NTPC Anta is a 419.33 MW combined cycle natural gas power plant located in Anta, Rajasthan. It was the first combined cycle power project set up by NTPC and consists of 3 gas turbine units of 88.71 MW each and 1 steam turbine unit of 153.2 MW. Natural gas is supplied via a pipeline while backup fuel is naphtha delivered by tankers. The plant supplies power to several northern Indian states including Uttar Pradesh, Jammu and Kashmir, Himachal Pradesh, and Rajasthan.
NTPC Anta is a 419.33 MW combined cycle power plant located in Anta, Rajasthan. It was the first combined cycle plant set up by NTPC and consists of 3 gas turbines totaling 267.13 MW and 1 steam turbine of 153.2 MW. The plant receives natural gas via pipeline and uses naphtha as a backup fuel. Water is sourced from the Kota Right Main Canal. NTPC Anta was commissioned between 1989-1990 and helps supply electricity to several northern Indian states.
complete overview of power sector in india with the total share in generation and introduction to ntpc ltd including the detailed description of ntpc dadri power plant mainly gas power plant and its auxillary are explained in detail
Nishant Pareek completed a summer training at the ANTA Gas Power Station owned by NTPC Ltd. The presentation summarized the power station's components and operations. The station has 3 gas turbines each rated at 88.71 MW that drive generators. Exhaust from the gas turbines is used to generate steam in a waste heat recovery boiler which powers a 153.2 MW steam turbine. Key components and maintenance practices for the gas turbines, boiler, and steam turbine were described. The power generated is allocated to various states in northern India.
The document provides information about Anil Jadon's industrial training at the NTPC power plant in Faridabad. It discusses the company NTPC, describes the Faridabad plant and its 432 MW capacity powered by natural gas. It explains the basic working of the power plant, from burning natural gas in the gas turbine to generating electricity. It also discusses the electrical systems, distribution of electricity, control and instrumentation, advantages of natural gas, and precautions taken at the plant. The training helped clear Anil's concepts and understand how electricity is generated at the large scale, efficient Faridabad plant.
CONTROL AND INSTRUMENTATION OF POWER PLANTSubarna Poddar
The document provides details about an industrial training report submitted by Subarna Poddar at NTPC Dadri power plant. It includes an overview of NTPC Dadri which operates both coal and gas based power plants with a total installed capacity of 2,159 MW. The report covers various aspects of the power generation process including the coal handling plant, main plant, steam cycles, boiler and turbine operations, instrumentation and control mechanisms. It provides figures and diagrams to explain the different units and processes at the thermal power station.
Ntpc unchahar summer or vocational training pptaryan5808
NTPC Unchahar power plant has a total installed capacity of 1050MW from its coal-based thermal units. It sources coal from nearby mines and water from the Sharda Sahayak canal. The presentation summarized the key processes and components of a thermal power plant including coal handling, boiler, turbine, generator, condenser, cooling tower, and ash handling. The main departments of the plant work together to convert the heat energy from coal combustion into electrical energy through these processes.
Final reprt at ntpc vindhyanagar , singrauliDevanshu Yadav
This document provides an overview of the author's vocational training project report on thermal power plants conducted at the National Thermal Power Corporation plant in Vindhyanchal, Madhya Pradesh, India. It includes declarations, certificates, acknowledgements, contents, and 12 chapters discussing topics like the basic power plant cycle, boiler maintenance, turbine systems, efficiency improvements, and environmental management. The report aims to document the author's 45-day training experience at the NTPC plant to fulfill their industrial training program requirements.
NTPC Anta is a 419.33 MW combined cycle power plant located in Anta, Rajasthan. It was the first combined cycle plant set up by NTPC and consists of 3 gas turbines totaling 267.13 MW and 1 steam turbine of 153.2 MW. The plant receives natural gas via pipeline and uses naphtha as a backup fuel. Water is sourced from the Kota Right Main Canal. NTPC Anta was commissioned between 1989-1990 and helps supply electricity to several northern Indian states.
complete overview of power sector in india with the total share in generation and introduction to ntpc ltd including the detailed description of ntpc dadri power plant mainly gas power plant and its auxillary are explained in detail
Nishant Pareek completed a summer training at the ANTA Gas Power Station owned by NTPC Ltd. The presentation summarized the power station's components and operations. The station has 3 gas turbines each rated at 88.71 MW that drive generators. Exhaust from the gas turbines is used to generate steam in a waste heat recovery boiler which powers a 153.2 MW steam turbine. Key components and maintenance practices for the gas turbines, boiler, and steam turbine were described. The power generated is allocated to various states in northern India.
The document provides information about Anil Jadon's industrial training at the NTPC power plant in Faridabad. It discusses the company NTPC, describes the Faridabad plant and its 432 MW capacity powered by natural gas. It explains the basic working of the power plant, from burning natural gas in the gas turbine to generating electricity. It also discusses the electrical systems, distribution of electricity, control and instrumentation, advantages of natural gas, and precautions taken at the plant. The training helped clear Anil's concepts and understand how electricity is generated at the large scale, efficient Faridabad plant.
CONTROL AND INSTRUMENTATION OF POWER PLANTSubarna Poddar
The document provides details about an industrial training report submitted by Subarna Poddar at NTPC Dadri power plant. It includes an overview of NTPC Dadri which operates both coal and gas based power plants with a total installed capacity of 2,159 MW. The report covers various aspects of the power generation process including the coal handling plant, main plant, steam cycles, boiler and turbine operations, instrumentation and control mechanisms. It provides figures and diagrams to explain the different units and processes at the thermal power station.
Ntpc unchahar summer or vocational training pptaryan5808
NTPC Unchahar power plant has a total installed capacity of 1050MW from its coal-based thermal units. It sources coal from nearby mines and water from the Sharda Sahayak canal. The presentation summarized the key processes and components of a thermal power plant including coal handling, boiler, turbine, generator, condenser, cooling tower, and ash handling. The main departments of the plant work together to convert the heat energy from coal combustion into electrical energy through these processes.
Final reprt at ntpc vindhyanagar , singrauliDevanshu Yadav
This document provides an overview of the author's vocational training project report on thermal power plants conducted at the National Thermal Power Corporation plant in Vindhyanchal, Madhya Pradesh, India. It includes declarations, certificates, acknowledgements, contents, and 12 chapters discussing topics like the basic power plant cycle, boiler maintenance, turbine systems, efficiency improvements, and environmental management. The report aims to document the author's 45-day training experience at the NTPC plant to fulfill their industrial training program requirements.
This document provides an overview of the National Thermal Power Plant in Kahalgaon, Bihar, India. It discusses that NTPC Kahalgaon has an installed capacity of 2340 MW and is fueled by coal sourced from nearby mines. The document outlines the key areas and systems within the plant including the coal handling plant, boiler and its auxiliaries, turbine auxiliaries, generator and switchyard. It also provides background on NTPC as the largest power company in India and describes the general layout of a thermal power plant's four main circuits for coal/ash, air/gas, feedwater/steam, and cooling water.
The document is an internship report submitted by Aditya Aryan about his four-week internship at the National Thermal Power Corporation (NTPC) power plant in Chennai, India. It provides an overview of NTPC, describes the key components and operations of a thermal power plant including the boiler, turbine, generator and cooling towers. It also includes figures and diagrams to illustrate the power plant layout and components. The report aims to document Aditya's experience and learnings during his internship at the NTPC power plant.
The document provides details about a presentation on summer training at NTPC Tanda power plant. It discusses that NTPC is the largest power company in India. It then summarizes information about NTPC Tanda power plant including its capacity, sources, main departments like coal handling plant, boiler, turbine, and generator. It also mentions advantages like low cost of fuel and disadvantages like atmospheric pollution of thermal power plants.
NTPC was established in 1975 by the Government of India to address growing power demand. It is now the largest power generating company in India with over 30 GW of installed capacity from coal, gas, hydro, and renewable sources. NTPC started with thermal power plants and has expanded into various power generation technologies and business areas. The document provides details on NTPC's thermal power plants across India, including their locations and installed capacities.
This document provides an overview of NTPC Limited, the largest power generating company in India. It discusses NTPC's history, operations, and growth strategy. Some key points:
- NTPC was established in 1975 and has emerged as a national power company with facilities across India. Its current installed capacity is over 27,000 MW.
- The company aims to become a 75,000 MW company by 2017 through diversifying its fuel mix to include more hydro, nuclear, renewable and gas-based power generation alongside coal.
- NTPC operates various coal-fired, gas/liquid-fired and joint venture power plants located across major regions in India. It also provides power consultancy and other services.
India has significant untapped small hydro power (SHP) potential. The estimated SHP potential is 19,749 MW, but only 3632 MW has been developed so far. SHP provides environmental and economic benefits. The Ministry of New and Renewable Energy promotes SHP development through private sector participation to utilize India's SHP resources and meet renewable energy targets.
training report on thermal power plant & thermal power generation by sagar me...Sagar Mehta
This document provides a practical training report submitted by Sagar Mehta to Rajasthan Technical University in partial fulfillment of the requirements for a Bachelor of Technology degree. The report details Mehta's summer training at the Nashik Thermal Power Station in Maharashtra, India. It includes sections on the history of the power sector and thermal power generation in India, an overview of the Nashik Thermal Power Station, descriptions of the various systems and processes within a thermal power plant including the steam power plant, coal handling plant, water treatment plant, boilers, turbines, generators, condensers and ash handling plant. The report concludes with discussions on energy conservation, auditing, and suggestions.
This document provides a summary of a seminar on summer vocational training at NTPC thermal power plants. It discusses the key components of a thermal power plant including coal handling, pulverizing, boilers, turbines, generators, condensers, and ash handling. It also describes various equipment like ball mills used in pulverizing coal and control and instrumentation labs that monitor critical parameters. Finally, it lists some major thermal power plants in Rajasthan and references used in preparing the seminar.
Project Report on Industrial Summer Training at NTPC SimhadriAshish Uppu
The following pdf is a Project Report about my Industrial Training at NTPC Limited Simhadri, Visakhapatnam, Andhra Pradesh, India. It includes all the fundamentals of a Thermal Power Plant: its layout, various departments, principal components etc. It also contains a brief profile about the company.
The document provides an overview of thermal power generation. It discusses the need for thermal power, the basic working principles, and classifications by fuel and prime mover. The key steps in the thermal power generation process include heating water to create steam, using the steam to power a turbine connected to a generator to produce electricity, and then condensing the steam to be reused. Thermal power plants have advantages of using widely available fuels but have lower efficiency and higher emissions than other generation methods. Improving plant efficiency and reducing emissions are important areas of ongoing research and development.
National Thermal Power Corporation Ltd. (NTPC) was incorporated in 1975 and began operations in 1976. It has grown to become one of the largest power producers in India, with an installed capacity of over 45,000 MW as of 2015. NTPC operates mainly coal and gas-fired power plants, with some hydro and renewable energy projects as well. It aims to increase power generation capacity to over 128,000 MW by 2032 through both organic and inorganic growth. NTPC makes a significant contribution to meeting India's increasing electricity demand in a sustainable and efficient manner.
training report NTPC Muzaffarpur Bihar Dilip kumar
This document provides an industrial training report on the generation system of the National Thermal Power Corporation Ltd. (NTPC). It discusses the key components of a thermal power plant that use the modified Rankine cycle to convert the chemical energy of coal into electrical energy. These include the boiler, turbine, condenser, and other auxiliary components. The report also provides an overview of the processes involved in coal handling, steam generation, power generation using steam turbines, and electricity distribution at NTPC power plants. It aims to provide an understanding of the technical aspects and management of thermal power generation.
The document provides information about the author's 4 week training at NTPC from June to July 2016. They visited the Boiler Maintenance Department and Turbine Maintenance Department to learn how electricity is produced. NTPC is India's largest power company, generating over 45,000 MW of electricity using steam turbines powered by coal. The company was founded in 1975 and uses the Rankine cycle to convert heat from coal into mechanical power and then electrical power.
Internship report of NTPC kawas ,summer internship report of ntpcLalitGoyal27
National Thermal Power Plant Kawas Project report,summer internship report of ntpc ,internship report, national thermal power plant kawas project report, summer internship report of ntpc,ntpc summer training report,ntpc training repntpc training reportort
Vishal Kumar completed a summer training program at NTPC Barh power plant in Bihar. He thanks the NTPC authorities for allowing him to complete his training and gain valuable experience observing the various mechanical and electrical operations across different parts of the power plant. The document provides an overview of NTPC as India's largest power generation company, including its vision, operations, environmental policies and practices, and details about the NTPC Barh power plant where Vishal completed his training.
