SlideShare a Scribd company logo
1 of 36
Kick Starting a PPP project
Presentation by :
Mrs. Audrey Mwala
Director of Project Finance & Risk Analysis
The Public Private Partnership Commission,
Malawi1
Session 3- Outline
•PPP Project life Cycle:
•Egypt
•Mauritius
•Kenya
•Knowledge, skill, attitudes for PPP delivery
•The readiness of state institutions
•Reorienting the public sector
•Working with the private sector
•Initiation and planning of PPP programme
•Importance of legal, Institutional, financial, fiducially
framework for capacity building
•Project Finance and financial Modeling
•Risk Management
2/26/2016 2
Presented by: Mrs Audrey Mwala, Director
Project Finance and Risk Analysis, The
PPPC, Malawi
What it is a PPP project Life
Cycle
• Logical sequence of activities to achieve project’s objectives.
• All projects go through a series of stages.
• Lifecycles differ across:
– countries,
– sectors and
– by the chosen implementation method
• A life cycle is used to:
– Control progress through a project;
– Provides review points
– Project’s likelihood of success is validated
– Decision to move to the next phase made.
2/26/2016 3
Presented by: Mrs Audrey Mwala, Director
Project Finance and Risk Analysis, The
PPPC, Malawi
Key Life Cycle Stages
1. Project Identification
1.1 Project selection and
definition
 Identification
 Output specifications
1.2 Assessment of the PPP
option
 Affordability
 Risk allocation
 Bankability
 Value for money
2. Detailed Preparation 2.1 Getting organised  Project team
 Advisory team
 Plan and timetable
2.2 Before launching the tender  Further studies
 Detailed PPP design
 Procurement method
 Bid evaluation criteria
 Draft PPP contract
3. Procurement 3.1 Bidding process  Notice and
prequalification
 Invitation to tender
 Interaction with bidders
 Contract award
3.2 PPP contract and financial
close
 Final PPP contract
 Financing agreements
 Financial close
4. Project Implementation 4.1 Contract management  Management
responsibilities
 Monitoring service
outputs
 Changes to the PPP
contract
 Dispute resolution
 PPP contract
termination
4.2 Ex post evaluation 4.2 Ex post evaluation  Institutional framework
 Analytical framework
2/26/2016 4
Presented by: Mrs Audrey Mwala, Director
Project Finance and Risk Analysis, The
PPPC, Malawi
Mauritius
• PPP Act of November 2004.
• Amended in June 2008 to:
– provided set up of a PPP Committee and
– provided for unsolicited bids
2/26/2016 5
Presented by: Mrs Audrey Mwala, Director
Project Finance and Risk Analysis, The
PPPC, Malawi
Key Institutions/ Parties
• Contracting Authority-
– Identify, appraise, develop and
monitor a projects
– Carry out feasibility studies
– Submit results to the PPP
Committee
– Prepares RFP on the approval of
the study
• Central Procurement Board
– Examine and evaluate bids
– Recommend to CA to negotiate
with preferred bidder
– Approve the award of the project
A PPP Unit
•Set up in July 2002
•Drafted the legislation
•Produced PPP guidelines Manual
•Reports to the PPP Committee
•Works with CAs to select PPP projects
•Deals with matters referred by PPP Committee
•Source of PPP information
•Develop PPP awareness.
PPP Committee
•Assessments projects, recommends to CA
•Develop PPP best practice guidelines
•Formulate PPP policy in relation
2/26/2016 6
Presented by: Mrs Audrey Mwala, Director
Project Finance and Risk Analysis, The
PPPC, Malawi
PPP Cycle – Govt. initiated PPPs
Feasibility Study-
• To assess if a project may be implemented under PPP.
• The feasibility study must demonstrate:
• comparative advantage for implementation under a PPP
– Affordability, VFM, Risk transfer
• Show contracting authority’s capacity to effectively:
– enforce agreement, Monitor implementation and performance
• The extent to which functions can lawfully and effectively be
performed by a private party
• The most appropriate form of PPP
2/26/2016 7
Presented by: Mrs Audrey Mwala, Director
Project Finance and Risk Analysis, The
PPPC, Malawi
Procurement
Pre-selection
• The CA obtains approval of CPB conduct pre-selection.
• The pre-selection documents are approved by CPB.
Request for Proposal
• The CA submits the RFP to the CPB for approval.
Evaluation and award of bids
• The CPB is responsible for the evaluation of bids -but
may set up an evaluation committee.
• The award of the contract is approved by the CPB.
2/26/2016 8
Presented by: Mrs Audrey Mwala, Director
Project Finance and Risk Analysis, The
PPPC, Malawi
Procurement unsolicited Proposal
• Private party submits project concept & feasibility study cost
to CA.
• CA examines project in line with sector strategies &
investment programme and if its suitable for PPP.
• CA submits it to the PPP Committee within 15 days.
• The PPP Committee may approve or reject the project
concept.
• If the CA within 5 working days requests the proponent to
submit:
– details of technical, commercial, managerial and financial
capabilities;
– a feasibility study
– the nature of information which is proprietary.
• No price proposal at this stage.
2/26/2016 9
Presented by: Mrs Audrey Mwala, Director
Project Finance and Risk Analysis, The
PPPC, Malawi
Unsolicited bid’s Cont1’
• The PPP Committee assesses the feasibility study and evaluates
the technical proposal.
– (a) If its accepted, the PPP Committee requests CA to proceed with an
Invitation to bid.
– (b) If its rejected, the process ends. No compensation for feasibility
study costs.
• CA prepares RFP based on information in the technical proposal.
• The RFP is approved by the CPB before bids are invited.
• The proponent is requested to submit only a financial proposal.
• The other bidders submit both technical and financial proposals.
2/26/2016 10
Presented by: Mrs Audrey Mwala, Director
Project Finance and Risk Analysis, The
PPPC, Malawi
Unsolicited bid’s Cont2’
• The RFP indicates that:
• (a)the project has emanated from a proponent whose
technical proposal was accepted
• (b)the proponent will be awarded the project if their
price is within 10 % of the price of the preferred bidder;
and
• (c) If the original proponent is not successful, the CA
will compensate the cost of the feasibility study which
will be claimed from the successful bidder.
• The CPB evaluates the bids gives and approval of the
successful bidder.
2/26/2016 11
Presented by: Mrs Audrey Mwala, Director
Project Finance and Risk Analysis, The
PPPC, Malawi
Egypt
• PPP Law (Law 67/2010), Partnership with Private
Sector for Infrastructure Projects & Public Utilities
• Regulations 2011
• Policy
2/26/2016 12
Presented by: Mrs Audrey Mwala, Director
Project Finance and Risk Analysis, The
PPPC, Malawi
Key Institutions
• Line Ministry
– (CA)- identifies projects
• Minister of Finance
• Satellite Units in Line
Ministries (Nodal Agencies)
2/26/2016 13
Presented by: Mrs Audrey Mwala, Director
Project Finance and Risk Analysis, The
PPPC, Malawi
A PPP Central Unit
•Promote the national PPP initiative
• Facilitate solutions to legal and institutional obstacles for PPPs
•Develop PPP best practices, models
•Validate and develop PPP proposals
•Shepherd pilot procurements of PPPs
•Build capacity in the Public sector
•Assist in selection of advisors, Investors
PPP Supreme Committee
•Approve projects
•Appoints advisors
•Prepare Contract Award
Requirements
The Cycle
– Line Ministry Submits Project Proposal to
– PPP Central Unit for Screening/ modification
– PPP Central Unit submits to
– PPP Ministerial Committee for Approval
2/26/2016 14
Presented by: Mrs Audrey Mwala, Director
Project Finance and Risk Analysis, The
PPPC, Malawi
Project
Preparation
Approval by
Supreme
Committee
Tendering
Implementation
& Post Contract
Monitoring
Project initiation
Competitive
Dialogue
–with the qualified
bidders
–with each bidder
separately
– to obtain explanations for
the contents of the
technical and financial
elements
– basis of equality amongst
the qualified Investors
2/26/2016 15
Presented by: Mrs Audrey Mwala, Director
Project Finance and Risk Analysis, The
PPPC, Malawi
Challenge of
disqualification
•Disqualified Investors
can object to the
Prequalification
Committee’s decision.
•An objection shall be
submitted to the PPP
Central Unit to study and
issue its binding decision.
Approval of draft
contracts
– Line Ministry has the
right to :
• approve third part
contracts to be entered
by the Project company
for the delivery of the
project works & services
• Object such
appointments
2/26/2016 16
Presented by: Mrs Audrey Mwala, Director
Project Finance and Risk Analysis, The
PPPC, Malawi
Challenge of
disqualification
•Disqualified Investors
can object to the
Prequalification
Committee’s decision.
•An objection shall be
submitted to the PPP
Central Unit to study and
issue its binding decision.
Kenya
“A center of
PPP Expertise”
• PPP Policy November 2011
• PPP Act 2012
• A Project Facilitation Fund to provide an avenue for
government support to PPP projects.
2/26/2016 17
Presented by: Mrs Audrey Mwala, Director
Project Finance and Risk Analysis, The
PPPC, Malawi
Project Implementation Structures
• PPP Nodes
– responsible for the development
and management of PPP projects;
• The PPP Unit
– domiciled at the State
Department responsible for
Finance,
– a national centre for PPP
expertise;
– develop and distribute PPP
Operating Guidelines and Manuals
2/26/2016 18
Presented by: Mrs Audrey Mwala, Director
