SlideShare a Scribd company logo
1 | s a n i t a r y p i p e w o r k
CONTENT
No. Title Page
1. Appreciation 3
2. Introduction 4
3. Definition terms 5
4. 1. Explain why inspection and testing the soundness and
performance of sanitary pipe work under ground.
6
5. 2. State the statutory and recommended soundness and
performance requirements for sanitary pipe work, including
connected sanitary appliances.
7 - 8
6. 3. Describe the air test n use of smoke to locate leaks in the pipe
work in sanitary pipe work systems. 9 – 13
7. 4. Describe the hydraulic test for appliances and sanitary pipe
work. 14 – 16
8. 5. Describe methods of simulating peak flow and pipe work. 17
9. 6. State inspection and testing procedures for various systems of
sanitary pipe work. 18 - 24
10. Conclusion 25
11. Reference 26
2 | s a n i t a r y p i p e w o r k
CONTENT OF FIGURE
No. Title Page
1. Figure 1.0 Air Test 7
2. Figure 2.0 Shows the method of carrying out an air test. 10
3. Figure 2.1 Shows the method of carrying out a smoke test. 11
4. Figure 2.2 Show the smoke machine during a test. 11
5. Figure 2.3 The drain is plugged or stopped by either an expanding
drain plug 12
6. Figure 2.4 Show the drain an inflatable bag 12
7. Figure 2. 5 Shows the method the carry out the water test using a
rubber tube connected to a testing vessel. 15
8. Figure 4.0 Shows a method of testing the water using a rubber tube
connected to the former test. 19
9. Figure 4.1 Shows a method of testing the wind. 20
10. Figure 4.2 Smoke tests on the drain 21
11. Figure 4.3 Smoke machine used during the test 22
12. Figure 4.4 Rubber drainage retaining expand 22
13. Figure 4.5 Retaining the drainage bag expands 23
14. Figure 4.6 Tests to determine the straightness and obstruction 24
3 | s a n i t a r y p i p e w o r k
APPRECIATION
Assalamualaikum…
Praise is presented only for ALLAH Almighty Disposer of all things. Peace and
blessings be upon beloved Prophet Muhammad leaflets bearing the revelation to
illuminate be universe, the companions, his family, all the scholars and lovers of Islam
throughout the world.
Thank to God that, we can complete the assignment on the sanitary pipe work to
be handed over to Mr. Huzaime b. Abdul Hadi very well. By making this assignment we
can add my knowledge about of the sanitary pipe work. With this we can add my
knowledge and understanding about it.
Our assignment was explain a bit about the soundness and performance testing
of sanitary pipe work above ground.
Finally, we thank the lecturers who taught me, Mr. Huzaime b. Abdul Hadi has
been providing guidance and information on how to produce this work. Thank also to
friends who also give lessons and share ideas and information.
4 | s a n i t a r y p i p e w o r k
INTRODUCTION
PRINCIPLES OF DRAINAGE BELOW GROUND
An effective drainage system is required to drain the dirty material from a surface
water drainage building.If not strong and leak, the water that comes out of it may affect
the health of this public.Condition will cause erosion of land under the building site
resulting in a building that settles.
Drainage must meet the requirements of economic technical.Factor often
influence the flow system and the planning of a public sewer system building.If found in
the vicinity of, a more economical way to handle waste is by passing the materials into
the sewer route public.If public sewer line is within 30m of a construction site, local
authorities may determine that the building drainage system must be connected to
public sewer.
Sanitary pipe work is a system of pipes installed to permit the transfer of waste
water and sewage from building to foul drain. Also it provides a means of ventilation for
the drain so that there can be no build up unpleasant odors or methane gas within the
system which might accidentally permeate into the building. For efficient working of
disposal installation pipe work system, a number of design criteria should be fulfilled.
In the following section we will look at some of the terms related to sanitary pipe
work.
5 | s a n i t a r y p i p e w o r k
DEFINITION OF TERMS
Soil Waste
- This is discharged from water closets, urinals, slop sinks, and similar appliances.
Soil Pipe
- This pipe conveys the discharge of water closets or fixtures with similar function,
with or without the discharges from other fixtures.
6 | s a n i t a r y p i p e w o r k
1. Explain why inspection and testing the soundness and
performance of sanitary pipe work under ground.
After the drain has been laid and before backfilling,or placing concrete,or
granular material round the pipes,it should be tested by either water or air,If any leak
occurs,the defective pipe or joint should be rectified and the drain again tested.
Wherever possible,testing should be carried out between the manholes and short
branch drains tested along with the main drainage system.Long branch drains and
monholes should be separately. The test before backfilling should be carried out as
soon as is practicable and the pipe should be strutted,to prevent any movement of the
drain during the test. A temporary bend and stand pipe should be fitted at the head of
the drain and a stopper fitted at the lower end. Alternatively,the test may be applied by
means of a rubber tube connected to a vessel and the drain stopper.
7 | s a n i t a r y p i p e w o r k
2. State the statutory and recommended soundness and performance
requirements for sanitary pipe work, including connected sanitary
appliances.
Soundness Testing of Discharge System
Plug all open ends with Drain Plugs
Fill all traps with water
Attach water gauge manometer and pump up to 38mm
Figure 1.0 Air Test
Leave to stand for 3 minute
No drop is permitted
If there is a drop - check all joints with Leak Detection Spray
The Water Test is carried out on sanitary appliances is up to flood level of lowest
appliance
8 | s a n i t a r y p i p e w o r k
Performance Testing of Discharge System
Check that trap seals are retained after use
Test for self siphonage or induced siphonage
Fill all appliances to level of overflow and then remove plugs
Test depth of trap seal with dipstick (painted matt black)
Trap seal remaining MUST be at least 25mm
Effective Trap Seal Depth - from the soffit to the invert of the trap outlet
Testing for Tap Siphonage
Self Siphonage - discharge pipe is too small
Induced Siphonage - suck water out of the second trap
Momentum - trap seal as water is carried away by water flowing at high speed
9 | s a n i t a r y p i p e w o r k
3. Describe the air test n use of smoke to locate leaks in the pipe
work in sanitary pipe work systems.
AIR TEST
The length of drain to be tested should be plugged and air pumped into the pipe
until a pressure of slightly more than 100 mm water gauge is obtained. Where gullies
and / or ground - floor appliances are connected the test pressure should be slightly
more than 50 mm water gauge. A change in air temperature will affect the test pressure
and therefore 5 minutes should be allowed for pressure stabilization. The air pressure
should be adjusted to 100 mm water gauge as necessary. Without further pumping, the
head of water during a period of 5 minutes should not fall more than 25 mm and 12 mm
for a 100 mm and 50 mm water gauge test pressures respectively.
Figure 2.0 shows the method of carrying out an air test. The test is carried out by
fixing a stopper, sealed with a cap, at one end of the drain and pumping in air at the
other end until the U gauge shows the required head of water.
10 | s a n i t a r y p i p e w o r k
FIGURE 2.0 Shows the method of carrying out an air test.
SMOKE TEST
The use of smoke cartridges for this test is not to be recommended, due to the
possibility of the build up of high pressure inside the drain. The test by use of a smoke
machine is usually applied to existing drains with the purpose of locating a leak. In order
to ensure that the drain is filled with smoke, a rubber tube should be passed through the
water seal of gully traps, so that air contained inside the drain may escape. Figure2.1
shows the method of carrying out a smoke test. The test is carried out by placing a
stopper, sealed with a cap, at one end of the drain and pumping in smoke at the other.
11 | s a n i t a r y p i p e w o r k
FIGURE 2.1 Shows the method of carrying out a smoke test.
The dome rises with the action of the bellows and if the drain is sound is
maintained in this elevated position. Figure 2.2 show the smoke machine during a test.
FIGURE 2.2 Show the smoke machine during a test.
12 | s a n i t a r y p i p e w o r k
Types of Stoppers
The drain is plugged or stopped by either an expanding drain plug (Shown in
Figure 2.3) or by an inflatable bag ( Shown in Figure. 2.4 )
FIGURE 2.3 The drain is plugged or stopped by either an expanding drain plug
FIGURE 2.4 Show the drain an inflatable bag
13 | s a n i t a r y p i p e w o r k
Test for Straightness and Obstruction
This can be carried out by placing an electric torch at one end of the drain and
looking through a mirror at the other end of the drain. Any fault in alignment or
obstruction will be seen through the mirror.
Testing Manholes
A bag stopper should be fitted in the outlet of manhole and bag stoppers or
expanding plugs fitted at all other connections. The manhole should be filled with clean
