Role of Functional Organization in Large Engineering and Construction ProgramsBob Prieto
Large corporate organizations typically employ some form of matrix organization to ensure a consistent approach in key areas across the organization. The nature and extent of this matrix or functional organization will be driven by:
•common approaches to human resources
•consistent application of legal approvals and reviews of significant actions
•common financial functions related to accounting, cash management, insurance and claims & suits
•common managerial, technical and support functions which accrue benefits from a consistent and coordinated approach
Within a project setting, required resources generally reside at the project level and corporate functional activities extend into the project environment only to the extent required to protect the parent organization, consistent with client requirements and practices.
The situation in large programs, however, is different and a functional organization more akin to the corporate functional organization is often created within the program team. This program level functional organization acts much in the same way as the corporate functional organization but its role and emphasis evolves throughout the programs life.
A typical program management organization will include a functional organization that will provide people, management processes, program-level project control tools, and systems. The program management team will thereby bring enhanced management, quality control, efficiency, and coordination to the entire program.
The project was done on Efficacy of Project Management... Research was conducted back in 2014 and was carried out by one of the Academic writer at www.assignmentstudio.net who is also a full time tutor and work for www.tutoringlounge.com.au.
Writer profile can be visited at http://tutoringlounge.com.au/erika-reynolds/
For similar projects you can visit our site and place an order...
www.assignmentstudio.net
or email at
contact@assignmentstudio.net
Design Patterns in Electronic Data ManagementGlen Alleman
The concept of a design pattern is based on the seminal work of Christopher Alexander
This White Paper describes the design patterns that are applicable to the Electronic Document Management domain. These include Management of Change, Hypermedia Navigation, Aggregated Relationships, Object to Relational Database Mapping, Compound Documents, and Data Entry Management.
The endeavor of the report is in the direction of scrutinizing the effectiveness of project management in expressions of managerial structures, technological proficiency, and management skill along with the features of an effectual venture manager.
Before exploring the main content of the report let us consider the general concepts of the key words of relative topic or respective report.
Efficacy simply coded, is the core skill, aptitude or the capacity on the way to bring into being a required or projected outcome. The extent in the direction of which a touch is victorious in generating a looked-for outcome is effectiveness
Resource Paper of Enterprise-Wide Deployment of EDMGlen Alleman
The acquisition of an Enterprise–wide software system requires careful planning and execution of a multitude of activities unrelated to the actual software systems being deployed.
Role of Functional Organization in Large Engineering and Construction ProgramsBob Prieto
Large corporate organizations typically employ some form of matrix organization to ensure a consistent approach in key areas across the organization. The nature and extent of this matrix or functional organization will be driven by:
•common approaches to human resources
•consistent application of legal approvals and reviews of significant actions
•common financial functions related to accounting, cash management, insurance and claims & suits
•common managerial, technical and support functions which accrue benefits from a consistent and coordinated approach
Within a project setting, required resources generally reside at the project level and corporate functional activities extend into the project environment only to the extent required to protect the parent organization, consistent with client requirements and practices.
The situation in large programs, however, is different and a functional organization more akin to the corporate functional organization is often created within the program team. This program level functional organization acts much in the same way as the corporate functional organization but its role and emphasis evolves throughout the programs life.
A typical program management organization will include a functional organization that will provide people, management processes, program-level project control tools, and systems. The program management team will thereby bring enhanced management, quality control, efficiency, and coordination to the entire program.
The project was done on Efficacy of Project Management... Research was conducted back in 2014 and was carried out by one of the Academic writer at www.assignmentstudio.net who is also a full time tutor and work for www.tutoringlounge.com.au.
Writer profile can be visited at http://tutoringlounge.com.au/erika-reynolds/
For similar projects you can visit our site and place an order...
www.assignmentstudio.net
or email at
contact@assignmentstudio.net
Design Patterns in Electronic Data ManagementGlen Alleman
The concept of a design pattern is based on the seminal work of Christopher Alexander
This White Paper describes the design patterns that are applicable to the Electronic Document Management domain. These include Management of Change, Hypermedia Navigation, Aggregated Relationships, Object to Relational Database Mapping, Compound Documents, and Data Entry Management.
