SlideShare a Scribd company logo
LAYINGWORK OF
STEEL PIPELINE IN
CGD SECTOR
AkshayToraskar
Material & equipment used in Steel piping
■ Pipe material specification details:
– For pipe size up to & including 12’’ NB: Carbon steel pipe - API 5L gr. B
– For pipe size up to & including 18’’ NB: Carbon steel pipe - API 5L gr. X-
60
– For pipe size up of 18’’ NB: Carbon steel pipe - API 5L gr. X-52
■ Fittings such asTees, elbows etc. are of smooth surface & without joint i.e.
seamless joint
– Elbows & reducers made by hot forging seamless steel pipe.
– Tees made by hot extrusion.
– All butt welds are beveled.
■ Ball valves (size: 4’’ to 18’’) used are of fully welded construction with stem
extension.
■ All lifting equipment including cranes, spreader bars, belts, slings etc. are
duly certified by competent authority. Every lifting accessories are
appropriately handled to safeguard no damaged caused to the coating of
pipe.
■ The material used for backfilling the trench is Soil which is stone free & have
maximum grit size of 12 mm.
■ PE warning sheet :
– Density: 925 kg/m3
– Size for Steel pipeline of 6’’ and below diameter: 250mm width x
1.5mm thickness
– Size for Steel pipeline of 6’’ and above : 400mm width x 1.5mm
thickness
REFERENCES
1. ASME B 31.8 – Code for gas transmission & distribution piping system
2. Petroleum & natural gas regulatory board (PNGRB) technical standards
3. Steel ISO processes & work instrunctions
4. UK IGE/TD/1
TRENCHING
■ Before starting trenching work, all necessary statutory clearances, licenses,
permissions are obtained & made available on site.
■ Hazard identification & risk assessment done by competent personnel.
■ Cable locating survey is carried before trench activity.
■ Trial pits are taken prior to starting of trenching work.Trial pits requirements:
– Depth is 200mm more than the depth of trench & suitable width at interval
of 25- 50 M.
■ Excavations below 2 meters have shuttering or trench protection & carried
out as per confined entry procedure compliance.
■ The proximity of pipeline is of at least 3 meters horizontal distance from the
building/permanent structure.
■ Clear separation of minimum 500 mm is strictly maintained between
adjacent pipelines, while laying more than one new pipeline in the same
trench.
■ When pipeline is laid parallel to any existing underground cable, drain etc.,
it is laid with horizontal distance of 300 mm from existing utilities.
■ Trench is kept free of water. Pumps, shoring equipment etc., are provided
to maintained trench in good condition.
■ Continuous plastic barricades are provided on either side of trench with
ensuring no gap between them. Barricades have retro reflective stripes and
red light to make it visible in night time.
■ Excavated soil is piled at least 300 mm away from trench.
Trench protection system
Confined space work
■ Trench plate, ladder & rope is provided for emergency access at a
distance of every 500 meters of excavated trench.
■ Welding of main joints is completed before lowering of pipes in trench.
Welding of tie-in joints is done inside trench.
■ Wherever rock is encountered, the pipeline in wrapped with rock shield
to protect pipe from coating damaged.
Rock shield for pipeline protection
Welding activity in trench
Excavation and trench hazards
Depth of cover for buried steel pipeline
Location Cover (m.)
Cased/uncased road crossing 1.2
Cased railroad crossing 1.7
Normal/rocky terrain 1.2
Nallah crossing 1.5
River crossing 2.5
■ Cover is measured from top of coated pipe to top of the undistributed
surface of soil.
