SlideShare a Scribd company logo
3100 words with case studies (US)
Partial Discharge (PD) techniques for measuring
the condition of ageing HV/MV switchgear
By Neil Davies, Director, EA Technology International
Throughout the world, the electricity transmission and distribution industry is experiencing major
issues: pressure from governments and customers to keep their systems operating reliably,
pressure from shareholders to reduce overhead costs and pressure to replace ageing
equipment.
Owners and operators of high voltage (HV) and medium voltage (MV) networks are facing ever
increasing challenges to maximize utilization of existing equipment and reduce operational costs,
whilst maintaining and improving system performance. Yet they all have the same problem: an
ageing infrastructure of equipment that has been installed and in operation for 20, 30 and in most
cases 40 years.
Switchgear in general has a proven record of reliability and failures are rare. However, when
switchgear fails, the consequences are often catastrophic. Damage to switchgear itself can be
extremely expensive. The consequences can involve damage to plant and buildings: and on rare
occasions death or serious injury to people.
Undetected degradation of switchgear may lead to sudden, explosive failures – sometimes with
catastrophic results
Switchgear maintenance is usually considered low priority by most companies, but a solid
maintenance program is much less costly than the impact of switchgear failure. Giving
maintenance the thought and effort it deserves improves safety, reliability and profitability: and
the latest non-invasive maintenance procedures are proven to prevent switchgear failure.
One of the most valuable new methods for monitoring the condition of HV and MV switchgear
involves the use of instruments to measure Partial Discharge (PD) activity non-intrusively.
Causes of Switchgear Failure
PD activity is a major cause of the long term degradation of insulation in HV and MV switchgear.
EA Technology’s experience of working with switchgear operators for more than 30 years
indicates that PD activity is a factor in around 85% of disruptive substation failures.
Issues of the mechanical operation of switching equipment are relatively easy to address, using
tests and maintenance procedures prescribed by the manufacturer. But standard maintenance
procedures are unlikely to detect the degradation of insulating components, which are associated
with the ageing process and are the most common cause of unexpected failures, especially if
triggered by environmental or electrical stresses.
The majority of the degradation processes affecting insulating components, such as bushings,
cable termination, current and voltage transformers, are associated with PD activity. This can be
defined as a localised electrical discharge in an insulation system that does not completely bridge
the electrodes. PD activity associated with the ageing and degradation of insulation typically
increases with the evolution of the defect. Therefore, the measurement of PD activity can be used
as a diagnostic tool, to assess equipment condition and to locate the defect source, enabling
selective intervention to rectify or remove the ageing component prior to complete failure.
What is Partial Discharge (PD) Measurement?
The basis of PD detection and monitoring is that the most common failure mode for electrical
assets is insulation breakdown, leading to flashover. These types of breakdowns produce the
most dramatic failures of switchgear and transformers, often leading to explosions and fires in the
event that protection systems fail to operate.
Insulation and insulation systems do not usually break down quickly. They are more likely to
suffer progressive deterioration over time, manifested in the form of increasing PD activity.
Fortunately for the owners and operators of electrical assets, it is now possible to measure and
quantify PD activity in live switchgear with unprecedented accuracy. This non-intrusive approach
to assessing the condition of switchgear insulation has been adopted by many countries
throughout the world.
Taking PD measurements using portable, lightweight and simple-to-use instruments is an ideal
method for evaluating HV electrical assets with a range of insulation types, including oil,
compound (bitumen) and cast resin. During a temporary over-voltage, during a high voltage test,
or under transient voltage conditions during operation, partial discharges may occur on insulation
of this type, which includes gas, liquid, and solid materials. If these partial discharges are
sustained due to poor materials, design, and/or foreign inclusions in the insulation, degradation
and possible failure of the insulation structure may occur.
In practice, PD activity in HV and MV insulation takes two forms: surface partial discharge and
internal partial discharge.
Surface Partial Discharge
When surface PD Activity is present, tracking occurs across the surface of the insulation, which is
exacerbated by airborne contamination and moisture. Often moisture combines with the NOx
gasses to produce nitric acid which attacks the surrounding metalwork and leads to severe
corrosion of the equipment. Insulation surfaces affected by such an acid attack produce an ideal
surface for tracking to occur, leading to the creepage distance of the insulator being
compromised. Tracking is the result of carbonization of the surface of insulation, brought on in the
early stages by the breakdown of contaminates.
Surface PD leads to erosion of the insulation as illustrated in Figure 1 and tracking phenomena
as illustrated on the CT (Current Transformer) in Figure 2.
Figure 1 – Damage caused by surface PD activity
Figure 2 – Treeing surface erosion on a current transformer
Surface discharges tend to occur between the particles of a contaminant, producing heat, light,
smoke, sound, electromagnetic radiation and ozone and nitrogen gasses. In the early stages of
this type of degradation process, and if an air path from the discharge site to the outside of the
equipment is present, the high frequency sound waves generated by the partial discharge activity
are readily detected using sensitive ultrasonic detection equipment in the 40kHz range.
Surface discharges are best detected using an ultrasonic detection instrument. However, there
must be an uninterrupted air path between the discharge site and the instrument to allow the
sound pressure waves to be detected externally.
Internal Partial Discharge
Internal partial discharge occurs within the bulk of insulation materials and is most commonly
caused by age, poor materials or poor quality manufacturing processes. The current transformer
illustrated in figure 3 was known to be exhibiting internal partial discharge. When it was removed
and sectioned, the damage was seen to be at the top and is illustrated in the figure on the right.
Figure 3 – Internal partial discharge
Within all insulation material, however manufactured, microscopic voids or cracks are present.
When in use, the insulation has one end connected to high voltage and the other to ground,
causing these voids and cracks to charge up and discharge with the 60Hz cycle, like small
capacitors. Eventually, because the breakdown strength of air is less than that of the surrounding
insulation, the air breaks down with a (very small) arc and a partial discharge occurs. These arcs
produce heat, light, smoke, sound and electromagnetic radiation: but as the void is buried within
the insulation material, only the electromagnetic radiation is detectable externally.
This discharge action also erodes the voids, making them bigger: and as they get bigger, the
discharge energy dissipated with each discharge increases in magnitude. During this process,
carbonisation of the inner surface of the void occurs, which progressively builds up to make the
void conductive and increases the electrical stress on the next void. This causes the process to
be repeated throughout the insulation system, leading to enough conductive voids in the
insulation to cause it to fail. This occurs even under normal working voltages and particularly
following transient over-voltages caused, for example, by switching operations.
The electromagnetic pulses produced by internal partial discharges are conducted away in every
direction by the surrounding metalwork. This charge in motion gives rise to an electric current
which, when it impinges on the impedance of the metal casing, leads to a very high frequency
voltage pulse. These high frequency voltage pulses (between 0.1mV and a few volts) escape
through joints in the metalwork and pass from the inner to the outer surface of the equipment and
then down to ground. The voltage pulse will stay on the surface of the steelwork, as their high
frequency leads to a skin effect.
These pulses were first observed at EA Technology in 1974 by Dr John Reeves and were termed
Transient Earth Voltages (TEVs). They were given this description because they only last for a
very short time and are travelling down to earth (ground). It was found after extensive trials that
these TEV signals are directly proportional to the magnitude of any active partial discharge
activity and the condition of the insulation for switchgear of the same type and model, measured
at the same point. This produced a very powerful comparative field based technique for non-
invasively checking the condition of switches of the same type and manufacture, whilst the
equipment is live and in service.
When new switchgear is tested for partial discharge under factory conditions, very expensive
bench top test equipment is used and the reading is expressed in pico-coulombs (pC): a value
obtained by direct measurement with the switchgear out of service. Once the switchgear or other
equipment has been installed and in service for some time, pico-coulomb readings from direct
measurements become relatively meaningless, as the individual service history (fault operations,
maintenance history) of each item of HV/MV equipment will lead to variations in their individual
insulation systems. Furthermore, whilst partial discharge measurements on new switchgear are a
