This document summarizes the Stage 1 assessment undertaken as part of the Habitats Regulations Assessment for the Severn Estuary Shoreline Management Plan Review. 30 European sites were initially considered based on their location and potential connectivity to the study area. Following an analysis of their interest features and conservation objectives, 20 sites were scoped out from further assessment because they were deemed unlikely to be affected by changes resulting from implementation of the SMP2. The remaining 10 sites were carried forward to Stage 2 assessment.
This document provides a theme review for the Severn Estuary Shoreline Management Plan Review (SMP2). It identifies and evaluates key natural, historic, and land use features along the shoreline. The review includes summaries of relevant policies and legislation, assessments of landscape and nature conservation designations, the historic environment, and current and future land uses. It then provides more detailed summaries of these themes for 16 specific areas along the shoreline to inform the development of objectives and policy options for the SMP2.
Appendix e issues and features final_dec2010Severn Estuary
This document provides an appendix to the Severn Estuary Shoreline Management Plan Review. It outlines the methodology used to identify issues, features, and objectives along the Severn Estuary coastline. Key features were identified through a theme review process and stakeholder input. The importance of each feature is evaluated based on the scale of its benefits, importance to users, sufficiency of the feature, and whether the benefits can be substituted. Features at risk of flooding under a no active intervention scenario within the next 100 years are also identified using GIS data. The appendix is divided into two parts: part A covers the identification and assessment of issues and features, while part B establishes objectives for shoreline management.
Appendix g preferred management approach testing final_dec2010Severn Estuary
This document tests different management approaches for shoreline policy units along the Severn Estuary to help identify preferred policies. It analyzes how policy units interact through coastal processes and flooding, and assesses approaches against objectives. Management Approach A represents the initial starting point, Approach B prioritizes natural processes, Approach C protects assets, and Approach D continues current policies. Completing the approach tables helps determine the most appropriate long-term policy, which is identified in the SMP2 Final Report. The analysis aims to improve understanding of coastal change to inform planning and development decisions.
This document summarizes an economic appraisal of the preferred plan for the Severn Estuary Shoreline Management Plan Review (SMP2). It finds that:
1) Allowing natural coastal evolution with no active intervention would result in significant economic damages from flooding and loss of assets over time.
2) Implementing the preferred plan of maintaining or improving coastal defences would cost an estimated $15 million but would prevent substantial economic damages estimated at $30 million.
3) A high-level benefit-cost assessment finds the preferred plan is economically viable, with benefits expected to outweigh the costs. However, more detailed analysis will be required to justify specific future schemes.
Appendix c baseline understanding final_dec2010Severn Estuary
This document contains three parts that provide baseline information for the Severn Estuary Shoreline Management Plan Review (SMP2):
Part A assesses coastal processes and evolution in the estuary based on geology, geomorphology, hydrodynamics, and sediment transport.
Part B details existing coastal defences along the shoreline based on surveys and updates from local authorities. It considers residual life of defences over 20, 50, and 100 years.
Part C develops baseline scenarios of shoreline change under conditions of No Active Intervention (NAI) and With Present Management (WPM), taking into account climate change and potential defence failure over different time periods. It aims to improve understanding of coastal risks to inform SMP
The document provides an environmental assessment report for the Severn Estuary Shoreline Management Plan Review (SMP2). It summarizes the baseline environmental conditions in the study area, including populations and human health, biodiversity, fisheries, geology, land use, water, air and climate, cultural heritage, landscape and contaminated land. It then describes the strategic environmental assessment process undertaken to evaluate the potential environmental impacts of different shoreline management policies. This included developing objectives, consulting stakeholders, reviewing other relevant plans and strategies, and assessing alternative policy options. The preferred policies were selected and their impacts evaluated, including cumulative effects and mitigation measures. An implementation and monitoring plan was also developed to track effects relating to access and recreation, biodiversity
This document provides a Water Framework Directive (WFD) assessment of the Severn Estuary Shoreline Management Plan 2 (SMP2). It identifies the transitional, coastal, river, lake and groundwater bodies in the SMP2 area and assesses how the SMP2's preferred policies may impact the environmental objectives of the WFD. The assessment found that several management areas' policies have the potential to not fully meet some of the WFD objectives. It provides recommendations to better align some SMP boundaries with WFD waterbody boundaries. Overall, the assessment determines whether the SMP2's policies will help or hinder achieving the WFD's goals in different water bodies in the plan's coastal region.
Appendix f policy development and appraisal final_dec2010Severn Estuary
This document summarizes the initial approach taken to develop policy options for the Severn Estuary Shoreline Management Plan Review (SMP2). The coastline was divided into Policy Units based on land use, flood and erosion risk. Potential policy options were identified for each unit considering features and objectives. Multiple options were selected for later appraisal over three epochs (0-20, 20-50, 50-100 years) to assess impacts on coastal processes and features. The aim was to identify appropriate combinations of policies to appraise for the whole coast as interactions between locations are important to developing a sustainable long-term plan.
This document provides a theme review for the Severn Estuary Shoreline Management Plan Review (SMP2). It identifies and evaluates key natural, historic, and land use features along the shoreline. The review includes summaries of relevant policies and legislation, assessments of landscape and nature conservation designations, the historic environment, and current and future land uses. It then provides more detailed summaries of these themes for 16 specific areas along the shoreline to inform the development of objectives and policy options for the SMP2.
Appendix e issues and features final_dec2010Severn Estuary
This document provides an appendix to the Severn Estuary Shoreline Management Plan Review. It outlines the methodology used to identify issues, features, and objectives along the Severn Estuary coastline. Key features were identified through a theme review process and stakeholder input. The importance of each feature is evaluated based on the scale of its benefits, importance to users, sufficiency of the feature, and whether the benefits can be substituted. Features at risk of flooding under a no active intervention scenario within the next 100 years are also identified using GIS data. The appendix is divided into two parts: part A covers the identification and assessment of issues and features, while part B establishes objectives for shoreline management.
Appendix g preferred management approach testing final_dec2010Severn Estuary
This document tests different management approaches for shoreline policy units along the Severn Estuary to help identify preferred policies. It analyzes how policy units interact through coastal processes and flooding, and assesses approaches against objectives. Management Approach A represents the initial starting point, Approach B prioritizes natural processes, Approach C protects assets, and Approach D continues current policies. Completing the approach tables helps determine the most appropriate long-term policy, which is identified in the SMP2 Final Report. The analysis aims to improve understanding of coastal change to inform planning and development decisions.
This document summarizes an economic appraisal of the preferred plan for the Severn Estuary Shoreline Management Plan Review (SMP2). It finds that:
1) Allowing natural coastal evolution with no active intervention would result in significant economic damages from flooding and loss of assets over time.
2) Implementing the preferred plan of maintaining or improving coastal defences would cost an estimated $15 million but would prevent substantial economic damages estimated at $30 million.
3) A high-level benefit-cost assessment finds the preferred plan is economically viable, with benefits expected to outweigh the costs. However, more detailed analysis will be required to justify specific future schemes.
Appendix c baseline understanding final_dec2010Severn Estuary
This document contains three parts that provide baseline information for the Severn Estuary Shoreline Management Plan Review (SMP2):
Part A assesses coastal processes and evolution in the estuary based on geology, geomorphology, hydrodynamics, and sediment transport.
Part B details existing coastal defences along the shoreline based on surveys and updates from local authorities. It considers residual life of defences over 20, 50, and 100 years.
Part C develops baseline scenarios of shoreline change under conditions of No Active Intervention (NAI) and With Present Management (WPM), taking into account climate change and potential defence failure over different time periods. It aims to improve understanding of coastal risks to inform SMP
The document provides an environmental assessment report for the Severn Estuary Shoreline Management Plan Review (SMP2). It summarizes the baseline environmental conditions in the study area, including populations and human health, biodiversity, fisheries, geology, land use, water, air and climate, cultural heritage, landscape and contaminated land. It then describes the strategic environmental assessment process undertaken to evaluate the potential environmental impacts of different shoreline management policies. This included developing objectives, consulting stakeholders, reviewing other relevant plans and strategies, and assessing alternative policy options. The preferred policies were selected and their impacts evaluated, including cumulative effects and mitigation measures. An implementation and monitoring plan was also developed to track effects relating to access and recreation, biodiversity
This document provides a Water Framework Directive (WFD) assessment of the Severn Estuary Shoreline Management Plan 2 (SMP2). It identifies the transitional, coastal, river, lake and groundwater bodies in the SMP2 area and assesses how the SMP2's preferred policies may impact the environmental objectives of the WFD. The assessment found that several management areas' policies have the potential to not fully meet some of the WFD objectives. It provides recommendations to better align some SMP boundaries with WFD waterbody boundaries. Overall, the assessment determines whether the SMP2's policies will help or hinder achieving the WFD's goals in different water bodies in the plan's coastal region.
Appendix f policy development and appraisal final_dec2010Severn Estuary
This document summarizes the initial approach taken to develop policy options for the Severn Estuary Shoreline Management Plan Review (SMP2). The coastline was divided into Policy Units based on land use, flood and erosion risk. Potential policy options were identified for each unit considering features and objectives. Multiple options were selected for later appraisal over three epochs (0-20, 20-50, 50-100 years) to assess impacts on coastal processes and features. The aim was to identify appropriate combinations of policies to appraise for the whole coast as interactions between locations are important to developing a sustainable long-term plan.
The document summarizes the Severn Estuary Shoreline Management Plan Review (SMP2). Key points include:
- The SMP2 proposes draft policies for managing the Severn Estuary shoreline over the next 100 years.
- It divides the shoreline into theme areas and policy units, with a preferred policy option chosen for each unit in three time periods.
- The main policy options are hold the line, no active intervention, and managed realignment.
- Climate change is a major consideration, as sea levels are projected to rise significantly over the century.
- The SMP2 aims to guide decisions on shoreline development in a sustainable way that considers risks to communities and
Appendix a development of the smp2 final_dec2010Severn Estuary
This document provides background information on the development of the second generation Shoreline Management Plan (SMP2) for the Severn Estuary. It discusses the purpose and process of SMPs, including considering longer timescales and factors like climate change. It also describes the relationship between the SMP2 and the parallel Flood Risk Management Strategy (SEFRMS) study. The SEFRMS will develop the policies in the SMP2 into more detailed coastal defence options. Finally, it briefly outlines the progress that has been made nationally on shoreline management planning since the first generation of SMPs.
Appendix b stakeholder engagement and consultation final_dec2010Severn Estuary
This document outlines the stakeholder engagement and consultation process for the Shoreline Management Plan Review (SMP2) of the Severn Estuary in the UK. It describes the various stakeholder groups involved, including a Client Steering Group, Elected Members Forum, and Key Stakeholders Group. It details the stages of stakeholder engagement during the SMP2 development and policy setting process, including identifying issues, developing policies, and public consultation. It also provides summaries of key stakeholder consultation events held from January to June 2009 to inform the SMP2 process.
Smp2 part b policy statements intro sections_finalSevern Estuary
This document summarizes changes in shoreline management policies between the SMP1 and the proposed SMP2 around the Severn Estuary. Key points:
- Policy changes are proposed upstream of the River Usk, around Congresbury Yeo, the Avon, Alvington, Sharpness, the upper Severn, and the Noose and Elmore areas.
- Changes reflect a better understanding of long-term tidal flood risks in these areas and opportunities to create new intertidal habitat.
- The potential outcomes of these policy changes over 50-100 years include allowing tidal flood risks to certain areas to be managed more naturally in the long run.
Appendix i part a sea annexes_final_dec2010Severn Estuary
The document reviews policies, plans, and programmes and their relevance to the Shoreline Management Plan Review. It identifies several pieces of EU and UK legislation related to environmental protection, water quality, waste management, and flood risk that the SMP2 will need to comply with. It also discusses national and regional planning documents in Wales, including strategies that address sustainable development, spatial planning, and the environment. The review concludes that the SMP2 process should seek opportunities to work with other organizations to deliver measures with environmental benefits and ensure planning incorporates the objectives and policies of the SMP2, including considering flood risk at a catchment scale.
Appendix k metadata and bibliographic database final_dec2010Severn Estuary
This document provides a bibliographic database of references used in developing the Severn Estuary Shoreline Management Plan Review (SMP2). It is divided into two parts: Part A lists key documents and reports produced for the SMP2, including the main SMP2 document and its appendices on development, stakeholder engagement, baseline understanding, theme review, policy development, and environmental assessments. Part B lists mapped data and digital information used in the SMP2, including policy maps, flood/erosion maps, and theme maps. The references provide transparency on the information and evidence base supporting the SMP2.
What is a Shoreline Management Plan?
Developed in partnership by local authorities, regulators and other stakeholders, a Shoreline Management Plan (SMP) is a high level non-statutory policy document designed to assist coastal flood and erosion risk management planning. It provides a large-scale assessment of the risks (to people, property, the natural and historic environment) associated with coastal erosion and flooding at the coast over the long-term. It also proposes policies to help manage these risks sustainably over the next hundred years.
The SMP enables planners and regulators to plan for and manage the way that the coast will change. This could be by maintaining or improving defences, by enabling the natural processes to play a greater role, creating new natural habitat or by helping areas that are at risk of flooding at some point in the future to cope with and limit the impact of flooding events.
The SMP2 for the Severn Estuary updates an earlier SMP1 (2000) for the estuary. It aims to provide more certainty for landowners, residents and businesses; to know how the coast will be managed by regulators during the next 100 years, so that they can plan ahead and make decisions about investments, homes, development and the management of their resources.
Smp2 part b policy statements bristol only_finalSevern Estuary
This document summarizes the preferred policies for coastal management in several policy units along the Severn Estuary in Bristol for three time periods: short term (0-20 years), medium term (20-50 years), and long term (50-100 years). The preferred policy for most units is Hold the Line (HTL), which means maintaining or replacing existing coastal defences to prevent coastal erosion and flooding. HTL is chosen to protect important infrastructure, economic assets, and residential areas from flooding while also considering environmental impacts like coastal squeeze and habitat loss over time with sea level rise. Maintaining defences is deemed economically viable but funding to do so is not guaranteed.
The document provides guidelines for the design of flood protection embankments. Some key points include:
1. The spacing between embankments on both river banks should not be less than 3 times the Lacey wetted perimeter for the design flood discharge.
2. The design high flood level should generally correspond to a 25-year flood for agricultural areas and a 100-year flood to protect towns.
3. A minimum freeboard of 1.5 meters over the design flood level should be provided, or 1.8 meters for higher discharges or aggrading rivers.
4. The top width of embankments should generally be 5 meters wide with 15-30 meter long turning platforms
Presentation by Hugh Walton of the GEF-UNDP Pacific Fisheries project 4746 at the 8th GEF Biennial International Waters Conference.