water and allowed to stand for 8 hours for a absorption, topping up the water level as
necessary. The criterion for acceptance should be , that no appreciable flow of water
should pass through the manhole during a further 30 minutes.
14 | s a n i t a r y p i p e w o r k
4. Describe the hydraulic test for appliances and sanitary pipe work.
Building Regulation and Code of Practice Tests.
The Building Regulations 1992 ang the Code of Practice B.S 8301, Building
Drainage 1985 give the following procedures for carrying out test on gravity drains and
private sewers up to 300 mm in diameter.
WATER TEST
1. The drain should be filled with water to give a test pressure equal to 1.5 m head
of water above the soffit of the drain at the high end but not more than 4 m head
of water above the soffit for the drain at the low end. Steeply graded drains
should be tested in stages so that the head of water at the lower end does not
exceed 4 m. This is to prevent damage to the drain and if may be necessary to
test a drain in several sections.
2. The pipeline should be allowed to stand for 2 hours for absorption and topped up
with water as necessary. After 2 hours the loss of water from the pipeline should
be measured by noting the quantity of water needed to maintain the test head for
30 minutes. The rate of water loss should not exceed 1 litre/hour per metre
diameter, per metre run of pipe. For various pipe diameters the rate of loss per
metre run during the 30 minute period is 0.05 litre for 100 mm pipe; 0.8 litre for
150 mm pipe; 0.12 litre for 225 mm pipe and 0.15 litre for 300 mm pipe. Figure
3.0 shows the method the carry out the water test using a rubber tube connected
to a testing vessel.
15 | s a n i t a r y p i p e w o r k
Figure 3.0 Shows the method the carry out the water test using a rubber tube
connected to a testing vessel.
Alternatively, the test may be carry out by means of a temporary bend and stand-
pipe connected to the head of the drain. The fall of water in the vessel or stand-pipe
may be due to one or more of the following causes:
a) Absorption by Pipe or Joints
The initial absorption may be of the order of 5 per cent of the total weight of the
pipeline.
b) Trapped Air
This usually occurs at the joints and the amount will vary with the type of joint,
diameter of pipes and joints and the gradient. Eventually the air is absorbed by the
water, but this can take some time.
16 | s a n i t a r y p i p e w o r k
c) Sweating of Pipe and Joints
Occasionally pipes and joints under water pressure may sweat slightly, but this
should not be considered a cause for rejection of the pipeline.
d) Leakage from Defective Pipes or Joints
The defective pipe or joint should be taken out and replaced and the pipeline re-
tested.
e) Leakage from Stoppers
These should be tightened, but if the leakage continues a new plug should be
inserted. Sometimes a leakage can occur on the threaded portion of the plug. All
equipment used for testing should be thoroughly checked before being used and the
rubber surfaces of plugs should be free from grit.
FINAL WATER TEST
There is a risk that the drain of private sewer can be damage during backfilling or
surrounding the pipeline with concrete. The final test therefore should be carried out
after the backfilling or concreting has been completed.
17 | s a n i t a r y p i p e w o r k
5. Describe methods of simulating peak flow and pipe work.
Flow in the pipe nowadays is very important as a medium to move a fluid from
one destination to another. Generally it used at indushial plant, to supply a water at
homea nde tc. Visualizationa nd Simulationo f Fluid Flows in a Piping Systemi s an
application system developed to solve and also overcome problems in fluid motion
field. The problem that existedi s the diffrculties to determinea n appearanceo f fluid
motion. Analytical and mathematical approach alone does not solve the problems
thosee xist. Therefore,t he new approachess ucha s visualizationa nd simulationa s a
support for the solution has helped to solve the problem. This study only focus on
laminar flow and specific on liquid which are water and used only single straighten
piping system made of from PI/C.
18 | s a n i t a r y p i p e w o r k
6. State inspection and testing procedures for various systems of
sanitary pipe work.
Water Test
1. Drainage should be connected to the water supply to be equal to the test
pressure of 1.5 m column of water above the soffit of the drainage at the highest
end, but not more than 4 m column of water above the soffit of the drainage at
the lowest end.
2. Very steep drainage should be tested in stages so that the water column at the
lowest end will not be covers many 4 m. aims to prevent damage to drainage and
tests should be done for a number of sections.
3. Pipe line must be left for 2 hours to allow the absorption and addition of water.
4. After 2 hours, loss of water from the pipeline must be measured by observing the
volume of water to be added to keep the test columns for 30 minutes.
5. Water loss rate must not exceed 1 liter / hr per meter diameter, per meter length
of pipe.
6. For pipes of variable diameter, the loss per meter length of pipe for 30 minutes is
0.05 liters to 100 mm diameter pipe, 12:08 liters to 150 mm diameter pipe, 12:12
liters to 225 mm diameter pipe and 0.15 liters for 300 diameter pipe mm.
7. Alternatively, the test can be done using a temporary bend and vertical pipe
connected to the column drainage.
19 | s a n i t a r y p i p e w o r k
8. In addition, the drainage must be supported to prevent movement of the drain
when it rains. decrease in water level in the container or vertical pipe during the
test due to the diffusion of pipes and connections, leaking pipes or connections
for damage, leakage at the conclusion of the test and the trapped air.
9. Some pipes absorbs more water or air traps more content than the rest of the
jacks. therefore, water should be added to maintain the test head test within 30
minutes.
Figure 4.0 Shows a method of testing the water using a rubber tube connected to the
former test.
20 | s a n i t a r y p i p e w o r k
Wind Test
1. Long drainage to be tested must be plugged and air pumped into the pipe until
the pressure is slightly higher than the 100 mm water gauge.
2. When gegeluk and ground equipment is connected, the test pressure must be
slightly higher than the 50 mm water gauge.
3. Changes in air temperature can affect the test pressure. Therefore, the pressure
must be kept stable in the last 5 minutes.
4. Air pressure should be adjusted to 100 mm or 50 mm water gauge, according as
may be required.
5. Without further pumping, the water column within 5 minutes should not be
dropped more than 25 mm for the test pressure of 100 mm and 12 mm water
gauge to test pressure of 50 mm water gauge.
6. Test was done by fitting a retainer, sealed with a lid, at one end of the drain and
the air is pumped in through the other end until the gauge-U indicates the desired
value of the water column.
Figure 4.1 Shows a method of testing the wind.
21 | s a n i t a r y p i p e w o r k
Smoke Test
1. Drainage should be plugged and connected to the smoke machine on the bottom
retainer.
2. Test was conducted by pumping smoke into the drain with a smoke machine to
vault up to the required height.
3. During the test was performed, the dome should be at steady state and drainage
to be examined to detect any leakage of smoke.
Figure 4.2 Smoke tests on the drain
22 | s a n i t a r y p i p e w o r k
Figure 4.3 Smoke machine used during the test
Figure 4.4 Rubber drainage retaining expand
23 | s a n i t a r y p i p e w o r k
Figure 4.5 Retaining the drainage bag expands
24 | s a n i t a r y p i p e w o r k
Straightness and resistance test
1. This test is maintained by placing a mirror at one end of the drainage and lighting
and the other end.
2. Light is seen through a mirror can show whether the drainage is straight or pu,
respectively.
Figure 4.6 Tests to determine the straightness and obstruction
25 | s a n i t a r y p i p e w o r k
CONCLUSION
Drainage must meet the requirements of economic technical.Factor often
influence the flow system and the planning of a public sewer system building.If found in
the vicinity of, a more economical way to handle waste is by passing the materials into
the sewer route public. Wherever possible,testing should be carried out between the
manholes and short branch drains tested along with the main drainage system.Long
branch drains and monholes should be separately. A temporary bend and stand pipe
should be fitted at the head of the drain and a stopper fitted at the lower end.
The air test use of smoke to located leaks in the pipe work in sanitary pipe work
systems air test The length of drain to be tested should be plugged and air pumped into
the pipe until a pressure of slightly more than 100 mm water gauge is obtained. Test for
Straightness and Obstruction This can be carried out by placing an electric torch at one
end of the drain and looking through a mirror at the other end of the drain.
26 | s a n i t a r y p i p e w o r k
REFERENCES
 BUILDING SERVICES AND EQUIPMENT
THIRD EDITION FREDERICK HALL
 F.HALL EDISI KEDUA KERJA PAIP : PEMBEKALAN AIR
SEJUK,SALIRAN DAN PEMBERSIHAN,Penerbit Universiti Teknologi
Malaysia Skudai Johor Darul Takzim 1999