very reliable indication of the build quality as it leaves the factory, it is older switchgear that is at
more risk from failure due to partial discharge.
If allowed to continue unchecked, either mechanism (surface or internal partial discharge) will
lead to failure of the insulation system under normal working stress, resulting in catastrophic
failure of the equipment.
Interpretation of TEV Measurements
The pulses that are being measured on the outside of the equipment are represented in the
Lissojous Figures contained in Annex A of IEEE std 1291 – 1993, an example of which is shown
in Figure 4:
Figure 4 - Lissajous Figure of Internal Discharge in a Solid Dielectric Cavity
ref IEEE std 1291 – 1993
It can be seen from that for each type of activity, the pulses shown have two distinct features: the
size (or magnitude) of the individual pulse and the number of pulses per cycle. In all instances,
the underlying feature is that as the partial discharge activity increases over time, the magnitude
and number of pulses per cycle increases. The method of interpreting the TEV readings relies on
being able to combine two aspects in the manner shown in Figure 5.
Figure 5 – Analysis of Transient Earth Voltages (TEV’s)
As shown, a low number and low magnitude of pulses means that there is little risk of insulation
failure. Either a low number of high magnitude pulses or a high number of low magnitude pulses
means that the risk of insulation failure is increasing and more regular testing should be
undertaken. Finally, a high number of high magnitude pulses means that the risk of failure may be
unacceptable and intervention is required at the earliest opportunity.
EA Technology began making partial discharge measurements of switchgear using TEV
detection instruments in 1983. Since that time, EA Technology has assembled, with the co-
operation of all the UK power utilities, a database of partial discharge survey results, with over
100,000 entries, covering many different manufacturers and types of high-voltage switchgear and
associated equipment.
When a survey is undertaken, the TEV readings (in dBmV) are compared with the database
results. If the level of partial discharge is within the top 5% of the database values for comparative
equipment (of the same voltage level, insulation type and design), then it is deemed to be in the
‘red’ quadrant of Figure 5. If the readings are in the top 25% of the database values, then the
equipment is deemed to be in the ‘amber’ quadrant. Below this level, the equipment is deemed to
be in the ‘green’ quadrant.
PD Measuring Instruments
PD testing has been used to check the condition of insulation systems in MV/HV assets for many
years, so it is a well proven technology in its own right. However, it is only quite since the early
2000s that more lightweight, portable and effective monitoring tools have been developed and its
full potential as a strategic technique for asset maintenance and management has been realised
fully.
The latest developments in PD measuring instruments are based on building dual sensors into
single instruments: ultrasonic sensors principally to measure surface PD activity, plus TEV
sensors to measure internal activity. This has led to the launch of a whole family of new
instruments, each of which has a specific role in the detection, location, measurement and
monitoring over time of PD activity.
Amplitude of pulses (in dBmV)
Number
of pulses
per cycle
Low High
Low risk of
failure
Unacceptable
risk of failure
Some risk of
failure
Some risk of
failure
Low
High
Perhaps the most historically significant of the new PD tools is EA Technology’s UltraTEV
Detector™: the world’s first dual sensor handheld PD detection tool, which in 2007 won the
Queen’s Award for Industry: Innovation – one of Britain’s top industrial awards. It is now standard
issue for substation use with every electricity network operator in the UK and has been widely
adopted by operators worldwide.
The UltraTEV Detector™ has been compared to a Apple iPod because of its ease of use,
minimum training required and the user friendly interface, beneath which lies a great deal of
technological development. A single button turns it on and a simple traffic light system shows the
operator instantly if PD activity is at one of three levels: green indicates OK, amber indicates that
the asset require further investigation, and red shows that it requires immediate intervention
and/or that PD activity is at a dangerous level.
The latest handheld instruments measure PD activity as both ultrasonic and TEV emissions
Whilst the basic Detector is invaluable for taking ‘first pass’ PD readings quickly, it has spawned a
range of even more sophisticated dual sensor instruments of increasing versatility. The UltraTEV
Plus+™ (pictured above) for example, presents ultrasonic emissions as numerical decibel values
and audible signals, which engineers can listen to via headphones, with the option of a directional
dish microphone for measuring PD activity in overhead assets. Measurement of internal PD
activity in the form of TEV signals is presented as numerical values: and a continuous PD
measurement mode incorporates maximum level, pulse count per cycle and severity level.
Dual sensor alarm systems continuously monitor assets for critical PD activity
Dual sensors are also built into the UltraTEV Alarm™ system (pictured), which provides
permanent or semi-permanent monitoring for PD activity in multiple assets or whole substations.
When PD activity reaches critical levels, the system automatically generates alerts via SMS or
email.
The UltraTEV Locator™ features twin probes to locate the source of PD activity accurately, using
time of flight measurement of pulses, as well as quantifying the level of PD activity in single probe
mode. The UltraTEV Monitor™ uses multiple probes, networked to a central server, to monitor
PD activity over time in hundreds of assets simultaneously, and includes software which
automatically analyses and interprets activity in the form of condition reports. This has also been
joined by the PD Monitor GIS™, a system specifically designed to monitor the condition of
extreme high voltage gas insulated switchgear by measuring internal partial discharges in the
UHF range.
CONCLUSION
At its most basic level, the ability to detect and measure PD activity in live assets is an extremely
valuable technique for spotting faults in the early stages of their development, before they
become failures and outages. It is also a uniquely effective way of ensuring the safety of
personnel, to the extent that it is now standard practice for many engineers to check for PD
activity every time before they will enter a substation.
However, it is rapidly becoming apparent that the greatest commercial value of PD measurement
is the ability to use accurate data on the condition of assets to change fundamentally the way
they are managed. Instead of basing asset maintenance and replacement on time schedules,
assets can be managed more efficiently on the basis of their actual condition. The results of this
change include less needless invasive maintenance, less downtime, potentially longer asset life,
greater safety and lower operating costs. The availability of data on the condition of each asset
also leads to more intelligence-based (and cost effective) decisions on asset replacement and
refurbishment.
As the experience of SP Powergrid in Singapore shows, the bottom line is that condition
measurement pays rich dividends.
More information from Neil Davies:
t. +44 151 347 2308
e. neil.davies@eatechnology.com
w. www.eatechnology.com
CASE STUDY 1: SP Powergrid, Singapore
SP Powergrid’s network includes nearly 10,000 substations, 40,000 switchgear sets, 14,000
transformers and 30,000km of cable. Since incorporating condition monitoring into its systems, it
has dramatically improved an already excellent performance. The System Average Interruption
Duration Index (SAIDI) has averaged less than 1 minute pa over a recent three year period.
NB: The blip in 2004/5 was caused by a third party supply issue outside SP Powergrid’s control.
SP Powergrid estimates that over the last eight financial years, condition monitoring has enabled
it to avert 450 network failure incidents, with a net financial saving of US$29 million. In addition to
improving customer service, it has been able to pass cost savings on to them.
CASE STUDY 2: ESB Networks (Dublin Ireland)
In 2002, a post-fault forensic investigation revealed that insulation failure was the root cause of a
catastrophic failure of switchgear that occurred shortly after a switching operation. The failure was
on a cast-resin ring main unit (RMU) that had been installed on ESB Networks’ (Dublin, Ireland)
10kV distribution network for more than 20 years. This failure resulted in the need for the utility to
revisit the process and procedures it had developed to manage the ageing switchgear population.
As a result of the failure, ESB placed an immediate operational restriction on all 250 substations
equipped with the same type of switchgear. The restriction required that this type of switch only
be operated after it had been de-energized by switching further up the line. The restriction
resulted in severe disruption to customers’ supplies and led ESB to experience major difficulties
in managing network operations.
Following field trails, ESB has solved this problem by issuing all operational switching and
inspection staff with handheld partial discharge measuring instruments, to check that PD activity
is at a non-critical level prior to switching.
CSE STUDY 3: ABB (Italy)
ABB (Italy) conducted similar trials to assess the capability of commercial non-intrusive PD
measuring equipment to detect and locate different PD sources induced in a 17.5 kV
metalclad/internal arc switchgear assembly, comparing the performance with a conventional
electrical detection system.
ABB concluded that commercial equipment, based on TEV and ultrasonic methods, clearly
demonstrated the capability to identify the presence of PD sources. The UltraTEV Detector™
device by EA Technology was identified as the most versatile in terms of ease to use and clear
indications of PD levels.