This training report summarizes Pratik Gupta's vocational training at the SIPAT Super Thermal Power Project. It provides details on the production of electricity at a thermal power plant. Coal is ground and blown into boilers where it burns, heating water in tubes to produce high pressure steam. The steam powers turbines connected to generators, producing electricity. The steam is then condensed back into water in condensers to be reused in the cycle. The report outlines the key components and processes involved in electricity generation at a coal-fired thermal power station.
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...haxxo24
This document is a summer training project report submitted by Dinesh Kumar, a mechanical engineering student, on his vocational training at the National Thermal Power Corporation Sipat power plant in Chhattisgarh, India. The report provides an overview of NTPC Sipat, including its location, installed capacity, use of supercritical technology, and environmental management practices. It also describes the basic Rankine cycle used in thermal power plants, the major sub-systems of a power plant such as the coal handling plant, mills, water treatment plant and boiler, and includes diagrams of a typical power plant layout and the interior of a bowl mill.
This industrial training report summarizes Deepak Kr Singh's one month internship at the Singrauli Super Thermal Power Plant in Shaktinagar, India. The report includes details of the power plant such as its seven units with a total capacity of 2,000 MW. It also covers various topics related to thermal power generation including the workings of boilers, turbines, generators, and switchgear. Deepak conducted his training under the supervision of his training incharge Mr. CH Satynarayan, during which he gained knowledge and experience in the electrical engineering aspects of thermal power generation.
The document discusses India's power generation capacity addition targets and plans over multiple 5-year plans from the 10th plan to the current 12th plan. It notes that the 12th plan aims to add over 88,000 MW of capacity across various sectors like thermal, hydro, and nuclear power. It also states that coal requirements to meet this generation target will be around 842 million tonnes. Biomass energy is highlighted as an organic matter that can be used to produce heat, electricity, or transportation fuels.
vocational training presentation on korba ntpcVIKASH BAGHEL
This document provides an overview of the thermal power plant located in Korba, Chhattisgarh, India. It discusses the key components and processes, including the coal handling plant, main plant, ash handling plant, and safety practices. The coal handling plant handles coal sourced from local mines, crushing it and pulverizing it for combustion. The main plant features the boiler, steam turbine, cooling tower, generator, and other equipment to generate electricity. The ash handling plant processes the remaining ash after combustion. The power plant has an installed capacity of 2600 MW and benefits several nearby states.
This document is a report on engineering materials that was prepared by an engineering student at Al Azhar University in Egypt. It provides an introduction to engineering materials and discusses their historical uses. It describes how materials science developed with advances in physics and chemistry. It then classifies and describes different types of materials like metals, ceramics, polymers, and composites. The document focuses on properties of metals, defining terms like hardness, brittleness, malleability, ductility, elasticity, toughness, density, fusibility, and conductivity. It provides examples to illustrate each property.
This document appears to be a training report submitted by Nishant Pareek to fulfill requirements for a Bachelor of Technology degree in Mechanical Engineering. It provides an overview of Nishant's summer training at the National Thermal Power Corporation plant in Anta. The report includes sections on the history and operations of NTPC, a description of the Anta plant layout and power production process, and details on the gas turbine, steam turbine, and waste heat recovery boiler systems.
This document provides an overview of the National Thermal Power Plant in Kahalgaon, Bihar, India. It discusses that NTPC Kahalgaon has an installed capacity of 2340 MW and is fueled by coal sourced from nearby mines. The document outlines the key areas and systems within the plant including the coal handling plant, boiler and its auxiliaries, turbine auxiliaries, generator and switchyard. It also provides background on NTPC as the largest power company in India and describes the general layout of a thermal power plant's four main circuits for coal/ash, air/gas, feedwater/steam, and cooling water.
The document is an internship report submitted by Aditya Aryan about his four-week internship at the National Thermal Power Corporation (NTPC) power plant in Chennai, India. It provides an overview of NTPC, describes the key components and operations of a thermal power plant including the boiler, turbine, generator and cooling towers. It also includes figures and diagrams to illustrate the power plant layout and components. The report aims to document Aditya's experience and learnings during his internship at the NTPC power plant.
The document provides details about a presentation on summer training at NTPC Tanda power plant. It discusses that NTPC is the largest power company in India. It then summarizes information about NTPC Tanda power plant including its capacity, sources, main departments like coal handling plant, boiler, turbine, and generator. It also mentions advantages like low cost of fuel and disadvantages like atmospheric pollution of thermal power plants.
NTPC was established in 1975 by the Government of India to address growing power demand. It is now the largest power generating company in India with over 30 GW of installed capacity from coal, gas, hydro, and renewable sources. NTPC started with thermal power plants and has expanded into various power generation technologies and business areas. The document provides details on NTPC's thermal power plants across India, including their locations and installed capacities.
This document provides an overview of NTPC Limited, the largest power generating company in India. It discusses NTPC's history, operations, and growth strategy. Some key points:
- NTPC was established in 1975 and has emerged as a national power company with facilities across India. Its current installed capacity is over 27,000 MW.
- The company aims to become a 75,000 MW company by 2017 through diversifying its fuel mix to include more hydro, nuclear, renewable and gas-based power generation alongside coal.
- NTPC operates various coal-fired, gas/liquid-fired and joint venture power plants located across major regions in India. It also provides power consultancy and other services.
India has significant untapped small hydro power (SHP) potential. The estimated SHP potential is 19,749 MW, but only 3632 MW has been developed so far. SHP provides environmental and economic benefits. The Ministry of New and Renewable Energy promotes SHP development through private sector participation to utilize India's SHP resources and meet renewable energy targets.
training report on thermal power plant & thermal power generation by sagar me...Sagar Mehta
This document provides a practical training report submitted by Sagar Mehta to Rajasthan Technical University in partial fulfillment of the requirements for a Bachelor of Technology degree. The report details Mehta's summer training at the Nashik Thermal Power Station in Maharashtra, India. It includes sections on the history of the power sector and thermal power generation in India, an overview of the Nashik Thermal Power Station, descriptions of the various systems and processes within a thermal power plant including the steam power plant, coal handling plant, water treatment plant, boilers, turbines, generators, condensers and ash handling plant. The report concludes with discussions on energy conservation, auditing, and suggestions.
This document provides a summary of a seminar on summer vocational training at NTPC thermal power plants. It discusses the key components of a thermal power plant including coal handling, pulverizing, boilers, turbines, generators, condensers, and ash handling. It also describes various equipment like ball mills used in pulverizing coal and control and instrumentation labs that monitor critical parameters. Finally, it lists some major thermal power plants in Rajasthan and references used in preparing the seminar.
Project Report on Industrial Summer Training at NTPC SimhadriAshish Uppu
The following pdf is a Project Report about my Industrial Training at NTPC Limited Simhadri, Visakhapatnam, Andhra Pradesh, India. It includes all the fundamentals of a Thermal Power Plant: its layout, various departments, principal components etc. It also contains a brief profile about the company.
The document provides an overview of thermal power generation. It discusses the need for thermal power, the basic working principles, and classifications by fuel and prime mover. The key steps in the thermal power generation process include heating water to create steam, using the steam to power a turbine connected to a generator to produce electricity, and then condensing the steam to be reused. Thermal power plants have advantages of using widely available fuels but have lower efficiency and higher emissions than other generation methods. Improving plant efficiency and reducing emissions are important areas of ongoing research and development.
National Thermal Power Corporation Ltd. (NTPC) was incorporated in 1975 and began operations in 1976. It has grown to become one of the largest power producers in India, with an installed capacity of over 45,000 MW as of 2015. NTPC operates mainly coal and gas-fired power plants, with some hydro and renewable energy projects as well. It aims to increase power generation capacity to over 128,000 MW by 2032 through both organic and inorganic growth. NTPC makes a significant contribution to meeting India's increasing electricity demand in a sustainable and efficient manner.
training report NTPC Muzaffarpur Bihar Dilip kumar
This document provides an industrial training report on the generation system of the National Thermal Power Corporation Ltd. (NTPC). It discusses the key components of a thermal power plant that use the modified Rankine cycle to convert the chemical energy of coal into electrical energy. These include the boiler, turbine, condenser, and other auxiliary components. The report also provides an overview of the processes involved in coal handling, steam generation, power generation using steam turbines, and electricity distribution at NTPC power plants. It aims to provide an understanding of the technical aspects and management of thermal power generation.
The document provides information about the author's 4 week training at NTPC from June to July 2016. They visited the Boiler Maintenance Department and Turbine Maintenance Department to learn how electricity is produced. NTPC is India's largest power company, generating over 45,000 MW of electricity using steam turbines powered by coal. The company was founded in 1975 and uses the Rankine cycle to convert heat from coal into mechanical power and then electrical power.
Internship report of NTPC kawas ,summer internship report of ntpcLalitGoyal27
National Thermal Power Plant Kawas Project report,summer internship report of ntpc ,internship report, national thermal power plant kawas project report, summer internship report of ntpc,ntpc summer training report,ntpc training repntpc training reportort
Vishal Kumar completed a summer training program at NTPC Barh power plant in Bihar. He thanks the NTPC authorities for allowing him to complete his training and gain valuable experience observing the various mechanical and electrical operations across different parts of the power plant. The document provides an overview of NTPC as India's largest power generation company, including its vision, operations, environmental policies and practices, and details about the NTPC Barh power plant where Vishal completed his training.
This training report summarizes Pratik Gupta's vocational training at the SIPAT Super Thermal Power Project. It provides details on the production of electricity at a thermal power plant. Coal is ground and blown into boilers where it burns, heating water in tubes to produce high pressure steam. The steam powers turbines connected to generators, producing electricity. The steam is then condensed back into water in condensers to be reused in the cycle. The report outlines the key components and processes involved in electricity generation at a coal-fired thermal power station.
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...haxxo24
This document is a summer training project report submitted by Dinesh Kumar, a mechanical engineering student, on his vocational training at the National Thermal Power Corporation Sipat power plant in Chhattisgarh, India. The report provides an overview of NTPC Sipat, including its location, installed capacity, use of supercritical technology, and environmental management practices. It also describes the basic Rankine cycle used in thermal power plants, the major sub-systems of a power plant such as the coal handling plant, mills, water treatment plant and boiler, and includes diagrams of a typical power plant layout and the interior of a bowl mill.
This industrial training report summarizes Deepak Kr Singh's one month internship at the Singrauli Super Thermal Power Plant in Shaktinagar, India. The report includes details of the power plant such as its seven units with a total capacity of 2,000 MW. It also covers various topics related to thermal power generation including the workings of boilers, turbines, generators, and switchgear. Deepak conducted his training under the supervision of his training incharge Mr. CH Satynarayan, during which he gained knowledge and experience in the electrical engineering aspects of thermal power generation.
The document discusses India's power generation capacity addition targets and plans over multiple 5-year plans from the 10th plan to the current 12th plan. It notes that the 12th plan aims to add over 88,000 MW of capacity across various sectors like thermal, hydro, and nuclear power. It also states that coal requirements to meet this generation target will be around 842 million tonnes. Biomass energy is highlighted as an organic matter that can be used to produce heat, electricity, or transportation fuels.
vocational training presentation on korba ntpcVIKASH BAGHEL
This document provides an overview of the thermal power plant located in Korba, Chhattisgarh, India. It discusses the key components and processes, including the coal handling plant, main plant, ash handling plant, and safety practices. The coal handling plant handles coal sourced from local mines, crushing it and pulverizing it for combustion. The main plant features the boiler, steam turbine, cooling tower, generator, and other equipment to generate electricity. The ash handling plant processes the remaining ash after combustion. The power plant has an installed capacity of 2600 MW and benefits several nearby states.
This document is a report on engineering materials that was prepared by an engineering student at Al Azhar University in Egypt. It provides an introduction to engineering materials and discusses their historical uses. It describes how materials science developed with advances in physics and chemistry. It then classifies and describes different types of materials like metals, ceramics, polymers, and composites. The document focuses on properties of metals, defining terms like hardness, brittleness, malleability, ductility, elasticity, toughness, density, fusibility, and conductivity. It provides examples to illustrate each property.
This document appears to be a training report submitted by Nishant Pareek to fulfill requirements for a Bachelor of Technology degree in Mechanical Engineering. It provides an overview of Nishant's summer training at the National Thermal Power Corporation plant in Anta. The report includes sections on the history and operations of NTPC, a description of the Anta plant layout and power production process, and details on the gas turbine, steam turbine, and waste heat recovery boiler systems.
A TedTalk by Sunni Brown advocates for doodling, arguing it helps people focus and learn in 4 ways: visually, through hearing, reading/writing, and kinesthetically through motion. The talk is summarized visually in under a minute by Khadeidra, who encourages teachers, bosses and judges to stop shaming people for doodling.
