SlideShare a Scribd company logo
THE IMPACT OF OFFSHORE PIPELINE INSTALLATION AND PRE-
COMMISSIONING ON FUTURE SYSTEM INTEGRITY
J. L. Grover
BJ Process and Pipeline Services, Dubai
ABSTRACT
Operators of offshore pipelines focus on the integrity of the system once commissioned, normally using internal
corrosion rates as the key measure of remaining life.
Such operators, who focus on pipeline integrity management and intelligent pigging throughout the life of the asset, pay
less attention to the asset during the installation and pre-commissioning of offshore pipelines, often entrusting this
activity to the installation contractor.
In this paper we draw on over 30 years of experience in pre-commissioning offshore pipelines to examine some of the
common mistakes and oversights in the areas of:
 Pipe spool storage and preservation
 Prevention of seawater ingress during lay
 Wet buckle impact and possible contingencies
 Pre-operational cleaning
 Source and treatment of hydrotest water
 Dewatering and drying
For each of the above we assess how the activity can affect the overall integrity of the pipeline and what steps can be
taken to minimize any adverse risk.
The objective of the paper is to raise the awareness amongst offshore pipeline operators of the impact installation and
pre-commissioning can have on operational pipeline integrity.
INTRODUCTION
Offshore pipelines are designed with an internal
corrosion allowance based on the proposed design life
of the pipeline and associated field. This may be
anywhere between 10 and 30 years. The pipeline
design contractor will consider a variety of factors in
predicting the likely pipeline internal corrosion rate
including product composition and likely composition
during the field life, presence of CO2, H2S, or water in
the product to be transported, whether the product will
be treated with a corrosion inhibitor and whether the
pipeline will be pigged on a regular basis.
What will not be considered in the corrosion allowance
will be corrosion occurring during the storage,
installation, and commissioning of the pipeline. In part
1 of this paper examples of newly laid pipelines are
illustrated where internal metal loss of 30%WT has
been recorded prior to start up.
Furthermore the facilities downstream of the pipeline
will be designed to accept the product in the pipeline
generally without consideration for the entrainment of
any materials remaining in the pipeline.
There are many occurances where debris remains in the
line after construction, or fine particles slough off the
pipeline wall during service, often referred to as “black
powder”.
In part 2 of this paper we will see examples of
pipelines which have been cleaned during pre-
commissioning to an agreed specification, and yet have
produced up to 50 tonnes of powder on start up,
damaging filters, shutting down the receiving facilities,
and eroding internal components such as control
valves.
PART 1 – CORROSION CAUSED DURING
INSTALLATION & PRE-COMMISSIONING
Cause
From leaving the pipe mill to commencing service each
pipeline joint will be exposed to many situations where
corrosion can occur including:
1. End protectors not fitted, or removed during
the pipe coating process
2. Pipe joints stored close to the sea, or on the
lay barge without end protectors fitted
3. Pipeline suffers a wet buckle or rupture during
installation allowing raw dewater to enter the
pipeline
4. Water used to flood and hydrotest the pipeline
is not correctly filtered or dosed with the
correct chemicals to prevent corrosion
5. Pipeline hydrotest water remains in the
pipeline beyond the life of the corrosion
inhibition chemicals
6. Hydrotest water is not adequately removed
from the pipeline by dewatering
Effect
Each of the above, or a combination thereof, can cause
internal corrosion (fig. 1) to occur on the pipe wall.
This effect is greatly mitigated by internally coating
the pipe joints prior to installation. The resulting
corrosion adversely impacts the time required to dry
the pipeline – in the line detailed in the first case
study, drying time increased 100% due to trapped
water from poor surface condition. Once the line is in
service, this fine corrosion sloughs off causing
operational difficulties as detailed in the second case
study.
Measurement
Many pipeline operators have recognised the benefit of
performing a baseline corrosion, or metal loss survey
on newly installed pipelines. Such a survey can either
be run during one of the pre-commissioning pigging
trains, or in the pipeline product immediately after the
line is put into production. Both USWM and MFL
tools can be used for this purpose, however MFL tools
are generally used due to cost, and future data
matching requirements.
It is generally accepted that such a baseline survey
should be performed as early as possible if the cause of
any internal corrosion (fig. 2) is to be accurately
attributed – there have been examples of newly
installed pipelines having 50%WT internal wall loss
within 18 months of start up which are then attributed
to product related corrosion. Obtaining such data
during, or immediately after pre-commissioning, may
allow for claims to be made, or potential losses
recovered from the project insurance.
In addition to ILI tools it is possible to measure riser
and topside corrosion using video inspection and
external UT inspection techniques. External UT can be
applied subsea but applications are limited on buried
lines or those that have a concrete weight coat fitted.
Figure 1 – Internal corrosion
Figure 2 – Pitting corrosion @ 6 o’clock
Mitigation
The following table summarises possible steps to mitigate the corrosion risks detailed above:
CORROSION RISK MITIGATION MEASURE
Corrosion during storage,
shipping and coating process
Fit end protectors, and use vapour phase corrosion inhibitor or nitrogen blanket to
preserve a non-corrosive atmosphere in each spool. Thoroughly clean each spool
using a mechanical brush system immediately prior to welding.
Free flooding with raw seawater
due to wet buckle
Ensure an emergency dewatering spread is available to quickly dewater the line
should a wet buckle occur causing the line to free flood
Water used to flood the line not
correctly filtered or chemically
treated
At the planning stage have a pre-commissioning specialist review the project
specifications for applicability. Take samples of seawater at the filling point to assess
suspended solids. Seek advice from the production chemical companies on the best
treatment chemicals and dosing rates.
Many projects specify a filtration level of 50µ but without any acceptance criteria on
suspended solids per unit volume. Some projects are now specifying a maximum
allowable level of suspended solids of 20g/m3
.
At the execution phase employ an independent representative to check the size and
efficacy of the fill water filtration used, and also the actual chemical dosing rates. In
addition analyse regular samples of the flooding water to check for quantity and size
distribution of suspended solids.
Pipeline hydrotest water
remains in the line beyond the
effective life of the chemicals
Often a pipeline may be “laid up” for a fixed period between the completion of
hydrotesting and the commencement of dewatering / commissioning. Where this
period extends beyond theoriginal planned duration, the chemical protection may not
be adequate.
Such an event needs to be recorded and the hydrotest water displaced with a fresh
batch of water, suitably treated for the revised lay up period.
Hydrotest water is not
adequately removed from the
pipeline by dewatering
A thorough pipeline dewatering operation should leave a water film in the pipe of
approx. 0.1mm for uncoated pipe and 0.07mm for internally coated pipe. In some
applications it is possible to measure the volume of water removed from the line
using flow meters.
A desalination slug forms part of the pig train suitably sized to dilute the residual
seawater – typically this is 4% of the line volume with acceptance criteria of a final
chloride content of below 200ppm.
If there is a delay between dewatering and subsequent swabbing / drying /
commissioning, the remaining water film will drain down to the bottom of the line
and collect at any low points. If this residual water has not been suitably desalinated
it can pose an additional corrosion risk.
Table 1 – Corrosion causes and mitigation measures
Case Study 1 – Wet Buckle
Due to confidentiality, the pipeline details below are
fictitious, however the engineering calculations and
outcomes are factual.
A 36” x 350km offshore gas transmission line suffered
a wet buckle during pipelay causing the line to free
flood with raw seawater at the buckle point when
approx. 160km of the line had been laid. The main
section of the line was 14.3mm WT. The pipe was free
flooded with seawater for 3 months. When fully
immersed in seawater, steel will corrode at a
remarkably steady rate to produce the oxide Fe2O3
(haematite) or Fe3O4 (magnetite). The corrosion is very
rapid initially, but falls off gradually over several
months to a fairly steady rate (Table 2).
Table 2 – General corrosion rates for steel in tropical
seawater.
It should be noted that these rates are for general
corrosion and not pitting corrosion. Pitting corrosion
rates are generally quoted as several orders of
magnitude higher than the average rate.
In this corrosion event, it is has been assumed that the
seawater is not stagnant and that there is a continuous
supply of fresh corrodant to the steel surface. In
addition, it has been assumed that the mill scale, and
the corrosion product from the first corrosion event
have formed a semi-protective coating on the steel
surface. Therefore a corrosion rate of 0.13mm/year has
been selected as representative of the average corrosion
rate during this event (see references below). No
pitting corrosion has been considered.
Therefore, assuming a corrosion rate of 0.13mm/yr
over a three month period the wall thickness loss for
the 150km pipeline will be d=0.00325cm. The volume
of metal loss is given by:
Volume = Area x Length
Volume = 2..r.d x L
In this equation r is the internal radius of the pipe =
44.3cm, taking the diameter of the pipe to be 91.4cm
and the wall thickness to be 1.43 cm. The total volume
of metal loss is:
Volume = 2 x 3.14 x 44.3 x 0.00325 x 161000 x 100 =
1.5 x 107
cm3
The mass of iron lost is therefore:
Mass = Fe x Volume
If the density of
iron (Fe) = 7.8
g/cm3
then the total
mass of iron lost =
1.1 x 108
g. The
total number of
moles of iron
consumed in the
reaction is given by
the equation:
RAM
Mass
Moles 
Where RAM = Relative Atomic Mass and RAMFe = 56
g/mol therefore MolesFe= 2.0 x 106
moles.
