Our town hall with information on construction impacts on Eglinton Avenue East between Warden Avenue to Ionview Road. The town hall will feature detailed project maps and imagery, a small presentation, and a Q&A segment.
Pharmacy kennedy clc meeting - deck - march 26,2019Crosstown TO
The document provides an update on construction progress and upcoming work for the Eglinton Crosstown LRT project in the Pharmacy and Kennedy areas. In Pharmacy, guideway and road work is ongoing, with intersection paving at Pharmacy Avenue scheduled for March 30-31 and April 13-14. In Kennedy, major milestones have been completed including the vertical piles and GO East platform restoration. Current activities include utility relocations and support of excavation for Kennedy Portal and Station Box. Upcoming work includes completion of the West Portal by summer 2019 and installation of a telecommunications antenna at Kennedy Station.
Pharmacy kennedy clc meeting -january 29 2019Crosstown TO
This document provides an update on construction progress for the Crosstown LRT Pharmacy stop and Kennedy Station area. It summarizes that at Pharmacy Avenue, guideway construction is underway between Victoria Park and Pharmacy Avenues. Utility work and road widening is ongoing from Victoria Park to Birchmount Road. Massey Creek culvert reconstruction will begin in February 2019. At Kennedy Station, the GO East platform was restored and will be handed over to GO on February 2, 2019. Utility upgrades and support of excavation for the station box and tail tracks is underway. The current traffic configuration at Kennedy Road is described and expected to last until May 2019.
Metrolinx is a transportation agency that oversees GO Transit, UP Express, and PRESTO payment systems in Toronto. It aims to connect communities better, faster and easier. Key points:
- Serves over 7 million people across 11,000 sq km in the Greater Toronto and Hamilton Area
- GO Transit carries over 70 million passengers annually
- PRESTO card replaces tickets and passes for 11 transit agencies in the GTHA and Ottawa
- UP Express provides a 25-minute connection between Toronto Pearson Airport and Union Station
- The agency published its first Regional Transportation Plan in 2008 to guide transportation development
The document provides information about the construction of east tunnel and stations for the Eglinton Crosstown LRT project in Toronto. Key details include:
- Tunnel boring machines will excavate the tunnels and will be launched from a shaft near Brentcliffe Road in 2016.
- Headwalls and other structures are being constructed using methods like secant pile walls and jet grouting to support future station excavation.
- Utility relocations and road adjustments are occurring to accommodate tunneling work, including temporary lane and sidewalk closures at locations like Laird Drive.
- Emergency exit buildings and cross passages will also be built between stations to aid passenger evacuation.
- Renderings show what the future tunnel, stations, and ent
The following construction update for Pharmacy to Kennedy stations has been updated as recently as November 30, 2021. You can view the presentation here:
Metrolinx is a transportation agency that oversees various transit services in the Greater Toronto and Hamilton Area (GTHA) including GO Transit, UP Express, and PRESTO fare payment. Their mission is to connect communities through transportation. Key projects mentioned include the Eglinton Crosstown LRT, which will be a 19km light rail line running mostly underground along Eglinton Avenue. The document provides details on the scope and status of construction for various sections of the project, including upcoming traffic restrictions to facilitate guideway and track installation at intersections along Eglinton Avenue East.
Pharmacy kennedy clc meeting - deck - march 26,2019Crosstown TO
The document provides an update on construction progress and upcoming work for the Eglinton Crosstown LRT project in the Pharmacy and Kennedy areas. In Pharmacy, guideway and road work is ongoing, with intersection paving at Pharmacy Avenue scheduled for March 30-31 and April 13-14. In Kennedy, major milestones have been completed including the vertical piles and GO East platform restoration. Current activities include utility relocations and support of excavation for Kennedy Portal and Station Box. Upcoming work includes completion of the West Portal by summer 2019 and installation of a telecommunications antenna at Kennedy Station.
Pharmacy kennedy clc meeting -january 29 2019Crosstown TO
This document provides an update on construction progress for the Crosstown LRT Pharmacy stop and Kennedy Station area. It summarizes that at Pharmacy Avenue, guideway construction is underway between Victoria Park and Pharmacy Avenues. Utility work and road widening is ongoing from Victoria Park to Birchmount Road. Massey Creek culvert reconstruction will begin in February 2019. At Kennedy Station, the GO East platform was restored and will be handed over to GO on February 2, 2019. Utility upgrades and support of excavation for the station box and tail tracks is underway. The current traffic configuration at Kennedy Road is described and expected to last until May 2019.
Metrolinx is a transportation agency that oversees GO Transit, UP Express, and PRESTO payment systems in Toronto. It aims to connect communities better, faster and easier. Key points:
- Serves over 7 million people across 11,000 sq km in the Greater Toronto and Hamilton Area
- GO Transit carries over 70 million passengers annually
- PRESTO card replaces tickets and passes for 11 transit agencies in the GTHA and Ottawa
- UP Express provides a 25-minute connection between Toronto Pearson Airport and Union Station
- The agency published its first Regional Transportation Plan in 2008 to guide transportation development
The document provides information about the construction of east tunnel and stations for the Eglinton Crosstown LRT project in Toronto. Key details include:
- Tunnel boring machines will excavate the tunnels and will be launched from a shaft near Brentcliffe Road in 2016.
- Headwalls and other structures are being constructed using methods like secant pile walls and jet grouting to support future station excavation.
- Utility relocations and road adjustments are occurring to accommodate tunneling work, including temporary lane and sidewalk closures at locations like Laird Drive.
- Emergency exit buildings and cross passages will also be built between stations to aid passenger evacuation.
