SlideShare a Scribd company logo
1 of 38
Download to read offline
Chapter	
  5:	
  	
  
Project	
  Cost	
  Management	
  
Stevbros	
  Training	
  &	
  Consultancy	
  
www.stevbros.edu.vn	
  
Copyright@STEVBROS	
   Project	
  Management	
  Fundamentals	
   1	
  
PMI,	
  PMP	
  and	
  PMBOK	
  are	
  registered	
  marks	
  of	
  the	
  Project	
  Management	
  Ins9tute,	
  Inc.	
  
Overview	
  
	
  	
   Ini%a%ng	
  
process	
  
group	
  
Planning	
  process	
  
group	
  
Execu%ng	
  
process	
  
group	
  
Monitoring	
  
&	
  
controlling	
  
process	
  
group	
  
Closing	
  
process	
  
group	
  
Project	
  cost	
  
management	
  
	
  	
   •  Plan	
  Cost	
  
Management	
  
•  EsHmate	
  
Costs	
  
•  Determine	
  
Budget	
  
	
  	
   •  Control	
  
Costs	
  
	
  	
  
Copyright@STEVBROS	
   Project	
  Management	
  Fundamentals	
   2	
  
Cost	
  Concepts	
  
Life	
  cycle	
  cosHng	
  
•  Looking	
  at	
  the	
  cost	
  of	
  whole	
  life	
  of	
  the	
  product	
  
(include	
  maintenance)	
  
	
  
Value	
  analysis	
  (value	
  engineering)	
  
•  Looking	
  at	
  less	
  costly	
  way	
  to	
  do	
  the	
  same	
  work	
  
within	
  the	
  same	
  scope	
  
Copyright@STEVBROS	
   Project	
  Management	
  Fundamentals	
   3	
  
Cost	
  Concepts	
  
A	
  Cost	
  can	
  be	
  either	
  variable	
  or	
  fixed:	
  
•  Variable	
   cost:	
   cost	
   that	
   change	
   with	
   the	
   amount	
   of	
  
producHon	
   or	
   the	
   amount	
   of	
   work.	
   Ex.,	
   cost	
   of	
   material,	
  
supplies,	
  wages…	
  
•  Fixed	
  cost:	
  cost	
  that	
  do	
  not	
  change	
  as	
  producHon	
  changes.	
  
Ex.,	
  set-­‐up,	
  rental…	
  
A	
  Cost	
  can	
  be	
  either	
  direct	
  or	
  indirect:	
  
•  Direct	
  cost:	
  cost	
  that	
  are	
  directly	
  aVributable	
  to	
  the	
  work	
  on	
  
the	
  project,	
  Ex.,	
  team	
  travel,	
  team	
  wages,	
  recogniHon,	
  and	
  
costs	
  of	
  material	
  used	
  on	
  the	
  project…	
  
•  Indirect	
   cost:	
   overhead	
   items	
   or	
   costs	
   incurred	
   for	
   the	
  
benefit	
  of	
  more	
  than	
  one	
  project,	
  Ex.,	
  taxes,	
  fringe	
  benefits	
  
and	
  janitorial	
  services	
  
Copyright@STEVBROS	
   Project	
  Management	
  Fundamentals	
   4	
  
Plan	
  cost	
  
management	
  
•  The	
   process	
   that	
   establishes	
   the	
   policies,	
   procedures,	
   and	
  
documentaHon	
   for	
   planning,	
   managing,	
   expending,	
   and	
  
controlling	
   project	
   costs.	
   The	
   key	
   benefit	
   of	
   this	
   process	
   is	
  
that	
   it	
   provides	
   guidance	
   and	
   direcHon	
   on	
   how	
   the	
   project	
  
costs	
  will	
  be	
  managed	
  throughout	
  the	
  project.	
  
Copyright@STEVBROS	
   Project	
  Management	
  Fundamentals	
   5	
  
A	
  Guide	
  to	
  the	
  Project	
  Management	
  Body	
  of	
  Knowledge,	
  FiBh	
  Edi9on	
  (PMBOK®	
  Guide)	
  ©2013	
  Project	
  Management	
  
Ins9tute,	
  Inc.	
  	
  All	
  Rights	
  Reserved.	
  	
  Figure	
  7-­‐2	
  Page	
  195.	
  
Inputs	
  
1.  Project	
  Management	
  Plan	
  	
  
•  contains	
   informaHon	
   used	
   to	
   develop	
   the	
   cost	
   management	
  
plan:	
  Scope	
  baseline,	
  Schedule	
  baseline,	
  Other	
  informaHon.	
  
2.  Project	
  Charter	
  	
  
•  provides	
  the	
  summary	
  budget	
  from	
  which	
  the	
  detailed	
  project	
  
costs	
  are	
  developed.	
  	
  
3.  Enterprise	
  Environmental	
  Factors	
  	
  
•  organizaHonal	
   culture	
   and	
   structure	
   can	
   all	
   influence	
   cost	
  
management;	
   market	
   condiHons;	
   currency	
   exchange	
   rates;	
  
published	
  commercial	
  informaHon;	
  PMIS.	
  
4.  Organiza%onal	
  Process	
  Assets	
  	
  
•  financial	
  controls	
  procedures;	
  historical	
  informaHon	
  and	
  lessons	
  
learned	
   knowledge	
   bases;	
   financial	
   databases;	
   and	
   exisHng	
  
formal	
   and	
   informal	
   cost	
   esHmaHng	
   and	
   budgeHng-­‐related	
  
policies,	
  procedures,	
  and	
  guidelines.	
  	
  
Copyright@STEVBROS	
   Project	
  Management	
  Fundamentals	
   6	
  
Tools	
  and	
  
techniques	
  
1.  Expert	
  Judgment	
  	
  
•  guided	
  by	
  historical	
  informaHon,	
  provides	
  valuable	
  insight	
  about	
  
the	
  environment	
  and	
  informaHon	
  from	
  prior	
  similar	
  projects.	
  
2.  Analy%cal	
  Techniques	
  	
  
•  involve	
   choosing	
   strategic	
   opHons	
   to	
   fund	
   the	
   project	
   such	
   as:	
  
self-­‐funding,	
  funding	
  with	
  equity,	
  or	
  funding	
  with	
  debt.	
  The	
  cost	
  
management	
   plan	
   may	
   also	
   detail	
   ways	
   to	
   finance	
   project	
  
resources	
  such	
  as	
  making,	
  purchasing,	
  renHng,	
  or	
  leasing.	
  
•  techniques	
   may	
   include:	
   payback	
   period,	
   return	
   on	
   investment,	
  
internal	
   rate	
   of	
   return,	
   discounted	
   cash	
   flow,	
   and	
   net	
   present	
  
value.	
  	
  
3.  Mee%ngs	
  	
  
•  aVendees	
   at	
   these	
   meeHngs	
   may	
   include	
   the	
   project	
   manager,	
  
the	
   project	
   sponsor,	
   selected	
   project	
   team	
   members,	
   selected	
  
stakeholders,	
   anyone	
   with	
   responsibility	
   for	
   project	
   costs,	
   and	
  
others	
  as	
  needed.	
  	
  
Copyright@STEVBROS	
   Project	
  Management	
  Fundamentals	
   7	
  
Outputs	
  
1.  Cost	
  Management	
  Plan	
  
•  describes	
   how	
   the	
   project	
   costs	
   will	
   be	
   planned,	
   structured,	
   and	
  
controlled.	
  the	
  cost	
  management	
  plan	
  can	
  establish	
  the	
  following:	
  	
  
ü units	
  of	
  measure.	
  	
  
ü Level	
   of	
   precision:	
   the	
   degree	
   to	
   which	
   acHvity	
   cost	
   esHmates	
   will	
   be	
  
rounded	
   up	
   or	
   down	
   (e.g.,	
   US$100.49	
   to	
   US$100,	
   or	
   US$995.59	
   to	
   US
$1,000)	
  
ü Level	
  of	
  accuracy:	
  the	
  acceptable	
  range	
  (e.g.,	
  ±10%)	
  
ü OrganizaHonal	
  procedures	
  links:	
  the	
  WBS	
  provides	
  the	
  framework	
  for	
  the	
  
cost	
   management	
   plan,	
   allowing	
   for	
   consistency	
   with	
   the	
   esHmates,	
  
budgets,	
  and	
  control	
  of	
  costs.	
  
ü control	
  thresholds.	
  
ü Rules	
  of	
  performance	
  measurement:	
  EVM	
  rules	
  of	
  performance	
  
ü ReporHng	
  formats	
  
ü Process	
  descripHons	
  
ü AddiHonal	
  details	
  
Copyright@STEVBROS	
   Project	
  Management	
  Fundamentals	
   8	
  
EsHmate	
  costs	
  
•  The	
  process	
  of	
  developing	
  an	
  approximaHon	
  of	
  the	
  monetary	
  
resources	
   needed	
   to	
   complete	
   project	
   acHviHes.	
   The	
   key	
  
benefit	
   of	
   this	
   process	
   is	
   that	
   it	
   determines	
   the	
   amount	
   of	
  
cost	
  required	
  to	
  complete	
  project	
  work.	
  
Copyright@STEVBROS	
   Project	
  Management	
  Fundamentals	
   9	
  
A	
  Guide	
  to	
  the	
  Project	
  Management	
  Body	
  of	
  Knowledge,	
  FiBh	
  Edi9on	
  (PMBOK®	
  Guide)	
  ©2013	
  Project	
  Management	
  
Ins9tute,	
  Inc.	
  	
  All	
  Rights	
  Reserved.	
  	
  Figure	
  7-­‐4	
  Page	
  200.	
  
EsHmaHng	
  	
  
techniques	
  
•  The	
  accuracy	
  of	
  a	
  project	
  esHmate	
  will	
  increase	
  
as	
  the	
  project	
  progresses	
  through	
  the	
  project	
  life	
  
cycle.	
   For	
   example,	
   a	
   project	
   in	
   the	
   iniHaHon	
  
phase	
   may	
   have	
   a	
   rough	
   order	
   of	
   magnitude	
  
(ROM)	
   esHmate	
   in	
   the	
   range	
   of	
   −25%	
   to	
   +75%.	
  
Later	
   in	
   the	
   project,	
   as	
   more	
   informaHon	
   is	
  
known,	
   definiHve	
   esHmates	
   could	
   narrow	
   the	
  
range	
  of	
  accuracy	
  to	
  -­‐5%	
  to	
  +10%.	
  
•  EsHmaHng	
  techniques:	
  analogous	
  esHmaHng	
  (top	
  
down	
  esHmaHng),	
  parametric	
  esHmaHng,	
  boVom	
  
up	
  esHmaHng,	
  three	
  point	
  esHmaHng.	
  
Copyright@STEVBROS	
   Project	
  Management	
  Fundamentals	
   10	
  
Inputs(1/2)	
  
1.  Cost	
  Management	
  Plan	
  
•  defines	
  how	
  project	
  costs	
  will	
  be	
  managed	
  and	
  controlled.	
  	