■ Clearance sufficiently large enough to avoid electrical fault current
interference is maintained among pipeline and grounding facilities of
electrical transmission lines.
LOWERINGOF STEEL PIPELINE
■ The trench is padded with minimum 150 mm with soft material or sand,
before lowering of pipeline in trench. After lowering, 450 mm soft
material is placed above it.
■ Both ends of pipeline is capped so as to prevent debris/ unwanted
foreign material from entering into pipeline during lowering activity.
■ Hydra machine is not used for transportation & lowering of steel pipe.
Required capacity of cranes/tripods with chain pulley blocks is used for
lowering .
Crane with chain pulley blocks
 Holiday detection test performed on coated pipes before lowering by
using full circle type holiday detector. Pipe is lowered only after
ensuring that trench is dried & clean. Holiday detection test is as
follows (photo is only for representation purpose):
BACKFILLING
■ Backfilling is followed immediately after lowering of pipe so that
coating is not exposed to undue temperature variation.
■ Before backfilling work, all activities belong to welding, NDT, blasting,
field joint coating, holiday testing is completed properly.
■ Backfilling material does not contained any irrelevant material or hard
lumps of soil.
■ Sand padding of 100 mm is done by covering all around the pipe.
■ Subsequent layers with protection tiles & warning sheets is placed
accordingly.
Difference between padding material &
backfill material
■ Backfill material is compressed in 150 mm layers to prevent trench from
settling & causing depression in road surface.
■ After backfilling appropriate crowning with existing soil is done
considering settling of surface.
■ Steel pipeline is covered by PCC concrete slab in case it passed through
overhead high tension electric line.
INSTALLATIONOF SECTIONALIZING
VALVE
■ In steel piping, valve is installed below ground with valve operating
device readily reachable.
■ The maximum distance between two valve is 3 km in steel pipeline.
■ Every alternating mainline valve is compatible for remotely operated
structure through SCADA.
HANDLING & STOCKINGOF PIPES
■ BARE PIPES:
– Bare pipes is handled by using lifting hooks equipped with a bend
brass copper plate placed within each pipe end.
– The used of steel cables, chains wound round the pipes is strictly
prohibited.
■ COATED PIPES:
– Coated pipes are handled by using twisted hemp, plastic or leather
straps, at least 100 mm wide & swing bar for limiting the flexion of
pipes.
– In stocking of coated pipes, the pipe is supported from the ground by
skids & wedges with neoprene strips of 25-30 cm wide.
STRINGING OF PIPES & ACCESSORIES
■ Pipes are strung along the edge of trench in such way that they cause no
inconvenience to road, street traffic & no damage to road.
■ Stringing of pipe is done at proper location in accordance with
construction drawings.
■ Strung coated pipes are kept clear from ground by padded skids.
■ Rolling, Dragging & sliding of pipes during stringing is not permitted.
■ End of pipes are protected with bevel protector.
■ Pipes are stacked at slope so that during rain, water doesn’t collect
inside pipes.
■ Predamaged pipes are stacked separately & taken to work only after
repair.
■ Pipes are strung preferably on left side of trench in flow direction of
pipe.
■ Pipe no., pipe length, heat no. are transferred on above pipes after
stringing with paint wherever stenciling is not clearly visible.
References: All images in this presentation is from google.com
THANK YOU