More Related Content

What's hot

Partial discharge switchgear ea tech
Partial discharge switchgear ea techPartial discharge switchgear ea tech
Partial discharge switchgear ea tech
Mauritz Roni Gabe Manurung
 
Substation grounding
Substation groundingSubstation grounding
Substation grounding
Syed Ubaid
 
IEEE-Alberta_Partial-Discharge.pdf
IEEE-Alberta_Partial-Discharge.pdfIEEE-Alberta_Partial-Discharge.pdf
IEEE-Alberta_Partial-Discharge.pdf
NitinPandya14
 
Guidelines for Unconventional Partial Discharge Measurement (CIGRE 444)
Guidelines for Unconventional Partial Discharge Measurement (CIGRE 444)Guidelines for Unconventional Partial Discharge Measurement (CIGRE 444)
Guidelines for Unconventional Partial Discharge Measurement (CIGRE 444)
AHMED MOHAMED HEGAB
 
Grounding,Earthing,Bonding
Grounding,Earthing,BondingGrounding,Earthing,Bonding
Grounding,Earthing,Bonding
Ko Winnwe
 
Lightning and Surge Protection Strategy for Instrumentation
Lightning and Surge Protection Strategy for InstrumentationLightning and Surge Protection Strategy for Instrumentation
Lightning and Surge Protection Strategy for Instrumentation
RekaNext Capital
 
Practical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineersPractical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineers
SARAVANAN A
 
Week 11
Week 11Week 11
High voltage underground cables
High voltage underground cablesHigh voltage underground cables
Transformers protection, an introduction
Transformers protection, an introductionTransformers protection, an introduction
Transformers protection, an introduction
H. Kheir
 
Cable sizing to withstand short circuit current
Cable sizing to withstand short circuit currentCable sizing to withstand short circuit current
Cable sizing to withstand short circuit current
Leonardo ENERGY
 
Simple Disconnector Switch (DS) Testing for Switchyard Equipment
Simple Disconnector Switch (DS) Testing for Switchyard EquipmentSimple Disconnector Switch (DS) Testing for Switchyard Equipment
Simple Disconnector Switch (DS) Testing for Switchyard Equipment
SARAVANAN A
 
Cable fault location methods (Megger)
Cable fault location methods (Megger)Cable fault location methods (Megger)
Cable fault location methods (Megger)
AHMED MOHAMED HEGAB
 
Testing of Transformer (AREVA)
Testing of Transformer (AREVA)Testing of Transformer (AREVA)
Testing of Transformer (AREVA)
AHMED MOHAMED HEGAB
 
Electrical safety
Electrical safetyElectrical safety
Electrical safety
Anu71
 
UNDERGROUND CABLES PRESENTATION
UNDERGROUND CABLES  PRESENTATIONUNDERGROUND CABLES  PRESENTATION
UNDERGROUND CABLES PRESENTATION
PANKAJ KUMAR
 
Types of cables
Types of cablesTypes of cables
Types of cables
Kaushal Patel
 
Transformer vector group_test_conditions
Transformer vector group_test_conditionsTransformer vector group_test_conditions
Transformer vector group_test_conditions
SARAVANAN A
 
Distribution Transformer testing, West Bengal, India
Distribution Transformer testing,  West Bengal, IndiaDistribution Transformer testing,  West Bengal, India
Distribution Transformer testing, West Bengal, India
RajuMondal18
 

What's hot (20)

Partial discharge switchgear ea tech
Partial discharge switchgear ea techPartial discharge switchgear ea tech
Partial discharge switchgear ea tech
 
Substation grounding
Substation groundingSubstation grounding
Substation grounding
 
IEEE-Alberta_Partial-Discharge.pdf
IEEE-Alberta_Partial-Discharge.pdfIEEE-Alberta_Partial-Discharge.pdf
IEEE-Alberta_Partial-Discharge.pdf
 
Guidelines for Unconventional Partial Discharge Measurement (CIGRE 444)
Guidelines for Unconventional Partial Discharge Measurement (CIGRE 444)Guidelines for Unconventional Partial Discharge Measurement (CIGRE 444)
Guidelines for Unconventional Partial Discharge Measurement (CIGRE 444)
 
Grounding,Earthing,Bonding
Grounding,Earthing,BondingGrounding,Earthing,Bonding
Grounding,Earthing,Bonding
 
Lightning and Surge Protection Strategy for Instrumentation
Lightning and Surge Protection Strategy for InstrumentationLightning and Surge Protection Strategy for Instrumentation
Lightning and Surge Protection Strategy for Instrumentation
 
Practical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineersPractical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineers
 
Week 11
Week 11Week 11
Week 11
 
High voltage underground cables
High voltage underground cablesHigh voltage underground cables
High voltage underground cables
 
Transformers protection, an introduction
Transformers protection, an introductionTransformers protection, an introduction
Transformers protection, an introduction
 
Cable sizing to withstand short circuit current
Cable sizing to withstand short circuit currentCable sizing to withstand short circuit current
Cable sizing to withstand short circuit current
 
Simple Disconnector Switch (DS) Testing for Switchyard Equipment
Simple Disconnector Switch (DS) Testing for Switchyard EquipmentSimple Disconnector Switch (DS) Testing for Switchyard Equipment
Simple Disconnector Switch (DS) Testing for Switchyard Equipment
 
Testing
TestingTesting
Testing
 
Cable fault location methods (Megger)
Cable fault location methods (Megger)Cable fault location methods (Megger)
Cable fault location methods (Megger)
 
Testing of Transformer (AREVA)
Testing of Transformer (AREVA)Testing of Transformer (AREVA)
Testing of Transformer (AREVA)
 
Electrical safety
Electrical safetyElectrical safety
Electrical safety
 
UNDERGROUND CABLES PRESENTATION
UNDERGROUND CABLES  PRESENTATIONUNDERGROUND CABLES  PRESENTATION
UNDERGROUND CABLES PRESENTATION
 
Types of cables
Types of cablesTypes of cables
Types of cables
 
Transformer vector group_test_conditions
Transformer vector group_test_conditionsTransformer vector group_test_conditions
Transformer vector group_test_conditions
 
Distribution Transformer testing, West Bengal, India
Distribution Transformer testing,  West Bengal, IndiaDistribution Transformer testing,  West Bengal, India
Distribution Transformer testing, West Bengal, India
 