  
2.  Human	
  Resource	
  Management	
  Plan	
  	
  
•  provides	
   project	
   staffing	
   aVributes,	
   personnel	
   rates,	
   and	
  
related	
  rewards/recogniHon,	
  which	
  are	
  necessary	
  components	
  
for	
  developing	
  the	
  project	
  cost	
  esHmates.	
  
3.  Scope	
  Baseline	
  	
  
•  addiHonal	
   informaHon	
   that	
   may	
   be	
   found	
   in	
   the	
   scope	
  
baseline	
   with	
   contractual	
   and	
   legal	
   implicaHons,	
   such	
   as	
  
health,	
   safety,	
   security,	
   performance,	
   environmental,	
  
insurance,	
   intellectual	
   property	
   rights,	
   licenses,	
   and	
   permits.	
  
All	
  of	
  this	
  informaHon	
  should	
  be	
  considered	
  when	
  developing	
  
the	
  cost	
  esHmates.	
  	
  
Copyright@STEVBROS	
   Project	
  Management	
  Fundamentals	
   11	
  
Inputs(2/2)	
  
4.  Project	
  Schedule	
  	
  
•  the	
  type	
  and	
  quanHty	
  of	
  resources	
  and	
  the	
  amount	
  of	
  Hme	
  which	
  those	
  
resources	
   are	
   applied	
   to	
   complete	
   the	
   work	
   of	
   the	
   project	
   are	
   major	
  
factors	
   in	
   determining	
   the	
   project	
   cost.	
   Schedule	
   acHvity	
   resources	
   and	
  
their	
  respecHve	
  duraHons	
  are	
  used	
  as	
  key	
  inputs	
  to	
  this	
  process.	
  
5.  Risk	
  Register	
  	
  
•  as	
  a	
  general	
  rule,	
  when	
  the	
  project	
  experiences	
  a	
  negaHve	
  risk	
  event,	
  the	
  
near-­‐term	
   cost	
   of	
   the	
   project	
   will	
   usually	
   increase,	
   and	
   there	
   will	
  
someHmes	
  be	
  a	
  delay	
  in	
  the	
  project	
  schedule.	
  In	
  a	
  similar	
  way,	
  the	
  project	
  
team	
  should	
  be	
  sensiHve	
  to	
  potenHal	
  opportuniHes	
  that	
  can	
  benefit	
  the	
  
business	
   either	
   by	
   directly	
   reducing	
   acHvity	
   costs	
   or	
   by	
   acceleraHng	
   the	
  
schedule.	
  
6.  Enterprise	
  Environmental	
  Factors	
  	
  
•  market	
  condiHons,	
  published	
  commercial	
  informaHon.	
  	
  
7.  Organiza%onal	
  Process	
  Assets	
  	
  
•  cost	
  esHmaHng	
  policies,	
  cost	
  esHmaHng	
  templates,	
  historical	
  informaHon,	
  
and	
  lessons	
  learned.	
  	
  
Copyright@STEVBROS	
   Project	
  Management	
  Fundamentals	
   12	
  
Tools	
  and	
  
techniques(1/3)	
  
1.  Expert	
  Judgment	
  	
  
•  guided	
   by	
   historical	
   informaHon,	
   provides	
   valuable	
   insight	
   about	
  
the	
  environment	
  and	
  informaHon	
  from	
  prior	
  similar	
  projects.	
  
2.  Analogous	
  Es%ma%ng	
  	
  
•  uses	
   the	
   values	
   such	
   as	
   scope,	
   cost,	
   budget,	
   and	
   duraHon	
   or	
  
measures	
   of	
   scale	
   such	
   as	
   size,	
   weight,	
   and	
   complexity	
   from	
   a	
  
previous,	
   similar	
   project	
   as	
   the	
   basis	
   for	
   esHmaHng	
   the	
   same	
  
parameter	
  or	
  measurement	
  for	
  a	
  current	
  project.	
  
3.  Parametric	
  Es%ma%ng	
  	
  
•  uses	
  a	
  staHsHcal	
  relaHonship	
  between	
  relevant	
  historical	
  data	
  and	
  
other	
  variables	
  (e.g.,	
  square	
  footage	
  in	
  construcHon)	
  to	
  calculate	
  a	
  
cost	
  esHmate	
  for	
  project	
  work.	
  This	
  technique	
  can	
  produce	
  higher	
  
levels	
   of	
   accuracy	
   depending	
   upon	
   the	
   sophisHcaHon	
   and	
  
underlying	
  data	
  built	
  into	
  the	
  model.	
  
Copyright@STEVBROS	
   Project	
  Management	
  Fundamentals	
   13	
  
Tools	
  and	
  
techniques(2/3)	
  
4.  BoVom-­‐Up	
  Es%ma%ng	
  	
  
•  is	
  a	
  method	
  of	
  esHmaHng	
  a	
  component	
  of	
  work.	
  The	
  cost	
  of	
  individual	
  
work	
  packages	
  or	
  acHviHes	
  is	
  esHmated	
  to	
  the	
  greatest	
  level	
  of	
  specified	
  
detail.	
   The	
   detailed	
   cost	
   is	
   then	
   summarized	
   or	
   “rolled	
   up”	
   to	
   higher	
  
levels	
  for	
  subsequent	
  reporHng	
  and	
  tracking	
  purposes.	
  
5.  Three-­‐Point	
  Es%ma%ng	
  	
  
•  Most	
   likely	
   (cM).	
   The	
   cost	
   of	
   the	
   acHvity,	
   based	
   on	
   realisHc	
   effort	
  
assessment	
  for	
  the	
  required	
  work	
  and	
  any	
  predicted	
  expenses.	
  	
  
•  OpHmisHc	
   (cO).	
   The	
   acHvity	
   cost	
   based	
   on	
   analysis	
   of	
   the	
   best-­‐case	
  
scenario	
  for	
  the	
  acHvity.	
  	
  
•  PessimisHc	
   (cP).	
   The	
   acHvity	
   cost	
   based	
   on	
   analysis	
   of	
   the	
   worst-­‐case	
  
scenario	
  for	
  the	
  acHvity.	
  	
  
•  Two	
  commonly	
  used	
  formulas	
  are	
  triangular	
  and	
  beta	
  distribuHons:	
  
ü Triangular	
  DistribuHon.	
  cE	
  =	
  (cO	
  +	
  cM	
  +	
  cP)	
  /	
  3	
  	
  
ü Beta	
  DistribuHon	
  (from	
  a	
  tradiHonal	
  PERT	
  analysis).	
  cE	
  =	
  (cO	
  +	
  4cM	
  +	
  cP)	
  /	
  6	
  	
  
Copyright@STEVBROS	
   Project	
  Management	
  Fundamentals	
   14	
  
Tools	
  and	
  
techniques(3/3)	
  
6.  Reserve	
  Analysis	
  	
  
•  Cost	
   esHmates	
   may	
   include	
   conHngency	
   reserves	
   (someHmes	
   called	
  
conHngency	
  allowances)	
  to	
  account	
  for	
  cost	
  uncertainty.	
  
7.  Cost	
  of	
  Quality	
  (COQ)	
  (details	
  in	
  next	
  slide)	
  
8.  Project	
  Management	
  So^ware	
  	
  
9.  Vendor	
  Bid	
  Analysis	
  	
  
•  include	
  analysis	
  of	
  what	
  the	
  project	
  should	
  cost,	
  based	
  on	
  the	
  responsive	
  
bids	
   from	
   qualified	
   vendors.	
   When	
   projects	
   are	
   awarded	
   to	
   a	
   vendor	
  
under	
   compeHHve	
   processes,	
   addiHonal	
   cost	
   esHmaHng	
   work	
   may	
   be	
  
required	
   of	
   the	
   project	
   team	
   to	
   examine	
   the	
   price	
   of	
   individual	
  
deliverables	
   and	
   to	
   derive	
   a	
   cost	
   that	
   supports	
   the	
   final	
   total	
   project	
  
cost.	
  
10.  Group	
  Decision-­‐Making	
  Techniques	
  
•  team-­‐based	
  approaches,	
  such	
  as	
  brainstorming,	
  the	
  Delphi	
  or	
  nominal	
  
group	
   techniques,	
   are	
   useful	
   for	
   engaging	
   team	
   members	
   to	
   improve	
  
esHmate	
  accuracy	
  and	
  commitment	
  to	
  the	
  emerging	
  esHmates.	
  	
  
Copyright@STEVBROS	
   Project	
  Management	
  Fundamentals	
   15	
  
Cost	
  of	
  quality	
  
Copyright@STEVBROS	
   Project	
  Management	
  Fundamentals	
   16	
  
A	
  Guide	
  to	
  the	
  Project	
  Management	
  Body	
  of	
  Knowledge,	
  FiBh	
  Edi9on	
  (PMBOK®	
  Guide)	
  ©2013	
  Project	
  Management	
  
Ins9tute,	
  Inc.	
  	
  All	
  Rights	
  Reserved.	
  	
  Figure	
  8-­‐5	
  Page	
  235.	
  
Outputs	
  
1.  Ac%vity	
  Cost	
  Es%mates	
  
•  Direct	
  Cost:	
  costs	
  that	
  are	
  directly	
  aVribute	
  to	
  work	
  on	
  the	
  project.	
  eg.	
  
training	
  cost,	
  travel	
  cost,	
  wages,	
  cost	
  of	
  material	
  used	
  in	
  the	
  project,	
  etc	
  
•  Indirect	
  Cost:	
  overhead	
  items	
  or	
  costs	
  incurred	
  for	
  the	
  benefit	
  of	
  more	
  
than	
  one	
  project.	
  eg.	
  taxes,	
  fringe	
  benefits,	
  etc	
  
•  Variable	
   Cost:	
   change	
   with	
   the	
   amount	
   of	
   producHon/work.	
   e.g.	
   material,	
  
supplies,	
  wages	
  
•  Fixed	
  Cost:	
  do	
  not	
  change	
  as	
  producHon	
  change.	
  e.g.	
  set-­‐up,	
  rental	
  
2.  Basis	
  of	
  Es%mates	
  	
  
•  DocumentaHon	
  of	
  the	
  basis	
  of	
  the	
  esHmate	
  (i.e.,	
  how	
  it	
  was	
  developed),	
  	
  
•  DocumentaHon	
  of	
  all	
  assumpHons	
  made,	
  	
  
•  DocumentaHon	
  of	
  any	
  known	
  constraints,	
  	
  
•  IndicaHon	
   of	
   the	
   range	
   of	
   possible	
   esHmates	
   (e.g.,	
   €10,000	
   (±10%)	
   to	
  
indicate	
  that	
  the	
  item	
  is	
  expected	
  to	
  cost	
  between	
  a	
  range	
  of	
  values),	
  and	
  	
  
•  IndicaHon	
  of	
  the	
  confidence	
  level	
  of	
  the	
  final	
  esHmate.	
  	