Este documento presenta la resolución de tres problemas relacionados con señales moduladas en frecuencia (FM). En el primer problema, se calcula el índice de modulación, la potencia en la portadora y las frecuencias de las bandas laterales para una señal FM con desviación de 10 KHz y frecuencia moduladora de 5 KHz. En el segundo problema, se realizan cálculos similares para una señal con desviación de 3 KHz y frecuencia moduladora de 1 KHz. El tercer problema solicita dibujar el espectro de f
This document discusses security considerations for cloud computing instances, networking, and storage. It recommends using bastion servers for CLI access with key-based authentication over secure protocols. For instances, it suggests using LTS OS releases, security patches, and HIDS for critical hosts. Networking advice includes using subnets for applications, public subnets only for public-facing systems, and private subnets with NAT for non-public systems. The document also recommends encrypting sensitive stored data with role-based access controls and logging, and storing authentication materials securely.
1) The document discusses several artists who use their art to raise awareness of environmental and social issues. Crystal Morey creates sculptures that depict humans and endangered animals interconnected to bring attention to habitat loss and human impacts on the environment. Elina Peduzzi makes jewelry that celebrates her diverse Venezuelan culture and comments on political issues. Jonathan Huang was inspired to create sculptures about child sex trafficking after helping build a rescue shelter for victims in the Philippines.
2) These artists see art as a way to educate others and a "contribution" to addressing important issues like climate change, cultural identity, and human rights. Their works often have symbolic meanings and personal narratives to convey specific messages.
3) Using their
Este documento sugiere que a pesar de tener éxito material, muchas personas aún no son felices y se sienten atrapadas por los estereotipos sociales. También menciona que salir de la zona de confort puede ayudar a alcanzar la felicidad y cumplir el deseo de larga data de convertirse en emprendedor para liberarse a sí mismo.
This document discusses how to find a "just right" book that is enjoyable and engaging to read. It explains that like shoes, not every book is a good fit for every reader. The just right book for a reader is one that is attractive to them, has an appropriate number of words, allows them to visualize a story, holds their interest so they cannot put it down, and can read aloud smoothly. It provides tips for determining if a book has too many difficult words. Additionally, it suggests that reading conditions, such as lighting and comfort, contribute to finding books that are just right.
ASTD to ATD- The Five Characteristics of an Adaptive Culture-Blog Post 2014KHADEIDRA LE GENDRE, M.A.
The document discusses the characteristics of an adaptive culture based on ASTD's recent rebranding as ATD. It identifies five key characteristics: 1) a culture willing to change, as ASTD has changed its name and focus over time to remain relevant; 2) identifying problems before they occur, like a snowshoe hare changing color with the seasons; 3) being innovation-focused and willing to take risks to develop talent with changing times; 4) emphasizing trust and candor for progress and adaptation; and 5) having enthusiasm from leadership to rally members through changes. The document questions how prepared practitioners and ASTD members are to adapt to the changes from ASTD to ATD.
This document lists the team members of a fundraising group including Garrett Johanson, Tonia Okowi, Mayu Kataoka, Brad Dowhaniuk (Owner), Folasade Ogunbanwo and Cyndy Patrick. The team is working on a fundraising effort labeled #FUNdraising.
This document discusses Docker containers and Amazon ECS container management. It defines what Docker containers are, why they are used, and why a container cluster management system is needed. It then explains what Amazon ECS is, including its key components like clusters, instances, tasks, and services. It describes how ECS manages the lifecycle of containers across a cluster of EC2 instances and provides high scalability and availability. Finally, it covers some advantages of ECS, challenges to consider, and default resource limits.
Dokumen tersebut membahas konsep dan notasi dasar proposisi dalam logika, termasuk definisi proposisi, operator logika seperti konjungsi, disjungsi, negasi, implikasi, dan tabel kebenaran yang terkait. Diberikan pula contoh-contoh penerapan operator logika dan hukum-hukum aljabar proposisi.
The reference describes the candidate's previous employment as a secretary at a construction company from 2004 to 2005. In that role, she managed the company's office operations and oversaw various departments. The reference characterized the candidate as highly organized, a strong team player, and focused on achieving goals and meeting quality standards. They would highly recommend her for a teacher position and would rehire her based on her work performance and skills.
NTPC is India's largest power company established in 1975 to accelerate power development. It has expanded beyond power generation into related areas. NTPC operates power plants across India with a total installed capacity of over 39 GW. The Badarpur Thermal Power Station (BTPS) was established in 1973 and has a total installed capacity of 720 MW across 5 units. BTPS uses coal to generate electricity through the Rankine cycle of heating water to steam to power a turbine generator.
NTPC is India's largest power company established in 1975 to accelerate power development. It has expanded beyond power generation into related areas. NTPC operates power plants across India with a total installed capacity of over 39 GW. The Badarpur Thermal Power Station (BTPS) was established in 1973 and has a total installed capacity of 720 MW across 5 units. BTPS uses coal to generate electricity through the Rankine cycle of heating water to steam to power a turbine generator. The key components of a power plant are the boiler, turbine, generator, cooling system and transmission lines.
NTPC is India's largest power company established in 1975 to accelerate power development. It has a total installed capacity of 39,174 MW from 16 coal and 7 gas power stations across India. NTPC aims to have 128,000 MW of capacity by 2032 from diverse fuel sources including 56% coal, 16% gas, 11% nuclear and 17% renewable energy. It focuses on high efficiency, contributing 27.4% of total power generation while having only 17.75% of total national capacity. NTPC has initiatives in technology, corporate social responsibility, partnering with government, and stringent environment management to be a sustainable and socially responsible company.
1. NTPC is India's largest power company established in 1975 to accelerate power development. It has expanded beyond power generation into related areas like consulting, trading, ash utilization, and coal mining.
2. NTPC had an installed capacity of 39,174 MW as of 2010 from various coal and gas-based power plants located across India. It aims to increase capacity to 128,000 MW by 2032 with a diversified fuel mix including renewable sources.
3. In addition to power generation, NTPC is involved in technological initiatives for more efficient power production, various corporate social responsibility programs, consulting with other power companies, and stringent environmental management practices at its plants.
Industrial training at NTPC ShaktinagarRishikesh .
This document is an industrial training project report submitted by Rishikesh after completing a 30 day vocational training program at the NTPC Shaktinagar thermal power plant in Uttar Pradesh, India. The report provides an overview of NTPC, including its strategies around technology, corporate social responsibility, partnering with the government, and environmental management. It also describes some of the environmental issues caused by power plants in the Singrauli region where pollution from coal mining and thermal power plants has resulted in health problems for local residents.
The document discusses the employee welfare benefits project the author completed at NTPC Ltd. in Delhi. The project involved analyzing the various benefits provided by NTPC to employees and collecting data through questionnaires and surveys on satisfaction levels and opportunities for improvement. The author would then provide recommendations based on the collected data.
National Thermal Power Corporation (NTPC) was established in 1975 to supplement India's efforts in increasing thermal power generation. It has since grown to become the largest power company in India and one of the largest in Asia, with over 34,000 MW of generation capacity across coal and gas plants. NTPC aims to increase capacity to 56,000 MW by 2012 and 75,000 MW by 2017. It has diversified into areas like hydro power, coal mining, oil and gas, power trading and distribution. NTPC's Anta gas power plant began operations in 1990 and generates 419 MW of power for states in northern India. The plant strives for excellence through various quality certifications and corporate social responsibility initiatives in local
NTPC Limited is India's largest power company, generating over 51,000 MW of power as of 2017 through various coal, gas, hydro, and joint venture plants across India. The document discusses NTPC's history and operations, technological initiatives in clean energy, corporate social responsibility programs, and environmental management practices. It also provides specific details about NTPC Kahalgaon, a 2,340 MW coal-fired power plant located in Bihar. The plant sources coal from nearby mines and uses a steam turbine process to generate electricity that is supplied to various states in Eastern India.
A presentation on summer training at NTPC corporate office noidaAshutosh Tripathi
This document provides a summary of a presentation about a summer training at NTPC Noida. It discusses NTPC's profile, including that it is India's largest power company and was established in 1975. It outlines NTPC's plants, power sharing in India, use of communication technologies like satellites, and new technologies being used like ultra supercritical plants. It also discusses NTPC's use of ash from plants and efforts to increase ash utilization. The presentation concludes by discussing the importance of conserving energy and developing renewable sources to improve the environment.
NTPC Limited is the largest thermal power generating company in India. It has a current generating capacity of 30,144 MW and aims to become a 75,000 MW company by 2017. NTPC Simhadri plant has a capacity of 1000 MW and is located in Andhra Pradesh. It sources coal from the Kalinga block in Odisha and water from the Yeleru canal. NTPC Simhadri has achieved high standards in technology utilization, efficiency, and environmental protection.
NTPC is India’s largest energy conglomerate with roots planted way back in 1975 to accelerate power development in India. Since then it has established itself as the dominant power major with presence in the entire value chain of the power generation business. From fossil fuels it has forayed into generating electricity via hydro, nuclear and renewable energy sources. This foray will play a major role in lowering its carbon footprint by reducing green house gas emissions. To strengthen its core business, the corporation has diversified into the fields of consultancy, power trading, training of power professionals, rural electrification, ash utilization and coal mining as well.
NTPC became a Maharatna company in May 2010, one of the only four companies to be awarded this status. NTPC was ranked 431st in the ‘2015, Forbes Global 2000’ ranking of the World’s biggest companies.
The total installed capacity of the company is 44,798 MW (including JVs) with 17 coal based and 7 gas based stations. 7 Joint Venture stations are coal based and 8 renewable energy projects. The company has set a target to have an installed power generating capacity of 1,28,000 MW by the year 2032. The capacity will have a diversified fuel mix comprising 56% coal, 16% Gas, 11% Nuclear and 17% Renewable Energy Sources including hydro. By 2032, non fossil fuel based generation capacity shall make up nearly 28% of NTPC’s portfolio.NTPC has been operating its plants at high efficiency levels. Although the company has 17.73% of the total national capacity, it contributes 25.91% of total power generation due to its focus on high efficiency.
Vision
“To be the world’s largest and best power producer, powering India’s growth.”
MISSION
Develop and provide reliable power, related products and services at competitive prices, integrating multiple energy sources with innovative and eco-friendly technologies and contribute to society.
Core Values – BE COMMITTED
B Business Ethics
E Environmentally & Economically Sustainable
C Customer Focus
O Organizational & Professional Pride
M Mutual Respect & Trust
M Motivating Self & others
I Innovation & Speed
T Total Quality for Excellence
T Transparent & Respected Organization
E Enterprising
D Devoted
NTPC Electric Supply Company Ltd. (NESCL)
The company was formed on August 21, 2002. It is a wholly owned subsidiary company of NTPC with the objective of making a foray into the business of distribution and supply of electrical power, as a sequel to reforms initiated in the power sector. The company was also mandated to take up consultancy and other assignments in the area of Electrical Distribution Management System.
Its maiden entry into power distribution was by forming a 50:50 JV company ‘KINESCO Power and Utility Private Ltd.’ with Kerala Industrial Infrastructure Development Corporation (KINFRA). It is already distributing power in KINFRA.
This document provides an overview of NTPC Limited, the largest power generating company in India. It discusses NTPC's history and growth over 30 years to become a national power company generating 28.5% of India's power. It specifically profiles the NTPC Kahalgaon power plant located in Bihar, which is the largest single-location power plant in India. The document then summarizes NTPC's key services and functions, including power generation from thermal, hydro and gas sources; consultancy services for domestic and international clients; international marketing; and research through NETRA to develop new technologies focused on efficiency, reliability, environmental protection and cost reduction.
This document provides information about Vikas Singh's internship project and training report submitted in partial fulfillment of the requirements for a Bachelor of Technology degree. It was completed under the guidance of internal supervisor Dinesh Jhakar and external supervisor Brahm Shanker at the Badarpur Thermal Power Station of NTPC Limited in New Delhi, India from March to June. The report includes details about NTPC, the evolution and operations of the Badarpur Thermal Power Station, and Vikas Singh's experiences during the internship period.
VOCATIONAL TRAINING REPORT ON NTPC KORBAVIKASH BAGHEL
The document provides details about Vikash Baghel's vocational training report on thermal power plants at NTPC Korba in Chhattisgarh, India. It discusses the key components and processes of a thermal power plant including the coal handling plant, main plant components like the boiler, turbine and generator, the basic power plant cycle, and safety aspects. NTPC Korba has an installed capacity of 2600MW and uses coal sourced from local mines to generate electricity.
This document is a summer training report submitted by Awnish Anand, a 3rd year mechanical engineering student at SMIC Hyderabad, after completing a 4-week internship at the National Thermal Power Corporation (NTPC) plant in Barh, Bihar from June 1-31, 2016. The report provides an overview of NTPC, details about the Barh Super Thermal Power Plant where the training took place, and describes the basic steps of electricity generation from coal as observed during the internship. It also includes sections on maintenance departments at the plant and the Rankine cycle of thermal power generation.