- Renderings show what the future tunnel, stations, and ent
The following construction update for Pharmacy to Kennedy stations has been updated as recently as November 30, 2021. You can view the presentation here:
Metrolinx is a transportation agency that oversees various transit services in the Greater Toronto and Hamilton Area (GTHA) including GO Transit, UP Express, and PRESTO fare payment. Their mission is to connect communities through transportation. Key projects mentioned include the Eglinton Crosstown LRT, which will be a 19km light rail line running mostly underground along Eglinton Avenue. The document provides details on the scope and status of construction for various sections of the project, including upcoming traffic restrictions to facilitate guideway and track installation at intersections along Eglinton Avenue East.
Leaside Laird CLC November 2019 PresentationCrosstown TO
This is a bi-monthly meeting hosted by Metrolinx and Crosslinx to provide construction and community relations updates to the members of Leaside and Laird Construction Liaison Committee (CLC).
Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019Crosstown TO
The document provides an update on construction progress for the Crosstown LRT project in September 2019. Work continued on guideway construction and intersections between Victoria Park and Ionview. Traction power substations 11 and 12 were under construction. Culvert reconstruction at Massey Creek was ongoing and expected to last 9 months. At Kennedy Station, excavation and underground work was progressing on the portals, station box, and areas east of GO Transit. Sidewalk closures and traffic configurations at Kennedy were also outlined.
The document provides accessibility highlights for the Leaside and Laird stations on the Eglinton Crosstown LRT. Both stations will have elevators connecting the street level to the platform level. They will also have accessible entrances and retail spaces. Additionally, all stations will have barrier-free routes, wayfinding strategies, enhanced communication devices, and other accessibility features. Construction updates are provided for ongoing work at Leaside station through summer 2021 and Laird station through July 2021.
Fall Open House: Mount Dennis - CaledoniaCrosstown TO
The document provides an update on the progress and upcoming work for the Eglinton Crosstown LRT project in Toronto. It is now 70% complete, with three stations largely finished and 69% of track installed. Vehicle testing is underway. Remaining work in 2020 includes further track, power, and station construction. Testing and commissioning of systems will continue through 2021.
Brentcliffe - Victoria Park Construction Liaison Committee MeetingCrosstown TO
The document provides information about the Crosstown LRT project, including that it will have 15 underground stations and 10 surface stops along a 19-kilometer route. Surface stops will be built at the level of the roadway on concrete pads. The project also includes a maintenance facility. Construction updates provided include that median removals and utility relocations are ongoing between Brentcliffe Portal and Victoria Park, and that the Wynford Bridge rehabilitation will begin soon in two stages. At Science Centre Station, excavation of the main station box is underway using a cut-and-cover methodology.
Eglinton & Mt pleasant CLC - November Crosstown TO
The document provides updates on construction activities for the Eglinton Crosstown LRT project, including:
- Extended hours for station box construction at Eglinton Station through early 2022.
- Berwick portal construction and a laneway closure at Berwick Avenue on November 15th for 5 hours.
- TTC works at Eglinton Station and an upcoming closure from November 13-14, 2021.
- A planned traffic configuration change at Yonge Street in late November 2021 for approximately 6 months.
- Ongoing station box, main entrance, and secondary entrance construction at Mount Pleasant Station through 2021.
Fairbank-Oakwood Construction Update - November 2021Crosstown TO
The document provides a construction progress update for the Fairbank and Oakwood stations on the Eglinton Crosstown LRT project. For Fairbank station, elevator, escalator, and floor installations were completed in October. Wall, ceiling, and lighting installations are ongoing through 2021. Sidewalk restoration along Eglinton Avenue is also ongoing. For Oakwood station, architectural finishes and mechanical/electrical works are underway in the station box through 2021. Main and secondary entrance construction is also progressing with architectural installations. The traffic configuration around both stations will continue through 2021 as construction progresses.
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018Crosstown TO
The document provides details about an upcoming Crosstown LRT meeting and construction updates. It discusses:
1) The agenda for the meeting, which will include updates on the east at-grade section and Kennedy Station.
2) Details about the Crosstown LRT, including the number of underground and surface stops, a maintenance facility, and connections to other transit lines.
3) Features of the Kennedy Station, including construction methodology, connections to other transit lines, entrances, and improvements to GO Transit infrastructure.
Pharmacy to Kennedy - November meeting Crosstown TO
The document provides an update on construction activities along Section Three and Four of the Eglinton Crosstown LRT project from O'Connor Station to Ionview Station. Road restoration from Brentcliffe Road to Kennedy Road is ongoing and will continue through winter 2021 and 2022. Testing and commissioning of light rail vehicles is also ongoing east of Brentcliffe Road. Construction at Kennedy Station is progressing with the main entrance works nearing completion in November 2021. Road configuration changes are planned at Kennedy Station in December 2021 and Transway Crescent will be closed for approximately two months for road restoration works.
This document provides an update on construction progress and upcoming work for the Eglinton Crosstown LRT project between O'Connor Drive and Ionview Road. It details construction completed between Victoria Park Avenue and Rosemount Drive, including stop installations. Upcoming work through spring 2020 includes additional stop construction and shelter installations. Temporary traffic and pedestrian impacts are expected, including lane closures. Work is also outlined at Kennedy Station, including portal excavation and structural steel installation through late 2020.
Leaside-Laird CLC Meeting - Presentation - November 8, 2021Crosstown TO
The document provides updates on construction progress at the Leaside and Laird stations of the Eglinton Crosstown LRT. At Leaside Station, work is ongoing on the station box, main entrance, and secondary entrance through 2021. Overnight utility works are scheduled for November 11th. At Laird Station, work includes main and secondary entrance construction through fall 2021, with sidewalk restoration and utility installations occurring in November. Lane reductions on Laird Drive are required for utility work from November 1st to 11th. Photos show ongoing construction and installation work.