Project Finance and Risk Analysis, The
PPPC, Malawi
•PPP Committee -
responsible for
developing and
implementing PPP
policy initiatives;
•Cabinet-Final
approval but delegate
to PPP Committee
The Cycle
• Project Identification, Selection and Prioritization
technical profile, operations, service delivery targets,
and future income and costs (Scooping)
• Project Preparation and Appraisal: a full investment
appraisal
• Project Tendering
• Project Negotiation
• Project Monitoring and evaluation- The CA to establish
clear procedures for monitoring. The PPP Unit and the
PPP Committee has an oversight role
2/26/2016 19
Presented by: Mrs Audrey Mwala, Director
Project Finance and Risk Analysis, The
PPPC, Malawi
Competitive dialogue
• A contracting authority may, hold a competitive
dialogue with each bidder to define technical or
financial aspects of the project
• may require a bidder to submit to the authority a
technical and financial non-binding proposal for
discussion
• held with each bidder on the basis of equality and
transparency.
2/26/2016
Presented by: Mrs Audrey Mwala, Director
Project Finance and Risk Analysis, The
PPPC, Malawi
20
Privately Initiated Investment
Proposals
• Limited to projects that demonstrate:
– genuine innovation and/or
– use of proprietary technology,
– economic viability and
– satisfy the principles of public interest
2/26/2016 21
Presented by: Mrs Audrey Mwala, Director
Project Finance and Risk Analysis, The
PPPC, Malawi
Privately Initiated Investment
Proposals
• A contracting authority, before negotiations:
– prescribes a criteria against which the outcome of
negotiations shall be evaluated;
– submits the proposal to the PPP unit for consideration
and recommendation
– apply for approval from the Committee to negotiate the
contract
– conduct the negotiations and award the tender
• Key issues: VFM, Affordability, Risk transfer
2/26/2016 22
Presented by: Mrs Audrey Mwala, Director
Project Finance and Risk Analysis, The
PPPC, Malawi
Knowledge skills & Altitudes for PPP
project delivery
• Project Development skills-
– Privately financed infrastructure project structuring skills
– Go to Market with a Solid Transaction Structure
• Economic and financial appraisal skills
– Evaluating traditional vs. PPP
• Communication skills: with general public
• Procurement/ evaluation
– Sensitivity to the objectives, political environment, public
• Technical skills- understand the technical details
2/26/2016 23
Presented by: Mrs Audrey Mwala, Director
Project Finance and Risk Analysis, The
PPPC, Malawi
Knowledge skills & Altitudes for PPP
project delivery
• Negotiations -to finalise agreements
• Contract management skills
– Reporting- on matter of general policy and projects
– Dispute resolution
• PPP transaction/ process management skills
– Approvals, what stages, whom.
• Monitoring -Implementation and compliance
• Legal & regulatory skills
• Experience in dealing with the private sector
• Market sounding: check with lenders to understand
their perspectives of their own market challenges
2/26/2016 24
Presented by: Mrs Audrey Mwala, Director
Project Finance and Risk Analysis, The
PPPC, Malawi
Monitoring skill…
• Monitor, transparency and accountability of PPP
unit work / State Authority / PPP partner
– Audit of PPP procurement processes
– Audit of PPP project performance – independent
reviews, Director of Audit
• Effectiveness / performance audit
– to see if projections regarding PPP procurement against
traditional procurement were realised
2/26/2016 25
Presented by: Mrs Audrey Mwala, Director
Project Finance and Risk Analysis, The
PPPC, Malawi
The state of readiness of
state Institutions
• Establish PPP policy and Legal frame work
– Need for clear mandate for state institutions
– Draft PPP contract
• Strong National Political Backing
– Clear Public Sector Commitment
• A realist pipeline of bankable projects
– Sound understanding of the needs of a particular sector
– be Bankable for Private Sector financing i.e. large, attractive size
• Establish clear ownership ( risks resistance by CAs)
• Adequate capacity for the PPP unit and the Nodal agencies
– To carry out rigorous project feasibility
– Risk-allocation structure must be clear
2/26/2016 26
Presented by: Mrs Audrey Mwala, Director
Project Finance and Risk Analysis, The
PPPC, Malawi
The state of readiness of
state Institutions
• Access to local and international financing
institutions
• Affordability by Govt.
– Creditworthiness to make unitary payments
• Project development fund ( revolving fund)
• Viability Gap fund
• Communication with stakeholders
• Professional and effective monitoring of the
private party
• Proper advisory support
2/26/2016 27
Presented by: Mrs Audrey Mwala, Director
Project Finance and Risk Analysis, The
PPPC, Malawi
Reorienting the Public sector
• Capacity Building, PPP training
• Targeted seminars
• Role of advisors
• Political will
• Political Champion
• Public awareness
• Low hanging fruits
2/26/2016 28
Presented by: Mrs Audrey Mwala, Director
Project Finance and Risk Analysis, The
PPPC, Malawi
Working with the private
sector
• Project preparation- project scooping
• Procurement
– Technical specifications
– VFM
– evaluation
• Negotiation
• Implementation/ construction phase
– Reporting
– Technical issues/ standards
- Payments
- Post implementation monitoring
• Contract Compliance
– Legal
• Streamline process - speed
2/26/2016 29
Presented by: Mrs Audrey Mwala, Director
Project Finance and Risk Analysis, The
PPPC, Malawi
PPP Programme initiation
and Planning
• Legal framework (Law and Policy)
• PPP guidelines
• Institutional framework
• PPP sector nodes
• Personnel Capacity;
• PPP expertise, legal, finance, economic, ‘sector specialists”
• PPP advisors
• Institutional roles & approvals
• Financial resources for:
– administration,
– project development &
– monitoring
2/26/2016 30
Presented by: Mrs Audrey Mwala, Director
Project Finance and Risk Analysis, The
PPPC, Malawi
PPP Project preparation
• Project pipeline Selection
– Potential candidates for further analyze
– Not too small, clear private sector interest
– conceptual stage
– limited information
– Project Desirability (public interest)
• APPRAISAL -structured, prepared, Ranking & Concept Paper
– Project Achievability/ deliverable output
– Project Ability (Policy and Program): Is the it a priority
– Project Viability (Financing)
– investment size and useful life
– Sequencing- low hanging fruits first
• APPROVAL
– final approval to proceed to implementation i.e. Developing a Business
Case
2/26/2016 31
Presented by: Mrs Audrey Mwala, Director
Project Finance and Risk Analysis, The
PPPC, Malawi
PPP unit
• Many countries with a successful
PPP programme have created a
dedicated PPP unit.
• Roles of PPP Units include:
– Regulating the PPP process
– Promoting PPPs within Govt.
– Helping agencies to implement PPPs
– Providing channels to investors
– Help in monitoring
2/26/2016 32
Presented by: Mrs Audrey Mwala, Director
Project Finance and Risk Analysis, The
PPPC, Malawi
Business case Development
• Assess if the project:
• Meets government’s policy sector objectives
• Is ‘feasible’: technically, financially, economically,
environmentally,
• Is ‘deliverable’- output standards;
• Is ‘affordable’ to the public authority
• Is ‘bankable’ to the private investors & lenders
• Management & Contract enforcement capability.
2/26/2016 33
Presented by: Mrs Audrey Mwala, Director
Project Finance and Risk Analysis, The
PPPC, Malawi
Plan
• for:
• Procurement
• Implementation
• Post construction
• Contract expiration
2/26/2016 34
Presented by: Mrs Audrey Mwala, Director
Project Finance and Risk Analysis, The
PPPC, Malawi
Success factors
• Stable macro economic environment
• Willingness of the Public Client to accept innovative solutions
• A detailed contract
• Professional and effective monitoring of the private contractor
• Selection of appropriate project candidates
• Good detailed preparation:
– Clear business cases,
– clear output specifications,
– A PPP project procurement team
• Proper advisory support
• A well structured, transparent, competitive PPP procurement process.
• A clear and consistent methodology for evaluating FVM
• Proper monitoring of the entire operational phase.
• A determination by all parties and stakeholders to make the PPP work
• Management of contingent liabilities
2/26/2016 35
Presented by: Mrs Audrey Mwala, Director
Project Finance and Risk Analysis, The
PPPC, Malawi
Importance of legal, institution;
fiduciary, financial framework in
Capacity building
• legal
– Sets Objectives to build capacity
– Sets Institutions for targeted capacity
building
– Gives legal mandate of the institutions
– Gives investors confidence to predict the
process
– transparent, and competitive procurement
• Institution
– Allows for building of a team of professionals
– Capacity building to include the private
sector to understand PPP framework before
they invest.
2/26/2016 36
Presented by: Mrs Audrey Mwala, Director
Project Finance and Risk Analysis, The
PPPC, Malawi
•Fiduciary
•Reporting provides accountability
excellence
•Approvals provide national will
•Audits provide confidence and due
respect of the process
•Financial
•Allows capacity building to happen
•Public awareness programmes
•Allows project preparation
•Allows PPP payment & investment

