The site visit evaluates a project that installed handpumps and water supply schemes in 7 villages affected by flooding. Physical verification found that most infrastructure was operational. Focus groups discussed project benefits and challenges. Villagers now have improved access to drinking water but feel additional infrastructure is still needed. Some conflicts emerged over water access between communities. The project overall increased access to safe water, but sustainability may require continued community management and awareness efforts.
it includes 21 slides, having definition of project, project management, project management cycle.
it also explains all the phases of PMC.
it also includes characteristics, advantages and disadvantages of project management cycle.
Project Planning and Approval Process Presentation.Presentation about how projects planned and approved. Presentation by Atif Nauman (University of Gujrat)
it includes 21 slides, having definition of project, project management, project management cycle.
it also explains all the phases of PMC.
it also includes characteristics, advantages and disadvantages of project management cycle.
Project Planning and Approval Process Presentation.Presentation about how projects planned and approved. Presentation by Atif Nauman (University of Gujrat)
PPT with overall coverage of the project evaluation and all the topic of project evaluation and post project evaluation are covered in this ppt.It includes all the topic of project evaluation:-
=>which of the project should be evaluated?
=>cost&timing
=>social analysis
=>environmental analysis
=>progress report
=>final report
and many more topics are covered in this ppt for the brief description of project evaluation and some left out topics are numerical of project evaluation.
This presentation explains the difference between Monitoring and Evaluation; the types of M&E frameworks; steps in logical framework and its difference from theory of change.
In this presentation we have done earlier a project for Phillip Morris (Pakistan) for the access control system and canteen management system. It is the project presentation for our subject Planning and Scheduling. i hope it is the best for the understanding Project planning and scheduling.
This chapter describes the means by which PSNP4 programme clients and other community members can express their views on how programme design or implementation can be improved. It also describes the means by which clients and community members can raise grievances with different aspects of programme implementation and get these grievances resolved.
A series of modules on project cycle, planning and the logical framework, aimed at team leaders of international NGOs in developing countries.
New improved version of Writing Project Proposals in February 2014.
PPT with overall coverage of the project evaluation and all the topic of project evaluation and post project evaluation are covered in this ppt.It includes all the topic of project evaluation:-
=>which of the project should be evaluated?
=>cost&timing
=>social analysis
=>environmental analysis
=>progress report
=>final report
and many more topics are covered in this ppt for the brief description of project evaluation and some left out topics are numerical of project evaluation.
This presentation explains the difference between Monitoring and Evaluation; the types of M&E frameworks; steps in logical framework and its difference from theory of change.
In this presentation we have done earlier a project for Phillip Morris (Pakistan) for the access control system and canteen management system. It is the project presentation for our subject Planning and Scheduling. i hope it is the best for the understanding Project planning and scheduling.
This chapter describes the means by which PSNP4 programme clients and other community members can express their views on how programme design or implementation can be improved. It also describes the means by which clients and community members can raise grievances with different aspects of programme implementation and get these grievances resolved.
A series of modules on project cycle, planning and the logical framework, aimed at team leaders of international NGOs in developing countries.
New improved version of Writing Project Proposals in February 2014.
A case that illustrates the importance of the introduction of “easy to introduce” measures and techniques when managing a project with some bad history and long delays.
Research Report: Strategies for Project RecoveryPM Solutions
New research on "Strategies for Project Recovery," released in February 2011 by PM Solutions Research, shows that, despite a long history of doom and gloom around project failures, successful project recoveries are actually quite common.
SymEx 2015 - Troubled Project Recovery, The Story of Firefighter & HeroPMI Indonesia Chapter
Have you ever been assigned to lead a project that was already in trouble?
Can troubled projects be recovered, or are they doomed to fail?
How do we know whether we can still rescue it or we just have to terminate it?
With little time to hone the perfect approach, project managers need to be able to identify and address the major causes of their troubled projects. Then, by understanding the causes, they can effectively deal with the issues, mitigate major risks and manage stakeholder expectations.
However, sometimes, the project is simply a 100% outright disaster. In this case, project managers should prepare themselves to come up with choices. They should be able to stand up and escalate to senior management/project owners to gain their decisions on whether to proceed.
Whether a troubled project ultimately succeeds or fails depends on the effectiveness of the actions taken to recover the project. Before these actions can be taken, however, project managers need to be able to recognize problems and prepare to take appropriate corrective measures. All of these actions need to be carried out with speed, accuracy and focus.
Through this presentation you will learn practical processes and techniques to assess the status of a project, to determine whether you can rescue the project through recovery plans, then finally to turn the project around.
Presentation given at the Kansas City Chapter of PMI several years ago. Examines and details 4 failed projects, their effects and how they were dealt with.