More Related Content

What's hot

Building drainage system
Building drainage systemBuilding drainage system
Building drainage system
Dipesh Jain
 
Cold water supply system & Components
Cold water supply system & ComponentsCold water supply system & Components
Cold water supply system & Components
ashikin
 
Part 1 - Water Supply in Buildings.pdf
Part 1 - Water Supply in Buildings.pdfPart 1 - Water Supply in Buildings.pdf
Part 1 - Water Supply in Buildings.pdf
Ignacio J. Palma, Arch PhD.
 
TRAPS AND ITS TYPES USED IN A BUILDING
TRAPS AND ITS TYPES USED IN A  BUILDING TRAPS AND ITS TYPES USED IN A  BUILDING
TRAPS AND ITS TYPES USED IN A BUILDING
BISHAL KHANAL
 
Sanitary and water supply
Sanitary and water supplySanitary and water supply
Fitting and fixtures
Fitting and fixturesFitting and fixtures
Fitting and fixtures
Nikhar Mehra
 
Sem 2 bs1 Hot water supply system 2
Sem 2 bs1 Hot water supply system 2Sem 2 bs1 Hot water supply system 2
Sem 2 bs1 Hot water supply system 2
Est
 
Hot water-supply-system-presentation-slides(1)
Hot water-supply-system-presentation-slides(1)Hot water-supply-system-presentation-slides(1)
Hot water-supply-system-presentation-slides(1)
Jackytiongleesong
 
Drainage System For a Building
Drainage System For a BuildingDrainage System For a Building
Drainage System For a Building
Aroh Thombre
 
SANITARY AND WATER SUPPLY
SANITARY AND WATER SUPPLYSANITARY AND WATER SUPPLY
SANITARY AND WATER SUPPLY
RIDDHESH VARIK
 
Types of traps
Types of trapsTypes of traps
Types of traps
bishan singh
 
Service pipes and water mains
Service pipes and water mainsService pipes and water mains
Service pipes and water mains
Pooja Vishwanath
 
DRAINAGE SYSTEM FOR BUILDING AND TRAPS
DRAINAGE SYSTEM FOR BUILDING AND TRAPSDRAINAGE SYSTEM FOR BUILDING AND TRAPS
DRAINAGE SYSTEM FOR BUILDING AND TRAPS
Karan Patel
 
Cold Water Supply Distribution In Building
Cold Water Supply Distribution In BuildingCold Water Supply Distribution In Building
Cold Water Supply Distribution In Building
Van Heina
 
Manholes, by mayank agrawal
Manholes, by mayank agrawalManholes, by mayank agrawal
Manholes, by mayank agrawal
Mayank Agrawal
 
08 Building Water Supply and Sanitary Fixtures
08 Building Water Supply and Sanitary Fixtures08 Building Water Supply and Sanitary Fixtures
08 Building Water Supply and Sanitary Fixtures
akashpadole
 
House Drainage System
House Drainage SystemHouse Drainage System
House Drainage System
Eddy Ankit Gangani
 
Drainage system one pipe
Drainage system   one pipeDrainage system   one pipe
Drainage system one pipe
Rabia S
 
Types of pitched roofs
Types of pitched roofsTypes of pitched roofs
Types of pitched roofs
anandcivil103
 

What's hot (20)

Building drainage system
Building drainage systemBuilding drainage system
Building drainage system
 
Traps
TrapsTraps
Traps
 
Cold water supply system & Components
Cold water supply system & ComponentsCold water supply system & Components
Cold water supply system & Components
 
Part 1 - Water Supply in Buildings.pdf
Part 1 - Water Supply in Buildings.pdfPart 1 - Water Supply in Buildings.pdf
Part 1 - Water Supply in Buildings.pdf
 
TRAPS AND ITS TYPES USED IN A BUILDING
TRAPS AND ITS TYPES USED IN A  BUILDING TRAPS AND ITS TYPES USED IN A  BUILDING
TRAPS AND ITS TYPES USED IN A BUILDING
 
Sanitary and water supply
Sanitary and water supplySanitary and water supply
Sanitary and water supply
 
Fitting and fixtures
Fitting and fixturesFitting and fixtures
Fitting and fixtures
 
Sem 2 bs1 Hot water supply system 2
Sem 2 bs1 Hot water supply system 2Sem 2 bs1 Hot water supply system 2
Sem 2 bs1 Hot water supply system 2
 
Hot water-supply-system-presentation-slides(1)
Hot water-supply-system-presentation-slides(1)Hot water-supply-system-presentation-slides(1)
Hot water-supply-system-presentation-slides(1)
 
Drainage System For a Building
Drainage System For a BuildingDrainage System For a Building
Drainage System For a Building
 
SANITARY AND WATER SUPPLY
SANITARY AND WATER SUPPLYSANITARY AND WATER SUPPLY
SANITARY AND WATER SUPPLY
 
Types of traps
Types of trapsTypes of traps
Types of traps
 
Service pipes and water mains
Service pipes and water mainsService pipes and water mains
Service pipes and water mains
 
DRAINAGE SYSTEM FOR BUILDING AND TRAPS
DRAINAGE SYSTEM FOR BUILDING AND TRAPSDRAINAGE SYSTEM FOR BUILDING AND TRAPS
DRAINAGE SYSTEM FOR BUILDING AND TRAPS
 
Cold Water Supply Distribution In Building
Cold Water Supply Distribution In BuildingCold Water Supply Distribution In Building
Cold Water Supply Distribution In Building
 
Manholes, by mayank agrawal
Manholes, by mayank agrawalManholes, by mayank agrawal
Manholes, by mayank agrawal
 
08 Building Water Supply and Sanitary Fixtures
08 Building Water Supply and Sanitary Fixtures08 Building Water Supply and Sanitary Fixtures
08 Building Water Supply and Sanitary Fixtures
 
House Drainage System
House Drainage SystemHouse Drainage System
House Drainage System
 
Drainage system one pipe
Drainage system   one pipeDrainage system   one pipe
Drainage system one pipe
 
Types of pitched roofs
Types of pitched roofsTypes of pitched roofs
Types of pitched roofs
 

Viewers also liked

S3 SEWAGE STORAGE, TREATMENT AND DISPOSAL Assignment
S3 SEWAGE STORAGE, TREATMENT AND DISPOSAL AssignmentS3 SEWAGE STORAGE, TREATMENT AND DISPOSAL Assignment
S3 SEWAGE STORAGE, TREATMENT AND DISPOSAL Assignment
no suhaila
 
Presentation plumbing
Presentation plumbingPresentation plumbing
Presentation plumbingLiguidliguid
 
Basic Plumbing System
Basic Plumbing System Basic Plumbing System
Basic Plumbing System
haroldtaylor1113
 
Water distribution system
Water distribution systemWater distribution system
Water distribution system
Bibhabasu Mohanty
 
Water supply system
Water supply systemWater supply system
Water supply system
aishah
 
P.P.T on water distribution system by Manish Pandey
P.P.T on water distribution system by Manish PandeyP.P.T on water distribution system by Manish Pandey
P.P.T on water distribution system by Manish Pandey
Manish Pandey
 
Water distribution system design report
Water distribution system design reportWater distribution system design report
Water distribution system design report
Muhammad Magsi
 
Assignment on Interview of a Principal of a Teacher Education Institute
Assignment on Interview of a Principal of a Teacher Education InstituteAssignment on Interview of a Principal of a Teacher Education Institute
Assignment on Interview of a Principal of a Teacher Education Institute
fatima roshan
 
plumbing
plumbingplumbing
plumbing
Piyush Dhola
 
House Drainage System
House Drainage SystemHouse Drainage System
House Drainage System
GAURAV. H .TANDON
 