This document discusses India's energy sector and initiatives to improve efficiency. It notes that India's economy has grown rapidly at around 9% annually in recent years, driving strong growth in electricity demand. To meet this demand, India plans large additions of new coal, hydro, nuclear and renewable generating capacity. Initiatives to improve existing plants include renovations to enhance efficiency, as well as policies to promote clean coal technologies, ultra-mega power projects, and increasing the share of hydro and renewable energy. The document outlines India's capacity targets through 2032 to support ongoing economic growth in a sustainable manner.
The document provides an overview of NTPC Limited, the largest power company in India. It discusses NTPC's operations, including its power generation capacity, operational performance, regional spread of power plants, and environmental management efforts. It also describes the basic components and functioning of a thermal power plant, including the steam generator, steam turbine, electric generator, and coal-based electricity generation process. Key details include NTPC having a generating capacity of 34,854 MW from 28 plants, high availability and plant load factors, and leadership in reducing environmental impacts from power generation in India.
This document is a training report submitted by Ayush Khare detailing his 6 week industrial training at the Badarpur Thermal Power Station (BTPS) in New Delhi, India. It provides background information on BTPS, describing how it started with one 95 MW unit in 1973 and now has five units with a total capacity of 720 MW. The report also summarizes Ayush's experiences in different divisions of the plant such as the Boiler Maintenance Department and Plant Auxiliary Maintenance.
Banti industrial training-report-on-ntpc-dadri GAS POWER PLANT94600banti
The document describes a report on an industrial training completed at the NTPC Dadri gas power plant. It provides an overview of NTPC and the Dadri station. The bulk of the document then focuses on introducing gas power plants, describing their components like the gas turbine starting system and fuel system. It explains how combined-cycle power plants work and the advantages they provide over conventional power generation methods.
ACEP Magazine edition 4th launched on 05.06.2024Rahul
This document provides information about the third edition of the magazine "Sthapatya" published by the Association of Civil Engineers (Practicing) Aurangabad. It includes messages from current and past presidents of ACEP, memories and photos from past ACEP events, information on life time achievement awards given by ACEP, and a technical article on concrete maintenance, repairs and strengthening. The document highlights activities of ACEP and provides a technical educational article for members.
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesChristina Lin
Traditionally, dealing with real-time data pipelines has involved significant overhead, even for straightforward tasks like data transformation or masking. However, in this talk, we’ll venture into the dynamic realm of WebAssembly (WASM) and discover how it can revolutionize the creation of stateless streaming pipelines within a Kafka (Redpanda) broker. These pipelines are adept at managing low-latency, high-data-volume scenarios.
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsVictor Morales
K8sGPT is a tool that analyzes and diagnoses Kubernetes clusters. This presentation was used to share the requirements and dependencies to deploy K8sGPT in a local environment.
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...IJECEIAES
Climate change's impact on the planet forced the United Nations and governments to promote green energies and electric transportation. The deployments of photovoltaic (PV) and electric vehicle (EV) systems gained stronger momentum due to their numerous advantages over fossil fuel types. The advantages go beyond sustainability to reach financial support and stability. The work in this paper introduces the hybrid system between PV and EV to support industrial and commercial plants. This paper covers the theoretical framework of the proposed hybrid system including the required equation to complete the cost analysis when PV and EV are present. In addition, the proposed design diagram which sets the priorities and requirements of the system is presented. The proposed approach allows setup to advance their power stability, especially during power outages. The presented information supports researchers and plant owners to complete the necessary analysis while promoting the deployment of clean energy. The result of a case study that represents a dairy milk farmer supports the theoretical works and highlights its advanced benefits to existing plants. The short return on investment of the proposed approach supports the paper's novelty approach for the sustainable electrical system. In addition, the proposed system allows for an isolated power setup without the need for a transmission line which enhances the safety of the electrical network
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...IJECEIAES
Medical image analysis has witnessed significant advancements with deep learning techniques. In the domain of brain tumor segmentation, the ability to
precisely delineate tumor boundaries from magnetic resonance imaging (MRI)
scans holds profound implications for diagnosis. This study presents an ensemble convolutional neural network (CNN) with transfer learning, integrating
the state-of-the-art Deeplabv3+ architecture with the ResNet18 backbone. The
model is rigorously trained and evaluated, exhibiting remarkable performance
metrics, including an impressive global accuracy of 99.286%, a high-class accuracy of 82.191%, a mean intersection over union (IoU) of 79.900%, a weighted
IoU of 98.620%, and a Boundary F1 (BF) score of 83.303%. Notably, a detailed comparative analysis with existing methods showcases the superiority of
our proposed model. These findings underscore the model’s competence in precise brain tumor localization, underscoring its potential to revolutionize medical
image analysis and enhance healthcare outcomes. This research paves the way
for future exploration and optimization of advanced CNN models in medical
imaging, emphasizing addressing false positives and resource efficiency.
International Conference on NLP, Artificial Intelligence, Machine Learning an...gerogepatton
International Conference on NLP, Artificial Intelligence, Machine Learning and Applications (NLAIM 2024) offers a premier global platform for exchanging insights and findings in the theory, methodology, and applications of NLP, Artificial Intelligence, Machine Learning, and their applications. The conference seeks substantial contributions across all key domains of NLP, Artificial Intelligence, Machine Learning, and their practical applications, aiming to foster both theoretical advancements and real-world implementations. With a focus on facilitating collaboration between researchers and practitioners from academia and industry, the conference serves as a nexus for sharing the latest developments in the field.
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTjpsjournal1
The rivalry between prominent international actors for dominance over Central Asia's hydrocarbon
reserves and the ancient silk trade route, along with China's diplomatic endeavours in the area, has been
referred to as the "New Great Game." This research centres on the power struggle, considering
geopolitical, geostrategic, and geoeconomic variables. Topics including trade, political hegemony, oil
politics, and conventional and nontraditional security are all explored and explained by the researcher.
Using Mackinder's Heartland, Spykman Rimland, and Hegemonic Stability theories, examines China's role
in Central Asia. This study adheres to the empirical epistemological method and has taken care of
objectivity. This study analyze primary and secondary research documents critically to elaborate role of
china’s geo economic outreach in central Asian countries and its future prospect. China is thriving in trade,
pipeline politics, and winning states, according to this study, thanks to important instruments like the
Shanghai Cooperation Organisation and the Belt and Road Economic Initiative. According to this study,
China is seeing significant success in commerce, pipeline politics, and gaining influence on other
governments. This success may be attributed to the effective utilisation of key tools such as the Shanghai
Cooperation Organisation and the Belt and Road Economic Initiative.
1. 1
CHAPTER-1
IINNTTRROODDUUCCTTIIOONN
1.1 Beginnings of NTPC LIMITED
India’s largest power company, NTPC was set up in 1975 to accelerate power development in
India. NTPC is emerging as a diversified power major with presence in the entire value chain
of the power generation business. Apart from power generation, which is the mainstay of the
company, NTPC has already ventured into consultancy, power trading, ash utilization and
coal mining. NTPC ranked 341st
in the „2010, Forbes Global 2000‟ ranking of the World’s
biggest companies. NTPC became a Maharatna company in May, 2010, one of the only four
companies to be awarded this status. A typical power plant of NTPC is shown in fig. 1.1
fig.- 1.1 A TYPICAL POWER PLANT OF NTPC
1.2 POWER GENERATION IN NTPC:
The total installed capacity of the company is 39,174 MW including joint ventures with 16
coal based and 7 gas based stations, located across the country. In addition, under JVs, 7
stations are coal based & another station uses naphtha/LNG as fuel. The company has set a
target to have an installed power generating capacity of 1,28,000 MW by the year 2032. The
capacity will have a diversified fuel mix comprising 56% coal,16% Gas, 11% Nuclear and
17% Renewable Energy Sources(RES) including hydro. By 2032, non-fossil fuel based
generation capacity shall make up nearly 28% of NTPC‟s portfolio In October 2004, NTPC
launched its Initial Public Offering (IPO) consisting of 5.25% as fresh issue and 5.25% as
offer for sale by Government of India. NTPC thus became a listed company in November
2004 with the Government holding 89.5% of the equity share capital. In February 2010, the
Shareholding of Government of India was reduced from 89.5% to 84.5% through Further.
3. 3
1.4NTPC Plants and their capacity:
1.4.1 Installed capacity:
Present installed capacity of NTPC is 47,228 MW (including 6,966 MW through
JVs/Subsidiaries) comprising of 44 NTPC Stations (18 Coal based stations, 7 combined cycle
gas/liquid fuel based stations, 1 Hydro based station), 9 Joint Venture stations (8 coal based and
one gas based) and 9 renewable energy projects. Installed capacity of NTPC is shown in table
no. 1.1.
TABLE 1.1 INSTALLED CAPACITY
1.4.2 Coal Based Power Stations:
NTPC is the largest thermal power generating company in the country with a coal based installed
capacity of 35,085 MW. Coal based power stations are shown in table 1.2 and 1.3 .
Table 1.2 Coal based power stations owned by NTPC
S.
N
o.
COAL BASED POWER
STATIONS
STATE COMMISSIONED
CAPACITY(MW)
1. Singrauli Uttar
Pradesh
2,000
2. Korba Chhattisgar
h
2,600
3. Ramagundam Telangana 2,600
4. Farakka West
Bengal
2,100
5. 5
1.4.3 Gas Based Power Stations
The details of NTPC gas based power stations is given in table 1.4 and 1.5.
Table 1.4Gas Based Power Stations owned by NTPC
Table 1.5 Gas Based Joint Ventures/Subsidiaries
1.4.4 Hydro Based Power Projects:
NTPC has increased thrust on hydro development for a balanced portfolio for long term
sustainability. Details are given below in table 1.6.
Table 1.6 Hydro Based Power Projects
6. 6
1.4.5 Renewable Energy Projects
Renewable energy technologies provide clean and green sources of electricity. NTPC has drafted
its business plan of capacity addition of about 1,000 MW through renewable resources by
2017.Solar energy projects commissioned are given below in table 1.7.
1) Solar Energy:
Table 1.7 Solar Energy Projects Commissioned
2) Hydro Energy:8 MW hydro energy based project at NTPC-Singrauli in Uttar Pradesh.
3) Geothermal Energy: Tattapani Geothermal Project in Chhattisgarh
1.5 Technological Initiatives
• Introduction of steam generators (boilers) of the size of 800 MW.
• Integrated Gasification Combined Cycle (IGCC) Technology.
• Launch of Energy Technology Centre -A new initiative for development of technologies with
focus on fundamental R&D.
• The company sets aside up to 0.5% of the profits for R&D.
• Roadmap developed for adopting µClean Development.
• Mechanism to help get / earn µCertified Emission Reduction.
7. 7
1.6 Corporate Social Responsibility
• As a responsible corporate citizen NTPC has taken up number of CSR initiatives.
• NTPC Foundation formed to address Social issues at national level
• NTPC has framed Corporate Social Responsibility Guidelines committing up to0.5% of net
profit annually for Community Welfare.
• The welfare of project affected persons and the local population around NTPC projects are
taken care of through well drawn Rehabilitation and Resettlement policies.
1.7 NTPC’S CORE VALUES:
B Business Ethics
E Environmentally & Economically Sustainable
C Customer Focus
O Organizational & Professional Pride
M Mutual Respect & Trust
M Motivating Self & others
I Innovation & Speed
T Total Quality for Excellence
T Transparent & Respected Organization
E Enterprising
D Devoted
1.8 NTPC’S VISION AND MISSION
NTPC’S VISION and MISSION are driving force in all our endeavor to ultimately produce
and deliver quality power in optimum cost and ecofriendly manner through concerted team
efforts and effective systems. Being an PSU, NTPC ANTA has derived its mission and vision
aligning with that of the corporate mission and vision.
VISION: - “To be the world’s largest and best power producer, powering India’s growth.”
MISSION: - “Develop and provide reliable power, related products and services at
competitive prices, integrating multiple energy sources with innovative and eco-friendly
technologies and contribute to society.”
8. 8
1.9 NTPC’S ENVIRONMENT POLICY: -
NTPC is committed to the environment, generating power at minimal environmental cost and
preserving the ecology in the vicinity of the plants. NTPC has undertaken massive a
forestation in the vicinity of its plants. Plantations have increased forest area and reduced
barren land. The massive a forestation by NTPC in and around its Ramagundam Power
station (2600 MW) have contributed reducing the temperature in the areas by about 3°c.
NTPC has also taken proactive steps for ash utilization. In 1991, it set up Ash Utilization
Division A
NTPC is the second largest owner of trees in the country after the Forest department.