GEF Pillar 1.2 Promoting Transformational Change in Major Global Industries
Hugh Walton – Pacific Islands Forum Fisheries Agency
PRESENTATION OVERVIEW
Background - The FFA region
GEF OFMP – 2001 – 2004 & 2005 – 2011
Evaluation in the context of transformational change
OFMP 2 – 2015 – 2019 – Setting the stage for institutional change
Federal Consistency, Geographic Location Descriptions (GLDs) and Coastal & Ma...riseagrant
Federal Consistency, Geographic Location Descriptions (GLDs) and Coastal & Marine Spatial Planning (CMSP) presented May 25, 2011 at The Workshop to Learn Ocean Planning Tools and Techniques
Presentation by Katharine Otto, Southern Windsor County Regional Planning Commission, at the National Rural Transportation Conference, December 3 - 5, 2014 in Cincinnati, OH.
GAO - Surface Ships: Status of the Navy’s Phased Modernization PlanTom "Blad" Lindblad
The Navy originally proposed a Phased Modernization Plan in 2014 that would place 11 cruisers and 3 dock-landing ships into reduced operating status for up to 12 years for maintenance and modernization. However, in 2015 the Navy significantly revised the plan in response to congressional concerns about capacity shortfalls. The revised plan limits the number of cruisers in modernization status at one time to no more than 6, and the time per cruiser to no more than 4 years. The Navy did not consider formal alternatives to the original plan and revised it primarily to address congressional concerns about reduced fleet capacity.
The document discusses the US Army Corps of Engineers' approach to flood risk management. It advocates for a comprehensive, risk-informed systems approach that considers entire river basins and coastal zones. Key aspects include quantifying and communicating residual risks, fostering collaboration among stakeholders, and planning for long-term performance and resilience of flood protection systems. The Corps' actions include risk-informed decision making, communication of risk to the public, and taking a systems approach that considers interdependencies.
Community engagement on adaptation to sea level changeNeil Dufty
A change in mean sea levels will require new ways to estimate flood risk, and ways
to mitigate this risk. This paper looks at the process of developing Adaptation Plans,
which are suburb specific studies on the risks and options for potential sea level rise,
and the key component of successful adaptation planning, community engagement.
Many coastal decision makers are actively assessing options to manage coastal
flood risk that incorporates rising sea levels. These adaptation options are broadly
grouped into three categories - protect, accommodate or retreat and each option has
its costs and benefits. The mix of options chosen largely depends on the attitudes
and perspectives of the community at risk - without their support, decisions within a
democratic political system are unlikely to be successful.
This paper reports the findings of a large survey and series of workshops of ‘at risk’
residents within Lake Macquarie Local Government Area. The survey helped gauge
their preferences for management options and decision-making considerations.
Following on from this survey is the current work on community engagement as part
of developing Adaptation Plans. This engagement is using an innovative
collaborative approach to engaging the community on sea level rise and adaptation
that focuses on building the capacity of Council and the community to work together
to find a solution that sticks.
The usefulness of this research is to increase understanding on the key concerns of
community to coastal adaptation, and more effective collaborative engagement on a
topic that is often controversial. As a result, this work aims to develop management
strategies that are more appealing to those at risk and the wider community.
Planning for the Future: Sea Level Rise in CaliforniaLaura Rinaldi
This document discusses California's efforts to plan for and address sea level rise. It provides an overview of state guidance documents on sea level rise, coastal mapping projects to assess vulnerability, and modeling of climate change impacts. It also describes legislative hearings on sea level rise and the economy, as well as potential new funding sources for planning and projects. Key state agencies involved include the Coastal Commission, Coastal Conservancy, and Ocean Protection Council. Case studies highlight adaptation planning for the Bay Area, managed retreat projects, and assessing vulnerability of coastal infrastructure and ecosystems.
Smp2 part b policy statements lydney-glos only_finalSevern Estuary
This document summarizes the preferred policies for coastal management in Policy Units GLO 1, GLO 2, and GLO 3 along the west bank of the Severn Estuary from Lydney Harbour to Newnham Church. For GLO 1 and GLO 3, the preferred policy is No Active Intervention due to limited flood and erosion risk from the hard geology. For GLO 2, the preferred policy has Managed Realignment in the short-term to create new intertidal habitat, followed by Hold the Line policies in the medium and long-term to maintain the new flood defenses.
The document discusses the CLME+ Project which aims to facilitate ecosystem-based management in the Caribbean and North Brazil Shelf Large Marine Ecosystems for sustainable provision of goods and services from shared marine resources. It identifies three key problems throughout the regions: habitat degradation, unsustainable fisheries, and pollution. The CLME Strategic Action Programme was developed to address these issues through six main strategies. The project will enhance governance, build capacity for effective use of arrangements, demonstrate ecosystem-based approaches, and conduct region-wide monitoring and evaluation of the SAP implementation.
This document discusses the implementation of the Water Framework Directive (WFD) in the Western Wales River Basin District (WWRBD). It describes how monitoring and legislation around water quality has changed over time, with an increasing focus on integrated, holistic management of water bodies. Specifically:
1) Prior to the WFD, water quality in the WWRBD was monitored using different systems that did not provide an integrated view. The WFD established a common approach to monitoring water quality across Europe.
2) In the WWRBD, the WFD aims to improve water quality by reducing pollution from agriculture and industry and protecting habitats. This is expected to result in 27.7% of rivers achieving good status by
The document discusses alternatives being considered for a water master plan, including optimizing existing facilities, imported supplies, and desalination, as well as a proposed new alternative of a Colorado River conveyance. It provides details on analyses being done to evaluate the alternatives and develop the master plan, and recommends approving contract amendments and budget increases to further study the Colorado River conveyance alternative.
An integrated pipeline data and risk management system can turn data into useful information. It allows companies to manage increasing volumes of pipeline data in a centralized location, perform risk assessments to identify high risk segments, and develop integrity management plans. By aligning disparate data sources and dynamically segmenting pipelines, the system facilitates accurate data analysis and risk-based decision making to focus inspection and maintenance efforts on the areas of greatest need.
Paper 43 - Deep Water Pipeline CT 9_2_15John Grover
This document discusses the use of coiled tubing as down-lines for pre-commissioning deepwater pipelines. It compares coiled tubing to other down-line options like flexible lines. Coiled tubing has advantages over flexible lines in terms of cost, delivery time, deck space requirements, reliability, and ability to provide contingency. The document outlines the latest custom coiled tubing equipment being deployed, which is designed for large diameters of 2 7/8" or 3 1/2" pipe and to operate in water depths up to 3,000m. It was also designed to be road transportable and for flexible installation on vessels through a moonpool or over the side.
The document summarizes the Severn Estuary Shoreline Management Plan Review (SMP2). Key points include:
- The SMP2 proposes draft policies for managing the Severn Estuary shoreline over the next 100 years.
- It divides the shoreline into theme areas and policy units, with a preferred policy option chosen for each unit in three time periods.
- The main policy options are hold the line, no active intervention, and managed realignment.
- Climate change is a major consideration, as sea levels are projected to rise significantly over the century.
- The SMP2 aims to guide decisions on shoreline development in a sustainable way that considers risks to communities and
Appendix a development of the smp2 final_dec2010Severn Estuary
This document provides background information on the development of the second generation Shoreline Management Plan (SMP2) for the Severn Estuary. It discusses the purpose and process of SMPs, including considering longer timescales and factors like climate change. It also describes the relationship between the SMP2 and the parallel Flood Risk Management Strategy (SEFRMS) study. The SEFRMS will develop the policies in the SMP2 into more detailed coastal defence options. Finally, it briefly outlines the progress that has been made nationally on shoreline management planning since the first generation of SMPs.
Appendix b stakeholder engagement and consultation final_dec2010Severn Estuary
This document outlines the stakeholder engagement and consultation process for the Shoreline Management Plan Review (SMP2) of the Severn Estuary in the UK. It describes the various stakeholder groups involved, including a Client Steering Group, Elected Members Forum, and Key Stakeholders Group. It details the stages of stakeholder engagement during the SMP2 development and policy setting process, including identifying issues, developing policies, and public consultation. It also provides summaries of key stakeholder consultation events held from January to June 2009 to inform the SMP2 process.
Smp2 part b policy statements intro sections_finalSevern Estuary
This document summarizes changes in shoreline management policies between the SMP1 and the proposed SMP2 around the Severn Estuary. Key points:
- Policy changes are proposed upstream of the River Usk, around Congresbury Yeo, the Avon, Alvington, Sharpness, the upper Severn, and the Noose and Elmore areas.
- Changes reflect a better understanding of long-term tidal flood risks in these areas and opportunities to create new intertidal habitat.
- The potential outcomes of these policy changes over 50-100 years include allowing tidal flood risks to certain areas to be managed more naturally in the long run.
Appendix i part a sea annexes_final_dec2010Severn Estuary
The document reviews policies, plans, and programmes and their relevance to the Shoreline Management Plan Review. It identifies several pieces of EU and UK legislation related to environmental protection, water quality, waste management, and flood risk that the SMP2 will need to comply with. It also discusses national and regional planning documents in Wales, including strategies that address sustainable development, spatial planning, and the environment. The review concludes that the SMP2 process should seek opportunities to work with other organizations to deliver measures with environmental benefits and ensure planning incorporates the objectives and policies of the SMP2, including considering flood risk at a catchment scale.
Appendix k metadata and bibliographic database final_dec2010Severn Estuary
This document provides a bibliographic database of references used in developing the Severn Estuary Shoreline Management Plan Review (SMP2). It is divided into two parts: Part A lists key documents and reports produced for the SMP2, including the main SMP2 document and its appendices on development, stakeholder engagement, baseline understanding, theme review, policy development, and environmental assessments. Part B lists mapped data and digital information used in the SMP2, including policy maps, flood/erosion maps, and theme maps. The references provide transparency on the information and evidence base supporting the SMP2.
What is a Shoreline Management Plan?
Developed in partnership by local authorities, regulators and other stakeholders, a Shoreline Management Plan (SMP) is a high level non-statutory policy document designed to assist coastal flood and erosion risk management planning. It provides a large-scale assessment of the risks (to people, property, the natural and historic environment) associated with coastal erosion and flooding at the coast over the long-term. It also proposes policies to help manage these risks sustainably over the next hundred years.
The SMP enables planners and regulators to plan for and manage the way that the coast will change. This could be by maintaining or improving defences, by enabling the natural processes to play a greater role, creating new natural habitat or by helping areas that are at risk of flooding at some point in the future to cope with and limit the impact of flooding events.
The SMP2 for the Severn Estuary updates an earlier SMP1 (2000) for the estuary. It aims to provide more certainty for landowners, residents and businesses; to know how the coast will be managed by regulators during the next 100 years, so that they can plan ahead and make decisions about investments, homes, development and the management of their resources.
Smp2 part b policy statements bristol only_finalSevern Estuary
This document summarizes the preferred policies for coastal management in several policy units along the Severn Estuary in Bristol for three time periods: short term (0-20 years), medium term (20-50 years), and long term (50-100 years). The preferred policy for most units is Hold the Line (HTL), which means maintaining or replacing existing coastal defences to prevent coastal erosion and flooding. HTL is chosen to protect important infrastructure, economic assets, and residential areas from flooding while also considering environmental impacts like coastal squeeze and habitat loss over time with sea level rise. Maintaining defences is deemed economically viable but funding to do so is not guaranteed.
The document provides guidelines for the design of flood protection embankments. Some key points include:
1. The spacing between embankments on both river banks should not be less than 3 times the Lacey wetted perimeter for the design flood discharge.
2. The design high flood level should generally correspond to a 25-year flood for agricultural areas and a 100-year flood to protect towns.
3. A minimum freeboard of 1.5 meters over the design flood level should be provided, or 1.8 meters for higher discharges or aggrading rivers.
4. The top width of embankments should generally be 5 meters wide with 15-30 meter long turning platforms
Presentation by Hugh Walton of the GEF-UNDP Pacific Fisheries project 4746 at the 8th GEF Biennial International Waters Conference.
GEF Pillar 1.2 Promoting Transformational Change in Major Global Industries
Hugh Walton – Pacific Islands Forum Fisheries Agency
PRESENTATION OVERVIEW
Background - The FFA region
GEF OFMP – 2001 – 2004 & 2005 – 2011
Evaluation in the context of transformational change
OFMP 2 – 2015 – 2019 – Setting the stage for institutional change
Federal Consistency, Geographic Location Descriptions (GLDs) and Coastal & Ma...riseagrant
Federal Consistency, Geographic Location Descriptions (GLDs) and Coastal & Marine Spatial Planning (CMSP) presented May 25, 2011 at The Workshop to Learn Ocean Planning Tools and Techniques
Presentation by Katharine Otto, Southern Windsor County Regional Planning Commission, at the National Rural Transportation Conference, December 3 - 5, 2014 in Cincinnati, OH.
GAO - Surface Ships: Status of the Navy’s Phased Modernization PlanTom "Blad" Lindblad
The Navy originally proposed a Phased Modernization Plan in 2014 that would place 11 cruisers and 3 dock-landing ships into reduced operating status for up to 12 years for maintenance and modernization. However, in 2015 the Navy significantly revised the plan in response to congressional concerns about capacity shortfalls. The revised plan limits the number of cruisers in modernization status at one time to no more than 6, and the time per cruiser to no more than 4 years. The Navy did not consider formal alternatives to the original plan and revised it primarily to address congressional concerns about reduced fleet capacity.
The document discusses the US Army Corps of Engineers' approach to flood risk management. It advocates for a comprehensive, risk-informed systems approach that considers entire river basins and coastal zones. Key aspects include quantifying and communicating residual risks, fostering collaboration among stakeholders, and planning for long-term performance and resilience of flood protection systems. The Corps' actions include risk-informed decision making, communication of risk to the public, and taking a systems approach that considers interdependencies.
Community engagement on adaptation to sea level changeNeil Dufty
A change in mean sea levels will require new ways to estimate flood risk, and ways
to mitigate this risk. This paper looks at the process of developing Adaptation Plans,
which are suburb specific studies on the risks and options for potential sea level rise,
and the key component of successful adaptation planning, community engagement.
Many coastal decision makers are actively assessing options to manage coastal
flood risk that incorporates rising sea levels. These adaptation options are broadly
grouped into three categories - protect, accommodate or retreat and each option has
its costs and benefits. The mix of options chosen largely depends on the attitudes
and perspectives of the community at risk - without their support, decisions within a
democratic political system are unlikely to be successful.
This paper reports the findings of a large survey and series of workshops of ‘at risk’
residents within Lake Macquarie Local Government Area. The survey helped gauge
their preferences for management options and decision-making considerations.
Following on from this survey is the current work on community engagement as part
of developing Adaptation Plans. This engagement is using an innovative
collaborative approach to engaging the community on sea level rise and adaptation
that focuses on building the capacity of Council and the community to work together
to find a solution that sticks.
The usefulness of this research is to increase understanding on the key concerns of
community to coastal adaptation, and more effective collaborative engagement on a
topic that is often controversial. As a result, this work aims to develop management
strategies that are more appealing to those at risk and the wider community.
Planning for the Future: Sea Level Rise in CaliforniaLaura Rinaldi
This document discusses California's efforts to plan for and address sea level rise. It provides an overview of state guidance documents on sea level rise, coastal mapping projects to assess vulnerability, and modeling of climate change impacts. It also describes legislative hearings on sea level rise and the economy, as well as potential new funding sources for planning and projects. Key state agencies involved include the Coastal Commission, Coastal Conservancy, and Ocean Protection Council. Case studies highlight adaptation planning for the Bay Area, managed retreat projects, and assessing vulnerability of coastal infrastructure and ecosystems.