The equation for the reaction of iron in seawater is:
Therefore the total amount to oxide formed from 2.0 x
106
moles of iron is 6.8 x 105
moles. The total weight
of oxide is given by
Mass = Moles x RMM
Where the Relative Molecular Mass (RMM) of Fe3O4
= 232 g/mol. Therefore the total mass of iron oxide
formed in this reaction is approximately 157,000 kg
(157 tonnes).
This pipeline was then subject to a baseline MFL
survey where the impact of this corrosion was noted in
a number of ways.
 Hard bed of debris at 6 o’clock position
masking pipe wall
 Internal corrosion measured up to 35% WT
 Blockage of filters from excessive debris
removed during the pigging operation
Exposure
Time
(months)
Average
corrosion rate
(mm/year)
1 0.33
2 0.25
3 0.19
6 0.15
12 0.13
24 0.11
48 0.11
r
Area of
metal loss
lloss
d
432 OFeO2Fe3 
Prior to the MFL survey being performed, a number of
standard cleaning pigs were run through the line by the
MFL vendor to remove debris from the pipeline. Due
to the internal corrosion caused by the wet buckle, and
the large amount of dust formed on the pipe wall,
these pigs suffered severe wear (fig. 3) and recovered
very little debris from the line. It can be seen that the
front of the pig is more heavily worn than the rear
caused by the pig “nose diving”
Subsequently an MFL tool was run in the line (fig. 4).
Such tools are fitted with high powered magnets and
strong brushes to magnetise the pipe wall – as such
these tools make highly effective pipeline cleaners.
During this first run nearly 20,000kg of fine powder
was recovered from the pig receiver, and all external
components of the MFL tool were badly worn or
damaged.
After repeated cleaning runs over 80 tonnes of ferrous
debris was removed from the pipeline before a
successful MFL run could be performed. This was in
addition to the estimated 40 tonnes removed during
pre-commissioning, and 20 to 30 tonnes removed from
filters downstream of the pig receiver. The results of
the MFL run endorsed the calculated corrosion rates
shown previously – the deepest internal defects were
greater than 35% WT with a large population of > 20%
WT shown in the area immediately downstream of the
wet buckle area. In total over 100,000 metal loss
defects were identified.
PART 2 – DEBRIS FROM INSTALLATION AND
PRE-COMMISSIONING
Cause
During the installation of an offshore pipeline it is
reasonable to expect that very little debris should enter
the pipeline, certainly far less than for an onshore
pipeline. Also a prudent installation contactor will
employ a system to manually brush the internal surface
of each pipe joint as it is welded to the pipe string.
However offshore pipelines often feature a landfall
section, or short onshore section at each end where
there is a greater risk of debris entering the line. Some
examples of debris recovered from offshore pipelines
during pre-commissioning include:
 Welding rods (fig. 5), welding bladders, hand
tools, and shims used to secure bevel
protectors to the pipe joint etc.
 Sand and soil introduced into the pipeline
either via the onshore / landfall pipelay, or in
the water used to flood and test the pipeline
 Naturally occurring seawater borne debris
below the project filtration levels such as shell
particles
Effect
During the pre-commissioning phase such debris has
an adverse effect on pig wear and hence efficacy of the
cleaning and filling pigs.
Where debris builds up in one location it can cause
damage to a gauge plate and can show as a dent during
a calliper inspection. This can then lead to delays and
possible expenditure trying to locate a dent or
restriction that does not actually exist – if this is post
rock dumping it may be impossible to inspect the line to
verify the presence of a dent.
Fine debris, such as particles below 50µ in size tend to
settle at the bottom of the pipeline (fig. 6) during
hydrotesting, and are very difficult to remove during
subsequent dewatering. Once settled this debris can
form a crust trapping water, which can adversely
affect the drying of the line.
Figure 3 – Worn cleaning pig
Figure 4 – MFL tool
Figure 5 – Welding rods on cleaning pig
Figure 6 – Fine debris removed by cleaning pig
Once the line goes into production (for dry gas lines)
this debris slowly dries out and sloughs off into the
gas stream as powder (fig. 7) causing downstream
problems with valves and filters (fig. 8).
There are also examples where this debris crust does
not slough off and remains at the bottom of the line –
affecting the efficacy of MFL inspections by masking
part of the pipeline to be inspected and causing the
MFL sensors to lift off. Such debris is often referred
to as “black powder” however it is actually an oxide
and ferrous in nature and may be mixed with fine rust
from the pipe wall.
Measurement
The debris removed during initial cleaning can be
measured by physically weighing the debris, or
analysing the suspended solids in the fill water. The
trending of samples taken between pigs in a filling and
cleaning pig train gives a good picture of the efficacy
of the cleaning process and provides data to
demonstrate compliance with the specification or
relevant standard. Where a debris pick-up gel is used
in the pre-commissioning process it is far easier to
measure the trend of debris removed from the pipeline
(fig. 9), and hence assert how much debris remains.
Once the pipeline is in service it is very difficult to
measure the amount of debris remaining in a pipeline.
MFL and calliper pig surveys will show concentrated
deposits or restrictions, and downstream product
analysis will show the presence of fine debris or
powder, however this often generates further debate as
to whether such debris is from the pipeline, or the
upstream facility feeding the pipeline.
Mitigation
DEBRIS RISK MITIGATION MEASURE
Large items such as welding rods,
hand tools, bevel protector shims
etc.
Stringent training and close supervision of installation personnel should prevent
such debris entering the pipeline. Where the presence of larger debris is suspected,
running high strength magnetic pigs in the cleaning pig train should remove most
metallic objects.
Sand / soil introduced during
installation of onshore and
landfall sections
Run cleaning pigs through the line propelled by compressed air prior to pre-
commissioning. Ensure the main line pre-commissioning standards are enforced
for onshore and landfall sections
Sand and naturally occurring sea
water material introduced
Take samples of sea water at the filling point to assess suspended solids levels
and specify a filtration level that will cover the full range of suspended solids,
rather than setting an arbitrary figure of 50µ to 100µ. If removal by filtration is
not feasible or practical, specify the use of water based debris pick up gel in the
dewatering pig train to remove all debris introduced by sea water filling.
Figure 9 – Debris removed by gel cleaning
Figure 7 – Dust removed by pigging
Figure 8 – Control valve cage damage
Table 3 – Debris causes and mitigation measures
Case Study 2 – Fine Debris
An offshore gas pipeline laid in the Arabian Gulf took
water from the landfall area to fill and test the pipeline.
This water was filtered to 50µ in line with good
industry practice and multiple cleaning pigs were run.
The line was subsequently vacuum dried to a dewpoint
of -20°C and left under a nitrogen blanket prior to start
up. Internationally accepted pre-commissioning
practices were observed at each phase of the operation.
The line was then commissioned and filled with dried
and filtered process gas from the offshore location with
production feeding an onshore treatment plant. Within
30 days of start up the throughput in the line dropped
off and flow had to be shut in causing a full field
shutdown. The filters upstream of the slug catcher were
found to be completely blocked with fine powder and
concerns were raised as to the efficay of the pre-
commissioning cleaning process. The fine powder was
analysed and results showed that the particle size was
typically below 50µ and hence could note have been
removed by the seawater filters. Furthermore this
debris was found to be fine sand and shell particles that
are typical in that geography.
The decision was made that for future lines a water
based debris pick-up gel train would be run after
hydrotesting on future lines to remove such fine debris
– this proved successful with no problems reported on
subsequent lines.
CONCLUSIONS
1. When planning a new offshore pipeline it is
important to look at the environment in which
it will be installed to assess any fundamental
problems that could adversely affect the line
during pre-commissioning, particularly the
source and quality of water to be used to fill
and test the line.
2. For gas pipelines, internal coating should be
considered not just on the merits of flow
efficiency, but also on the corrosion protection
and ease of cleaning and drying facilitated by
the internal coating.
3. Wet buckles in uncoated pipelines will cause
significant internal corrosion if the line is not
quickly dewatered – for projects in remote
areas a permanent dewatering spread should
be considered as mobilisation of such a spread
may take many weeks.
4. Corrosion caused by untreated seawater
entering uncoated pipelines can cause
significant internal corrosion, reducing the
effective corrosion allowance and design life
of the line.
5. Simply filtering the fill and test water to 50µ
will not prevent smaller sized particles from
entering and collecting in the line - there are
many examples of fine powder being
recovered from gas lines immediately after
start-up, damaging in-line components and
affecting downstream facilities
6. Pipeline debris can build up during pre-
commissioning into hard lumps that can
resemble dents. This can lead to false data on
geometry surveys, adversely affecting a
project in both financial and schedule terms.
7. When executing a new pipeline, pre-
commissioning should be viewed with equal
importance to design, procurement and
installation, with the process being overseen
by the pipeline end user.
References
1. Shreir, L.L., Jarman, R.A, Burstein, G.T.:
Corrosion - Metal/Environment Reactions,
Vol. 1. Publ.: Butterworth Heinemann,
Oxford, 1994.
2. Butler, G.: Ison, H.C.K.: Corrosion and its
prevention in waters. Publ.: Robert E. Krieger
Publishing Company, New York, 1978.
3. John Morgan : Cathodic Protection, Publ.:
NACE, 1987.
4. Jaime Perez ; Black Powder in Sales Gas
Pipelines, Pipeline Management for Oil &
Gas Conference, Kuala Lumpur, 2005.
Acknowledgements
The author would like to thank his colleagues at BJ
Services for sharing their wealth of experience in
pipeline pre-commissioning and inspection in the
preparation of this paper.

