SlideShare a Scribd company logo
PILE CAP DESIGN
PILE CAP:-
A reinforced concrete slab or block which interconnects a group of piles and acts
as a medium to transmit the load from wall or column to the Piles is called a Pile
Cap. The Pile cap should normally be rigid so as to distribute the forces equally on
the piles of a group. In general it is designed like a footing on soil but with the
difference that instead of uniform reaction from the soil, the reactions in this case
are concentrated either point loads or distributed.
As per IS 2911 (Part I/ Sec 3) -2010, the pile cap may be designed by assuming
that the load from column is dispersed at 45˚ from the top of the cap up to the mid
depth of the pile cap from the base of the column or pedestal. The reaction from
piles may also be taken to be distributed at 45˚ from the edge of the pile, up to the
mid depth of the pile cap. On this basis the maximum bending moment and shear
forces should be worked out at critical sections.
ASSUMPTIONS INVOLVED IN THE DESIGN OF PILE CAPS:-
(i) Pile cap is perfectly rigid.
(ii) Pile heads are hinged to the pile cap and hence no bending moment is
transmitted to piles from pile caps.
(iii) Since the piles are short and elastic columns, the deformations and stress
distribution are planer.
DESIGN PARAMETERS OF PILE CAPS:-
(i) Shape of pile cap.
(ii) Depth of pile cap.
(iii) Amount of steel to be provided.
(iv) Arrangement of reinforcement.
(i) Shape of pile cap:-
Whittle and Beattie have developed through computer program the
relationship between dimension of pile cap and the size of the pile.
The minimum spacing of piles permitted from soil mechanics depends on the
type and end conditions. CP 2004 requires a minimum centre- to –centre
spacing of twice the diameter of the piles for end bearing and three times the
diameter for friction piles. IS 2911 part1, sections 1 and 2 recommended a
minimum spacing of two and half times the diameter of the pile for both driven
cast in situ and bored cast in situ piles.
For accommodating deviations in driving of piles, the size of the pile cap is
made 300 mm more than the outer- to outer distance of the exterior piles. (150
mm on either side).
The plan dimension of the pile cap is based on the fact that the actual final
position of piles can be in construction up to 100 mm out of line from the
theoretical centre lines. Pile caps should be made very large to accommodate these
deviations. In practice, pile caps are extended as much as 150 mm beyond the
outer face of the piles.
Standard Pile Caps:
s-spacing of pile = F x hp where
hp = diameter of pile in mm
F = spacing factor= centre to centre spacing
Pile diameter
(ii) Depth of Pile Cap :-
The thickness of the Pile Cap is fixed such that it is adequate to resist shear
without shear reinforcement and the bars projecting from the piles and the
dowel bars for the column can be provided adequate bond length. As per IS
456- 2000, the minimum thickness on top of piles should not be less than 300
mm. Pile cap depth should be kept on the high side to effect economy in the
consumption of steel and also to provide adequate rigidity to pile cap. Generally,
pile cap thickness should not be less than 500 mm which may be reduced to 300
mm at the free edges. For pile caps to be rigid, pile cap has to be quite deep
with 600 mm as the minimum depth. As a guide line the formula given in
Reinforced concrete by Reynolds may be followed.
For Pile dia > 550 mm,
Pile cap depth (h) = (2 hp + 100)mm
For Pile dia ≥ 550 mm,
h= ⅓ x( 8 hp + 600) mm
Pile Dia
hp (mm)
300 350 400 450 500 550 600 750
Pile Cap
depth
h(mm)
700 800 900 1000 1100 1200 1400 1800
(i) Amount of steel to be provided :-
The Pile Cap has to be designed either truss theory or beam theory.
Although, the pile caps are assumed to act as a simply supported beam
and are designed for the usual condition of bending and shear, their
tendency is to fail by bursting due to high principal tension and they will
therefore always require a cage of reinforcement in three dimensions to
resist this tendency.
The main reinforcement is usually bend (full bend) and extended
for full depth of pile cap to fulfill the check for development length.
Though IS 456-2000 is silent on specifying the minimum reinforcement, a
minimum reinforcement of 0.15 % BD for main reinforcement and 0.12
% BD for secondary reinforcement may be provided as per clause
3 .11.4.1 and 2 of CP 110 code). For bursting (horizontal binders) it is
suggested that 25 % of the main reinforcement (usually 12 Φ RTS at
150 mm c/c) shall be used.
Cover :- A cover of 75 mm is usually provided for the pile cap surfaces in
contact with earth and 60 mm against blinding concrete of 75 to 100 mm
thick. In marine situations the cover should be increased to a minimum
of 80 mm.
DESIGN OF PILE CAP BASED ON TRUSS THEORY:
The truss theory applied to pile caps with up to 5 piles. In this method the
load from the column is transmitted to the piles by inclined thrust and the tie
necessary to maintain equilibrium is provided by reinforcement. (Steel acts as
tension chord and concrete as diagonal struts).
If the Ultimate load on the column is N and we have two piles the load on each
pile is N/2.
From the diagram of forces T = l
(N/2) d
i.e. T = N l/2d
Area of reinforcement required = Nl/ (2d x 0.87 fy )
In the simple frame described above, the dimensions of the columns have been
ignored. If the Column is square of side 2a,
T = N (3l
2
– a
2
)
6 ld
In truss theory, it has usually been the practice to band the
reinforcement along the lines joining the piles. The code now suggests that this
method of banding is only necessary if the piles are spaced at more than
3 times the pile dia. For the more normal spacing of 3 times the pile dia the total
reinforcement forming the tie force in one direction can be distributed uniformly
across the cap with a three- pile cap designed on the truss theory, it is difficult
to see how this can be done and it is suggested that the reinforcement is
banded along the centre lines joining the piles.
In the case of pile caps designed using the truss theory it is
suggested that the effective depth is approximately half the distance between
the centre of piles. This means the truss has an angle of approximately 45˚.
Allowable shear resistance is given by
N= 2 (d hp ) 2 ζc (d/av) + (b- 2 hp ) ζc bd where ζc = design shear strength of
concrete.
av = 0.5(l- b) where l= c/c of piles & b = width of column.
The section should be safe without extra shear reinforcement.
Truss theory design can be done using Table 194 of Reynould’s hand book.
Beam theory :- When (av / d) ratio is more than 2 as in shallow pile cap or
with the arrangement of 6 or more piles, bending action is more predominant
than truss action. In this case the pile cap is designed as a normal beam for
bending moment and shear. The pile cap area is divided into a framework of