Smp2 part b policy statements lydney-glos only_finalSevern Estuary
This document summarizes the preferred policies for coastal management in Policy Units GLO 1, GLO 2, and GLO 3 along the west bank of the Severn Estuary from Lydney Harbour to Newnham Church. For GLO 1 and GLO 3, the preferred policy is No Active Intervention due to limited flood and erosion risk from the hard geology. For GLO 2, the preferred policy has Managed Realignment in the short-term to create new intertidal habitat, followed by Hold the Line policies in the medium and long-term to maintain the new flood defenses.
The document discusses the CLME+ Project which aims to facilitate ecosystem-based management in the Caribbean and North Brazil Shelf Large Marine Ecosystems for sustainable provision of goods and services from shared marine resources. It identifies three key problems throughout the regions: habitat degradation, unsustainable fisheries, and pollution. The CLME Strategic Action Programme was developed to address these issues through six main strategies. The project will enhance governance, build capacity for effective use of arrangements, demonstrate ecosystem-based approaches, and conduct region-wide monitoring and evaluation of the SAP implementation.
This document discusses the implementation of the Water Framework Directive (WFD) in the Western Wales River Basin District (WWRBD). It describes how monitoring and legislation around water quality has changed over time, with an increasing focus on integrated, holistic management of water bodies. Specifically:
1) Prior to the WFD, water quality in the WWRBD was monitored using different systems that did not provide an integrated view. The WFD established a common approach to monitoring water quality across Europe.
2) In the WWRBD, the WFD aims to improve water quality by reducing pollution from agriculture and industry and protecting habitats. This is expected to result in 27.7% of rivers achieving good status by
The document discusses alternatives being considered for a water master plan, including optimizing existing facilities, imported supplies, and desalination, as well as a proposed new alternative of a Colorado River conveyance. It provides details on analyses being done to evaluate the alternatives and develop the master plan, and recommends approving contract amendments and budget increases to further study the Colorado River conveyance alternative.
An integrated pipeline data and risk management system can turn data into useful information. It allows companies to manage increasing volumes of pipeline data in a centralized location, perform risk assessments to identify high risk segments, and develop integrity management plans. By aligning disparate data sources and dynamically segmenting pipelines, the system facilitates accurate data analysis and risk-based decision making to focus inspection and maintenance efforts on the areas of greatest need.
Paper 43 - Deep Water Pipeline CT 9_2_15John Grover
This document discusses the use of coiled tubing as down-lines for pre-commissioning deepwater pipelines. It compares coiled tubing to other down-line options like flexible lines. Coiled tubing has advantages over flexible lines in terms of cost, delivery time, deck space requirements, reliability, and ability to provide contingency. The document outlines the latest custom coiled tubing equipment being deployed, which is designed for large diameters of 2 7/8" or 3 1/2" pipe and to operate in water depths up to 3,000m. It was also designed to be road transportable and for flexible installation on vessels through a moonpool or over the side.
Smp2 part b policy statements tidenham only_finalSevern Estuary
This document summarizes the preferred policies for two policy units - TID 1 and TID 2 - along the Severn Estuary coastline in Gloucestershire. For TID 1, the preferred policy is No Active Intervention for all three epochs (0-20 years, 20-50 years, and 50-100 years) as the mudstone cliffs are expected to undergo only limited erosion. For TID 2, the preferred policies are Hold the Line for the first two epochs, and Managed Realignment for the third epoch, as new defences may need to be constructed further inland to manage increasing flood risks in the long term.
This document discusses advances in pre-commissioning of subsea and deepwater pipelines. It describes challenges of testing pipelines without surface connections and reviews technologies like remote flooding modules and smart gauge tools to enable subsea testing. Using a case study of an 8km, 16" pipeline at 1,000m depth, it analyzes vessel requirements and costs of traditional vessel-based systems versus newer remote flooding modules. The remote flooding module reduces vessel time on site from 77 hours to 9 hours, space needs from 290m2 to 32m2, and eliminates the 48 hour water temperature stabilization period to lower overall project costs.
PII Paper for PetroMin Gas Pipeline ConferenceJohn Grover
Pipelines deteriorate over time due to corrosion and fatigue, threatening their integrity. To manage this risk, operators have implemented inspection and maintenance programs using intelligent pigs to detect corrosion. These programs were limited until PII pioneered Total Pipeline Integrity solutions combining affordable technology, methodology, and expertise. The paper discusses the history of pipeline inspection technology advances pioneered by PII, from the first magnetic flux tool in the 1970s to current tools, enabling operators to effectively manage pipeline integrity.
This document discusses the various uses of industrial gases, particularly liquid nitrogen, in the offshore oil and gas industry. It provides an overview of downhole and topside applications of gases, focusing on nitrogen/helium leak testing which is a large market. The document discusses offshore equipment for transporting, storing, and vaporizing cryogenic liquids as well as typical gas consumption amounts. It analyzes the growth potential in areas like Qatar, UAE, and India as offshore natural gas developments increase.
This document discusses how pipeline installation and pre-commissioning can impact future pipeline integrity if not properly managed. Specifically, it examines common issues like corrosion from seawater ingress during installation, inadequate cleaning, and hydrotesting. One case study describes over 80 tons of debris and corrosion products removed from a line that flooded with seawater during installation. The document stresses that operators should be aware of how early-life issues can negatively affect integrity over the long-term if not properly mitigated during pre-commissioning.
Tasnia Tabassum is a recent graduate of the University of Dhaka with a B.Sc. in Leather Products Engineering. She has excellent communication skills and can work independently or in a team. Her objectives are to work in a challenging environment where she can be creative and take on responsibility. She has strong computer skills including Microsoft Office, graphics programs, and experience with data entry. She is fluent in English and Bengali and has good spoken Hindi. Her hobbies include new technology and Google. She is currently residing in Dhaka and is looking for a reference.
Smp2 part b policy statements kingston seymour only_finalSevern Estuary
This document summarizes coastal management plans for several policy units along the east bank of the River Severn in England. For unit KIN 1, the preferred policy is managed realignment over all three epochs (0-20 years, 20-50 years, and 50-100 years) to allow for habitat creation and reduced flood risk. For unit KIN 2, the preferred policy is no active intervention for all epochs due to naturally stable geology. For unit KIN 3, the preferred policy is hold the line for all epochs to maintain protective sand dunes and manage flood risk to properties.
This document discusses the use of coiled tubing systems for pre-commissioning deepwater pipelines. It describes how coiled tubing can serve as a down-line connection between a surface vessel and subsea pipeline for injecting fluids like air, nitrogen and MEG during pre-commissioning. It outlines the design of a customized coiled tubing system capable of operating in depths up to 3,000m, and describes challenges like fatigue from current movements that were addressed through modeling and engineering solutions like adding a bend stiffener. The document concludes that coiled tubing is a preferred down-line solution and discusses its use for partial subsea dewatering as a faster contingency option than a full dewatering spread.
The document summarizes the pre-commissioning of the Nord Stream natural gas pipelines, which transport natural gas from Russia to Germany. Some key points:
- Nord Stream consists of two 1,224 km pipelines running along the Baltic Sea floor, the longest single-section offshore pipelines ever built.
- Pre-commissioning included flooding the pipelines with water, cleaning and gauging them using pigs, then pressure testing and dewatering prior to gas commissioning.
- Effective planning was required to coordinate the complex offshore and onshore pre-commissioning activities given constraints like winter freezing of the Baltic Sea.
- Offshore operations used a vessel-based spread for flooding, cleaning and gauging. On
The document discusses the pre-commissioning of the Nord Stream gas pipeline project, which included flooding, cleaning, gauging, pressure testing, dewatering, drying, and nitrogen purging of the 1,224 km twin pipeline system. Key achievements of the pre-commissioning included setting records for the longest single dewatering run and lowest residual water film thickness, completing the work for the first pipeline ahead of schedule, and achieving excellent pig tracking and test results with no indications of issues. The project demonstrated the successful application of vessel-based pre-commissioning for a large, complex subsea pipeline system.
This document discusses the use of coiled tubing as down-lines for pre-commissioning deepwater pipelines and contingency dewatering. It describes how coiled tubing is advantageous compared to composite flexible hose as a down-line option. The document also details how coiled tubing can be used to partially dewater a section of pipeline in the event of a wet buckle, providing a faster and lower-cost alternative to fully dewatering the entire pipeline. In conclusion, the document advocates for considering coiled tubing as the preferred down-line solution and notes its current use in several countries for deepwater pipeline pre-commissioning and contingency applications.
Smp2 part b policy statements sharpness-sev cross only_finalSevern Estuary
The document summarizes the preferred policies for six policy units along the Severn Estuary shoreline from Sharpness to Severn Crossings. The preferred policy for all units over all time periods (0-20, 20-50, 50-100 years) is Hold the Line (HTL) to manage flood risk and protect critical infrastructure like nuclear power stations. HTL involves maintaining and replacing existing flood defenses but does not guarantee funding to address future risks from sea level rise. Coastal squeeze is expected to increase due to HTL, reducing intertidal habitats over time.
Este documento presenta un mapa conceptual para la planeación de una clase. Explica que la planeación requiere un marco teórico, metodología, valores fundamentales como el respeto y la responsabilidad, conocimientos básicos, habilidades de pensamiento e infraestructura. También considera factores como las disposiciones reglamentarias, técnicas de enseñanza, situación de los alumnos y limitaciones personales del docente. Finalmente, proporciona referencias bibliográficas sobre metodologías constructivistas y cuadros sin
Smp2 part b policy statements wentlooge only_finalSevern Estuary
This document provides local details for two policy units, WEN1 and WEN2, located along the Severn Estuary in the context of the wider SMP policy. For both units, the preferred policy is to hold the line over the short (0-20 years), medium (20-50 years) and long (50-100 years) term. This involves maintaining and replacing existing flood defences to protect agricultural land, infrastructure, and communities from flooding and erosion due to sea level rise, while seeking opportunities to mitigate environmental impacts through managed realignment.
Smp2 part b policy statements cardiff only_finalSevern Estuary
The document outlines policies for three policy units along the Cardiff coastline in Wales:
1) CAR 1 focuses on Cardiff Bay Barrage and prefers a long-term policy of holding the line to maintain defences and manage flood risk.
2) CAR 2 covers an area west of Cardiff Bay and also prefers holding the line to maintain earth embankments and manage flood risk to urban areas.
3) CAR 3 covers both banks of the River Rhymney and prefers holding the line to maintain defences and manage flood risk, including to a landfill site.
The policies aim to balance flood protection for communities with potential environmental impacts like coastal squeeze over the long term.
Smp2 part b policy statements caldicot only_finalSevern Estuary
This document summarizes the preferred policies for three policy units in the Caldicot Levels area of the Severn Estuary:
- CALD 1 (Uskmouth Power Station point to Sudbrook point) will have a Hold the Line policy to protect coastal defences and maintain flood protection for infrastructure and development.
- CALD 2 (Sudbrook point to Black Rock) will have a No Active Intervention policy as high ground and geology limit flood and erosion risks.
- CALD 3 (Black Rock to River Wye) is not described.
This presentation was given as part of the EPA-funded Catchment Science and Management Course focusing on Integrated Catchment Management, held in June 2015. This course was delivered by RPS Consultants. If you have any queries or comments, or wish to use the material in this presentation, please contact catchments@epa.ie
It is increasingly being recognised internationally that integrated catchment management (ICM) is a useful organising framework for tackling the ongoing challenge of balancing sustainable use and development of our natural resource, against achieving environmental goals. The basic principles of ICM (Williams, 2012) are to:
• Take a holistic and integrated approach to the management of land, biodiversity, water and community resources at the water catchment scale;
• Involve communities in planning and managing their landscapes; and
• Find a balance between resource use and resource conservation
ICM is now well established in Australia, New Zealand, and the United States. In Europe the ICM approach has been proposed as being required to achieve effective water and catchment management, and is the approach being promoted by DEFRA for the UK, where it is called the “Catchment Based Approach” (CaBA). The principles and methodologies behind ICM sit well within the context of the Water Framework Directive with its aims and objectives for good water quality, sustainable development and public participation in water resource management. In Ireland it is proposed that the ICM approach will underlie the work and philosophy in developing and implementing future River Basin Management Plans.
Smp2 part b policy statements glos-sharpness only_finalSevern Estuary
This document provides local details for several policy units along the Gloucester to Sharpness area of the Severn Estuary in England. It summarizes the preferred policies for coastal management over three time periods (epochs) from present day to 100 years in the future. The preferred policies are generally to hold the existing flood defense line until defenses need replenishing, then allow managed realignment to create intertidal habitat while maintaining a new secondary defense line. This will involve breaching existing defenses to allow approximately 350 hectares of agricultural land to flood but will reduce risk to assets behind the new defenses.
Smp2 part b policy statements glos-haw bridge only_finalSevern Estuary
The document provides local details for several policy units along the Severn Estuary between Gloucester and Haw Bridge. For policy unit MAI 1, the preferred policy is managed realignment for the first epoch to allow habitat creation by establishing a new set back defense line, then hold the line for the next two epochs to maintain the new defenses. For policy unit MAI 2, the preferred policy is hold the line for all three epochs to maintain existing and new defenses along this reach. For policy unit MAI 3, the preferred policy for the first epoch is no active intervention since there is limited flood risk, but mitigation may be considered for some properties.
SLIPP Shoreline Care Contractors Outreach Meeting 24 November 2011Erin Vieira
The document summarizes a workshop on shoreline management near Shuswap Lake. It discusses the importance of protecting shoreline ecosystems, an overview of regulations for working near shorelines, and examples of how to apply the Shoreline Management Guidelines for proposed activities like installing a waterline, building a retaining wall, or constructing a private dock. The Guidelines provide a process for identifying habitat sensitivity, rating project risk, and determining any required permits or reviews.
C5.02: The Global Ocean Acidification Observing Network: data for decisions -...Blue Planet Symposium
Ocean acidification describes the changes in seawater chemistry that result from the uptake of anthropogenic carbon dioxide by the ocean. The changes this century are predicted to have profound impacts on marine ecosystems with potential flow-on effects to economic and environmental services the ecosystems provide, including fisheries and aquaculture, coastal protection, and tourism. The Global Ocean Acidification - Observing Network (GOA-ON) has been developed in response to the widespread concern of the impacts of ocean acidification. The network is an internationally coordinated effort, combining ‘bottom up’ collaboration by the research community with ‘top down’ encouragement and support from a range of international bodies and organisations, including the Intergovernmental Oceanographic Commission (UNESCO-IOC), the International Atomic Energy Agency (IAEA), and the Global Ocean Observing System (GOOS). The aim is to provide chemical and biological data from local to global scales that can be used to improve understanding of ocean acidification conditions and ecosystem responses, and to provide uniformly collected and quality-controlled data to assist policy making through research products and model-based projections of ecosystem responses. Capability development is a key aspect of the network. The status and future plans of the GOA-ON initiative will be described – providing the opportunity for additional involvement in its implementation.