More Related Content

What's hot

4 city-gas-distribution
4 city-gas-distribution4 city-gas-distribution
4 city-gas-distribution
Hiren Patel
 
City Gas Distribution
City Gas DistributionCity Gas Distribution
City Gas Distribution
Joydeep Mukherjee
 
LPG.PPT
LPG.PPTLPG.PPT
Demand Analysis And Selection Of City For Cgd Network Establishment On Propos...
Demand Analysis And Selection Of City For Cgd Network Establishment On Propos...Demand Analysis And Selection Of City For Cgd Network Establishment On Propos...
Demand Analysis And Selection Of City For Cgd Network Establishment On Propos...
Subodh Maithani
 
Pipeline and instrumentation diagram for lpg tank farm project
Pipeline and instrumentation diagram for lpg tank farm project Pipeline and instrumentation diagram for lpg tank farm project
Pipeline and instrumentation diagram for lpg tank farm project
lpgbnhgastank
 
Guidelines for storage Handling and Dispensing of CNG.pptx
Guidelines for storage Handling and Dispensing of CNG.pptxGuidelines for storage Handling and Dispensing of CNG.pptx
Guidelines for storage Handling and Dispensing of CNG.pptx
Abhishek Padiyar
 
OISD STD-150
OISD STD-150OISD STD-150
OISD STD-150
AnupamaPanoli
 
Installation of lpg bottling plant
Installation of lpg bottling plantInstallation of lpg bottling plant
Installation of lpg bottling plant
lpgbnhgastank
 
Piping engineering guide
Piping engineering guidePiping engineering guide
Piping engineering guide
ram111eg
 
Production of MDPE gas Pipe as per IS 14885 in Industries with Pictorial Repr...
Production of MDPE gas Pipe as per IS 14885 in Industries with Pictorial Repr...Production of MDPE gas Pipe as per IS 14885 in Industries with Pictorial Repr...
Production of MDPE gas Pipe as per IS 14885 in Industries with Pictorial Repr...
Rishabh Sirvaiya
 
Pngrb
PngrbPngrb
ASME Vessels, Pig Launchers, Strainers and More from Sweco Fab
ASME Vessels, Pig Launchers, Strainers and More from Sweco FabASME Vessels, Pig Launchers, Strainers and More from Sweco Fab
ASME Vessels, Pig Launchers, Strainers and More from Sweco Fab
Piping Technology & Products, Inc.
 
Domestic Gas Infrastructure
Domestic Gas InfrastructureDomestic Gas Infrastructure
Domestic Gas Infrastructure
Malvika Jaishal
 
An overview of cng and png
An overview of cng and pngAn overview of cng and png
An overview of cng and png
Rohit Bisht
 
Fuel conversion IBR Boiler HSD to LPG .
Fuel conversion IBR Boiler HSD to LPG .Fuel conversion IBR Boiler HSD to LPG .
Fuel conversion IBR Boiler HSD to LPG .
SoorajThakur3
 
Lpg Bottling Plant
Lpg Bottling PlantLpg Bottling Plant
Lpg Bottling Plant
Subodh Maithani
 
Gis for cgd
Gis for cgdGis for cgd
Gis for cgd
Rishabh Sirvaiya
 
Pipe & its wall thickness calculation
Pipe & its wall thickness calculationPipe & its wall thickness calculation
Pipe & its wall thickness calculation
sandeepkrish2712
 
CNG NETWORK PPT.pdf
CNG NETWORK PPT.pdfCNG NETWORK PPT.pdf
CNG NETWORK PPT.pdf
ARHANMOHSIN
 
Grp installation procedure
Grp installation procedureGrp installation procedure
Grp installation procedure
kaustav mukherjee
 

What's hot (20)

4 city-gas-distribution
4 city-gas-distribution4 city-gas-distribution
4 city-gas-distribution
 
City Gas Distribution
City Gas DistributionCity Gas Distribution
City Gas Distribution
 
LPG.PPT
LPG.PPTLPG.PPT
LPG.PPT
 
Demand Analysis And Selection Of City For Cgd Network Establishment On Propos...
Demand Analysis And Selection Of City For Cgd Network Establishment On Propos...Demand Analysis And Selection Of City For Cgd Network Establishment On Propos...
Demand Analysis And Selection Of City For Cgd Network Establishment On Propos...
 
Pipeline and instrumentation diagram for lpg tank farm project
Pipeline and instrumentation diagram for lpg tank farm project Pipeline and instrumentation diagram for lpg tank farm project
Pipeline and instrumentation diagram for lpg tank farm project
 
Guidelines for storage Handling and Dispensing of CNG.pptx
Guidelines for storage Handling and Dispensing of CNG.pptxGuidelines for storage Handling and Dispensing of CNG.pptx
Guidelines for storage Handling and Dispensing of CNG.pptx
 
OISD STD-150
OISD STD-150OISD STD-150
OISD STD-150
 
Installation of lpg bottling plant
Installation of lpg bottling plantInstallation of lpg bottling plant
Installation of lpg bottling plant
 
Piping engineering guide
Piping engineering guidePiping engineering guide
Piping engineering guide
 
Production of MDPE gas Pipe as per IS 14885 in Industries with Pictorial Repr...
Production of MDPE gas Pipe as per IS 14885 in Industries with Pictorial Repr...Production of MDPE gas Pipe as per IS 14885 in Industries with Pictorial Repr...
Production of MDPE gas Pipe as per IS 14885 in Industries with Pictorial Repr...
 