rectangular beam depending on the geometry of the pile group. The width of the
beam is taken as equal to the width of the pile. The beam may be simply
supported or continuous.
The reinforcement is evenly distributed or concentrated. The reaction from
the pile is taken as distributed at 45˚ from the edge of the pile cap up to the
mid- depth of the pile cap. The maximum bending moment and shear force are
calculated on this basis. However, it is much easier to consider the loads as
concentrated loads and calculate the B.M. and S.F. The depth should be such
that no extra shear reinforcement is necessary for the section.
Practical Aspects on Pile cap Design:
The structural design of a pile cap is similar to the design of spread footing. The load
acting on the pile cap from the superstructure and piles are resisted by the
developments of bending moment and shear force in the pile cap.
Codal provisions made in IS 2911(Part 1/sec3)-2010 :
1. The size of the pile cap is fixed in such way that it has clear overhang beyond
the outermost pile not less than 100mm, but preferably 150mm.
2. It should be deep enough to allow the necessary overlap of reinforcements from
column and piles.
3. The clear cover to the main reinforcement should not be less than 40mm.
4. The span to thickness ratio of the cap should not be more than 5 so that pile cap
is rigid enough to distribute the load uniformly to the piles.
5. Generally, its thickness should not be less than 500mm which may be reduced to
300mm at the free edges.
6. The piles should atleast 50mm into the pile cap.
7. A leveling course of not less 75mm thick concrete should be provided under the
pile cap.
Design Aspects :-
The reaction from the piles under the concentric axial load on the cap is
assumed equal and is determined by,
Pp = Q/n ----- (1)
where Q = concentric axial load on the cap
n = Number of Piles
When the Pile cap is eccentrically loaded or subjected to a load and moments
then the reactions from the Piles are determined as
Pp = Q/n +/- My x +/- Mx y ----- (2) where
∑x2
∑y2
Mx, My = moments with respect to x and y axes.
X, y = distances from y and x axes to the Piles.
The critical section for bending moments and bond shall be calculated at the
face of column or pedestal.
The critical section for two way shear (Punching shear) will be at a distance d/2
from face of column or pedestal.
One way shear is checked at a distance of d/2 from the face of the column.
The Clause 34.2.4.2 of IS 456 – 2000 states the following :-
“In computing the external shear or any section through a footing supported on
Piles, the entire reaction from any pile of diameter Dp whose centre is located
Dp/2 or more outside the section shall be assumed as producing shear on the
section; the reaction from any Pile whose centre is located Dp/2 or more inside
the section shall be assumed as producing no shear on the section. For
intermediate positions of the pile centre, the position of pile reaction to be
assumed as producing shear on the section shall be based on straight line
interpolation between full value at Dp/2 outside the section and zero value at
Dp/2 inside the section.”
In computing external shear on any section the entire (100%) reaction of the
Pile shall be taken if the pile centre is located at 150 mm or more outside the
section. The pile reaction will produce no shear (0%) if the pile centre is located
at 150 mm or more inside the section. A linear interpolation shall be made for
intermediate values of the pile centre.
Let the centre of the pile be located at ‘x’ from the face of the column. Let
‘d’ be the effective depth of the pile cap. Then the critical section is located at
d/2 from face of the column.
If pile centre is located at (d/2 –x) outside the critical section when x
< d/2.
If x > d/2, the expression (d/2-x) yields negative value indicating that
the pile centre is located at (x-d/2) inside the section. When
(d/2-x), outside is true for other case.
Let the fraction of pile reaction inducing shear be f R where R is the pile
reaction.
Rule for checking one way shear,
f = 150 +(x-d/2)
300
where x and d are in millimeters.
DESIGN OF TWO PILE CAP
DATA:-
Pile Diameter : 400 mm
Spacing of piles 2 hp = 2 x 400 : 800 mm
Column Dimension B x D : 300 x 450 mm
Factored Load : 1072.8 KN
Factored Moment Mxu :51.29 KN.m
Safe Load on Single Pile :500KN
Concrete Mix : M20
Steel Grade : Fe 415
DESIGN : -
1. Pile Cap Dimension :
Breadth of Pile Cap = C/c of Pile + hp /2+ 150 + hp /2 + 150
= 800 + 400/2+ 150 +400/2+ 150 =1500 mm
Width of pile cap = hp + 150 + 150 = 700 mm
Depth of Pile cap = 2 hp + 100 = 2 x 400 + 100 = 900 mm.
2. Check for Pile Load capacity :-
Total factored axial compressive load
= Pu +/- Mxy +/- Mxx
n ∑y
2
∑x
2
Self weight of Pile Cap = (1.5 x0.7 x 0.9 x 25 ) x1.5 = 35.45 KN
Factored load from column Pu = 1072.80 KN
------------
Total Factored Load Pu = 1108.25 KN
-------------
No. of Piles along one side of axis = 2
y coordinate of Pile cap = 0.4 m
Mx = Moment about x axis = 51.29 KN.m
Compressive load in A1 & A2 about x – x axis
= 1108.25 + 51.29 x 0.4
2 2 x 0.4
2
= 554.13 + 64.11
=618.24 KN
Design working load = 618.24 /1.5 = 412.16 KN < Safe Load on Pile i.e
500KN. O.K.
3. Bending Moment :-
Factored Moment in section Y-Y
Mu = 618.24 x (0.8-0.3)= 154.56 KN.m
2
4. Check for effective depth :
Mu = 0.138 fck b d
2
= 154.56 x 10
6
d required = √ (154.56 x 10
6
) / 2.76 x700 =282.84 mm
D provided = 900 mm
d available = 900 – 60 -12- 6 = 822 mm > d required i.e. 282.84 mm
5. Check for Punching Shear (Two way shear) : -
Punching shear at a distance d/2 (i.e.822/2= 411mm) from face of column
= 1072.80 KN
The critical section of punching comes the centre of pile.
Hence the net load is to be taken. However the depth is checked for factored
axial load from column = 1072.80 KN
b= 700 x 822 mm
d= 822 mm
Perimeter of critical section = 2 (700 + 822) = 3044 mm
Punching shear stress = 1072.80 x 10
3
= 0. 43 N/mm
2
3044 x 822
Allowable shear stress for M20
= 0.25 √fck = 0.25 √20 = 1.12 N/mm
2
Hence safe.
6. Main Reinforcement : -
Mu = 154.56 x 10
6
KN.m
K = Mu / bd
2
= 154.56 x 10
6
= 0.33
700 x 822
2
Pt from Table 2 of Design Aid=0.11
Minimum Ast = 0.12 x 700 x 822 = 690.48 mm
2
100
Provide 7 Nos. 12 Φ RTS at bottom on both ways.
(Ast = 791 mm
2
> 690.48 mm
2
)
Reinforcement at top :-
Minimum Ast = 0.12 x 700 x 822 = 690.48 mm
2
100
Provide 7 Nos. 12 mm Dia RTS at top .
(Ast = 791 mm
2
> 690.48 mm
2
)
7. Check for one way shear :-
Maximum Shear force at face of column = 618.24 KN
Shear stress = 618.24 x 10
3
= 1.07 N/mm
2
700 x 822
For Pt = 0.20%
ζc from Table 61 of Design Aid to IS 456 -1978 = 0.33 N /mm
2
Shear to be carried by stirrups shear
Vus =(1.07– 0.33) x700 x822 x 10
-3
= 425.80 KN.
Vus /d = 425.80 / 82.2 = 5.18 KN/cm
Provide 8 Φ RTS 4 legged stirrups @ 120 mm c/c.
(Vus /d =5.58 KN/m > 5.18 KN/cm ).
8. Sketch :