The endeavor of the report is in the direction of scrutinizing the effectiveness of project management in expressions of managerial structures, technological proficiency, and management skill along with the features of an effectual venture manager.
Before exploring the main content of the report let us consider the general concepts of the key words of relative topic or respective report.
Efficacy simply coded, is the core skill, aptitude or the capacity on the way to bring into being a required or projected outcome. The extent in the direction of which a touch is victorious in generating a looked-for outcome is effectiveness
Resource Paper of Enterprise-Wide Deployment of EDMGlen Alleman
The acquisition of an Enterprise–wide software system requires careful planning and execution of a multitude of activities unrelated to the actual software systems being deployed.
Nicholas Carr’s, Does IT Matter? asks the question – “isn’t it enough for IT to enable companies to operate more efficiently or deliver better services, to reduce costs or heighten customer satisfaction?” [1, p. 7]. This question is the infrastructure question. Carr suggests the investments in IT have “gone to waste” after the collapse of the Internet Bubble. While much has been wasted to what were probably poor business choices, IT investment as a strategic initiative still has merit. This merit needs to be connected to the financial performance of the business. The measurement and valuation of these investments must take place in the same way other investment decisions are made. Carr’s thesis is IT has become a commodity service and not the basis of a differentiated strategic advantage. As the costs of IT go down, its power increases the capabilities of IT outstrip the company’s needs. Again this is an infrastructure view of IT. Like the railroads and electric utilities, if is only a “utility” it will have difficulty describing its differentiated advantage.
Project Management Body of Knowledge (Time)Jeffrey Cheah
Time Management Process in Project Management Body of Knowledge (PMBOK 5th Edition)
Project Management Professional (PMP) topics sourced from the Project Management Institute (PMI)
Project Management Body of Knowledge (Introduction)Jeffrey Cheah
Introduction to Project Management Body of Knowledge (PMBOK 5th Edition)
Project Management Professional (PMP) topics sourced from the Project Management Institute (PMI)
The Role of the Architect in ERP and PDM System DeploymentGlen Alleman
The architect’s role in the development of an ERP or PDM system is to maintain the integrity of the vision statement produced by the owners, users, and funders of the system.
Lightweight processes are beginning to replace more formal methods. The motivation for this transition is based on many factors. The Internet, time to market, cost reduction, quality increases, market pressures, as well as the popularization of these programming methods. This series of articles will investigate the various lightweight methods, their impact on the management of software development projects and the processes by which managers can determine the appropriateness and usefulness of the various processes. The definition of a lightweight Process is more difficult than it would first appear. This article outlines the foundations of a heavyweight process and describes the appropriate pieces that can be converted to lightweight.
PMP eligibility (By PMP Pulse)
for more study material, lectures, free exam preparations, free PMP mock tests follow us at www.pmppulse.com
email us at: marketing@pmppulse.com
Get Free For Life project management subscription of CONSYSA https://www.consysa.com/
Information systems are being used by large organization to increase their business efficiency and productivity.
These systems are designed to help commercial enterprise complete their project efficiently and effectively. Tracking, reporting functions, scheduling, calendar are components of the project management system. Construction Project management system can be accessed by the team members irrespective of their location.
Management software is utilized by management systems to carry-out different processes which include collaboration, risk management, cost management, Communication, quality management and so on. Documentation and keeping of records are very important when executing a project because it helps you to gain insight into the future projects which are related to the project you are currently executing. There are two ways of using construction management systems. We have the offline desktop system and the web-based system.
Also Visit :
https://www.consysa.com/forum/pages/pms-project-management-system
https://youtu.be/u_f1WRcliK8
Project Management System SharePoint Apps by adapt embeds all the necessary features required to achieve efficient Project Management and is suitable for EPC, Manufacturing & Service Industries.manage all your documents.and communication centrally and foster seamless callaboration,allocate budgets for various categories including manpower and material.
Stepwise Project planning in software developmentProf Ansari
The following activities are:
Identify objectives and practical measures of the effectiveness in meeting those objectives.