Practical Strategies for Project Recovery Webinar SlidesPM Solutions
Organizations spend a lot of money on projects. In the last year alone, the average firm closed US$200 million in projects, according to a just-released study conducted by PM Solutions Research. And more than a third of those projects were troubled. That means US$74 million of those projects were at risk of failure. The good news is that project recoveries are common and firms that proactively undertake successful project recoveries report saving US$50 million on average per firm. Learn what other organizations are doing to recover troubled projects and the significant business results they have been able to realize.
The 5 Phases of a Project TurnAround - How to rescue troubled projectsTorsten Koerting
Projects do fail.
Whether they are big or small. At some point they will go through crisis and major challenges. This presentation focuses on how to recover troubled projects.
Questions that will be answered:
Why do projects fail?
What are the 5 phases of a TurnAround
What Tools / Methods / Approaches to use to help you recover
Understand the concepts by applying them to actual living cases
Learn how to apply them in your own environment
Content is based on the book project www.turnaroundpm.com which will be published in May / June this year.
This lecture provides a short review of postmortem analysis. The core responsibility of software project manager. Postmortem analysis describes reasons of software project failure or success.
In this session, we are looking at Business Analysis as an important element in making projects / programs successful.
This presentation explores the link between Business Analysis and Project Life Cycle.
We also looked at PMI's Business Analysis Certificate, PMI-PBA®
Urban Waters Forum 2023 - Water sustainability workshopbiometrust
The second edition of Urban Waters Forum workshop 2023 was conducted on the 15th and 16th of March 2023 and brought together water practitioners from across the country for knowledge sharing, including new developments in their respective domains of work. There were around 60+ members, who included academicians, lake group members, water professionals and government officials, and representatives from various states like Maharashtra, Kerala, Gujarat, West Bengal, Jharkhand, Uttarakhand and Karnataka.
we call upon you to stand with us on this program of promoting the communities to improve on their health and even helping the communities to have clean safe water sources .
All the information has been attached .
The Water Security Plan (WSP) is a sample copy of one out of 97 villages in Rapar Taluka of Kachchh district in Gujrat. WSP for all the 97 revenue villages of the block is prepared for Samerth Charitable Trust with support from Argyam Trust, Bangalore.
By D. Dhanuraj
This study is on the initiative of the Pazhakulam Service Society (PASS) for the conservation of natural springs in order to use it as a source of safe drinking water. PASS situated at Pazhakulam near to Adoor, Kerala is active in various social activities. It has build up to 1500 schemes across Kerala and has widened the coverage of the accessibility of safe drinking water to rural people and brought the various actors in a provider group to a collective organ in the course of time.
Water Exploration and Conservation with Renewable Energy to Accomplish Sustai...ESD UNU-IAS
Water Exploration and Conservation with Renewable Energy to Accomplish Sustainable Water Supply
Dr. Nanung Fitriyanto, RCE Yogyakarta
Asia-Pacific Regional RCE Meeting 2018
25-27 September, 2018, Parramatta (Sydney), Australia
This paper highlights the importance of community owinerships in piped water supply. Better water accessibility will be provided to people if they take ownership in water supply and learn to manage it within the community. See More : https://www.wateraidindia.in/
This document has been prepared under the project “Decentralised drinking water security in 6 Arsenic affected
GPs of Sahibganj district” supported by Arghyam, Bangalore.
http://www.pria.org/decentralised_drinking_water.htm
Author: Dr Alok Pandey, Deputy Director, PRIA
To know more about the project visit
How to write an development project evaluation report. Format and principle guidelines for mid-term and for completed projects. This format can be used for any kind of development project.
1. POST PROJECT EVALUATION REPORT
Project Name Clean Drinking Water for the Population of TM
Khan District, Sindh
Project Location UC Ghulam Shah Bagrani, Moya TM Khan
District Sindh
Donor organization Association for the Development of Pakistan
(ADP)
Sector Water and sanitation
Implementing Partner Sindh Community Foundation (SCF)
Visiting Person Irfan Hussain Shaikh
Site Visit Date 20-12-2014
Introduction
Thisreportis intendanttoinformthe donororganization,implementingpartnerandotherstake holder
regardingthe reverence,performance,impactandsustainabilityof the intervention.The majorpurpose
of thisreportisto keepinformthe decision makerssotheymaylearnfromexperience andguide future
action-projectphase two.Forthe purpose one meetinghasbeenorganizedwithkeyprojectofficersand
severvillages-projectsite were visited.Sevenfocusgroupdiscussionandtwokeyinformantinterview
were conducted.The datawas recordedonthe structuredquestionnaire andinanaudiorecorder.No
one majorissue wasfoundinthe intervention,accesstosave drinkingwaterandsanitationhave been
remarkablyimprove of the directbeneficiaries.