Smp2 part b policy statements newport-usk only_finalSevern Estuary
This document summarizes the local coastal management plan for an area along the Severn Estuary in South Wales, including the city of Newport. It outlines 5 policy units - NEW 1 to NEW 5 - and describes the preferred coastal management policies for each over the next 100 years to balance flood risk management with nature conservation and development needs. The key drivers are international nature sites, critical infrastructure like railways and ports, and residential areas. For units NEW 1 and NEW 2, which border Newport, the preferred long-term policy is to "Hold the Line" and maintain existing flood defenses to protect properties and infrastructure. For unit NEW 3 along the River Usk, the plan shifts to "No Active Intervention" and then "Managed
The document outlines the environmental impact assessment (EIA) procedure and requirements in Malaysia, including describing what activities require an EIA, the EIA process, guidelines for site selection, and relevant laws and appendices on prescribed activities requiring an EIA and the Environmental Quality Act. The EIA process in Malaysia aims to identify and mitigate potential environmental impacts of development projects through assessing proposed activities, consulting stakeholders, and obtaining approval from the Department of Environment.
The document outlines the environmental impact assessment (EIA) procedure and requirements in Malaysia, including describing what activities require an EIA, the EIA process, guidelines for site selection, and relevant laws and appendices on prescribed activities requiring an EIA and the Environmental Quality Act. The EIA process in Malaysia aims to identify and mitigate potential environmental impacts of development projects through assessing proposed activities, consulting stakeholders, and obtaining approval from the Department of Environment.
Shoreline Change Special Area Management Plan (Beach SAMP) Stakeholder Meeting. Held on July 14, 2015. The purpose of the meeting was to review progress to date on development of tools, and discuss the next phase of the Beach SAMP porject.
This document summarizes the development of a new self-regulating tide gate (SRT) design by the Environment Agency. Key points:
- The SRT allows controlled tidal exchange to restore intertidal habitats while maintaining flood protection. Previous proprietary designs had to be imported.
- The new design is float-operated and adaptable to different locations. Prototypes were installed at Seaton, Devon and Lymington, Hampshire to demonstrate uses.
- The design meets criteria for being locally produced, fail-safe, low maintenance, and facilitating fish passage. Monitoring shows it operates automatically in response to tides as intended.
The document provides the terms of reference for conducting an environmental impact assessment study of the proposed Ken-Betwa link project in India. The scope of work includes assessing the positive and adverse environmental impacts of the project, preparing an environmental management plan to mitigate negative effects, and developing a resettlement and rehabilitation plan for project-affected people. Key project components are the construction of Daudhan Dam on the Ken River and a 231 km long link canal connecting to the Betwa River basin.
Smp2 part b policy statements portishead only_finalSevern Estuary
This document provides local details for shoreline management in four policy units along the east bank of the River Severn from Portishead to Clevedon. The preferred policy for all four policy units from the present day to 2100 is No Active Intervention (NAI) as the high ground and hard geology naturally limit flood and erosion risk. NAI will allow natural processes to continue with limited impact on coastal assets and intertidal habitats. The rate of erosion will be monitored and actions may be considered if erosion increases and puts assets at risk.
Mangrove Restoration Monitoring Plan FinalIan Kissoon
The monitoring plan outlines data collection strategies to evaluate the success of mangrove restoration efforts in Guyana. The plan aims to 1) verify that 11km of coastline has been replanted/protected by September 2012 and 2) determine factors influencing the success or failure of replanting sites. Data on seedling survival, plant growth, anthropogenic activities, soil type, topography, wave energy, salinity, and pH will be collected regularly at replanted and natural sites. Community rangers will monitor sites and record data to be analyzed and reported on annually to assess progress towards project goals and inform future restoration efforts.
ACOE Coastal Storm Management Alternative for Jamaica Bay Communitiesecowatchers
The document summarizes plans for managing coastal storm risk in Jamaica Bay, New York. It discusses the US Army Corps of Engineers' process for formulating alternatives, addressing sea level rise, and evaluating alternatives for the East Rockaway Inlet to Rockaway Inlet and Jamaica Bay reach. High-level details are provided on recommended plans for the Atlantic shorefront, Back Bay flooding risk reduction features, and nature-based features in Jamaica Bay. The schedule and opportunities for public involvement in the ongoing New York-New Jersey Harbor and Tributaries Coastal Storm Risk Management Feasibility Study are also outlined.
Similar to Appendix i part b _hra_final_dec2010 (20)
Improving the viability of probiotics by encapsulation methods for developmen...Open Access Research Paper
The popularity of functional foods among scientists and common people has been increasing day by day. Awareness and modernization make the consumer think better regarding food and nutrition. Now a day’s individual knows very well about the relation between food consumption and disease prevalence. Humans have a diversity of microbes in the gut that together form the gut microflora. Probiotics are the health-promoting live microbial cells improve host health through gut and brain connection and fighting against harmful bacteria. Bifidobacterium and Lactobacillus are the two bacterial genera which are considered to be probiotic. These good bacteria are facing challenges of viability. There are so many factors such as sensitivity to heat, pH, acidity, osmotic effect, mechanical shear, chemical components, freezing and storage time as well which affects the viability of probiotics in the dairy food matrix as well as in the gut. Multiple efforts have been done in the past and ongoing in present for these beneficial microbial population stability until their destination in the gut. One of a useful technique known as microencapsulation makes the probiotic effective in the diversified conditions and maintain these microbe’s community to the optimum level for achieving targeted benefits. Dairy products are found to be an ideal vehicle for probiotic incorporation. It has been seen that the encapsulated microbial cells show higher viability than the free cells in different processing and storage conditions as well as against bile salts in the gut. They make the food functional when incorporated, without affecting the product sensory characteristics.
Kinetic studies on malachite green dye adsorption from aqueous solutions by A...Open Access Research Paper
Water polluted by dyestuffs compounds is a global threat to health and the environment; accordingly, we prepared a green novel sorbent chemical and Physical system from an algae, chitosan and chitosan nanoparticle and impregnated with algae with chitosan nanocomposite for the sorption of Malachite green dye from water. The algae with chitosan nanocomposite by a simple method and used as a recyclable and effective adsorbent for the removal of malachite green dye from aqueous solutions. Algae, chitosan, chitosan nanoparticle and algae with chitosan nanocomposite were characterized using different physicochemical methods. The functional groups and chemical compounds found in algae, chitosan, chitosan algae, chitosan nanoparticle, and chitosan nanoparticle with algae were identified using FTIR, SEM, and TGADTA/DTG techniques. The optimal adsorption conditions, different dosages, pH and Temperature the amount of algae with chitosan nanocomposite were determined. At optimized conditions and the batch equilibrium studies more than 99% of the dye was removed. The adsorption process data matched well kinetics showed that the reaction order for dye varied with pseudo-first order and pseudo-second order. Furthermore, the maximum adsorption capacity of the algae with chitosan nanocomposite toward malachite green dye reached as high as 15.5mg/g, respectively. Finally, multiple times reusing of algae with chitosan nanocomposite and removing dye from a real wastewater has made it a promising and attractive option for further practical applications.
Evolving Lifecycles with High Resolution Site Characterization (HRSC) and 3-D...Joshua Orris
The incorporation of a 3DCSM and completion of HRSC provided a tool for enhanced, data-driven, decisions to support a change in remediation closure strategies. Currently, an approved pilot study has been obtained to shut-down the remediation systems (ISCO, P&T) and conduct a hydraulic study under non-pumping conditions. A separate micro-biological bench scale treatability study was competed that yielded positive results for an emerging innovative technology. As a result, a field pilot study has commenced with results expected in nine-twelve months. With the results of the hydraulic study, field pilot studies and an updated risk assessment leading site monitoring optimization cost lifecycle savings upwards of $15MM towards an alternatively evolved best available technology remediation closure strategy.
Optimizing Post Remediation Groundwater Performance with Enhanced Microbiolog...Joshua Orris
Results of geophysics and pneumatic injection pilot tests during 2003 – 2007 yielded significant positive results for injection delivery design and contaminant mass treatment, resulting in permanent shut-down of an existing groundwater Pump & Treat system.
Accessible source areas were subsequently removed (2011) by soil excavation and treated with the placement of Emulsified Vegetable Oil EVO and zero-valent iron ZVI to accelerate treatment of impacted groundwater in overburden and weathered fractured bedrock. Post pilot test and post remediation groundwater monitoring has included analyses of CVOCs, organic fatty acids, dissolved gases and QuantArray® -Chlor to quantify key microorganisms (e.g., Dehalococcoides, Dehalobacter, etc.) and functional genes (e.g., vinyl chloride reductase, methane monooxygenase, etc.) to assess potential for reductive dechlorination and aerobic cometabolism of CVOCs.
In 2022, the first commercial application of MetaArray™ was performed at the site. MetaArray™ utilizes statistical analysis, such as principal component analysis and multivariate analysis to provide evidence that reductive dechlorination is active or even that it is slowing. This creates actionable data allowing users to save money by making important site management decisions earlier.
The results of the MetaArray™ analysis’ support vector machine (SVM) identified groundwater monitoring wells with a 80% confidence that were characterized as either Limited for Reductive Decholorination or had a High Reductive Reduction Dechlorination potential. The results of MetaArray™ will be used to further optimize the site’s post remediation monitoring program for monitored natural attenuation.
Optimizing Post Remediation Groundwater Performance with Enhanced Microbiolog...
Appendix i part b _hra_final_dec2010
1. Severn Estuary SMP2 – Appendix I – Part B – Habitats Regulation Assessment
i
Severn Estuary SMP Review
Appendix I: Part B - Habitat
Regulations Assessment
2. Severn Estuary SMP2 – Appendix I – Part B – Habitats Regulation Assessment
ii
Severn Estuary SMP Review
Notice
This report was produced by Atkins Ltd for the Severn Estuary Coastal Group for the specific purpose of the
Severn Estuary SMP2.
This report may not be used by any person other than the Severn Estuary Coastal Group without the Severn
Estuary Coastal Group’s express permission. In any event, Atkins accepts no liability for any costs, liabilities
or losses arising as a result of the use of or reliance upon the contents of this report by any person other
than the Severn Estuary Coastal Group.
Document History
JOB NUMBER: 5078599 DOCUMENT REF: 5078599
1.0 For Review SP KRH KRH JMC 06/05/10
2.0 For QRG SP KRH KRH JMC 27/05/10
3.0 Final SP KRH KRH RS Dec 2010
Revision Purpose Description Originated Checked Reviewed Authorised Date
3. Severn Estuary SMP2 – Appendix I – Part B – Habitats Regulation Assessment
iii
Severn Estuary SMP Review
Contents
1. INTRODUCTION ...................................................................................1
2. STAGE 1 ASSESSMENT .......................................................................2
2.1 Consideration of Sites ...............................................................................................2
2.2 Conclusion of Stage 1 Assessment........................................................................... 5
3. STAGE 2 ASSESSMENT .......................................................................6
4. STAGE 3 ASSESSMENT – ASSESSMENT OF ADVERSE EFFECT ON SITE
INTEGRITY................................................................................................45
4.1 Summary of Conclusions of Stage 2 Assessment...................................................... 45
4.2 Appropriate Assessment Record............................................................................. 51
4.3 Conclusion of Stage 3 Assessment......................................................................... 62
5.0 PART B: FINAL APPROPRIATE ASSESSMENT RECORD: SEVERN
ESTUARY SMP2 (MAY 2010) ...................................................................65
4. Severn Estuary SMP2 – Appendix I – Part B – Habitats Regulation Assessment
Severn Estuary SMP Review 1
Severn Estuary Shoreline Management Plan Review
Habitats Regulations Assessment
March 2010
1. Introduction
The Severn Estuary Shoreline Management Plan Review (SMP2) has the potential to affect a
number of European sites (Special Protection Areas (SPAs), Special Areas of Conservation (SACs)
and Ramsar sites) located across the estuary. The European Union Birds Directive (79/409/EEC)
and Habitats Directive (92/43/EEC) (under which these sites are designated) are implemented in the
UK by the Conservation of Habitats and Species Regulations 2010 (SI 290) (also known as the
Habitats Regulations), which consolidate and update the Conservation (Natural Habitats, &c.)
Regulations 1994 (the 1994 Regulations).
Section 61 of the Habitats Regulations requires that a competent authority, before deciding to
undertake, or give any consent, permission or other authorisation for a plan or project which is likely
to have a significant effect on a European site in Great Britain (either alone or in combination with
other plans or projects) shall make an appropriate assessment of the implications for the site in view
of that site's conservation objectives.
This document is a record of the Habitats Regulations Assessment undertaken for the Severn
Estuary Shoreline Management Plan Review (SMP2). In undertaking this assessment the
Environment Agency EU Habitats and Birds Directive Handbook has been used to provide guidance
on the approach to the assessment and the format of the report.
The HRA process can be broken down into four stages:
• Stage 1 : Determine whether the plan is relevant and identify the Competent Authority and
scope which sites are going to be assessed, along with a rationale for decisions made;
• Stage 2 : Assess whether the plan is likely to have a significant effect on a European site
alone or in combination with other plans or projects;
• Stage 3 : Where required, assess adverse effect on site integrity (Appropriate Assessment);
• Stages 4 & 5: Where the Appropriate Assessment (Stage 3) is unable to conclude that the
plan or project does not adversely affect the integrity of the Natura 2000 site, the plan or
project may only be adopted if it can be demonstrated that there are no alternative solutions
that would have a lesser effect on the Natura 2000 site; and, if there are no alternative
solutions, there must be imperative reasons of overriding public interest (IROPI) for adopting
the plan or project; compensatory measures also need to be identified.
The HRA has been informed by predicted future changes in flood and erosion risk, derived from
modelling and assessment undertaken as part of the development of the SMP2; this work is detailed
in Appendix C of the SMP2 Report: Baseline Understanding of Coastal Behaviour and Dynamics.
One of the main impacts arising from the implementation of the SMP2 will be losses of intertidal
habitat (Atlantic salt meadows and intertidal mud and sandlflats) potentially arising from options that
hold the existing line of defence. In order to try to quantify and address this impact the Environment
Agency has commissioned work undertaken as part of the development of the Severn Estuary Flood
Risk Management Strategy (FRMS) (in progress). As part of this element of work the 2006 CHaMP
model was updated with revised sea level predictions (Defra 2006), improved 1D-regime modelling
techniques, and removal of the 18.6 year astronomical nodal cycle (which previously masked habitat
impacts). This work has identified indicative figures for losses of intertidal habitat within each of the
CHaMP habitat behaviour units (HBUs). Figures are based on the assumption that all existing
defences and the current standard of protection are maintained, and as such presents a worst case
5. Severn Estuary SMP2 – Appendix I – Part B – Habitats Regulation Assessment
Severn Estuary SMP Review 2
scenario for habitat loss arising from coastal squeeze. Further information on the modelling and
results arising from it can be found in; Morphological Form of the Severn Estuary, February 2009,
Atkins/ABPmer and the Severn Estuary Flood Risk Management Strategy Habitat Delivery Plan,
Atkins/ABPmer, April 2009.