Establish a project authority
Stakeholder analysis – identify all stakeholders in the project and their interests
Modify objectives in the light of stakeholder’s analysis
Establish methods of communication with all parties
2.4
Nicholas Carr’s, Does IT Matter? asks the question – “isn’t it enough for IT to enable companies to operate more efficiently or deliver better services, to reduce costs or heighten customer satisfaction?” [1, p. 7]. This question is the infrastructure question. Carr suggests the investments in IT have “gone to waste” after the collapse of the Internet Bubble. While much has been wasted to what were probably poor business choices, IT investment as a strategic initiative still has merit. This merit needs to be connected to the financial performance of the business. The measurement and valuation of these investments must take place in the same way other investment decisions are made. Carr’s thesis is IT has become a commodity service and not the basis of a differentiated strategic advantage. As the costs of IT go down, its power increases the capabilities of IT outstrip the company’s needs. Again this is an infrastructure view of IT. Like the railroads and electric utilities, if is only a “utility” it will have difficulty describing its differentiated advantage.
Project Management Body of Knowledge (Time)Jeffrey Cheah
Time Management Process in Project Management Body of Knowledge (PMBOK 5th Edition)
Project Management Professional (PMP) topics sourced from the Project Management Institute (PMI)
Project Management Body of Knowledge (Introduction)Jeffrey Cheah
Introduction to Project Management Body of Knowledge (PMBOK 5th Edition)
Project Management Professional (PMP) topics sourced from the Project Management Institute (PMI)
The Role of the Architect in ERP and PDM System DeploymentGlen Alleman
The architect’s role in the development of an ERP or PDM system is to maintain the integrity of the vision statement produced by the owners, users, and funders of the system.
Lightweight processes are beginning to replace more formal methods. The motivation for this transition is based on many factors. The Internet, time to market, cost reduction, quality increases, market pressures, as well as the popularization of these programming methods. This series of articles will investigate the various lightweight methods, their impact on the management of software development projects and the processes by which managers can determine the appropriateness and usefulness of the various processes. The definition of a lightweight Process is more difficult than it would first appear. This article outlines the foundations of a heavyweight process and describes the appropriate pieces that can be converted to lightweight.
PMP eligibility (By PMP Pulse)
for more study material, lectures, free exam preparations, free PMP mock tests follow us at www.pmppulse.com
email us at: marketing@pmppulse.com
Get Free For Life project management subscription of CONSYSA https://www.consysa.com/
Information systems are being used by large organization to increase their business efficiency and productivity.
These systems are designed to help commercial enterprise complete their project efficiently and effectively. Tracking, reporting functions, scheduling, calendar are components of the project management system. Construction Project management system can be accessed by the team members irrespective of their location.
Management software is utilized by management systems to carry-out different processes which include collaboration, risk management, cost management, Communication, quality management and so on. Documentation and keeping of records are very important when executing a project because it helps you to gain insight into the future projects which are related to the project you are currently executing. There are two ways of using construction management systems. We have the offline desktop system and the web-based system.
Also Visit :
https://www.consysa.com/forum/pages/pms-project-management-system
https://youtu.be/u_f1WRcliK8
Project Management System SharePoint Apps by adapt embeds all the necessary features required to achieve efficient Project Management and is suitable for EPC, Manufacturing & Service Industries.manage all your documents.and communication centrally and foster seamless callaboration,allocate budgets for various categories including manpower and material.
Stepwise Project planning in software developmentProf Ansari
The following activities are:
Identify objectives and practical measures of the effectiveness in meeting those objectives.
Establish a project authority
Stakeholder analysis – identify all stakeholders in the project and their interests
Modify objectives in the light of stakeholder’s analysis
Establish methods of communication with all parties
2.4
Francesca Gottschalk - How can education support child empowerment.pptxEduSkills OECD
Francesca Gottschalk from the OECD’s Centre for Educational Research and Innovation presents at the Ask an Expert Webinar: How can education support child empowerment?
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...Levi Shapiro
Letter from the Congress of the United States regarding Anti-Semitism sent June 3rd to MIT President Sally Kornbluth, MIT Corp Chair, Mark Gorenberg
Dear Dr. Kornbluth and Mr. Gorenberg,
The US House of Representatives is deeply concerned by ongoing and pervasive acts of antisemitic
harassment and intimidation at the Massachusetts Institute of Technology (MIT). Failing to act decisively to ensure a safe learning environment for all students would be a grave dereliction of your responsibilities as President of MIT and Chair of the MIT Corporation.