Objective
To evaluate the overall relevance,performance,impactandsustainabilityof the project
To evaluate issuesinprojectimplementation,tokeepinformthe decisionmakers
To evaluate the impactof the interventiononthe communities
Methodology
Structuredquestionnaireswere usedtocollectthe data,focusgroupdiscussion,keyinformant
interviewsandtransitwalkgeneral observationtechniqueswere appliedtogatherthe data. Anindepth
analysisof the qualitativedatawasundertaken.Total no of sevenFGDand keythree information
interview were contacted.
2. Findings
MEETING WITH THE SINDH COMMUNITY FOUNDATION (SCF) KEY STAFF
A meeting was conducted with the SCF Staff on 16 December 2014 at the Head Office
Qasimabad, Hyderabad. The agenda of the meeting included progress review of Phase – I of
the project including works in seven villages. Based on the documents received from SCF and
ADP, project information was discussed and reinforced with the SCF representatives in the
meeting.
Project Coordinator Jawed Hussain,
Program Manager Rizwan Soomro,
Accounts Manager Nayar Azam,
Project Supervisor and Associate Engineer Abdul Ghafoor
3. Following main points emerged during the meeting:
Sites were selected with the consent of beneficiaries keeping in view the need of the most
vulnerable and to ensure better distribution among the villagers. DRR and gender issues were
also kept in consideration and to the ease of women who are primarily water managers. Site
selection was also subject to considerations of physical security of installations.
Water tests were conducted through PCSRW and samples were drawn by boring. Aquifers with
sweet and plenty water were preferred. DRR and gender issues are in consideration.
Community members participated at all levels of project works. Beneficiaries also took part as
lobour in the project works.
Village Water Management Committees (VWMC) was formed in each of the seven villages.
These VWMCs were responsible to oversee project works in their respective villages as per
agreed responsibilities including reporting to the Project Supervisor on the progress and issues
in implementation. The WMCs were also responsible to undertake maintenance or repair work
as arise may arise with time.
Awareness sessions were conducted by SCF on hygiene and health in each village. Focusing
“Personal Health and Hygiene, Best Water Practices and Balanced Nutrition”. The same
sessions were used for social mobilization for the project.
Internal monitoring on part of SCF was conducted by Project Steering Committee (PSC) formed
in relation to the project and beneficiaries (VWMC and SWC along with community leader).
On average around 90 people have access to portable water through each Daccar Pump per
day Project Coordinator Javed Hussain supervised inputs for the project providing guidelines to
4. other project staff and overseeing overall implementation. Project Supervisor and Associate
Engineer Abdul Ghafoor was responsible to look directly into the identification/demarcation of
land, installation of pumps and water supply schemes, pre-site approvals and testing of water
quality, checking of material and internal monitoring under intimation to Project Coordinator. The
Project Supervisor was also responsible for daily update of project progress along with monthly
reporting. VWMC and SWC along with community leader were also involved in monitoring
works. Social Mobilizer Ghalib was responsible to arrange sessions/ mobilization meetings and
focused group discussions.
The Project Coordinator said that village wise profiles were developed and technical reports
were submitted to ADP. Project Supervisor and Associate Engineer added that demarcation of
land and developing consensus in community is time consuming and recommends that ADP
should increase the time duration of project. Program Manager said that delays in payment lead
to cost over runs in material and transportation.
After completion of Phase – I, the Project Staff including Project Coordinator undertook
meetings and informal discussions with the villagers to inquire if any immediate issues may
have arise or the conflicts may have occurred on water allocation. In cases of such conflicts,
VWMC and SCW and community leaders were involved in resolutions.
By raising height of the pump by 1.5 feet, possible damage by soil erosion and rain flooding may
be minimized. In addition, Daccar pumps are much better in raising water from more depths and
also provide greater quantity of water.
5. SUMMARY OF SITE VISIT & COMMUNITY INTERVIEW
The site visit is scheduled in the meeting with scf staff on 16, dec, 2015. The visite is take place
on 21 dec. The agenda of the site visit is to verify that all the handpumps and water supply
scheme are operational and to conduct a focus group discussion is each village with
beneficaries and other villagers and to evaluate the project work.