2. Stage 1 Assessment
2.1 Consideration of Sites
Due to the fact that SMPs are considered by Defra, WAG, the Environment Agency, Natural England
and CCW to fall within the criteria outlined within Regulation 61 of the Conservation of Habitats and
Species Regulations 2010 (SI 290)), they require a Habitats Regulations Assessment (HRA) to be
undertaken.
Within England, the Environment Agency is considered to be the competent authority for this HRA.
WAG has confirmed that it will be the competent authority within Wales.
Due to the magnitude of the estuary and the scale of physical processes involved, it was considered
possible that the effects of implementing the SMP2 could extend beyond the boundary of the study
area. Therefore the area included within this initial Stage extends beyond the SMP2 study area,
and is bounded in the east by the tidal extent of the River Severn north of Gloucester, and in
the west by St Govan’s Head (north) and Hartland Point (south); in addition, sites which might
potentially be hydrologically connected with the Severn Estuary or its tidal tributaries, sites with
mobile features such as birds or bats which could be affected by the SMP2, or those which have a
clear ecological connection with the estuary have also been included. The 30 sites considered
within this Stage are listed below:
• Severn Estuary/Mor Hafren SAC
• Severn Estuary/Mor Hafren SPA
• Severn Estuary/Mor Hafren Ramsar
• River Usk/Afon Wysg SAC
• River Wye/Afon Gwy SAC
• Somerset Levels and Moors SPA
• Somerset Levels and Moors Ramsar
• Limestone Coast of South West Wales/ Arfordir Calchfaen de Orllewin Cymru SAC
• River Tywi/Afon Tywi SAC
• Pembrokeshire Marine/Sir Benfro Forol SAC
• Carmarthen Bay and Estuaries/ Bae Caerfyrddin ac Aberoedd SAC
• Carmarthen Bay/ Bae Caerfyrddin SPA
• Carmarthen Bay Dunes/Twyni Bae Caerfyrddin SAC
• Castlemartin Coast SPA
• Burry Inlet SPA Ramsar
• Dunraven Bay SAC
• Crymlyn Bog SAC Ramsar
• Kenfig/Cynffig SAC
• Wye Valley Woodlands/ Coetiroedd Dyffryn Gwy SAC
• Wye Valley and Forest of Dean Bat sites / Safleoedd Ystlumod Dyffryn Gwy a Fforest y
Ddena SAC
• Walmore Common SPA, Ramsar
• Avon Gorge Woodlands SAC
• North Somerset and Mendip Bat SAC
• Mendip Limestone Grasslands SAC
• Mendip Woodlands SAC
6. Severn Estuary SMP2 – Appendix I – Part B – Habitats Regulation Assessment
Severn Estuary SMP Review 3
• Exmoor Heaths SAC
• Exmoor and Quantocks Oak Woods SAC
• Tintagel Marsland Clovelly Coast SAC
• Braunton Burrows SAC
• Lundy SAC
Following an initial review of the sites’ interest features (seeAnnex A) and conservation objectives
the following sites were scoped out from further assessment; a brief justification as to why no
impacts are considered likely is provided.
A. Although the following sites are hydraulically linked to the study area via the estuary they are
outside the SMP2 study area and have been assessed as being unaffected by any changes in
coastal processes.
• Limestone Coast of South West Wales/ Arfordir Calchfaen de Orllewin Cymru SAC
- located at least 65 km downstream of study area
• River Tywi/Afon Tywi SAC - located more than 100km downstream of study area
• Pembrokeshire Marine/Sir Benfro Forol SAC - located approximately 110 km downstream
of study area
• Carmarthen Bay and Estuaries/ Bae Caerfyrddin ac Aberoedd SAC - located
approximately 80 km downstream of the study area.
• Carmarthen Bay/ Bae Caerfyrddin SPA - located approximately 80 km downstream of
study area
• Camarthern Bay Dunes/Twymi Bae Caerfyrddin SAC - located approximately 85 km
downstream of study area
• Castlemartin Coast SPA - located approximately 120 km downstream of study area
• Burry Inlet SPA and Ramsar - located approximately 74 km downstream of study area
• Dunraven Bay SAC - located approximately 30 km downstream of study area
• Kenfig/Cynffig SAC - located approximately 40 km downstream of study area
Discussion of potential effects: the risk of tidal flooding or erosion of the sites will not
increase as a result of the implementation of the SMP2. Any alterations to coastal processes
that could potentially result from the implementation of SMP2 policies will typically be local in
nature. The headland at Penarth will constrain impacts on coastal processes westwards along
the estuary; any impacts from the Severn SMP2 would be small scale and local in nature when
compared to the magnitude and complexity of processes operating at an estuary wide scale.
Habitats, species and conservation objectives of the sites are therefore considered unlikely to
be affected by the SMP2. Significant adverse in combination effects are also considered
unlikely.
B. Crymlyn Bog SAC & Ramsar - located approximately 80 km downstream of study area; there
is also potential for hydraulic connectivity via The Glan y Wern Canal and the Tennant Canal.
Discussion of potential effects: The risk of tidal flooding of the site will not increase as a
result of the implementation of the SMP2. Any alterations to coastal processes that could
potentially result from the implementation of SMP2 policies will typically be local in nature; the
headland at Penarth will constrain impacts on coastal processes westwards along the estuary.
In addition, the site is approximately 600m inland and would be protected from any changes to
7. Severn Estuary SMP2 – Appendix I – Part B – Habitats Regulation Assessment
Severn Estuary SMP Review 4
coastal erosional and depositional processes. Habitats, species and conservation objectives of
the site are therefore considered unlikely to be affected by the SMP2. Significant adverse in
combination effects are also considered unlikely.
C. Although the following sites are hydraulically linked to the study area via the estuary they are
outside the SMP2 study area and have been assessed as being unaffected by any changes in
coastal processes
• Exmoor and Quantocks Oak Woods SAC - located 40 km downstream of study area and
elevated outside the flood risk area.
• Exmoor Heaths SAC - located 40 km downstream of study area and elevated outside the
flood risk area.
• Tintagel Marsland Covelly Coast SAC - located approximately 120km downstream of the
study area
• Braunton Burrows SAC - located 90 km downstream of study area
• Lundy SAC - located approximately 120km downstream of study area
Discussion of potential effects: the implementation of the Severn SMP2 will not affect tidal
ranges, coastal processes or flood risk west of the Middle Hope and Brean Down promontories.
Any impacts from the Severn SMP2 would be very small scale both alone and in combination
with other plans and projects and local in effect when compared to the magnitude and
complexity of processes operating at an estuary wide scale. Habitats, species and conservation
objectives of the sites are therefore considered unlikely to be affected by the SMP2.
D. Wye Valley Woodlands/ Coetiroedd Dyffryn Gwy SAC - A policy of No Active Intervention
(NAI) is proposed for each of the reaches within the Wye policy unit. No increase in flood or
erosion risk is predicted within any of the above reaches over the lifetime of the SMP2; natural
processes will continue to dominate. The SAC comprises several woodland areas spread along
the Wye Valley, predominantly within reaches WYE2 and 3. None of the sites are currently
affected by tidal processes or flooding and this will remain the case in the future; within this
section of the study area flood and erosion risk is not predicted to increase under an NAI policy;
neither the woodland sites themselves nor associated bat foraging habitat within the area will be
affected by the implementation of the SMP2 policies. Significant adverse in combination effects
are also considered unlikely.
E. Wye Valley and Forest of Dean Bat Sites / Safleoedd Ystlumod Dyffryn Gwy a Fforest y
Ddena SAC - A policy of NAI is proposed for each of the reaches within the Wye policy unit. No
increase in flood or erosion risk is predicted within any of the above reaches over the lifetime of
the SMP2; natural processes will continue to dominate and therefore no impacts are predicted.
The SAC comprises several sites spread along the Wye Valley. None of the sites are currently
affected by tidal processes or flooding and this will remain the case in the future; within this
section of the study area flood and erosion risk is not predicted to increase under an NAI policy;
neither the SACs nor associated bat foraging habitat within the area will be affected by the
implementation of the SMP2 policies. Significant adverse in combination effects are also
considered unlikely.
F. Walmore Common SPA and Ramsar
Options for policy units along this stretch of coast are as follows:
GLO5 GLO6 GL7 GLO8
HTL NAI HTL HTL
The existing defence
line will be
maintained
Natural processes
will continue to
operate within this
The existing defence
line will be maintained
Given that a key
The existing
defence line will be
maintained Given
8. Severn Estuary SMP2 – Appendix I – Part B – Habitats Regulation Assessment
Severn Estuary SMP Review 5
reach. There is
currently no flood or
erosion risk within
this reach and
modelling indicates
that this will not
change in the future
transport route and a
number of properties lie
between the estuary and
the site it has been
assumed that the SoP
will be retained or
improved and the site
will receive ongoing
protection from tidal
flooding
that a key transport
route and a number
of properties lie
between the
estuary and the site
it has been
assumed that the
SoP will be retained
or improved and
the site will receive
ongoing protection
from tidal flooding
An important habitat on the site is the grassland, which is maintained by grazing and natural
freshwater winter flooding which is in turn determined by rainfall, run-off and river levels. The
marshy grassland and ditches are maintained and enhanced by maintaining high water levels
from spring to autumn through the implementation of a water level management plan The site
currently has roughly a 1 in 200 year standard of protection from tidal flooding. With a HTL
policy at GL7, it has been assumed that the standard of protection offered to the site will be
maintained or increased. The site will not be at risk from tidal flooding and/or erosion. Sea level
rise may result in increased tide locking of land behind the defences, however this would be as
a result of sea levels rise, not the implementation of the SMP2 The feature of the site
(Bewick’s Swan) and the habitats that support them will be unaffected by the preferred policy
options. However the SMP2 does not identify the standard of flood protection to be provided by
flood defences; this will be addressed by the Severn Flood Risk Management Strategy (FRMS).
This assessment has concluded no likely significant effects on the SAC and Ramsar site at the
SMP2 level, however the potential for impacts will be reviewed as part of the HRA for the
FRMS, when further information on the standard of protection from tidal flooding to be provided
will be available. Significant adverse in combination effects are considered unlikely.
G. Avon Gorge Woodlands SAC - A Hold the Line policy is proposed for all the reaches within the
policy unit. There is currently no flood or erosion risk within this reach and this will not change in
the future. The SAC is located adjacent to the River Avon on both the left and right banks within
Policy Units BRIS 4 and 5. The site is currently unaffected by tidal processes and this will
remain the case under the preferred policy. None of the habitats for which the site is designated
nor the sites’ conservation objectives will be affected. Significant adverse in combination effects
are also considered unlikely.
H. Mendip Woodlands SAC - the SAC is a woodland site, over 41km from the coast. The site is
more than 40km outside the tidal floodplain and this situation is predicted to continue over the
lifetime of the SMP2. The Annex I feature for which the site is designated (Tilio-Acerion forests )
will not be affected by the SMP2. Significant adverse in combination effects are also considered
unlikely.
2.2 Conclusion of Stage 1 Assessment
Likely significant adverse effects on the following sites could not be ruled out at this stage and they
have therefore been carried forward for further assessment at Stage 2 (Section 3):
• Severn Estuary/Mor Hafren SPA
• Severn Estuary/Mor Hafren Ramsar
• Severn Estuary/Mor Hafren SAC
• River Usk/Afon Wysg SAC
• River Wye / Afon Gwy SAC
• Somerset Levels and Moors SPA and Ramsar
• North Somerset and Mendip Bat SAC
9. Severn Estuary SMP2 – Appendix I – Part B – Habitats Regulation Assessment
Severn Estuary SMP Review 6
• Mendip Limestone Grasslands SAC
3. Stage 2 Assessment
This Section assesses whether the SMP2 is likely to have a significant effect on any of the European
sites carried through from Stage 1, either alone or in combination with other plans or projects. The
results of the Stage 2 assessment are presented in the table below:
Record of Assessment of Likely Significant Effect On European Sites (Stage 2)
1. Type of permissions/activities: Severn Estuary SMP2
2. Brief description of proposals: Shoreline Management Plans set high level policy approaches
for the future management of flood and erosion risk along
coastline, typicsally over a 100 year timeframe. SMPs allow the
development of strategy plans to be prioritised. The Severn
SMP2 is a review of the Severn SMP (2000) and has divided the
Severn Estuary study area into policy units, with one of four
policy options being applied to each unit:
• Hold the existing defence line (HTL);
• Advance the existing defence line (ATL);
• Managed realignment - identifying a new shape for the
shoreline and actively managing change (MR);
• No Active Intervention - a decision not to invest in providing
or maintaining defences (NAI).
Preferred SMP2 policy options are listed in Annex B. This HRA
concentrates on the impacts of the proposed SMP2 policies on
the European and international sites identified rather than
project level impacts that may occur as a result of implementing
these policies. There will be a need to carry out more detailed,
project level HRAs on specific development proposals and these
may ultimately influence the implementation of specific policies
on a site by site basis.
European site name(s) and status:
There are a number of sites, namely Severn Estuary SPA/SAC/Ramsar, River Usk SAC, River Wye
SAC, North Somerset and Mendip Bat SAC, Mendip Limestone Grasslands SAC and the Somerset
Levels and Moors SPA/Ramsar where Stage 1 identified that a further assessment of hazards and
potential effects was required and this is detailed in Section 6. Conservation objectives for all these sites
can be obtained from CCW and NE.
Qualifying Features of International Importance:
Severn Estuary/Mor Hafren SPA
Total area of site:
24662.98 ha
Annex 1 species:
Bewick’s swan (Cygnus columbianus bewickii) (3.4, 3.6, 3.7, 3.8)
Internationally important populations of regularly occurring migratory bird
species:
European white-fronted goose (Anser albifrons albifrons) (3.6, 3.7, 3.8, 3.9)
Dunlin (Calidris alpine alpine) (3.4, 3.7, 3.8, 3,9)
Redshank (Tringa totanus) (3.4, 3.7, 3.8, 3.9)
Shelduck (Tadorna tadorna) (3.6, 3.8, 3.9)
Gadwall (Anas strepera) (3.6)
Curlew (Numenius arquata) (3.4, 3.7, 3.8, 3.9)
Pintail (Anas acuta) (3.6, 3.8, 3.9)
Ringed plover (Charadrius hiaticula) (3.6, 3.8, 3.9)
Internationally important assemblage of waterfowl populations (3.4, 3.6, 3.7,
3.8, 3.9)
10. Severn Estuary SMP2 – Appendix I – Part B – Habitats Regulation Assessment
Severn Estuary SMP Review 7
Reference numbers as used in EA HRA Handbook:
3.4 = Birds of lowland wet grasslands
3.6 = Birds of lowland freshwaters and their margins
3.7 = Birds of farmlandb
3.8 = Birds of coastal habitats
3.9 = Birds of estuarine habitats
Severn Estuary/Mor Hafren Ramsar
Total area of site:
24662.98 ha
Ramsar criterion 1 : immense tidal range (second – largest in world), this
affects both the physical environment and biological communities. (Estuarine
and intertidal habitats : 1.12)
Ramsar criterion 3 unusual estuarine communities, reduced diversity and
high productivity. (Estuarine and intertidal habitats : 1.12).