Viewers also liked

Assuring Reliability of Critical Power Cable Systems
Assuring Reliability of Critical Power Cable SystemsAssuring Reliability of Critical Power Cable Systems
Assuring Reliability of Critical Power Cable Systems
michaeljmack
 
3M Cold Shrink QT-III Silicone Rubber Outdoor Cable Terminations 7600S - Inst...
3M Cold Shrink QT-III Silicone Rubber Outdoor Cable Terminations 7600S - Inst...3M Cold Shrink QT-III Silicone Rubber Outdoor Cable Terminations 7600S - Inst...
3M Cold Shrink QT-III Silicone Rubber Outdoor Cable Terminations 7600S - Inst...
Thorne & Derrick International
 
Comparison of coupling capacitors and the inverter filter in partial discharg...
Comparison of coupling capacitors and the inverter filter in partial discharg...Comparison of coupling capacitors and the inverter filter in partial discharg...
Comparison of coupling capacitors and the inverter filter in partial discharg...
IOSR Journals
 
Electrical Generators & Excitation Systems, Partial Discharge, Diagnostic Tes...
Electrical Generators & Excitation Systems, Partial Discharge, Diagnostic Tes...Electrical Generators & Excitation Systems, Partial Discharge, Diagnostic Tes...
Electrical Generators & Excitation Systems, Partial Discharge, Diagnostic Tes...
PowerEDGE
 
Basic Partial Discharge
Basic Partial DischargeBasic Partial Discharge
Basic Partial Discharge
Mauritz Roni Gabe Manurung
 
Factors considered for High Voltage Cable Joint design
Factors considered for High Voltage Cable Joint design Factors considered for High Voltage Cable Joint design
Factors considered for High Voltage Cable Joint design Shahab Khan
 
Descarga Parcial de Cables - Conferencia Virtual
Descarga Parcial de Cables - Conferencia VirtualDescarga Parcial de Cables - Conferencia Virtual
Descarga Parcial de Cables - Conferencia Virtual
TRANSEQUIPOS S.A.
 

Viewers also liked (7)

Assuring Reliability of Critical Power Cable Systems
Assuring Reliability of Critical Power Cable SystemsAssuring Reliability of Critical Power Cable Systems
Assuring Reliability of Critical Power Cable Systems
 
3M Cold Shrink QT-III Silicone Rubber Outdoor Cable Terminations 7600S - Inst...
3M Cold Shrink QT-III Silicone Rubber Outdoor Cable Terminations 7600S - Inst...3M Cold Shrink QT-III Silicone Rubber Outdoor Cable Terminations 7600S - Inst...
3M Cold Shrink QT-III Silicone Rubber Outdoor Cable Terminations 7600S - Inst...
 
Comparison of coupling capacitors and the inverter filter in partial discharg...
Comparison of coupling capacitors and the inverter filter in partial discharg...Comparison of coupling capacitors and the inverter filter in partial discharg...
Comparison of coupling capacitors and the inverter filter in partial discharg...
 
Electrical Generators & Excitation Systems, Partial Discharge, Diagnostic Tes...
Electrical Generators & Excitation Systems, Partial Discharge, Diagnostic Tes...Electrical Generators & Excitation Systems, Partial Discharge, Diagnostic Tes...
Electrical Generators & Excitation Systems, Partial Discharge, Diagnostic Tes...
 
Basic Partial Discharge
Basic Partial DischargeBasic Partial Discharge
Basic Partial Discharge
 
Factors considered for High Voltage Cable Joint design
Factors considered for High Voltage Cable Joint design Factors considered for High Voltage Cable Joint design
Factors considered for High Voltage Cable Joint design
 
Descarga Parcial de Cables - Conferencia Virtual
Descarga Parcial de Cables - Conferencia VirtualDescarga Parcial de Cables - Conferencia Virtual
Descarga Parcial de Cables - Conferencia Virtual
 

Similar to Partial Discharge Techniques For Measuring Condition Of MV & HV Switchgear

03 partial discharge theory cutler-hammer
03 partial discharge theory cutler-hammer03 partial discharge theory cutler-hammer
03 partial discharge theory cutler-hammer
prasadkappala
 
Arc Flash Hazards In The Workplace
Arc Flash Hazards In The WorkplaceArc Flash Hazards In The Workplace
Arc Flash Hazards In The Workplace
gdifrank
 
The benefits of pd monitoring Ben Jones
The benefits of pd monitoring Ben JonesThe benefits of pd monitoring Ben Jones
The benefits of pd monitoring Ben Jones
NSW Environment and Planning
 
IRJET - A Review of an Investigation of Partial Discharge Sources and Loc...
IRJET -  	  A Review of an Investigation of Partial Discharge Sources and Loc...IRJET -  	  A Review of an Investigation of Partial Discharge Sources and Loc...
IRJET - A Review of an Investigation of Partial Discharge Sources and Loc...
IRJET Journal
 
High voltage switchgear charged detection
High voltage switchgear charged detectionHigh voltage switchgear charged detection
High voltage switchgear charged detection
katherine feng
 
Electrostatic precipitator EPS Maintenance
Electrostatic precipitator EPS MaintenanceElectrostatic precipitator EPS Maintenance
Electrostatic precipitator EPS MaintenanceFebrianto Utomo
 
Chakresh Tiwari Philips report
Chakresh Tiwari Philips reportChakresh Tiwari Philips report
Chakresh Tiwari Philips report
pranav kapoor
 
Protection Devices and the Lightning
Protection Devices and the LightningProtection Devices and the Lightning
Protection Devices and the Lightning
Ameen San
 
Safety & environmental usage of equipment
Safety & environmental usage of equipmentSafety & environmental usage of equipment
Safety & environmental usage of equipmentDaniel Afuwai
 
Multi – Grounding in the Distribution System.pptx
Multi – Grounding in the Distribution System.pptxMulti – Grounding in the Distribution System.pptx
Multi – Grounding in the Distribution System.pptx
MarlonAgustin3
 
Inspection of Electrical Installations in Homes
Inspection of Electrical Installations in HomesInspection of Electrical Installations in Homes
Inspection of Electrical Installations in Homes
Leonardo ENERGY
 
transformer dignostics on high voltage
transformer dignostics on high voltagetransformer dignostics on high voltage
transformer dignostics on high voltage
Kamal Deep
 
Circuit interruption
Circuit interruptionCircuit interruption
Circuit interruption
jawaharramaya
 
Report earthing grounding pv with shielded, armoured dc cabling (worldwide)
Report earthing grounding pv with shielded, armoured dc cabling (worldwide)Report earthing grounding pv with shielded, armoured dc cabling (worldwide)
Report earthing grounding pv with shielded, armoured dc cabling (worldwide)
Andreas ILIOU - Elektro- Solar
 
Insulation and Dielectric Breakdown Design Paper SM54
Insulation and Dielectric Breakdown Design Paper SM54Insulation and Dielectric Breakdown Design Paper SM54
Insulation and Dielectric Breakdown Design Paper SM54
Subhash Mahla
 
ELECTROSURGERY VSR.pptx
ELECTROSURGERY VSR.pptxELECTROSURGERY VSR.pptx
ELECTROSURGERY VSR.pptx
DrKanteshkumarMJ
 
What is leakage current testing
What is leakage current testingWhat is leakage current testing
What is leakage current testing
Power System Operation
 

Similar to Partial Discharge Techniques For Measuring Condition Of MV & HV Switchgear (20)

03 partial discharge theory cutler-hammer
03 partial discharge theory cutler-hammer03 partial discharge theory cutler-hammer
03 partial discharge theory cutler-hammer
 
Arc Flash Hazards In The Workplace
Arc Flash Hazards In The WorkplaceArc Flash Hazards In The Workplace
Arc Flash Hazards In The Workplace
 
The benefits of pd monitoring Ben Jones
The benefits of pd monitoring Ben JonesThe benefits of pd monitoring Ben Jones
The benefits of pd monitoring Ben Jones
 
IRJET - A Review of an Investigation of Partial Discharge Sources and Loc...
IRJET -  	  A Review of an Investigation of Partial Discharge Sources and Loc...IRJET -  	  A Review of an Investigation of Partial Discharge Sources and Loc...
IRJET - A Review of an Investigation of Partial Discharge Sources and Loc...
 