Sanitary fitting
Sanitary fittingSanitary fitting
Sanitary fitting
AB MAKASANA
 
LIGHT AND LIGHTING FIXTURES
LIGHT AND LIGHTING FIXTURESLIGHT AND LIGHTING FIXTURES
LIGHT AND LIGHTING FIXTURESShamba Sarkar
 
60 Plumbing Terms Homeowners Should Know
60 Plumbing Terms Homeowners Should Know60 Plumbing Terms Homeowners Should Know
60 Plumbing Terms Homeowners Should Know
Apollo Drain & Rooter Service, Inc.
 
project-sewer construction
project-sewer constructionproject-sewer construction
project-sewer constructionMayank Gautam
 
Drainsandsewers unit7 By K R Thanki
Drainsandsewers unit7 By K R Thanki Drainsandsewers unit7 By K R Thanki
Drainsandsewers unit7 By K R Thanki
Krunal Thanki
 
plumber
plumberplumber
EP LAB MANUAL
EP LAB MANUALEP LAB MANUAL
EP LAB MANUAL
Sethu Ram
 
Practical Work Report - Fletcher
Practical Work Report - FletcherPractical Work Report - Fletcher
Practical Work Report - FletcherJade Keswick
 

Viewers also liked (20)

Bs assignment
Bs assignmentBs assignment
Bs assignment
 
S3 SEWAGE STORAGE, TREATMENT AND DISPOSAL Assignment
S3 SEWAGE STORAGE, TREATMENT AND DISPOSAL AssignmentS3 SEWAGE STORAGE, TREATMENT AND DISPOSAL Assignment
S3 SEWAGE STORAGE, TREATMENT AND DISPOSAL Assignment
 
Presentation plumbing
Presentation plumbingPresentation plumbing
Presentation plumbing
 
Basic Plumbing System
Basic Plumbing System Basic Plumbing System
Basic Plumbing System
 
Water distribution system
Water distribution systemWater distribution system
Water distribution system
 
Water supply system
Water supply systemWater supply system
Water supply system
 
P.P.T on water distribution system by Manish Pandey
P.P.T on water distribution system by Manish PandeyP.P.T on water distribution system by Manish Pandey
P.P.T on water distribution system by Manish Pandey
 
Water distribution system design report
Water distribution system design reportWater distribution system design report
Water distribution system design report
 
Assignment on Interview of a Principal of a Teacher Education Institute
Assignment on Interview of a Principal of a Teacher Education InstituteAssignment on Interview of a Principal of a Teacher Education Institute
Assignment on Interview of a Principal of a Teacher Education Institute
 
plumbing
plumbingplumbing
plumbing
 
House Drainage System
House Drainage SystemHouse Drainage System
House Drainage System
 
Example of acknowledgment
Example of acknowledgmentExample of acknowledgment
Example of acknowledgment
 
Sanitary fitting
Sanitary fittingSanitary fitting
Sanitary fitting
 
LIGHT AND LIGHTING FIXTURES
LIGHT AND LIGHTING FIXTURESLIGHT AND LIGHTING FIXTURES
LIGHT AND LIGHTING FIXTURES
 
60 Plumbing Terms Homeowners Should Know
60 Plumbing Terms Homeowners Should Know60 Plumbing Terms Homeowners Should Know
60 Plumbing Terms Homeowners Should Know
 
project-sewer construction
project-sewer constructionproject-sewer construction
project-sewer construction
 
Drainsandsewers unit7 By K R Thanki
Drainsandsewers unit7 By K R Thanki Drainsandsewers unit7 By K R Thanki
Drainsandsewers unit7 By K R Thanki
 
plumber
plumberplumber
plumber
 
EP LAB MANUAL
EP LAB MANUALEP LAB MANUAL
EP LAB MANUAL
 
Practical Work Report - Fletcher
Practical Work Report - FletcherPractical Work Report - Fletcher
Practical Work Report - Fletcher
 

Similar to S3 SANITARY PIPE WORK ASSIGNMENT

Unit 5 final
Unit 5 finalUnit 5 final
Unit 5 finaliampichu
 
Maintenance of sewer
Maintenance of sewerMaintenance of sewer
Maintenance of sewer
dhara dattani
 
Environmental engineering PPT
Environmental engineering PPTEnvironmental engineering PPT
Environmental engineering PPT
Kavin Raval
 
Tightness testing of gravity pipelines
Tightness testing of gravity pipelinesTightness testing of gravity pipelines
Tightness testing of gravity pipelines
Vladimir Popovic
 
Hydrostatic pressure testing of PE pipelines (handbook) as per EN805
Hydrostatic pressure testing of PE pipelines (handbook) as per EN805Hydrostatic pressure testing of PE pipelines (handbook) as per EN805
Hydrostatic pressure testing of PE pipelines (handbook) as per EN805
Vladimir Popovic
 
sewage layy out lec
sewage layy out lecsewage layy out lec
sewage layy out lec
shams ur rehman
 
Piping design sheets
Piping design sheetsPiping design sheets
Piping design sheets
Subramaniam Chandrasekaran
 
Leak testing-steam-turbine-condensers-application
Leak testing-steam-turbine-condensers-applicationLeak testing-steam-turbine-condensers-application
Leak testing-steam-turbine-condensers-application
Udhayakumar Venkataraman
 
Hazard operability study - in Industires and plant
Hazard operability study - in Industires and plantHazard operability study - in Industires and plant
Hazard operability study - in Industires and plant
JayaKarthic1
 
HAZOP.ppt
HAZOP.pptHAZOP.ppt
HAZOP.ppt
JayaKarthic1
 
MANUALS FOR FLUID MECHANICS LAB.pdf
MANUALS FOR FLUID MECHANICS LAB.pdfMANUALS FOR FLUID MECHANICS LAB.pdf
MANUALS FOR FLUID MECHANICS LAB.pdf
amgothusandeep
 
Ky3419651971
Ky3419651971Ky3419651971
Ky3419651971
IJERA Editor
 
S3 End Of Chapter - Loss of a Trap Seal
S3 End Of Chapter - Loss of a Trap SealS3 End Of Chapter - Loss of a Trap Seal
S3 End Of Chapter - Loss of a Trap Seal
no suhaila
 
singh_rohitendra
singh_rohitendrasingh_rohitendra
singh_rohitendraRoy Singh
 
Download-manuals-water quality-wq-manuals-gwvolume6fieldmanualwaterqualitysa...
 Download-manuals-water quality-wq-manuals-gwvolume6fieldmanualwaterqualitysa... Download-manuals-water quality-wq-manuals-gwvolume6fieldmanualwaterqualitysa...
Download-manuals-water quality-wq-manuals-gwvolume6fieldmanualwaterqualitysa...hydrologywebsite1
 
Download-manuals-water quality-wq-manuals-gwvolume6fieldmanualwaterqualitysa...
 Download-manuals-water quality-wq-manuals-gwvolume6fieldmanualwaterqualitysa... Download-manuals-water quality-wq-manuals-gwvolume6fieldmanualwaterqualitysa...
Download-manuals-water quality-wq-manuals-gwvolume6fieldmanualwaterqualitysa...hydrologyproject001
 
L 44 leakge management
L 44 leakge managementL 44 leakge management
L 44 leakge management
Dr. shrikant jahagirdar
 
CO2QUEST – Instrumentation and measurement of large-scale releases of impure ...
CO2QUEST – Instrumentation and measurement of large-scale releases of impure ...CO2QUEST – Instrumentation and measurement of large-scale releases of impure ...
CO2QUEST – Instrumentation and measurement of large-scale releases of impure ...
UK Carbon Capture and Storage Research Centre
 

Similar to S3 SANITARY PIPE WORK ASSIGNMENT (20)

Unit 5 final
Unit 5 finalUnit 5 final
Unit 5 final
 
Maintenance of sewer
Maintenance of sewerMaintenance of sewer
Maintenance of sewer
 
Environmental engineering PPT
Environmental engineering PPTEnvironmental engineering PPT
Environmental engineering PPT
 
Tightness testing of gravity pipelines
Tightness testing of gravity pipelinesTightness testing of gravity pipelines
Tightness testing of gravity pipelines
 