More Related Content

What's hot

external & internal corrosion monitoring
external & internal corrosion monitoringexternal & internal corrosion monitoring
external & internal corrosion monitoring
sair ali khan
 
ePIPE lining lead pipe
ePIPE  lining lead pipe ePIPE  lining lead pipe
ePIPE lining lead pipe
Larry Gillanders
 
Rei corrosion monitoring
Rei corrosion monitoringRei corrosion monitoring
Rei corrosion monitoring
vms
 
Why Concrete Coatings Fail
Why Concrete Coatings FailWhy Concrete Coatings Fail
Why Concrete Coatings Fail
Will Fowler
 
01 hydro ripple+clarifier
01 hydro ripple+clarifier01 hydro ripple+clarifier
01 hydro ripple+clarifier
Nguyễn Mến CưMgar
 
CRA Lined Pipe Presentation_Pipe Conference_Final
CRA Lined Pipe Presentation_Pipe Conference_FinalCRA Lined Pipe Presentation_Pipe Conference_Final
CRA Lined Pipe Presentation_Pipe Conference_FinalTony Nelemans
 
Avoiding high-temperature-hydrogen-attack
Avoiding high-temperature-hydrogen-attackAvoiding high-temperature-hydrogen-attack
Avoiding high-temperature-hydrogen-attack
ahmadexsan
 
Nace workshop 2017
Nace workshop 2017Nace workshop 2017
Nace workshop 2017
Waldemar Husada
 
Wachs Water Full Service
Wachs Water Full ServiceWachs Water Full Service
Wachs Water Full Service
mfrench62
 
Challenges and solutions for improved durability of materials - Concrete in m...
Challenges and solutions for improved durability of materials - Concrete in m...Challenges and solutions for improved durability of materials - Concrete in m...
Challenges and solutions for improved durability of materials - Concrete in m...
Sirris
 
Corrosion Laboratory-slides show
Corrosion Laboratory-slides showCorrosion Laboratory-slides show
Corrosion Laboratory-slides showIgor Kosacki
 
Deionized water presentation
Deionized water presentationDeionized water presentation
Deionized water presentation
Alan Brown
 
Challenges and solutions for improved durability of materials - Coatings done...
Challenges and solutions for improved durability of materials - Coatings done...Challenges and solutions for improved durability of materials - Coatings done...
Challenges and solutions for improved durability of materials - Coatings done...
Sirris
 
Underwater Welding techniques
Underwater Welding techniquesUnderwater Welding techniques
Underwater Welding techniques
IJERA Editor
 
Islam Abdul naby general cv 2016
Islam Abdul naby general cv 2016Islam Abdul naby general cv 2016
Islam Abdul naby general cv 2016Islam Naby
 
CORROSION INSPECTION IN OIL AND GAS PIPELINE
CORROSION INSPECTION IN OIL AND GAS PIPELINECORROSION INSPECTION IN OIL AND GAS PIPELINE
CORROSION INSPECTION IN OIL AND GAS PIPELINEIlugbusi Blessing
 
Challenges and solutions for improved durability of materials - Hybrid joints...
Challenges and solutions for improved durability of materials - Hybrid joints...Challenges and solutions for improved durability of materials - Hybrid joints...
Challenges and solutions for improved durability of materials - Hybrid joints...
Sirris
 

What's hot (19)

external & internal corrosion monitoring
external & internal corrosion monitoringexternal & internal corrosion monitoring
external & internal corrosion monitoring
 
ePIPE lining lead pipe
ePIPE  lining lead pipe ePIPE  lining lead pipe
ePIPE lining lead pipe
 