  
3.  Project	
  Documents	
  Updates	
  	
  
Copyright@STEVBROS	
   Project	
  Management	
  Fundamentals	
   17	
  
Determine	
  budget	
  
•  The	
  process	
  of	
  aggregaHng	
  the	
  esHmated	
  costs	
  of	
  individual	
  
acHviHes	
   or	
   work	
   packages	
   to	
   establish	
   an	
   authorized	
   cost	
  
baseline.	
  The	
  key	
  benefit	
  of	
  this	
  process	
  is	
  that	
  it	
  determines	
  
the	
  cost	
  baseline	
  against	
  which	
  project	
  performance	
  can	
  be	
  
monitored	
  and	
  controlled.	
  
Copyright@STEVBROS	
   Project	
  Management	
  Fundamentals	
   18	
  
A	
  Guide	
  to	
  the	
  Project	
  Management	
  Body	
  of	
  Knowledge,	
  FiBh	
  Edi9on	
  (PMBOK®	
  Guide)	
  ©2013	
  Project	
  Management	
  
Ins9tute,	
  Inc.	
  	
  All	
  Rights	
  Reserved.	
  	
  Figure	
  7-­‐6	
  Page	
  208.	
  
Inputs(1/2)	
  
1.  Cost	
  Management	
  Plan	
  
•  describes	
  how	
  the	
  project	
  costs	
  will	
  be	
  managed	
  and	
  controlled.	
  	
  	
  
2.  Scope	
  Baseline	
  	
  
•  includes	
  project	
  scope	
  statement,	
  WBS,	
  WBS	
  dicHonary.	
  
3.  Ac%vity	
  Cost	
  Es%mates	
  	
  
•  cost	
   esHmates	
   for	
   each	
   acHvity	
   within	
   a	
   work	
   package	
   are	
  
aggregated	
  to	
  obtain	
  a	
  cost	
  esHmate	
  for	
  each	
  work	
  package.	
  	
  
4.  Basis	
  of	
  Es%mates	
  	
  
•  supporHng	
  detail	
  for	
  cost	
  esHmates	
  contained	
  in	
  the	
  basis	
  for	
  
esHmates	
  should	
  specify	
  any	
  basic	
  assumpHons	
  dealing	
  with	
  the	
  
inclusion	
   or	
   exclusion	
   of	
   indirect	
   or	
   other	
   costs	
   in	
   the	
   project	
  
budget.	
  	
  
Copyright@STEVBROS	
   Project	
  Management	
  Fundamentals	
   19	
  
Inputs(2/2)	
  
5.  Project	
  Schedule	
  
•  This	
   informaHon	
   can	
   be	
   used	
   to	
   aggregate	
   costs	
   to	
   the	
   calendar	
  
periods	
  in	
  which	
  the	
  costs	
  are	
  planned	
  to	
  be	
  incurred.	
  	
  
6.  Resource	
  Calendars	
  	
  
7.  Risk	
  Register	
  	
  
•  The	
  risk	
  register	
  should	
  be	
  reviewed	
  to	
  consider	
  how	
  to	
  aggregate	
  
the	
  risk	
  response	
  costs.	
  
8.  Agreements	
  	
  
•  Applicable	
   agreement	
   informaHon	
   and	
   costs	
   relaHng	
   to	
   products,	
  
services,	
  or	
  results	
  that	
  have	
  been	
  or	
  will	
  be	
  purchased	
  are	
  included	
  
when	
  determining	
  the	
  budget.	
  	
  
9.  Organiza%onal	
  Process	
  Assets	
  
•  ExisHng	
   formal	
   and	
   informal	
   cost	
   budgeHng-­‐related	
   policies,	
  
procedures,	
   and	
   guidelines;	
   cost	
   budgeHng	
   tools;	
   and	
   reporHng	
  
methods.	
  
Copyright@STEVBROS	
   Project	
  Management	
  Fundamentals	
   20	
  
Tools	
  and	
  
techniques	
  
1.  Cost	
  Aggrega%on	
  	
  
•  Cost	
  esHmates	
  are	
  aggregated	
  by	
  work	
  packages	
  in	
  accordance	
  with	
  the	
  WBS.	
  The	
  
work	
  package	
  cost	
  esHmates	
  are	
  then	
  aggregated	
  for	
  the	
  higher	
  component	
  levels	
  
of	
  the	
  WBS	
  (such	
  as	
  control	
  accounts)	
  and	
  ulHmately	
  for	
  the	
  enHre	
  project.	
  	
  
2.  Reserve	
  Analysis	
  	
  
•  Budget	
   reserve	
   analysis	
   can	
   establish	
   both	
   the	
   conHngency	
   reserves	
   and	
   the	
  
management	
  reserves	
  for	
  the	
  project.	
  
3.  Expert	
  Judgment	
  	
  
•  guided	
  by	
  experience	
  in	
  an	
  applicaHon	
  area,	
  knowledge	
  area,	
  discipline,	
  industry,	
  or	
  
similar	
  project,	
  aids	
  in	
  determining	
  the	
  budget.	
  
4.  Historical	
  Rela%onships	
  	
  
•  Any	
   historical	
   relaHonships	
   that	
   result	
   in	
   parametric	
   esHmates	
   or	
   analogous	
  
esHmates	
   involve	
   the	
   use	
   of	
   project	
   characterisHcs	
   (parameters)	
   to	
   develop	
  
mathemaHcal	
  models	
  to	
  predict	
  total	
  project	
  costs.	
  
5.  Funding	
  Limit	
  Reconcilia%on	
  
•  The	
   expenditure	
   of	
   funds	
   should	
   be	
   reconciled	
   with	
   any	
   funding	
   limits	
   on	
   the	
  
commitment	
  of	
  funds	
  for	
  the	
  project.	
  A	
  variance	
  between	
  the	
  funding	
  limits	
  and	
  the	
  
planned	
  expenditures	
  will	
  someHmes	
  necessitate	
  the	
  rescheduling	
  of	
  work	
  to	
  level	
  
out	
  the	
  rate	
  of	
  expenditures.	
  
Copyright@STEVBROS	
   Project	
  Management	
  Fundamentals	
   21	
  
Outputs	
  
1.  Cost	
  Baseline	
  
•  is	
  the	
  approved	
  version	
  of	
  the	
  Hme-­‐phased	
  project	
  budget,	
  
excluding	
  any	
  management	
  reserves	
  (details	
  at	
  next	
  slide)	
  
2.  Project	
  Funding	
  Requirements	
  	
  
•  total	
   funding	
   requirements	
   and	
   periodic	
   funding	
  
requirements	
   (e.g.,	
   quarterly,	
   annually)	
   are	
   derived	
   from	
  
the	
  cost	
  baseline.	
  The	
  cost	
  baseline	
  will	
  include	
  projected	
  
expenditures	
  plus	
  anHcipated	
  liabiliHes.	
  	
  
•  the	
   total	
   funds	
   required	
   are	
   those	
   included	
   in	
   the	
   cost	
  
baseline,	
  plus	
  management	
  reserves,	
  if	
  any.	
  	
  
3.  Project	
  Documents	
  Updates	
  	
  
•  such	
   as	
   risk	
   register,	
   acHvity	
   cost	
   esHmates,	
   and	
   project	
  
schedule.	
  	
  
Copyright@STEVBROS	
   Project	
  Management	
  Fundamentals	
   22	
  
Project	
  budget	
  
Copyright@STEVBROS	
   Project	
  Management	
  Fundamentals	
   23	
  
A	
  Guide	
  to	
  the	
  Project	
  Management	
  Body	
  of	
  Knowledge,	
  FiBh	
  Edi9on	
  (PMBOK®	
  Guide)	
  ©2013	
  Project	
  Management	
  
Ins9tute,	
  Inc.	
  	
  All	
  Rights	
  Reserved.	
  	
  Figure	
  7-­‐8	
  Page	
  213.	
  
Project	
  budget	
  
Copyright@STEVBROS	
   Project	
  Management	
  Fundamentals	
   24	
  
A	
  Guide	
  to	
  the	
  Project	
  Management	
  Body	
  of	
  Knowledge,	
  FiBh	
  Edi9on	
  (PMBOK®	
  Guide)	
  ©2013	
  Project	
  Management	
  
Ins9tute,	
  Inc.	
  	
  All	
  Rights	
  Reserved.	
  	
  Figure	
  7-­‐9	
  Page	
  214.	
  
Control	
  cost	
  
•  The	
  process	
  of	
  monitoring	
  the	
  status	
  of	
  the	
  project	
  to	
  update	
  
the	
  project	
  costs	
  and	
  managing	
  changes	
  to	
  the	
  cost	
  baseline.	
  
The	
  key	
  benefit	
  of	
  this	
  process	
  is	
  that	
  it	
  provides	
  the	
  means	
  to	
  
recognize	
  variance	
  from	
  the	
  plan	
  in	
  order	
  to	
  take	
  correcHve	
  
acHon	
  and	
  minimize	
  risk.	
  	
  
Copyright@STEVBROS	
   Project	
  Management	
  Fundamentals	
   25	
  
A	
  Guide	
  to	
  the	
  Project	
  Management	
  Body	
  of	
  Knowledge,	
  FiBh	
  Edi9on	
  (PMBOK®	
  Guide)	
  ©2013	
  Project	
  Management	
  
Ins9tute,	
  Inc.	
  	
  All	
  Rights	
  Reserved.	
  	
  Figure	
  7-­‐10	
  Page	
  215.	
  
Inputs	
  
1.  Project	
  Management	
  Plan	
  	
  
•  contains	
  cost	
  baseline	
  and	
  cost	
  management	
  plan.	
  
2.  Project	
  Funding	
  Requirements	
  	
  
•  requirements	
   include	
   projected	
   expenditures	
   plus	
   anHcipated	
  
liabiliHes.	
  	
  
3.  Work	
  Performance	
  Data	
  
•  data	
  includes	
  informaHon	
  about	
  project	
  progress,	
  such	
  as	
  which	
  
acHviHes	
   have	
   started,	
   their	
   progress,	
   and	
   which	
   deliverables	
  
have	
   finished.	
   InformaHon	
   also	
   includes	
   costs	
   that	
   have	
   been	
  
authorized	
  and	
  incurred.	
  	
  
4.  OrganizaHonal	
  Process	
  Assets	
  	
  
•  include	
   exisHng	
   formal	
   and	
   informal	
   cost	
   control-­‐related	
  
policies,	
   procedures,	
   and	
   guidelines;	
   cost	
   control	
   tools;	
   and	
  
monitoring	
  and	
  reporHng	
  methods	
  to	
  be	
  used.	
  	
