SlideShare a Scribd company logo
1 of 31
Pipeline Construction
Activities
1) Right of Way clearing and
grading
2) Delivery , Transporting ,
Handling , Hauling,
Stringing of pipes.
3) Trenching Normal & Rock
4) Bending
5) Lining up And Welding
6) Radiography Inspection
7) Application of Joint
Coating
8) Lowering & back filling
9) Tie-ins
10) River and Road crossings
11) Clean-up and restoration
of ROW
11) Air Pigging cleaning and
gauging
12) Hydrostatic testing
13) Dewatering cleaning and
swabbing
14) Golden Tie-ins
15) Valve Installation
16) Calliper Survey and dent
repairs
17) Line Preservation
18) Boundary Pillars
19) Kilometre Post
20) TP marker & Direction Marker
21) Documentation
Activities of Pipeline Construction
Right Of Way (ROW)
Activities
 ROW opening document handling over to contractor.
 18m marking of ROW Corridor.
 Centre Line Marking based on Intermediate Points and
Terminate Points.
 Wooden Pegs are put on either side of the centre line at a
distance of 9 meters for 18m ROW
 6m marking for pipeline on the left of the ROW corridor and
12m
for movements of equipments
 Cleaning and grading of the ROW strip from bushes , trees
etc.
Resources
 ROW Document.
 Wooden Pegs .
 Survey Team and Survey Marker
 Measuring Tape.
 Powder to mark the line.
 Dozer, Dozer Operator, Dozer Helper.
 Some Unskilled labours.
Right Of Way (ROW)
Transportation Handling and Stringing of the
Pipes
Activities
 Approaching to the site
 Delivery Inspection
 Loading Arrangement in trailor
 Tying the pipeline with nylon strap at every three meter.
 Profiled wooden support is prepared and pipeline is laid on it.
 Rubber pads bevel protector is put on the ends of the bevels.
 Unloading arrangement of pipe at the site.
 Putting pipe at the sandbags to avoid any damages
 Pipe is put in a string
Resources
 Material Requisition
 Nylon strap
 Wooden support
 Sandbags
 Cranes , Crane operator, Crane helper
 Tailor, Tailor Operator, Tailor helper
 Technician, Rigger for loading, Supervisor
 Some Unskilled labours
Transportation Handling and Stringing of
the Pipes
Trenching
Activities
 Excavate the trench soil
 Making extra depth to fit minimum radius of bend at
crossings.
 Top soil of 30cm is store separately.
 Making temporary crossings / diversions at bridges at road
crossings.
Resources
 Backhoe as excavator.
 Backhoe operator, helper, supervisor.
 Foreman
 2-4 unskilled labours to do random activities.
Bending
Activities
 Pipe is inserted into the bending machine.
 Pipe is bended in vertical or horizontal direction as mentioned
in alignment sheet.
 Mandreal is inserted inside the pipe to prevent it from
buckling while bending.
 Ovality of bent pipe is checked by passing a gauge disk of
95% of internal diameter.
 Sag bends are dressed up so to put at bottom of trench to
avoid any damage.
 Material is flown is checked at external point to check the
reduced thickness.
Resources
 Bending machine
 Bending Machine Engineer, Helper.
 Side booms.
 Side boom operator,, helper
 Foreman.
 Disc Gauges
 Mandreal
 Tape marker
Bending
Welding
Activities
 Pipe is line up for welding
 Pipe is lined up through internal or external line up clamp
 Pipe is put on wooden support.
 Cleaning and grinding of bevel.
 Welder Qualification Test is done to get qualified welders.
 Welders specimen sample is tested on destructive test to
check the strength of sample.
 In destructive test it is subjected to below test-
1) Tensile strength test
2) Nick Break Test
3) Root , face and side bent test
 After welder is qualified , then it is approved on mainline
welding
 Making availability of generator to operate welding activities.
 Providing the welding accessories and equipment’s to
welders
 Welding is done in four phases-
1) Root run for about 6-8 inches/min
2) Hot pass for about 11-13 inches/min
3) Filler-1 for about 9-11 inches/min
4) Filler-2 for about 3-5 inches/min
 Above welding activities is done at 5g position, downhill(from
top to bottom)
Welding
Resources
 Line-up clamp. For internal line-up clamp, compressor is
required
for compressed air.
 Line-up clamp mechanic, helper
 Side booms, operator, helper
 Wooden support
 Welding machine, welding accessories