PD_Presentation_1.pdf
PD_Presentation_1.pdfPD_Presentation_1.pdf
PD_Presentation_1.pdf
 
High voltage switchgear charged detection
High voltage switchgear charged detectionHigh voltage switchgear charged detection
High voltage switchgear charged detection
 
Electrostatic precipitator EPS Maintenance
Electrostatic precipitator EPS MaintenanceElectrostatic precipitator EPS Maintenance
Electrostatic precipitator EPS Maintenance
 
Chakresh Tiwari Philips report
Chakresh Tiwari Philips reportChakresh Tiwari Philips report
Chakresh Tiwari Philips report
 
Protection Devices and the Lightning
Protection Devices and the LightningProtection Devices and the Lightning
Protection Devices and the Lightning
 
Safety & environmental usage of equipment
Safety & environmental usage of equipmentSafety & environmental usage of equipment
Safety & environmental usage of equipment
 
Multi – Grounding in the Distribution System.pptx
Multi – Grounding in the Distribution System.pptxMulti – Grounding in the Distribution System.pptx
Multi – Grounding in the Distribution System.pptx
 
Inspection of Electrical Installations in Homes
Inspection of Electrical Installations in HomesInspection of Electrical Installations in Homes
Inspection of Electrical Installations in Homes
 
transformer dignostics on high voltage
transformer dignostics on high voltagetransformer dignostics on high voltage
transformer dignostics on high voltage
 
Circuit interruption
Circuit interruptionCircuit interruption
Circuit interruption
 
Report earthing grounding pv with shielded, armoured dc cabling (worldwide)
Report earthing grounding pv with shielded, armoured dc cabling (worldwide)Report earthing grounding pv with shielded, armoured dc cabling (worldwide)
Report earthing grounding pv with shielded, armoured dc cabling (worldwide)
 
Insulation and Dielectric Breakdown Design Paper SM54
Insulation and Dielectric Breakdown Design Paper SM54Insulation and Dielectric Breakdown Design Paper SM54
Insulation and Dielectric Breakdown Design Paper SM54
 
Megger-insulationtester
Megger-insulationtesterMegger-insulationtester
Megger-insulationtester
 
ELECTROSURGERY VSR.pptx
ELECTROSURGERY VSR.pptxELECTROSURGERY VSR.pptx
ELECTROSURGERY VSR.pptx
 
What is leakage current testing
What is leakage current testingWhat is leakage current testing
What is leakage current testing
 
Amin
AminAmin
Amin
 

More from Thorne & Derrick International

Isolation procedures for safe working on electrical systems and equipment by ...
Isolation procedures for safe working on electrical systems and equipment by ...Isolation procedures for safe working on electrical systems and equipment by ...
Isolation procedures for safe working on electrical systems and equipment by ...
Thorne & Derrick International
 
THORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical Eqpt
THORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical EqptTHORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical Eqpt
THORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical Eqpt
Thorne & Derrick International
 
The Children North East Annual Golf Day Wednesday 9th May 2018
The Children North East Annual Golf Day Wednesday 9th May 2018The Children North East Annual Golf Day Wednesday 9th May 2018
The Children North East Annual Golf Day Wednesday 9th May 2018
Thorne & Derrick International
 
3M Electrical Products Stocked By Thorne & Derrick International
3M Electrical Products Stocked By Thorne & Derrick International3M Electrical Products Stocked By Thorne & Derrick International
3M Electrical Products Stocked By Thorne & Derrick International
Thorne & Derrick International
 
CATU Electrical Safety Catalogue
CATU Electrical Safety CatalogueCATU Electrical Safety Catalogue
CATU Electrical Safety Catalogue
Thorne & Derrick International
 
11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A
11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A
11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A
Thorne & Derrick International
 
THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...
THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...
THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...
Thorne & Derrick International
 
Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...
Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...
Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...
Thorne & Derrick International
 
Roxtec Cable Transit - B Frame Dimensional Drawing
Roxtec Cable Transit - B Frame Dimensional DrawingRoxtec Cable Transit - B Frame Dimensional Drawing
Roxtec Cable Transit - B Frame Dimensional Drawing
Thorne & Derrick International
 
Pepperl & Fuchs SIL Training Certificate - T&D Adam Rowe
Pepperl & Fuchs SIL Training Certificate - T&D Adam RowePepperl & Fuchs SIL Training Certificate - T&D Adam Rowe
Pepperl & Fuchs SIL Training Certificate - T&D Adam Rowe
Thorne & Derrick International
 
T&D Experts In Equipment For Explosive Atmospheres
T&D Experts In Equipment For Explosive AtmospheresT&D Experts In Equipment For Explosive Atmospheres
T&D Experts In Equipment For Explosive Atmospheres
Thorne & Derrick International
 
Ultrasonic Flow Meters - Customer Specification Demand
Ultrasonic Flow Meters - Customer Specification DemandUltrasonic Flow Meters - Customer Specification Demand
Ultrasonic Flow Meters - Customer Specification Demand
Thorne & Derrick International
 
Emtelle Fibre Optic Cables - Product Catalogue 2016
Emtelle Fibre Optic Cables - Product Catalogue 2016Emtelle Fibre Optic Cables - Product Catalogue 2016
Emtelle Fibre Optic Cables - Product Catalogue 2016
Thorne & Derrick International
 
Thorne & Derrick Process Heating Brochure 2016
Thorne & Derrick Process Heating Brochure 2016Thorne & Derrick Process Heating Brochure 2016
Thorne & Derrick Process Heating Brochure 2016
Thorne & Derrick International
 
SIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282D
SIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282DSIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282D
SIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282D
Thorne & Derrick International
 
Ripley Utility Tool Cable Preparation Tools
Ripley Utility Tool Cable Preparation ToolsRipley Utility Tool Cable Preparation Tools
Ripley Utility Tool Cable Preparation Tools
Thorne & Derrick International
 
RIDGID micro CD100 Combustible Gas Detector
RIDGID micro CD100 Combustible Gas DetectorRIDGID micro CD100 Combustible Gas Detector
RIDGID micro CD100 Combustible Gas Detector
Thorne & Derrick International
 
Itron Fact Sheet
Itron Fact SheetItron Fact Sheet
United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...
United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...
United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...
Thorne & Derrick International
 
Filoform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec Sheet
Filoform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec SheetFiloform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec Sheet
Filoform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec Sheet
Thorne & Derrick International
 

More from Thorne & Derrick International (20)

Isolation procedures for safe working on electrical systems and equipment by ...
Isolation procedures for safe working on electrical systems and equipment by ...Isolation procedures for safe working on electrical systems and equipment by ...
Isolation procedures for safe working on electrical systems and equipment by ...
 
THORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical Eqpt
THORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical EqptTHORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical Eqpt
THORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical Eqpt
 
The Children North East Annual Golf Day Wednesday 9th May 2018
The Children North East Annual Golf Day Wednesday 9th May 2018The Children North East Annual Golf Day Wednesday 9th May 2018
The Children North East Annual Golf Day Wednesday 9th May 2018
 
3M Electrical Products Stocked By Thorne & Derrick International
3M Electrical Products Stocked By Thorne & Derrick International3M Electrical Products Stocked By Thorne & Derrick International
3M Electrical Products Stocked By Thorne & Derrick International
 
CATU Electrical Safety Catalogue
CATU Electrical Safety CatalogueCATU Electrical Safety Catalogue
CATU Electrical Safety Catalogue
 
11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A
11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A
11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A
 
THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...
THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...
THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...
 
Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...
Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...
Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...
 
Roxtec Cable Transit - B Frame Dimensional Drawing
Roxtec Cable Transit - B Frame Dimensional DrawingRoxtec Cable Transit - B Frame Dimensional Drawing
Roxtec Cable Transit - B Frame Dimensional Drawing
 
Pepperl & Fuchs SIL Training Certificate - T&D Adam Rowe
Pepperl & Fuchs SIL Training Certificate - T&D Adam RowePepperl & Fuchs SIL Training Certificate - T&D Adam Rowe
Pepperl & Fuchs SIL Training Certificate - T&D Adam Rowe
 
T&D Experts In Equipment For Explosive Atmospheres
T&D Experts In Equipment For Explosive AtmospheresT&D Experts In Equipment For Explosive Atmospheres
T&D Experts In Equipment For Explosive Atmospheres
 
Ultrasonic Flow Meters - Customer Specification Demand
Ultrasonic Flow Meters - Customer Specification DemandUltrasonic Flow Meters - Customer Specification Demand
Ultrasonic Flow Meters - Customer Specification Demand
 
Emtelle Fibre Optic Cables - Product Catalogue 2016
Emtelle Fibre Optic Cables - Product Catalogue 2016Emtelle Fibre Optic Cables - Product Catalogue 2016
Emtelle Fibre Optic Cables - Product Catalogue 2016
 
Thorne & Derrick Process Heating Brochure 2016
Thorne & Derrick Process Heating Brochure 2016Thorne & Derrick Process Heating Brochure 2016
Thorne & Derrick Process Heating Brochure 2016
 
SIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282D
SIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282DSIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282D
SIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282D
 
Ripley Utility Tool Cable Preparation Tools
Ripley Utility Tool Cable Preparation ToolsRipley Utility Tool Cable Preparation Tools
Ripley Utility Tool Cable Preparation Tools
 
RIDGID micro CD100 Combustible Gas Detector
RIDGID micro CD100 Combustible Gas DetectorRIDGID micro CD100 Combustible Gas Detector
RIDGID micro CD100 Combustible Gas Detector
 
Itron Fact Sheet
Itron Fact SheetItron Fact Sheet
Itron Fact Sheet
 
United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...
United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...
United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...
 
Filoform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec Sheet
Filoform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec SheetFiloform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec Sheet
Filoform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec Sheet
 

Recently uploaded

GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
Sri Ambati
 
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdfFIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance
 
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Ramesh Iyer
 
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdfFIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance
 
Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...
Product School
 
Epistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI supportEpistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI support
Alan Dix
 
Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !
KatiaHIMEUR1
 
How world-class product teams are winning in the AI era by CEO and Founder, P...
How world-class product teams are winning in the AI era by CEO and Founder, P...How world-class product teams are winning in the AI era by CEO and Founder, P...
How world-class product teams are winning in the AI era by CEO and Founder, P...
Product School
 
Generating a custom Ruby SDK for your web service or Rails API using Smithy
Generating a custom Ruby SDK for your web service or Rails API using SmithyGenerating a custom Ruby SDK for your web service or Rails API using Smithy
Generating a custom Ruby SDK for your web service or Rails API using Smithy
g2nightmarescribd
 
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Jeffrey Haguewood
 
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
BookNet Canada
 
PCI PIN Basics Webinar from the Controlcase Team
PCI PIN Basics Webinar from the Controlcase TeamPCI PIN Basics Webinar from the Controlcase Team
PCI PIN Basics Webinar from the Controlcase Team
ControlCase
 
Neuro-symbolic is not enough, we need neuro-*semantic*
Neuro-symbolic is not enough, we need neuro-*semantic*Neuro-symbolic is not enough, we need neuro-*semantic*
Neuro-symbolic is not enough, we need neuro-*semantic*
Frank van Harmelen
 
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdfSmart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
91mobiles
 
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdfFIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance
 
Knowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and backKnowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and back
Elena Simperl
 
The Future of Platform Engineering
The Future of Platform EngineeringThe Future of Platform Engineering
The Future of Platform Engineering
Jemma Hussein Allen
 
Bits & Pixels using AI for Good.........
Bits & Pixels using AI for Good.........Bits & Pixels using AI for Good.........
Bits & Pixels using AI for Good.........
Alison B. Lowndes
 
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdfFIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance
 
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Albert Hoitingh
 

Recently uploaded (20)

GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
 
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdfFIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdf
 
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
 
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdfFIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
 
Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...
 
Epistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI supportEpistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI support
 
Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !
 
How world-class product teams are winning in the AI era by CEO and Founder, P...
How world-class product teams are winning in the AI era by CEO and Founder, P...How world-class product teams are winning in the AI era by CEO and Founder, P...
How world-class product teams are winning in the AI era by CEO and Founder, P...
 
Generating a custom Ruby SDK for your web service or Rails API using Smithy
Generating a custom Ruby SDK for your web service or Rails API using SmithyGenerating a custom Ruby SDK for your web service or Rails API using Smithy
Generating a custom Ruby SDK for your web service or Rails API using Smithy
 
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
 
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
 
PCI PIN Basics Webinar from the Controlcase Team
PCI PIN Basics Webinar from the Controlcase TeamPCI PIN Basics Webinar from the Controlcase Team
PCI PIN Basics Webinar from the Controlcase Team
 
Neuro-symbolic is not enough, we need neuro-*semantic*
Neuro-symbolic is not enough, we need neuro-*semantic*Neuro-symbolic is not enough, we need neuro-*semantic*
Neuro-symbolic is not enough, we need neuro-*semantic*
 
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdfSmart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
 
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdfFIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
 
Knowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and backKnowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and back
 
The Future of Platform Engineering
The Future of Platform EngineeringThe Future of Platform Engineering
The Future of Platform Engineering
 
Bits & Pixels using AI for Good.........
Bits & Pixels using AI for Good.........Bits & Pixels using AI for Good.........
Bits & Pixels using AI for Good.........
 