  
Copyright@STEVBROS	
   Project	
  Management	
  Fundamentals	
   26	
  
Tools	
  and	
  
techniques	
  
1.  Earned	
  Value	
  Management	
  (next	
  slides)	
  
2.  Forecas%ng	
  (next	
  slides)	
  
3.  To-­‐Complete	
  Performance	
  Index	
  (TCPI)	
  (next	
  slides)	
  
4.  Performance	
  Reviews	
  (next	
  slides)	
  
5.  Project	
  Management	
  So^ware	
  	
  
6.  Reserve	
  Analysis	
  	
  
•  During	
  cost	
  control,	
  reserve	
  analysis	
  is	
  used	
  to	
  monitor	
  the	
  
status	
  of	
  conHngency	
  and	
  management	
  reserves	
  	
  
for	
  the	
  project	
  to	
  determine	
  if	
  these	
  reserves	
  are	
  sHll	
  
needed	
  or	
  if	
  addiHonal	
  reserves	
  need	
  to	
  be	
  requested.	
  	
  
Copyright@STEVBROS	
   Project	
  Management	
  Fundamentals	
   27	
  
EVM	
  
•  Earned	
   Value	
   Management	
   (EVM):	
   is	
   the	
   most	
  
common	
   tool	
   which	
   help	
   project	
   managers	
  
measure	
   project	
   performance	
   and	
   determine	
  
where	
   the	
   project	
   stands	
   in	
   relaHon	
   to	
   the	
  
budget	
  and	
  the	
  schedule	
  at	
  a	
  point	
  in	
  Hme.	
  
•  Work	
  performance	
  informaHon:	
  BAC,	
  PV,	
  EV,	
  AC.	
  
•  Work	
   performance	
   measurement:	
   CPI,	
   CV,	
   SPI,	
  
SV.	
  
•  ForecasHng:	
  ETC,	
  EAC.	
  
•  To-­‐Complete	
  Performance	
  Index:	
  TCPI.	
  
Copyright@STEVBROS	
   Project	
  Management	
  Fundamentals	
   28	
  
EVM	
  
•  Work	
  performance	
  informaHon:	
  
o BAC-­‐	
  Budget	
  At	
  CompleHon	
  (project	
  budget).	
  
o PV	
  -­‐	
  Planned	
  Value	
  (value	
  of	
  work	
  schedule):	
  
	
  PV	
  =	
  BAC	
  *	
  planned	
  %	
  complete.	
  
o EV	
  -­‐	
  Earned	
  Value	
  (value	
  of	
  work	
  performed):	
  
	
  EV	
  =BAC	
  *	
  actual	
  %	
  complete.	
  
o AC—Actual	
  Cost	
  (spent	
  cost).	
  
Copyright@STEVBROS	
   Project	
  Management	
  Fundamentals	
   29	
  
EVM	
  
•  Work	
  performance	
  measurement:	
  
o  SPI—Schedule	
  Performance	
  Index	
  =	
  EV/PV.	
  	
  
	
  If	
  SPI	
  	
  >	
  1,	
  you’re	
  ahead	
  of	
  schedule.	
  If	
  SPI	
  <	
  1,	
  you’re	
  behind	
  schedule.	
  
o  SV—Schedule	
  Variance	
  =	
  EV-­‐PV.	
  	
  
	
  If	
  SV	
  >	
  0,	
  it	
  tells	
  you	
  how	
  many	
  dollars	
  you’re	
  ahead.	
  If	
  SV	
  <	
  0,	
  it	
  tells	
  
you	
  how	
  many	
  dollars	
  you’re	
  behind.	
  
o  CPI—Cost	
  Performance	
  Index	
  =	
  EV/AC.	
  	
  
	
  If	
  CPI	
  	
  >	
  1,	
  you’re	
  under	
  budget.	
  If	
  CPI	
  <	
  1,	
  you’re	
  over	
  budget.	
  
o  CV—Cost	
  Variance	
  =	
  EV-­‐AC.	
  	
  	
  
	
  If	
  CV	
  >	
  0,	
  it	
  tells	
  you	
  how	
  many	
  dollars	
  you’re	
  above.	
  If	
  CV	
  <	
  0,	
  it	
  tells	
  
you	
  how	
  many	
  dollars	
  you’re	
  below.	
  
Copyright@STEVBROS	
   Project	
  Management	
  Fundamentals	
   30	
  
EVM	
  
Copyright@STEVBROS	
   Project	
  Management	
  Fundamentals	
   31	
  
A	
  Guide	
  to	
  the	
  Project	
  Management	
  Body	
  of	
  Knowledge,	
  FiBh	
  Edi9on	
  (PMBOK®	
  Guide)	
  ©2013	
  Project	
  Management	
  
Ins9tute,	
  Inc.	
  	
  All	
  Rights	
  Reserved.	
  	
  Figure	
  7-­‐12	
  Page	
  219.	
  
EVM	
  
•  ForecasHng:	
  
o EsHmate	
  to	
  Complete	
  (ETC),	
  which	
  tells	
  you	
  how	
  
much	
  more	
  money	
  you’ll	
  probably	
  spend	
  on	
  your	
  
project.	
  
o EsHmate	
   at	
   CompleHon	
   (EAC)	
   is	
   used	
   to	
   predict	
  
what	
   your	
   project	
   will	
   actually	
   cost	
   when	
   it’s	
  
complete.	
  
o EAC	
  =	
  AC	
  +	
  boVom-­‐up	
  ETC	
  
	
  
Copyright@STEVBROS	
   Project	
  Management	
  Fundamentals	
   32	
  
EVM	
  
•  ForecasHng:	
  
o  EAC	
  forecast	
  for	
  ETC	
  work	
  performed	
  at	
  the	
  budgeted	
  rate.	
  This	
  EAC	
  
method	
   accepts	
   the	
   actual	
   project	
   performance	
   to	
   date	
   (whether	
  
favorable	
   or	
   unfavorable)	
   as	
   represented	
   by	
   the	
   actual	
   costs,	
   and	
  
predicts	
  that	
  all	
  future	
  ETC	
  work	
  will	
  be	
  accomplished	
  at	
  the	
  budgeted	
  
rate.	
  EquaHon:	
  EAC	
  =	
  AC	
  +	
  (BAC	
  -­‐	
  EV)	
  	
  
o  EAC	
  forecast	
  for	
  ETC	
  work	
  performed	
  at	
  the	
  present	
  CPI.	
  This	
  method	
  
assumes	
  what	
  the	
  project	
  has	
  experienced	
  to	
  date	
  can	
  be	
  expected	
  to	
  
conHnue	
  in	
  the	
  future.	
  The	
  ETC	
  work	
  is	
  assumed	
  to	
  be	
  performed	
  at	
  
the	
  same	
  cumulaHve	
  cost	
  performance	
  index	
  (CPI)	
  as	
  that	
  incurred	
  by	
  
the	
  project	
  to	
  date.	
  EquaHon:	
  EAC	
  =	
  BAC	
  /	
  CPI	
  	
  
o  EAC	
  forecast	
  for	
  ETC	
  work	
  considering	
  both	
  SPI	
  and	
  CPI	
  factors.	
  In	
  
this	
  forecast,	
  the	
  ETC	
  work	
  will	
  be	
  performed	
  at	
  an	
  efficiency	
  rate	
  that	
  
considers	
   both	
   the	
   cost	
   and	
   schedule	
   performance	
   indices.	
   This	
  
method	
  is	
  most	
  useful	
  when	
  the	
  project	
  schedule	
  is	
  a	
  factor	
  impacHng	
  
the	
  ETC	
  effort.	
  EquaHon:	
  EAC	
  =	
  AC	
  +	
  [(BAC	
  -­‐	
  EV)	
  /	
  (CPI	
  ×	
  SPI)]	
  	
  
Copyright@STEVBROS	
   Project	
  Management	
  Fundamentals	
   33	
  
EVM	
  
•  To-­‐Complete	
   Performance	
   Index	
   (TCPI):	
   is	
   a	
  
measure	
   of	
   the	
   cost	
   performance	
   that	
   is	
   required	
   to	
   be	
   achieved	
   with	
   the	
  
remaining	
  resources	
  in	
  order	
  to	
  meet	
  a	
  specified	
  management	
  goal,	
  expressed	
  as	
  
the	
  raHo	
  of	
  the	
  cost	
  to	
  finish	
  the	
  outstanding	
  work	
  to	
  the	
  remaining	
  budget.	
  
Copyright@STEVBROS	
   Project	
  Management	
  Fundamentals	
   34	
  
A	
  Guide	
  to	
  the	
  
Project	
  
Management	
  
Body	
  of	
  
Knowledge,	
  FiBh	
  
Edi9on	
  (PMBOK®	
  
Guide)	
  ©2013	
  
Project	
  
Management	
  
Ins9tute,	
  Inc.	
  	
  All	
  
Rights	
  Reserved.	
  	
  
Figure	
  7-­‐13	
  Page	
  
222.	
  
EVM	
  
Copyright@STEVBROS	
   Project	
  Management	
  Fundamentals	
   35	
  
Outputs	
  
1.  Work	
  Performance	
  Informa%on	
  
•  The	
  calculated	
  CV,	
  SV,	
  CPI,	
  SPI,	
  TCPI,	
  and	
  VAC	
  values	
  for	
  WBS	
  
components,	
   in	
   parHcular	
   the	
   work	
   packages	
   and	
   control	
  
accounts,	
  are	
  documented	
  and	
  communicated	
  to	
  stakeholders.	
  
2.  Cost	
  Forecasts	
  
•  EAC	
  value	
  is	
  documented	
  and	
  communicated	
  to	
  stakeholders.	
  
3.  Change	
  Requests	
  
•  analysis	
  of	
  project	
  performance	
  may	
  result	
  in	
  a	
  change	
  request	
  
to	
   the	
   cost	
   baseline	
   or	
   other	
   components	
   of	
   the	
   project	
  
management	
  plan.	
  
4.  Project	
  Management	
  Plan	
  Updates	
  
5.  Project	
  Documents	
  Updates	
  
6.  Organiza%onal	
  Process	
  Assets	
  Updates	
  
Copyright@STEVBROS	
   Project	
  Management	
  Fundamentals	
   36	
  
Summary	
  
•  Cost	
  esHmaHng	
  techniques	
  
•  The	
  accuracy	
  of	
  a	
  project	
  esHmate	
  
•  Project	
  budget	
  vs.	
  cost	
  baseline	
  
•  Management	
  reserve	
  vs.	
  conHngence	
  reserve	
  
•  Earned	
   value	
   management:	
   PV,	
   AC,	
   EV,	
   CPI,	
  
SPI,	
  CV,	
  SV,	
  ETC,	
  EAC,	
  TCPI.	
  
Copyright@STEVBROS	
   Project	
  Management	
  Fundamentals	
   37	
  
QuesHons	
  
for	
  review	
  
Copyright@STEVBROS	
   Project	
  Management	
  Fundamentals	
   38	
  
•  You	
  did	
  the	
  good	
  job	
  at	
  this	
  chapter.	
  	