 Welding machine trailor, trailor helper.
 Electrodes, Electrodes machine operator, helper, supervisor
 Generator, operator , helper
 Fitter, grinder, Foreman for supervision
 Welding Inspector, Welding Engineer
Welding
Radiography
Activities
 Transportation of X-ray source to the site , along with the
operator.
 Making the area free from the any activity
 Applying the film around the welded joints according to the
procedure, 10’O or 2’O lock.
 Positioning of radioactive source, maybe inside or outside
 Development of film.
 Interpretation of radiographic images.
Resources
 Licensed approved Radiographer, X-ray Machines, with
safety equipment’s.
 Film source.
 Barricading safety lead.
 Image quality , film processing facility.
 Interpretation developer , Interpreter
 Computerized data entry facilities, computer system
Radiography
Joint Coating
Activities
 Taking clearance from the radiography team.
 If humidity is 75-85 % then heat the area before blasting
 Cleaning the joint area.
 Preheating of the welded joint area to 60°- 80° C.
 Sand blasting the area to clean up the welded area.
 Primer is applied on the welded area.
 Sleeves is applied after primer coating.
 Sleeves are overlapped at position of 2 or 10 ‘O’ clock.
 Closure patch of sleeves is heated , pressed & sealed.
 Roller is pressed to remove trapped air.
 Holiday test is done to detect any pinholes in pipe.
 Peel test is done on next day to check the strength of the
sleeves
Resources
 Compressor , Flame machine
 Primer Paint .
 Primer paint Brush
 Sleeves
 Blasting equipment, 1 helper
 Sand blasting unit
 2 for sleeves, 1 for heat, 1 for rolling
 Holiday tester, operator, helper.
Joint Coating
Lowering & Backfilling
Activities
 Trench is cleared from all debris, stones, pipe cut pieces,
welding rods, etc.
 Dewatering the trench
 Repairing of the coating damages.
 Sand padding to put pipe on gravel/pebbles in rocky areas.
 Lifting the pipe with minimum 3 side booms to lower down in
the trench.
 Lowering clearance from joint coating site is taken
 Radiography clearance for left out joints is taken.
 Coatings is checked visually and repaired.
 Depth of trench is checked around of 1.5m
 Width of trench is checked at bottom , to be of around 1.2 m
 Night caps are put on open ends of pipe section.
 Pipe is lifted with side booms by the sling, sling is avoided on
the welded area.
 Pipe is lowered in the trench at a distance of 400 mm from
the HDPE Pipe.
 Warning tape is put at 400mm above HDPE Pipe.
Resources
 Side booms, operator,, helper
 Foreman, rigger , insulator for repair
 Dewatering pump.
 Sand padding
 Measuring tape.
 Night caps
 Warning tape.
Lowering & Backfilling
Tie-Ins
Activities
 Marking the joints to be tied in which are left during mainline
welding.
 Pipe is line up for welding
 Pipe is lined up through internal or external line up clamp
 Making availability of generator to operate welding activities.
 Providing the welding accessories and equipment’s to
welders
 Welding is done in four phases-
1) Root run for about 6-8 inches/min
2) Hot pass for about 11-13 inches/min
3) Filler-1 for about 9-11 inches/min
4) Filler-2 for about 3-5 inches/min
 Above welding activities is done at 5g position, downhill(from
top to bottom)
Tie-ins
Resources
 Line-up clamp. For internal line-up clamp, compressor is
required
for compressed air.
 Line-up clamp mechanic, helper
 Side booms, operator, helper
 Welding machine, welding accessories
 Welding machine trailor, trailor helper.
 Electrodes, Electrodes machine operator, helper, supervisor
 Generator, operator , helper
 Fitter, grinder, Foreman for supervision
 Welding Inspector, Welding Engineer
Crossings
Activities
 Bore path is determined under the crossings.
 Statutory authority permission is taken.
 Equipment’s deployed .
 Soil investigations is done.
 For small crossings , open cut trench is made, after installing
pipe it is backfilled.
 For submerged pipe , a concrete coating is done across the
pipe,
Pipe of thick wall thickness (0.375m) is installed.
 For lengthy bore path, pipe is installed in casing
 Casing of 6 inch extra diameter than carrier pipeline is used
 .Cased crossing is executed by the horizontal boring technique.