PHYSICAL VERIFICATION
a. Following Handpumps (Phase – I)
b. Water Supply Schemes (Phase – I)
S # Village Handpumps Status Timing
1 Nizam Khan Rind 1 Operational 12:45pm to 01:23 pm
2 Haji Photo Bhatti 3 Operational 02:17pm to 02:59pm
3 Ghulam Shah Bagrani 1 Operational 03:28pm to 0352pm
4 Bambo Khokar/ Agay Dino Rind 1 Not verified
5 Veeho Kohli 1 Operational 06:25pm to 07:02pm
7
S # Village Water
Scheme
Status Timing
1 Shadi Khan Rind 1 Operational 04:23pm to 05:52pm
2 Mehboob Ali Rind 1 Operational 11:am to 12:15pm
2
6. UC Ghulam Shah Bagrain Moya, District Tando Mahammad Khan is an underdeveloped area.
Rind Baloch, Shah, Khaskheli, Soomrow, Chandia, Arain, and in minorities Kohli, Bheel and
Megwar inhabit the villages. Local language is Sindhi. People live in clusters of small scale
settlements locally known as bastis usually relatives with old tradations, norms and coustoms.
90 percent of the population is dependent upon agricultural and allied activities. Rare proportion
of the population is involved in market related activity and trading, including general stores,
easypaisa shops, local hotels and cabins.
In 2011 Sindh province experienced abnormal rains leading to flooding in the interior areas
affecting all 23 district including Tando Muhammad Khan District. Flood water recession took
much time for people to resettle. They have had to live in camps deprived of the assets they
needed to restore their livelihood. People were of the view that there was ‘no life during the
7. flood’. Most of the inhabitants of the seven villages (of Phase – I) fased the same condition/.
Diseases which became prevalent after the flood are mostly skin diseases, eye soaring,
dirrehea and malaria.
In most of the villages, water is not fit for drinking. Villagers are dependent on ground water
sources for household needs. According to these villagers canal water is not drinkable and they
use it only in cultivation and wash purposes. Ground water is the main source of drinking water
currently being drawn by a hand pumps locally known as Sunni Machine and Nalka. However,
most of the communities prefer Daccar Hand pumps according to them Daccar Hand pumps are
easy to use and can draw water from more depths and supply large quantity of water.
It is observed in the visit that if the hand pumps are installed in community (basti) close to the
houses, every person can access and draw water for their needs but if the same are located
outside the villages, then women and children are engaged in fetching water to manage the
household needs and not save too.
In some villages community is of the view that water supply system was more accessible before
the flood. They said that the floods destroyed their water courses and caused extensive damage
to the existing water supply installations. Some community members were of the view that water
system has become more accessible after last flooding since a number of NGO set up hand
pumps and some are of the view that the condition is same.
According to the villagers, it takes longer time to fetch water from nearby community/ areas. On
average, they have to walk up to 2 to 3 km to reach to the nearest source of water. Conflicts
also arise due to children misbehavior in other bustis. They say that insecurity surmounts and
therefore women in particular go in groups to fetch water. With hand pumps this burden is
gradually decreasing.
They are of the view that installation of hand pumps and construction of water tanks is
necessary to minimize the problems but not the permanent solution. They said installation of
water filtration plants and construction of water and drainage infrastructure are further
requirements.
In some villages people are not aware about Sindh Community Foundation (SCF). According to
them SCF as an organization did not do any development work before this Project.
Villagers had positive thinking. They were happy with SCF and ADP development works and
expressed satisfaction.
In these villages minor conflict have arise but there is no major conflict between different groups
and castes. During the interview it has been noticed that in village Mehboob Ali Rind, Ghulam
Shah Bagrani and Shadi Khan Rind there is no conflict in sharing water but in village Nizam
Khan Rind, Haji Photo Bhatti and Ceeho Kohli people are having minnor conflicts and only the
community members are taking benefit from these hand pumps and water supply scheme and
restricting others. The reasons behind are old conflicts, religious and personal. It is also found
that if hand pumps are installed in community near their houses, only the communities take
benefit and if hand pumps are installed at common place all the community take benefit from it.
8. In village Mehboob Ali Rind, Shadi Khan Rind Veeho Kohli and Ghulam Shah Bagrani the taste
of water is salty and in village Nazam Khan Rind, Hiji Photo Bhatti water is Sweet.
During the visit, it has been verified that SCF has conducted Water Quality Test from
Government water testing laboritory according to PCRWR standard and social mobilization and
monitoring visits are also done by SCF key project team and PSC.
Community leaders and members of VWMC are of the view that if any conflict arises in water
allocation or any technical problem is found in the water system, they are responsible to resolve
the issue and maintain the water system. It has been notice that communities are quite concious
about this project and are direclty and indirectly involve at every level of this project.
Recommendation
The project has benefited people in the area and providing access to safe drinking water. I
recommend that SCF work can proceed further with:
1. SCF be asked to move further deep/ remote, deprived areas and avoid cosmetic zones
2. Awareness sessions should be made more effective so that the community participation
with SCF may increase and beneficiaries be mobilized to the extent that they can take
care/maintenance of water installations.
3. Avoid delay in implementation by realizing funds on time.
4. Ensure that all the community member financial contribute in the maintenance work of
water structure.