  Please	
  
complete	
  quesHons	
  for	
  review	
  before	
  moving	
  
to	
  next	
  chapter.	
  

More Related Content

What's hot

Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Agus Suhanto
 
Project Resource Management - PMBOK6
Project Resource Management - PMBOK6Project Resource Management - PMBOK6
Project Resource Management - PMBOK6Agus Suhanto
 
Project Management Foundations Course 101 - Project Management Concepts
Project Management Foundations Course 101 - Project Management ConceptsProject Management Foundations Course 101 - Project Management Concepts
Project Management Foundations Course 101 - Project Management ConceptsThink For A Change
 
Project risk management
Project risk managementProject risk management
Project risk managementDewang Agrawal
 
Project Management and Leadership
Project Management and Leadership Project Management and Leadership
Project Management and Leadership Paul Needleman
 
11. Project Communication Management
11. Project Communication Management11. Project Communication Management
11. Project Communication ManagementBhuWan Khadka
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..pptPedadaSaikumar
 
Project execution and implementation
Project execution and implementationProject execution and implementation
Project execution and implementationDr. Saima Baig
 

What's hot (20)

Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
 
Cost management
Cost managementCost management
Cost management
 
Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Project Cost Management - PMBOK6
Project Cost Management - PMBOK6
 
1. project integration management
1. project integration management1. project integration management
1. project integration management
 
Project cost management
Project cost managementProject cost management
Project cost management
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
PMP_Project Cost Management
PMP_Project Cost ManagementPMP_Project Cost Management
PMP_Project Cost Management
 
Fundamentals of Project Management
Fundamentals of Project ManagementFundamentals of Project Management
Fundamentals of Project Management
 
Project cost management-slides
Project cost management-slidesProject cost management-slides
Project cost management-slides
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Project governance
Project governanceProject governance
Project governance
 
Project Resource Management - PMBOK6
Project Resource Management - PMBOK6Project Resource Management - PMBOK6
Project Resource Management - PMBOK6
 
Project Management Foundations Course 101 - Project Management Concepts
Project Management Foundations Course 101 - Project Management ConceptsProject Management Foundations Course 101 - Project Management Concepts
Project Management Foundations Course 101 - Project Management Concepts
 
Project risk management
Project risk managementProject risk management
Project risk management
 
Project Management and Leadership
Project Management and Leadership Project Management and Leadership
Project Management and Leadership
 
11. Project Communication Management
11. Project Communication Management11. Project Communication Management
11. Project Communication Management
 
Project Resource Management
Project Resource ManagementProject Resource Management
Project Resource Management
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt
 
Project execution and implementation
Project execution and implementationProject execution and implementation
Project execution and implementation
 
Overview of Program Management
Overview of Program ManagementOverview of Program Management
Overview of Program Management
 

Viewers also liked (8)

Project Stakeholder Management
Project Stakeholder ManagementProject Stakeholder Management
Project Stakeholder Management
 
Project Procurement Management
Project Procurement ManagementProject Procurement Management
Project Procurement Management
 
Project Quality Management
Project Quality ManagementProject Quality Management
Project Quality Management
 
Project Integration Management
Project Integration ManagementProject Integration Management
Project Integration Management
 
Project Scope Management
Project Scope ManagementProject Scope Management
Project Scope Management
 
Project Communications Management
Project Communications ManagementProject Communications Management
Project Communications Management
 
Project Human Resource Management
Project Human Resource ManagementProject Human Resource Management
Project Human Resource Management
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 

Similar to Project Cost Management

cost Management V4
cost Management V4cost Management V4
cost Management V4Qussay Karam
 
1 ch 1 Project CM.pptx ggggggggggggggggg
1 ch 1 Project CM.pptx ggggggggggggggggg1 ch 1 Project CM.pptx ggggggggggggggggg
1 ch 1 Project CM.pptx gggggggggggggggggadabotor7
 
Pmp – pmbok 5th edition chapter7 project cost management
Pmp – pmbok 5th edition chapter7 project cost managementPmp – pmbok 5th edition chapter7 project cost management
Pmp – pmbok 5th edition chapter7 project cost managementYudha Pratama, PMP
 
Project Cost Managementttttttttttt .pdf
Project Cost Managementttttttttttt   .pdfProject Cost Managementttttttttttt   .pdf
Project Cost Managementttttttttttt .pdfAliaaAl4
 
Software Project Cost Management and estimation
Software Project Cost Management and estimationSoftware Project Cost Management and estimation
Software Project Cost Management and estimationssuser9d62d6
 
Overall project management
Overall project managementOverall project management
Overall project managementDesh Kapoor
 
Preparing cost estimation
Preparing cost estimationPreparing cost estimation
Preparing cost estimationSomashekar S.M
 
W4N1 Cost Management OverviewCost management is a critical comp.docx
W4N1 Cost Management OverviewCost management is a critical comp.docxW4N1 Cost Management OverviewCost management is a critical comp.docx
W4N1 Cost Management OverviewCost management is a critical comp.docxcelenarouzie
 
PMP Training Project Cost Management Part 1
PMP Training Project Cost Management Part 1PMP Training Project Cost Management Part 1
PMP Training Project Cost Management Part 1Skillogic Solutions
 
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
4. PAE AcFn621Ch-4a Project Alaysis and Selection.pptProfDrAnbalaganChinn
 
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...GlobalSkillup
 
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptsheryl90
 
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptsheryl90
 
PPT1-PROJECT-_-Project-Management.pptx
PPT1-PROJECT-_-Project-Management.pptxPPT1-PROJECT-_-Project-Management.pptx
PPT1-PROJECT-_-Project-Management.pptxSabrinaScott22
 

Similar to Project Cost Management (20)

cost Management V4
cost Management V4cost Management V4
cost Management V4
 
1 ch 1 Project CM.pptx ggggggggggggggggg
1 ch 1 Project CM.pptx ggggggggggggggggg1 ch 1 Project CM.pptx ggggggggggggggggg
1 ch 1 Project CM.pptx ggggggggggggggggg
 
Pmp – pmbok 5th edition chapter7 project cost management
Pmp – pmbok 5th edition chapter7 project cost managementPmp – pmbok 5th edition chapter7 project cost management
Pmp – pmbok 5th edition chapter7 project cost management
 
PMP-Cost Management area
PMP-Cost Management areaPMP-Cost Management area
PMP-Cost Management area
 
Project Cost Managementttttttttttt .pdf
Project Cost Managementttttttttttt   .pdfProject Cost Managementttttttttttt   .pdf
Project Cost Managementttttttttttt .pdf
 
Cost Management PMBOK
Cost Management PMBOKCost Management PMBOK
Cost Management PMBOK
 
Software Project Cost Management and estimation
Software Project Cost Management and estimationSoftware Project Cost Management and estimation
Software Project Cost Management and estimation
 
Overall project management
Overall project managementOverall project management
Overall project management
 
Ibm projectmgmt-1
Ibm  projectmgmt-1Ibm  projectmgmt-1
Ibm projectmgmt-1
 
Preparing cost estimation
Preparing cost estimationPreparing cost estimation
Preparing cost estimation
 
W4N1 Cost Management OverviewCost management is a critical comp.docx
W4N1 Cost Management OverviewCost management is a critical comp.docxW4N1 Cost Management OverviewCost management is a critical comp.docx
W4N1 Cost Management OverviewCost management is a critical comp.docx
 
PME UNIT-3.pptx
PME UNIT-3.pptxPME UNIT-3.pptx
PME UNIT-3.pptx
 
MandC.pdf
MandC.pdfMandC.pdf
MandC.pdf
 
PMP Training Project Cost Management Part 1
PMP Training Project Cost Management Part 1PMP Training Project Cost Management Part 1
PMP Training Project Cost Management Part 1
 
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
 
PMP integration review
PMP integration reviewPMP integration review
PMP integration review
 
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
 
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.ppt
 
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.ppt
 
PPT1-PROJECT-_-Project-Management.pptx
PPT1-PROJECT-_-Project-Management.pptxPPT1-PROJECT-_-Project-Management.pptx
PPT1-PROJECT-_-Project-Management.pptx
 

More from Andersson Lujan Ojeda

Problemas Resueltos de Mecanica de Suelos
Problemas Resueltos de Mecanica de SuelosProblemas Resueltos de Mecanica de Suelos
Problemas Resueltos de Mecanica de SuelosAndersson Lujan Ojeda
 
Ejemplo de Diseño de Presa de Pillones
Ejemplo de Diseño de Presa de PillonesEjemplo de Diseño de Presa de Pillones
Ejemplo de Diseño de Presa de PillonesAndersson Lujan Ojeda
 
Diseño Sísmico de Presas de Relaves
Diseño Sísmico de Presas de RelavesDiseño Sísmico de Presas de Relaves
Diseño Sísmico de Presas de RelavesAndersson Lujan Ojeda
 
Sistemas de Drenaje en Presas de Relaves
Sistemas de Drenaje en Presas de RelavesSistemas de Drenaje en Presas de Relaves
Sistemas de Drenaje en Presas de RelavesAndersson Lujan Ojeda
 
Introducción al diseño de Presas de Relave
Introducción al diseño de Presas de RelaveIntroducción al diseño de Presas de Relave
Introducción al diseño de Presas de RelaveAndersson Lujan Ojeda
 
Implementacion de lean construction en las organizaciones
Implementacion de lean construction en las organizacionesImplementacion de lean construction en las organizaciones
Implementacion de lean construction en las organizacionesAndersson Lujan Ojeda
 
Principios evaluacion proyectos privados
Principios evaluacion proyectos privadosPrincipios evaluacion proyectos privados
Principios evaluacion proyectos privadosAndersson Lujan Ojeda
 
Indices de rentabilidad (VAN - TIR - B/C)
Indices de rentabilidad (VAN - TIR - B/C)Indices de rentabilidad (VAN - TIR - B/C)
Indices de rentabilidad (VAN - TIR - B/C)Andersson Lujan Ojeda
 
Edificaciones con aisladores sismicos en la base
Edificaciones con aisladores sismicos en la baseEdificaciones con aisladores sismicos en la base
Edificaciones con aisladores sismicos en la baseAndersson Lujan Ojeda
 
Edificaciones con Disipadores de Energia
Edificaciones con Disipadores de EnergiaEdificaciones con Disipadores de Energia
Edificaciones con Disipadores de EnergiaAndersson Lujan Ojeda
 
Interaccion Sismica Suelo-Pilote-Superestructura
Interaccion Sismica Suelo-Pilote-SuperestructuraInteraccion Sismica Suelo-Pilote-Superestructura
Interaccion Sismica Suelo-Pilote-SuperestructuraAndersson Lujan Ojeda
 
Analisis Sismico entre muros de ductilidad limitada y albañileria confinada
Analisis Sismico  entre muros de ductilidad limitada y albañileria confinadaAnalisis Sismico  entre muros de ductilidad limitada y albañileria confinada
Analisis Sismico entre muros de ductilidad limitada y albañileria confinadaAndersson Lujan Ojeda
 