Pngrb
PngrbPngrb
Pngrb
 
ASME Vessels, Pig Launchers, Strainers and More from Sweco Fab
ASME Vessels, Pig Launchers, Strainers and More from Sweco FabASME Vessels, Pig Launchers, Strainers and More from Sweco Fab
ASME Vessels, Pig Launchers, Strainers and More from Sweco Fab
 
Domestic Gas Infrastructure
Domestic Gas InfrastructureDomestic Gas Infrastructure
Domestic Gas Infrastructure
 
An overview of cng and png
An overview of cng and pngAn overview of cng and png
An overview of cng and png
 
Fuel conversion IBR Boiler HSD to LPG .
Fuel conversion IBR Boiler HSD to LPG .Fuel conversion IBR Boiler HSD to LPG .
Fuel conversion IBR Boiler HSD to LPG .
 
Lpg Bottling Plant
Lpg Bottling PlantLpg Bottling Plant
Lpg Bottling Plant
 
Gis for cgd
Gis for cgdGis for cgd
Gis for cgd
 
Pipe & its wall thickness calculation
Pipe & its wall thickness calculationPipe & its wall thickness calculation
Pipe & its wall thickness calculation
 
CNG NETWORK PPT.pdf
CNG NETWORK PPT.pdfCNG NETWORK PPT.pdf
CNG NETWORK PPT.pdf
 
Grp installation procedure
Grp installation procedureGrp installation procedure
Grp installation procedure
 

Similar to Steel pipeline laying in City Gas Distribution industry

Intake and Pipes joining
Intake and Pipes joiningIntake and Pipes joining
Intake and Pipes joining
Lobsang Jampa
 
SPECIFICATION WRITING II-FIRE FIGHTING.pptx
SPECIFICATION WRITING II-FIRE FIGHTING.pptxSPECIFICATION WRITING II-FIRE FIGHTING.pptx
SPECIFICATION WRITING II-FIRE FIGHTING.pptx
AbhiSharma727808
 
Gas Installation
Gas InstallationGas Installation
Gas Installation
Kushagra Goel
 
MEASURING, CUTTING, AND JOINING PIPES
MEASURING, CUTTING, AND JOINING PIPESMEASURING, CUTTING, AND JOINING PIPES
MEASURING, CUTTING, AND JOINING PIPES
Crislyn Monterde
 
S966 magnesium anode
S966 magnesium anodeS966 magnesium anode
S966 magnesium anode
Hedi Mohamed
 
Conventional shaft sinking by manual means
Conventional shaft sinking by manual meansConventional shaft sinking by manual means
Conventional shaft sinking by manual means
Safdar Ali
 
Yard and Rack Area Piping.pdf
Yard and Rack Area Piping.pdfYard and Rack Area Piping.pdf
Yard and Rack Area Piping.pdf
NoorulK
 
Module 1 - Jacking techniques.pptx
Module 1 - Jacking techniques.pptxModule 1 - Jacking techniques.pptx
Module 1 - Jacking techniques.pptx
ChinnuNinan
 
signature bridge short presentation
signature bridge short presentationsignature bridge short presentation
signature bridge short presentation
Pravin Gaurav
 
Pipes
PipesPipes
Construction and testing of sewer line
Construction and testing of sewer lineConstruction and testing of sewer line
Construction and testing of sewer line
RAMPRASAD KUMAWAT
 
Tunnel engineering
  Tunnel engineering  Tunnel engineering
Tunnel engineering
Saurabh Samant
 
Fluid conductors: Design and selection criteria
Fluid conductors: Design and selection criteriaFluid conductors: Design and selection criteria
Fluid conductors: Design and selection criteria
Anand Prithviraj
 