Hydrostatic pressure testing of PE pipelines (handbook) as per EN805
Hydrostatic pressure testing of PE pipelines (handbook) as per EN805Hydrostatic pressure testing of PE pipelines (handbook) as per EN805
Hydrostatic pressure testing of PE pipelines (handbook) as per EN805
 
sewage layy out lec
sewage layy out lecsewage layy out lec
sewage layy out lec
 
Edited j6.doc
Edited j6.docEdited j6.doc
Edited j6.doc
 
Piping design sheets
Piping design sheetsPiping design sheets
Piping design sheets
 
Leak testing-steam-turbine-condensers-application
Leak testing-steam-turbine-condensers-applicationLeak testing-steam-turbine-condensers-application
Leak testing-steam-turbine-condensers-application
 
Hazard operability study - in Industires and plant
Hazard operability study - in Industires and plantHazard operability study - in Industires and plant
Hazard operability study - in Industires and plant
 
HAZOP.ppt
HAZOP.pptHAZOP.ppt
HAZOP.ppt
 
MANUALS FOR FLUID MECHANICS LAB.pdf
MANUALS FOR FLUID MECHANICS LAB.pdfMANUALS FOR FLUID MECHANICS LAB.pdf
MANUALS FOR FLUID MECHANICS LAB.pdf
 
Ky3419651971
Ky3419651971Ky3419651971
Ky3419651971
 
Hydraulicdesignofsewer
HydraulicdesignofsewerHydraulicdesignofsewer
Hydraulicdesignofsewer
 
S3 End Of Chapter - Loss of a Trap Seal
S3 End Of Chapter - Loss of a Trap SealS3 End Of Chapter - Loss of a Trap Seal
S3 End Of Chapter - Loss of a Trap Seal
 
singh_rohitendra
singh_rohitendrasingh_rohitendra
singh_rohitendra
 
Download-manuals-water quality-wq-manuals-gwvolume6fieldmanualwaterqualitysa...
 Download-manuals-water quality-wq-manuals-gwvolume6fieldmanualwaterqualitysa... Download-manuals-water quality-wq-manuals-gwvolume6fieldmanualwaterqualitysa...
Download-manuals-water quality-wq-manuals-gwvolume6fieldmanualwaterqualitysa...
 
Download-manuals-water quality-wq-manuals-gwvolume6fieldmanualwaterqualitysa...
 Download-manuals-water quality-wq-manuals-gwvolume6fieldmanualwaterqualitysa... Download-manuals-water quality-wq-manuals-gwvolume6fieldmanualwaterqualitysa...
Download-manuals-water quality-wq-manuals-gwvolume6fieldmanualwaterqualitysa...
 
L 44 leakge management
L 44 leakge managementL 44 leakge management
L 44 leakge management
 
CO2QUEST – Instrumentation and measurement of large-scale releases of impure ...
CO2QUEST – Instrumentation and measurement of large-scale releases of impure ...CO2QUEST – Instrumentation and measurement of large-scale releases of impure ...
CO2QUEST – Instrumentation and measurement of large-scale releases of impure ...
 

More from no suhaila

INTERIOR LIGHTING DESIGN A STUDENT'S GUIDE
INTERIOR LIGHTING DESIGN A STUDENT'S GUIDEINTERIOR LIGHTING DESIGN A STUDENT'S GUIDE
INTERIOR LIGHTING DESIGN A STUDENT'S GUIDE
no suhaila
 
Interior Lighting Guide - Interior Lighting Bringing Rooms To Life
Interior Lighting Guide - Interior Lighting Bringing Rooms To LifeInterior Lighting Guide - Interior Lighting Bringing Rooms To Life
Interior Lighting Guide - Interior Lighting Bringing Rooms To Life
no suhaila
 
Boiler Feed Water Control
Boiler Feed Water ControlBoiler Feed Water Control
Boiler Feed Water Controlno suhaila
 
Introduction to Boiler Control Systems
Introduction to Boiler Control SystemsIntroduction to Boiler Control Systems
Introduction to Boiler Control Systems
no suhaila
 
INSTRUMENTATION AND PROCESS CONTROL - BOILER CONTROL
INSTRUMENTATION AND PROCESS CONTROL - BOILER CONTROLINSTRUMENTATION AND PROCESS CONTROL - BOILER CONTROL
INSTRUMENTATION AND PROCESS CONTROL - BOILER CONTROLno suhaila
 
Led Lighting (CIBSE Code for Interior Lighting, 1994)
Led Lighting (CIBSE Code for Interior Lighting, 1994)Led Lighting (CIBSE Code for Interior Lighting, 1994)
Led Lighting (CIBSE Code for Interior Lighting, 1994)
no suhaila
 
Risk Management Process
Risk Management ProcessRisk Management Process
Risk Management Processno suhaila
 
A Guide to Risk Control Plans
A Guide to Risk Control PlansA Guide to Risk Control Plans
A Guide to Risk Control Plansno suhaila
 
Fia Best Practice Guide to Fire Safety
Fia Best Practice Guide to Fire SafetyFia Best Practice Guide to Fire Safety
Fia Best Practice Guide to Fire Safetyno suhaila
 
Guidance on the prevention and control of fire and explosion at mines used fo...
Guidance on the prevention and control of fire and explosion at mines used fo...Guidance on the prevention and control of fire and explosion at mines used fo...
Guidance on the prevention and control of fire and explosion at mines used fo...no suhaila
 
Controling osh hazards and risks
Controling osh hazards and risksControling osh hazards and risks
Controling osh hazards and risks
no suhaila
 
S3 Supply Devices and Room Air Distribution
S3 Supply Devices and Room Air DistributionS3 Supply Devices and Room Air Distribution
S3 Supply Devices and Room Air Distribution
no suhaila
 
S3 Embryo
S3 EmbryoS3 Embryo
S3 Embryo
no suhaila
 
S3 Bab 2 Manusia dan Masyrakat
S3 Bab 2 Manusia dan MasyrakatS3 Bab 2 Manusia dan Masyrakat
S3 Bab 2 Manusia dan Masyrakat
no suhaila
 
S3 Tamadun islam zaman nabi muhammad s.a.w (zaman makkiyah n madaniah) (1)
S3 Tamadun islam zaman nabi muhammad s.a.w (zaman makkiyah n madaniah) (1)S3 Tamadun islam zaman nabi muhammad s.a.w (zaman makkiyah n madaniah) (1)
S3 Tamadun islam zaman nabi muhammad s.a.w (zaman makkiyah n madaniah) (1)
no suhaila
 
S3 PEMBENTANGAN PERKEMBANGAN TAMADUN ISLAM ERA SAHABAT
S3 PEMBENTANGAN PERKEMBANGAN TAMADUN ISLAM ERA SAHABATS3 PEMBENTANGAN PERKEMBANGAN TAMADUN ISLAM ERA SAHABAT
S3 PEMBENTANGAN PERKEMBANGAN TAMADUN ISLAM ERA SAHABAT
no suhaila
 
S3 Minor Losses Assignment
S3 Minor Losses AssignmentS3 Minor Losses Assignment
S3 Minor Losses Assignment
no suhaila
 
S3 Reynolds Number Presentation
S3 Reynolds Number PresentationS3 Reynolds Number Presentation
S3 Reynolds Number Presentation
no suhaila
 
S3 Chapter 1 Introduction of Fluid
S3 Chapter 1 Introduction of FluidS3 Chapter 1 Introduction of Fluid
S3 Chapter 1 Introduction of Fluid
no suhaila
 
S3 Minor Losses Presentation
S3 Minor Losses PresentationS3 Minor Losses Presentation
S3 Minor Losses Presentation
no suhaila
 

More from no suhaila (20)

INTERIOR LIGHTING DESIGN A STUDENT'S GUIDE
INTERIOR LIGHTING DESIGN A STUDENT'S GUIDEINTERIOR LIGHTING DESIGN A STUDENT'S GUIDE
INTERIOR LIGHTING DESIGN A STUDENT'S GUIDE
 
Interior Lighting Guide - Interior Lighting Bringing Rooms To Life
Interior Lighting Guide - Interior Lighting Bringing Rooms To LifeInterior Lighting Guide - Interior Lighting Bringing Rooms To Life
Interior Lighting Guide - Interior Lighting Bringing Rooms To Life
 