Rei corrosion monitoring
Rei corrosion monitoringRei corrosion monitoring
Rei corrosion monitoring
 
Why Concrete Coatings Fail
Why Concrete Coatings FailWhy Concrete Coatings Fail
Why Concrete Coatings Fail
 
01 hydro ripple+clarifier
01 hydro ripple+clarifier01 hydro ripple+clarifier
01 hydro ripple+clarifier
 
SPE Well Prep Paper
SPE Well Prep PaperSPE Well Prep Paper
SPE Well Prep Paper
 
CRA Lined Pipe Presentation_Pipe Conference_Final
CRA Lined Pipe Presentation_Pipe Conference_FinalCRA Lined Pipe Presentation_Pipe Conference_Final
CRA Lined Pipe Presentation_Pipe Conference_Final
 
Avoiding high-temperature-hydrogen-attack
Avoiding high-temperature-hydrogen-attackAvoiding high-temperature-hydrogen-attack
Avoiding high-temperature-hydrogen-attack
 
Nace workshop 2017
Nace workshop 2017Nace workshop 2017
Nace workshop 2017
 
Wachs Water Full Service
Wachs Water Full ServiceWachs Water Full Service
Wachs Water Full Service
 
Challenges and solutions for improved durability of materials - Concrete in m...
Challenges and solutions for improved durability of materials - Concrete in m...Challenges and solutions for improved durability of materials - Concrete in m...
Challenges and solutions for improved durability of materials - Concrete in m...
 
Corrosion Laboratory-slides show
Corrosion Laboratory-slides showCorrosion Laboratory-slides show
Corrosion Laboratory-slides show
 
Water quality
Water qualityWater quality
Water quality
 
Deionized water presentation
Deionized water presentationDeionized water presentation
Deionized water presentation
 
Challenges and solutions for improved durability of materials - Coatings done...
Challenges and solutions for improved durability of materials - Coatings done...Challenges and solutions for improved durability of materials - Coatings done...
Challenges and solutions for improved durability of materials - Coatings done...
 
Underwater Welding techniques
Underwater Welding techniquesUnderwater Welding techniques
Underwater Welding techniques
 
Islam Abdul naby general cv 2016
Islam Abdul naby general cv 2016Islam Abdul naby general cv 2016
Islam Abdul naby general cv 2016
 
CORROSION INSPECTION IN OIL AND GAS PIPELINE
CORROSION INSPECTION IN OIL AND GAS PIPELINECORROSION INSPECTION IN OIL AND GAS PIPELINE
CORROSION INSPECTION IN OIL AND GAS PIPELINE
 
Challenges and solutions for improved durability of materials - Hybrid joints...
Challenges and solutions for improved durability of materials - Hybrid joints...Challenges and solutions for improved durability of materials - Hybrid joints...
Challenges and solutions for improved durability of materials - Hybrid joints...
 

Viewers also liked

Appendix f policy development and appraisal final_dec2010
Appendix f policy development and appraisal final_dec2010Appendix f policy development and appraisal final_dec2010
Appendix f policy development and appraisal final_dec2010
Severn Estuary
 
Appendix c baseline understanding final_dec2010
Appendix c baseline understanding final_dec2010Appendix c baseline understanding final_dec2010
Appendix c baseline understanding final_dec2010
Severn Estuary
 
Appendix a development of the smp2 final_dec2010
Appendix a development of the smp2 final_dec2010Appendix a development of the smp2 final_dec2010
Appendix a development of the smp2 final_dec2010
Severn Estuary
 
Smp2 part b policy statements tidenham only_final
Smp2 part b policy statements tidenham only_finalSmp2 part b policy statements tidenham only_final
Smp2 part b policy statements tidenham only_final
Severn Estuary
 
26-grover-john-final
26-grover-john-final26-grover-john-final
26-grover-john-finalJohn Grover
 
Smp2 part b policy statements kingston seymour only_final
Smp2 part b policy statements kingston seymour only_finalSmp2 part b policy statements kingston seymour only_final
Smp2 part b policy statements kingston seymour only_final
Severn Estuary
 
Smp2 part c action plan final
Smp2 part c action plan finalSmp2 part c action plan final
Smp2 part c action plan final
Severn Estuary
 
Offshore - Coiled Tubing Offers Pre-Commissioning Tool for Deepwater Pipeline...
Offshore - Coiled Tubing Offers Pre-Commissioning Tool for Deepwater Pipeline...Offshore - Coiled Tubing Offers Pre-Commissioning Tool for Deepwater Pipeline...
Offshore - Coiled Tubing Offers Pre-Commissioning Tool for Deepwater Pipeline...John Grover
 
Appendix d theme review final_dec2010a
Appendix d theme review final_dec2010aAppendix d theme review final_dec2010a
Appendix d theme review final_dec2010a
Severn Estuary
 
Appendix i part b _hra_final_dec2010
Appendix i part b _hra_final_dec2010Appendix i part b _hra_final_dec2010
Appendix i part b _hra_final_dec2010
Severn Estuary
 
Appendix k metadata and bibliographic database final_dec2010
Appendix k metadata and bibliographic database final_dec2010Appendix k metadata and bibliographic database final_dec2010
Appendix k metadata and bibliographic database final_dec2010
Severn Estuary
 
Appendix i part a sea_final_dec2010
Appendix i part a sea_final_dec2010Appendix i part a sea_final_dec2010
Appendix i part a sea_final_dec2010
Severn Estuary
 
Appendix b stakeholder engagement and consultation final_dec2010
Appendix b stakeholder engagement and consultation final_dec2010Appendix b stakeholder engagement and consultation final_dec2010
Appendix b stakeholder engagement and consultation final_dec2010
Severn Estuary
 
PII Paper for PetroMin Gas Pipeline Conference
PII Paper for PetroMin Gas Pipeline ConferencePII Paper for PetroMin Gas Pipeline Conference
PII Paper for PetroMin Gas Pipeline ConferenceJohn Grover
 
Offshore Ind Gases J Grover 11 Dec 07
Offshore Ind Gases J Grover 11 Dec 07Offshore Ind Gases J Grover 11 Dec 07
Offshore Ind Gases J Grover 11 Dec 07John Grover
 
Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15John Grover
 
Appendix g preferred management approach testing final_dec2010
Appendix g preferred management approach testing final_dec2010Appendix g preferred management approach testing final_dec2010
Appendix g preferred management approach testing final_dec2010
Severn Estuary
 
Smp2 part b policy statements bristol only_final
Smp2 part b policy statements bristol only_finalSmp2 part b policy statements bristol only_final
Smp2 part b policy statements bristol only_final
Severn Estuary
 

Viewers also liked (20)

Appendix f policy development and appraisal final_dec2010
Appendix f policy development and appraisal final_dec2010Appendix f policy development and appraisal final_dec2010
Appendix f policy development and appraisal final_dec2010
 
Appendix c baseline understanding final_dec2010
Appendix c baseline understanding final_dec2010Appendix c baseline understanding final_dec2010
Appendix c baseline understanding final_dec2010
 
Appendix a development of the smp2 final_dec2010
Appendix a development of the smp2 final_dec2010Appendix a development of the smp2 final_dec2010
Appendix a development of the smp2 final_dec2010
 
Tasnia
TasniaTasnia
Tasnia
 
Smp2 part b policy statements tidenham only_final
Smp2 part b policy statements tidenham only_finalSmp2 part b policy statements tidenham only_final
Smp2 part b policy statements tidenham only_final
 
26-grover-john-final
26-grover-john-final26-grover-john-final
26-grover-john-final
 
Smp2 part b policy statements kingston seymour only_final
Smp2 part b policy statements kingston seymour only_finalSmp2 part b policy statements kingston seymour only_final
Smp2 part b policy statements kingston seymour only_final
 
Smp2 part c action plan final
Smp2 part c action plan finalSmp2 part c action plan final
Smp2 part c action plan final
 
Offshore - Coiled Tubing Offers Pre-Commissioning Tool for Deepwater Pipeline...
Offshore - Coiled Tubing Offers Pre-Commissioning Tool for Deepwater Pipeline...Offshore - Coiled Tubing Offers Pre-Commissioning Tool for Deepwater Pipeline...
Offshore - Coiled Tubing Offers Pre-Commissioning Tool for Deepwater Pipeline...
 