More Related Content

What's hot

Geotechnical Engineering-II [Lec #19: General Bearing Capacity Equation]
Geotechnical Engineering-II [Lec #19: General Bearing Capacity Equation]Geotechnical Engineering-II [Lec #19: General Bearing Capacity Equation]
Geotechnical Engineering-II [Lec #19: General Bearing Capacity Equation]
Muhammad Irfan
 
Chapter 15
Chapter 15Chapter 15
Chapter 15
SantistebanCampos
 
Design of R.C.C Beam
Design of R.C.C BeamDesign of R.C.C Beam
Design of R.C.C Beam
Ar. Aakansha
 
Stucture Design of various Watre tank
 Stucture Design of various Watre tank Stucture Design of various Watre tank
Stucture Design of various Watre tank
Nagma Modi
 
Lateral Earth pressure
Lateral Earth pressureLateral Earth pressure
Lateral Earth pressure
Latif Hyder Wadho
 
Design of concrete beam
Design of concrete beamDesign of concrete beam
Design of concrete beam
sathananthankartheep
 
Design of columns uniaxial load as per IS 456-2000
Design of columns  uniaxial load as per IS 456-2000Design of columns  uniaxial load as per IS 456-2000
Design of columns uniaxial load as per IS 456-2000
PraveenKumar Shanmugam
 
Sgp4813 measurement of quantities
Sgp4813 measurement of quantitiesSgp4813 measurement of quantities
Sgp4813 measurement of quantities
alanchong88
 
water tank
water tankwater tank
water tank
Sukanta Paul
 
05 chapter 6 mat foundations
05 chapter 6 mat foundations05 chapter 6 mat foundations
05 chapter 6 mat foundations
Fábio Albino De Souza
 
Design of One-Way Slab
Design of One-Way SlabDesign of One-Way Slab
Design of One-Way Slab
Mohotasimur Anik
 
Cube test REPORT - DCC2042
Cube test REPORT - DCC2042Cube test REPORT - DCC2042
Cube test REPORT - DCC2042
Pavitrah Segaran
 
Watertank
WatertankWatertank
Watertank
Shawon Aziz
 
Design and analysis of slabs
Design and analysis of slabsDesign and analysis of slabs
Design and analysis of slabs
himachal pradesh technical university
 
Settlement of piles
Settlement of pilesSettlement of piles
Settlement of piles
Latif Hyder Wadho
 
2911 1 3
2911 1 32911 1 3
Design project
Design projectDesign project
Design project
Kabilan Kabi
 
Circular slabs
Circular slabsCircular slabs
Circular slabs
Rahul
 
Retaining wall
Retaining wallRetaining wall
Retaining wall
51412
 
Intze ppt
Intze pptIntze ppt

What's hot (20)

Geotechnical Engineering-II [Lec #19: General Bearing Capacity Equation]
Geotechnical Engineering-II [Lec #19: General Bearing Capacity Equation]Geotechnical Engineering-II [Lec #19: General Bearing Capacity Equation]
Geotechnical Engineering-II [Lec #19: General Bearing Capacity Equation]
 
Chapter 15
Chapter 15Chapter 15
Chapter 15
 
Design of R.C.C Beam
Design of R.C.C BeamDesign of R.C.C Beam
Design of R.C.C Beam
 