Ramsar criterion 4 : important for the run of migratory fish between sea and
river via estuary. Species include Salmon (Salmo salar), sea trout (S. trutta),
sea lamprey (Petromyzon marinus), river lamprey (Lampetra fluviatilis), allis
shad (Alosa alsoa), twaite shad (A. failax), and eel (Anguilla Anguilla)
(Anadromous fish : 2.5)
Ramsar criterion 8 : the fish assemblage of the whole estuarine and river
system is one of the most diverse in Britain, with over 110 species recorded
(Non-migratory fish and invertebrates of rivers: 2.6).
Ramsar criterion 6: regularly supports 1% of the individuals in a population of
one species or subspecies of waterbird.
Species with peak counts in winter:
Bewick’s swan (Cygnus columbianus bewickii) (3.4, 3.6, 3.7, 3.8)
European white-fronted goose (Anser albifrons albifrons) (3.6, 3.7, 3.8, 3.9)
Dunlin (Calidris alpine alpine) (3.4, 3.7, 3.8, 3,9)
Redshank (Tringa totanus) (3.4, 3.7, 3.8, 3.9)
Shelduck (Tadorna tadorna) (3.6, 3.8, 3.9)
Gadwall (Anas strepera) (3.6)
Ringed plover (Charadrius hiaticula) (3.6, 3.8, 3.9)
Teal (Anas crecca) (3.4, 3.6, 3.8, 3.9)
Pintail (Anas acuta) (3.6, 3.8, 3.9)
Lesser black-backed gull (Larus fuscus) (3.6, 3.8, 3.9)
Pochard(Aythya ferina) (3.3, 3.6, 3.8, 3.9)
Tufted Duck (Aythya fuligula) (3.6)
Grey Plover (Pluvialis squatarola) (3.4, 3.7, 3.8, 3.9)
Curlew (Numenius arquata) (3.4, 3.7, 3.8, 3.9)
Whimbrel (Numenius phaeopus) (3.6, 3.9)
Wigeon (Anas penelope) (3.6, 3.7, 3.8, 3.9)
Ramsar criterion 5 : Supports an assemblage of international importance –
(1998/99-2002/2003 5 year peak mean was 70,919 waterfowl) (3.4, 3.6, 3.7,
3.8, 3.9).
Reference numbers as used in EA HRA Handbook:
3.4 = Birds of lowland wet grasslands
3.6 = Birds of lowland freshwaters and their margins
3.7 = Birds of farmland
3.8 = Birds of coastal habitats
3.9 = Birds of estuarine habitats
11. Severn Estuary SMP2 – Appendix I – Part B – Habitats Regulation Assessment
Severn Estuary SMP Review 8
Severn Estuary/Mor Hafren SAC
Total area of site:
73715.4 ha
Annex 1 Habitats
1130 Estuaries (Estuarine and intertidal habitats : 1.12)
1110 Subtidal sandbanks (Submerged marine habitats: 1.13)
1140 Intertidal mudflats and sandflats (Estuarine and intertidal habitats :
1.12)
1330 Atlantic salt meadows (Estuarine and intertidal habitats : 1.12)
1170 Reefs (Submerged marine habitats: 1.13)
Annex II species
1099 River lamprey (Lampetra fluviatilis) (Anadromous fish : 2.5)
1095 Sea lamprey (Petromyzon marinus) (Anadromous fish : 2.5)
1103 Twaite shad (Alosa fallax) (Anadromous fish : 2.5)
River Usk/Afon Wysg SAC
Total area of site:
1007.71 ha
Annex I Habitats
3260 Water courses of plain to montane levels with the Ranunculion fluitantis
and Callitricho-Batrachion vegetation (Riverine habitats and running waters:
1.1)
Annex II species
1095 Sea Lamprey (Petromyzon marinus) (Anadromous fish : 2.5)
1096 Brook Lamprey (Lampetra planeri) (Anadromous fish : 2.5)
1099 River Lamprey (Lampetra fluviatilis) (Anadromous fish : 2.5)
1103 Twaite shad (Alosa fallax) (Anadromous fish : 2.5)
1106 Atlantic salmon (Salmo salar) (Anadromous fish : 2.5)
1163 Bullhead (Cottus gobio) (Non-migratory fish and invertebrates of
rivers: 2.6)
1355 Otter (Lutra lutra) (Mammals of riverine habitats: 2.9)
1102 Allis shad (Alosa alosa) )(Anadromous fish : 2.5)
River Wye / Afon Gwy SAC
Total area of site:
2234.89 ha
Annex I habitats
3260 Riverine habitats & running waters (Water courses of plain to montane
levels with the Ranunculion fluitantis and Callitricho-Batrachion vegetation)
(Riverine habitats and running waters: 1.1)
7140 Transition mires and quaking bogs (Bogs and wet habitats: 1.2)
Annex II species
1092 White-clawed (or Atlantic stream) crayfish (Austropotamobius pallipes)
(Non-migratory fish and invertebrates of rivers: 2.6)
1095 Sea Lamprey (Petromyzon marinus) (Anadromous fish : 2.5)
1096 Brook Lamprey(Lampetra planeri) (Non-migratory fish and
invertebrates of rivers: 2.6)
1099 River Lamprey (Lampetra fluviatilis) (Anadromous fish : 2.5)
1103 Twaite shad (Alosa fallax) (Anadromous fish : 2.5)
1106 Atlantic salmon (Salmo salar) (Anadromous fish : 2.5)
1163 Bullhead (Cottus gobio) (Non-migratory fish and invertebrates of
rivers: 2.6)
1355 Otter (Lutra lutra) (Mammals of riverine habitats: 2.9)
Somerset Levels and Moors SPA and Ramsar
Total area of site:
SPA: 6388.49 ha
Ramsar: 6388.49ha
Somerset Levels and Moors SPA
Supports the following species of birds overwinter:
Bewick’s swan (Cygnus columbianus bewickii) (2.7% of wintering population in
GB) (3.4, 3.6, 3.7, 3.8)
Golden Plover (Pluvialis apricaria) (1.2% of wintering population in GB) (3.4, 3.7,
3.8, 3.9)
12. Severn Estuary SMP2 – Appendix I – Part B – Habitats Regulation Assessment
Severn Estuary SMP Review 9
Supports the following species overwinter:
Teal (Anas crecca) (3.3% of the population) (3.4, 3.6, 3.8, 3.9)
Lapwing (Vanellus vanellus) (0.5% of the population) (3.4, 3.7, 3.9)
Supports species which are considered internationally important assemblage of
waterfowl populations. (3.4, 3.6, 3.7, 3.8, 3.9).
Somerset Levels and Moors Ramsar
Ramsar criterion 2 : Supports 17 species of British Red Data Book
invertebrates.
Ramsar criterion 5 : Assemblages of international importance species with
peak counts in winter: 70919 waterfowl (5 year peak mean 1998/99-2002/2003)
(3.4, 3.6, 3.7, 3.8, 3.9).
Ramsar criterion 6 : Species occurring at internationally important levels.
Species with peak counts in winter:
Bewick’s swan (Cygnus columbianus bewickii) (3.4, 3.6, 3.7, 3.8)
Teal (Anas creecca) (3.4, 3.6, 3.8, 3.9)
Northern lapwing (Vanellus vanellus) (3.4, 3.7, 3.9)
Species with possible future consideration under criterion 6.
Species with peak counts in winter:
Mute swan (Cygnus olor) (3.6, 3.9)
Widgeon (Anas penelope) (3.6, 3.7, 3.8, 3.9)
Pintail (Anus acuta) (3.6, 3.8, 3.9)
Northern shoveler (Anas clypeata) (3.6, 3.9)
Reference numbers as used in EA HRA Handbook
3.4 = Birds of lowland wet grasslands
3.6 = Birds of lowland freshwaters and their margins
3.7 = Birds of farmland
3.8 = Birds of coastal habitats
3.9 = Birds of estuarine habitats
North Somerset and Mendip Bat SAC
Total area of site:
151.19ha
Annex I habitats
6210 Semi-natural dry grasslands and scrubland facies: on calcareous
substrates (Festuco-Brometalia) (1.7 Dry grassland)
9180 Tilio-Acerion forests of slopes, screes and ravines (Priority feature) (1.6
Dry woodlands and scrub)
8310 Caves not open to the public
Annex II species
1303 Lesser horseshoe bat (Rhinolophus hipposideros) (2.8 Mammals of
woodland habitats)
1304 Greater horseshoe bat (Rhinolophus ferrumequinum) 2.8 Mammals of
woodland habitats
Mendip Limestone Grasslands SAC
Total area of site:
417.47ha
Annex I habitats
6210 Semi-natural dry grasslands and scrubland facies: on calcareous
substrates (Festuco-Brometalia) (1.7 Dry grassland)
9180 Tilio-Acerion forests of slopes, screes and ravines (Priority feature) (1.6
Dry woodlands and scrub)
8310 Caves not open to the public
4030 European dry heaths (1.5 Dry heathland habitat)
Annex II species
1304 Greater horseshoe bat (Rhinolophus ferrumequinum) (2.8 Mammals of
13. Severn Estuary SMP2 – Appendix I – Part B – Habitats Regulation Assessment
Severn Estuary SMP Review 10
woodland habitats)
5. Is the proposal directly connected with or necessary to the
management of the sites for nature conservation?
No
6. What potential hazards are likely to affect the interest features?
Key impacts that could potentially arise as a result of the implementation of the SMP2 and that have
been taken into consideration in undertaking this screening exercise are summarised below :
Changes in physical regime, flow or velocity regime: including coastal or estuarine erosion or
deposition and altered flooding regimes.
Changes to water chemistry: resulting from alterations in salinity or an increased risk of pollution (e.g.
as a result of increased risk of flooding of current or historical landfill sites or other contaminated land)
Habitat severance : resulting for example from retreat of defences or construction of new defences
Disturbance: including to features within and adjacent to the site e.g. during construction or
maintenance
Habitat loss/physical damage: potentially resulting from: coastal squeeze, sea level rise, the footprint
of new defences or retreat of the defence line. Estimates of potential habitat loss have been based on
work undertaken by Atkins and ABPmer as part of the Severn FRMS. Further information can be found
in: Severn Estuary Flood Risk Management Strategy - Habitat Delivery Plan (2009) Atkins/ABPmer and
Predicted Morphological Form of the Severn Estuary (February 2009) Atkins/ABPmer.
In undertaking the assessment a number of assumptions have been made:
• In assessing likely impacts of sea level rise, Defra 2006 predictions have been used which give
an overall predicted increase in sea level for the Severn of 1m by 2105.
• The HRA has been informed by predicted future changes in flood and erosion risk, derived from
modelling and assessment undertaken as part of the development of the SMP2; this work is
detailed in Appendix C of the SMP2 Report: Baseline Understanding of Coastal Behaviour and
Dynamics.
• The Environment Agency has commissioned work as part of the development of the Severn
Estuary FRMS (in progress) to investigate predictions of habitat loss and compensation issues
in more detail. As part of this of work, the 2006 CHaMP model was updated with revised sea
level predictions (Defra 2006), improved 1D-regime modelling techniques, and removal of the
18.6 year astronomical nodal cycle (which previously masked habitat impacts). This work has
identified indicative figures for losses of intertidal habitat within each of the CHaMP habitat
behaviour units. Figures are based on the assumption that all existing defences and the current
standard of protection are maintained, and as such presents a worst case scenario for habitat
loss arising from coastal squeeze. Further information on the modelling and results arising from
it can be found in; Morphological Form of the Severn Estuary, February 2009, Atkins/ABPmer
and the Severn Estuary Flood Risk Management Strategy Habitat Delivery Plan,
Atkins/ABPmer, April 2009.
• A Hold the Line policy does not necessarily mean that the current standard of protection will be
maintained and it could decrease or increase instead. However the SMP2 does not look at how
the Hold the Line option will be implemented (i.e. what standard of protection will be provided).
Whether or not a Hold the Line policy will result in a decrease in the standard of protection will
not be apparent until the FRMS is completed. The Severn FRMS and the HRA undertaken to
document its effects on the European sites will review this HRA and identify and assess impacts
in more detail, and address any adverse impacts. However, it is logical to conclude that a Hold
the Line policy will result in costal squeeze and loss of intertidal habitats.
14. Severn Estuary SMP2 – Appendix I – Part B – Habitats Regulation Assessment
Severn Estuary SMP Review 11
• Advance the line is not proposed for any policy units within the study area; the potential impacts
of this policy option will therefore not be considered further within this assessment.
• This assessment is being undertaken at the strategic level and will therefore focus on the
potential impacts of the SMP2 policies once implemented; impacts that could potentially result
during the construction phase of any of the policy options have not been considered in detail
within this HRA. Exceptions have been made where CCW and NE have requested the
consideration of specific construction issues known to present a significant risk to the sites
including: historic contamination on the Usk and disturbance to birds along the Gwent and
Somerset Levels. An HRA of the Severn FRMS will be undertaken to assess potential impacts
resulting from this next tier of planning; in addition, more detailed project level HRAs will be
undertaken on specific development proposals and these may ultimately influence the
implementation of specific policies on a site by site basis.
15. Severn Estuary SMP2 – Appendix I – Part B – Habitats Regulation Assessment
Severn Estuary SMP Review 12
Severn Estuary SPA and Ramsar
Severn Estuary SPA and Ramsar: The site extends through much of the study area and could be
affected by the implementation of all three of the SMP2 policy options
Sensitive Interest Feature Potential Hazard Potential exposure to Hazard and mechanism of
effect/impact if known
Birds of lowland wet
grasslands (3.4)
Severn Estuary SPA,
Ramsar: Bewick’s swan,
Dunlin, Redshank, Curlew,
waterfowl (>20,000)
Severn Estuary Ramsar
only: Teal, Grey plover
Change in physical
regime, flow or
velocity regime
No Active Intervention and/or Managed
Realignment. No direct impact on the
designated bird species assemblage but
potential to alter physical processes and affect
habitats on which species are dependent for
feeding and roosting. Impacts may affect the
long term survival of individuals or alter
behaviour and pattern of use or distribution:
Alone: LSE
In combination: None of the plans and projects
reviewed are considered likely to result in
increased inundation of freshwater habitats: No
LSE
Hold the Line Assuming the standard of
protection is maintained or increased, raised sea
levels could potentially increase the amount of
time outfalls and drainage ditches are tide
locked, temporarily increasing freshwater levels
behind the defence. This impact could benefit
wet grassland and species it supports. However,
increased tide locking would occur as a result of
sea level rise rather than implementation of the
strategy. Given the extensive tidal range of the
estuary any increase in tide locking is not
anticipated to be great enough to result in a
significant effect on habitats: Alone and in
combination No LSE
If standard of protection decreases, potential
impacts would be as for NAI and MR. However
the SMP does not specify how the HTL policy
will be implemented, neither does it identify the
SoP to be provided. Therefore at this stage it is
not possible to identify whether impacts could
occur or not. The potential for impacts to occur
will be reviewed as part of the HRA for the
FRMS which will address how HTL will be
implemented including option alignments and
SoP:
Alone: Uncertain – it is not possible to rule
out the likelihood of LSE (Alone) at SMP2
level, further review to be undertaken at
FRMS stage.