Appendix d theme review final_dec2010a
Appendix d theme review final_dec2010aAppendix d theme review final_dec2010a
Appendix d theme review final_dec2010a
 
PII_IQPC_May_04
PII_IQPC_May_04PII_IQPC_May_04
PII_IQPC_May_04
 
Appendix i part b _hra_final_dec2010
Appendix i part b _hra_final_dec2010Appendix i part b _hra_final_dec2010
Appendix i part b _hra_final_dec2010
 
Appendix k metadata and bibliographic database final_dec2010
Appendix k metadata and bibliographic database final_dec2010Appendix k metadata and bibliographic database final_dec2010
Appendix k metadata and bibliographic database final_dec2010
 
Appendix i part a sea_final_dec2010
Appendix i part a sea_final_dec2010Appendix i part a sea_final_dec2010
Appendix i part a sea_final_dec2010
 
Appendix b stakeholder engagement and consultation final_dec2010
Appendix b stakeholder engagement and consultation final_dec2010Appendix b stakeholder engagement and consultation final_dec2010
Appendix b stakeholder engagement and consultation final_dec2010
 
PII Paper for PetroMin Gas Pipeline Conference
PII Paper for PetroMin Gas Pipeline ConferencePII Paper for PetroMin Gas Pipeline Conference
PII Paper for PetroMin Gas Pipeline Conference
 
Offshore Ind Gases J Grover 11 Dec 07
Offshore Ind Gases J Grover 11 Dec 07Offshore Ind Gases J Grover 11 Dec 07
Offshore Ind Gases J Grover 11 Dec 07
 
Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15
 
Appendix g preferred management approach testing final_dec2010
Appendix g preferred management approach testing final_dec2010Appendix g preferred management approach testing final_dec2010
Appendix g preferred management approach testing final_dec2010
 
Smp2 part b policy statements bristol only_final
Smp2 part b policy statements bristol only_finalSmp2 part b policy statements bristol only_final
Smp2 part b policy statements bristol only_final
 

Similar to OSEA 2006 - Precom Impact final

OSEA J Grover 7 Dec 06
OSEA J Grover 7 Dec 06OSEA J Grover 7 Dec 06
OSEA J Grover 7 Dec 06John Grover
 
Well_Completions.pdf
Well_Completions.pdfWell_Completions.pdf
Well_Completions.pdf
AihamAltayeh1
 
A life cycle approach to corrosion management and asset integrity
A life cycle approach to corrosion management and asset integrityA life cycle approach to corrosion management and asset integrity
A life cycle approach to corrosion management and asset integrity
Okeme Esegine PMP
 
Post tensioned-bridges-diagnosing-remediating-corrosive-conditions
Post tensioned-bridges-diagnosing-remediating-corrosive-conditionsPost tensioned-bridges-diagnosing-remediating-corrosive-conditions
Post tensioned-bridges-diagnosing-remediating-corrosive-conditions
stevendsanders
 
Water loss detection and management
Water loss detection and management Water loss detection and management
Water loss detection and management
Yogesh SN
 
HT & LT Bus Ducts Manufacturer in Telangana and Andhra Pradesh
HT & LT Bus Ducts Manufacturer in Telangana and Andhra PradeshHT & LT Bus Ducts Manufacturer in Telangana and Andhra Pradesh
HT & LT Bus Ducts Manufacturer in Telangana and Andhra Pradesh
Mohit Bathineni
 
Well Integrity.pptx
Well Integrity.pptxWell Integrity.pptx
Well Integrity.pptx
AnjanKumar960785
 
Corrosion control
Corrosion controlCorrosion control
Corrosion control
Duy Vu
 
KNPC Volume 3B.pdf
KNPC Volume 3B.pdfKNPC Volume 3B.pdf
KNPC Volume 3B.pdf
MohamedElAyoutti
 
Pipeline integrity assessment with LRUT method
Pipeline integrity assessment with LRUT methodPipeline integrity assessment with LRUT method
Pipeline integrity assessment with LRUT method
paulus konda
 
Trenchless Rehabilitation of Sewer & Water Networks
Trenchless Rehabilitation of Sewer & Water NetworksTrenchless Rehabilitation of Sewer & Water Networks
Trenchless Rehabilitation of Sewer & Water Networks
Loay Ghazaleh MBA, BSc Civil Eng.
 
Tip 0492 19
Tip 0492 19Tip 0492 19
PROC 2076 Assignment Report, Pipeline
PROC 2076 Assignment Report, PipelinePROC 2076 Assignment Report, Pipeline
PROC 2076 Assignment Report, PipelineSyafiq Dan
 
L 44 leakge management
L 44 leakge managementL 44 leakge management
L 44 leakge management
Dr. shrikant jahagirdar
 
Jim Reed - The Gas Co. - Pipeline Safety In A Post San Bruno Era
Jim Reed - The Gas Co. - Pipeline Safety In A Post San Bruno EraJim Reed - The Gas Co. - Pipeline Safety In A Post San Bruno Era
Jim Reed - The Gas Co. - Pipeline Safety In A Post San Bruno EraContract Cities
 
06 carbon brush and collector maintenance
06 carbon brush and collector maintenance06 carbon brush and collector maintenance
06 carbon brush and collector maintenance
prasadkappala
 
Emergency Pipeline Repair Systems, A Global Overview of Best Practice
Emergency Pipeline Repair Systems, A Global Overview of Best PracticeEmergency Pipeline Repair Systems, A Global Overview of Best Practice
Emergency Pipeline Repair Systems, A Global Overview of Best PracticeJames Rowley
 
NDT
NDTNDT
Corrosion control of underwater piles
Corrosion control of underwater pilesCorrosion control of underwater piles
Corrosion control of underwater piles
Aglaia Connect
 

Similar to OSEA 2006 - Precom Impact final (20)

OSEA J Grover 7 Dec 06
OSEA J Grover 7 Dec 06OSEA J Grover 7 Dec 06
OSEA J Grover 7 Dec 06
 
Well_Completions.pdf
Well_Completions.pdfWell_Completions.pdf
Well_Completions.pdf
 
A life cycle approach to corrosion management and asset integrity
A life cycle approach to corrosion management and asset integrityA life cycle approach to corrosion management and asset integrity
A life cycle approach to corrosion management and asset integrity
 
Post tensioned-bridges-diagnosing-remediating-corrosive-conditions
Post tensioned-bridges-diagnosing-remediating-corrosive-conditionsPost tensioned-bridges-diagnosing-remediating-corrosive-conditions
Post tensioned-bridges-diagnosing-remediating-corrosive-conditions
 
Water loss detection and management
Water loss detection and management Water loss detection and management
Water loss detection and management
 