 Horizontal Direction Drilling machine & crew set up is done at
site.
 Boring path is tracked and monitored by the HDD crew.
 Hydrostat pre-testing is done at pressure corresponding to
95% SMYS.
 Insulator is placed between casing and carrier pipeline to
provide isolation between them. 2 insulators is placed at the
end
 Air vent is provided at the end of the casing to let the moisture
evaporates
 Electrical test is done to determine the resistance between
carrier pipe and casing pipe or carrier pipe or soil.
 Pipe is installed
 100% radiography is done for the welded joints.
 Closed sheet piles is laid if boring pits is unstable.
 Backfilling in boring /exits pits is done at 15cm after checking
90% proctor density by mechanical compactor after
dewatering.
Crossings
Resources
 Excavators
 HDD machine set up.
 HDD machine operators, technicians , helpers
 Pipe casing.
 Insulators
 Closed sheet piles
 Radiography kit for welding check
 Proctor density machine checker, operator
 Dewatering pump
 Mechanical compactor
 Foreman, supervisor, unskilled labours
Crossings
Clean-up and Restoration
Activities
 Cleaning the site , removing all the construction material.
 Restoring the ROW corridor and taking the NOC from the
land owners.
 Taking NOC from the statutory authority, government
authority.
Resources
 Cranes, Dozer
 Operator, helper
 NOC document
Air pigging cleaning and Gauging
Activities
 Pig is carried with loader at the launching site.
 Pig is launched into the pipe with the help of launcher and
compressed air.
 Gauge plate of 95% of ID is fastened to pig.
 Pig location and signals is monitored by the pigging crew.
 Pig is received at the other end through the receiver
 Retrieved gauge plate is analyzed and preserved.
 Brush Pigs , Foam pigs etc. are launched into pipe for
cleaning purposes
Resources
 Pig , Pig carrying trailor , trailor helper
 Pig launcher and Pig receiver , operator , helper
 Gauge plates
 Pig monitoring crew.
Hydrostatic test
Activities
 Mechanical clearance is taken .
 Water testing certificate and corrosion inhibtor is checked
 Instrument and equipment’s is checked for valid calibration
 Gauge plate of 95% ID and 10 mm thickness is passe
through the pig to check the dent.
 Repairing of the dent, if not then pipe section is cut
accordingly.
 Checking the condition of the hydrostatic header.
 Welding the header through the qualified welder.
 Water is taken from the tested source.
 Water is filled 500mtrs before first pig and 1000 meter
between first and second pig.
 After the pig is received then water flushing is done for 2 hrs.
Resources
 High capacity filling pump
 Pressurizing pump
 Corrosion Inhibitor Injection Pump
 Water free from debris
 Pressure gauge of proper range
 Dead bed tester
 Pressure recorder with chart
 Temp recorder with chart
 Ambient temp recorder
 Portable thermometer
 Test header
 Pigs
 Additional- Vehicles, Tents , dewatering stations ,welders and
welding accessories
Hydrostatic test
Markers and Valve Installation
Activities
 Marking boundary pillars at every 250 m
 Marking with kilometre post
 Marking turning point marker
 Marking direction marker before and after a TP at 200m
 Marking a warning sign
 Valves location is marked and installed wherever is needed
Resources
 Boundary pillars
 Markers
 Kilometre post
 Valves
Activities
 Dewatering by using foam pigs in pipeline
 Cleaning by brush pigging
 Magnetic Pigging to attracts electrodes and iron parts present
inside pipeline.
 Pigging records is monitored
 Download the data and record it for future use.
Resources
 Dewatering pump
 Pigs, Pig launcher , Pig receiver , operator, helper
 Pig monitoring team/agency
Calliper Survey
Line Preservation
Activities
 Preserving the line from the internal corrosion by the inhibited
water
 If the time period is more than it is filled with nitrogen
 Line is kept with air tight pressure.
Resources
 Inhibited corrosion protector
 Nitrogen. Pressure monitoring gauge
Documentation
Activities
 Collecting all the data from all the construction activities and
teams
 Getting the data approved from the clients.
 Archiving the data for the future use.
Resources
 Data from all the construction activities and teams.