Interaccion Sismica Suelo-Estructura
Interaccion Sismica Suelo-EstructuraInteraccion Sismica Suelo-Estructura
Interaccion Sismica Suelo-EstructuraAndersson Lujan Ojeda
 
Importancia del Coeficiente de Balasto en el Analisis Sismico de Edificaciones
Importancia del Coeficiente de Balasto en el Analisis Sismico de EdificacionesImportancia del Coeficiente de Balasto en el Analisis Sismico de Edificaciones
Importancia del Coeficiente de Balasto en el Analisis Sismico de EdificacionesAndersson Lujan Ojeda
 
Estructura, elementos y sistemas estructurales
Estructura, elementos y sistemas estructuralesEstructura, elementos y sistemas estructurales
Estructura, elementos y sistemas estructuralesAndersson Lujan Ojeda
 

More from Andersson Lujan Ojeda (19)

Problemas Resueltos de Mecanica de Suelos
Problemas Resueltos de Mecanica de SuelosProblemas Resueltos de Mecanica de Suelos
Problemas Resueltos de Mecanica de Suelos
 
Ejemplo de Diseño de Presa de Pillones
Ejemplo de Diseño de Presa de PillonesEjemplo de Diseño de Presa de Pillones
Ejemplo de Diseño de Presa de Pillones
 
Diseño Sísmico de Presas de Relaves
Diseño Sísmico de Presas de RelavesDiseño Sísmico de Presas de Relaves
Diseño Sísmico de Presas de Relaves
 
Sistemas de Drenaje en Presas de Relaves
Sistemas de Drenaje en Presas de RelavesSistemas de Drenaje en Presas de Relaves
Sistemas de Drenaje en Presas de Relaves
 
Introducción al diseño de Presas de Relave
Introducción al diseño de Presas de RelaveIntroducción al diseño de Presas de Relave
Introducción al diseño de Presas de Relave
 
Control de cronogramas
Control de cronogramas Control de cronogramas
Control de cronogramas
 
Herramientas Lean Construction
Herramientas Lean ConstructionHerramientas Lean Construction
Herramientas Lean Construction
 
Implementacion de lean construction en las organizaciones
Implementacion de lean construction en las organizacionesImplementacion de lean construction en las organizaciones
Implementacion de lean construction en las organizaciones
 
Principios evaluacion proyectos privados
Principios evaluacion proyectos privadosPrincipios evaluacion proyectos privados
Principios evaluacion proyectos privados
 
Indices de rentabilidad (VAN - TIR - B/C)
Indices de rentabilidad (VAN - TIR - B/C)Indices de rentabilidad (VAN - TIR - B/C)
Indices de rentabilidad (VAN - TIR - B/C)
 
Edificaciones con aisladores sismicos en la base
Edificaciones con aisladores sismicos en la baseEdificaciones con aisladores sismicos en la base
Edificaciones con aisladores sismicos en la base
 
Edificaciones con Disipadores de Energia
Edificaciones con Disipadores de EnergiaEdificaciones con Disipadores de Energia
Edificaciones con Disipadores de Energia
 
Interaccion Sismica Suelo-Pilote-Superestructura
Interaccion Sismica Suelo-Pilote-SuperestructuraInteraccion Sismica Suelo-Pilote-Superestructura
Interaccion Sismica Suelo-Pilote-Superestructura
 
Analisis Sismico entre muros de ductilidad limitada y albañileria confinada
Analisis Sismico  entre muros de ductilidad limitada y albañileria confinadaAnalisis Sismico  entre muros de ductilidad limitada y albañileria confinada
Analisis Sismico entre muros de ductilidad limitada y albañileria confinada
 
Interaccion Sismica Suelo-Estructura
Interaccion Sismica Suelo-EstructuraInteraccion Sismica Suelo-Estructura
Interaccion Sismica Suelo-Estructura
 
Importancia del Coeficiente de Balasto en el Analisis Sismico de Edificaciones
Importancia del Coeficiente de Balasto en el Analisis Sismico de EdificacionesImportancia del Coeficiente de Balasto en el Analisis Sismico de Edificaciones
Importancia del Coeficiente de Balasto en el Analisis Sismico de Edificaciones
 
Analisis Sismico de Edificaciones
Analisis Sismico de EdificacionesAnalisis Sismico de Edificaciones
Analisis Sismico de Edificaciones
 
Estructura, elementos y sistemas estructurales
Estructura, elementos y sistemas estructuralesEstructura, elementos y sistemas estructurales
Estructura, elementos y sistemas estructurales
 
Diseño de Malla de Perforación
Diseño de Malla de PerforaciónDiseño de Malla de Perforación
Diseño de Malla de Perforación
 

Recently uploaded

Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Celine George
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Jisc
 
Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...jaredbarbolino94
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPCeline George
 
AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.arsicmarija21
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for BeginnersSabitha Banu
 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfUjwalaBharambe
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
Pharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfPharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfMahmoud M. Sallam
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersSabitha Banu
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxAvyJaneVismanos
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 

Recently uploaded (20)

OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...
 
Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERP
 
AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for Beginners
 
ESSENTIAL of (CS/IT/IS) class 06 (database)
ESSENTIAL of (CS/IT/IS) class 06 (database)ESSENTIAL of (CS/IT/IS) class 06 (database)
ESSENTIAL of (CS/IT/IS) class 06 (database)
 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
Pharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfPharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdf
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginners
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptx
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 