HT & LT Bus Ducts Manufacturer in Telangana and Andhra Pradesh
HT & LT Bus Ducts Manufacturer in Telangana and Andhra PradeshHT & LT Bus Ducts Manufacturer in Telangana and Andhra Pradesh
HT & LT Bus Ducts Manufacturer in Telangana and Andhra Pradesh
 
Well Integrity.pptx
Well Integrity.pptxWell Integrity.pptx
Well Integrity.pptx
 
Corrosion control
Corrosion controlCorrosion control
Corrosion control
 
KNPC Volume 3B.pdf
KNPC Volume 3B.pdfKNPC Volume 3B.pdf
KNPC Volume 3B.pdf
 
Pipeline integrity assessment with LRUT method
Pipeline integrity assessment with LRUT methodPipeline integrity assessment with LRUT method
Pipeline integrity assessment with LRUT method
 
Trenchless Rehabilitation of Sewer & Water Networks
Trenchless Rehabilitation of Sewer & Water NetworksTrenchless Rehabilitation of Sewer & Water Networks
Trenchless Rehabilitation of Sewer & Water Networks
 
Tip 0492 19
Tip 0492 19Tip 0492 19
Tip 0492 19
 
PROC 2076 Assignment Report, Pipeline
PROC 2076 Assignment Report, PipelinePROC 2076 Assignment Report, Pipeline
PROC 2076 Assignment Report, Pipeline
 
01_WP-CPL_0608_LR
01_WP-CPL_0608_LR01_WP-CPL_0608_LR
01_WP-CPL_0608_LR
 
L 44 leakge management
L 44 leakge managementL 44 leakge management
L 44 leakge management
 
Jim Reed - The Gas Co. - Pipeline Safety In A Post San Bruno Era
Jim Reed - The Gas Co. - Pipeline Safety In A Post San Bruno EraJim Reed - The Gas Co. - Pipeline Safety In A Post San Bruno Era
Jim Reed - The Gas Co. - Pipeline Safety In A Post San Bruno Era
 
06 carbon brush and collector maintenance
06 carbon brush and collector maintenance06 carbon brush and collector maintenance
06 carbon brush and collector maintenance
 
Emergency Pipeline Repair Systems, A Global Overview of Best Practice
Emergency Pipeline Repair Systems, A Global Overview of Best PracticeEmergency Pipeline Repair Systems, A Global Overview of Best Practice
Emergency Pipeline Repair Systems, A Global Overview of Best Practice
 
NDT
NDTNDT
NDT
 
Corrosion control of underwater piles
Corrosion control of underwater pilesCorrosion control of underwater piles
Corrosion control of underwater piles
 

More from John Grover

26-grover-john-draft
26-grover-john-draft26-grover-john-draft
26-grover-john-draftJohn Grover
 
50-Marco Casirati-Nord Stream Pre-Commissioning
50-Marco Casirati-Nord Stream Pre-Commissioning50-Marco Casirati-Nord Stream Pre-Commissioning
50-Marco Casirati-Nord Stream Pre-CommissioningJohn Grover
 
Paper 43 - OPT 2015_BHI 9_2_15
Paper 43 - OPT 2015_BHI 9_2_15Paper 43 - OPT 2015_BHI 9_2_15
Paper 43 - OPT 2015_BHI 9_2_15John Grover
 
BHI NSP Final 14_6_12
BHI NSP Final 14_6_12BHI NSP Final 14_6_12
BHI NSP Final 14_6_12John Grover
 
20130411110129735 (2)
20130411110129735 (2)20130411110129735 (2)
20130411110129735 (2)John Grover
 

More from John Grover (6)

26-grover-john-draft
26-grover-john-draft26-grover-john-draft
26-grover-john-draft
 
50-Marco Casirati-Nord Stream Pre-Commissioning
50-Marco Casirati-Nord Stream Pre-Commissioning50-Marco Casirati-Nord Stream Pre-Commissioning
50-Marco Casirati-Nord Stream Pre-Commissioning
 
Paper 43 - OPT 2015_BHI 9_2_15
Paper 43 - OPT 2015_BHI 9_2_15Paper 43 - OPT 2015_BHI 9_2_15
Paper 43 - OPT 2015_BHI 9_2_15
 
BHI NSP Final 14_6_12
BHI NSP Final 14_6_12BHI NSP Final 14_6_12
BHI NSP Final 14_6_12
 
OGJ Nordstream
OGJ NordstreamOGJ Nordstream
OGJ Nordstream
 
20130411110129735 (2)
20130411110129735 (2)20130411110129735 (2)
20130411110129735 (2)
 