More Related Content

What's hot

Introduction to Project Management and Planning.ppt
Introduction to Project Management and Planning.pptIntroduction to Project Management and Planning.ppt
Introduction to Project Management and Planning.pptAyushSrivastava8761
 
Role and Responsibilities of Project Manager
Role and Responsibilities of Project ManagerRole and Responsibilities of Project Manager
Role and Responsibilities of Project Managerkanti choudhary
 
Life cycle cost analysis
Life cycle cost analysisLife cycle cost analysis
Life cycle cost analysisAnkur Bansal
 
Quantity surveyor
Quantity surveyorQuantity surveyor
Quantity surveyorSyafiq Deen
 
6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource SmoothingDavidMcLachlan1
 
Addressing the challenges of delivering Mega Projects
Addressing the challenges of delivering Mega ProjectsAddressing the challenges of delivering Mega Projects
Addressing the challenges of delivering Mega ProjectsIbrahim Al-Hudhaif
 
5 principles of construction project management
5 principles of construction project management5 principles of construction project management
5 principles of construction project managementreachfirst01
 
Financial management of construction contracts
Financial management of construction contractsFinancial management of construction contracts
Financial management of construction contractsidnobleg77
 
Construction project risk management
Construction project risk managementConstruction project risk management
Construction project risk managementIQPC
 
OWNERSHIP COST OF CONSTRUCTION PLANT & EQUIPMENT
OWNERSHIP COST OF CONSTRUCTION PLANT & EQUIPMENTOWNERSHIP COST OF CONSTRUCTION PLANT & EQUIPMENT
OWNERSHIP COST OF CONSTRUCTION PLANT & EQUIPMENTConstruction Mechanizer
 
Key Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionKey Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionWaleed Liaqat
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contractssrinivas2036
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniquesShivangi Saini
 
Project formulation and appraisal
Project formulation and appraisalProject formulation and appraisal
Project formulation and appraisalSurya C D
 
Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & ScheduleVîñõđ Kůmåř
 
Public private partnership
Public private partnershipPublic private partnership
Public private partnershipAnkit GAJJAR
 

What's hot (20)

Introduction to Project Management and Planning.ppt
Introduction to Project Management and Planning.pptIntroduction to Project Management and Planning.ppt
Introduction to Project Management and Planning.ppt
 
Role and Responsibilities of Project Manager
Role and Responsibilities of Project ManagerRole and Responsibilities of Project Manager
Role and Responsibilities of Project Manager
 
Life cycle cost analysis
Life cycle cost analysisLife cycle cost analysis
Life cycle cost analysis
 
Quantity surveyor
Quantity surveyorQuantity surveyor
Quantity surveyor
 
Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
 
6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing
 
Addressing the challenges of delivering Mega Projects
Addressing the challenges of delivering Mega ProjectsAddressing the challenges of delivering Mega Projects
Addressing the challenges of delivering Mega Projects
 
5 principles of construction project management
5 principles of construction project management5 principles of construction project management
5 principles of construction project management
 
Financial management of construction contracts
Financial management of construction contractsFinancial management of construction contracts
Financial management of construction contracts
 
Construction project risk management
Construction project risk managementConstruction project risk management
Construction project risk management
 
OWNERSHIP COST OF CONSTRUCTION PLANT & EQUIPMENT
OWNERSHIP COST OF CONSTRUCTION PLANT & EQUIPMENTOWNERSHIP COST OF CONSTRUCTION PLANT & EQUIPMENT
OWNERSHIP COST OF CONSTRUCTION PLANT & EQUIPMENT
 
Key Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionKey Components of Cost Estimation in construction
Key Components of Cost Estimation in construction
 
PPP for Infrastructure Projects
PPP for Infrastructure ProjectsPPP for Infrastructure Projects
PPP for Infrastructure Projects
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
 
Project formulation and appraisal
Project formulation and appraisalProject formulation and appraisal
Project formulation and appraisal
 
Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & Schedule
 
Public private partnership
Public private partnershipPublic private partnership
Public private partnership
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
Project planning and control
Project planning and controlProject planning and control
Project planning and control
 

Viewers also liked

Public Private Partnerships (Ppp) And Affordable Housing By David Hoicka
Public Private Partnerships (Ppp) And Affordable Housing By David HoickaPublic Private Partnerships (Ppp) And Affordable Housing By David Hoicka
Public Private Partnerships (Ppp) And Affordable Housing By David HoickaDavid Hoicka
 
ISMED Training: PPP Fundamentals by Andrew Fitzpatrick, OECD
ISMED Training: PPP Fundamentals by Andrew Fitzpatrick, OECDISMED Training: PPP Fundamentals by Andrew Fitzpatrick, OECD
ISMED Training: PPP Fundamentals by Andrew Fitzpatrick, OECDOECDGlobalRelations
 
Valerie Allison PPP Project
Valerie Allison PPP ProjectValerie Allison PPP Project
Valerie Allison PPP ProjectValerie Allison
 
project-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxproject-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxLisa Cooley, LEED AP
 
Diversifying MENA Affordable Housing Financing & PPP Options - Affordable Hou...
Diversifying MENA Affordable Housing Financing & PPP Options - Affordable Hou...Diversifying MENA Affordable Housing Financing & PPP Options - Affordable Hou...
Diversifying MENA Affordable Housing Financing & PPP Options - Affordable Hou...Loay Ghazaleh MBA, BSc Civil Eng.
 
Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...
Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...
Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...marcus evans Network
 
Project delivery, what good looks like
Project delivery, what good looks likeProject delivery, what good looks like
Project delivery, what good looks likeMatthew Rees
 
Capital Summit 2015 - IFC, partner of Municipalities for a successfull introd...
Capital Summit 2015 - IFC, partner of Municipalities for a successfull introd...Capital Summit 2015 - IFC, partner of Municipalities for a successfull introd...
Capital Summit 2015 - IFC, partner of Municipalities for a successfull introd...NALED Serbia
 
Vilnius street lighting PPP project presentation by peritus 2012.03
Vilnius street lighting PPP project presentation by peritus 2012.03Vilnius street lighting PPP project presentation by peritus 2012.03
Vilnius street lighting PPP project presentation by peritus 2012.03Andrius Šiaudinis
 
Public-Private Partnerships (PPP): Funding Infrastructure for Ghana
Public-Private Partnerships (PPP): Funding Infrastructure for GhanaPublic-Private Partnerships (PPP): Funding Infrastructure for Ghana
Public-Private Partnerships (PPP): Funding Infrastructure for GhanaA Hagan
 
PPPs for Energy Efficient Street Lighting and PPPs for Rooftop Solar Power Ge...
PPPs for Energy Efficient Street Lighting and PPPs for Rooftop Solar Power Ge...PPPs for Energy Efficient Street Lighting and PPPs for Rooftop Solar Power Ge...
PPPs for Energy Efficient Street Lighting and PPPs for Rooftop Solar Power Ge...lacclimatebusinessforum
 
Case studies ppp
Case studies pppCase studies ppp
Case studies pppamityasum23
 
Role of infrastructure in economic development
Role of infrastructure in economic developmentRole of infrastructure in economic development
Role of infrastructure in economic developmentKashif Hussain
 
Basics Of Procurement Process
Basics Of Procurement ProcessBasics Of Procurement Process
Basics Of Procurement ProcessRameswara Vedula
 
Project appraisal and Analysis
Project appraisal and AnalysisProject appraisal and Analysis
Project appraisal and AnalysisSuhail Hussain
 

Viewers also liked (19)

111212 ppp life cycle project delivery.pptx
111212 ppp life cycle project delivery.pptx111212 ppp life cycle project delivery.pptx
111212 ppp life cycle project delivery.pptx
 
Public Private Partnerships (Ppp) And Affordable Housing By David Hoicka
Public Private Partnerships (Ppp) And Affordable Housing By David HoickaPublic Private Partnerships (Ppp) And Affordable Housing By David Hoicka
Public Private Partnerships (Ppp) And Affordable Housing By David Hoicka
 
African ppp doc 1
African ppp   doc 1African ppp   doc 1
African ppp doc 1
 
ISMED Training: PPP Fundamentals by Andrew Fitzpatrick, OECD
ISMED Training: PPP Fundamentals by Andrew Fitzpatrick, OECDISMED Training: PPP Fundamentals by Andrew Fitzpatrick, OECD
ISMED Training: PPP Fundamentals by Andrew Fitzpatrick, OECD
 
Valerie Allison PPP Project
Valerie Allison PPP ProjectValerie Allison PPP Project
Valerie Allison PPP Project
 
project-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxproject-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptx
 
Diversifying MENA Affordable Housing Financing & PPP Options - Affordable Hou...
Diversifying MENA Affordable Housing Financing & PPP Options - Affordable Hou...Diversifying MENA Affordable Housing Financing & PPP Options - Affordable Hou...
Diversifying MENA Affordable Housing Financing & PPP Options - Affordable Hou...
 
Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...
Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...
Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...
 
Project delivery, what good looks like
Project delivery, what good looks likeProject delivery, what good looks like
Project delivery, what good looks like
 
Capital Summit 2015 - IFC, partner of Municipalities for a successfull introd...
Capital Summit 2015 - IFC, partner of Municipalities for a successfull introd...Capital Summit 2015 - IFC, partner of Municipalities for a successfull introd...
Capital Summit 2015 - IFC, partner of Municipalities for a successfull introd...
 
Vilnius street lighting PPP project presentation by peritus 2012.03
Vilnius street lighting PPP project presentation by peritus 2012.03Vilnius street lighting PPP project presentation by peritus 2012.03
Vilnius street lighting PPP project presentation by peritus 2012.03
 
Procurement process
Procurement processProcurement process
Procurement process
 
Public-Private Partnerships (PPP): Funding Infrastructure for Ghana
Public-Private Partnerships (PPP): Funding Infrastructure for GhanaPublic-Private Partnerships (PPP): Funding Infrastructure for Ghana
Public-Private Partnerships (PPP): Funding Infrastructure for Ghana
 
PROCUREMENT
PROCUREMENTPROCUREMENT
PROCUREMENT
 
PPPs for Energy Efficient Street Lighting and PPPs for Rooftop Solar Power Ge...
PPPs for Energy Efficient Street Lighting and PPPs for Rooftop Solar Power Ge...PPPs for Energy Efficient Street Lighting and PPPs for Rooftop Solar Power Ge...
PPPs for Energy Efficient Street Lighting and PPPs for Rooftop Solar Power Ge...
 
Case studies ppp
Case studies pppCase studies ppp
Case studies ppp
 
Role of infrastructure in economic development
Role of infrastructure in economic developmentRole of infrastructure in economic development
Role of infrastructure in economic development
 
Basics Of Procurement Process
Basics Of Procurement ProcessBasics Of Procurement Process
Basics Of Procurement Process
 
Project appraisal and Analysis
Project appraisal and AnalysisProject appraisal and Analysis
Project appraisal and Analysis
 

Similar to PPP Project Life Cycle Presentation

Project finance presentation ppp conference- south africa 2015
Project finance presentation  ppp conference- south africa 2015Project finance presentation  ppp conference- south africa 2015
Project finance presentation ppp conference- south africa 2015Audrey Mwala
 
How Public Private Partnerships Change The World - Nick Houlton
How Public Private Partnerships Change The World - Nick HoultonHow Public Private Partnerships Change The World - Nick Houlton
How Public Private Partnerships Change The World - Nick HoultonPink Elephant
 
Risk management of a ppp programme
Risk management of a ppp programmeRisk management of a ppp programme
Risk management of a ppp programmeAudrey Mwala
 