As early as in November 1995, NTPC brought out a comprehensive document entitled
1.9.1 Environment Management, Occupational Health and Safety Systems:
NTPC has actively gone for adoption of best international practices on environment,
occupational health and safety areas. The organization has pursued the Environmental
Management System (EMS) ISO 14001 and the Occupational Health and Safety Assessment
System OHSAS 18001 at its different establishments. As a result of pursuing these practices,
all NTPC power stations have been certified for ISO 14001 & OHSAS 18001 by reputed
national and international Certifying Agencies
1.9.2 Pollution Control systems:
While deciding the appropriate technology for its projects, NTPC integrates many
environmental provisions into the plant design. In order to ensure that NTPC complies with
all the stipulated environment norms, various state-of-the-art pollution control systems /
devices as discussed below have been installed to control air and water pollution.
(a). Ash Dykes & Ash Disposal systems:
Ash ponds have been provided at all coal based stations except Dadri where Dry Ash
Disposal System has been provided. Ash Ponds have been divided into lagoons and provided
with garlanding arrangement for changeover of the ash slurry feed points for even filling of
the pond and for effective settlement of the ash particles.
(b). Electrostatic Precipitators:
The ash left behind after combustion of coal is arrested in high efficiency Electrostatic
Precipitators (ESPs) and particulate emission is controlled well within the stipulated norms. A
schematic diagram of Electrostatic Precipitators is given below In fig. 1.2
9. 9
fig 1.2 Electrostatic Precipitators
(c). Flue Gas Stacks:
Tall Flue Gas Stacks have been provided for wide dispersion of the gaseous emissions (SOX,
NOX etc.) into the atmosphere.
(d). Low-NOX Burners:
In gas based NTPC power stations, NOX emissions are controlled by provision of Low-
NOX Burners (Dry or wet type) and in coal fired stations, by adopting best combustion
practices.
(e). Coal Settling Pits / Oil Settling Pits:
In these Pits, coal dust and oil are removed from the effluents emanating from the Coal
Handling Plant (CHP), coal yard and Fuel Oil Handling areas before discharge into ETP.
(f). Neutralization Pits:
Neutralization pits have been provided in the Water Treatment Plant (WTP) for pH correction
of the Effluents before discharge into Effluent Treatment Plant (ETP) for further treatment
and use. View of neutralization pits is shown in fig. 1.3
fig. 1.3 Neutralization Pits
10. 10
(h). Dry Ash Extraction System (DAES):
Dry ash has much higher utilization potential in ash-based products (such as bricks, aerated
autoclaved concrete blocks, concrete, Portland pozzolana cement, etc.). DAES has been
installed at Unchahar, Dadri, Simhadri, Ramagundam, Singrauli, Kahalgaon, Farakka, Talcher
Thermal, Korba, Vindhyachal, TalcherKaniha and BTPS. A view of Dry Ash Extraction
System (DAES) is given I fig. 1.4.
fig. 1.4 Dry Ash Extraction System (DAES)
(h). Ash Water Recycling System:
Further, in a number of NTPC stations, as a proactive measure, Ash Water Recycling System
(AWRS) has been provided. In the AWRS, the effluent from ash pond is circulated back to
the station for further ash sluicing to the ash pond. This helps in savings of fresh water
requirements for transportation of ash from the plant. The ash water recycling system has
already been installed and is in operation at Ramagundam, Simhadri, Rihand, TalcherKaniha,
Talcher Thermal, Kahalgaon, Korba and Vindhyachal. The scheme has helped stations to
save huge quantity of fresh water required as make-up water for disposal of ash.
11. 11
CHAPTER-2
ANTA Thermal Power GAS Station
2.1 ANTA Thermal Power Station (ATPS)
NTPC, Anta project is located about 23km from Baran district and close to Anta town of the
district. Anta project is the first in the series of combined cycle power projects set up by
NTPC in different parts of the country. The installed capacity of first stage is 419.33 MW
comprising 3 gas turbines of 88.71 MW each and a steam turbine of 153.2 MW. All the units
were synchronized ahead of schedule. A bird view of NTPC ANTA s given in fig. 2.1
fig. 2.1 Bird view of NTPC anta
Anta national gas power project is the first in the series of combined cycle power project set
up by NTPC in different parts of country. The installed capacity is 419.33 MW with 3 GTG
units of 88.71 MW each and 1 STG Unit combined cycle with a capacity of 153.2 MW. The
approximate cost of this project is built on turkey based “Area brown bowers of Germany and
Hindustan brown bovver of India.”
2.2 LOCATION: -The plant is located to town in Baran dist. (Rajasthan). Anta town is 5km
from NTPC plant and Anta railway station is just 2km away. Anta town is 55km from Kota
district. The area covered by plant station is 248 acres and 142 acres for township.
12. 12
2.3 FUEL SOURCE: - The natural gas is brought through Hazira – Bijalpur – Jagdishpur gas
field. One 18 inch pipe is tapped from Bijalpur to Anta. Naphtha source is PSUs oil
companies through road tankers and source of water is “Kota right main canal.”
2.3 PROJECT PROFILE: Project profile of NTPC anta plant is given in table 2.1
Table 2.1 Project profile of NTPC anta
Approved capacity 419.33 MW.
Installed capacity 419.33 MW.
Location Anta, distt.-Baran (Rajasthan).
Gas source HBJ pipeline- South basin gas field.
Water source Kota right main canal.
Unit sizes 3 x 88.71 GTG + 1 x 153.2 STG
Units commissioned Unit I -88.71 MW GTG January 1989
Unit II - 88.71 MW GTG March 1989
Unit III - 88.71 MW GTG May 1989
Unit IV - 153.2 MW STG March 1990
Beneficiary states Uttar Pradesh, Jammu & Kashmir,
Himachal Pradesh, Chandigarh, Rajasthan,
Haryana, Punjab & Delhi
Approved statement RS.418.97 Crores
2.4 SALIENT FEATURES OF ANTA
1. GAS TURBINE : 89.20MW, TYPE 13D-2, ABB MAKE,
5th
STAGE REACTION TURBINE
2. GT COMPRESSOR : 18th
STAGE AXUIAL FLOW, RECTION
BLADING
3. COMBUSTION CHAMBER : SINGLE SILO TYPE, DUAL FUEL FIRED
BURNER
4. AIR INTAKE FILTER : SELF CLEANING, SYNTHATIC PAPER,
TOTAL 945 FILTERS IN THREE TIERS.
5. BYPASS STACK : VERTICAL 25M.HIGH.
13. 13
6. WASTE HEAT RECOVERY : DUAL PRESSURE, DOUBLEDRUM,
BOILER UNFIRED, FORCED CIRCULATION.
BOILER PRESSURE FLOW TEMP
HP 62.70BAR 163 T/Hr 4850
C
LP 5.5 BAR 39.1T/Hr 2070
C
7. STEAM TURBINE : 153.20MW, TANDEM COMPOUNDED,
DOUBLE EXHAUST, CONDENSING TYPE,
SINGLE FLOW HORIZONTAL 25 STAGE HP
TURBINE.
8. CONDENSOR : DOUBLE PASS SURFACE CONDENSOR WITH
STAINLESS STEEL TUBES, COOLING 13988M3.
9. GENERATOR : 3 PHASES, TWO POLE, AIR COOLED
OUT PUT VOLTAGE SPEED
GTG. 135MVA 10.5 KV 3000 RPM
STG.191MVA 15.75 KV 3000 RPM
10. DM. WATER PLANT : TWO STREAM OF 35 M3
/HR EACH
11. FUEL : NATURAL GAS (MAIN FUEL), THROUGH
HBJ PIPE LINE, NAPHTHA FUEL BY ROAD
TANKER
12. WATER SOURCE : KOTA RIGHT MAIN CANAL
13. RESERVIOUR : 10 MILLION M3
, FOR 1 MONTH
14. TOTAL LAND : 390.75 ACRES
15. PLANT OUTPUT : 419.33MW
14. 14
2.5 ALLOCATION OF POWER TO STATES: States and their percentage in total power
is given in table 2.2
Table 2.2 ALLOCATION OF POWER TO STATES
STATES ALLOCATION IN MW PERCENTAGE
RAJASTHAN 83 19.81%
DELHI 44 10.5%
PUNJAB 49 11.69%
HARYANA 24 5.73%
HIMANCHAL 15 3.58%
J & K 29 6.92%
CHANDIGARH 05 1.19%
UTTAR PRADESH 91.45 21.75%
UTTARANCHAL 15.88 3.79%
UNALLOCATED 63 15.04%
TOTAL 419.33 100%
15. 15
CHAPTER-3
POWER PRODUCTION AT NTPC ANTA
A gas power station turns the chemical energy in natural gas into electrical energy that can be
used in homes and business. Natural gas is pumped into the gas turbine, where it is mixed
with air and burned, converting its chemical energy into heat energy. As well as heat, burning
natural gas produces a mixture of gases called the combustion gas. The heat makes the
combustion gas expand. A schematic diagram of process is given below in fig. 3.1
fig. 3.1 combined cycle power plant
In the enclosed gas turbine, this causes a build-up of pressure. The pressure drives the
combustion gas over the blades of the gas turbine, causing it to spin, converting some of the
heat energy into mechanical energy. A shaft connects the gas turbine to the gas turbine
generator, so when the turbine spins, the generator does too. The generator uses an
electromagnetic field to convert this mechanical energy into electrical energy. After passing
through the gas turbine,
16. 16
The still-hot combustion gas is piped to the heat recovery steam generator. Here it is used to
heat pipes full of water, turning the water to steam, before escaping through the exhaust
stack.
As shown in fig. 3.2 Natural gas burns very cleanly, but the stack is still built tall so that the
exhaust gas plume can disperse before it touches the ground. This ensures that it does not
affect the quality of the air around the station. The hot steam expands in the pipes, so when it
emerges it is under high pressure.
fig. 3.2 HEAT BALANCE DIAGRAM
These high-pressure steam jets spin the steam turbine, just like the combustion gas spins the
gas turbine. The steam turbine is connected by a shaft to the steam turbine generator, which
converts the turbine’s mechanical energy into electrical energy. After passing through the
turbine, the steam comes into contact with pipes full of cold water. Here water is pumped
from Rampur distributaries of gudgeon canal. The cold pipes cool the steam so that it
condenses back into water. It is then piped back to the heat recovery steam generator to be
reused.
Finally, a transformer converts the electrical energy from the generator to a high voltage.
17. 17
FLOW PROCESS CHART OF COMBINED CYCLE POWER PLANT IS GIVEN BELOW
IN FIG. 3.3
fig.. 3.3 FLOW PROCESS CHART OF COMBINED CYCLE POWER PLANT
18. 18
3.2 Parts of combined cycle power plant:
The step by step description of the process and the machinery is as follows:
3.2.1. Air Intake System:
The air intake system consists of huge suction pumps in order to meet the air requirements.
The air to fuel ratio is 11:1. Thus the amount of air being taken in is controlled so as to keep
this ratio constant. The view of air intake system at NTPC ANTA is given in fig. 3.4.
fig.3.4: The view of air intake system at NTPC ANTA
3.2.2. Air filters:
The air obtained from the environment contains numerous pollutants and unwanted
compounds which may harm the machinery and reduce the efficiency of the system. These
unwanted compounds may also react with the surface of the machinery and cause scaling
which would subsequently reduce the lifetime of the machinery. To overcome this problem,
the air is passed through the filter section. This section consists of an array of 576 filters to
eliminate all the unwanted particles and compounds present in the air.
3.2.3. Air compressor
The filtered air is then passed through the compressor section. The compression of air takes
place in 16 stages. The compression reduces the temperature of air. To compensate the heat
19. 19
loss and prevent the temperature shock in the next stage, heat addition is done in the next
stage of combustion. A sectional view of an air compressor is given below in fig. 3.5
fig.3.5 A sectional view of an air compressor
3.2.4. Combustion chamber
After compression, the air is sent to the combustion chamber In combustion chamber, the air
compressed and supplied by compressor is brought to the required process temperature by
combustion of liquid/gas fuel. As shown in fig. 3.6 The single combustion chamber is fitted
with only one duel fired burner and mounted vertically on the compressor/turbine assembly.
The combustion chamber is all welded steel plate fabricated.
fig.: -3.6 STANDERD COMBUSTTION CHAMBER
20. 20
The main parts are jacket with cover, lower upper combustion chamber bodies, finned
segment body, burner and inner casing.
Combustion chamber jacket, which houses the components, is made of heat resistant, low
alloy ferrite steel. Finned segment body encloses the hottest zone of the combustion chamber.