OSEA 2006 - Precom Impact final

  • 1. THE IMPACT OF OFFSHORE PIPELINE INSTALLATION AND PRE- COMMISSIONING ON FUTURE SYSTEM INTEGRITY J. L. Grover BJ Process and Pipeline Services, Dubai ABSTRACT Operators of offshore pipelines focus on the integrity of the system once commissioned, normally using internal corrosion rates as the key measure of remaining life. Such operators, who focus on pipeline integrity management and intelligent pigging throughout the life of the asset, pay less attention to the asset during the installation and pre-commissioning of offshore pipelines, often entrusting this activity to the installation contractor. In this paper we draw on over 30 years of experience in pre-commissioning offshore pipelines to examine some of the common mistakes and oversights in the areas of:  Pipe spool storage and preservation  Prevention of seawater ingress during lay  Wet buckle impact and possible contingencies  Pre-operational cleaning  Source and treatment of hydrotest water  Dewatering and drying For each of the above we assess how the activity can affect the overall integrity of the pipeline and what steps can be taken to minimize any adverse risk. The objective of the paper is to raise the awareness amongst offshore pipeline operators of the impact installation and pre-commissioning can have on operational pipeline integrity. INTRODUCTION Offshore pipelines are designed with an internal corrosion allowance based on the proposed design life of the pipeline and associated field. This may be anywhere between 10 and 30 years. The pipeline design contractor will consider a variety of factors in predicting the likely pipeline internal corrosion rate including product composition and likely composition during the field life, presence of CO2, H2S, or water in the product to be transported, whether the product will be treated with a corrosion inhibitor and whether the pipeline will be pigged on a regular basis. What will not be considered in the corrosion allowance will be corrosion occurring during the storage, installation, and commissioning of the pipeline. In part 1 of this paper examples of newly laid pipelines are illustrated where internal metal loss of 30%WT has been recorded prior to start up. Furthermore the facilities downstream of the pipeline will be designed to accept the product in the pipeline generally without consideration for the entrainment of any materials remaining in the pipeline. There are many occurances where debris remains in the line after construction, or fine particles slough off the pipeline wall during service, often referred to as “black powder”. In part 2 of this paper we will see examples of pipelines which have been cleaned during pre- commissioning to an agreed specification, and yet have produced up to 50 tonnes of powder on start up, damaging filters, shutting down the receiving facilities, and eroding internal components such as control valves.
  • 2. PART 1 – CORROSION CAUSED DURING INSTALLATION & PRE-COMMISSIONING Cause From leaving the pipe mill to commencing service each pipeline joint will be exposed to many situations where corrosion can occur including: 1. End protectors not fitted, or removed during the pipe coating process 2. Pipe joints stored close to the sea, or on the lay barge without end protectors fitted 3. Pipeline suffers a wet buckle or rupture during installation allowing raw dewater to enter the pipeline 4. Water used to flood and hydrotest the pipeline is not correctly filtered or dosed with the correct chemicals to prevent corrosion 5. Pipeline hydrotest water remains in the pipeline beyond the life of the corrosion inhibition chemicals 6. Hydrotest water is not adequately removed from the pipeline by dewatering Effect Each of the above, or a combination thereof, can cause internal corrosion (fig. 1) to occur on the pipe wall. This effect is greatly mitigated by internally coating the pipe joints prior to installation. The resulting corrosion adversely impacts the time required to dry the pipeline – in the line detailed in the first case study, drying time increased 100% due to trapped water from poor surface condition. Once the line is in service, this fine corrosion sloughs off causing operational difficulties as detailed in the second case study. Measurement Many pipeline operators have recognised the benefit of performing a baseline corrosion, or metal loss survey on newly installed pipelines. Such a survey can either be run during one of the pre-commissioning pigging trains, or in the pipeline product immediately after the line is put into production. Both USWM and MFL tools can be used for this purpose, however MFL tools are generally used due to cost, and future data matching requirements. It is generally accepted that such a baseline survey should be performed as early as possible if the cause of any internal corrosion (fig. 2) is to be accurately attributed – there have been examples of newly installed pipelines having 50%WT internal wall loss within 18 months of start up which are then attributed to product related corrosion. Obtaining such data during, or immediately after pre-commissioning, may allow for claims to be made, or potential losses recovered from the project insurance. In addition to ILI tools it is possible to measure riser and topside corrosion using video inspection and external UT inspection techniques. External UT can be applied subsea but applications are limited on buried lines or those that have a concrete weight coat fitted. Figure 1 – Internal corrosion Figure 2 – Pitting corrosion @ 6 o’clock
  • 3. Mitigation The following table summarises possible steps to mitigate the corrosion risks detailed above: CORROSION RISK MITIGATION MEASURE Corrosion during storage, shipping and coating process Fit end protectors, and use vapour phase corrosion inhibitor or nitrogen blanket to preserve a non-corrosive atmosphere in each spool. Thoroughly clean each spool using a mechanical brush system immediately prior to welding. Free flooding with raw seawater due to wet buckle Ensure an emergency dewatering spread is available to quickly dewater the line should a wet buckle occur causing the line to free flood Water used to flood the line not correctly filtered or chemically treated At the planning stage have a pre-commissioning specialist review the project specifications for applicability. Take samples of seawater at the filling point to assess suspended solids. Seek advice from the production chemical companies on the best treatment chemicals and dosing rates. Many projects specify a filtration level of 50µ but without any acceptance criteria on suspended solids per unit volume. Some projects are now specifying a maximum allowable level of suspended solids of 20g/m3 . At the execution phase employ an independent representative to check the size and efficacy of the fill water filtration used, and also the actual chemical dosing rates. In addition analyse regular samples of the flooding water to check for quantity and size distribution of suspended solids. Pipeline hydrotest water remains in the line beyond the effective life of the chemicals Often a pipeline may be “laid up” for a fixed period between the completion of hydrotesting and the commencement of dewatering / commissioning. Where this period extends beyond theoriginal planned duration, the chemical protection may not be adequate. Such an event needs to be recorded and the hydrotest water displaced with a fresh batch of water, suitably treated for the revised lay up period. Hydrotest water is not adequately removed from the pipeline by dewatering A thorough pipeline dewatering operation should leave a water film in the pipe of approx. 0.1mm for uncoated pipe and 0.07mm for internally coated pipe. In some applications it is possible to measure the volume of water removed from the line using flow meters. A desalination slug forms part of the pig train suitably sized to dilute the residual seawater – typically this is 4% of the line volume with acceptance criteria of a final chloride content of below 200ppm. If there is a delay between dewatering and subsequent swabbing / drying / commissioning, the remaining water film will drain down to the bottom of the line and collect at any low points. If this residual water has not been suitably desalinated it can pose an additional corrosion risk. Table 1 – Corrosion causes and mitigation measures
  • 4. Case Study 1 – Wet Buckle Due to confidentiality, the pipeline details below are fictitious, however the engineering calculations and outcomes are factual. A 36” x 350km offshore gas transmission line suffered a wet buckle during pipelay causing the line to free flood with raw seawater at the buckle point when approx. 160km of the line had been laid. The main section of the line was 14.3mm WT. The pipe was free flooded with seawater for 3 months. When fully immersed in seawater, steel will corrode at a remarkably steady rate to produce the oxide Fe2O3 (haematite) or Fe3O4 (magnetite). The corrosion is very rapid initially, but falls off gradually over several months to a fairly steady rate (Table 2). Table 2 – General corrosion rates for steel in tropical seawater. It should be noted that these rates are for general corrosion and not pitting corrosion. Pitting corrosion rates are generally quoted as several orders of magnitude higher than the average rate. In this corrosion event, it is has been assumed that the seawater is not stagnant and that there is a continuous supply of fresh corrodant to the steel surface. In addition, it has been assumed that the mill scale, and the corrosion product from the first corrosion event have formed a semi-protective coating on the steel surface. Therefore a corrosion rate of 0.13mm/year has been selected as representative of the average corrosion rate during this event (see references below). No pitting corrosion has been considered. Therefore, assuming a corrosion rate of 0.13mm/yr over a three month period the wall thickness loss for the 150km pipeline will be d=0.00325cm. The volume of metal loss is given by: Volume = Area x Length Volume = 2..r.d x L In this equation r is the internal radius of the pipe = 44.3cm, taking the diameter of the pipe to be 91.4cm and the wall thickness to be 1.43 cm. The total volume of metal loss is: Volume = 2 x 3.14 x 44.3 x 0.00325 x 161000 x 100 = 1.5 x 107 cm3 The mass of iron lost is therefore: Mass = Fe x Volume If the density of iron (Fe) = 7.8 g/cm3 then the total mass of iron lost = 1.1 x 108 g. The total number of moles of iron consumed in the reaction is given by the equation: RAM Mass Moles  Where RAM = Relative Atomic Mass and RAMFe = 56 g/mol therefore MolesFe= 2.0 x 106 moles. The equation for the reaction of iron in seawater is: Therefore the total amount to oxide formed from 2.0 x 106 moles of iron is 6.8 x 105 moles. The total weight of oxide is given by Mass = Moles x RMM Where the Relative Molecular Mass (RMM) of Fe3O4 = 232 g/mol. Therefore the total mass of iron oxide formed in this reaction is approximately 157,000 kg (157 tonnes). This pipeline was then subject to a baseline MFL survey where the impact of this corrosion was noted in a number of ways.  Hard bed of debris at 6 o’clock position masking pipe wall  Internal corrosion measured up to 35% WT  Blockage of filters from excessive debris removed during the pigging operation Exposure Time (months) Average corrosion rate (mm/year) 1 0.33 2 0.25 3 0.19 6 0.15 12 0.13 24 0.11 48 0.11 r Area of metal loss lloss d 432 OFeO2Fe3 