Project Development Routemap - Infrastructure Foundation Masterclass
Project Development Routemap - Infrastructure Foundation  MasterclassProject Development Routemap - Infrastructure Foundation  Masterclass
Project Development Routemap - Infrastructure Foundation MasterclassCaribbean Development Bank
 
projectfinancingandpublicprivatepartnershipppp-191120191032.pdf
projectfinancingandpublicprivatepartnershipppp-191120191032.pdfprojectfinancingandpublicprivatepartnershipppp-191120191032.pdf
projectfinancingandpublicprivatepartnershipppp-191120191032.pdfSeshukumar53
 
Project financing and public private partnership (ppp)
Project financing and public private partnership (ppp)Project financing and public private partnership (ppp)
Project financing and public private partnership (ppp)M. Asim U Khan
 
Kazakhstan PPP Review - Ana-Maria Ruiz Rivadeneira, OECD
Kazakhstan PPP Review - Ana-Maria Ruiz Rivadeneira, OECDKazakhstan PPP Review - Ana-Maria Ruiz Rivadeneira, OECD
Kazakhstan PPP Review - Ana-Maria Ruiz Rivadeneira, OECDOECD Governance
 
Project Initiation Routemap - Denise Bower, United Kingdom
Project Initiation Routemap - Denise Bower, United KingdomProject Initiation Routemap - Denise Bower, United Kingdom
Project Initiation Routemap - Denise Bower, United KingdomOECD Governance
 
Public Private Partnership presentation Nov 2018
Public Private Partnership presentation Nov 2018Public Private Partnership presentation Nov 2018
Public Private Partnership presentation Nov 2018Audrey Mwala
 
SPUR + TransbayCoalition-Project Delivery Workshop 1 08.31.22.pdf
SPUR + TransbayCoalition-Project Delivery Workshop 1 08.31.22.pdfSPUR + TransbayCoalition-Project Delivery Workshop 1 08.31.22.pdf
SPUR + TransbayCoalition-Project Delivery Workshop 1 08.31.22.pdfAdina Levin
 
Public private partnerships in infrastructure projects
Public private partnerships in infrastructure projectsPublic private partnerships in infrastructure projects
Public private partnerships in infrastructure projectsHillary Fernando
 
Project Development Routemap UK – Caribbean Knowledge Exchange Programme
Project Development Routemap UK – Caribbean  Knowledge Exchange  ProgrammeProject Development Routemap UK – Caribbean  Knowledge Exchange  Programme
Project Development Routemap UK – Caribbean Knowledge Exchange ProgrammeCaribbean Development Bank
 
Ta 7844 project introduction ppt annual road managers' forum 23 march 2012 eng
Ta 7844 project introduction ppt annual road managers' forum 23 march 2012 engTa 7844 project introduction ppt annual road managers' forum 23 march 2012 eng
Ta 7844 project introduction ppt annual road managers' forum 23 march 2012 engOchir Consulting Ltd
 
Ch2 m hill amer khan presentation to meed 15.09.14
Ch2 m hill amer khan presentation to meed 15.09.14Ch2 m hill amer khan presentation to meed 15.09.14
Ch2 m hill amer khan presentation to meed 15.09.14Ibrahim Al-Hudhaif
 
SAR Readiness - v10 - 4-06-2023.pptx
SAR Readiness - v10 - 4-06-2023.pptxSAR Readiness - v10 - 4-06-2023.pptx
SAR Readiness - v10 - 4-06-2023.pptxRakanAlAnazi10
 
Proposal for Salt Iodization
Proposal for Salt IodizationProposal for Salt Iodization
Proposal for Salt IodizationSohail Azeem
 
New guideline norway
New guideline norwayNew guideline norway
New guideline norwayHabib Ahmad
 

Similar to PPP Project Life Cycle Presentation (20)

Project finance presentation ppp conference- south africa 2015
Project finance presentation  ppp conference- south africa 2015Project finance presentation  ppp conference- south africa 2015
Project finance presentation ppp conference- south africa 2015
 
How Public Private Partnerships Change The World - Nick Houlton
How Public Private Partnerships Change The World - Nick HoultonHow Public Private Partnerships Change The World - Nick Houlton
How Public Private Partnerships Change The World - Nick Houlton
 
Risk management of a ppp programme
Risk management of a ppp programmeRisk management of a ppp programme
Risk management of a ppp programme
 
Project Financing and Investment Planning - BORAQS Kenya
Project Financing and Investment Planning - BORAQS KenyaProject Financing and Investment Planning - BORAQS Kenya
Project Financing and Investment Planning - BORAQS Kenya
 
Project Development Routemap - Infrastructure Foundation Masterclass
Project Development Routemap - Infrastructure Foundation  MasterclassProject Development Routemap - Infrastructure Foundation  Masterclass
Project Development Routemap - Infrastructure Foundation Masterclass
 
projectfinancingandpublicprivatepartnershipppp-191120191032.pdf
projectfinancingandpublicprivatepartnershipppp-191120191032.pdfprojectfinancingandpublicprivatepartnershipppp-191120191032.pdf
projectfinancingandpublicprivatepartnershipppp-191120191032.pdf
 
Project financing and public private partnership (ppp)
Project financing and public private partnership (ppp)Project financing and public private partnership (ppp)
Project financing and public private partnership (ppp)
 
Kazakhstan PPP Review - Ana-Maria Ruiz Rivadeneira, OECD
Kazakhstan PPP Review - Ana-Maria Ruiz Rivadeneira, OECDKazakhstan PPP Review - Ana-Maria Ruiz Rivadeneira, OECD
Kazakhstan PPP Review - Ana-Maria Ruiz Rivadeneira, OECD
 
Project Initiation Routemap - Denise Bower, United Kingdom
Project Initiation Routemap - Denise Bower, United KingdomProject Initiation Routemap - Denise Bower, United Kingdom
Project Initiation Routemap - Denise Bower, United Kingdom
 
Public Private Partnership presentation Nov 2018
Public Private Partnership presentation Nov 2018Public Private Partnership presentation Nov 2018
Public Private Partnership presentation Nov 2018
 
SPUR + TransbayCoalition-Project Delivery Workshop 1 08.31.22.pdf
SPUR + TransbayCoalition-Project Delivery Workshop 1 08.31.22.pdfSPUR + TransbayCoalition-Project Delivery Workshop 1 08.31.22.pdf
SPUR + TransbayCoalition-Project Delivery Workshop 1 08.31.22.pdf
 
Public private partnerships in infrastructure projects
Public private partnerships in infrastructure projectsPublic private partnerships in infrastructure projects
Public private partnerships in infrastructure projects
 
Project Development Routemap UK – Caribbean Knowledge Exchange Programme
Project Development Routemap UK – Caribbean  Knowledge Exchange  ProgrammeProject Development Routemap UK – Caribbean  Knowledge Exchange  Programme
Project Development Routemap UK – Caribbean Knowledge Exchange Programme
 
Ta 7844 project introduction ppt annual road managers' forum 23 march 2012 eng
Ta 7844 project introduction ppt annual road managers' forum 23 march 2012 engTa 7844 project introduction ppt annual road managers' forum 23 march 2012 eng
Ta 7844 project introduction ppt annual road managers' forum 23 march 2012 eng
 
Risk management in_the_ESS_Vision_2020v3
Risk management in_the_ESS_Vision_2020v3Risk management in_the_ESS_Vision_2020v3
Risk management in_the_ESS_Vision_2020v3
 
Ch2 m hill amer khan presentation to meed 15.09.14
Ch2 m hill amer khan presentation to meed 15.09.14Ch2 m hill amer khan presentation to meed 15.09.14
Ch2 m hill amer khan presentation to meed 15.09.14
 
SAR Readiness - v10 - 4-06-2023.pptx
SAR Readiness - v10 - 4-06-2023.pptxSAR Readiness - v10 - 4-06-2023.pptx
SAR Readiness - v10 - 4-06-2023.pptx
 