More Related Content

Similar to Pipeline Construct.pptx

Proper installation GRE
Proper installation  GREProper installation  GRE
Proper installation GREmanx75
 
Conventional shaft sinking by manual means
Conventional shaft sinking by manual meansConventional shaft sinking by manual means
Conventional shaft sinking by manual meansSafdar Ali
 
Laying of Sewer Line
Laying of Sewer LineLaying of Sewer Line
Laying of Sewer Linesumitvikram
 
Case history doha linea red line north en
Case history   doha linea red line north enCase history   doha linea red line north en
Case history doha linea red line north enstefanolupifamaspa
 
Case history doha linea red line north en
Case history   doha linea red line north enCase history   doha linea red line north en
Case history doha linea red line north enstefanolupifamaspa
 
Construction Presentations 2019
Construction Presentations 2019Construction Presentations 2019
Construction Presentations 2019David H Moloney
 
Case history doha linea red line north en
Case history   doha linea red line north enCase history   doha linea red line north en
Case history doha linea red line north enstefanolupifamaspa
 
HDPE LINING - TANKS (002).pptx
HDPE LINING - TANKS (002).pptxHDPE LINING - TANKS (002).pptx
HDPE LINING - TANKS (002).pptxGanesh725683
 
Quality aspects in Cross Country Pipeline construction
Quality aspects in Cross Country Pipeline constructionQuality aspects in Cross Country Pipeline construction
Quality aspects in Cross Country Pipeline constructionSuresh Zanwar
 
coal mining training report
coal mining training report coal mining training report
coal mining training report VIKRAMSINGH1231
 
Sequence of well completion part 1
Sequence of well completion part 1Sequence of well completion part 1
Sequence of well completion part 1Elsayed Amer
 
Sequence of well completion part 1
Sequence of well completion part 1Sequence of well completion part 1
Sequence of well completion part 1Elsayed Amer
 
Stripping of liners from pipes using hdd technology (2007)
Stripping of liners from pipes using hdd technology (2007)Stripping of liners from pipes using hdd technology (2007)
Stripping of liners from pipes using hdd technology (2007)Western Pipeway
 
Trenchless technologies comparing thrust boring with horizontal directional ...
Trenchless technologies  comparing thrust boring with horizontal directional ...Trenchless technologies  comparing thrust boring with horizontal directional ...
Trenchless technologies comparing thrust boring with horizontal directional ...Tobiloba Omitola
 

Similar to Pipeline Construct.pptx (20)

Proper installation GRE
Proper installation  GREProper installation  GRE
Proper installation GRE
 
Conventional shaft sinking by manual means
Conventional shaft sinking by manual meansConventional shaft sinking by manual means
Conventional shaft sinking by manual means
 
Laying of Sewer Line
Laying of Sewer LineLaying of Sewer Line
Laying of Sewer Line
 
Grp installation procedure
Grp installation procedureGrp installation procedure
Grp installation procedure
 
Case history doha linea red line north en
Case history   doha linea red line north enCase history   doha linea red line north en
Case history doha linea red line north en
 
Case history doha linea red line north en
Case history   doha linea red line north enCase history   doha linea red line north en
Case history doha linea red line north en
 
PPT-on-false-air.ppt
PPT-on-false-air.pptPPT-on-false-air.ppt
PPT-on-false-air.ppt
 
Construction Presentations 2019
Construction Presentations 2019Construction Presentations 2019
Construction Presentations 2019
 
