensus estimating  A briefing is provided to the estimating team on the project.  Each person is provided with a list of work components to estimate.  Each person independently estimates O, M and P for each work component.  The estimates are written up on the whiteboard.  Each person discusses the basis and assumptions for their estimates.  A revised set of estimates is produced.  Averages for the O, M and P values are calculated.  These averages are then used in the weighted averages formula to calculate the estimated effort. Steps in conducting a consensus estimating session:
  • 16. 16 Phase ratios Project phase ratios provide a means of generating a top-down order of magnitude duration estimate for a project, or they can be used as a sense check of bottom-up duration estimates of the time allocated to each project phase. Phase ratio estimating uses an estimate for one phase of a project to derive the likely size of the other phases, and hence an overall estimate for the project. For example, if analysis takes 5 weeks, and this represents 10% of the project, then the project is likely to take 50 weeks. The concept behind this method is that similar types of projects would normally spend the same percentage of time in each phase. Phase ratios are not accurate enough to be used as a budget or definitive estimates.
  • 17. 17 Phase ratio percentages Initiation 5% Planning 20% Analysis 10% Design 10% Construction 20% Testing 20% Implementation 10% Closure 5% Phase Ratio The phase ratio technique is based on studies that average the proportion of time that a large sample of projects has spent on standard project phases. An initial set of project phase ratios is provided below. These should be refined based on results from completed projects.
  • 18. 18 Estimating assumptions An estimate is a qualified guess. Every estimate is based on assumptions. An estimate assumption is a statement which has been considered to be true in deriving the estimate. These estimate assumptions need to be specified so that the basis of the estimate is known and validity of the assumptions can be assessed. For example, a work effort estimate is usually based on a level of skill and expertise. If a lower level of skill and expertise is utilised then it is likely that the task will require more effort.
  • 19. 19 Applying contingency to estimates  Can be applied to each project stage or to each task. It provides a buffer to absorb the impact of dealing with unforeseen issues or complexities in completing the task or stage.  Assess the uncertainty of the estimate and the level of risk.  Assess the length of time between when the estimate is produced and when the estimated task or stage is likely to be executed. For example, if there are four sequential stages to a project, then there is more uncertainty about the last stage than the first and hence the contingency for the last stage should be greater.  Apply an increase to the estimate as a contingency in line with the uncertainty, risk and the length of time to execution. Apply the contingency as a percentage of the estimate, 10% is often used as an average.
  • 20. 20 Recommended estimating principles  Always obtain at least two estimates.  Involve the people who will be doing the work (or with the skills to do the work if resources have not yet been allocated) in the estimating process and the people who require the work done where possible.  Use more than one estimating method.  Each estimate must be independently derived.  Review the estimates and rationalise the differences.  Document assumptions made  Add contingency based on the level of uncertainty and risk.  Get agreement and commitment from the project team for their task estimates and also from the project sponsor for the overall project estimate.  Review and refine the estimates as the project proceeds based on progress.
  • 21. 21 Estimates need to be reviewed to check they are realistic. Using more than one method of estimating and/or two or more independent estimators to produce estimates, then comparing these provides a very effective verification of the estimates. For example, phase ratios is a useful technique for checking estimates derived by other means. As tasks progress, regularly obtain updated estimates of effort, and time to complete the tasks from the resources performing the tasks. These are called “revised estimates” and should be used to keep project schedules continually up to date. Verification of estimates