Boiler Feed Water Control
Boiler Feed Water ControlBoiler Feed Water Control
Boiler Feed Water Control
 
Introduction to Boiler Control Systems
Introduction to Boiler Control SystemsIntroduction to Boiler Control Systems
Introduction to Boiler Control Systems
 
INSTRUMENTATION AND PROCESS CONTROL - BOILER CONTROL
INSTRUMENTATION AND PROCESS CONTROL - BOILER CONTROLINSTRUMENTATION AND PROCESS CONTROL - BOILER CONTROL
INSTRUMENTATION AND PROCESS CONTROL - BOILER CONTROL
 
Led Lighting (CIBSE Code for Interior Lighting, 1994)
Led Lighting (CIBSE Code for Interior Lighting, 1994)Led Lighting (CIBSE Code for Interior Lighting, 1994)
Led Lighting (CIBSE Code for Interior Lighting, 1994)
 
Risk Management Process
Risk Management ProcessRisk Management Process
Risk Management Process
 
A Guide to Risk Control Plans
A Guide to Risk Control PlansA Guide to Risk Control Plans
A Guide to Risk Control Plans
 
Fia Best Practice Guide to Fire Safety
Fia Best Practice Guide to Fire SafetyFia Best Practice Guide to Fire Safety
Fia Best Practice Guide to Fire Safety
 
Guidance on the prevention and control of fire and explosion at mines used fo...
Guidance on the prevention and control of fire and explosion at mines used fo...Guidance on the prevention and control of fire and explosion at mines used fo...
Guidance on the prevention and control of fire and explosion at mines used fo...
 
Controling osh hazards and risks
Controling osh hazards and risksControling osh hazards and risks
Controling osh hazards and risks
 
S3 Supply Devices and Room Air Distribution
S3 Supply Devices and Room Air DistributionS3 Supply Devices and Room Air Distribution
S3 Supply Devices and Room Air Distribution
 
S3 Embryo
S3 EmbryoS3 Embryo
S3 Embryo
 
S3 Bab 2 Manusia dan Masyrakat
S3 Bab 2 Manusia dan MasyrakatS3 Bab 2 Manusia dan Masyrakat
S3 Bab 2 Manusia dan Masyrakat
 
S3 Tamadun islam zaman nabi muhammad s.a.w (zaman makkiyah n madaniah) (1)
S3 Tamadun islam zaman nabi muhammad s.a.w (zaman makkiyah n madaniah) (1)S3 Tamadun islam zaman nabi muhammad s.a.w (zaman makkiyah n madaniah) (1)
S3 Tamadun islam zaman nabi muhammad s.a.w (zaman makkiyah n madaniah) (1)
 
S3 PEMBENTANGAN PERKEMBANGAN TAMADUN ISLAM ERA SAHABAT
S3 PEMBENTANGAN PERKEMBANGAN TAMADUN ISLAM ERA SAHABATS3 PEMBENTANGAN PERKEMBANGAN TAMADUN ISLAM ERA SAHABAT
S3 PEMBENTANGAN PERKEMBANGAN TAMADUN ISLAM ERA SAHABAT
 
S3 Minor Losses Assignment
S3 Minor Losses AssignmentS3 Minor Losses Assignment
S3 Minor Losses Assignment
 
S3 Reynolds Number Presentation
S3 Reynolds Number PresentationS3 Reynolds Number Presentation
S3 Reynolds Number Presentation
 
S3 Chapter 1 Introduction of Fluid
S3 Chapter 1 Introduction of FluidS3 Chapter 1 Introduction of Fluid
S3 Chapter 1 Introduction of Fluid
 
S3 Minor Losses Presentation
S3 Minor Losses PresentationS3 Minor Losses Presentation
S3 Minor Losses Presentation
 

Recently uploaded

Natural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama UniversityNatural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama University
Akanksha trivedi rama nursing college kanpur.
 
special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
Special education needs
 
The Diamond Necklace by Guy De Maupassant.pptx
The Diamond Necklace by Guy De Maupassant.pptxThe Diamond Necklace by Guy De Maupassant.pptx
The Diamond Necklace by Guy De Maupassant.pptx
DhatriParmar
 
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
Nguyen Thanh Tu Collection
 
Acetabularia Information For Class 9 .docx
Acetabularia Information For Class 9  .docxAcetabularia Information For Class 9  .docx
Acetabularia Information For Class 9 .docx
vaibhavrinwa19
 
Francesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptxFrancesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptx
EduSkills OECD
 
Thesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.pptThesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.ppt
EverAndrsGuerraGuerr
 
A Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptxA Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptx
thanhdowork
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
Sandy Millin
 
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
Levi Shapiro
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
camakaiclarkmusic
 
Unit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdfUnit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdf
Thiyagu K
 
Pride Month Slides 2024 David Douglas School District
Pride Month Slides 2024 David Douglas School DistrictPride Month Slides 2024 David Douglas School District
Pride Month Slides 2024 David Douglas School District
David Douglas School District
 
Digital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments UnitDigital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments Unit
chanes7
 
S1-Introduction-Biopesticides in ICM.pptx
S1-Introduction-Biopesticides in ICM.pptxS1-Introduction-Biopesticides in ICM.pptx
S1-Introduction-Biopesticides in ICM.pptx
tarandeep35
 
Azure Interview Questions and Answers PDF By ScholarHat
Azure Interview Questions and Answers PDF By ScholarHatAzure Interview Questions and Answers PDF By ScholarHat
Azure Interview Questions and Answers PDF By ScholarHat
Scholarhat
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
JosvitaDsouza2
 
Chapter 4 - Islamic Financial Institutions in Malaysia.pptx
Chapter 4 - Islamic Financial Institutions in Malaysia.pptxChapter 4 - Islamic Financial Institutions in Malaysia.pptx
Chapter 4 - Islamic Financial Institutions in Malaysia.pptx
Mohd Adib Abd Muin, Senior Lecturer at Universiti Utara Malaysia
 
Lapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdfLapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdf
Jean Carlos Nunes Paixão
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
Jisc
 

Recently uploaded (20)

Natural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama UniversityNatural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama University
 
special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
 
The Diamond Necklace by Guy De Maupassant.pptx
The Diamond Necklace by Guy De Maupassant.pptxThe Diamond Necklace by Guy De Maupassant.pptx
The Diamond Necklace by Guy De Maupassant.pptx
 
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
 
Acetabularia Information For Class 9 .docx
Acetabularia Information For Class 9  .docxAcetabularia Information For Class 9  .docx
Acetabularia Information For Class 9 .docx
 
Francesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptxFrancesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptx
 
Thesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.pptThesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.ppt
 
A Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptxA Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptx
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
 
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
 
Unit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdfUnit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdf
 
Pride Month Slides 2024 David Douglas School District
Pride Month Slides 2024 David Douglas School DistrictPride Month Slides 2024 David Douglas School District
Pride Month Slides 2024 David Douglas School District
 
Digital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments UnitDigital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments Unit
 
S1-Introduction-Biopesticides in ICM.pptx
S1-Introduction-Biopesticides in ICM.pptxS1-Introduction-Biopesticides in ICM.pptx
S1-Introduction-Biopesticides in ICM.pptx
 
Azure Interview Questions and Answers PDF By ScholarHat
Azure Interview Questions and Answers PDF By ScholarHatAzure Interview Questions and Answers PDF By ScholarHat
Azure Interview Questions and Answers PDF By ScholarHat
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
 
Chapter 4 - Islamic Financial Institutions in Malaysia.pptx
Chapter 4 - Islamic Financial Institutions in Malaysia.pptxChapter 4 - Islamic Financial Institutions in Malaysia.pptx
Chapter 4 - Islamic Financial Institutions in Malaysia.pptx
 
Lapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdfLapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdf
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
 