In combination : effects unlikely as potentials
impacts associated with increased overtopping
of defences: No LSE
16. Severn Estuary SMP2 – Appendix I – Part B – Habitats Regulation Assessment
Severn Estuary SMP Review 13
Changes in water
chemistry
All Options
No major changes in the water quality of the
Severn Estuary will result from the
implementation of any of the SMP2 policies, due
the limited extent of contamination present
around the estuary and the large volume of
water flowing through the estuary on each tidal
cycle which would serve to dilute any local
pollution event: Alone and in combination No
LSE
No Active Intervention and/or Managed
Realignment could result in increased tidal
inundation and salinisation of terrestrial habitats
with potential knock on effects for the birds using
the habitats; these habitats may be outside the
European sites but could be supporting habitats
for qualifying bird features:
Alone: LSE
In combination: None of the plans and projects
reviewed are considered likely to result in
increased inundation of freshwater habitats: No
LSE
Hold the Line: assuming the standard of
protection is maintained or increased existing
grassland habitat would be maintained, no
anticipated long-term changes to habitat: Alone
and in combination No LSE
If standard of protection decreases, potential
impacts would be as for NAI and HTL. However
the SMP does not specify how the HTL policy
will be implemented, neither does it identify the
SoP to be provided. Therefore at this stage it is
not possible to identify whether impacts could
occur or not. The potential for impacts to occur
will be reviewed as part of the HRA for the
FRMS which will address how HTL will be
implemented including option alignments and
SoP: Alone: Uncertain – it is not possible to
rule out the likelihood of LSE (Alone) at
SMP2 level, further review to be undertaken
at FRMS stage.
In combination : effects unlikely as potentials
impacts associated with increased overtopping
of defences: No LSE
Habitat Severance Hold the Line: defences maintained in current
position so no habitat fragmentation : Alone
and in combination No LSE
Managed Realignment: realignment of
defences would result in habitat loss or damage
(see below) rather than habitat fragmentation:
Alone and in combination No LSE
No Active Intervention : Alone and in
combination No LSE
17. Severn Estuary SMP2 – Appendix I – Part B – Habitats Regulation Assessment
Severn Estuary SMP Review 14
Disturbance Improvement or maintenance works under a
Hold the Line or Managed Realignment option
have the potential to disturb birds through noise
or visual disturbance. This can displace the
birds from their feeding grounds. Disturbance
can prevent the birds from feeding and in
response they either a) decrease their energy
intake at their present (disturbed) feeding site
through displacement activity, or b) move to an
alternative less favoured feeding site. Works will
only be permitted at the appropriate time of year
(only between April – September) to avoid the
most sensitive time: Alone and in combination
No LSE
No Active Intervention : Alone and in
combination No LSE
Habitat Loss/
Physical Damage
No Active Intervention/Managed
Realignment: Increased tidal inundation has the
potential to change habitats, possibly resulting in
areas of lowland grassland being reduced
decreasing available habitat for species foraging
and roosting: Alone: LSE
In combination: None of the plans and projects
reviewed are considered likely to result in
increased inundation of freshwater habitats: No
LSE
Hold the Line: assuming the standard of
protection is maintained or increased, the
existing grassland habitat behind defence would
be maintained: Alone and in combination No
LSE
If standard of protection decreases, potential
impacts would be as for NAI and HTL. However
the SMP does not specify how the HTL policy
will be implemented, neither does it identify the
SoP to be provided. Therefore at this stage it is
not possible to identify whether impacts could
occur or not. The potential for impacts to occur
will be reviewed as part of the HRA for the
FRMS which will address how HTL will be
implemented including option alignments and
SoP: Alone: Uncertain – it is not possible to
rule out the likelihood of LSE (Alone) at
SMP2 level, further review to be undertaken
at FRMS stage.
In combination : effects unlikely as potentials
impacts associated with increased overtopping
of defences: No LSE
18. Severn Estuary SMP2 – Appendix I – Part B – Habitats Regulation Assessment
Severn Estuary SMP Review 15
Potential for some minor habitat loss as a
consequence of the increased footprint of the
defence- if SoP maintained or increased. Also
potential for more significant cumulative and in
combination effects when all defences around
the estuary are taken into consideration. The
SMP2 does not specify how the HTL policy will
be implemented so it is not possible to identify
whether any impacts could occur or not. Further
assessment to be undertaken as part of the
FRMS. Alone and in combination : Uncertain
– it is not possible to rule out the likelihood
of LSE at SMP2 level, further review to be
undertaken at FRMS stage
Birds of lowland
freshwaters and their
margins (3.6)
Severn Estuary SPA,
Ramsar:
Bewick’s,Swan White-
fronted goose, Shelduck,
Gadwall, Pintail , Ringed
plover Waterfowl(>20, 000)
Severn Ramsar only: Teal.
Lesser black backed gull,
Wigeon, Pochard, Tufted
duck, Wimbrel
Change in physical
regime, flow or
velocity regime
No Active Intervention and/or Managed
Realignment. No direct impact on the
designated bird species assemblage but
potential to alter physical processes and affect
habitats on which species are dependent for
feeding and roosting. Impacts may affect the
long term survival of individuals or alter
behaviour and pattern of use or distribution:
Alone: LSE
In combination: None of the plans and projects
reviewed are considered likely to result in
increased inundation of freshwater habitats: No
LSE
Hold the Line Assuming the standard of
protection is maintained or increased, raised sea
levels could potentially increase the amount of
time outfalls and drainage ditches are tide
locked, temporarily increasing freshwater levels
behind the defence. However, increased tide
locking would occur as a result of sea level rise
rather than implementation of the strategy.
Given the extensive tidal range of the estuary
this increase is not anticipated to be great
enough to result in a significant effect on
habitats: Alone and in combination No LSE
If standard of protection decreases, potential
impacts would be as for NAI and HTL. However
the SMP does not specify how the HTL policy
will be implemented, neither does it identify the
SoP to be provided. Therefore at this stage it is
not possible to identify whether impacts could
occur or not. The potential for impacts to occur
will be reviewed as part of the HRA for the
FRMS which will address how HTL will be
implemented including option alignments and
SoP: Alone: Uncertain – it is not possible to
rule out the likelihood of LSE (Alone) at
SMP2 level, further review to be undertaken
at FRMS stage.
In combination : effects unlikely as potentials
impacts associated with increased overtopping
of defences: No LSE
19. Severn Estuary SMP2 – Appendix I – Part B – Habitats Regulation Assessment
Severn Estuary SMP Review 16
Changes in water
chemistry
All Options
No major changes in the water quality of the
Severn Estuary will result from the
implementation of the SMP2, due to the limited
extent of contamination present around the
estuary and the large volume of water flowing
through the estuary on each tidal cycle which
would serve to dilute any local pollution event :
Alone and in combination No LSE
No Active Intervention and/or Managed
Realignment could result in increased tidal
inundation and salinisation of terrestrial habitats
with potential knock on effects for the birds using
the habitats; these habitats may be outside the
European sites but could be supporting habitats
for qualifying bird features: Alone: LSE
In combination: None of the plans and projects
reviewed are considered likely to result in
increased inundation of freshwater habitats: No
LSE
Hold the Line: Assuming the standard of
protection is maintained or increased, existing
grassland habitat maintained, no anticipated
long-term changes to habitat: Alone and in
combination No LSE
If standard of protection decreases, potential
impacts would be as for NAI and HTL. However
the SMP does not specify how the HTL policy
will be implemented, neither does it identify the
SoP to be provided. Therefore at this stage it is
not possible to identify whether impacts could
occur or not. The potential for impacts to occur
will be reviewed as part of the HRA for the
FRMS which will address how HTL will be
implemented including option alignments and
SoP: Alone: Uncertain – it is not possible to
rule out the likelihood of LSE (Alone) at
SMP2 level, further review to be undertaken
at FRMS stage.
In combination : effects unlikely as potentials
impacts associated with increased overtopping
of defences: No LSE
Habitat Severance Hold the Line: defences maintained in current
position so no habitat fragmentation: Alone and
in combination No LSE
Managed Realignment : realignment of
defences would result in habitat loss or damage
(see below) rather than habitat fragmentation:
Alone and in combination No LSE
No Active Intervention: Alone and in
combination No LSE
20. Severn Estuary SMP2 – Appendix I – Part B – Habitats Regulation Assessment
Severn Estuary SMP Review 17
Disturbance Improvement or maintenance works under a
Hold the Line or Managed Realignment option
have the potential to disturb birds through noise
or visual disturbance. This can displace the
birds from their feeding grounds. Disturbance
can prevent the birds from feeding and in
response they either a) decrease their energy
intake at their present (disturbed) feeding site
through displacement activity, or b) move to an
alternative less favoured feeding site. Works will
only be permitted at the appropriate time of year
(only between April – September) to avoid the
most sensitive time: Alone and in combination
No LSE
No Active Intervention: Alone and in
combination No LSE
Habitat Loss/
Physical Damage
No Active Intervention/Managed
Realignment: increased tidal inundation
resulting in alterations to vegetation, habitats
and the birds they support: Alone: LSE
In combination: None of the plans and projects
reviewed are considered likely to result in
increased inundation of freshwater habitats: No
LSE
Hold the line: Assuming the standard of
protection is maintained or increased, the
defences are retained in place and will maintain
freshwater and marginal habitats: Alone and in
combination No LSE
If standard of protection decreases, potential
impacts would be as for NAI and HTL. However
the SMP does not specify how the HTL policy
will be implemented, neither does it identify the
SoP to be provided. Therefore at this stage it is
not possible to identify whether impacts could
occur or not. The potential for impacts to occur
will be reviewed as part of the HRA for the
FRMS which will address how HTL will be
implemented including option alignments and
SoP: Alone: Uncertain – it is not possible to
rule out the likelihood of LSE (Alone) at
SMP2 level, further review to be undertaken
at FRMS stage.
In combination : effects unlikely as potentials
impacts associated with increased overtopping
of defences: No LSE
21. Severn Estuary SMP2 – Appendix I – Part B – Habitats Regulation Assessment
Severn Estuary SMP Review 18
Potential for some minor habitat loss as a
consequence of the increased footprint of the
defence - if SoP maintained or increased. Also
potential for more significant cumulative and in
combination effects when all defences around
the estuary are taken into consideration. The
SMP2 does not specify how the HTL policy will
be implemented so it is not possible to identify
whether any impacts could occur or not. Further
assessment to be undertaken as part of the
FRMS. Alone and in combination :Uncertain
– it is not possible to rule out the likelihood
of LSE at SMP2 level, further review to be
undertaken at FRMS stage
Birds of farmland (3.7)
Severn Estuary SPA,
Ramsar:
Bewick’s Swan, White-
fronted goose, Dunlin,
Redshank, Curlew
Severn Estuary Ramsar
only: Teal, Grey plover
Change in physical
regime, flow or
velocity regime
No Active Intervention and/or Managed
Realignment. No direct impact on the
designated bird species assemblage but
potential to alter physical processes and affect
habitats on which species are dependent for
feeding and roosting. Impacts may affect the
long term survival of individuals or alter
behaviour and pattern of use or distribution:
Alone: LSE
In combination: None of the plans and projects
reviewed are considered likely to result in
increased inundation of freshwater habitats: No
LSE
Hold the Line Assuming the standard of
protection is maintained or increased, raised sea
levels could potentially increase the amount of
time outfalls and drainage ditches are tide
locked, temporarily increasing freshwater levels
behind the defence. However, increased tide
locking would occur as a result of sea level rise
rather than implementation of the strategy.
Given the extensive tidal range of the estuary
this increase is not anticipated to be great
enough to result in a significant effect on
habitats: Alone and in combination No LSE
If standard of protection decreases, potential
impacts would be as for NAI and HTL. However
the SMP does not specify how the HTL policy
will be implemented, neither does it identify the
SoP to be provided. Therefore at this stage it is
not possible to identify whether impacts could
occur or not. The potential for impacts to occur
will be reviewed as part of the HRA for the
FRMS which will address how HTL will be
implemented including option alignments and
SoP: Alone: Uncertain – it is not possible to
rule out the likelihood of LSE (Alone) at
SMP2 level, further review to be undertaken
at FRMS stage.
In combination : effects unlikely as potentials
impacts associated with increased overtopping
of defences: No LSE
22. Severn Estuary SMP2 – Appendix I – Part B – Habitats Regulation Assessment
Severn Estuary SMP Review 19
Changes in water
chemistry
All Options
No major changes in the water quality of the
Severn Estuary will result from the
implementation of any of the SMP2 policies, due
the limited extent of contamination present
around the estuary and the large volume of
water flowing through the estuary on each tidal
cycle which would serve to dilute any local
pollution event: Alone and in combination No
LSE
No Active Intervention and/or Managed
Realignment could result in increased tidal
inundation and salinisation of terrestrial habitats
with potential knock on effects for the birds using
the habitats; these habitats may be outside the
European sites but could be supporting habitats
for qualifying bird features: Alone: LSE
In combination: None of the plans and projects
reviewed are considered likely to result in
increased inundation of freshwater habitats: No
LSE
Hold the Line: Assuming the standard of
protection is maintained or increased, existing
farmland habitat maintained, no anticipated
long-term changes to habitat: Alone and in
combination No LSE
If standard of protection decreases, potential
impacts would be as for NAI and HTL. However
the SMP does not specify how the HTL policy
will be implemented, neither does it identify the
SoP to be provided. Therefore at this stage it is
not possible to identify whether impacts could
occur or not. The potential for impacts to occur
will be reviewed as part of the HRA for the
FRMS which will address how HTL will be
implemented including option alignments and
SoP: Alone: Uncertain – it is not possible to
rule out the likelihood of LSE (Alone) at
SMP2 level, further review to be undertaken
at FRMS stage.
In combination : effects unlikely as potentials
impacts associated with increased overtopping
of defences: No LSE
Habitat Severance Hold the Line: the defences will be maintained
in current position so no habitat fragmentation:
Alone and in combination No LSE
Managed Realignment: realignment of
defences would result in habitat loss or damage
(see below) rather than habitat fragmentation:
Alone and in combination No LSE
No Active Intervention : Alone and in
combination No LSE
23. Severn Estuary SMP2 – Appendix I – Part B – Habitats Regulation Assessment
Severn Estuary SMP Review 20
Disturbance Improvement or maintenance works under a
Hold the Line or Managed Realignment option
have the potential to disturb birds through noise
or visual disturbance. This can displace the
birds from their feeding grounds. Disturbance
can prevent the birds from feeding and in
response they either a) decrease their energy
intake at their present (disturbed) feeding site
through displacement activity, or b) move to an
alternative less favoured feeding site. Works will
only be permitted at the appropriate time of year
(only between April – September) to avoid the
most sensitive time: Alone and in combination
No LSE
No Active Intervention : Alone and in
combination No LSE
Habitat Loss/
Physical Damage
No Active Intervention/Managed
Realignment: increased tidal inundation
resulting in alteration in vegetation and farmland
habitats which could reduce suitability for
feeding and roosting: Alone: LSE
In combination: None of the plans and projects
reviewed are considered likely to result in
increased inundation of freshwater habitats: No
LSE
Hold the Line: assuming the standard of
protection is maintained or increased the
habitats beyond will be maintained and not
damaged: Alone and in combination No LSE
If standard of protection decreases, potential
impacts would be as for NAI and HTL. However
the SMP does not specify how the HTL policy
will be implemented, neither does it identify the
SoP to be provided. Therefore at this stage it is
not possible to identify whether impacts could
occur or not. The potential for impacts to occur
will be reviewed as part of the HRA for the
FRMS which will address how HTL will be
implemented including option alignments and
SoP: Alone: Uncertain – it is not possible to
rule out the likelihood of LSE (Alone) at
SMP2 level, further review to be undertaken
at FRMS stage.