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdfFIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
 
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
 

Partial Discharge Techniques For Measuring Condition Of MV & HV Switchgear

  • 1. 3100 words with case studies (US) Partial Discharge (PD) techniques for measuring the condition of ageing HV/MV switchgear By Neil Davies, Director, EA Technology International Throughout the world, the electricity transmission and distribution industry is experiencing major issues: pressure from governments and customers to keep their systems operating reliably, pressure from shareholders to reduce overhead costs and pressure to replace ageing equipment. Owners and operators of high voltage (HV) and medium voltage (MV) networks are facing ever increasing challenges to maximize utilization of existing equipment and reduce operational costs, whilst maintaining and improving system performance. Yet they all have the same problem: an ageing infrastructure of equipment that has been installed and in operation for 20, 30 and in most cases 40 years. Switchgear in general has a proven record of reliability and failures are rare. However, when switchgear fails, the consequences are often catastrophic. Damage to switchgear itself can be extremely expensive. The consequences can involve damage to plant and buildings: and on rare occasions death or serious injury to people. Undetected degradation of switchgear may lead to sudden, explosive failures – sometimes with catastrophic results Switchgear maintenance is usually considered low priority by most companies, but a solid maintenance program is much less costly than the impact of switchgear failure. Giving maintenance the thought and effort it deserves improves safety, reliability and profitability: and the latest non-invasive maintenance procedures are proven to prevent switchgear failure.
  • 2. One of the most valuable new methods for monitoring the condition of HV and MV switchgear involves the use of instruments to measure Partial Discharge (PD) activity non-intrusively. Causes of Switchgear Failure PD activity is a major cause of the long term degradation of insulation in HV and MV switchgear. EA Technology’s experience of working with switchgear operators for more than 30 years indicates that PD activity is a factor in around 85% of disruptive substation failures. Issues of the mechanical operation of switching equipment are relatively easy to address, using tests and maintenance procedures prescribed by the manufacturer. But standard maintenance procedures are unlikely to detect the degradation of insulating components, which are associated with the ageing process and are the most common cause of unexpected failures, especially if triggered by environmental or electrical stresses. The majority of the degradation processes affecting insulating components, such as bushings, cable termination, current and voltage transformers, are associated with PD activity. This can be defined as a localised electrical discharge in an insulation system that does not completely bridge the electrodes. PD activity associated with the ageing and degradation of insulation typically increases with the evolution of the defect. Therefore, the measurement of PD activity can be used as a diagnostic tool, to assess equipment condition and to locate the defect source, enabling selective intervention to rectify or remove the ageing component prior to complete failure. What is Partial Discharge (PD) Measurement? The basis of PD detection and monitoring is that the most common failure mode for electrical assets is insulation breakdown, leading to flashover. These types of breakdowns produce the most dramatic failures of switchgear and transformers, often leading to explosions and fires in the event that protection systems fail to operate. Insulation and insulation systems do not usually break down quickly. They are more likely to suffer progressive deterioration over time, manifested in the form of increasing PD activity. Fortunately for the owners and operators of electrical assets, it is now possible to measure and quantify PD activity in live switchgear with unprecedented accuracy. This non-intrusive approach to assessing the condition of switchgear insulation has been adopted by many countries throughout the world. Taking PD measurements using portable, lightweight and simple-to-use instruments is an ideal method for evaluating HV electrical assets with a range of insulation types, including oil, compound (bitumen) and cast resin. During a temporary over-voltage, during a high voltage test, or under transient voltage conditions during operation, partial discharges may occur on insulation of this type, which includes gas, liquid, and solid materials. If these partial discharges are sustained due to poor materials, design, and/or foreign inclusions in the insulation, degradation and possible failure of the insulation structure may occur. In practice, PD activity in HV and MV insulation takes two forms: surface partial discharge and internal partial discharge. Surface Partial Discharge When surface PD Activity is present, tracking occurs across the surface of the insulation, which is exacerbated by airborne contamination and moisture. Often moisture combines with the NOx gasses to produce nitric acid which attacks the surrounding metalwork and leads to severe corrosion of the equipment. Insulation surfaces affected by such an acid attack produce an ideal surface for tracking to occur, leading to the creepage distance of the insulator being
  • 3. compromised. Tracking is the result of carbonization of the surface of insulation, brought on in the early stages by the breakdown of contaminates. Surface PD leads to erosion of the insulation as illustrated in Figure 1 and tracking phenomena as illustrated on the CT (Current Transformer) in Figure 2. Figure 1 – Damage caused by surface PD activity Figure 2 – Treeing surface erosion on a current transformer Surface discharges tend to occur between the particles of a contaminant, producing heat, light, smoke, sound, electromagnetic radiation and ozone and nitrogen gasses. In the early stages of this type of degradation process, and if an air path from the discharge site to the outside of the equipment is present, the high frequency sound waves generated by the partial discharge activity are readily detected using sensitive ultrasonic detection equipment in the 40kHz range. Surface discharges are best detected using an ultrasonic detection instrument. However, there must be an uninterrupted air path between the discharge site and the instrument to allow the sound pressure waves to be detected externally. Internal Partial Discharge Internal partial discharge occurs within the bulk of insulation materials and is most commonly caused by age, poor materials or poor quality manufacturing processes. The current transformer illustrated in figure 3 was known to be exhibiting internal partial discharge. When it was removed and sectioned, the damage was seen to be at the top and is illustrated in the figure on the right.
  • 4. Figure 3 – Internal partial discharge Within all insulation material, however manufactured, microscopic voids or cracks are present. When in use, the insulation has one end connected to high voltage and the other to ground, causing these voids and cracks to charge up and discharge with the 60Hz cycle, like small capacitors. Eventually, because the breakdown strength of air is less than that of the surrounding insulation, the air breaks down with a (very small) arc and a partial discharge occurs. These arcs produce heat, light, smoke, sound and electromagnetic radiation: but as the void is buried within the insulation material, only the electromagnetic radiation is detectable externally. This discharge action also erodes the voids, making them bigger: and as they get bigger, the discharge energy dissipated with each discharge increases in magnitude. During this process, carbonisation of the inner surface of the void occurs, which progressively builds up to make the void conductive and increases the electrical stress on the next void. This causes the process to be repeated throughout the insulation system, leading to enough conductive voids in the insulation to cause it to fail. This occurs even under normal working voltages and particularly following transient over-voltages caused, for example, by switching operations. The electromagnetic pulses produced by internal partial discharges are conducted away in every direction by the surrounding metalwork. This charge in motion gives rise to an electric current which, when it impinges on the impedance of the metal casing, leads to a very high frequency voltage pulse. These high frequency voltage pulses (between 0.1mV and a few volts) escape through joints in the metalwork and pass from the inner to the outer surface of the equipment and then down to ground. The voltage pulse will stay on the surface of the steelwork, as their high frequency leads to a skin effect. These pulses were first observed at EA Technology in 1974 by Dr John Reeves and were termed Transient Earth Voltages (TEVs). They were given this description because they only last for a very short time and are travelling down to earth (ground). It was found after extensive trials that these TEV signals are directly proportional to the magnitude of any active partial discharge activity and the condition of the insulation for switchgear of the same type and model, measured at the same point. This produced a very powerful comparative field based technique for non- invasively checking the condition of switches of the same type and manufacture, whilst the equipment is live and in service. When new switchgear is tested for partial discharge under factory conditions, very expensive bench top test equipment is used and the reading is expressed in pico-coulombs (pC): a value