Construction Sequence.pptx
Construction Sequence.pptxConstruction Sequence.pptx
Construction Sequence.pptx
ssuser480182
 
Power system earthing
Power system earthingPower system earthing
Power system earthing
Nisarg Amin
 
Installation, testing and jointing of lt and ht power cables up to 33 kv
Installation, testing and jointing of lt and ht power cables up to 33 kvInstallation, testing and jointing of lt and ht power cables up to 33 kv
Installation, testing and jointing of lt and ht power cables up to 33 kv
Alexander Decker
 
Tube-to-Tube-Sheet.ppt
Tube-to-Tube-Sheet.pptTube-to-Tube-Sheet.ppt
Tube-to-Tube-Sheet.ppt
ssuserea7ebc
 
NATM ppt sumit
NATM ppt sumitNATM ppt sumit
NATM ppt sumit
SuMitt MaNdla
 
Laying, jointing and testing of pipes
Laying, jointing and testing of pipesLaying, jointing and testing of pipes
Laying, jointing and testing of pipes
sathyan s
 
ppt on sub structure construction.pptx
ppt on sub structure construction.pptxppt on sub structure construction.pptx
ppt on sub structure construction.pptx
RaviUraiya1
 

Similar to Steel pipeline laying in City Gas Distribution industry (20)

Intake and Pipes joining
Intake and Pipes joiningIntake and Pipes joining
Intake and Pipes joining
 
SPECIFICATION WRITING II-FIRE FIGHTING.pptx
SPECIFICATION WRITING II-FIRE FIGHTING.pptxSPECIFICATION WRITING II-FIRE FIGHTING.pptx
SPECIFICATION WRITING II-FIRE FIGHTING.pptx
 
Gas Installation
Gas InstallationGas Installation
Gas Installation
 
MEASURING, CUTTING, AND JOINING PIPES
MEASURING, CUTTING, AND JOINING PIPESMEASURING, CUTTING, AND JOINING PIPES
MEASURING, CUTTING, AND JOINING PIPES
 
S966 magnesium anode
S966 magnesium anodeS966 magnesium anode
S966 magnesium anode
 
Conventional shaft sinking by manual means
Conventional shaft sinking by manual meansConventional shaft sinking by manual means
Conventional shaft sinking by manual means
 
Yard and Rack Area Piping.pdf
Yard and Rack Area Piping.pdfYard and Rack Area Piping.pdf
Yard and Rack Area Piping.pdf
 
Module 1 - Jacking techniques.pptx
Module 1 - Jacking techniques.pptxModule 1 - Jacking techniques.pptx
Module 1 - Jacking techniques.pptx
 
signature bridge short presentation
signature bridge short presentationsignature bridge short presentation
signature bridge short presentation
 
Pipes
PipesPipes
Pipes
 
Construction and testing of sewer line
Construction and testing of sewer lineConstruction and testing of sewer line
Construction and testing of sewer line
 
Tunnel engineering
  Tunnel engineering  Tunnel engineering
Tunnel engineering
 
Fluid conductors: Design and selection criteria
Fluid conductors: Design and selection criteriaFluid conductors: Design and selection criteria
Fluid conductors: Design and selection criteria
 
Construction Sequence.pptx
Construction Sequence.pptxConstruction Sequence.pptx
Construction Sequence.pptx
 
Power system earthing
Power system earthingPower system earthing
Power system earthing
 
Installation, testing and jointing of lt and ht power cables up to 33 kv
Installation, testing and jointing of lt and ht power cables up to 33 kvInstallation, testing and jointing of lt and ht power cables up to 33 kv
Installation, testing and jointing of lt and ht power cables up to 33 kv
 
Tube-to-Tube-Sheet.ppt
Tube-to-Tube-Sheet.pptTube-to-Tube-Sheet.ppt
Tube-to-Tube-Sheet.ppt
 
NATM ppt sumit
NATM ppt sumitNATM ppt sumit
NATM ppt sumit
 
Laying, jointing and testing of pipes
Laying, jointing and testing of pipesLaying, jointing and testing of pipes
Laying, jointing and testing of pipes
 
ppt on sub structure construction.pptx
ppt on sub structure construction.pptxppt on sub structure construction.pptx
ppt on sub structure construction.pptx
 