Case history doha linea red line north en
Case history   doha linea red line north enCase history   doha linea red line north en
Case history doha linea red line north en
 
HDPE LINING - TANKS (002).pptx
HDPE LINING - TANKS (002).pptxHDPE LINING - TANKS (002).pptx
HDPE LINING - TANKS (002).pptx
 
Quality aspects in Cross Country Pipeline construction
Quality aspects in Cross Country Pipeline constructionQuality aspects in Cross Country Pipeline construction
Quality aspects in Cross Country Pipeline construction
 
Slide Plates and Rollers in the Fight Against Friction
Slide Plates and Rollers in the Fight Against FrictionSlide Plates and Rollers in the Fight Against Friction
Slide Plates and Rollers in the Fight Against Friction
 
coal mining training report
coal mining training report coal mining training report
coal mining training report
 
Slide Plates V.2 Webinar
Slide Plates V.2 WebinarSlide Plates V.2 Webinar
Slide Plates V.2 Webinar
 
Barry Cutting - Booster fans Angus Place Colliery
Barry Cutting  - Booster fans Angus Place CollieryBarry Cutting  - Booster fans Angus Place Colliery
Barry Cutting - Booster fans Angus Place Colliery
 
Sequence of well completion part 1
Sequence of well completion part 1Sequence of well completion part 1
Sequence of well completion part 1
 
Sequence of well completion part 1
Sequence of well completion part 1Sequence of well completion part 1
Sequence of well completion part 1
 
Stripping of liners from pipes using hdd technology (2007)
Stripping of liners from pipes using hdd technology (2007)Stripping of liners from pipes using hdd technology (2007)
Stripping of liners from pipes using hdd technology (2007)
 
Hydraulic catalogue
Hydraulic catalogueHydraulic catalogue
Hydraulic catalogue
 
Trenchless technologies comparing thrust boring with horizontal directional ...
Trenchless technologies  comparing thrust boring with horizontal directional ...Trenchless technologies  comparing thrust boring with horizontal directional ...
Trenchless technologies comparing thrust boring with horizontal directional ...
 

More from ssuserfc98db

Presentation13.pptx
Presentation13.pptxPresentation13.pptx
Presentation13.pptxssuserfc98db
 
Equipment Sizing.pdf
Equipment Sizing.pdfEquipment Sizing.pdf
Equipment Sizing.pdfssuserfc98db
 
A PPT ON CONSTRUction PROJECT PLANNING - RASHID HUSSAIN.pdf
A PPT ON CONSTRUction PROJECT PLANNING - RASHID HUSSAIN.pdfA PPT ON CONSTRUction PROJECT PLANNING - RASHID HUSSAIN.pdf
A PPT ON CONSTRUction PROJECT PLANNING - RASHID HUSSAIN.pdfssuserfc98db
 

More from ssuserfc98db (8)

CI.pptx
CI.pptxCI.pptx
CI.pptx
 
Presentation13.pptx
Presentation13.pptxPresentation13.pptx
Presentation13.pptx
 
Budget3207.pptx
Budget3207.pptxBudget3207.pptx
Budget3207.pptx
 
Equipment Sizing.pdf
Equipment Sizing.pdfEquipment Sizing.pdf
Equipment Sizing.pdf
 
Pid.pdf
Pid.pdfPid.pdf
Pid.pdf
 
Mangemnt3207.pptx
Mangemnt3207.pptxMangemnt3207.pptx
Mangemnt3207.pptx
 
SP and R.pptx
SP and R.pptxSP and R.pptx
SP and R.pptx
 
A PPT ON CONSTRUction PROJECT PLANNING - RASHID HUSSAIN.pdf
A PPT ON CONSTRUction PROJECT PLANNING - RASHID HUSSAIN.pdfA PPT ON CONSTRUction PROJECT PLANNING - RASHID HUSSAIN.pdf
A PPT ON CONSTRUction PROJECT PLANNING - RASHID HUSSAIN.pdf
 