Stucture Design of various Watre tank
 Stucture Design of various Watre tank Stucture Design of various Watre tank
Stucture Design of various Watre tank
 
Lateral Earth pressure
Lateral Earth pressureLateral Earth pressure
Lateral Earth pressure
 
Design of concrete beam
Design of concrete beamDesign of concrete beam
Design of concrete beam
 
Design of columns uniaxial load as per IS 456-2000
Design of columns  uniaxial load as per IS 456-2000Design of columns  uniaxial load as per IS 456-2000
Design of columns uniaxial load as per IS 456-2000
 
Sgp4813 measurement of quantities
Sgp4813 measurement of quantitiesSgp4813 measurement of quantities
Sgp4813 measurement of quantities
 
water tank
water tankwater tank
water tank
 
05 chapter 6 mat foundations
05 chapter 6 mat foundations05 chapter 6 mat foundations
05 chapter 6 mat foundations
 
Design of One-Way Slab
Design of One-Way SlabDesign of One-Way Slab
Design of One-Way Slab
 
Cube test REPORT - DCC2042
Cube test REPORT - DCC2042Cube test REPORT - DCC2042
Cube test REPORT - DCC2042
 
Watertank
WatertankWatertank
Watertank
 
Design and analysis of slabs
Design and analysis of slabsDesign and analysis of slabs
Design and analysis of slabs
 
Settlement of piles
Settlement of pilesSettlement of piles
Settlement of piles
 
2911 1 3
2911 1 32911 1 3
2911 1 3
 
Design project
Design projectDesign project
Design project
 
Circular slabs
Circular slabsCircular slabs
Circular slabs
 
Retaining wall
Retaining wallRetaining wall
Retaining wall
 
Intze ppt
Intze pptIntze ppt
Intze ppt
 

Viewers also liked

Pile Foundation presentation
Pile Foundation presentationPile Foundation presentation
Pile Foundation presentation
Sevar Dilkhaz
 
Sachpazis: 4 rc piles cap design with eccentricity example (bs8110 part1-1997)
Sachpazis: 4 rc piles cap design with eccentricity example (bs8110 part1-1997)Sachpazis: 4 rc piles cap design with eccentricity example (bs8110 part1-1997)
Sachpazis: 4 rc piles cap design with eccentricity example (bs8110 part1-1997)
Dr.Costas Sachpazis
 
Pile foundation
Pile  foundation Pile  foundation
Pile foundation
Sherchandra Shrestha
 
Pile foundation ppt
Pile foundation pptPile foundation ppt
Pile foundation ppt
Surat Construction PVT LTD
 
Pile foundation
Pile foundationPile foundation
Pile foundation
Shivam Gandhi
 
Pile Foundations
Pile FoundationsPile Foundations
Pile Foundations
VARANASI RAMA RAO
 

Viewers also liked (6)

Pile Foundation presentation
Pile Foundation presentationPile Foundation presentation
Pile Foundation presentation
 
Sachpazis: 4 rc piles cap design with eccentricity example (bs8110 part1-1997)
Sachpazis: 4 rc piles cap design with eccentricity example (bs8110 part1-1997)Sachpazis: 4 rc piles cap design with eccentricity example (bs8110 part1-1997)
Sachpazis: 4 rc piles cap design with eccentricity example (bs8110 part1-1997)
 
Pile foundation
Pile  foundation Pile  foundation
Pile foundation
 
Pile foundation ppt
Pile foundation pptPile foundation ppt
Pile foundation ppt
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
Pile Foundations
Pile FoundationsPile Foundations
Pile Foundations
 

Similar to Pile cap two pile laod 50 t desigh and drawing

Memo 55b-rvk-101-rekommended-reinforcement-pattern
Memo 55b-rvk-101-rekommended-reinforcement-patternMemo 55b-rvk-101-rekommended-reinforcement-pattern
Memo 55b-rvk-101-rekommended-reinforcement-pattern
S.s. Lee
 
Memo 55c-tss-41-rekommended-reinforcement-pattern
Memo 55c-tss-41-rekommended-reinforcement-patternMemo 55c-tss-41-rekommended-reinforcement-pattern
Memo 55c-tss-41-rekommended-reinforcement-pattern
S.s. Lee
 
Design of Beam- RCC Singly Reinforced Beam
Design of Beam- RCC Singly Reinforced BeamDesign of Beam- RCC Singly Reinforced Beam
Design of Beam- RCC Singly Reinforced Beam
SHAZEBALIKHAN1
 
Esd ppt 150180106093,111,160183106008 GECDAHOD
Esd ppt 150180106093,111,160183106008 GECDAHODEsd ppt 150180106093,111,160183106008 GECDAHOD
Esd ppt 150180106093,111,160183106008 GECDAHOD
yasir Khan
 
Compression member
Compression memberCompression member
Compression member
Vikas Mehta
 
Design of torsion reinforcement
 Design of torsion reinforcement Design of torsion reinforcement
Design of torsion reinforcement
MuskanDeura
 
lacing and battening .pptx
lacing and battening .pptxlacing and battening .pptx
lacing and battening .pptx
mayur280524
 
Design of singly reinforced.
Design of singly reinforced.Design of singly reinforced.
Design of singly reinforced.
ITM College of engineering,kamptee,nagpur
 
Design of short columns using helical reinforcement
Design of short columns using helical reinforcementDesign of short columns using helical reinforcement
Design of short columns using helical reinforcement
shivam gautam
 
Chapter 2 shear design
Chapter 2   shear design Chapter 2   shear design
Chapter 2 shear design
ZINZINTUN
 
Paper no. 2
Paper no. 2Paper no. 2
Paper no. 2
Nicolae Danila
 
Strut and-tie modeling
Strut and-tie modelingStrut and-tie modeling
Strut and-tie modeling
Khaled Sobhy Emam
 