Avenue & Chaplin CLC - Construction Update: September 1, 2021Crosstown TO
The document provides updates on construction activities at Chaplin Station and Avenue Station of the Eglinton Crosstown LRT. At Chaplin Station, work is underway on the tertiary, main, and secondary entrances as well as station box construction through fall 2021, with activities such as concrete work, steel installations, and utility works expected to cause noise and lane reductions. At Avenue Station, similar construction is ongoing on the station box, main and secondary entrances through 2021, with deliveries, concrete pours, and crane use impacting traffic. Eglinton Connects streetscape work between Lascelles Blvd and Duplex Ave will begin as early as September 7th, reducing traffic to one lane in each direction for approximately two
Avenue & Chaplin CLC - Construction Update: September 9, 2020Crosstown TO
The document provides updates on construction activities for the Chaplin Station and Avenue Station of the Eglinton Crosstown LRT. It details the delivery of a dewatering system tank, ongoing construction of station entrances and the station box, and work on the Eglinton Connects streetscape project between September 2020 and 2021. Construction will include concrete pours, utility work and installation of street furnishings. Traffic reductions on Eglinton Avenue are expected during this time period.
The document provides information about the Eglinton Crosstown LRT project in Toronto. It summarizes that (1) tunnelling is underway from Black Creek to Caledonia Avenue and will continue to Yonge Street, (2) tunnel boring machine extraction and launch shafts are being constructed near Allen Road, and (3) utility relocations and other preparatory works are occurring at future station sites to allow for tunnel construction.
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)Crosstown TO
The document provides updates on construction activities for Sections One and Two of the Eglinton Crosstown LRT project. For Section One between Brentcliffe Road and Victoria Park Avenue, work includes road widening, retaining wall construction, bridge rehabilitation, and multi-use path building. Section Two between Aga Khan Park and O'Connor sees road work, sidewalk construction, track laying, and shelter installation at O'Connor station. Construction is ongoing at Science Centre station with mechanical and electrical work as well as entrance building.
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018Crosstown TO
1) Construction is underway on the Crosstown LRT project including the Kennedy Station area. Utility relocations and road widening on Eglinton Avenue are ongoing.
2) At Kennedy Station, demolition of the existing north entrance has begun in preparation for construction of the new station. Support of excavation work will start in late March/early April.
3) A short-term closure of Ionview Road is planned to relocate utilities. GO Transit will undertake improvements including a new platform and pedestrian underpass requiring track removal over a 74.5 hour weekend blitz in late March/early April.
Brentcliffe to Victoria Park - March 4, 2021Crosstown TO
This document provides updates on construction progress for Section One and Section Two of the at-grade portion of the Eglinton Crosstown LRT. For Section One between Brentcliffe Road and Victoria Park Avenue, work is ongoing on retaining walls, track wiring installation, multi-use path construction, and pedestrian staircases. For Section Two between Aga Khan Park and Museum Stop and O'Connor Stop, work continues on station shelters, retaining walls, road widening, and track wiring with expected completion by March/April 2021. Progress photos show ongoing work at various sites including Science Centre Station.
The document provides updates on the progress and remaining work for the Eglinton Crosstown LRT project. It states that as of the end of 2020, three stations will be largely complete and 69% of track has been installed. It then provides details on the progress and upcoming work for systems installation and individual stations, including Chaplin, Avenue, Eglinton, Mount Pleasant, and Leaside stations. It also notes that the project has hired over 200 people from disadvantaged groups and spent over $600,000 on social enterprises and $6 million at local businesses.
Proposed Leslie Street Closure Town Hall Meeting - April 2019Crosstown TO
The document summarizes a town hall meeting about the Crosstown LRT project. It provides an overview of the 19km route, details about construction in 2019 including traffic restrictions from July-August at Leslie Street to allow for guideway construction, and renderings of some station areas. It also addresses questions about traction power substations that will supply power to the route.
Pharmacy kennedy clc meeting- april 30, 2019Crosstown TO
This document provides an update on construction progress and upcoming work for the Crosstown LRT project between O'Connor Drive and Ionview Road from April 2019 through 2020. Key points include:
- Guideway and boulevard work continuing between Victoria Park and Birchmount Road, with Pharmacy Avenue guideway work starting in May 2019.
- Traffic restrictions and TTC bus stop relocations between Pharmacy and Ionview Roads during guideway construction.
- Reconstruction of the Massey Creek culvert expected to be complete by late 2019.
- Infrastructure upgrades continuing at Kennedy Station through 2020, including portal and station box excavation and GO platform reconstruction.
Leaside Laird CLC November 2019 PresentationCrosstown TO
This is a bi-monthly meeting hosted by Metrolinx and Crosslinx to provide construction and community relations updates to the members of Leaside and Laird Construction Liaison Committee (CLC).
Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019Crosstown TO
The document provides an update on construction progress for the Crosstown LRT project in September 2019. Work continued on guideway construction and intersections between Victoria Park and Ionview. Traction power substations 11 and 12 were under construction. Culvert reconstruction at Massey Creek was ongoing and expected to last 9 months. At Kennedy Station, excavation and underground work was progressing on the portals, station box, and areas east of GO Transit. Sidewalk closures and traffic configurations at Kennedy were also outlined.