Recently uploaded

ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
JamalHussainArman
 
Casting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdfCasting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdf
zubairahmad848137
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
IJECEIAES
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
mamunhossenbd75
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
bijceesjournal
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
Engine Lubrication performance System.pdf
Engine Lubrication performance System.pdfEngine Lubrication performance System.pdf
Engine Lubrication performance System.pdf
mamamaam477
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
University of Maribor
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
rpskprasana
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
Las Vegas Warehouse
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
NidhalKahouli2
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
IJECEIAES
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
gerogepatton
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
mahammadsalmanmech
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
Yasser Mahgoub
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
Rahul
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
KrishnaveniKrishnara1
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
Hitesh Mohapatra
 
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
ihlasbinance2003
 

Recently uploaded (20)

ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
 
Casting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdfCasting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdf
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
Engine Lubrication performance System.pdf
Engine Lubrication performance System.pdfEngine Lubrication performance System.pdf
Engine Lubrication performance System.pdf
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
 
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
 

Steel pipeline laying in City Gas Distribution industry

  • 1. LAYINGWORK OF STEEL PIPELINE IN CGD SECTOR AkshayToraskar
  • 2. Material & equipment used in Steel piping ■ Pipe material specification details: – For pipe size up to & including 12’’ NB: Carbon steel pipe - API 5L gr. B – For pipe size up to & including 18’’ NB: Carbon steel pipe - API 5L gr. X- 60 – For pipe size up of 18’’ NB: Carbon steel pipe - API 5L gr. X-52 ■ Fittings such asTees, elbows etc. are of smooth surface & without joint i.e. seamless joint – Elbows & reducers made by hot forging seamless steel pipe. – Tees made by hot extrusion. – All butt welds are beveled.
  • 3. ■ Ball valves (size: 4’’ to 18’’) used are of fully welded construction with stem extension. ■ All lifting equipment including cranes, spreader bars, belts, slings etc. are duly certified by competent authority. Every lifting accessories are appropriately handled to safeguard no damaged caused to the coating of pipe. ■ The material used for backfilling the trench is Soil which is stone free & have maximum grit size of 12 mm. ■ PE warning sheet : – Density: 925 kg/m3 – Size for Steel pipeline of 6’’ and below diameter: 250mm width x 1.5mm thickness – Size for Steel pipeline of 6’’ and above : 400mm width x 1.5mm thickness
  • 4. REFERENCES 1. ASME B 31.8 – Code for gas transmission & distribution piping system 2. Petroleum & natural gas regulatory board (PNGRB) technical standards 3. Steel ISO processes & work instrunctions 4. UK IGE/TD/1
  • 5. TRENCHING ■ Before starting trenching work, all necessary statutory clearances, licenses, permissions are obtained & made available on site. ■ Hazard identification & risk assessment done by competent personnel. ■ Cable locating survey is carried before trench activity. ■ Trial pits are taken prior to starting of trenching work.Trial pits requirements: – Depth is 200mm more than the depth of trench & suitable width at interval of 25- 50 M. ■ Excavations below 2 meters have shuttering or trench protection & carried out as per confined entry procedure compliance. ■ The proximity of pipeline is of at least 3 meters horizontal distance from the building/permanent structure.
  • 6. ■ Clear separation of minimum 500 mm is strictly maintained between adjacent pipelines, while laying more than one new pipeline in the same trench. ■ When pipeline is laid parallel to any existing underground cable, drain etc., it is laid with horizontal distance of 300 mm from existing utilities. ■ Trench is kept free of water. Pumps, shoring equipment etc., are provided to maintained trench in good condition. ■ Continuous plastic barricades are provided on either side of trench with ensuring no gap between them. Barricades have retro reflective stripes and red light to make it visible in night time. ■ Excavated soil is piled at least 300 mm away from trench.