The air from the compressor enter the combustion chamber from below and flow upward
through the annular space between combustion chamber jacket and inner section of the lower
combustion chamber body. Approximately 30% air flow enter the combustion chamber
approximately 30% air flow enter the combustion chamber through upper body via finned
segment row (there are 5 rows). The remaining 40% flow as primary air for combustion, into
the swirl insert and enter the combustion space with turbulence. After the fuel has ignited
these gases are thoroughly mixed with secondary air from mixing nozzles and brought to the
permissible turbine inlet temp. The inner casing guides the hot gases coming from
combustion chamber to the turbine balding. It is thin welled construction made of heat
resistant chrome-nickel austenitic alloy
3.2.5. Gas turbine
It is a single shaft (with line compressive unit). It is a 50 Hz; 88.71MW machine which runs
on natural gas could also be operated on the liquid Naphtha. The gas turbine is very heavy,
industrial type, within line compressor multistage flow type. The combustion chamber is of
annular type. According to the flow of the air; compressor is placed first, combustion
chamber is next to it and turbine at the end of gas turbine.
fig.3.7: Gas Turbine
21. 21
Two bearings are placed to support the shaft of the machine,
these turbines are provided at the compressor starting end, and other are placed at the turbine
end. The shaft of the unit is provided with the blades in the turbine region. A schematic
diagram of gas turbine is shown in fig. 3.7.
3.2.6. Generator
The rotation of gas turbine leads to the rotation of the rotor part of the generator which is
connected to the same shaft as that of the turbine. A view of the Turbine and the generator
mounted on a single shaft is given below in fig. 3.8.
fig. 3.8: Turbine and the generator mounted on a single shaft
3.2.7. Step up transformer
The electricity is generated at 10.5KV. But this voltage is very less for the purpose of
transmission over a long distance and hence the step-up transformer is used to step up the
voltage from 10.5KV to 220KV. A view of step up transformer is given below in fig. 3.9
fig. 3.9: Step Up Transformer
22. 22
3.2.8. Unit auxiliary transformer
For the purpose of running the machinery of the plant and exciting the generator, the power
obtained from the gas turbine is utilized. Since the machinery is operated at 6.6KV, the
voltage is first stepped down from 10.5KV to 6.6KV using the unit auxiliary transformer and
then supplied within the plant.
3.2.9Waste Heat Recovery boilers (WHRB)
Wagner-biro supplied boilers for anta combined cycle power plant known as waste heat
recovery boilers (WHRB) shown in fig. 3.10, which are of non-fired, dual pressure, forced
circulation type. The boiler has two different water/steam cycles known as high pressure
system and low pressure system. Each system has its own boiler drum and circulating pumps,
and is feed by HP & LP feed water pumps from a common feed water tank. The pressure and
temperature of high pressure super heated steam is 64 bar and 4900
C and that of LP 6 bar
and2060
C.
(a). High pressure boiler drum
The flue gas from the turbine has a very high temperature of 5400o
C. This is utilized to heat
the water in the boiler drums. High power boiler drum absorbs most of the heat from the flue
gas and thus generates high power steam.
fig. 3.10 waste heat recovery boiler
23. 23
(b). Low pressure boiler drum
The remaining heat is absorbed by the low power boiler drum. Thus low power steam is
generated. Both the low power and high power steams are sent to the steam turbine.
3.2.10. Steam turbine
The plant is provided with one steam turbine generating unit shown in fig. 3.11. The turbine
is a 3000-rpm condensing set without any extraction for feed heating. It is a 160 MW, 50 Hz
two-cylinder condensing type turbines. The first cylinder (H.P) is a single flow type 25
reactions stages and the second cylinder (L.P) is a double flow with 7 reaction stages. It is
provided with two main and two LP stop and control valves. The H.P and L.P sections have
individual turbine rotors, which are connected to each other, and the generator with rigid
couplings.
fig.3.11: A steam turbine
3.2.11. Condenser
The condenser condenses the steam from the exhaust of the turbine into liquid to allow it to
be pumped. If the condenser is made cooler, the pressure of the exhaust steam is reduced and
efficiency of the cycle increases.
The surface condenser is a shell and tube heat exchanger in which cooling water is circulated
through the tubes. The exhaust steam from the low-pressure turbine enters the shell where it
is cooled and converted to condensate (water) by flowing over the tubes.
For best efficiency, the temperature in the condenser must be kept low practically in order to
24. 24
achieve the lowest possible pressure in the condensing steam. Since the condenser
temperature can be kept below 100°C, where the vapor pressure of water is much less than
atmospheric pressure, the condenser generally works under vacuum. Thus, two vacuum
pumps are used to maintain the vacuum pressure of 0.9 Kg/cm2. A third vacuum pump is
kept on standby in case of emergency.
fig. 3.12: Condenser
The water thus condensed is sent to the de-aerator for the removal of air. This is done by the
condensate extraction pumps. A schematic diagram of condenser is given in fig. 3.12
3.2.12. Steam turbine generator
As the thrust is created on the steam turbine blades, the rotor section of the generator to which
the turbine is connected, is rotated due to the rotation of the turbine shaft. This generates power
of 156 MW and a voltage of 15.75 KV is generated which is then stepped up at the next stage
and sent for transmission. A view of the steam turbine generator is shown in fig. 3.13
fig. 3.13 A view of the steam turbine generator
25. 25
3.2.13. Waste Heat Recovery Steam Generator
The waste heat generator are unfired, heat recovery type design to accept the maximum
exhaust temperature along with flue gas flow from the turbine. It is a natural circulation dual
unit. All heat transfer surface are of fin type. The feed control system is located in between
the economizer and drain to eliminate the possibility of streaming in the economizer and to
enable operation with zero approach point thereby increasing in the efficiency of the combine
cycle plant. A condensate preheated is added to low temperature zone of WHRG. There are
two types of steam produced in this unit (H.P & L.P).
3.1.14. Step up transformer
The voltage generated from the steam turbine is 15.75 KV which is very less for the purpose
of transmission over a long distance. The voltage is thus stepped up using a voltage step up
transformer. A typical step up transformer in NTPC ANTA is shown in fig. 3.14
fig. 3.14: A typical step up transformer
3.2.15. De-aerator
As shown in fig. 3.15 The water from the condenser is led here by the condensate extraction
pumps. The de-aerating boiler feed water system eliminates the need of expensive oxygen
scavenger chemicals and also offers the following advantages:
Removes carbon dioxide as well as oxygen.
Raises the boiler feed water temperature, eliminating thermal shock in boilers.
26. 26
Improves overall boiler room efficiency.
Feed water pumps are sized for each individual application - assuring total compatibility and
optimum operation.
fig. 3.15 De-aerator
3.2.16. Feed storage
The de-aerated water is then stored into the feed storage tank and is pumped out when
required.
3.2.17. Boiler feed pumps
They are used to pump the water from the feed storage tank to the respective boiler drums.
They are classified as high and low pressure boiler feed pumps based on the boiler drum to
which they pump the water.
3.2.18. Cooling towers
A cooling tower shown in fig. 3.17 is equipment used to reduce the temperature of a water
stream by extracting heat from water and emitting it to the atmosphere. Cooling towers make
use of evaporation whereby some of the water is evaporated into a moving air stream and
subsequently discharged into the atmosphere.
27. 27
fig. 3.17 Cooling towers
Cooling towers are heat removal devices used to transfer process waste heat to the
atmosphere. Cooling towers may either use the evaporation of water to remove process heat
and cool the working fluid to near the wet-bulb air temperature or in the case of closed circuit
dry cooling towers rely solely on air to cool the working fluid to near the dry-bulb air
temperature. The towers vary in size from small roof-top units to very large hyperboloid
structures that can be up to 200 meters tall and 100 meters in diameter, or rectangular
structures that can be over 40 meters tall and 80 meters long.
28. 28
CHAPTER-4
GAS TURBINE AND STEAM TURBINE UNIT
4.1 GAS TURBINE UNIT: -
4.1.1 INTRODUCTION
The compressor sucks in air from the atmosphere through the filters called air intake filters.
The compressed air at approx. 10.4 bar passes into the combustion chamber where it is used
as primary air for combustion and secondary air for cooling of various hot parts.
The gas turbine generates the necessary power to drive the axial-flow compressor and the
generator. The turbine and compressor are in common casing. Gas turbine electricity process
production layout is shown in fig, 4.1
fig..4.1 GAS TURBINE ELECTRICITY PRODUCTION PROCESS
Start-up of the GT drives with the help of starting equipment which runs the generator as a
motor with speed increasing from 0 to 600 r.p.m. At this speed a pilot flame is ignited in the
combustion chamber, fuel (gas/naphtha) enters and combustion takes place. The speed
increases further both with the help of generator motoring and the combustion of fuel up to
about 2000 rpm. At this speed starting equipment is switched off and only the generator is
made ready for synchronization with the grid. After synchronizations, the turbine load
29. 29
increases up to base load with more and more fuel entering the combustion chamber.
The hot gases after combustion enter the gas turbine at about 10050
C (at base load). The
higher pressure and temperature gas pass through the turbine rotating it and generator, this
produces the electrical power. The exhaust gas coming out of the GT is at about 5080
C. This
can be utilized to produce steam in WHRB.
4.1.2. GAS TURBINE SPECIFICATIONS: The exhaust gas turbine specifications are given
in table 4.1
TABLE 4.1 GAS TURBINE SPECIFICATIONS
manufacture SEIMENS(Germany); model-ABB 13D2
capacity 88.71 MW
compressor 18 stage
turbine 5 stages
burner Hybrid dual fuel
combustors SILO type
Air intake filters self cleaning(945 in numbers)
By pass take Vertical 25 m in height
Ambient
temperature 27 deg c
Ambient pressure 1013 Mbar
4.1.3 FEATURES OF ABB 13D2 TYPE GAS TURBINE:
1. A single shaft of welded construction.
2. Axial compressor of 18 stages with bleed valves after 3rd
, 6th
, 9th
stages for protection
against surging and also to reduce power required for start-up.
3. A single combustion chamber with a single burner. The combustion chamber is mounted
vertically on the turbine outer casing. The large size of the combustion chamber provides
easy access to inspection of its internals as well as approach to the turbine inner casing
30. 30
and first stage blades of turbine.
4. The burner is of dual fuel design and either gas, naphtha (or any
liquid fuel) or both can be fired.
5. Five stage axial turbine with axial exhaust for easy connection to a waste heat boiler. First
two stages of turbine blades are coated.
6. First 5 stage of compressor blades are coated to protect against corrosion due to humidity.
7. First 2 stages of turbine blades are coated against high temperature corrosion.
4.1.4 OTHER CHARACTERISTICS OF GAS TURBINE
1. The gas flow ducts must offer minimum hydraulic resistance.
2. The axial flow at exit from last stage of a gas turbine constitutes 150-200 mm/s and the
kinetic energy of the gases attain 10% of the total useful energy. To minimize losses an
exhaust diffuser is provided.
3. If the ratio of mid diameter of stage to blade height is less than or equal to 12 to14 twisted
blades are decided.
4. There is no extraction like in steam turbines hence the flow path is Simpler.
5. Along with use of high temp and heat resistant metals, various design techniques are
employed to reduce temperature levels and remove heat from the hottest elements in gas
turbines. As much as 15% of compressor discharge air is used for cooling of blades, rotors
and blade carrier etc.
6. First rows of blades are made hollow or have longitudinal bore holes for cooling. Non-
cooled blades are made solid and often have a thinned portion at the tip to minimize risk of
damage on contact with the turbine casing.
4.1.5 GENERAL DESCRIPTION OF GAS TURBINE
A gas turbine plant in its most simple form consists of following main part: -
Air intake system
Compressor
Combustion chamber
Turbine
Generator
Main bearing thrust bearing
31. 31
Oil pump: -main oil pump, auxiliary oil pump, hydraulic oil pump, recirculation oil pump,
DC emergency oil pump, jack oil pump, barring oil pump (ac/dc supply)
Naphtha fuel pump
Bleed valves 4 nos.
1. AIR INTAKE SYSTEM
The air flow radial inward through the filter elements then upward to clean air duct. The air
inlet connection has horizontal air inlet and situated axially in front of the compressor. There
are three horizontal floors in filter house each floor carry 315 filters. (Total filters are made of
synthetic and cellulose fibers, using resign impregnated.
2. COMPRESSOR
It is 18 stages compressor with additional inlet guide blades, axial flow and reaction
compressor. The blade of the 18 rotor and 19 fixed rows are made of high tensile ferric
chrome steel.
The compressor casing is horizontally split at axis, and is made of spherical graphite cast
iron. This material possesses high tensile strength and good expansion quality. Upper and
lower halves of the compressor casing are provided with robust flanges and are held together
by expansion studs with socket head. The compressor casing has three circular ducts at 4th
, 7th
and 10th
row of fixed blades.
fig. 4.2 : A 18 stages compressor
32. 32
These ducts are closed to the outside by four bleed valves. Bleed valves are kept open up to
2700 r.p.m, so that certain amount of compressor air can be blown off. These bleed valves
reduces the external power input required running compressor during start up and also during
reverse flows, they can ensure the safety of compressor.