The document provides accessibility highlights for the Leaside and Laird stations on the Eglinton Crosstown LRT. Both stations will have elevators connecting the street level to the platform level. They will also have accessible entrances and retail spaces. Additionally, all stations will have barrier-free routes, wayfinding strategies, enhanced communication devices, and other accessibility features. Construction updates are provided for ongoing work at Leaside station through summer 2021 and Laird station through July 2021.
Fall Open House: Mount Dennis - CaledoniaCrosstown TO
The document provides an update on the progress and upcoming work for the Eglinton Crosstown LRT project in Toronto. It is now 70% complete, with three stations largely finished and 69% of track installed. Vehicle testing is underway. Remaining work in 2020 includes further track, power, and station construction. Testing and commissioning of systems will continue through 2021.
Brentcliffe - Victoria Park Construction Liaison Committee MeetingCrosstown TO
The document provides information about the Crosstown LRT project, including that it will have 15 underground stations and 10 surface stops along a 19-kilometer route. Surface stops will be built at the level of the roadway on concrete pads. The project also includes a maintenance facility. Construction updates provided include that median removals and utility relocations are ongoing between Brentcliffe Portal and Victoria Park, and that the Wynford Bridge rehabilitation will begin soon in two stages. At Science Centre Station, excavation of the main station box is underway using a cut-and-cover methodology.
Eglinton & Mt pleasant CLC - November Crosstown TO
The document provides updates on construction activities for the Eglinton Crosstown LRT project, including:
- Extended hours for station box construction at Eglinton Station through early 2022.
- Berwick portal construction and a laneway closure at Berwick Avenue on November 15th for 5 hours.
- TTC works at Eglinton Station and an upcoming closure from November 13-14, 2021.
- A planned traffic configuration change at Yonge Street in late November 2021 for approximately 6 months.
- Ongoing station box, main entrance, and secondary entrance construction at Mount Pleasant Station through 2021.
Fairbank-Oakwood Construction Update - November 2021Crosstown TO
The document provides a construction progress update for the Fairbank and Oakwood stations on the Eglinton Crosstown LRT project. For Fairbank station, elevator, escalator, and floor installations were completed in October. Wall, ceiling, and lighting installations are ongoing through 2021. Sidewalk restoration along Eglinton Avenue is also ongoing. For Oakwood station, architectural finishes and mechanical/electrical works are underway in the station box through 2021. Main and secondary entrance construction is also progressing with architectural installations. The traffic configuration around both stations will continue through 2021 as construction progresses.
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018Crosstown TO
The document provides details about an upcoming Crosstown LRT meeting and construction updates. It discusses:
1) The agenda for the meeting, which will include updates on the east at-grade section and Kennedy Station.
2) Details about the Crosstown LRT, including the number of underground and surface stops, a maintenance facility, and connections to other transit lines.
3) Features of the Kennedy Station, including construction methodology, connections to other transit lines, entrances, and improvements to GO Transit infrastructure.
Pharmacy to Kennedy - November meeting Crosstown TO
The document provides an update on construction activities along Section Three and Four of the Eglinton Crosstown LRT project from O'Connor Station to Ionview Station. Road restoration from Brentcliffe Road to Kennedy Road is ongoing and will continue through winter 2021 and 2022. Testing and commissioning of light rail vehicles is also ongoing east of Brentcliffe Road. Construction at Kennedy Station is progressing with the main entrance works nearing completion in November 2021. Road configuration changes are planned at Kennedy Station in December 2021 and Transway Crescent will be closed for approximately two months for road restoration works.
This document provides an update on construction progress and upcoming work for the Eglinton Crosstown LRT project between O'Connor Drive and Ionview Road. It details construction completed between Victoria Park Avenue and Rosemount Drive, including stop installations. Upcoming work through spring 2020 includes additional stop construction and shelter installations. Temporary traffic and pedestrian impacts are expected, including lane closures. Work is also outlined at Kennedy Station, including portal excavation and structural steel installation through late 2020.
Leaside-Laird CLC Meeting - Presentation - November 8, 2021Crosstown TO
The document provides updates on construction progress at the Leaside and Laird stations of the Eglinton Crosstown LRT. At Leaside Station, work is ongoing on the station box, main entrance, and secondary entrance through 2021. Overnight utility works are scheduled for November 11th. At Laird Station, work includes main and secondary entrance construction through fall 2021, with sidewalk restoration and utility installations occurring in November. Lane reductions on Laird Drive are required for utility work from November 1st to 11th. Photos show ongoing construction and installation work.
Avenue & Chaplin CLC - Construction Update: September 1, 2021Crosstown TO
The document provides updates on construction activities at Chaplin Station and Avenue Station of the Eglinton Crosstown LRT. At Chaplin Station, work is underway on the tertiary, main, and secondary entrances as well as station box construction through fall 2021, with activities such as concrete work, steel installations, and utility works expected to cause noise and lane reductions. At Avenue Station, similar construction is ongoing on the station box, main and secondary entrances through 2021, with deliveries, concrete pours, and crane use impacting traffic. Eglinton Connects streetscape work between Lascelles Blvd and Duplex Ave will begin as early as September 7th, reducing traffic to one lane in each direction for approximately two
Avenue & Chaplin CLC - Construction Update: September 9, 2020Crosstown TO
The document provides updates on construction activities for the Chaplin Station and Avenue Station of the Eglinton Crosstown LRT. It details the delivery of a dewatering system tank, ongoing construction of station entrances and the station box, and work on the Eglinton Connects streetscape project between September 2020 and 2021. Construction will include concrete pours, utility work and installation of street furnishings. Traffic reductions on Eglinton Avenue are expected during this time period.