  • 5. Prior to the MFL survey being performed, a number of standard cleaning pigs were run through the line by the MFL vendor to remove debris from the pipeline. Due to the internal corrosion caused by the wet buckle, and the large amount of dust formed on the pipe wall, these pigs suffered severe wear (fig. 3) and recovered very little debris from the line. It can be seen that the front of the pig is more heavily worn than the rear caused by the pig “nose diving” Subsequently an MFL tool was run in the line (fig. 4). Such tools are fitted with high powered magnets and strong brushes to magnetise the pipe wall – as such these tools make highly effective pipeline cleaners. During this first run nearly 20,000kg of fine powder was recovered from the pig receiver, and all external components of the MFL tool were badly worn or damaged. After repeated cleaning runs over 80 tonnes of ferrous debris was removed from the pipeline before a successful MFL run could be performed. This was in addition to the estimated 40 tonnes removed during pre-commissioning, and 20 to 30 tonnes removed from filters downstream of the pig receiver. The results of the MFL run endorsed the calculated corrosion rates shown previously – the deepest internal defects were greater than 35% WT with a large population of > 20% WT shown in the area immediately downstream of the wet buckle area. In total over 100,000 metal loss defects were identified. PART 2 – DEBRIS FROM INSTALLATION AND PRE-COMMISSIONING Cause During the installation of an offshore pipeline it is reasonable to expect that very little debris should enter the pipeline, certainly far less than for an onshore pipeline. Also a prudent installation contactor will employ a system to manually brush the internal surface of each pipe joint as it is welded to the pipe string. However offshore pipelines often feature a landfall section, or short onshore section at each end where there is a greater risk of debris entering the line. Some examples of debris recovered from offshore pipelines during pre-commissioning include:  Welding rods (fig. 5), welding bladders, hand tools, and shims used to secure bevel protectors to the pipe joint etc.  Sand and soil introduced into the pipeline either via the onshore / landfall pipelay, or in the water used to flood and test the pipeline  Naturally occurring seawater borne debris below the project filtration levels such as shell particles Effect During the pre-commissioning phase such debris has an adverse effect on pig wear and hence efficacy of the cleaning and filling pigs. Where debris builds up in one location it can cause damage to a gauge plate and can show as a dent during a calliper inspection. This can then lead to delays and possible expenditure trying to locate a dent or restriction that does not actually exist – if this is post rock dumping it may be impossible to inspect the line to verify the presence of a dent. Fine debris, such as particles below 50µ in size tend to settle at the bottom of the pipeline (fig. 6) during hydrotesting, and are very difficult to remove during subsequent dewatering. Once settled this debris can form a crust trapping water, which can adversely affect the drying of the line. Figure 3 – Worn cleaning pig Figure 4 – MFL tool Figure 5 – Welding rods on cleaning pig Figure 6 – Fine debris removed by cleaning pig
  • 6. Once the line goes into production (for dry gas lines) this debris slowly dries out and sloughs off into the gas stream as powder (fig. 7) causing downstream problems with valves and filters (fig. 8). There are also examples where this debris crust does not slough off and remains at the bottom of the line – affecting the efficacy of MFL inspections by masking part of the pipeline to be inspected and causing the MFL sensors to lift off. Such debris is often referred to as “black powder” however it is actually an oxide and ferrous in nature and may be mixed with fine rust from the pipe wall. Measurement The debris removed during initial cleaning can be measured by physically weighing the debris, or analysing the suspended solids in the fill water. The trending of samples taken between pigs in a filling and cleaning pig train gives a good picture of the efficacy of the cleaning process and provides data to demonstrate compliance with the specification or relevant standard. Where a debris pick-up gel is used in the pre-commissioning process it is far easier to measure the trend of debris removed from the pipeline (fig. 9), and hence assert how much debris remains. Once the pipeline is in service it is very difficult to measure the amount of debris remaining in a pipeline. MFL and calliper pig surveys will show concentrated deposits or restrictions, and downstream product analysis will show the presence of fine debris or powder, however this often generates further debate as to whether such debris is from the pipeline, or the upstream facility feeding the pipeline. Mitigation DEBRIS RISK MITIGATION MEASURE Large items such as welding rods, hand tools, bevel protector shims etc. Stringent training and close supervision of installation personnel should prevent such debris entering the pipeline. Where the presence of larger debris is suspected, running high strength magnetic pigs in the cleaning pig train should remove most metallic objects. Sand / soil introduced during installation of onshore and landfall sections Run cleaning pigs through the line propelled by compressed air prior to pre- commissioning. Ensure the main line pre-commissioning standards are enforced for onshore and landfall sections Sand and naturally occurring sea water material introduced Take samples of sea water at the filling point to assess suspended solids levels and specify a filtration level that will cover the full range of suspended solids, rather than setting an arbitrary figure of 50µ to 100µ. If removal by filtration is not feasible or practical, specify the use of water based debris pick up gel in the dewatering pig train to remove all debris introduced by sea water filling. Figure 9 – Debris removed by gel cleaning Figure 7 – Dust removed by pigging Figure 8 – Control valve cage damage Table 3 – Debris causes and mitigation measures
  • 7. Case Study 2 – Fine Debris An offshore gas pipeline laid in the Arabian Gulf took water from the landfall area to fill and test the pipeline. This water was filtered to 50µ in line with good industry practice and multiple cleaning pigs were run. The line was subsequently vacuum dried to a dewpoint of -20°C and left under a nitrogen blanket prior to start up. Internationally accepted pre-commissioning practices were observed at each phase of the operation. The line was then commissioned and filled with dried and filtered process gas from the offshore location with production feeding an onshore treatment plant. Within 30 days of start up the throughput in the line dropped off and flow had to be shut in causing a full field shutdown. The filters upstream of the slug catcher were found to be completely blocked with fine powder and concerns were raised as to the efficay of the pre- commissioning cleaning process. The fine powder was analysed and results showed that the particle size was typically below 50µ and hence could note have been removed by the seawater filters. Furthermore this debris was found to be fine sand and shell particles that are typical in that geography. The decision was made that for future lines a water based debris pick-up gel train would be run after hydrotesting on future lines to remove such fine debris – this proved successful with no problems reported on subsequent lines. CONCLUSIONS 1. When planning a new offshore pipeline it is important to look at the environment in which it will be installed to assess any fundamental problems that could adversely affect the line during pre-commissioning, particularly the source and quality of water to be used to fill and test the line. 2. For gas pipelines, internal coating should be considered not just on the merits of flow efficiency, but also on the corrosion protection and ease of cleaning and drying facilitated by the internal coating. 3. Wet buckles in uncoated pipelines will cause significant internal corrosion if the line is not quickly dewatered – for projects in remote areas a permanent dewatering spread should be considered as mobilisation of such a spread may take many weeks. 4. Corrosion caused by untreated seawater entering uncoated pipelines can cause significant internal corrosion, reducing the effective corrosion allowance and design life of the line. 5. Simply filtering the fill and test water to 50µ will not prevent smaller sized particles from entering and collecting in the line - there are many examples of fine powder being recovered from gas lines immediately after start-up, damaging in-line components and affecting downstream facilities 6. Pipeline debris can build up during pre- commissioning into hard lumps that can resemble dents. This can lead to false data on geometry surveys, adversely affecting a project in both financial and schedule terms. 7. When executing a new pipeline, pre- commissioning should be viewed with equal importance to design, procurement and installation, with the process being overseen by the pipeline end user. References 1. Shreir, L.L., Jarman, R.A, Burstein, G.T.: Corrosion - Metal/Environment Reactions, Vol. 1. Publ.: Butterworth Heinemann, Oxford, 1994. 2. Butler, G.: Ison, H.C.K.: Corrosion and its prevention in waters. Publ.: Robert E. Krieger Publishing Company, New York, 1978. 3. John Morgan : Cathodic Protection, Publ.: NACE, 1987. 4. Jaime Perez ; Black Powder in Sales Gas Pipelines, Pipeline Management for Oil & Gas Conference, Kuala Lumpur, 2005. Acknowledgements The author would like to thank his colleagues at BJ Services for sharing their wealth of experience in pipeline pre-commissioning and inspection in the preparation of this paper.