Recently uploaded

the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 

Recently uploaded (20)

the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 

Pipeline Construct.pptx

  • 2. 1) Right of Way clearing and grading 2) Delivery , Transporting , Handling , Hauling, Stringing of pipes. 3) Trenching Normal & Rock 4) Bending 5) Lining up And Welding 6) Radiography Inspection 7) Application of Joint Coating 8) Lowering & back filling 9) Tie-ins 10) River and Road crossings 11) Clean-up and restoration of ROW 11) Air Pigging cleaning and gauging 12) Hydrostatic testing 13) Dewatering cleaning and swabbing 14) Golden Tie-ins 15) Valve Installation 16) Calliper Survey and dent repairs 17) Line Preservation 18) Boundary Pillars 19) Kilometre Post 20) TP marker & Direction Marker 21) Documentation Activities of Pipeline Construction
  • 3. Right Of Way (ROW) Activities  ROW opening document handling over to contractor.  18m marking of ROW Corridor.  Centre Line Marking based on Intermediate Points and Terminate Points.  Wooden Pegs are put on either side of the centre line at a distance of 9 meters for 18m ROW  6m marking for pipeline on the left of the ROW corridor and 12m for movements of equipments  Cleaning and grading of the ROW strip from bushes , trees etc.
  • 4. Resources  ROW Document.  Wooden Pegs .  Survey Team and Survey Marker  Measuring Tape.  Powder to mark the line.  Dozer, Dozer Operator, Dozer Helper.  Some Unskilled labours. Right Of Way (ROW)
  • 5. Transportation Handling and Stringing of the Pipes Activities  Approaching to the site  Delivery Inspection  Loading Arrangement in trailor  Tying the pipeline with nylon strap at every three meter.  Profiled wooden support is prepared and pipeline is laid on it.  Rubber pads bevel protector is put on the ends of the bevels.  Unloading arrangement of pipe at the site.  Putting pipe at the sandbags to avoid any damages  Pipe is put in a string
  • 6. Resources  Material Requisition  Nylon strap  Wooden support  Sandbags  Cranes , Crane operator, Crane helper  Tailor, Tailor Operator, Tailor helper  Technician, Rigger for loading, Supervisor  Some Unskilled labours Transportation Handling and Stringing of the Pipes
  • 7. Trenching Activities  Excavate the trench soil  Making extra depth to fit minimum radius of bend at crossings.  Top soil of 30cm is store separately.  Making temporary crossings / diversions at bridges at road crossings. Resources  Backhoe as excavator.  Backhoe operator, helper, supervisor.  Foreman  2-4 unskilled labours to do random activities.
  • 8. Bending Activities  Pipe is inserted into the bending machine.  Pipe is bended in vertical or horizontal direction as mentioned in alignment sheet.  Mandreal is inserted inside the pipe to prevent it from buckling while bending.  Ovality of bent pipe is checked by passing a gauge disk of 95% of internal diameter.  Sag bends are dressed up so to put at bottom of trench to avoid any damage.  Material is flown is checked at external point to check the reduced thickness.
  • 9. Resources  Bending machine  Bending Machine Engineer, Helper.  Side booms.  Side boom operator,, helper  Foreman.  Disc Gauges  Mandreal  Tape marker Bending
  • 10. Welding Activities  Pipe is line up for welding  Pipe is lined up through internal or external line up clamp  Pipe is put on wooden support.  Cleaning and grinding of bevel.  Welder Qualification Test is done to get qualified welders.  Welders specimen sample is tested on destructive test to check the strength of sample.  In destructive test it is subjected to below test- 1) Tensile strength test 2) Nick Break Test 3) Root , face and side bent test
  • 11.  After welder is qualified , then it is approved on mainline welding  Making availability of generator to operate welding activities.  Providing the welding accessories and equipment’s to welders  Welding is done in four phases- 1) Root run for about 6-8 inches/min 2) Hot pass for about 11-13 inches/min 3) Filler-1 for about 9-11 inches/min 4) Filler-2 for about 3-5 inches/min  Above welding activities is done at 5g position, downhill(from top to bottom) Welding