The document provides information about the Eglinton Crosstown LRT project in Toronto. It summarizes that (1) tunnelling is underway from Black Creek to Caledonia Avenue and will continue to Yonge Street, (2) tunnel boring machine extraction and launch shafts are being constructed near Allen Road, and (3) utility relocations and other preparatory works are occurring at future station sites to allow for tunnel construction.
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)Crosstown TO
The document provides updates on construction activities for Sections One and Two of the Eglinton Crosstown LRT project. For Section One between Brentcliffe Road and Victoria Park Avenue, work includes road widening, retaining wall construction, bridge rehabilitation, and multi-use path building. Section Two between Aga Khan Park and O'Connor sees road work, sidewalk construction, track laying, and shelter installation at O'Connor station. Construction is ongoing at Science Centre station with mechanical and electrical work as well as entrance building.
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018Crosstown TO
1) Construction is underway on the Crosstown LRT project including the Kennedy Station area. Utility relocations and road widening on Eglinton Avenue are ongoing.
2) At Kennedy Station, demolition of the existing north entrance has begun in preparation for construction of the new station. Support of excavation work will start in late March/early April.
3) A short-term closure of Ionview Road is planned to relocate utilities. GO Transit will undertake improvements including a new platform and pedestrian underpass requiring track removal over a 74.5 hour weekend blitz in late March/early April.
Brentcliffe to Victoria Park - March 4, 2021Crosstown TO
This document provides updates on construction progress for Section One and Section Two of the at-grade portion of the Eglinton Crosstown LRT. For Section One between Brentcliffe Road and Victoria Park Avenue, work is ongoing on retaining walls, track wiring installation, multi-use path construction, and pedestrian staircases. For Section Two between Aga Khan Park and Museum Stop and O'Connor Stop, work continues on station shelters, retaining walls, road widening, and track wiring with expected completion by March/April 2021. Progress photos show ongoing work at various sites including Science Centre Station.
The document provides updates on the progress and remaining work for the Eglinton Crosstown LRT project. It states that as of the end of 2020, three stations will be largely complete and 69% of track has been installed. It then provides details on the progress and upcoming work for systems installation and individual stations, including Chaplin, Avenue, Eglinton, Mount Pleasant, and Leaside stations. It also notes that the project has hired over 200 people from disadvantaged groups and spent over $600,000 on social enterprises and $6 million at local businesses.
Proposed Leslie Street Closure Town Hall Meeting - April 2019Crosstown TO
The document summarizes a town hall meeting about the Crosstown LRT project. It provides an overview of the 19km route, details about construction in 2019 including traffic restrictions from July-August at Leslie Street to allow for guideway construction, and renderings of some station areas. It also addresses questions about traction power substations that will supply power to the route.
Pharmacy kennedy clc meeting- april 30, 2019Crosstown TO
This document provides an update on construction progress and upcoming work for the Crosstown LRT project between O'Connor Drive and Ionview Road from April 2019 through 2020. Key points include:
- Guideway and boulevard work continuing between Victoria Park and Birchmount Road, with Pharmacy Avenue guideway work starting in May 2019.
- Traffic restrictions and TTC bus stop relocations between Pharmacy and Ionview Roads during guideway construction.
- Reconstruction of the Massey Creek culvert expected to be complete by late 2019.
- Infrastructure upgrades continuing at Kennedy Station through 2020, including portal and station box excavation and GO platform reconstruction.
- The document provides a construction update for the Eglinton Crosstown LRT project in Toronto, including progress at various stations along the eastern section from Science Centre station to Kennedy station.
- Construction is ongoing with excavation, structural works, guideway and track installation underway or completed at most stations. Interior station works and finishes are nearing completion at Science Centre station.
- The project involves a 19km LRT route, 10km underground and 9km at surface, with 15 underground stations and 10 surface stops. A maintenance facility is also being constructed.
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdfCrosstown TO
The document provides updates on construction activities for different sections of the Eglinton Crosstown LRT project from September 2022. Vehicle testing is ongoing from Brentcliffe to Kennedy. Road and sidewalk restoration is ongoing from Brentcliffe to Don Mills through summer 2022. Landscaping along Eglinton is also ongoing through summer 2022. Finishing work at various stations including Science Centre station is ongoing through summer 2022 with periodic lane closures on Eglinton and Don Mills for inspections.
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...Crosstown TO
Extended construction hours from 4:30am to 11pm will continue on the Eglinton Crosstown LRT project. This may involve guideway construction, road widening, retaining walls, and bridge work. There will be daily lane closures and potential sidewalk closures along Eglinton Ave. Noise from construction can be expected. From December to June 2020, guideway work will occur on the West Don River bridge and road work will be on the south side of Eglinton Ave between Brentcliffe Rd and the east portal. A retaining wall east of Brentcliffe Rd will be constructed from May to August 2020.
Pharmacy to Kennedy Construction Liaison Committee Meeting - Nov 2019Crosstown TO
This document provides an update on construction progress and upcoming work for the Eglinton Crosstown LRT project between O'Connor Station and Ionview Station. It discusses completed works including left turn removals at various intersections. Current and upcoming traffic configurations are presented for areas around Victoria Park Avenue, Birchmount Road, Rosemount Drive, and Kennedy Station. Construction of guideway, stations, and track installation is underway and expected to continue through spring 2020 between Victoria Park and Birchmount. Traffic changes are scheduled for intersections at Rosemount Drive and Kennedy Road. Photos show current progress on stations, portals, track installation and other infrastructure works.