S3 SANITARY PIPE WORK ASSIGNMENT

  • 1. 1 | s a n i t a r y p i p e w o r k CONTENT No. Title Page 1. Appreciation 3 2. Introduction 4 3. Definition terms 5 4. 1. Explain why inspection and testing the soundness and performance of sanitary pipe work under ground. 6 5. 2. State the statutory and recommended soundness and performance requirements for sanitary pipe work, including connected sanitary appliances. 7 - 8 6. 3. Describe the air test n use of smoke to locate leaks in the pipe work in sanitary pipe work systems. 9 – 13 7. 4. Describe the hydraulic test for appliances and sanitary pipe work. 14 – 16 8. 5. Describe methods of simulating peak flow and pipe work. 17 9. 6. State inspection and testing procedures for various systems of sanitary pipe work. 18 - 24 10. Conclusion 25 11. Reference 26
  • 2. 2 | s a n i t a r y p i p e w o r k CONTENT OF FIGURE No. Title Page 1. Figure 1.0 Air Test 7 2. Figure 2.0 Shows the method of carrying out an air test. 10 3. Figure 2.1 Shows the method of carrying out a smoke test. 11 4. Figure 2.2 Show the smoke machine during a test. 11 5. Figure 2.3 The drain is plugged or stopped by either an expanding drain plug 12 6. Figure 2.4 Show the drain an inflatable bag 12 7. Figure 2. 5 Shows the method the carry out the water test using a rubber tube connected to a testing vessel. 15 8. Figure 4.0 Shows a method of testing the water using a rubber tube connected to the former test. 19 9. Figure 4.1 Shows a method of testing the wind. 20 10. Figure 4.2 Smoke tests on the drain 21 11. Figure 4.3 Smoke machine used during the test 22 12. Figure 4.4 Rubber drainage retaining expand 22 13. Figure 4.5 Retaining the drainage bag expands 23 14. Figure 4.6 Tests to determine the straightness and obstruction 24
  • 3. 3 | s a n i t a r y p i p e w o r k APPRECIATION Assalamualaikum… Praise is presented only for ALLAH Almighty Disposer of all things. Peace and blessings be upon beloved Prophet Muhammad leaflets bearing the revelation to illuminate be universe, the companions, his family, all the scholars and lovers of Islam throughout the world. Thank to God that, we can complete the assignment on the sanitary pipe work to be handed over to Mr. Huzaime b. Abdul Hadi very well. By making this assignment we can add my knowledge about of the sanitary pipe work. With this we can add my knowledge and understanding about it. Our assignment was explain a bit about the soundness and performance testing of sanitary pipe work above ground. Finally, we thank the lecturers who taught me, Mr. Huzaime b. Abdul Hadi has been providing guidance and information on how to produce this work. Thank also to friends who also give lessons and share ideas and information.
  • 4. 4 | s a n i t a r y p i p e w o r k INTRODUCTION PRINCIPLES OF DRAINAGE BELOW GROUND An effective drainage system is required to drain the dirty material from a surface water drainage building.If not strong and leak, the water that comes out of it may affect the health of this public.Condition will cause erosion of land under the building site resulting in a building that settles. Drainage must meet the requirements of economic technical.Factor often influence the flow system and the planning of a public sewer system building.If found in the vicinity of, a more economical way to handle waste is by passing the materials into the sewer route public.If public sewer line is within 30m of a construction site, local authorities may determine that the building drainage system must be connected to public sewer. Sanitary pipe work is a system of pipes installed to permit the transfer of waste water and sewage from building to foul drain. Also it provides a means of ventilation for the drain so that there can be no build up unpleasant odors or methane gas within the system which might accidentally permeate into the building. For efficient working of disposal installation pipe work system, a number of design criteria should be fulfilled. In the following section we will look at some of the terms related to sanitary pipe work.
  • 5. 5 | s a n i t a r y p i p e w o r k DEFINITION OF TERMS Soil Waste - This is discharged from water closets, urinals, slop sinks, and similar appliances. Soil Pipe - This pipe conveys the discharge of water closets or fixtures with similar function, with or without the discharges from other fixtures.
  • 6. 6 | s a n i t a r y p i p e w o r k 1. Explain why inspection and testing the soundness and performance of sanitary pipe work under ground. After the drain has been laid and before backfilling,or placing concrete,or granular material round the pipes,it should be tested by either water or air,If any leak occurs,the defective pipe or joint should be rectified and the drain again tested. Wherever possible,testing should be carried out between the manholes and short branch drains tested along with the main drainage system.Long branch drains and monholes should be separately. The test before backfilling should be carried out as soon as is practicable and the pipe should be strutted,to prevent any movement of the drain during the test. A temporary bend and stand pipe should be fitted at the head of the drain and a stopper fitted at the lower end. Alternatively,the test may be applied by means of a rubber tube connected to a vessel and the drain stopper.
  • 7. 7 | s a n i t a r y p i p e w o r k 2. State the statutory and recommended soundness and performance requirements for sanitary pipe work, including connected sanitary appliances. Soundness Testing of Discharge System Plug all open ends with Drain Plugs Fill all traps with water Attach water gauge manometer and pump up to 38mm Figure 1.0 Air Test Leave to stand for 3 minute No drop is permitted If there is a drop - check all joints with Leak Detection Spray The Water Test is carried out on sanitary appliances is up to flood level of lowest appliance
  • 8. 8 | s a n i t a r y p i p e w o r k Performance Testing of Discharge System Check that trap seals are retained after use Test for self siphonage or induced siphonage Fill all appliances to level of overflow and then remove plugs Test depth of trap seal with dipstick (painted matt black) Trap seal remaining MUST be at least 25mm Effective Trap Seal Depth - from the soffit to the invert of the trap outlet Testing for Tap Siphonage Self Siphonage - discharge pipe is too small Induced Siphonage - suck water out of the second trap Momentum - trap seal as water is carried away by water flowing at high speed
  • 9. 9 | s a n i t a r y p i p e w o r k 3. Describe the air test n use of smoke to locate leaks in the pipe work in sanitary pipe work systems. AIR TEST The length of drain to be tested should be plugged and air pumped into the pipe until a pressure of slightly more than 100 mm water gauge is obtained. Where gullies and / or ground - floor appliances are connected the test pressure should be slightly more than 50 mm water gauge. A change in air temperature will affect the test pressure and therefore 5 minutes should be allowed for pressure stabilization. The air pressure should be adjusted to 100 mm water gauge as necessary. Without further pumping, the head of water during a period of 5 minutes should not fall more than 25 mm and 12 mm for a 100 mm and 50 mm water gauge test pressures respectively. Figure 2.0 shows the method of carrying out an air test. The test is carried out by fixing a stopper, sealed with a cap, at one end of the drain and pumping in air at the other end until the U gauge shows the required head of water.
  • 10. 10 | s a n i t a r y p i p e w o r k FIGURE 2.0 Shows the method of carrying out an air test. SMOKE TEST The use of smoke cartridges for this test is not to be recommended, due to the possibility of the build up of high pressure inside the drain. The test by use of a smoke machine is usually applied to existing drains with the purpose of locating a leak. In order to ensure that the drain is filled with smoke, a rubber tube should be passed through the water seal of gully traps, so that air contained inside the drain may escape. Figure2.1 shows the method of carrying out a smoke test. The test is carried out by placing a stopper, sealed with a cap, at one end of the drain and pumping in smoke at the other.
  • 11. 11 | s a n i t a r y p i p e w o r k FIGURE 2.1 Shows the method of carrying out a smoke test. The dome rises with the action of the bellows and if the drain is sound is maintained in this elevated position. Figure 2.2 show the smoke machine during a test. FIGURE 2.2 Show the smoke machine during a test.
  • 12. 12 | s a n i t a r y p i p e w o r k Types of Stoppers The drain is plugged or stopped by either an expanding drain plug (Shown in Figure 2.3) or by an inflatable bag ( Shown in Figure. 2.4 ) FIGURE 2.3 The drain is plugged or stopped by either an expanding drain plug FIGURE 2.4 Show the drain an inflatable bag
  • 13. 13 | s a n i t a r y p i p e w o r k Test for Straightness and Obstruction This can be carried out by placing an electric torch at one end of the drain and looking through a mirror at the other end of the drain. Any fault in alignment or obstruction will be seen through the mirror. Testing Manholes A bag stopper should be fitted in the outlet of manhole and bag stoppers or expanding plugs fitted at all other connections. The manhole should be filled with clean water and allowed to stand for 8 hours for a absorption, topping up the water level as necessary. The criterion for acceptance should be , that no appreciable flow of water should pass through the manhole during a further 30 minutes.