  • 5. obtained by direct measurement with the switchgear out of service. Once the switchgear or other equipment has been installed and in service for some time, pico-coulomb readings from direct measurements become relatively meaningless, as the individual service history (fault operations, maintenance history) of each item of HV/MV equipment will lead to variations in their individual insulation systems. Furthermore, whilst partial discharge measurements on new switchgear are a very reliable indication of the build quality as it leaves the factory, it is older switchgear that is at more risk from failure due to partial discharge. If allowed to continue unchecked, either mechanism (surface or internal partial discharge) will lead to failure of the insulation system under normal working stress, resulting in catastrophic failure of the equipment. Interpretation of TEV Measurements The pulses that are being measured on the outside of the equipment are represented in the Lissojous Figures contained in Annex A of IEEE std 1291 – 1993, an example of which is shown in Figure 4: Figure 4 - Lissajous Figure of Internal Discharge in a Solid Dielectric Cavity ref IEEE std 1291 – 1993 It can be seen from that for each type of activity, the pulses shown have two distinct features: the size (or magnitude) of the individual pulse and the number of pulses per cycle. In all instances, the underlying feature is that as the partial discharge activity increases over time, the magnitude and number of pulses per cycle increases. The method of interpreting the TEV readings relies on being able to combine two aspects in the manner shown in Figure 5.
  • 6. Figure 5 – Analysis of Transient Earth Voltages (TEV’s) As shown, a low number and low magnitude of pulses means that there is little risk of insulation failure. Either a low number of high magnitude pulses or a high number of low magnitude pulses means that the risk of insulation failure is increasing and more regular testing should be undertaken. Finally, a high number of high magnitude pulses means that the risk of failure may be unacceptable and intervention is required at the earliest opportunity. EA Technology began making partial discharge measurements of switchgear using TEV detection instruments in 1983. Since that time, EA Technology has assembled, with the co- operation of all the UK power utilities, a database of partial discharge survey results, with over 100,000 entries, covering many different manufacturers and types of high-voltage switchgear and associated equipment. When a survey is undertaken, the TEV readings (in dBmV) are compared with the database results. If the level of partial discharge is within the top 5% of the database values for comparative equipment (of the same voltage level, insulation type and design), then it is deemed to be in the ‘red’ quadrant of Figure 5. If the readings are in the top 25% of the database values, then the equipment is deemed to be in the ‘amber’ quadrant. Below this level, the equipment is deemed to be in the ‘green’ quadrant. PD Measuring Instruments PD testing has been used to check the condition of insulation systems in MV/HV assets for many years, so it is a well proven technology in its own right. However, it is only quite since the early 2000s that more lightweight, portable and effective monitoring tools have been developed and its full potential as a strategic technique for asset maintenance and management has been realised fully. The latest developments in PD measuring instruments are based on building dual sensors into single instruments: ultrasonic sensors principally to measure surface PD activity, plus TEV sensors to measure internal activity. This has led to the launch of a whole family of new instruments, each of which has a specific role in the detection, location, measurement and monitoring over time of PD activity. Amplitude of pulses (in dBmV) Number of pulses per cycle Low High Low risk of failure Unacceptable risk of failure Some risk of failure Some risk of failure Low High
  • 7. Perhaps the most historically significant of the new PD tools is EA Technology’s UltraTEV Detector™: the world’s first dual sensor handheld PD detection tool, which in 2007 won the Queen’s Award for Industry: Innovation – one of Britain’s top industrial awards. It is now standard issue for substation use with every electricity network operator in the UK and has been widely adopted by operators worldwide. The UltraTEV Detector™ has been compared to a Apple iPod because of its ease of use, minimum training required and the user friendly interface, beneath which lies a great deal of technological development. A single button turns it on and a simple traffic light system shows the operator instantly if PD activity is at one of three levels: green indicates OK, amber indicates that the asset require further investigation, and red shows that it requires immediate intervention and/or that PD activity is at a dangerous level. The latest handheld instruments measure PD activity as both ultrasonic and TEV emissions Whilst the basic Detector is invaluable for taking ‘first pass’ PD readings quickly, it has spawned a range of even more sophisticated dual sensor instruments of increasing versatility. The UltraTEV Plus+™ (pictured above) for example, presents ultrasonic emissions as numerical decibel values and audible signals, which engineers can listen to via headphones, with the option of a directional dish microphone for measuring PD activity in overhead assets. Measurement of internal PD activity in the form of TEV signals is presented as numerical values: and a continuous PD measurement mode incorporates maximum level, pulse count per cycle and severity level. Dual sensor alarm systems continuously monitor assets for critical PD activity
  • 8. Dual sensors are also built into the UltraTEV Alarm™ system (pictured), which provides permanent or semi-permanent monitoring for PD activity in multiple assets or whole substations. When PD activity reaches critical levels, the system automatically generates alerts via SMS or email. The UltraTEV Locator™ features twin probes to locate the source of PD activity accurately, using time of flight measurement of pulses, as well as quantifying the level of PD activity in single probe mode. The UltraTEV Monitor™ uses multiple probes, networked to a central server, to monitor PD activity over time in hundreds of assets simultaneously, and includes software which automatically analyses and interprets activity in the form of condition reports. This has also been joined by the PD Monitor GIS™, a system specifically designed to monitor the condition of extreme high voltage gas insulated switchgear by measuring internal partial discharges in the UHF range. CONCLUSION At its most basic level, the ability to detect and measure PD activity in live assets is an extremely valuable technique for spotting faults in the early stages of their development, before they become failures and outages. It is also a uniquely effective way of ensuring the safety of personnel, to the extent that it is now standard practice for many engineers to check for PD activity every time before they will enter a substation. However, it is rapidly becoming apparent that the greatest commercial value of PD measurement is the ability to use accurate data on the condition of assets to change fundamentally the way they are managed. Instead of basing asset maintenance and replacement on time schedules, assets can be managed more efficiently on the basis of their actual condition. The results of this change include less needless invasive maintenance, less downtime, potentially longer asset life, greater safety and lower operating costs. The availability of data on the condition of each asset also leads to more intelligence-based (and cost effective) decisions on asset replacement and refurbishment. As the experience of SP Powergrid in Singapore shows, the bottom line is that condition measurement pays rich dividends. More information from Neil Davies: t. +44 151 347 2308 e. neil.davies@eatechnology.com w. www.eatechnology.com
  • 9. CASE STUDY 1: SP Powergrid, Singapore SP Powergrid’s network includes nearly 10,000 substations, 40,000 switchgear sets, 14,000 transformers and 30,000km of cable. Since incorporating condition monitoring into its systems, it has dramatically improved an already excellent performance. The System Average Interruption Duration Index (SAIDI) has averaged less than 1 minute pa over a recent three year period. NB: The blip in 2004/5 was caused by a third party supply issue outside SP Powergrid’s control. SP Powergrid estimates that over the last eight financial years, condition monitoring has enabled it to avert 450 network failure incidents, with a net financial saving of US$29 million. In addition to improving customer service, it has been able to pass cost savings on to them.
  • 10. CASE STUDY 2: ESB Networks (Dublin Ireland) In 2002, a post-fault forensic investigation revealed that insulation failure was the root cause of a catastrophic failure of switchgear that occurred shortly after a switching operation. The failure was on a cast-resin ring main unit (RMU) that had been installed on ESB Networks’ (Dublin, Ireland) 10kV distribution network for more than 20 years. This failure resulted in the need for the utility to revisit the process and procedures it had developed to manage the ageing switchgear population. As a result of the failure, ESB placed an immediate operational restriction on all 250 substations equipped with the same type of switchgear. The restriction required that this type of switch only be operated after it had been de-energized by switching further up the line. The restriction resulted in severe disruption to customers’ supplies and led ESB to experience major difficulties in managing network operations. Following field trails, ESB has solved this problem by issuing all operational switching and inspection staff with handheld partial discharge measuring instruments, to check that PD activity is at a non-critical level prior to switching. CSE STUDY 3: ABB (Italy) ABB (Italy) conducted similar trials to assess the capability of commercial non-intrusive PD measuring equipment to detect and locate different PD sources induced in a 17.5 kV metalclad/internal arc switchgear assembly, comparing the performance with a conventional electrical detection system. ABB concluded that commercial equipment, based on TEV and ultrasonic methods, clearly demonstrated the capability to identify the presence of PD sources. The UltraTEV Detector™ device by EA Technology was identified as the most versatile in terms of ease to use and clear indications of PD levels.