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)Crosstown TO
The document provides updates on construction activities for Section One and Section Two of the at-grade portion of the Eglinton Crosstown LRT project. For Section One from Brentcliffe Road to Sunnybrook Park Stop, work includes installing light poles and sidewalks, excavating for a retaining wall, and restoring areas around bridges. For Section Two from Aga Khan Park & Museum Stop to O'Connor Stop, work includes platform installation, guideway wall construction, and sidewalk/curb/driveway work between Bermondsey Rd and Victoria Park Ave. The Science Centre Station update outlines work like mechanical installation, deck removal, and tunnel/terminal construction.
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017Crosstown TO
1) The Crosstown LRT will be a 19-kilometre light rail line running east-west across Toronto, with 15 underground stations and 10 surface stops.
2) Construction involves distinct phases including preliminary works, utility relocations, tunnel excavation, station construction, track installation, and testing.
3) Recent progress includes completing tunnel construction, ongoing station construction activities, and beginning excavation of station boxes in 2017. Upcoming milestones are excavating 1 million tons of material and advancing utility relocations and guideway installation.
This document provides a summary of infrastructure investments and construction updates in the city of Ottawa for Fall 2016. It discusses the O-Train Confederation Line LRT construction, OC Transpo fall service changes, and various road construction and renewal projects. Traffic impacts are expected to be high around the downtown core due to LRT station construction and other projects. Tips are provided to help residents plan trips and commute during the busy construction season.
Pharmacy to Kennedy Construction Liaison Committee MeetingCrosstown TO
This document provides an update on construction progress and upcoming work for the Crosstown LRT project in the Pharmacy to Kennedy area. Key points include:
- Guideway, intersection, and station construction is ongoing between Pharmacy and Birchmount Avenues, with some intersection restrictions planned for June.
- Excavation and structural work continues at Kennedy Station, with portals and station box work through late 2019. GO Transit platform work is also ongoing.
- The sidewalk on the south side of Eglinton at Kennedy Station will remain closed until December 2020 to support excavation and utility work. Nearby intersection configurations will also change through 2020.
Metrolinx is a transportation agency that serves the Greater Toronto and Hamilton Area. It operates GO Transit, UP Express, and manages the PRESTO fare payment system. Metrolinx aims to connect communities through regional transit and published a Regional Transportation Plan in 2008 to quadruple rapid transit access. Upcoming works on Eglinton Crosstown LRT stations in 2019-2020 include excavation, concrete pours, traffic configuration changes, and underpinning the existing subway line at Eglinton station to allow construction of the underground interchange station.
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)Crosstown TO
The document provides updates on construction activities for Sections One and Two of the Eglinton Crosstown LRT project. For Section One between Brentcliffe Road and Victoria Park Avenue, work includes road widening, retaining wall construction, bridge rehabilitation, and multi-use path building. Section Two between Aga Khan Park and O'Connor sees road work, sidewalk construction, track laying, and shelter installation at O'Connor station. Construction is ongoing at Science Centre station with mechanical and electrical work as well as entrance building.
Central Eastern Works Open House - October 2019Crosstown TO
Contains current and upcoming stages of construction for the stations/stops of: Eglinton, Mount Pleasant, Leaside, Laird, Brentcliffe (Portal), Sunnybrook Park and Science Centre.
Western Works CLC - January 17, 2023.pdfCrosstown TO
The document provides updates on construction progress for the Eglinton Crosstown LRT project. It summarizes work completed in December 2022 and ongoing work at Caledonia Station, Keelesdale Station, and Mount Dennis Station. It also discusses track installation in the rail corridor, testing of light rail vehicles at the Eglinton Maintenance and Storage Facility, and lane reductions planned for heat trace installation works. Construction and testing activities are expected to continue through early 2023 and into 2023.
The document provides updates on construction activities for the Eglinton Crosstown LRT. Work is ongoing at Caledonia, Keelesdale, and Mount Dennis stations, and in the rail corridor, and will continue through spring 2023. This includes finishing works, system testing, and commissioning of trains. Lane reductions will occur between Weston Rd and Black Creek Dr in March for heat trace installation works. LRVs are being tested on the mainline in preparation for passenger service.
The document provides updates on construction progress for the Eglinton Crosstown LRT project, including at Leaside and Laird stations. At Leaside Station, architectural finishes, mechanical and electrical works are underway with station box and entrance construction expected to be complete in spring 2023. At Laird Station, similar finishing works are ongoing with the main and secondary entrances projected to be finished in early 2023. Utility works and asphalt restoration requiring periodic lane closures on Eglinton Avenue are also outlined.
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfCrosstown TO
The document provides updates on construction activities for the Eglinton Crosstown LRT project. It notes that work will continue through spring 2023 at Eglinton Station to finish architectural details, mechanical, electrical and testing. It also provides details on construction progress photos and updates for Mount Pleasant Station, including ongoing work on the station box and entrances through spring 2023. Traffic impacts are noted at both locations through late May 2023 for line painting and other works.
Chaplin-Avenue CLC - May 3 2023 Updated.pptxCrosstown TO
The document provides updates on construction progress for the Eglinton Crosstown LRT Chaplin Station and Avenue Station. For Chaplin Station, work is underway on the station entrances, station box, and Chaplin Parkette through Spring 2023. For Avenue Station, construction is ongoing on the station box, main and secondary entrances, and Eglinton Avenue streetscape through Summer 2023. Traffic configurations and lane closures are also outlined.
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCrosstown TO
The document provides updates on construction activities for the Eglinton Crosstown LRT project from Brentcliffe Road to O'Connor Drive. It notes that vehicle testing is ongoing from Brentcliffe to Kennedy, and that landscaping will continue through the summer. It also summarizes specific utility works, platform works, traffic restrictions and closures taking place between April and May 2023 at various locations along the route. Photos show examples of construction progress such as Presto machine installations and work at Aga Khan Park Station.