Project Cost Management

  • 1. Chapter  5:     Project  Cost  Management   Stevbros  Training  &  Consultancy   www.stevbros.edu.vn   Copyright@STEVBROS   Project  Management  Fundamentals   1   PMI,  PMP  and  PMBOK  are  registered  marks  of  the  Project  Management  Ins9tute,  Inc.  
  • 2. Overview       Ini%a%ng   process   group   Planning  process   group   Execu%ng   process   group   Monitoring   &   controlling   process   group   Closing   process   group   Project  cost   management       •  Plan  Cost   Management   •  EsHmate   Costs   •  Determine   Budget       •  Control   Costs       Copyright@STEVBROS   Project  Management  Fundamentals   2  
  • 3. Cost  Concepts   Life  cycle  cosHng   •  Looking  at  the  cost  of  whole  life  of  the  product   (include  maintenance)     Value  analysis  (value  engineering)   •  Looking  at  less  costly  way  to  do  the  same  work   within  the  same  scope   Copyright@STEVBROS   Project  Management  Fundamentals   3  
  • 4. Cost  Concepts   A  Cost  can  be  either  variable  or  fixed:   •  Variable   cost:   cost   that   change   with   the   amount   of   producHon   or   the   amount   of   work.   Ex.,   cost   of   material,   supplies,  wages…   •  Fixed  cost:  cost  that  do  not  change  as  producHon  changes.   Ex.,  set-­‐up,  rental…   A  Cost  can  be  either  direct  or  indirect:   •  Direct  cost:  cost  that  are  directly  aVributable  to  the  work  on   the  project,  Ex.,  team  travel,  team  wages,  recogniHon,  and   costs  of  material  used  on  the  project…   •  Indirect   cost:   overhead   items   or   costs   incurred   for   the   benefit  of  more  than  one  project,  Ex.,  taxes,  fringe  benefits   and  janitorial  services   Copyright@STEVBROS   Project  Management  Fundamentals   4  
  • 5. Plan  cost   management   •  The   process   that   establishes   the   policies,   procedures,   and   documentaHon   for   planning,   managing,   expending,   and   controlling   project   costs.   The   key   benefit   of   this   process   is   that   it   provides   guidance   and   direcHon   on   how   the   project   costs  will  be  managed  throughout  the  project.   Copyright@STEVBROS   Project  Management  Fundamentals   5   A  Guide  to  the  Project  Management  Body  of  Knowledge,  FiBh  Edi9on  (PMBOK®  Guide)  ©2013  Project  Management   Ins9tute,  Inc.    All  Rights  Reserved.    Figure  7-­‐2  Page  195.  
  • 6. Inputs   1.  Project  Management  Plan     •  contains   informaHon   used   to   develop   the   cost   management   plan:  Scope  baseline,  Schedule  baseline,  Other  informaHon.   2.  Project  Charter     •  provides  the  summary  budget  from  which  the  detailed  project   costs  are  developed.     3.  Enterprise  Environmental  Factors     •  organizaHonal   culture   and   structure   can   all   influence   cost   management;   market   condiHons;   currency   exchange   rates;   published  commercial  informaHon;  PMIS.   4.  Organiza%onal  Process  Assets     •  financial  controls  procedures;  historical  informaHon  and  lessons   learned   knowledge   bases;   financial   databases;   and   exisHng   formal   and   informal   cost   esHmaHng   and   budgeHng-­‐related   policies,  procedures,  and  guidelines.     Copyright@STEVBROS   Project  Management  Fundamentals   6  
  • 7. Tools  and   techniques   1.  Expert  Judgment     •  guided  by  historical  informaHon,  provides  valuable  insight  about   the  environment  and  informaHon  from  prior  similar  projects.   2.  Analy%cal  Techniques     •  involve   choosing   strategic   opHons   to   fund   the   project   such   as:   self-­‐funding,  funding  with  equity,  or  funding  with  debt.  The  cost   management   plan   may   also   detail   ways   to   finance   project   resources  such  as  making,  purchasing,  renHng,  or  leasing.   •  techniques   may   include:   payback   period,   return   on   investment,   internal   rate   of   return,   discounted   cash   flow,   and   net   present   value.     3.  Mee%ngs     •  aVendees   at   these   meeHngs   may   include   the   project   manager,   the   project   sponsor,   selected   project   team   members,   selected   stakeholders,   anyone   with   responsibility   for   project   costs,   and   others  as  needed.     Copyright@STEVBROS   Project  Management  Fundamentals   7  
  • 8. Outputs   1.  Cost  Management  Plan   •  describes   how   the   project   costs   will   be   planned,   structured,   and   controlled.  the  cost  management  plan  can  establish  the  following:     ü units  of  measure.     ü Level   of   precision:   the   degree   to   which   acHvity   cost   esHmates   will   be   rounded   up   or   down   (e.g.,   US$100.49   to   US$100,   or   US$995.59   to   US $1,000)   ü Level  of  accuracy:  the  acceptable  range  (e.g.,  ±10%)   ü OrganizaHonal  procedures  links:  the  WBS  provides  the  framework  for  the   cost   management   plan,   allowing   for   consistency   with   the   esHmates,   budgets,  and  control  of  costs.   ü control  thresholds.   ü Rules  of  performance  measurement:  EVM  rules  of  performance   ü ReporHng  formats   ü Process  descripHons   ü AddiHonal  details   Copyright@STEVBROS   Project  Management  Fundamentals   8  
  • 9. EsHmate  costs   •  The  process  of  developing  an  approximaHon  of  the  monetary   resources   needed   to   complete   project   acHviHes.   The   key   benefit   of   this   process   is   that   it   determines   the   amount   of   cost  required  to  complete  project  work.   Copyright@STEVBROS   Project  Management  Fundamentals   9   A  Guide  to  the  Project  Management  Body  of  Knowledge,  FiBh  Edi9on  (PMBOK®  Guide)  ©2013  Project  Management   Ins9tute,  Inc.    All  Rights  Reserved.    Figure  7-­‐4  Page  200.  
  • 10. EsHmaHng     techniques   •  The  accuracy  of  a  project  esHmate  will  increase   as  the  project  progresses  through  the  project  life   cycle.   For   example,   a   project   in   the   iniHaHon   phase   may   have   a   rough   order   of   magnitude   (ROM)   esHmate   in   the   range   of   −25%   to   +75%.   Later   in   the   project,   as   more   informaHon   is   known,   definiHve   esHmates   could   narrow   the   range  of  accuracy  to  -­‐5%  to  +10%.   •  EsHmaHng  techniques:  analogous  esHmaHng  (top   down  esHmaHng),  parametric  esHmaHng,  boVom   up  esHmaHng,  three  point  esHmaHng.   Copyright@STEVBROS   Project  Management  Fundamentals   10  
  • 11. Inputs(1/2)   1.  Cost  Management  Plan   •  defines  how  project  costs  will  be  managed  and  controlled.     2.  Human  Resource  Management  Plan     •  provides   project   staffing   aVributes,   personnel   rates,   and   related  rewards/recogniHon,  which  are  necessary  components   for  developing  the  project  cost  esHmates.   3.  Scope  Baseline     •  addiHonal   informaHon   that   may   be   found   in   the   scope   baseline   with   contractual   and   legal   implicaHons,   such   as   health,   safety,   security,   performance,   environmental,   insurance,   intellectual   property   rights,   licenses,   and   permits.   All  of  this  informaHon  should  be  considered  when  developing   the  cost  esHmates.     Copyright@STEVBROS   Project  Management  Fundamentals   11  
  • 12. Inputs(2/2)   4.  Project  Schedule     •  the  type  and  quanHty  of  resources  and  the  amount  of  Hme  which  those   resources   are   applied   to   complete   the   work   of   the   project   are   major   factors   in   determining   the   project   cost.   Schedule   acHvity   resources   and   their  respecHve  duraHons  are  used  as  key  inputs  to  this  process.   5.  Risk  Register     •  as  a  general  rule,  when  the  project  experiences  a  negaHve  risk  event,  the   near-­‐term   cost   of   the   project   will   usually   increase,   and   there   will   someHmes  be  a  delay  in  the  project  schedule.  In  a  similar  way,  the  project   team  should  be  sensiHve  to  potenHal  opportuniHes  that  can  benefit  the   business   either   by   directly   reducing   acHvity   costs   or   by   acceleraHng   the   schedule.   6.  Enterprise  Environmental  Factors     •  market  condiHons,  published  commercial  informaHon.     7.  Organiza%onal  Process  Assets     •  cost  esHmaHng  policies,  cost  esHmaHng  templates,  historical  informaHon,   and  lessons  learned.     Copyright@STEVBROS   Project  Management  Fundamentals   12  
  • 13. Tools  and   techniques(1/3)   1.  Expert  Judgment     •  guided   by   historical   informaHon,   provides   valuable   insight   about   the  environment  and  informaHon  from  prior  similar  projects.   2.  Analogous  Es%ma%ng     •  uses   the   values   such   as   scope,   cost,   budget,   and   duraHon   or   measures   of   scale   such   as   size,   weight,   and   complexity   from   a   previous,   similar   project   as   the   basis   for   esHmaHng   the   same   parameter  or  measurement  for  a  current  project.   3.  Parametric  Es%ma%ng     •  uses  a  staHsHcal  relaHonship  between  relevant  historical  data  and   other  variables  (e.g.,  square  footage  in  construcHon)  to  calculate  a   cost  esHmate  for  project  work.  This  technique  can  produce  higher   levels   of   accuracy   depending   upon   the   sophisHcaHon   and   underlying  data  built  into  the  model.   Copyright@STEVBROS   Project  Management  Fundamentals   13  
  • 14. Tools  and   techniques(2/3)   4.  BoVom-­‐Up  Es%ma%ng     •  is  a  method  of  esHmaHng  a  component  of  work.  The  cost  of  individual   work  packages  or  acHviHes  is  esHmated  to  the  greatest  level  of  specified   detail.   The   detailed   cost   is   then   summarized   or   “rolled   up”   to   higher   levels  for  subsequent  reporHng  and  tracking  purposes.   5.  Three-­‐Point  Es%ma%ng     •  Most   likely   (cM).   The   cost   of   the   acHvity,   based   on   realisHc   effort   assessment  for  the  required  work  and  any  predicted  expenses.     •  OpHmisHc   (cO).   The   acHvity   cost   based   on   analysis   of   the   best-­‐case   scenario  for  the  acHvity.     •  PessimisHc   (cP).   The   acHvity   cost   based   on   analysis   of   the   worst-­‐case   scenario  for  the  acHvity.     •  Two  commonly  used  formulas  are  triangular  and  beta  distribuHons:   ü Triangular  DistribuHon.  cE  =  (cO  +  cM  +  cP)  /  3     ü Beta  DistribuHon  (from  a  tradiHonal  PERT  analysis).  cE  =  (cO  +  4cM  +  cP)  /  6     Copyright@STEVBROS   Project  Management  Fundamentals   14  
  • 15. Tools  and   techniques(3/3)   6.  Reserve  Analysis     •  Cost   esHmates   may   include   conHngency   reserves   (someHmes   called   conHngency  allowances)  to  account  for  cost  uncertainty.   7.  Cost  of  Quality  (COQ)  (details  in  next  slide)   8.  Project  Management  So^ware     9.  Vendor  Bid  Analysis     •  include  analysis  of  what  the  project  should  cost,  based  on  the  responsive   bids   from   qualified   vendors.   When   projects   are   awarded   to   a   vendor   under   compeHHve   processes,   addiHonal   cost   esHmaHng   work   may   be   required   of   the   project   team   to   examine   the   price   of   individual   deliverables   and   to   derive   a   cost   that   supports   the   final   total   project   cost.   10.  Group  Decision-­‐Making  Techniques   •  team-­‐based  approaches,  such  as  brainstorming,  the  Delphi  or  nominal   group   techniques,   are   useful   for   engaging   team   members   to   improve   esHmate  accuracy  and  commitment  to  the  emerging  esHmates.     Copyright@STEVBROS   Project  Management  Fundamentals   15  
  • 16. Cost  of  quality   Copyright@STEVBROS   Project  Management  Fundamentals   16   A  Guide  to  the  Project  Management  Body  of  Knowledge,  FiBh  Edi9on  (PMBOK®  Guide)  ©2013  Project  Management   Ins9tute,  Inc.    All  Rights  Reserved.    Figure  8-­‐5  Page  235.  
  • 17. Outputs   1.  Ac%vity  Cost  Es%mates   •  Direct  Cost:  costs  that  are  directly  aVribute  to  work  on  the  project.  eg.   training  cost,  travel  cost,  wages,  cost  of  material  used  in  the  project,  etc   •  Indirect  Cost:  overhead  items  or  costs  incurred  for  the  benefit  of  more   than  one  project.  eg.  taxes,  fringe  benefits,  etc   •  Variable   Cost:   change   with   the   amount   of   producHon/work.   e.g.   material,   supplies,  wages   •  Fixed  Cost:  do  not  change  as  producHon  change.  e.g.  set-­‐up,  rental   2.  Basis  of  Es%mates     •  DocumentaHon  of  the  basis  of  the  esHmate  (i.e.,  how  it  was  developed),     •  DocumentaHon  of  all  assumpHons  made,     •  DocumentaHon  of  any  known  constraints,     •  IndicaHon   of   the   range   of   possible   esHmates   (e.g.,   €10,000   (±10%)   to   indicate  that  the  item  is  expected  to  cost  between  a  range  of  values),  and     •  IndicaHon  of  the  confidence  level  of  the  final  esHmate.     3.  Project  Documents  Updates     Copyright@STEVBROS   Project  Management  Fundamentals   17  