0 ne way slab
0 ne way slab0 ne way slab
0 ne way slab
Golu Singh
 
Practical on cotter joint.pptx
Practical on cotter joint.pptxPractical on cotter joint.pptx
Practical on cotter joint.pptx
fahamkhan7
 
Iii design-of-steel-structures-unit-2
Iii design-of-steel-structures-unit-2Iii design-of-steel-structures-unit-2
Iii design-of-steel-structures-unit-2
saibabu48
 
Design of column base plates anchor bolt
Design of column base plates anchor boltDesign of column base plates anchor bolt
Design of column base plates anchor bolt
Khaled Eid
 
design-of-singly-reinforced-beam.ppt
design-of-singly-reinforced-beam.pptdesign-of-singly-reinforced-beam.ppt
design-of-singly-reinforced-beam.ppt
ProfKaushalParikh
 
fdocuments.in_design-of-singly-reinforced-5681874f52c1b.ppt
fdocuments.in_design-of-singly-reinforced-5681874f52c1b.pptfdocuments.in_design-of-singly-reinforced-5681874f52c1b.ppt
fdocuments.in_design-of-singly-reinforced-5681874f52c1b.ppt
SuvenduMajumder
 
Koppolu abishek prying action
Koppolu abishek   prying actionKoppolu abishek   prying action
Koppolu abishek prying action
Koppolu Abishek
 
Steel column base44
Steel column base44Steel column base44
Steel column base44
tapaswini Mohapatra Samant
 

Similar to Pile cap two pile laod 50 t desigh and drawing (20)

Memo 55b-rvk-101-rekommended-reinforcement-pattern
Memo 55b-rvk-101-rekommended-reinforcement-patternMemo 55b-rvk-101-rekommended-reinforcement-pattern
Memo 55b-rvk-101-rekommended-reinforcement-pattern
 
Memo 55c-tss-41-rekommended-reinforcement-pattern
Memo 55c-tss-41-rekommended-reinforcement-patternMemo 55c-tss-41-rekommended-reinforcement-pattern
Memo 55c-tss-41-rekommended-reinforcement-pattern
 
Design of Beam- RCC Singly Reinforced Beam
Design of Beam- RCC Singly Reinforced BeamDesign of Beam- RCC Singly Reinforced Beam
Design of Beam- RCC Singly Reinforced Beam
 
Esd ppt 150180106093,111,160183106008 GECDAHOD
Esd ppt 150180106093,111,160183106008 GECDAHODEsd ppt 150180106093,111,160183106008 GECDAHOD
Esd ppt 150180106093,111,160183106008 GECDAHOD
 
Compression member
Compression memberCompression member
Compression member
 
Design of torsion reinforcement
 Design of torsion reinforcement Design of torsion reinforcement
Design of torsion reinforcement
 
lacing and battening .pptx
lacing and battening .pptxlacing and battening .pptx
lacing and battening .pptx
 
Design of singly reinforced.
Design of singly reinforced.Design of singly reinforced.
Design of singly reinforced.
 
Design of short columns using helical reinforcement
Design of short columns using helical reinforcementDesign of short columns using helical reinforcement
Design of short columns using helical reinforcement
 
Chapter 2 shear design
Chapter 2   shear design Chapter 2   shear design
Chapter 2 shear design
 
Paper no. 2
Paper no. 2Paper no. 2
Paper no. 2
 
Strut and-tie modeling
Strut and-tie modelingStrut and-tie modeling
Strut and-tie modeling
 
0 ne way slab
0 ne way slab0 ne way slab
0 ne way slab
 
Practical on cotter joint.pptx
Practical on cotter joint.pptxPractical on cotter joint.pptx
Practical on cotter joint.pptx
 
Iii design-of-steel-structures-unit-2
Iii design-of-steel-structures-unit-2Iii design-of-steel-structures-unit-2
Iii design-of-steel-structures-unit-2
 
Design of column base plates anchor bolt
Design of column base plates anchor boltDesign of column base plates anchor bolt
Design of column base plates anchor bolt
 
design-of-singly-reinforced-beam.ppt
design-of-singly-reinforced-beam.pptdesign-of-singly-reinforced-beam.ppt
design-of-singly-reinforced-beam.ppt
 
fdocuments.in_design-of-singly-reinforced-5681874f52c1b.ppt
fdocuments.in_design-of-singly-reinforced-5681874f52c1b.pptfdocuments.in_design-of-singly-reinforced-5681874f52c1b.ppt
fdocuments.in_design-of-singly-reinforced-5681874f52c1b.ppt
 
Koppolu abishek prying action
Koppolu abishek   prying actionKoppolu abishek   prying action
Koppolu abishek prying action
 
Steel column base44
Steel column base44Steel column base44
Steel column base44
 

More from RAJESH JAIN

Structural design including disaster (wind & cyclone land slide_eq_ resistan...
Structural design including disaster (wind & cyclone  land slide_eq_ resistan...Structural design including disaster (wind & cyclone  land slide_eq_ resistan...
Structural design including disaster (wind & cyclone land slide_eq_ resistan...
RAJESH JAIN
 
IS 13920 1993 ductile detailing of RCC structures subjected to seismic force...
IS 13920 1993  ductile detailing of RCC structures subjected to seismic force...IS 13920 1993  ductile detailing of RCC structures subjected to seismic force...
IS 13920 1993 ductile detailing of RCC structures subjected to seismic force...
RAJESH JAIN
 
Correlation between cbr and index propertys of soil
Correlation between cbr and index propertys of soilCorrelation between cbr and index propertys of soil
Correlation between cbr and index propertys of soil
RAJESH JAIN
 
Rj non updating of demand ay 2007 08
Rj non updating of demand ay 2007 08Rj non updating of demand ay 2007 08
Rj non updating of demand ay 2007 08
RAJESH JAIN
 