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxCrosstown TO
The document provides updates on construction activities for the Eglinton Crosstown LRT project from Pharmacy Station to Kennedy Station. It notes that vehicle testing and landscaping work will continue through spring 2023 between Brentcliffe and Kennedy stations. Between O'Connor and Ionview stops, traffic sign installation and line painting will take place through late spring. Sidewalk repairs are scheduled along Eglinton Ave East from mid-March 2023. Testing and commissioning activities are ongoing at Kennedy Station and will continue into early 2023. GO train platform service at Kennedy Station will shift east through 2023 with accessibility shuttle services provided.
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCrosstown TO
The document provides an update on construction activities for the Eglinton Crosstown LRT project from Pharmacy Station to Kennedy Station. It summarizes that testing and commissioning of light rail vehicles is ongoing between Brentcliffe Road and Kennedy Road through 2023. It also outlines ongoing construction and finishing work at multiple stations along the route including O'Connor, Pharmacy, Golden Mile, Birchmount, Ionview and Kennedy stations. Temporary traffic and pedestrian configurations are in place at 1995 Eglinton Avenue East and Kennedy Station during construction activities.
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCrosstown TO
The document provides updates on construction progress for different sections of the Eglinton Crosstown LRT project. Section One details work between Brentcliffe Portal to Sunnybrook Park Stop including vehicle testing, noise barrier removal, landscaping and utility works. Section Two details work from Aga Khan Park & Museum Stop to O'Connor Stop including vehicle testing, station finishes, and upcoming watermain restoration works. Science Centre Station work includes finishing activities and ongoing traffic configuration. Photos show ongoing signage, electrical and landscaping work throughout the alignment.
Chaplin-Avenue CLC - March 1, 2023.pptxCrosstown TO
The document provides updates on construction progress for the Chaplin Station and Avenue Station of the Eglinton Crosstown LRT. For Chaplin Station, work is underway on the station entrances, station box, and Chaplin Parkette through Spring 2023, with periodic lane closures on Chaplin Cres. For Avenue Station, construction is ongoing on the station box, entrances, and Eglinton Avenue streetscape/cycle track between Avenue Rd and Duplex Ave, with the traffic configuration shifting and lane reductions expected by March 2, 2023. Periodic lane and sidewalk closures as well as pedestrian rerouting will occur.
Leaside-Laird CLC - March 13, 2023.pdfCrosstown TO
The document provides updates on construction progress for the Eglinton Crosstown LRT project. It summarizes work happening at Leaside Station, including finishing the station box, main entrance, and secondary entrance through spring 2023. It also summarizes work at Laird Station, including main and secondary entrance construction through early 2023. Utility and road work is occurring through spring 2023 at both stations.
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCrosstown TO
The document provides updates on construction progress for different sections of the Eglinton Crosstown LRT project. Section One details work happening from Brentcliffe Portal to Sunnybrook Park Stop, including vehicle testing, noise barrier removal, landscaping, and overnight utility works. Section Two details work from Aga Khan Park & Museum Stop to O'Connor Stop, including vehicle testing, landscaping, station finishes, and upcoming watermain restoration works. Science Centre Station work includes finishing activities and ongoing traffic configuration. Photos show ongoing signage, electrical, and landscaping works.
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfCrosstown TO
The document provides updates on construction activities for the Eglinton Crosstown LRT project. It acknowledges that the project is taking place on Indigenous land and discusses the importance of reconciliation. It then details construction timelines and plans for the Eglinton and Mount Pleasant stations, including extended work hours, entrance construction, traffic shifts, and anticipated completion dates in spring 2023. Photos show progress on the station structures and entrances.
Chaplin-Avenue CLC - November 2 2022 compressed.pptxCrosstown TO
The document provides updates on construction progress at the Chaplin Station and Avenue Station sites of the Eglinton Crosstown LRT. At Chaplin Station, work is underway on the main, secondary, and tertiary entrances through December 2022, along with station box construction and road closures. At Avenue Station, station box construction and work on the main and secondary entrances is progressing through December 2022, along with Eglinton Avenue streetscape and cycle track construction between Eastbourne and Duplex Avenues. Construction photos depict ongoing work.
Chaplin-Avenue CLC - January 11 2023 (002).pptxCrosstown TO
The document provides updates on construction progress for the Chaplin Station and Avenue Station of the Eglinton Crosstown LRT. For Chaplin Station, construction of the main, secondary and tertiary entrances and Chaplin Parkette are underway through Spring 2023. Station box construction and intersection reinstatement at Chaplin Cres and Eglinton Ave are also progressing. For Avenue Station, station box construction, main and secondary entrance construction, and Eglinton Avenue streetscape work are underway through Spring 2023, with a traffic configuration change expected in early February 2023. Construction photos depict progress at station boxes, entrances and connections to local trails.
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCrosstown TO
This is a meeting invite for the Brentcliffe-Victoria Park CLC (Construction Liaison Committee) Monthly Meeting, covering the Brentcliffe Portal, Sunnybrook Park, Science Centre, Aga Khan, Wynford, Sloane and O’ Connor Stops.
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfCrosstown TO
The document provides updates on construction progress for the Eglinton Crosstown LRT project. It discusses ongoing work at Eglinton Station including extended hours for station box construction and main entrance construction. It also discusses ongoing work at Mount Pleasant Station including station box construction and main and secondary entrance construction. Traffic configuration changes at Mount Pleasant are also noted as completed. Construction progress photos of station box work are included.