  • 8.
  • 10. ■ Trench plate, ladder & rope is provided for emergency access at a distance of every 500 meters of excavated trench. ■ Welding of main joints is completed before lowering of pipes in trench. Welding of tie-in joints is done inside trench. ■ Wherever rock is encountered, the pipeline in wrapped with rock shield to protect pipe from coating damaged.
  • 11. Rock shield for pipeline protection
  • 14. Depth of cover for buried steel pipeline Location Cover (m.) Cased/uncased road crossing 1.2 Cased railroad crossing 1.7 Normal/rocky terrain 1.2 Nallah crossing 1.5 River crossing 2.5
  • 15. ■ Cover is measured from top of coated pipe to top of the undistributed surface of soil. ■ Clearance sufficiently large enough to avoid electrical fault current interference is maintained among pipeline and grounding facilities of electrical transmission lines.
  • 16. LOWERINGOF STEEL PIPELINE ■ The trench is padded with minimum 150 mm with soft material or sand, before lowering of pipeline in trench. After lowering, 450 mm soft material is placed above it. ■ Both ends of pipeline is capped so as to prevent debris/ unwanted foreign material from entering into pipeline during lowering activity. ■ Hydra machine is not used for transportation & lowering of steel pipe. Required capacity of cranes/tripods with chain pulley blocks is used for lowering .
  • 17. Crane with chain pulley blocks
  • 18.  Holiday detection test performed on coated pipes before lowering by using full circle type holiday detector. Pipe is lowered only after ensuring that trench is dried & clean. Holiday detection test is as follows (photo is only for representation purpose):
  • 19. BACKFILLING ■ Backfilling is followed immediately after lowering of pipe so that coating is not exposed to undue temperature variation. ■ Before backfilling work, all activities belong to welding, NDT, blasting, field joint coating, holiday testing is completed properly. ■ Backfilling material does not contained any irrelevant material or hard lumps of soil. ■ Sand padding of 100 mm is done by covering all around the pipe. ■ Subsequent layers with protection tiles & warning sheets is placed accordingly.
  • 20. Difference between padding material & backfill material
  • 21. ■ Backfill material is compressed in 150 mm layers to prevent trench from settling & causing depression in road surface. ■ After backfilling appropriate crowning with existing soil is done considering settling of surface. ■ Steel pipeline is covered by PCC concrete slab in case it passed through overhead high tension electric line.
  • 22. INSTALLATIONOF SECTIONALIZING VALVE ■ In steel piping, valve is installed below ground with valve operating device readily reachable. ■ The maximum distance between two valve is 3 km in steel pipeline. ■ Every alternating mainline valve is compatible for remotely operated structure through SCADA.
  • 23. HANDLING & STOCKINGOF PIPES ■ BARE PIPES: – Bare pipes is handled by using lifting hooks equipped with a bend brass copper plate placed within each pipe end. – The used of steel cables, chains wound round the pipes is strictly prohibited.
  • 24. ■ COATED PIPES: – Coated pipes are handled by using twisted hemp, plastic or leather straps, at least 100 mm wide & swing bar for limiting the flexion of pipes. – In stocking of coated pipes, the pipe is supported from the ground by skids & wedges with neoprene strips of 25-30 cm wide.
  • 25. STRINGING OF PIPES & ACCESSORIES ■ Pipes are strung along the edge of trench in such way that they cause no inconvenience to road, street traffic & no damage to road. ■ Stringing of pipe is done at proper location in accordance with construction drawings. ■ Strung coated pipes are kept clear from ground by padded skids. ■ Rolling, Dragging & sliding of pipes during stringing is not permitted. ■ End of pipes are protected with bevel protector.
  • 26. ■ Pipes are stacked at slope so that during rain, water doesn’t collect inside pipes. ■ Predamaged pipes are stacked separately & taken to work only after repair. ■ Pipes are strung preferably on left side of trench in flow direction of pipe. ■ Pipe no., pipe length, heat no. are transferred on above pipes after stringing with paint wherever stenciling is not clearly visible. References: All images in this presentation is from google.com