Me thesis effect of cement kiln dust on geotechnical properties of black cott...
Me thesis effect of cement kiln dust on geotechnical properties of black cott...Me thesis effect of cement kiln dust on geotechnical properties of black cott...
Me thesis effect of cement kiln dust on geotechnical properties of black cott...
RAJESH JAIN
 
Me thesis effect of common salt (na cl) on behaviour of black cotton soil e...
Me  thesis effect of common salt (na cl) on behaviour of black cotton soil  e...Me  thesis effect of common salt (na cl) on behaviour of black cotton soil  e...
Me thesis effect of common salt (na cl) on behaviour of black cotton soil e...
RAJESH JAIN
 
Guideline , rules notice verification reval_2015
Guideline , rules notice verification reval_2015Guideline , rules notice verification reval_2015
Guideline , rules notice verification reval_2015
RAJESH JAIN
 

More from RAJESH JAIN (7)

Structural design including disaster (wind & cyclone land slide_eq_ resistan...
Structural design including disaster (wind & cyclone  land slide_eq_ resistan...Structural design including disaster (wind & cyclone  land slide_eq_ resistan...
Structural design including disaster (wind & cyclone land slide_eq_ resistan...
 
IS 13920 1993 ductile detailing of RCC structures subjected to seismic force...
IS 13920 1993  ductile detailing of RCC structures subjected to seismic force...IS 13920 1993  ductile detailing of RCC structures subjected to seismic force...
IS 13920 1993 ductile detailing of RCC structures subjected to seismic force...
 
Correlation between cbr and index propertys of soil
Correlation between cbr and index propertys of soilCorrelation between cbr and index propertys of soil
Correlation between cbr and index propertys of soil
 
Rj non updating of demand ay 2007 08
Rj non updating of demand ay 2007 08Rj non updating of demand ay 2007 08
Rj non updating of demand ay 2007 08
 
Me thesis effect of cement kiln dust on geotechnical properties of black cott...
Me thesis effect of cement kiln dust on geotechnical properties of black cott...Me thesis effect of cement kiln dust on geotechnical properties of black cott...
Me thesis effect of cement kiln dust on geotechnical properties of black cott...
 
Me thesis effect of common salt (na cl) on behaviour of black cotton soil e...
Me  thesis effect of common salt (na cl) on behaviour of black cotton soil  e...Me  thesis effect of common salt (na cl) on behaviour of black cotton soil  e...
Me thesis effect of common salt (na cl) on behaviour of black cotton soil e...
 
Guideline , rules notice verification reval_2015
Guideline , rules notice verification reval_2015Guideline , rules notice verification reval_2015
Guideline , rules notice verification reval_2015
 

Recently uploaded

ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
Mukeshwaran Balu
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
IJNSA Journal
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
Rahul
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
nooriasukmaningtyas
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
mahammadsalmanmech
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
bank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdfbank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdf
Divyam548318
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
gerogepatton
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
jpsjournal1
 
2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt
PuktoonEngr
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
JamalHussainArman
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
VICTOR MAESTRE RAMIREZ
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
NidhalKahouli2
 
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
awadeshbabu
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
anoopmanoharan2
 
Wearable antenna for antenna applications
Wearable antenna for antenna applicationsWearable antenna for antenna applications
Wearable antenna for antenna applications
Madhumitha Jayaram
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
Dr Ramhari Poudyal
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
insn4465
 

Recently uploaded (20)

ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
bank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdfbank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdf
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
 
2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
 
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
 
Wearable antenna for antenna applications
Wearable antenna for antenna applicationsWearable antenna for antenna applications
Wearable antenna for antenna applications
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
 