Leaside-Laird CLC - January 9, 2023.pdfCrosstown TO
The document provides updates on construction progress at the Eglinton Crosstown LRT Leaside and Laird stations. At Leaside Station, work is underway on the station box, main entrance, secondary entrance, and utility and road works, with sidewalk restoration planned for January 9-11, 2023. At Laird Station, work continues on the main entrance, secondary entrance, and station box, with sidewalk restoration and monitoring well decommissioning requiring periodic lane reductions into early-mid 2023. Photos show ongoing construction and finishing works at both stations.
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCrosstown TO
Construction updates for the following locations/stops: Brentcliffe Portal, Sunnybrook Park, Science Centre, Aga Khan Park & Museum, Wynford, Sloane and O'Connor.
Causes Supporting Charity for Elderly PeopleSERUDS INDIA
Around 52% of the elder populations in India are living in poverty and poor health problems. In this technological world, they became very backward without having any knowledge about technology. So they’re dependent on working hard for their daily earnings, they’re physically very weak. Thus charity organizations are made to help and raise them and also to give them hope to live.
Donate Us:
https://serudsindia.org/supporting-charity-for-elderly-people-india/
#oldagehome, #donateforeldersinkurnool, #donateforelders, #donationforelders, #donateforoldpeople, #donationforoldpeople, #sponsorforelders, #sponsorforoldpeople, #donationforcharity, #charity, #seruds, #kurnool, #donateforoldagehome, #oldagehomedonation
The Power of Community Newsletters: A Case Study from Wolverton and Greenleys...Scribe
YOU WILL DISCOVER:
The engaging history and evolution of Wolverton and Greenleys Town Council's newsletter
Strategies for producing a successful community newsletter and generating income through advertising
The decision-making process behind moving newsletter design from in-house to outsourcing and its impacts
Dive into the success story of Wolverton and Greenleys Town Council's newsletter in this insightful webinar. Hear from Mandy Shipp and Jemma English about the newsletter's journey from its inception to becoming a vital part of their community's communication, including its history, production process, and revenue generation through advertising. Discover the reasons behind outsourcing its design and the benefits this brought. Ideal for anyone involved in community engagement or interested in starting their own newsletter.
Presentation by Rebecca Sachs and Joshua Varcie, analysts in CBO’s Health Analysis Division, at the 13th Annual Conference of the American Society of Health Economists.
Presentation by Julie Topoleski, CBO’s Director of Labor, Income Security, and Long-Term Analysis, at the 16th Annual Meeting of the OECD Working Party of Parliamentary Budget Officials and Independent Fiscal Institutions.
7. 7
Current Work – Credit Union Drive to Ionview Road
• Utilities work, road widening and road reconstruction in progress
• Guideway construction starting Victoria Park & Pharmacy.
• Rehabilitation at Celestica, Wynford, West Don and East Don River
bridges.
• Excavation and construction of green wall at E.T. Seton Park.
• Culvert re-construction Wilson Brook and Massey Creek.
7
8. 8
2019 Construction at Intersections
– Credit Union Drive to Ionview Road
Paving Guideway Construction
9. 9
- ASPHALT REMOVAL
- EXCAVATION
- OVERHEAD CATENARY SYSTEM
(OCS) FOUNDATION
- DUCT BANK
- SAND LAYER
- INSULATION LAYER
- BACKFILL
- BARRIER WALLS
- TRACK SLAB
- RAILWAY
- TRAFFIC SHIFTING
Excavation depth is 2 to 6 metres; width 8 metres.
How we build the guideway
8
10. 10
Intersection Paving
10
• CTS requires temporary changes at intersections from Credit Union to
Ionview for road paving:
– Eglinton is being widened and road must be paved before guideway
installed
– Traffic restrictions required for two weekends – one weekend for each
side of the intersection
– Credit Union/Swift & Bermondsey/Sloane require six weeks for each
side of the intersection
• Not full intersection closures.
– Eglinton remains open in both directions at all times
– Work will not take place at adjacent intersections
– Emergency services access maintained
11. 11
Intersection operations during construction
- Paving
Sloane/Bermondsey
(6 weeks per side)
Victoria Park to Ionview
(One weekend per side)
11
12. 12
Intersection Guideway Construction
12
• After paving temporary changes at intersections from Credit Union to
Ionview required for guideway construction:
– Work carried out in the middle of intersection
– No through north/south traffic for six weeks; traffic maintained on
Eglinton
– Signal timing will be set at the intersection and adjacent intersections
to keep traffic moving
• Restrictions are not full intersection closures.
– Eglinton remains open in both directions at all times
– Work will not take place at adjacent intersections
– North and south traffic can access Eglinton at all times via right turns
– Eglinton traffic can make right turns to access north and south streets
– Emergency services access maintained
18. 18
Communications & Engagement
18
• On-street activations & info booths leading up to works in high
traffic areas and with TTC
- Eglinton Square Mall, Smart Centre Plaza, Golden Mile Plaza, Eglinton
Town Centre, Don Montgomery Community Centre, residential lobbies,
• Distribution of construction notices and wayfinding postcards to
businesses and residents
• Open Houses – planned for early April
• Advertising – radio, print, digital, TTC locations
• Digital – social media, Metrolinx & TTC websites
• Advanced signage – informing road users of the status of the
intersections far upstream of Eglinton and leading up to
date of works
19. 19
416-782-8118 or 416-482-7411
24 hours/7days a week
www.thecrosstown.ca
crosstown@metrolinx.com
facebook.com/thecrosstown
twitter.com/crosstownTO
instagram.com/eglinton_crosstown
Crosstown West Office
1848 Eglinton Ave W (at Dufferin)
Crosstown East Office
660 Eglinton Ave E (at Bayview)
Stay in Touch