3. COMBUSTION CHAMBER
In combustion chamber shown in figure 4.3, the air compressed and supplied by compressor
is brought to the required process temperature by combustion of liquid/gas fuel. The single
combustion chamber is fitted with only one duel fired burner and mounted vertically on the
compressor/turbine assembly. The combustion chamber is all welded steel plate fabricated.
The main parts are jacket with cover, lower upper combustion chamber bodies, finned
segment body, burner and inner casing.
fig.: -4.3 STANDERD SILO COMBITION CHAMBER
Combustion chamber jacket, which houses the components, is made of heat resistant, low
alloy ferrite steel. Finned segment body encloses the hottest zone of the combustion chamber.
33. 33
The air from the compressor enter the combustion chamber from below and flow upward
through the annular space between combustion chamber jacket and inner section of the lower
combustion chamber as shown in fig. 4.4
body. Approximately 30% air flow enter the combustion chamber through eight mixing
nozzles provided at the lower body as secondary air and approximately30% air flow enter the
combustion chamber through upper body via finned segment row (there are 5 rows). The
remaining 40% flow as primary air for combustion, into the swirl insert and enter the
combustion space with turbulence. After the fuel has ignited these gases are thoroughly
mixed with secondary air from mixing nozzles and brought to the permissible turbine inlet
temp.
fig:-4.4 COMBUSTION CHAMBER
The inner casing guides the hot gases coming from combustion chamber to the turbine
balding. It is thin welled construction made of heat resistant chrome-nickel austenitic alloy.
4. TURBINE
There are 5 reaction stages in our gas turbine. Due to high temperature of incoming gases, the
first and second row of rotor and fixed blading are air cooled with air from compressor
34. 34
discharge. The cooling air is fed to the first & second row of fixed blades through holes
drilled in the blade carrier and to the first & second row of rotor blades through hole drilled in
shaft, cooling air passes along several holes made in blades and finally blowing out through
numbers of slits in the trailing/leading edge of the blade. This method of cooling ensures that
blades are thoroughly cooled, thereby avoiding cracks induced by thermal stresses. These
cooled blades are fixed rotor blades of other rows are made of cast in nickel based alloy. The
fourth and fifth row of rotor blades fifth row of fixed blades are drop forged. Turbine outer
casing is split into two halves like compressor casing. The turbine and compressor casing are
bolted together at radial flange with expansion bolts; turbine casing is made of heat resisting
ferrite steel in order to with stand thermal stresses. The blade carrier for turbine fixed blades
is made of ferrite steel alloy casting.
5. GENERATOR
Generator is three phase, two pole air cooled machine. The generator and turbine are placed
on common and plain concrete foundation, with same centre line level for the turbine and
generator rotor.
The mechanical energy generated by turbine is converted to electrical energy by the generator
and appear in the stator winding in the form of current and voltage.
It lead the magnetic flux, and carries the field winding, the generator is self excited. The
power required for the excitation is taken from the generator term finals and fed to the field
winding through the excitation transformer and the thyristor-controlled rectifier units.
6. FUEL SYSTEM GAS
Gas comes from Gas Reducing Station at around 18 bars. Manual isolation valve is to be
opened by operator. Motorized stop relief valve will be opened by GT program, when this
valve is depressurized. When valve opens, the relief port is closed. In the gas control block
there is an emergency stop valve (ESV). This opens with the help of power oil pressure
against spring force. Whenever, turbine trip the oil is drained (depressurized) and spray force
closes the valve, cutting off gas supply to combustion chamber.
After the ESV, the gas CV controls the flow of gas. The opening of this valve controls the
amount of fuel going to the combustion chamber.
35. 35
7. FUEL SYSTEM NAPHTHA
Naphtha comes from naphtha station via the forwarding pumps as shown in fig.4.5at around
15bar. Manual isolation valve outside GT hall is to be opened by the operator. Manual
isolation valves before main fuel oil pump are also to be opened. Motorized valve will be
opened by GT program when functional group liquid fuel is selected. Naphtha then passes
through duplex filter to the main fuel oil pump, which raises the press to approx. 80 bar.
There is release valve which opens when firing speed is reached (600rpm).
fig 4.5: Pipelines of gas source
There is an emergency stop valve similar to one in the gas scheme. Finally there is the control
valve directly coupled with the Naphtha nozzle. A minimum opening of the nozzle is already
pre-set. Once stable flame is formed then nozzle opening increases with the control valve
opening.
8. OIL PUMPS
1. OIL SUPPLY
A single oil supply line shown in fig. 4.6 lubricates and cools the bearing, governs the m/c
and operates the hydraulic actuators and safety and protective devices.
During start-up & shut-down, aux oil pump supplies the control oil. Once the turbine speed is
36. 36
more than 2850 rpm, the main oil pump (M.O.P) takes over. It draws oil from main tank. The
lubricating oil passes through oil cooler, before can be supplied to the bearing (Under
emergency, lube oil can be supplied by a DC oil pump). Before the turbine is turned or
barred, Jacking oil pump (2 nos.) supplies high pressure oil to the jack up the TG shaft to
prevent boundary lubrication and also supplies high pressure oil to drive the hydraulic motor
(turning gear).
fig. 4.6: Oil system overview
2. Turbine lubricating oil system
Function:
1. Provides a supply of oil to journal bearings to give an oil wedge as the shaft rotates.
2. Maintains the temperature of turbine bearings constant at the required level.
3. Provides a medium for hydraulically operating the governor gear and controlling steam
admission valve.
4. Provides for hydrogen cooled generators a sealing medium to
prevent hydrogen leaking out along the shaft.
3. Main components
1) Main Oil Pump
2) Auxiliary Oil Pump
3) Emergency Oil Pump
4) Jacking Oil Pump
37. 37
5) Main Oil Tank (MOT)
6) Overhung Centrifugal pump
3.1. Main Oil Pump
This pump is located at the front bearing pedestal of the HP turbine.
It is coupled to the turbine rotor through a gear coupling.
When the turbine is running at a normal speed of 3000rpm, then the desired quantity of oil
to the governing systems and the lubrication systems is supplied by this pump.
3.2. Auxiliary Oil Pump
Auxiliary Oil Pump can meet the requirements of lubrication system under emergency
conditions
One stage vertical centrifugal pump driven by an A.C. electric
motor.
It has radial impeller and volute casing.
The pump automatically takes over under interlock action
whenever the oil pressure in the lubrication system fails below
certain desired level.
3.3 Emergency Oil Pump
Emergency oil pump has been foreseen by as a back-up
protection to AC driven standby oil pump.
This is a centrifugal pump, driven by DC electric motor.
This automatically cuts in whenever there is a failure of AC
supply at power station
3.4 Jacking Oil Pump:
JOP ensures that there is no metal contact between a journal
and the bearing.
Positive displacement pumps that provide high pressure supply
of oil under strategic journals of the turbo generator and oil lifts
the shaft slightly.
This greatly reduces the static friction and bearing wear.
The JOP can be stopped after the lubricating oil film is
established between the shaft and bearings.
Pressure produced is 120 bars
3.5. Main oil tank
The oil used for lubrication is stored in the Mai Oil Tank.
Capacity -20/32 m3.
The Main Oil Tank holds the oil inside the tank for a period long
enough to ensure liberation of air from the oil.
38. 38
Filters are located inside the tank to filter the oil during its
normal course.
The oil tank is supported on a framed structure just below the
turbine floor at the left-hand side of the turbine.
4.2 STEAM TURBINE UNIT:
4.2.1 INTRODUCTION
A steam turbine is a prime mover in which rotary motion is obtained by gradual change of
momentum of the steam. In a steam turbine, the force exerted on the blades is due the
velocity of steam. This is due to the fact that the curved blades by changing the direction of
steam receive a force or impulse. The dynamical pressure of steam rotates the blades directly.
The turbine blades are curved in such a way that steam directed upon them enters without
shock.
The steam turbine essentially consists of following two parts.
The nozzle in which the heat energy of high pressure steam is converted into K.E., so that the
steam issues from the nozzle with a very high velocity.
The blade which changes the direction of steam issuing from the nozzle, so that a force acts
on the blades due to the change of momentum and propel them.
fig. 4.7: A steam turbine
39. 39
The two basic types of steam turbines are described below.
1. Impulse Turbine
In Impulse turbine steam expands in fixed nozzles. The high velocity steam from nozzles
does work on moving blades, which causes the shaft to rotate. The essential features of
impulse turbine are that all pressure drop occur in nozzle and not on blade.
2. Reaction Turbine
In this type, pressure is reduced at both fixed and moving blades. Both blades act like
nozzles. The expansion of steam
Figure 4.8 Schematic diagram summarising the differences between impulse turbine
and reaction turbine
4.2.2. Basic parts of Steam Turbine:
1. H.P. Turbine:
It is a single flow type turbine, with horizontal split casing and double shell. The provision of
steam inlet temperature and high pressure to admission section is subjected only to low
temperature and pressure and pressure effective at the exhaust of the turbine. The high
pressure turbine is provided with two main stop and control valves to check and regulate the
entry of the steam in to casing
2. L.P. Turbine:
it is a three cell design and has a double flow system for max efficiency. The inner casing
caries the first row of stationary blades and is supported on the outer casing so as to allow for
thermal expansion. The middle casing rest on four girders, independent of the outer casing.
The LP turbine is provided with two control valves.
40. 40
3. Bearing:
The HP rotor is supported on two bearings, a combined journal bearing close to the coupling
with LP rotor. The LP journal bearing at its end. The bearing pedestals are anchored to the
foundation and are fixed in position.
4.Turbine Shaft & Moving Blades:
The rotor shaft transmits the torque generated by the change of momentum of steam. Turbine
shaft or rotor holds turbine blades. The moving blades are used to convert kinetic energy of
steam into driving force of the shaft. Shrouding are provided at the last stage of turbine blades
to avoid vibration due to long length of blades. In impulse turbine moving blades change the
momentum of steam to generate torque. No pressure / temperature drop occurs while passing
through moving blades of Impulse Turbine. Impulse blades are compact, heavy and robust. In
reaction turbine driving force is generated by reaction force of steam as it accelerates through
the moving blades. In this turbine pressure drops both in the nozzles / fixed blades as well as
in the moving blades since shape of the moving blade channels are also nozzle shaped. Due to
the expansion of steam while flowing through the blades, there is an increase of kinetic
energy, which gives rise to reaction in the opposite direction (Newton’s third law of motion).
Blades rotate due to both impulse effect of the jets (due to change in momentum) and the
reaction force of the exiting jets impressed on the blades in the opposite direction. Such
turbines are called impulse-reaction turbines, or to distinguish from impulse turbine, simply
reaction turbines.
5.Outer Casing:
It is the stationary part of the turbine. It holds the fixed blades/ diaphragm of the turbine.
Casing may be singles hell or double shell. Metal thickness of single shell casing is high to
withstand the temperature difference of steam inlet temperature and atmospheric temperature
210 MW LMW turbine is of single shell type. To reduce metal thickness high pressure
turbines are made of double casings. Each casing is designed to withstand relatively low
temperature difference. This reduces metal thickness. 210 MW KWU turbines are made of
double shell type.
6.Fixed Blades:
The fixed blades convert heat energy of steam into kinetic energy. The first stage of HP
impulse turbine fixed blades is nozzles shaped to perform as nozzles. Steam pressure drop
takes place in these nozzles. In reaction turbine small amount of heat drop takes place in each
stage, hence size of each stage is smaller than of impulse turbine and no. of stages is high.
One pair of fixed blade and rotating blade forms a stage of turbine.
7.Turbine bearing to support rotor
A turbine rotor is supported by two radial bearings, one on each end of the steam cylinder.
These bearings must be accurately aligned to maintain the close clearance between the shaft
and the shaft seals, and between the rotor and the casing. If excessive bearing wear lowers the
he rotor, great harm can be done to the turbine. Thrust bearings keep the rotor in its correct
axial position.
41. 41
8.Stop and Control Valve
Two Emergency Stop Valves (ESV) are provided for 500MW turbine. These valves are of
full open or full close type and are operated by control oil pressure. There are six control
valves through which steam is entering in the turbine. Three control valves are mounted on
top of HP cylinder and three at the bottom.
9. Barring gear
The steam turbine set is provided with an automatic barring gear capable of continuously
rotating the turbine shaft at 5.4 rpm to affect uniform cooling and warming up during shut
down and start up respectively. It is meshed with AC motor and rotates turbine rotor through
gear train.