  • 18. Determine  budget   •  The  process  of  aggregaHng  the  esHmated  costs  of  individual   acHviHes   or   work   packages   to   establish   an   authorized   cost   baseline.  The  key  benefit  of  this  process  is  that  it  determines   the  cost  baseline  against  which  project  performance  can  be   monitored  and  controlled.   Copyright@STEVBROS   Project  Management  Fundamentals   18   A  Guide  to  the  Project  Management  Body  of  Knowledge,  FiBh  Edi9on  (PMBOK®  Guide)  ©2013  Project  Management   Ins9tute,  Inc.    All  Rights  Reserved.    Figure  7-­‐6  Page  208.  
  • 19. Inputs(1/2)   1.  Cost  Management  Plan   •  describes  how  the  project  costs  will  be  managed  and  controlled.       2.  Scope  Baseline     •  includes  project  scope  statement,  WBS,  WBS  dicHonary.   3.  Ac%vity  Cost  Es%mates     •  cost   esHmates   for   each   acHvity   within   a   work   package   are   aggregated  to  obtain  a  cost  esHmate  for  each  work  package.     4.  Basis  of  Es%mates     •  supporHng  detail  for  cost  esHmates  contained  in  the  basis  for   esHmates  should  specify  any  basic  assumpHons  dealing  with  the   inclusion   or   exclusion   of   indirect   or   other   costs   in   the   project   budget.     Copyright@STEVBROS   Project  Management  Fundamentals   19  
  • 20. Inputs(2/2)   5.  Project  Schedule   •  This   informaHon   can   be   used   to   aggregate   costs   to   the   calendar   periods  in  which  the  costs  are  planned  to  be  incurred.     6.  Resource  Calendars     7.  Risk  Register     •  The  risk  register  should  be  reviewed  to  consider  how  to  aggregate   the  risk  response  costs.   8.  Agreements     •  Applicable   agreement   informaHon   and   costs   relaHng   to   products,   services,  or  results  that  have  been  or  will  be  purchased  are  included   when  determining  the  budget.     9.  Organiza%onal  Process  Assets   •  ExisHng   formal   and   informal   cost   budgeHng-­‐related   policies,   procedures,   and   guidelines;   cost   budgeHng   tools;   and   reporHng   methods.   Copyright@STEVBROS   Project  Management  Fundamentals   20  
  • 21. Tools  and   techniques   1.  Cost  Aggrega%on     •  Cost  esHmates  are  aggregated  by  work  packages  in  accordance  with  the  WBS.  The   work  package  cost  esHmates  are  then  aggregated  for  the  higher  component  levels   of  the  WBS  (such  as  control  accounts)  and  ulHmately  for  the  enHre  project.     2.  Reserve  Analysis     •  Budget   reserve   analysis   can   establish   both   the   conHngency   reserves   and   the   management  reserves  for  the  project.   3.  Expert  Judgment     •  guided  by  experience  in  an  applicaHon  area,  knowledge  area,  discipline,  industry,  or   similar  project,  aids  in  determining  the  budget.   4.  Historical  Rela%onships     •  Any   historical   relaHonships   that   result   in   parametric   esHmates   or   analogous   esHmates   involve   the   use   of   project   characterisHcs   (parameters)   to   develop   mathemaHcal  models  to  predict  total  project  costs.   5.  Funding  Limit  Reconcilia%on   •  The   expenditure   of   funds   should   be   reconciled   with   any   funding   limits   on   the   commitment  of  funds  for  the  project.  A  variance  between  the  funding  limits  and  the   planned  expenditures  will  someHmes  necessitate  the  rescheduling  of  work  to  level   out  the  rate  of  expenditures.   Copyright@STEVBROS   Project  Management  Fundamentals   21  
  • 22. Outputs   1.  Cost  Baseline   •  is  the  approved  version  of  the  Hme-­‐phased  project  budget,   excluding  any  management  reserves  (details  at  next  slide)   2.  Project  Funding  Requirements     •  total   funding   requirements   and   periodic   funding   requirements   (e.g.,   quarterly,   annually)   are   derived   from   the  cost  baseline.  The  cost  baseline  will  include  projected   expenditures  plus  anHcipated  liabiliHes.     •  the   total   funds   required   are   those   included   in   the   cost   baseline,  plus  management  reserves,  if  any.     3.  Project  Documents  Updates     •  such   as   risk   register,   acHvity   cost   esHmates,   and   project   schedule.     Copyright@STEVBROS   Project  Management  Fundamentals   22  
  • 23. Project  budget   Copyright@STEVBROS   Project  Management  Fundamentals   23   A  Guide  to  the  Project  Management  Body  of  Knowledge,  FiBh  Edi9on  (PMBOK®  Guide)  ©2013  Project  Management   Ins9tute,  Inc.    All  Rights  Reserved.    Figure  7-­‐8  Page  213.  
  • 24. Project  budget   Copyright@STEVBROS   Project  Management  Fundamentals   24   A  Guide  to  the  Project  Management  Body  of  Knowledge,  FiBh  Edi9on  (PMBOK®  Guide)  ©2013  Project  Management   Ins9tute,  Inc.    All  Rights  Reserved.    Figure  7-­‐9  Page  214.  
  • 25. Control  cost   •  The  process  of  monitoring  the  status  of  the  project  to  update   the  project  costs  and  managing  changes  to  the  cost  baseline.   The  key  benefit  of  this  process  is  that  it  provides  the  means  to   recognize  variance  from  the  plan  in  order  to  take  correcHve   acHon  and  minimize  risk.     Copyright@STEVBROS   Project  Management  Fundamentals   25   A  Guide  to  the  Project  Management  Body  of  Knowledge,  FiBh  Edi9on  (PMBOK®  Guide)  ©2013  Project  Management   Ins9tute,  Inc.    All  Rights  Reserved.    Figure  7-­‐10  Page  215.  
  • 26. Inputs   1.  Project  Management  Plan     •  contains  cost  baseline  and  cost  management  plan.   2.  Project  Funding  Requirements     •  requirements   include   projected   expenditures   plus   anHcipated   liabiliHes.     3.  Work  Performance  Data   •  data  includes  informaHon  about  project  progress,  such  as  which   acHviHes   have   started,   their   progress,   and   which   deliverables   have   finished.   InformaHon   also   includes   costs   that   have   been   authorized  and  incurred.     4.  OrganizaHonal  Process  Assets     •  include   exisHng   formal   and   informal   cost   control-­‐related   policies,   procedures,   and   guidelines;   cost   control   tools;   and   monitoring  and  reporHng  methods  to  be  used.     Copyright@STEVBROS   Project  Management  Fundamentals   26  
  • 27. Tools  and   techniques   1.  Earned  Value  Management  (next  slides)   2.  Forecas%ng  (next  slides)   3.  To-­‐Complete  Performance  Index  (TCPI)  (next  slides)   4.  Performance  Reviews  (next  slides)   5.  Project  Management  So^ware     6.  Reserve  Analysis     •  During  cost  control,  reserve  analysis  is  used  to  monitor  the   status  of  conHngency  and  management  reserves     for  the  project  to  determine  if  these  reserves  are  sHll   needed  or  if  addiHonal  reserves  need  to  be  requested.     Copyright@STEVBROS   Project  Management  Fundamentals   27  
  • 28. EVM   •  Earned   Value   Management   (EVM):   is   the   most   common   tool   which   help   project   managers   measure   project   performance   and   determine   where   the   project   stands   in   relaHon   to   the   budget  and  the  schedule  at  a  point  in  Hme.   •  Work  performance  informaHon:  BAC,  PV,  EV,  AC.   •  Work   performance   measurement:   CPI,   CV,   SPI,   SV.   •  ForecasHng:  ETC,  EAC.   •  To-­‐Complete  Performance  Index:  TCPI.   Copyright@STEVBROS   Project  Management  Fundamentals   28  
  • 29. EVM   •  Work  performance  informaHon:   o BAC-­‐  Budget  At  CompleHon  (project  budget).   o PV  -­‐  Planned  Value  (value  of  work  schedule):    PV  =  BAC  *  planned  %  complete.   o EV  -­‐  Earned  Value  (value  of  work  performed):    EV  =BAC  *  actual  %  complete.   o AC—Actual  Cost  (spent  cost).   Copyright@STEVBROS   Project  Management  Fundamentals   29  
  • 30. EVM   •  Work  performance  measurement:   o  SPI—Schedule  Performance  Index  =  EV/PV.      If  SPI    >  1,  you’re  ahead  of  schedule.  If  SPI  <  1,  you’re  behind  schedule.   o  SV—Schedule  Variance  =  EV-­‐PV.      If  SV  >  0,  it  tells  you  how  many  dollars  you’re  ahead.  If  SV  <  0,  it  tells   you  how  many  dollars  you’re  behind.   o  CPI—Cost  Performance  Index  =  EV/AC.      If  CPI    >  1,  you’re  under  budget.  If  CPI  <  1,  you’re  over  budget.   o  CV—Cost  Variance  =  EV-­‐AC.        If  CV  >  0,  it  tells  you  how  many  dollars  you’re  above.  If  CV  <  0,  it  tells   you  how  many  dollars  you’re  below.   Copyright@STEVBROS   Project  Management  Fundamentals   30  
  • 31. EVM   Copyright@STEVBROS   Project  Management  Fundamentals   31   A  Guide  to  the  Project  Management  Body  of  Knowledge,  FiBh  Edi9on  (PMBOK®  Guide)  ©2013  Project  Management   Ins9tute,  Inc.    All  Rights  Reserved.    Figure  7-­‐12  Page  219.  
  • 32. EVM   •  ForecasHng:   o EsHmate  to  Complete  (ETC),  which  tells  you  how   much  more  money  you’ll  probably  spend  on  your   project.   o EsHmate   at   CompleHon   (EAC)   is   used   to   predict   what   your   project   will   actually   cost   when   it’s   complete.   o EAC  =  AC  +  boVom-­‐up  ETC     Copyright@STEVBROS   Project  Management  Fundamentals   32  
  • 33. EVM   •  ForecasHng:   o  EAC  forecast  for  ETC  work  performed  at  the  budgeted  rate.  This  EAC   method   accepts   the   actual   project   performance   to   date   (whether   favorable   or   unfavorable)   as   represented   by   the   actual   costs,   and   predicts  that  all  future  ETC  work  will  be  accomplished  at  the  budgeted   rate.  EquaHon:  EAC  =  AC  +  (BAC  -­‐  EV)     o  EAC  forecast  for  ETC  work  performed  at  the  present  CPI.  This  method   assumes  what  the  project  has  experienced  to  date  can  be  expected  to   conHnue  in  the  future.  The  ETC  work  is  assumed  to  be  performed  at   the  same  cumulaHve  cost  performance  index  (CPI)  as  that  incurred  by   the  project  to  date.  EquaHon:  EAC  =  BAC  /  CPI     o  EAC  forecast  for  ETC  work  considering  both  SPI  and  CPI  factors.  In   this  forecast,  the  ETC  work  will  be  performed  at  an  efficiency  rate  that   considers   both   the   cost   and   schedule   performance   indices.   This   method  is  most  useful  when  the  project  schedule  is  a  factor  impacHng   the  ETC  effort.  EquaHon:  EAC  =  AC  +  [(BAC  -­‐  EV)  /  (CPI  ×  SPI)]     Copyright@STEVBROS   Project  Management  Fundamentals   33  
  • 34. EVM   •  To-­‐Complete   Performance   Index   (TCPI):   is   a   measure   of   the   cost   performance   that   is   required   to   be   achieved   with   the   remaining  resources  in  order  to  meet  a  specified  management  goal,  expressed  as   the  raHo  of  the  cost  to  finish  the  outstanding  work  to  the  remaining  budget.   Copyright@STEVBROS   Project  Management  Fundamentals   34   A  Guide  to  the   Project   Management   Body  of   Knowledge,  FiBh   Edi9on  (PMBOK®   Guide)  ©2013   Project   Management   Ins9tute,  Inc.    All   Rights  Reserved.     Figure  7-­‐13  Page   222.  
  • 35. EVM   Copyright@STEVBROS   Project  Management  Fundamentals   35  
  • 36. Outputs   1.  Work  Performance  Informa%on   •  The  calculated  CV,  SV,  CPI,  SPI,  TCPI,  and  VAC  values  for  WBS   components,   in   parHcular   the   work   packages   and   control   accounts,  are  documented  and  communicated  to  stakeholders.   2.  Cost  Forecasts   •  EAC  value  is  documented  and  communicated  to  stakeholders.   3.  Change  Requests   •  analysis  of  project  performance  may  result  in  a  change  request   to   the   cost   baseline   or   other   components   of   the   project   management  plan.   4.  Project  Management  Plan  Updates   5.  Project  Documents  Updates   6.  Organiza%onal  Process  Assets  Updates   Copyright@STEVBROS   Project  Management  Fundamentals   36  
  • 37. Summary   •  Cost  esHmaHng  techniques   •  The  accuracy  of  a  project  esHmate   •  Project  budget  vs.  cost  baseline   •  Management  reserve  vs.  conHngence  reserve   •  Earned   value   management:   PV,   AC,   EV,   CPI,   SPI,  CV,  SV,  ETC,  EAC,  TCPI.   Copyright@STEVBROS   Project  Management  Fundamentals   37  
  • 38. QuesHons   for  review   Copyright@STEVBROS   Project  Management  Fundamentals   38   •  You  did  the  good  job  at  this  chapter.    Please   complete  quesHons  for  review  before  moving   to  next  chapter.