Proposal for Salt Iodization
Proposal for Salt IodizationProposal for Salt Iodization
Proposal for Salt Iodization
 
Readiness Programme for Climate Finance
Readiness Programme for Climate Finance Readiness Programme for Climate Finance
Readiness Programme for Climate Finance
 
New guideline norway
New guideline norwayNew guideline norway
New guideline norway
 

Recently uploaded

No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...Sheetaleventcompany
 
Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...
Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...
Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...Hasting Chen
 
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...NETWAYS
 
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...henrik385807
 
Thirunelveli call girls Tamil escorts 7877702510
Thirunelveli call girls Tamil escorts 7877702510Thirunelveli call girls Tamil escorts 7877702510
Thirunelveli call girls Tamil escorts 7877702510Vipesco
 
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...Pooja Nehwal
 
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779Night 7k Call Girls Noida Sector 128 Call Me: 8448380779
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779Delhi Call girls
 
Call Girl Number in Khar Mumbai📲 9892124323 💞 Full Night Enjoy
Call Girl Number in Khar Mumbai📲 9892124323 💞 Full Night EnjoyCall Girl Number in Khar Mumbai📲 9892124323 💞 Full Night Enjoy
Call Girl Number in Khar Mumbai📲 9892124323 💞 Full Night EnjoyPooja Nehwal
 
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...Salam Al-Karadaghi
 
George Lever - eCommerce Day Chile 2024
George Lever -  eCommerce Day Chile 2024George Lever -  eCommerce Day Chile 2024
George Lever - eCommerce Day Chile 2024eCommerce Institute
 
Mathematics of Finance Presentation.pptx
Mathematics of Finance Presentation.pptxMathematics of Finance Presentation.pptx
Mathematics of Finance Presentation.pptxMoumonDas2
 
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdf
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdfOpen Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdf
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdfhenrik385807
 
ANCHORING SCRIPT FOR A CULTURAL EVENT.docx
ANCHORING SCRIPT FOR A CULTURAL EVENT.docxANCHORING SCRIPT FOR A CULTURAL EVENT.docx
ANCHORING SCRIPT FOR A CULTURAL EVENT.docxNikitaBankoti2
 
Microsoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AIMicrosoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AITatiana Gurgel
 
Russian Call Girls in Kolkata Vaishnavi 🤌 8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Vaishnavi 🤌  8250192130 🚀 Vip Call Girls KolkataRussian Call Girls in Kolkata Vaishnavi 🤌  8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Vaishnavi 🤌 8250192130 🚀 Vip Call Girls Kolkataanamikaraghav4
 
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024eCommerce Institute
 
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝soniya singh
 
Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...
Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...
Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...Kayode Fayemi
 
Introduction to Prompt Engineering (Focusing on ChatGPT)
Introduction to Prompt Engineering (Focusing on ChatGPT)Introduction to Prompt Engineering (Focusing on ChatGPT)
Introduction to Prompt Engineering (Focusing on ChatGPT)Chameera Dedduwage
 
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )Pooja Nehwal
 

Recently uploaded (20)

No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...
 
Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...
Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...
Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...
 
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
 
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
 
Thirunelveli call girls Tamil escorts 7877702510
Thirunelveli call girls Tamil escorts 7877702510Thirunelveli call girls Tamil escorts 7877702510
Thirunelveli call girls Tamil escorts 7877702510
 
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
 
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779Night 7k Call Girls Noida Sector 128 Call Me: 8448380779
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779
 
Call Girl Number in Khar Mumbai📲 9892124323 💞 Full Night Enjoy
Call Girl Number in Khar Mumbai📲 9892124323 💞 Full Night EnjoyCall Girl Number in Khar Mumbai📲 9892124323 💞 Full Night Enjoy
Call Girl Number in Khar Mumbai📲 9892124323 💞 Full Night Enjoy
 
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
 
George Lever - eCommerce Day Chile 2024
George Lever -  eCommerce Day Chile 2024George Lever -  eCommerce Day Chile 2024
George Lever - eCommerce Day Chile 2024
 
Mathematics of Finance Presentation.pptx
Mathematics of Finance Presentation.pptxMathematics of Finance Presentation.pptx
Mathematics of Finance Presentation.pptx
 
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdf
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdfOpen Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdf
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdf
 
ANCHORING SCRIPT FOR A CULTURAL EVENT.docx
ANCHORING SCRIPT FOR A CULTURAL EVENT.docxANCHORING SCRIPT FOR A CULTURAL EVENT.docx
ANCHORING SCRIPT FOR A CULTURAL EVENT.docx
 
Microsoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AIMicrosoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AI
 
Russian Call Girls in Kolkata Vaishnavi 🤌 8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Vaishnavi 🤌  8250192130 🚀 Vip Call Girls KolkataRussian Call Girls in Kolkata Vaishnavi 🤌  8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Vaishnavi 🤌 8250192130 🚀 Vip Call Girls Kolkata
 
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
 
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
 
Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...
Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...
Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...
 
Introduction to Prompt Engineering (Focusing on ChatGPT)
Introduction to Prompt Engineering (Focusing on ChatGPT)Introduction to Prompt Engineering (Focusing on ChatGPT)
Introduction to Prompt Engineering (Focusing on ChatGPT)
 
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )
 