Pile cap two pile laod 50 t desigh and drawing

  • 1. PILE CAP DESIGN PILE CAP:- A reinforced concrete slab or block which interconnects a group of piles and acts as a medium to transmit the load from wall or column to the Piles is called a Pile Cap. The Pile cap should normally be rigid so as to distribute the forces equally on the piles of a group. In general it is designed like a footing on soil but with the difference that instead of uniform reaction from the soil, the reactions in this case are concentrated either point loads or distributed. As per IS 2911 (Part I/ Sec 3) -2010, the pile cap may be designed by assuming that the load from column is dispersed at 45˚ from the top of the cap up to the mid depth of the pile cap from the base of the column or pedestal. The reaction from piles may also be taken to be distributed at 45˚ from the edge of the pile, up to the mid depth of the pile cap. On this basis the maximum bending moment and shear forces should be worked out at critical sections. ASSUMPTIONS INVOLVED IN THE DESIGN OF PILE CAPS:- (i) Pile cap is perfectly rigid. (ii) Pile heads are hinged to the pile cap and hence no bending moment is transmitted to piles from pile caps. (iii) Since the piles are short and elastic columns, the deformations and stress distribution are planer. DESIGN PARAMETERS OF PILE CAPS:- (i) Shape of pile cap. (ii) Depth of pile cap. (iii) Amount of steel to be provided. (iv) Arrangement of reinforcement.
  • 2. (i) Shape of pile cap:- Whittle and Beattie have developed through computer program the relationship between dimension of pile cap and the size of the pile. The minimum spacing of piles permitted from soil mechanics depends on the type and end conditions. CP 2004 requires a minimum centre- to –centre spacing of twice the diameter of the piles for end bearing and three times the diameter for friction piles. IS 2911 part1, sections 1 and 2 recommended a minimum spacing of two and half times the diameter of the pile for both driven cast in situ and bored cast in situ piles. For accommodating deviations in driving of piles, the size of the pile cap is made 300 mm more than the outer- to outer distance of the exterior piles. (150 mm on either side). The plan dimension of the pile cap is based on the fact that the actual final position of piles can be in construction up to 100 mm out of line from the theoretical centre lines. Pile caps should be made very large to accommodate these deviations. In practice, pile caps are extended as much as 150 mm beyond the outer face of the piles. Standard Pile Caps: s-spacing of pile = F x hp where hp = diameter of pile in mm F = spacing factor= centre to centre spacing Pile diameter
  • 3. (ii) Depth of Pile Cap :- The thickness of the Pile Cap is fixed such that it is adequate to resist shear without shear reinforcement and the bars projecting from the piles and the dowel bars for the column can be provided adequate bond length. As per IS 456- 2000, the minimum thickness on top of piles should not be less than 300 mm. Pile cap depth should be kept on the high side to effect economy in the consumption of steel and also to provide adequate rigidity to pile cap. Generally, pile cap thickness should not be less than 500 mm which may be reduced to 300 mm at the free edges. For pile caps to be rigid, pile cap has to be quite deep with 600 mm as the minimum depth. As a guide line the formula given in Reinforced concrete by Reynolds may be followed. For Pile dia > 550 mm, Pile cap depth (h) = (2 hp + 100)mm For Pile dia ≥ 550 mm, h= ⅓ x( 8 hp + 600) mm Pile Dia hp (mm) 300 350 400 450 500 550 600 750 Pile Cap depth h(mm) 700 800 900 1000 1100 1200 1400 1800 (i) Amount of steel to be provided :- The Pile Cap has to be designed either truss theory or beam theory. Although, the pile caps are assumed to act as a simply supported beam and are designed for the usual condition of bending and shear, their tendency is to fail by bursting due to high principal tension and they will therefore always require a cage of reinforcement in three dimensions to resist this tendency. The main reinforcement is usually bend (full bend) and extended for full depth of pile cap to fulfill the check for development length. Though IS 456-2000 is silent on specifying the minimum reinforcement, a minimum reinforcement of 0.15 % BD for main reinforcement and 0.12 % BD for secondary reinforcement may be provided as per clause 3 .11.4.1 and 2 of CP 110 code). For bursting (horizontal binders) it is
  • 4. suggested that 25 % of the main reinforcement (usually 12 Φ RTS at 150 mm c/c) shall be used. Cover :- A cover of 75 mm is usually provided for the pile cap surfaces in contact with earth and 60 mm against blinding concrete of 75 to 100 mm thick. In marine situations the cover should be increased to a minimum of 80 mm. DESIGN OF PILE CAP BASED ON TRUSS THEORY: The truss theory applied to pile caps with up to 5 piles. In this method the load from the column is transmitted to the piles by inclined thrust and the tie necessary to maintain equilibrium is provided by reinforcement. (Steel acts as tension chord and concrete as diagonal struts). If the Ultimate load on the column is N and we have two piles the load on each pile is N/2. From the diagram of forces T = l (N/2) d i.e. T = N l/2d Area of reinforcement required = Nl/ (2d x 0.87 fy ) In the simple frame described above, the dimensions of the columns have been ignored. If the Column is square of side 2a, T = N (3l 2 – a 2 ) 6 ld In truss theory, it has usually been the practice to band the reinforcement along the lines joining the piles. The code now suggests that this method of banding is only necessary if the piles are spaced at more than 3 times the pile dia. For the more normal spacing of 3 times the pile dia the total reinforcement forming the tie force in one direction can be distributed uniformly across the cap with a three- pile cap designed on the truss theory, it is difficult to see how this can be done and it is suggested that the reinforcement is banded along the centre lines joining the piles. In the case of pile caps designed using the truss theory it is suggested that the effective depth is approximately half the distance between the centre of piles. This means the truss has an angle of approximately 45˚.
  • 5. Allowable shear resistance is given by N= 2 (d hp ) 2 ζc (d/av) + (b- 2 hp ) ζc bd where ζc = design shear strength of concrete. av = 0.5(l- b) where l= c/c of piles & b = width of column. The section should be safe without extra shear reinforcement. Truss theory design can be done using Table 194 of Reynould’s hand book.