4.2.3 specifications of steam turbine: Specifications of HP Turbine and LP turbines are shown
below in table 4.2 and 4.3
Table 4.2 Specifications of HP Turbine
TYPE Single flow
No. of stages 25 reaction stages
Total H.P main steam pressure 76.4 bar
HP main steam temp. 528 deg c
HPT exhaust pressure 5.1 bar
HPT exhaust temp. 175 deg
Table 4.3Specifications of LP Turbine
Type Double flow
No. Of stages 7 reaction stages
Total LP steam flow 46 T/hr
LP main steam pressure 4.38 bar
4.2.3. Working of steam turbine:
The HP steam is fed to the HP section of the steam turbine. The steam passes through the
stop and control valves of the HP turbine and enters the inner casing. On entering the inner
42. 42
casing the steam after leaving the HP turbine gets converted into LP steam. This LP steam
produced at the WHRSG is passed into the inlet of the double flow LP turbine. On entering
the steam once again expands and due to the combined effect of HP&LP rotors, the generator
rotor also rotated and electricity is produced.
fig.4.9 Main turbine
The two outlet of the LP turbine are connected to the condenser where water and steam
mixture are connected into water for further use in the WHRSG.
4.2.4 Maintenance of steam turbine
Steam turbine generators are reliable machines, and often operate continuously for many
months. Such operation at steady outputs can lead to deposition from the steam on the fixed
and moving blades. Deposits cause output and efficiency to drop, by reducing the efficiency
of energy transfer and eventually restricting steam flow. This occurs less on sets which vary
in load, as they undergo a regular blade washing effect.
In Table 5.1, the main wears out problems with steam turbines are summarized, together with
an outline of how condition monitoring can detect them.
Table 4.4 wears out problems with steam turbines and how condition monitoring can detect them
Part Affected Wear out problem Comments, suitable
condition monitoring
Blading Erosion by solid
particles (also erosion
by water droplets on
Usually occurs gradually,
worst at inlet blading. Less
usual on sets with drum
43. 43
latter LP blades boilers and/or sub- 44 critical
inlet steam conditions, or
with bypass systems.
Performance analysis detects
Blading Parts breaking off Usually sudden. Vibration
analysis detects.
Bearings Scoring damage to
white metal
Performance analysis,
vibration analysis, wear
particles in oil
Rotors Rubbing, temporary
unbalance, cracking,
misalignment
Vibration analysis, and
offline, some NDT
Valve spindles
shaft and
interstage glands
(seals), casing
joints LP manhole
gaskets Internal
steam piping and
fittings
Leakage due to wear,
distortion, breakage
Likely to occur gradually, but
can be sudden. Performance
analysis detects. Effect of
seal water is relatively
greater for HP blading. For
impulse machines, the
relative lost output for each
25m increase above design
clearance of about 600 m is:
HP: blade tips, 5KW;
interstage seals, 6KW per
stage; end glands 15 to
25KW.
IP: blade tips, 2.5KW;
interstage 2KW per stage;
end glands 5KW LP: blade
tips and interstage, 1.5KW
per stage; end glands 2KW.
For reaction blading, the
effect will be greater
44. 44
Steam valve
strainers, valves
spindles,
Deposits Likely to occur gradually,
mostly in areas around
260ºC. Some on load blade
washing occurs with forced
steam cooling. Performance
analysis detects. Blade
surface roughness has
biggest effect at higher
steam pressures. One case
gave 17% drop in output
Generator rotor,
stator
Insulation faults Electrical plant testing
several techniques
Condenser Air in leakage Tube
fouling
Performance analysis
Feedwater heaters Air in leakage, tube
fouling by scale or oil
Performance analysis
Valves- HP, IP
bypass
Leakage Performance analysis.
Acoustic leakage detection is
also possible
4.3 ADVANTAGES OF GAS TURBINE OVER STEAM TURBINE
1. Gas turbine is more compact. There is no boiler or condenser. Auxiliaries are very few.
2. They can be started and loaded very quickly (within 20 minute form cold start to full load)
3. Gas turbines are simpler in maintenance and designs.
4. Gas turbine plants involve less metal and material.
5. They are lower in cost for installation capacity.
6. Gas turbines don’t require enormous quantities of cooling water as in steam turbines.
4.4 DISADVANTAGES
1. Gas turbines have lower specific power.
2. They have lower efficiency.
3. Gas turbines have shorter service life.
4. They are very sensitive to fuel quality.
45. 45
CHAPTER-5
Waste Heat Recovery Boiler
5.1 INTRODUCTION: -
A boiler is a closed vessel in which steam is produced from water by combustion of fuel.
Classification of boilers: -
Horizontal, vertical and inclined.
Fire tube and water tube.
5.2 Waste Heat Recovery Boiler
Wagner-biro supplied boilers for anta combined cycle power plant known as waste heat
recovery boilers (WHRB) shown in fig. 5.1, which are of non-fired, dual pressure, forced
circulation type. The boiler has two different water/steam cycles known as high pressure
system and low pressure system. Each system has its own boiler drum and circulating pumps,
and is feed by HP & LP feed water pumps from a common feed water tank.
fig: -5.1 WASTE HEAT RECOVERY BOILER
46. 46
The pressure and temperature of high pressure super heated steam is 64 bar and 4900
C and
that of LP 6 bar and2060
C.
The HP & LP steam from the three boiler from four common headers HP live steam line, HP
bypass line, LP live steam line and LP bypass line, the bypass line dump steam in the
condenser through the HP and LP bypass system. The HP steam drives the HP steam turbine
through stop valves and control valves. The LP steam after passing through stop valves and
control valves mixes with the HP turbine exhaust and drivers the gas turbine. This dual
system of operating utilizes the waste heat from the gas turbine with maximum efficiency.
From LP turbine steam enters the condenser where it get condensed to water with the help of
cooling water. Condenser is shell and tube, water flow through the tubes and steam flow out
side. The condensate get collected in hot well, from hot well it enters the feed water tank
through condensate extraction pump (3*50%).
Each of the WHRB is feed with waste heat flue gas from the respective gas turbine (GT). The
gas turbines are fired either with gas or naphtha. The flue gas temp. At boiler inlet is about
5000
C depending on GT load and outside temp. Conditions. The flue gas temp. At boiler
outlet is about 110c-140c to avoid cold end corrosion. During WHRB operation the flue gas
is led through a horizontal duct with integrated silencer to diverter damper of the WHRB.
There are two positions of diverter damper one open to the boiler and another is open to
bypass stack. The energy from waste heat flue gas is transferred to water/steam by means of
heating surfaces of super heaters, evaporators, economizers and condensate preheater. The
heating surface of each boiler is about 96000 m2
. The heating surfaces in staggered
arrangement are manufactured as finned tubes arranged horizontally and installed in vertical
duct supported by tube plates.
5.3 VARIOUS ACCESSORIES USED IN (WHRB) ARE: -
1.SUPERHEATER- Super heater as shown in figure 5.2 is used to raise the temperature of
steam above the saturation temperature by absorbing the heat from flue gases which are
coming from the diffuser. Superheated steam has the following advantages: -
Steam consumption of the turbine is reduced.
Erosion of turbine blade is eliminated.
47. 47
Efficiency of steam plant is increased.
fig: -5.2 schematic diagram of a super heater
2. EVAPORATOR- An evaporator is the component of a refrigeration system and is used to
extract heat from the chamber is to be kept at low temperature. The refrigerating liquid enters
the evaporator, absorbs latent heat from the chamber at constant pressure and comes out as a
vapor.
3. ECONOMIZER-The function of an economizer shown in fig. 5.3 in a steam generating
unit is to absorb heat from the flue gases and add this as sensible heat to the feed water before
the water enters the evaporative circuit to the boiler.
Advantages of economizer: -
The temperature between various parts of boiler is reduced which result in reduction of
stresses due to unequal expansion.
Evaporative capacity of the boiler is increased.
Overall efficiency of the plant is increased.
48. 48
fig: -5.3 schematic diagram of a ECONOMIZER
4. AIR PREHEATER- An air preheater shown in figure 5.4 is used to recover heat from
flue gases. It is installed between the chimney and economizer.
It absorbs waste heat from the flue gases and transfers this heat to the incoming cold air, by
means of continuously rotating heat transfer element of specially formed metal plates. Sloped
compartments of a radially divided cylindrical shell called the rotor.
The housing surrounding the rotor is provided with duct connecting both the ends and is
ade7uately scaled by radial and circumferential scaling.
fig 5.4 An air preheater
49. 49
5. DEAERATOR- It is used to remove air from water as air carries oxygen which is
corrosive in nature so to protect the various parts of boiler from corrosion. We add the
hydrazine (NH2=NH2) in to the water which react with O2 and makes the pure water.
fig. 5.5 A deaerator
6. DESUPERHEATOR- It is used keep the temp. Of superheated steam constant. By
spraying of some amount of water over the superheated steam, we can decrease the temp. of
steam to keep it at constant temp. About 5250
C.
fig 5.6 A desuperheater
50. 50
5.4 WHRB-SPECIFICATION
Registration No. : RJ-661-RJ 666
Constructor’s Name and Address : Wagner-Biro AG
Graz-Vienna, Austria
Manufactured For : National Thermal Power
Corporation (NTPC)
Contract No. : 01/CC/9505-001-01-1505
Type of Boiler : Forced Circulation
Overall Dimension of flue gas path : Width: 6, 4 m
Length: 18, 5 m
Height:28,0 m
Design parameters:
DESIGN DATA: HP-Part LP-Part Cond. rec.
Design Pressure: 83 bar (g) 9 bar (g) 15 bar (g)
Intended working
Pressure:
73 bar (g) 5.5 bar (g) 11 bar (g)
51. 51
mass flow of Steam and condensate 162, 6 t/h 39, 1 t/h 56 t/h
Firing : Unfired –waste Heat temperature maz. 5270C
Final temp. Of steam : 488/5010C 2070C 1600C
Total Heating surface:
Year of Manufacture : 1988
Brief description of boiler : Waste heat recovery boiler with separate High and Low Pressure
system as well as Condensate preheating, horizontally arranged finned
tubes (except LP-Super heater)
5.5 Maintenance of WHRB: A boiler efficiency improvement program must include two
aspects:
I. Action to bring the boiler to peak efficiency
II. Action to maintain the efficiency at the maximum level.
Good maintenance and efficiency start with having a working knowledge of the components
associated with the boiler, keeping records, etc., and end with cleaning heat transfer surfaces,
adjusting the air-to-fuel ratio, etc.
General requirements for safe and efficient Boiler room
1. equipment, controls, safety devices, and up-to-date operating procedures.
2. Before start-up, ensure that the boiler room is free of all potentially dangerous situations, like
flammable materials, mechanical, or physical damage to the boiler or related equipment.
Clear intakes and exhaust vents; check for deterioration and possible leaks.
3. Ensure a thorough inspection by a properly qualified inspector.
4. After any extensive repair or new installation of equipment, make sure a qualified boiler
inspector re-inspects the entire system.
5. Monitor all new equipment closely until safety and efficiency are demonstrated.
Water tubes: 59910m2 23859m2 6715m2
Super heater
Tubes
8990 m2
584 m2 -
52. 52
6. Use boiler operating log sheets, maintenance records, and manufacturer’s recommendations
to establish a preventive maintenance schedule based on operating conditions, past
maintenance, repair, and replacement that were performed on the equipment.
7. Establish a checklist for proper start up and shutdown of boilers and all related equipment
according to manufacturer’s recommendations.
8. Observe equipment extensively before allowing an automating operation system to be used
with minimal supervision.
9. .Keep the boiler room clean and clear of all unnecessary items. The boiler room should not be
considered an all-purpose storage area. The burner requires proper air circulation in order to
prevent incomplete fuel combustion. Use boiler operating log sheets, maintenance records,
and the production of carbon monoxide. The boiler room is for the boiler.
53. 53
Conclusion
I have studied about the power plant. Especially in ANTA. Studied about gas power plant.
Especially natural gas could be used for power generation in gas power plant. It is very
economical but less efficient. Mainly methane (CH4) is used as fuel. It is very profitable in
case of pollution. It is very less polluted. At place of fuel naphtha is used in alternate form.
But it is very costly and polluted. So it is used in very few shortages. This is very profitable
plant because it has combined cycle plant. According to combined cycle plant less
temperature gas will be recycled and used for generation of power. ANTA gas power plant
has four units in which three gas units and one steam unit. ANTA gas power plant has more
plants for reduction for pollution approximately 1.8 lakhs trees.
54. 54
REFEREENCES & BIBLIOGRAPHY
1. http://en.wikipedia.org/wiki/boiler.
2. http://en.google.com/images/Turbine.
3. www.ntpc.co.in
4. http://baran.nic.in/industries.htm
5. http://forhealthy.com//7364-ntpc-anta-plant-information.html
6. http://en.wikipedia.org/wiki/National_Thermal_Power_Corporat.
7. http://www.educypedia.be/education/physicsjavalaboenergy.htm
8. http://www.instrumentationengineers.org/2013/06/working-principle-of-impulse-
turbines.html
9. Bolaji and Emeka, R. 2014. Operation and Maintenance Schedule of a Steam
Turbine Plant in Lappeenranta, Masters Thesis, Saimaa University of Applied
Sciences. 99p