PPP Project Life Cycle Presentation

  • 1. Kick Starting a PPP project Presentation by : Mrs. Audrey Mwala Director of Project Finance & Risk Analysis The Public Private Partnership Commission, Malawi1
  • 2. Session 3- Outline •PPP Project life Cycle: •Egypt •Mauritius •Kenya •Knowledge, skill, attitudes for PPP delivery •The readiness of state institutions •Reorienting the public sector •Working with the private sector •Initiation and planning of PPP programme •Importance of legal, Institutional, financial, fiducially framework for capacity building •Project Finance and financial Modeling •Risk Management 2/26/2016 2 Presented by: Mrs Audrey Mwala, Director Project Finance and Risk Analysis, The PPPC, Malawi
  • 3. What it is a PPP project Life Cycle • Logical sequence of activities to achieve project’s objectives. • All projects go through a series of stages. • Lifecycles differ across: – countries, – sectors and – by the chosen implementation method • A life cycle is used to: – Control progress through a project; – Provides review points – Project’s likelihood of success is validated – Decision to move to the next phase made. 2/26/2016 3 Presented by: Mrs Audrey Mwala, Director Project Finance and Risk Analysis, The PPPC, Malawi
  • 4. Key Life Cycle Stages 1. Project Identification 1.1 Project selection and definition  Identification  Output specifications 1.2 Assessment of the PPP option  Affordability  Risk allocation  Bankability  Value for money 2. Detailed Preparation 2.1 Getting organised  Project team  Advisory team  Plan and timetable 2.2 Before launching the tender  Further studies  Detailed PPP design  Procurement method  Bid evaluation criteria  Draft PPP contract 3. Procurement 3.1 Bidding process  Notice and prequalification  Invitation to tender  Interaction with bidders  Contract award 3.2 PPP contract and financial close  Final PPP contract  Financing agreements  Financial close 4. Project Implementation 4.1 Contract management  Management responsibilities  Monitoring service outputs  Changes to the PPP contract  Dispute resolution  PPP contract termination 4.2 Ex post evaluation 4.2 Ex post evaluation  Institutional framework  Analytical framework 2/26/2016 4 Presented by: Mrs Audrey Mwala, Director Project Finance and Risk Analysis, The PPPC, Malawi
  • 5. Mauritius • PPP Act of November 2004. • Amended in June 2008 to: – provided set up of a PPP Committee and – provided for unsolicited bids 2/26/2016 5 Presented by: Mrs Audrey Mwala, Director Project Finance and Risk Analysis, The PPPC, Malawi
  • 6. Key Institutions/ Parties • Contracting Authority- – Identify, appraise, develop and monitor a projects – Carry out feasibility studies – Submit results to the PPP Committee – Prepares RFP on the approval of the study • Central Procurement Board – Examine and evaluate bids – Recommend to CA to negotiate with preferred bidder – Approve the award of the project A PPP Unit •Set up in July 2002 •Drafted the legislation •Produced PPP guidelines Manual •Reports to the PPP Committee •Works with CAs to select PPP projects •Deals with matters referred by PPP Committee •Source of PPP information •Develop PPP awareness. PPP Committee •Assessments projects, recommends to CA •Develop PPP best practice guidelines •Formulate PPP policy in relation 2/26/2016 6 Presented by: Mrs Audrey Mwala, Director Project Finance and Risk Analysis, The PPPC, Malawi
  • 7. PPP Cycle – Govt. initiated PPPs Feasibility Study- • To assess if a project may be implemented under PPP. • The feasibility study must demonstrate: • comparative advantage for implementation under a PPP – Affordability, VFM, Risk transfer • Show contracting authority’s capacity to effectively: – enforce agreement, Monitor implementation and performance • The extent to which functions can lawfully and effectively be performed by a private party • The most appropriate form of PPP 2/26/2016 7 Presented by: Mrs Audrey Mwala, Director Project Finance and Risk Analysis, The PPPC, Malawi
  • 8. Procurement Pre-selection • The CA obtains approval of CPB conduct pre-selection. • The pre-selection documents are approved by CPB. Request for Proposal • The CA submits the RFP to the CPB for approval. Evaluation and award of bids • The CPB is responsible for the evaluation of bids -but may set up an evaluation committee. • The award of the contract is approved by the CPB. 2/26/2016 8 Presented by: Mrs Audrey Mwala, Director Project Finance and Risk Analysis, The PPPC, Malawi
  • 9. Procurement unsolicited Proposal • Private party submits project concept & feasibility study cost to CA. • CA examines project in line with sector strategies & investment programme and if its suitable for PPP. • CA submits it to the PPP Committee within 15 days. • The PPP Committee may approve or reject the project concept. • If the CA within 5 working days requests the proponent to submit: – details of technical, commercial, managerial and financial capabilities; – a feasibility study – the nature of information which is proprietary. • No price proposal at this stage. 2/26/2016 9 Presented by: Mrs Audrey Mwala, Director Project Finance and Risk Analysis, The PPPC, Malawi
  • 10. Unsolicited bid’s Cont1’ • The PPP Committee assesses the feasibility study and evaluates the technical proposal. – (a) If its accepted, the PPP Committee requests CA to proceed with an Invitation to bid. – (b) If its rejected, the process ends. No compensation for feasibility study costs. • CA prepares RFP based on information in the technical proposal. • The RFP is approved by the CPB before bids are invited. • The proponent is requested to submit only a financial proposal. • The other bidders submit both technical and financial proposals. 2/26/2016 10 Presented by: Mrs Audrey Mwala, Director Project Finance and Risk Analysis, The PPPC, Malawi
  • 11. Unsolicited bid’s Cont2’ • The RFP indicates that: • (a)the project has emanated from a proponent whose technical proposal was accepted • (b)the proponent will be awarded the project if their price is within 10 % of the price of the preferred bidder; and • (c) If the original proponent is not successful, the CA will compensate the cost of the feasibility study which will be claimed from the successful bidder. • The CPB evaluates the bids gives and approval of the successful bidder. 2/26/2016 11 Presented by: Mrs Audrey Mwala, Director Project Finance and Risk Analysis, The PPPC, Malawi
  • 12. Egypt • PPP Law (Law 67/2010), Partnership with Private Sector for Infrastructure Projects & Public Utilities • Regulations 2011 • Policy 2/26/2016 12 Presented by: Mrs Audrey Mwala, Director Project Finance and Risk Analysis, The PPPC, Malawi
  • 13. Key Institutions • Line Ministry – (CA)- identifies projects • Minister of Finance • Satellite Units in Line Ministries (Nodal Agencies) 2/26/2016 13 Presented by: Mrs Audrey Mwala, Director Project Finance and Risk Analysis, The PPPC, Malawi A PPP Central Unit •Promote the national PPP initiative • Facilitate solutions to legal and institutional obstacles for PPPs •Develop PPP best practices, models •Validate and develop PPP proposals •Shepherd pilot procurements of PPPs •Build capacity in the Public sector •Assist in selection of advisors, Investors PPP Supreme Committee •Approve projects •Appoints advisors •Prepare Contract Award Requirements
  • 14. The Cycle – Line Ministry Submits Project Proposal to – PPP Central Unit for Screening/ modification – PPP Central Unit submits to – PPP Ministerial Committee for Approval 2/26/2016 14 Presented by: Mrs Audrey Mwala, Director Project Finance and Risk Analysis, The PPPC, Malawi Project Preparation Approval by Supreme Committee Tendering Implementation & Post Contract Monitoring Project initiation
  • 15. Competitive Dialogue –with the qualified bidders –with each bidder separately – to obtain explanations for the contents of the technical and financial elements – basis of equality amongst the qualified Investors 2/26/2016 15 Presented by: Mrs Audrey Mwala, Director Project Finance and Risk Analysis, The PPPC, Malawi Challenge of disqualification •Disqualified Investors can object to the Prequalification Committee’s decision. •An objection shall be submitted to the PPP Central Unit to study and issue its binding decision.
  • 16. Approval of draft contracts – Line Ministry has the right to : • approve third part contracts to be entered by the Project company for the delivery of the project works & services • Object such appointments 2/26/2016 16 Presented by: Mrs Audrey Mwala, Director Project Finance and Risk Analysis, The PPPC, Malawi Challenge of disqualification •Disqualified Investors can object to the Prequalification Committee’s decision. •An objection shall be submitted to the PPP Central Unit to study and issue its binding decision.
  • 17. Kenya “A center of PPP Expertise” • PPP Policy November 2011 • PPP Act 2012 • A Project Facilitation Fund to provide an avenue for government support to PPP projects. 2/26/2016 17 Presented by: Mrs Audrey Mwala, Director Project Finance and Risk Analysis, The PPPC, Malawi
  • 18. Project Implementation Structures • PPP Nodes – responsible for the development and management of PPP projects; • The PPP Unit – domiciled at the State Department responsible for Finance, – a national centre for PPP expertise; – develop and distribute PPP Operating Guidelines and Manuals 2/26/2016 18 Presented by: Mrs Audrey Mwala, Director Project Finance and Risk Analysis, The PPPC, Malawi •PPP Committee - responsible for developing and implementing PPP policy initiatives; •Cabinet-Final approval but delegate to PPP Committee