  • 12. Resources  Line-up clamp. For internal line-up clamp, compressor is required for compressed air.  Line-up clamp mechanic, helper  Side booms, operator, helper  Wooden support  Welding machine, welding accessories  Welding machine trailor, trailor helper.  Electrodes, Electrodes machine operator, helper, supervisor  Generator, operator , helper  Fitter, grinder, Foreman for supervision  Welding Inspector, Welding Engineer Welding
  • 13. Radiography Activities  Transportation of X-ray source to the site , along with the operator.  Making the area free from the any activity  Applying the film around the welded joints according to the procedure, 10’O or 2’O lock.  Positioning of radioactive source, maybe inside or outside  Development of film.  Interpretation of radiographic images.
  • 14. Resources  Licensed approved Radiographer, X-ray Machines, with safety equipment’s.  Film source.  Barricading safety lead.  Image quality , film processing facility.  Interpretation developer , Interpreter  Computerized data entry facilities, computer system Radiography
  • 15. Joint Coating Activities  Taking clearance from the radiography team.  If humidity is 75-85 % then heat the area before blasting  Cleaning the joint area.  Preheating of the welded joint area to 60°- 80° C.  Sand blasting the area to clean up the welded area.  Primer is applied on the welded area.  Sleeves is applied after primer coating.  Sleeves are overlapped at position of 2 or 10 ‘O’ clock.  Closure patch of sleeves is heated , pressed & sealed.  Roller is pressed to remove trapped air.  Holiday test is done to detect any pinholes in pipe.  Peel test is done on next day to check the strength of the sleeves
  • 16. Resources  Compressor , Flame machine  Primer Paint .  Primer paint Brush  Sleeves  Blasting equipment, 1 helper  Sand blasting unit  2 for sleeves, 1 for heat, 1 for rolling  Holiday tester, operator, helper. Joint Coating
  • 17. Lowering & Backfilling Activities  Trench is cleared from all debris, stones, pipe cut pieces, welding rods, etc.  Dewatering the trench  Repairing of the coating damages.  Sand padding to put pipe on gravel/pebbles in rocky areas.  Lifting the pipe with minimum 3 side booms to lower down in the trench.  Lowering clearance from joint coating site is taken  Radiography clearance for left out joints is taken.  Coatings is checked visually and repaired.  Depth of trench is checked around of 1.5m  Width of trench is checked at bottom , to be of around 1.2 m
  • 18.  Night caps are put on open ends of pipe section.  Pipe is lifted with side booms by the sling, sling is avoided on the welded area.  Pipe is lowered in the trench at a distance of 400 mm from the HDPE Pipe.  Warning tape is put at 400mm above HDPE Pipe. Resources  Side booms, operator,, helper  Foreman, rigger , insulator for repair  Dewatering pump.  Sand padding  Measuring tape.  Night caps  Warning tape. Lowering & Backfilling
  • 19. Tie-Ins Activities  Marking the joints to be tied in which are left during mainline welding.  Pipe is line up for welding  Pipe is lined up through internal or external line up clamp  Making availability of generator to operate welding activities.  Providing the welding accessories and equipment’s to welders  Welding is done in four phases- 1) Root run for about 6-8 inches/min 2) Hot pass for about 11-13 inches/min 3) Filler-1 for about 9-11 inches/min 4) Filler-2 for about 3-5 inches/min  Above welding activities is done at 5g position, downhill(from top to bottom)
  • 20. Tie-ins Resources  Line-up clamp. For internal line-up clamp, compressor is required for compressed air.  Line-up clamp mechanic, helper  Side booms, operator, helper  Welding machine, welding accessories  Welding machine trailor, trailor helper.  Electrodes, Electrodes machine operator, helper, supervisor  Generator, operator , helper  Fitter, grinder, Foreman for supervision  Welding Inspector, Welding Engineer
  • 21. Crossings Activities  Bore path is determined under the crossings.  Statutory authority permission is taken.  Equipment’s deployed .  Soil investigations is done.  For small crossings , open cut trench is made, after installing pipe it is backfilled.  For submerged pipe , a concrete coating is done across the pipe, Pipe of thick wall thickness (0.375m) is installed.  For lengthy bore path, pipe is installed in casing  Casing of 6 inch extra diameter than carrier pipeline is used  .Cased crossing is executed by the horizontal boring technique.  Horizontal Direction Drilling machine & crew set up is done at site.