  • 14. 14 | s a n i t a r y p i p e w o r k 4. Describe the hydraulic test for appliances and sanitary pipe work. Building Regulation and Code of Practice Tests. The Building Regulations 1992 ang the Code of Practice B.S 8301, Building Drainage 1985 give the following procedures for carrying out test on gravity drains and private sewers up to 300 mm in diameter. WATER TEST 1. The drain should be filled with water to give a test pressure equal to 1.5 m head of water above the soffit of the drain at the high end but not more than 4 m head of water above the soffit for the drain at the low end. Steeply graded drains should be tested in stages so that the head of water at the lower end does not exceed 4 m. This is to prevent damage to the drain and if may be necessary to test a drain in several sections. 2. The pipeline should be allowed to stand for 2 hours for absorption and topped up with water as necessary. After 2 hours the loss of water from the pipeline should be measured by noting the quantity of water needed to maintain the test head for 30 minutes. The rate of water loss should not exceed 1 litre/hour per metre diameter, per metre run of pipe. For various pipe diameters the rate of loss per metre run during the 30 minute period is 0.05 litre for 100 mm pipe; 0.8 litre for 150 mm pipe; 0.12 litre for 225 mm pipe and 0.15 litre for 300 mm pipe. Figure 3.0 shows the method the carry out the water test using a rubber tube connected to a testing vessel.
  • 15. 15 | s a n i t a r y p i p e w o r k Figure 3.0 Shows the method the carry out the water test using a rubber tube connected to a testing vessel. Alternatively, the test may be carry out by means of a temporary bend and stand- pipe connected to the head of the drain. The fall of water in the vessel or stand-pipe may be due to one or more of the following causes: a) Absorption by Pipe or Joints The initial absorption may be of the order of 5 per cent of the total weight of the pipeline. b) Trapped Air This usually occurs at the joints and the amount will vary with the type of joint, diameter of pipes and joints and the gradient. Eventually the air is absorbed by the water, but this can take some time.
  • 16. 16 | s a n i t a r y p i p e w o r k c) Sweating of Pipe and Joints Occasionally pipes and joints under water pressure may sweat slightly, but this should not be considered a cause for rejection of the pipeline. d) Leakage from Defective Pipes or Joints The defective pipe or joint should be taken out and replaced and the pipeline re- tested. e) Leakage from Stoppers These should be tightened, but if the leakage continues a new plug should be inserted. Sometimes a leakage can occur on the threaded portion of the plug. All equipment used for testing should be thoroughly checked before being used and the rubber surfaces of plugs should be free from grit. FINAL WATER TEST There is a risk that the drain of private sewer can be damage during backfilling or surrounding the pipeline with concrete. The final test therefore should be carried out after the backfilling or concreting has been completed.
  • 17. 17 | s a n i t a r y p i p e w o r k 5. Describe methods of simulating peak flow and pipe work. Flow in the pipe nowadays is very important as a medium to move a fluid from one destination to another. Generally it used at indushial plant, to supply a water at homea nde tc. Visualizationa nd Simulationo f Fluid Flows in a Piping Systemi s an application system developed to solve and also overcome problems in fluid motion field. The problem that existedi s the diffrculties to determinea n appearanceo f fluid motion. Analytical and mathematical approach alone does not solve the problems thosee xist. Therefore,t he new approachess ucha s visualizationa nd simulationa s a support for the solution has helped to solve the problem. This study only focus on laminar flow and specific on liquid which are water and used only single straighten piping system made of from PI/C.
  • 18. 18 | s a n i t a r y p i p e w o r k 6. State inspection and testing procedures for various systems of sanitary pipe work. Water Test 1. Drainage should be connected to the water supply to be equal to the test pressure of 1.5 m column of water above the soffit of the drainage at the highest end, but not more than 4 m column of water above the soffit of the drainage at the lowest end. 2. Very steep drainage should be tested in stages so that the water column at the lowest end will not be covers many 4 m. aims to prevent damage to drainage and tests should be done for a number of sections. 3. Pipe line must be left for 2 hours to allow the absorption and addition of water. 4. After 2 hours, loss of water from the pipeline must be measured by observing the volume of water to be added to keep the test columns for 30 minutes. 5. Water loss rate must not exceed 1 liter / hr per meter diameter, per meter length of pipe. 6. For pipes of variable diameter, the loss per meter length of pipe for 30 minutes is 0.05 liters to 100 mm diameter pipe, 12:08 liters to 150 mm diameter pipe, 12:12 liters to 225 mm diameter pipe and 0.15 liters for 300 diameter pipe mm. 7. Alternatively, the test can be done using a temporary bend and vertical pipe connected to the column drainage.
  • 19. 19 | s a n i t a r y p i p e w o r k 8. In addition, the drainage must be supported to prevent movement of the drain when it rains. decrease in water level in the container or vertical pipe during the test due to the diffusion of pipes and connections, leaking pipes or connections for damage, leakage at the conclusion of the test and the trapped air. 9. Some pipes absorbs more water or air traps more content than the rest of the jacks. therefore, water should be added to maintain the test head test within 30 minutes. Figure 4.0 Shows a method of testing the water using a rubber tube connected to the former test.
  • 20. 20 | s a n i t a r y p i p e w o r k Wind Test 1. Long drainage to be tested must be plugged and air pumped into the pipe until the pressure is slightly higher than the 100 mm water gauge. 2. When gegeluk and ground equipment is connected, the test pressure must be slightly higher than the 50 mm water gauge. 3. Changes in air temperature can affect the test pressure. Therefore, the pressure must be kept stable in the last 5 minutes. 4. Air pressure should be adjusted to 100 mm or 50 mm water gauge, according as may be required. 5. Without further pumping, the water column within 5 minutes should not be dropped more than 25 mm for the test pressure of 100 mm and 12 mm water gauge to test pressure of 50 mm water gauge. 6. Test was done by fitting a retainer, sealed with a lid, at one end of the drain and the air is pumped in through the other end until the gauge-U indicates the desired value of the water column. Figure 4.1 Shows a method of testing the wind.
  • 21. 21 | s a n i t a r y p i p e w o r k Smoke Test 1. Drainage should be plugged and connected to the smoke machine on the bottom retainer. 2. Test was conducted by pumping smoke into the drain with a smoke machine to vault up to the required height. 3. During the test was performed, the dome should be at steady state and drainage to be examined to detect any leakage of smoke. Figure 4.2 Smoke tests on the drain
  • 22. 22 | s a n i t a r y p i p e w o r k Figure 4.3 Smoke machine used during the test Figure 4.4 Rubber drainage retaining expand
  • 23. 23 | s a n i t a r y p i p e w o r k Figure 4.5 Retaining the drainage bag expands
  • 24. 24 | s a n i t a r y p i p e w o r k Straightness and resistance test 1. This test is maintained by placing a mirror at one end of the drainage and lighting and the other end. 2. Light is seen through a mirror can show whether the drainage is straight or pu, respectively. Figure 4.6 Tests to determine the straightness and obstruction
  • 25. 25 | s a n i t a r y p i p e w o r k CONCLUSION Drainage must meet the requirements of economic technical.Factor often influence the flow system and the planning of a public sewer system building.If found in the vicinity of, a more economical way to handle waste is by passing the materials into the sewer route public. Wherever possible,testing should be carried out between the manholes and short branch drains tested along with the main drainage system.Long branch drains and monholes should be separately. A temporary bend and stand pipe should be fitted at the head of the drain and a stopper fitted at the lower end. The air test use of smoke to located leaks in the pipe work in sanitary pipe work systems air test The length of drain to be tested should be plugged and air pumped into the pipe until a pressure of slightly more than 100 mm water gauge is obtained. Test for Straightness and Obstruction This can be carried out by placing an electric torch at one end of the drain and looking through a mirror at the other end of the drain.
  • 26. 26 | s a n i t a r y p i p e w o r k REFERENCES  BUILDING SERVICES AND EQUIPMENT THIRD EDITION FREDERICK HALL  F.HALL EDISI KEDUA KERJA PAIP : PEMBEKALAN AIR SEJUK,SALIRAN DAN PEMBERSIHAN,Penerbit Universiti Teknologi Malaysia Skudai Johor Darul Takzim 1999