  • 19. The Cycle • Project Identification, Selection and Prioritization technical profile, operations, service delivery targets, and future income and costs (Scooping) • Project Preparation and Appraisal: a full investment appraisal • Project Tendering • Project Negotiation • Project Monitoring and evaluation- The CA to establish clear procedures for monitoring. The PPP Unit and the PPP Committee has an oversight role 2/26/2016 19 Presented by: Mrs Audrey Mwala, Director Project Finance and Risk Analysis, The PPPC, Malawi
  • 20. Competitive dialogue • A contracting authority may, hold a competitive dialogue with each bidder to define technical or financial aspects of the project • may require a bidder to submit to the authority a technical and financial non-binding proposal for discussion • held with each bidder on the basis of equality and transparency. 2/26/2016 Presented by: Mrs Audrey Mwala, Director Project Finance and Risk Analysis, The PPPC, Malawi 20
  • 21. Privately Initiated Investment Proposals • Limited to projects that demonstrate: – genuine innovation and/or – use of proprietary technology, – economic viability and – satisfy the principles of public interest 2/26/2016 21 Presented by: Mrs Audrey Mwala, Director Project Finance and Risk Analysis, The PPPC, Malawi
  • 22. Privately Initiated Investment Proposals • A contracting authority, before negotiations: – prescribes a criteria against which the outcome of negotiations shall be evaluated; – submits the proposal to the PPP unit for consideration and recommendation – apply for approval from the Committee to negotiate the contract – conduct the negotiations and award the tender • Key issues: VFM, Affordability, Risk transfer 2/26/2016 22 Presented by: Mrs Audrey Mwala, Director Project Finance and Risk Analysis, The PPPC, Malawi
  • 23. Knowledge skills & Altitudes for PPP project delivery • Project Development skills- – Privately financed infrastructure project structuring skills – Go to Market with a Solid Transaction Structure • Economic and financial appraisal skills – Evaluating traditional vs. PPP • Communication skills: with general public • Procurement/ evaluation – Sensitivity to the objectives, political environment, public • Technical skills- understand the technical details 2/26/2016 23 Presented by: Mrs Audrey Mwala, Director Project Finance and Risk Analysis, The PPPC, Malawi
  • 24. Knowledge skills & Altitudes for PPP project delivery • Negotiations -to finalise agreements • Contract management skills – Reporting- on matter of general policy and projects – Dispute resolution • PPP transaction/ process management skills – Approvals, what stages, whom. • Monitoring -Implementation and compliance • Legal & regulatory skills • Experience in dealing with the private sector • Market sounding: check with lenders to understand their perspectives of their own market challenges 2/26/2016 24 Presented by: Mrs Audrey Mwala, Director Project Finance and Risk Analysis, The PPPC, Malawi
  • 25. Monitoring skill… • Monitor, transparency and accountability of PPP unit work / State Authority / PPP partner – Audit of PPP procurement processes – Audit of PPP project performance – independent reviews, Director of Audit • Effectiveness / performance audit – to see if projections regarding PPP procurement against traditional procurement were realised 2/26/2016 25 Presented by: Mrs Audrey Mwala, Director Project Finance and Risk Analysis, The PPPC, Malawi
  • 26. The state of readiness of state Institutions • Establish PPP policy and Legal frame work – Need for clear mandate for state institutions – Draft PPP contract • Strong National Political Backing – Clear Public Sector Commitment • A realist pipeline of bankable projects – Sound understanding of the needs of a particular sector – be Bankable for Private Sector financing i.e. large, attractive size • Establish clear ownership ( risks resistance by CAs) • Adequate capacity for the PPP unit and the Nodal agencies – To carry out rigorous project feasibility – Risk-allocation structure must be clear 2/26/2016 26 Presented by: Mrs Audrey Mwala, Director Project Finance and Risk Analysis, The PPPC, Malawi
  • 27. The state of readiness of state Institutions • Access to local and international financing institutions • Affordability by Govt. – Creditworthiness to make unitary payments • Project development fund ( revolving fund) • Viability Gap fund • Communication with stakeholders • Professional and effective monitoring of the private party • Proper advisory support 2/26/2016 27 Presented by: Mrs Audrey Mwala, Director Project Finance and Risk Analysis, The PPPC, Malawi
  • 28. Reorienting the Public sector • Capacity Building, PPP training • Targeted seminars • Role of advisors • Political will • Political Champion • Public awareness • Low hanging fruits 2/26/2016 28 Presented by: Mrs Audrey Mwala, Director Project Finance and Risk Analysis, The PPPC, Malawi
  • 29. Working with the private sector • Project preparation- project scooping • Procurement – Technical specifications – VFM – evaluation • Negotiation • Implementation/ construction phase – Reporting – Technical issues/ standards - Payments - Post implementation monitoring • Contract Compliance – Legal • Streamline process - speed 2/26/2016 29 Presented by: Mrs Audrey Mwala, Director Project Finance and Risk Analysis, The PPPC, Malawi
  • 30. PPP Programme initiation and Planning • Legal framework (Law and Policy) • PPP guidelines • Institutional framework • PPP sector nodes • Personnel Capacity; • PPP expertise, legal, finance, economic, ‘sector specialists” • PPP advisors • Institutional roles & approvals • Financial resources for: – administration, – project development & – monitoring 2/26/2016 30 Presented by: Mrs Audrey Mwala, Director Project Finance and Risk Analysis, The PPPC, Malawi
  • 31. PPP Project preparation • Project pipeline Selection – Potential candidates for further analyze – Not too small, clear private sector interest – conceptual stage – limited information – Project Desirability (public interest) • APPRAISAL -structured, prepared, Ranking & Concept Paper – Project Achievability/ deliverable output – Project Ability (Policy and Program): Is the it a priority – Project Viability (Financing) – investment size and useful life – Sequencing- low hanging fruits first • APPROVAL – final approval to proceed to implementation i.e. Developing a Business Case 2/26/2016 31 Presented by: Mrs Audrey Mwala, Director Project Finance and Risk Analysis, The PPPC, Malawi
  • 32. PPP unit • Many countries with a successful PPP programme have created a dedicated PPP unit. • Roles of PPP Units include: – Regulating the PPP process – Promoting PPPs within Govt. – Helping agencies to implement PPPs – Providing channels to investors – Help in monitoring 2/26/2016 32 Presented by: Mrs Audrey Mwala, Director Project Finance and Risk Analysis, The PPPC, Malawi
  • 33. Business case Development • Assess if the project: • Meets government’s policy sector objectives • Is ‘feasible’: technically, financially, economically, environmentally, • Is ‘deliverable’- output standards; • Is ‘affordable’ to the public authority • Is ‘bankable’ to the private investors & lenders • Management & Contract enforcement capability. 2/26/2016 33 Presented by: Mrs Audrey Mwala, Director Project Finance and Risk Analysis, The PPPC, Malawi
  • 34. Plan • for: • Procurement • Implementation • Post construction • Contract expiration 2/26/2016 34 Presented by: Mrs Audrey Mwala, Director Project Finance and Risk Analysis, The PPPC, Malawi
  • 35. Success factors • Stable macro economic environment • Willingness of the Public Client to accept innovative solutions • A detailed contract • Professional and effective monitoring of the private contractor • Selection of appropriate project candidates • Good detailed preparation: – Clear business cases, – clear output specifications, – A PPP project procurement team • Proper advisory support • A well structured, transparent, competitive PPP procurement process. • A clear and consistent methodology for evaluating FVM • Proper monitoring of the entire operational phase. • A determination by all parties and stakeholders to make the PPP work • Management of contingent liabilities 2/26/2016 35 Presented by: Mrs Audrey Mwala, Director Project Finance and Risk Analysis, The PPPC, Malawi
  • 36. Importance of legal, institution; fiduciary, financial framework in Capacity building • legal – Sets Objectives to build capacity – Sets Institutions for targeted capacity building – Gives legal mandate of the institutions – Gives investors confidence to predict the process – transparent, and competitive procurement • Institution – Allows for building of a team of professionals – Capacity building to include the private sector to understand PPP framework before they invest. 2/26/2016 36 Presented by: Mrs Audrey Mwala, Director Project Finance and Risk Analysis, The PPPC, Malawi •Fiduciary •Reporting provides accountability excellence •Approvals provide national will •Audits provide confidence and due respect of the process •Financial •Allows capacity building to happen •Public awareness programmes •Allows project preparation •Allows PPP payment & investment