  • 22.  Boring path is tracked and monitored by the HDD crew.  Hydrostat pre-testing is done at pressure corresponding to 95% SMYS.  Insulator is placed between casing and carrier pipeline to provide isolation between them. 2 insulators is placed at the end  Air vent is provided at the end of the casing to let the moisture evaporates  Electrical test is done to determine the resistance between carrier pipe and casing pipe or carrier pipe or soil.  Pipe is installed  100% radiography is done for the welded joints.  Closed sheet piles is laid if boring pits is unstable.  Backfilling in boring /exits pits is done at 15cm after checking 90% proctor density by mechanical compactor after dewatering. Crossings
  • 23. Resources  Excavators  HDD machine set up.  HDD machine operators, technicians , helpers  Pipe casing.  Insulators  Closed sheet piles  Radiography kit for welding check  Proctor density machine checker, operator  Dewatering pump  Mechanical compactor  Foreman, supervisor, unskilled labours Crossings
  • 24. Clean-up and Restoration Activities  Cleaning the site , removing all the construction material.  Restoring the ROW corridor and taking the NOC from the land owners.  Taking NOC from the statutory authority, government authority. Resources  Cranes, Dozer  Operator, helper  NOC document
  • 25. Air pigging cleaning and Gauging Activities  Pig is carried with loader at the launching site.  Pig is launched into the pipe with the help of launcher and compressed air.  Gauge plate of 95% of ID is fastened to pig.  Pig location and signals is monitored by the pigging crew.  Pig is received at the other end through the receiver  Retrieved gauge plate is analyzed and preserved.  Brush Pigs , Foam pigs etc. are launched into pipe for cleaning purposes Resources  Pig , Pig carrying trailor , trailor helper  Pig launcher and Pig receiver , operator , helper  Gauge plates  Pig monitoring crew.
  • 26. Hydrostatic test Activities  Mechanical clearance is taken .  Water testing certificate and corrosion inhibtor is checked  Instrument and equipment’s is checked for valid calibration  Gauge plate of 95% ID and 10 mm thickness is passe through the pig to check the dent.  Repairing of the dent, if not then pipe section is cut accordingly.  Checking the condition of the hydrostatic header.  Welding the header through the qualified welder.  Water is taken from the tested source.  Water is filled 500mtrs before first pig and 1000 meter between first and second pig.  After the pig is received then water flushing is done for 2 hrs.
  • 27. Resources  High capacity filling pump  Pressurizing pump  Corrosion Inhibitor Injection Pump  Water free from debris  Pressure gauge of proper range  Dead bed tester  Pressure recorder with chart  Temp recorder with chart  Ambient temp recorder  Portable thermometer  Test header  Pigs  Additional- Vehicles, Tents , dewatering stations ,welders and welding accessories Hydrostatic test
  • 28. Markers and Valve Installation Activities  Marking boundary pillars at every 250 m  Marking with kilometre post  Marking turning point marker  Marking direction marker before and after a TP at 200m  Marking a warning sign  Valves location is marked and installed wherever is needed Resources  Boundary pillars  Markers  Kilometre post  Valves
  • 29. Activities  Dewatering by using foam pigs in pipeline  Cleaning by brush pigging  Magnetic Pigging to attracts electrodes and iron parts present inside pipeline.  Pigging records is monitored  Download the data and record it for future use. Resources  Dewatering pump  Pigs, Pig launcher , Pig receiver , operator, helper  Pig monitoring team/agency Calliper Survey
  • 30. Line Preservation Activities  Preserving the line from the internal corrosion by the inhibited water  If the time period is more than it is filled with nitrogen  Line is kept with air tight pressure. Resources  Inhibited corrosion protector  Nitrogen. Pressure monitoring gauge
  • 31. Documentation Activities  Collecting all the data from all the construction activities and teams  Getting the data approved from the clients.  Archiving the data for the future use. Resources  Data from all the construction activities and teams.