  • 6. Beam theory :- When (av / d) ratio is more than 2 as in shallow pile cap or with the arrangement of 6 or more piles, bending action is more predominant than truss action. In this case the pile cap is designed as a normal beam for bending moment and shear. The pile cap area is divided into a framework of rectangular beam depending on the geometry of the pile group. The width of the beam is taken as equal to the width of the pile. The beam may be simply supported or continuous. The reinforcement is evenly distributed or concentrated. The reaction from the pile is taken as distributed at 45˚ from the edge of the pile cap up to the mid- depth of the pile cap. The maximum bending moment and shear force are calculated on this basis. However, it is much easier to consider the loads as concentrated loads and calculate the B.M. and S.F. The depth should be such that no extra shear reinforcement is necessary for the section.
  • 7. Practical Aspects on Pile cap Design: The structural design of a pile cap is similar to the design of spread footing. The load acting on the pile cap from the superstructure and piles are resisted by the developments of bending moment and shear force in the pile cap. Codal provisions made in IS 2911(Part 1/sec3)-2010 : 1. The size of the pile cap is fixed in such way that it has clear overhang beyond the outermost pile not less than 100mm, but preferably 150mm. 2. It should be deep enough to allow the necessary overlap of reinforcements from column and piles. 3. The clear cover to the main reinforcement should not be less than 40mm. 4. The span to thickness ratio of the cap should not be more than 5 so that pile cap is rigid enough to distribute the load uniformly to the piles. 5. Generally, its thickness should not be less than 500mm which may be reduced to 300mm at the free edges. 6. The piles should atleast 50mm into the pile cap. 7. A leveling course of not less 75mm thick concrete should be provided under the pile cap. Design Aspects :- The reaction from the piles under the concentric axial load on the cap is assumed equal and is determined by, Pp = Q/n ----- (1) where Q = concentric axial load on the cap n = Number of Piles When the Pile cap is eccentrically loaded or subjected to a load and moments then the reactions from the Piles are determined as Pp = Q/n +/- My x +/- Mx y ----- (2) where ∑x2 ∑y2 Mx, My = moments with respect to x and y axes. X, y = distances from y and x axes to the Piles.
  • 8. The critical section for bending moments and bond shall be calculated at the face of column or pedestal. The critical section for two way shear (Punching shear) will be at a distance d/2 from face of column or pedestal. One way shear is checked at a distance of d/2 from the face of the column. The Clause 34.2.4.2 of IS 456 – 2000 states the following :- “In computing the external shear or any section through a footing supported on Piles, the entire reaction from any pile of diameter Dp whose centre is located Dp/2 or more outside the section shall be assumed as producing shear on the section; the reaction from any Pile whose centre is located Dp/2 or more inside the section shall be assumed as producing no shear on the section. For intermediate positions of the pile centre, the position of pile reaction to be assumed as producing shear on the section shall be based on straight line interpolation between full value at Dp/2 outside the section and zero value at Dp/2 inside the section.” In computing external shear on any section the entire (100%) reaction of the Pile shall be taken if the pile centre is located at 150 mm or more outside the section. The pile reaction will produce no shear (0%) if the pile centre is located at 150 mm or more inside the section. A linear interpolation shall be made for intermediate values of the pile centre. Let the centre of the pile be located at ‘x’ from the face of the column. Let ‘d’ be the effective depth of the pile cap. Then the critical section is located at d/2 from face of the column. If pile centre is located at (d/2 –x) outside the critical section when x < d/2. If x > d/2, the expression (d/2-x) yields negative value indicating that the pile centre is located at (x-d/2) inside the section. When (d/2-x), outside is true for other case. Let the fraction of pile reaction inducing shear be f R where R is the pile reaction. Rule for checking one way shear, f = 150 +(x-d/2) 300 where x and d are in millimeters.
  • 9. DESIGN OF TWO PILE CAP DATA:- Pile Diameter : 400 mm Spacing of piles 2 hp = 2 x 400 : 800 mm Column Dimension B x D : 300 x 450 mm Factored Load : 1072.8 KN Factored Moment Mxu :51.29 KN.m Safe Load on Single Pile :500KN Concrete Mix : M20 Steel Grade : Fe 415 DESIGN : - 1. Pile Cap Dimension : Breadth of Pile Cap = C/c of Pile + hp /2+ 150 + hp /2 + 150 = 800 + 400/2+ 150 +400/2+ 150 =1500 mm Width of pile cap = hp + 150 + 150 = 700 mm Depth of Pile cap = 2 hp + 100 = 2 x 400 + 100 = 900 mm.
  • 10. 2. Check for Pile Load capacity :- Total factored axial compressive load = Pu +/- Mxy +/- Mxx n ∑y 2 ∑x 2 Self weight of Pile Cap = (1.5 x0.7 x 0.9 x 25 ) x1.5 = 35.45 KN Factored load from column Pu = 1072.80 KN ------------ Total Factored Load Pu = 1108.25 KN ------------- No. of Piles along one side of axis = 2 y coordinate of Pile cap = 0.4 m Mx = Moment about x axis = 51.29 KN.m Compressive load in A1 & A2 about x – x axis = 1108.25 + 51.29 x 0.4 2 2 x 0.4 2 = 554.13 + 64.11 =618.24 KN Design working load = 618.24 /1.5 = 412.16 KN < Safe Load on Pile i.e 500KN. O.K. 3. Bending Moment :- Factored Moment in section Y-Y Mu = 618.24 x (0.8-0.3)= 154.56 KN.m 2 4. Check for effective depth : Mu = 0.138 fck b d 2 = 154.56 x 10 6 d required = √ (154.56 x 10 6 ) / 2.76 x700 =282.84 mm D provided = 900 mm d available = 900 – 60 -12- 6 = 822 mm > d required i.e. 282.84 mm 5. Check for Punching Shear (Two way shear) : - Punching shear at a distance d/2 (i.e.822/2= 411mm) from face of column = 1072.80 KN The critical section of punching comes the centre of pile.
  • 11. Hence the net load is to be taken. However the depth is checked for factored axial load from column = 1072.80 KN b= 700 x 822 mm d= 822 mm Perimeter of critical section = 2 (700 + 822) = 3044 mm Punching shear stress = 1072.80 x 10 3 = 0. 43 N/mm 2 3044 x 822 Allowable shear stress for M20 = 0.25 √fck = 0.25 √20 = 1.12 N/mm 2 Hence safe. 6. Main Reinforcement : - Mu = 154.56 x 10 6 KN.m K = Mu / bd 2 = 154.56 x 10 6 = 0.33 700 x 822 2 Pt from Table 2 of Design Aid=0.11 Minimum Ast = 0.12 x 700 x 822 = 690.48 mm 2 100 Provide 7 Nos. 12 Φ RTS at bottom on both ways. (Ast = 791 mm 2 > 690.48 mm 2 ) Reinforcement at top :- Minimum Ast = 0.12 x 700 x 822 = 690.48 mm 2 100 Provide 7 Nos. 12 mm Dia RTS at top . (Ast = 791 mm 2 > 690.48 mm 2 ) 7. Check for one way shear :- Maximum Shear force at face of column = 618.24 KN Shear stress = 618.24 x 10 3 = 1.07 N/mm 2 700 x 822 For Pt = 0.20% ζc from Table 61 of Design Aid to IS 456 -1978 = 0.33 N /mm 2 Shear to be carried by stirrups shear
  • 12. Vus =(1.07– 0.33) x700 x822 x 10 -3 = 425.80 KN. Vus /d = 425.80 / 82.2 = 5.18 KN/cm Provide 8 Φ RTS 4 legged stirrups @ 120 mm c/c. (Vus /d =5.58 KN/m > 5.18 KN/cm ). 8. Sketch :