This Congress will not stand idly by and allow an environment hostile to Jewish students to persist. The House believes that your institution is in violation of Title VI of the Civil Rights Act, and the inability or
unwillingness to rectify this violation through action requires accountability.
Postsecondary education is a unique opportunity for students to learn and have their ideas and beliefs challenged. However, universities receiving hundreds of millions of federal funds annually have denied
students that opportunity and have been hijacked to become venues for the promotion of terrorism, antisemitic harassment and intimidation, unlawful encampments, and in some cases, assaults and riots.
The House of Representatives will not countenance the use of federal funds to indoctrinate students into hateful, antisemitic, anti-American supporters of terrorism. Investigations into campus antisemitism by the Committee on Education and the Workforce and the Committee on Ways and Means have been expanded into a Congress-wide probe across all relevant jurisdictions to address this national crisis. The undersigned Committees will conduct oversight into the use of federal funds at MIT and its learning environment under authorities granted to each Committee.
• The Committee on Education and the Workforce has been investigating your institution since December 7, 2023. The Committee has broad jurisdiction over postsecondary education, including its compliance with Title VI of the Civil Rights Act, campus safety concerns over disruptions to the learning environment, and the awarding of federal student aid under the Higher Education Act.
• The Committee on Oversight and Accountability is investigating the sources of funding and other support flowing to groups espousing pro-Hamas propaganda and engaged in antisemitic harassment and intimidation of students. The Committee on Oversight and Accountability is the principal oversight committee of the US House of Representatives and has broad authority to investigate “any matter” at “any time” under House Rule X.
• The Committee on Ways and Means has been investigating several universities since November 15, 2023, when the Committee held a hearing entitled From Ivory Towers to Dark Corners: Investigating the Nexus Between Antisemitism, Tax-Exempt Universities, and Terror Financing. The Committee followed the hearing with letters to those institutions on January 10, 202
Operation “Blue Star” is the only event in the history of Independent India where the state went into war with its own people. Even after about 40 years it is not clear if it was culmination of states anger over people of the region, a political game of power or start of dictatorial chapter in the democratic setup.
The people of Punjab felt alienated from main stream due to denial of their just demands during a long democratic struggle since independence. As it happen all over the word, it led to militant struggle with great loss of lives of military, police and civilian personnel. Killing of Indira Gandhi and massacre of innocent Sikhs in Delhi and other India cities was also associated with this movement.
Normal Labour/ Stages of Labour/ Mechanism of LabourWasim Ak
Normal labor is also termed spontaneous labor, defined as the natural physiological process through which the fetus, placenta, and membranes are expelled from the uterus through the birth canal at term (37 to 42 weeks
How to Make a Field invisible in Odoo 17Celine George
It is possible to hide or invisible some fields in odoo. Commonly using “invisible” attribute in the field definition to invisible the fields. This slide will show how to make a field invisible in odoo 17.
Acetabularia Information For Class 9 .docxvaibhavrinwa19
Acetabularia acetabulum is a single-celled green alga that in its vegetative state is morphologically differentiated into a basal rhizoid and an axially elongated stalk, which bears whorls of branching hairs. The single diploid nucleus resides in the rhizoid.
A Strategic Approach: GenAI in EducationPeter Windle
Artificial Intelligence (AI) technologies such as Generative AI, Image Generators and Large Language Models have had a dramatic impact on teaching, learning and assessment over the past 18 months. The most immediate threat AI posed was to Academic Integrity with Higher Education Institutes (HEIs) focusing their efforts on combating the use of GenAI in assessment. Guidelines were developed for staff and students, policies put in place too. Innovative educators have forged paths in the use of Generative AI for teaching, learning and assessments leading to pockets of transformation springing up across HEIs, often with little or no top-down guidance, support or direction.
This Gasta posits a strategic approach to integrating AI into HEIs to prepare staff, students and the curriculum for an evolving world and workplace. We will highlight the advantages of working with these technologies beyond the realm of teaching, learning and assessment by considering prompt engineering skills, industry impact, curriculum changes, and the need for staff upskilling. In contrast, not engaging strategically with Generative AI poses risks, including falling behind peers, missed opportunities and failing to ensure our graduates remain employable. The rapid evolution of AI technologies necessitates a proactive and strategic approach if we are to remain relevant.
Embracing GenAI - A Strategic ImperativePeter Windle
Artificial Intelligence (AI) technologies such as Generative AI, Image Generators and Large Language Models have had a dramatic impact on teaching, learning and assessment over the past 18 months. The most immediate threat AI posed was to Academic Integrity with Higher Education Institutes (HEIs) focusing their efforts on combating the use of GenAI in assessment. Guidelines were developed for staff and students, policies put in place too. Innovative educators have forged paths in the use of Generative AI for teaching, learning and assessments leading to pockets of transformation springing up across HEIs, often with little or no top-down guidance, support or direction.
This Gasta posits a strategic approach to integrating AI into HEIs to prepare staff, students and the curriculum for an evolving world and workplace. We will highlight the advantages of working with these technologies beyond the realm of teaching, learning and assessment by considering prompt engineering skills, industry impact, curriculum changes, and the need for staff upskilling. In contrast, not engaging strategically with Generative AI poses risks, including falling behind peers, missed opportunities and failing to ensure our graduates remain employable. The rapid evolution of AI technologies necessitates a proactive and strategic approach if we are to remain relevant.
Unit 8 - Information and Communication Technology (Paper I).pdfThiyagu K
This slides describes the basic concepts of ICT, basics of Email, Emerging Technology and Digital Initiatives in Education. This presentations aligns with the UGC Paper I syllabus.
Unit 8 - Information and Communication Technology (Paper I).pdf
Pm chapter 4...
1. Chapter-04
PROJECT PLANNING
Outline Syllabus
Project Coordination - Systems Integration, Sorting out the project - Work
Breakdown structure.
5.01 PROJECT PLANNING
Project planning is a procedural step in project management, where required documentation is
created to ensure successful project completion. Some of the important definition are given
below.
According to Harold Kerzner, “Project planning is part of project management, which
relates to the use of schedules such as Gantt charts to plan and subsequently report progress
within the project environment.”
According to R. L. Marline, "A project planning establishes the duration of the project, the
resources needed to complete each activity and the required sequence of performance of each
job.”
Mark Hehl define project planning as, “A formal approved document that defines how the
project is executed, monitored, and controlled. It may be summary or detailed and may be
composed of one or more subsidiary management plans and other planning documents.”
So we can say that the primary purpose of planning is to establish a set of directions in sufficient
detail to tell the project team exactly what must be done, when it must be done, and what
resources to use in order to produce the deliverables of the project successfully.
5.02 ELEMENTS OF PROJECT PLANNING
A project planning establishes the duration of the project, the resources needed to complete each
activity and the required sequence of performance of each job. Key Elements of Project Planning
are stated below.
Define project planning. BBA (Professional) 2007, 2009,2013
2. Project Management
1. Over view : This is a short summary of the objective and scope of the project is directed to
top management and contains a statement of the goals of the project, a brief explanation of
their relationship to the firm's objectives, a description of the managerial structure that will be
used for the project, and a list of the major milestones in the project schedule.
2. Objective: This contains a more detailed statements of the general goals noted in the
overview section. The statement should include profit and competitive aims as well as
technical goals.
3. General approach: This section describes both the managerial and the technical approaches
to the work. The technical discussion describes the relationship of the project to available
technologies.
4. Contractual aspects: This critical section of the plan includes a complete list and description
of all the reporting requirement, customer-supplied resources, liaison arrangements, advisory
committees, project review and cancellation procedures, proprietary requirements, any
specific management arrangement, as well as the technical deliverables and their
specifications, delivery schedules, and a specific procedure for changing of the above.
5. Schedules: This section outlines the various schedules and lists all milestone events. Each
task is listed, and the estimated time for each task should be obtained from those who will do
the work.
6. Resources: There are two primary aspects to this section. The first is the budget. Second,
monitoring and control procedure should be described.
7. Personnel: This section lists the expected personnel requirements of the project. Special
skills, types of training needed, possible recruiting problems, legal or policy restriction on
work force composition, and any other special requirements, such as security clearance,
should be noted here.
8. Risk management plans: This covers potential problems as well as potential lucky breaks
that could affect the project. Sometimes it is difficulties to convince planners to make a
serious attempt to anticipate potential difficulties Or benefits.
9. Evaluation methods: Every project should be evaluated against standards and by methods
established at the project's inception, allowing for both the direct and ancillary goals of the
project.
5.05 SYSTEM INTEGRATION
A system is an aggregation of subsystems cooperating so that the system is able to deliver the
overarching functionality. System integration involves integrating existing often disparate
systems. System integration (SI) is also about adding value to the system, capabilities that are
possible because of interactions between subsystems. In today’s connected world, the role of
Name different elements of project planning. BBA (Professional) 2007, 2009,2013
80
3. Chapter4: Project Planning
system integration engineers is becoming more and more important. Some of the important
definitions are given below.
According to Gilkey, Herbert T, “System integration is defined as the process of bringing
together the component subsystems into one system and ensuring that the subsystems function
together as a system.”
According to Lau, Edwin, “Systems integration is the process of linking together different
computing systems and software applications physically or functionally.”
The system integrator brings together discrete systems utilizing a variety of techniques such as
computer networking, enterprise application integration, business process management or manual
programming.
5.06 ROLE OF SYSTEM INTEGRATION
A system is an aggregation of subsystems cooperating so that the system is able to deliver the
overarching functionality. System integration involves integrating existing often disparate
systems. System integration (SI) is also about adding value to the system, capabilities that are
possible because of interactions between subsystems. In today’s connected world, the role of
system integration engineers is becoming more and more important. It is because of the following
reasons.
(i) Require .no component performance specifications unless necessary to meet one or more
systems requirements.
(ii) Every component requirement should be traceable to one or more systems requirements.
(iii) Design components for effective system performance, not the performance of subsystems
5.07 OBJECTIVES OF SYSTEM INTEGRATION
System integration involves integrating existing often disparate systems. System integration (SI)
is also about adding value to the system, capabilities that are possible because of interactions
between subsystems. The objectives of systems integration of an organization are given below.
1. Performance: Performance is what a system does. It includes system design, reliability,
quality, maintainability, and reparability. Obviously, these are not separate, independent elements
of the system, but are highly interrelated qualities.
2. Effectiveness: (i) Require no component performance specifications unless necessary to meet
one or more systems requirements. (ii) Every component requirement should be traceable to one
or more systems requirements. (iii) Design components for effective system performance, not the
performance of ' subsystems.
3. Cost: Cost system integration considers cost to be a design parameter, and costs can be
accumulated in several areas. Added design cost may lead to decreased component cost, leaving
performance and effectiveness otherwise unchanged.
Define system integration. BBA (Professional) 2009
What is the role of systems integration in project management?
BBA (Professional) 2012
81
4. Project Management
5.08 STEPS OF BREAKDOWN STRUCTURE
The basic steps to design and use the work breakdown structure are given below.
1. Using information from the action plan, list the task breakdown in successively finer levels of
detail. Continue until all meaningful tasks or work package have been identified and each task or
package can be individually planned, scheduled, monitored, and controlled.
2. For each such work package, identify the data relevant to the WBS (e.g., vendors, durations,
equipment, materials, and special specifications.
3. All work package information should be reviewed with the individuals or organizations that
have responsibility for doing or supporting the work in order to verify the WBS's accuracy.
4. For the purpose of pricing a proposal, or determining profit and loss, the total project budget
should consist of four elements.
5. Similarly, schedule information and miles one (significant) events can be aggregated into a
project master schedule.
6. As a project is carried out, step by step, the PM can continually examine actual resources use,
by work element, work package, task, and so on up to the full project level.
7. Finally, the project schedule may be subjected to the same comparisons as the project budget.
What is the obsessive of system integration? BBA (Professional) 2012
What are the basic steps to design and use the work breakdown structure?