In combination : effects unlikely as potentials
impacts associated with increased overtopping
of defences: No LSE
24. Severn Estuary SMP2 – Appendix I – Part B – Habitats Regulation Assessment
Severn Estuary SMP Review 21
Potential for some minor habitat loss as a
consequence of the increased footprint of the
defence- if SoP maintained or increased. Also
potential for cumulative and in combination
effects when all defences around the estuary are
taken into consideration. The SMP2 does not
specify how the HTL policy will be implemented
so it is not possible to identify whether any
impacts could occur or not. Further assessment
to be undertaken as part of the FRMS. Alone
and in combination Uncertain – it is not
possible to rule out the likelihood of LSE at
SMP2 level, further review to be undertaken
at FRMS stage
Birds of coastal habitats
(3.8)
Severn Estuary SPA,
Ramsar: Bewick’s Swan, ,
White-fronted goose, Dunlin,
Redshank, Shelduck,
Curlew Pintail, Ringed
plover, Waterfowl(>20, 000)
Severn Ramsar only: Teal,
lesser black backed gull,
Wigeon, Pochard
Change in physical
regime, flow or
velocity regime
No Active Intervention and/or Managed
Realignment: physical processes likely to result
in an increase in coastal and intertidal habitats:
Alone and in combination No LSE
Hold the Line increased sea level and coastal
squeeze could alter physical processes on the
foreshore potentially drowning out intertidal
habitats : Alone and in combination (with
North Devon and Somerset and Swansea and
Carmarthen Bay SMP2s) LSE
Changes in water
chemistry
All Options: No major changes in the water
quality of the Severn Estuary will result from the
implementation of the SMP2, due the limited
extent of contamination present around the
estuary and the large volume of water flowing
through the estuary on each tidal cycle which
would serve to dilute any local pollution event :
Alone and in combination No LSE
Habitat Severance Managed Realignment would increase extent
of coastal habitat; severance would not occur:
Alone and in combination No LSE
No Active Intervention : Alone and in
combination No LSE
Hold the Line: defences maintained in current
position so no habitat fragmentation: Alone and
in combination No LSE
Disturbance Improvement or maintenance works under a
Hold the Line or Managed Realignment option
have the potential to disturb birds through noise
or visual disturbance. This can displace the
birds from their feeding grounds. Disturbance
can prevent the birds from feeding and in
response they either a) decrease their energy
intake at their present (disturbed) feeding site
through displacement activity, or b) move to an
alternative less favoured feeding site. Works will
only be permitted at the appropriate time of year
(only between April – September) to avoid the
most sensitive time: Alone and in combination
No LSE
No Active Intervention : Alone and in
combination No LSE
25. Severn Estuary SMP2 – Appendix I – Part B – Habitats Regulation Assessment
Severn Estuary SMP Review 22
Habitat Loss/
Physical Damage
No Active Intervention/Managed
Realignment: Extent of coastal and intertidal
habitat would increase : Alone and in
combination No LSE
Hold the line: sea level rise and coastal
squeeze would result in the loss of intertidal
habitats, potentially reducing bird feeding areas:
Alone and in combination (with North Devon
and Somerset and Swansea and Carmarthen
Bay SMP2s) LSE
Potential for some minor habitat loss as a
consequence of the increased footprint of the
defence - if SoP maintained or increased. Also
potential for more significant cumulative and in
combination effects when all defences around
the estuary are taken into consideration. The
SMP2 does not specify how the HTL policy will
be implemented so it is not possible to identify
whether any impacts could occur or not. Further
assessment to be undertaken as part of the
FRMS. Alone and in combination Uncertain –
it is not possible to rule out the likelihood of
LSE at SMP2 level, further review to be
undertaken at FRMS stage
Birds of estuarine habitats
(3.9)
Severn Estuary SPA,
Ramsar: White-fronted
goose, Dunlin, Redshank,
Shelduck, Curlew,
Pintail,Ringed Plover)
Waterfowl(>20, 000)
Severn Ramsar only: Teal,
lesser black backed gull,
Wimbrel, Pochard
Change in physical
regime, flow or
velocity regime
No Active Intervention and Managed
Realignment options are likely to result in an
increase in the extent of intertidal habitats:
Alone and in combination No LSE
Under Hold the Line climate change and sea
level rise (coastal squeeze) will result in a
changes to flows and physical regimes which
could in turn potentially result in a change in the
extent and distribution of intertidal habitats in
front of the defence: Alone and in combination
(with North Devon and Somerset and Swansea
and Carmarthen Bay SMP2s) LSE
Changes in water
chemistry
No major changes in the water quality of the
Severn Estuary will result from the
implementation of the SMP2, due the limited
extent of contamination present around the
estuary and the large volume of water flowing
through the estuary on each tidal cycle which
would serve to dilute any local pollution event:
Alone and in combination No LSE
Habitat Severance Managed Realignment would increase the
extent of intertidal habitat; severance would not
occur: Alone and in combination No LSE
No Active Intervention : this option would
increase the extent of intertidal habitat Alone
and in combination No LSE
Hold the Line: defences maintained in current
position so no habitat fragmentation: Alone and
in combination No LSE
26. Severn Estuary SMP2 – Appendix I – Part B – Habitats Regulation Assessment
Severn Estuary SMP Review 23
Disturbance Improvement or maintenance works under a
Hold the Line or Managed Realignment option
have the potential to disturb birds through noise
or visual disturbance. This can displace the
birds from their feeding grounds. Disturbance
can prevent the birds from feeding and in
response they either a) decrease their energy
intake at their present (disturbed) feeding site
through displacement activity, or b) move to an
alternative less favoured feeding site. Works will
only be permitted at the appropriate time of year
(only between April – September) to avoid the
most sensitive time: Alone and in combination
No LSE
No Active Intervention : no disturbance would
result: Alone and in combination No LSE
Habitat Loss/
Physical Damage
No Active Intervention and Managed
Realignment options are likely to result in an
increase in the extent of intertidal habitats:
Alone and in combination No LSE
Under Hold the Line climate change and sea
level rise (coastal squeeze) could potentially
result in loss of or damage to intertidal habitats
in front of the defence, reducing feeding areas:
Alone and in combination (with North Devon
and Somerset and Swansea and Carmarthen
Bay SMP2s) LSE
Potential for some minor habitat loss as a
consequence of the increased footprint of the
defence- if SoP increased. Also potential for
more significant cumulative and in combination
effects when all defences around the estuary are
taken into consideration. The SMP2 does not
specify how the HTL policy will be implemented
so it is not possible to identify whether any
impacts could occur or not. Further assessment
to be undertaken as part of the FRMS. Alone
and in combination Uncertain – it is not
possible to rule out the likelihood of LSE at
SMP2 level, further review to be undertaken
at FRMS stage
27. Severn Estuary SMP2 – Appendix I – Part B – Habitats Regulation Assessment
Severn Estuary SMP Review 24
Severn Estuary SAC and Ramsar: The site extends through much of the study area and could be
affected by the implementation of all three of the SMP2 policy options
Sensitive Interest
Feature
Potential Hazard Potential exposure to Hazard and mechanism of
effect/impact if known
Estuarine & intertidal
habitats (1.12) :
Atlantic salt meadows,
Estuaries, Mudflats
and sandflats not
covered by
seawater at low tide
Change in physical
regime, flow or
velocity regime
Under Hold the Line climate change and sea level
rise (coastal squeeze) will result in a changes to
flows and physical regimes which will in turn alter
sedimentation and erosion processes potentially
resulting in a change in the extent and distribution of
intertidal habitats in front of the defence: Alone and
in combination (with North Devon and Somerset
and Swansea and Carmarthen Bay SMP2s) LSE
No Active Intervention and Managed Realignment
options are likely to result in an increase in the extent
of intertidal habitats: Alone and in combination No
LSE
Changes in water
chemistry
No major changes in the water quality of the Severn
Estuary will result from the implementation of the
SMP2, due the limited extent of contamination
present around the estuary and the large volume of
water flowing through the estuary on each tidal cycle
which would serve to dilute any local pollution event :
Alone and in combination No LSE
Habitat Severance Hold the Line: defences maintained in current
position so no habitat fragmentation: Alone and in
combination No LSE
Managed Realignment would increase the extent of
intertidal and estuarine habitat; severance would not
occur : Alone and in combination No LSE
No Active Intervention : Alone and in combination
No LSE
Disturbance N/A
Habitat Loss/
Physical Damage
Hold the Line: Sea level rise could potentially result
in habitat loss due to coastal squeeze Alone and in
combination (with North Devon and Somerset and
Swansea and Carmarthen Bay SMP2s) LSE
Potential for some minor habitat loss as a
consequence of the increased footprint of the
defence- if SoP increased. Also potential for more
significant cumulative and in combination effects
when all defences around the estuary are taken into
consideration. The SMP2 does not specify how the
HTL policy will be implemented so it is not possible to
identify whether any impacts could occur or not.
Further assessment to be undertaken as part of the
FRMS. Alone and in combination Uncertain – it is
not possible to rule out the likelihood of LSE at
SMP2 level, further review to be undertaken at
FRMS stage
28. Severn Estuary SMP2 – Appendix I – Part B – Habitats Regulation Assessment
Severn Estuary SMP Review 25
Managed Realignment: Realignment of defences
would increase the extent of intertidal and estuarine
habitats: Alone and in combination No LSE
No Active Intervention: extent if intertidal habitat
would roll back as sea level rose: Alone and in
combination No LSE
Anadromous fish
(2.5) : Allis shad,
Atlantic salmon, River
Lamprey, Sea
lamprey, Twaite shad
Change in physical
regime, flow or
velocity regime
All Options: Any changes in estuarine process that
might arise from any of the SMP2 policies will not be
significant enough at the estuary scale to affect fish
species for which the site is designated : Alone and
in combination No LSE
Changes in water
chemistry
All Options: No major changes in the water quality
of the Severn Estuary will result from the
implementation of the SMP2, due the limited extent
of contamination present around the estuary and the
large volume of water flowing through the estuary on
each tidal cycle which would serve to dilute any local
pollution event : Alone and in combination No LSE
Habitat Severance All Options: Implementation of any of the SMP2 will
not result in the severance of any of habitats relied
on by the listed fish species: Alone and in
combination No LSE
Disturbance All Options: None of the SMP2 policy options will
result in disturbance to fish species within the estuary
primarily due to the size of the estuary (and therefore
available fish habitats) and the fact that any works
would be located on the line or landward of existing
defences: Alone and in combination No LSE
Habitat Loss/
Physical Damage
All Options: Implementation of the SMP2 policies
will not result in the loss of or damage to any habitats
relied on by the listed fish species: Alone and in
combination No LSE
Severn Estuary Ramsar Only
The site extends through much of the study area and could be affected by the implementation of all
three of the SMP2 policy options
Sensitive Interest
Feature
Potential Hazard Potential exposure to Hazard and mechanism of
effect/impact if known
Severn Estuary
Ramsar
Non-migratory fish &
invertebrates of rivers
(2.6)
Change in physical
regime, flow or velocity
regime
All Options: Any changes in estuarine process that
might arise from any of the SMP2 policies will not
be significant enough at the estuary scale to affect
fish species for which the site is designated: Alone
and in combination No LSE
Changes in water
chemistry
All Options: No major changes in the water quality
of the Severn Estuary will result from the
implementation of the SMP2, due the limited extent
of contamination present around the estuary and
the large volume of water flowing through the
estuary on each tidal cycle which would serve to
dilute any local pollution event : Alone and in
combination No LSE
Habitat Severance All Options: Implementation of any of the SMP2
will not result in the severance of any of habitats
relied on by the listed fish species: Alone and in
combination No LSE
29. Severn Estuary SMP2 – Appendix I – Part B – Habitats Regulation Assessment
Severn Estuary SMP Review 26
Disturbance All Options: None of the SMP2 policy options will
result in disturbance to fish species within the
estuary primarily due to the size of the estuary (and
therefore available fish habitats) and the fact that
any works would be located on the line or landward
of existing defences: Alone and in combination
No LSE
Habitat Loss/ Physical
Damage
All Options: Implementation of the SMP2 policies
will not result in the loss of or damage to any
habitats relied on by the listed fish species: Alone
and in combination No LSE
Severn/Mor Hafren SAC Only
The site extends through much of the study area and could be affected by the implementation of all
three of the SMP2 policy options
Sensitive Interest
Feature
Potential Hazard Potential exposure to Hazard and mechanism of
effect/impact if known
Submerged marine
habitats (1.13) :
Reefs, subtidal
sandbanks that are
slightly covered by
sea water all the time.
Change in physical
regime/flow or velocity
regime
All Options: SMP2 polices could lead to changes
in estuarine process which in turn could affect
patterns of erosion and sedimentation; however
when considered in the context of the large scale
dynamic sub-tidal processes already operating
within the estuary any changes due to the SMP2
policy options would not be significant: Alone
and in combination No LSE
Changes in water
chemistry
All Options: No major changes in the water
quality of the Severn Estuary will result from the
implementation of the SMP2, due the limited
extent of contamination present around the
estuary and the large volume of water flowing
through the estuary on each tidal cycle which
would serve to dilute any local pollution event :
Alone and in combination No LSE
Habitat Severance N/A
Disturbance N/A
Habitat Loss /Physical
Damage
All Options: There would be no direct habitat loss
to any submerged habitats: Alone and in
combination No LSE
Somerset Levels and Moors SPA and Ramsar
The site lies outside the study area, (located approximately 15km downstream) but is potentially
hydraulically linked to the study area via flooding from the estuary. The levels are currently at risk
from extreme flood events from the estuary (e.g. 1 in 1000 year events). The preferred SMP2 policies
will not increase tidal flood risk to the site
Sensitive Interest
Feature
Potential Hazard Potential exposure to Hazard and mechanism of
effect/impact if known
Birds of lowland wet
grasslands (3.4)
Bewick’s swan,
Golden Plover, Teal,
Lapwing
Waterfowl(>20, 000)
Change in physical
regime, flow or velocity
regime
All Options: The preferred SMP2 policies will not
increase tidal flood risk to the site; physical
processes operating on the site will remain
unaltered: Alone and in combination No LSE
Changes in water
chemistry
All Options: The preferred SMP2 policies will not
affect water quality on the site: Alone and in
combination No LSE
Habitat Severance All Options: The preferred SMP2 policies will not
sever any habitats within the site: Alone and in
combination No LSE
Disturbance All Options: The preferred SMP2 policies will not
disturb birds using wet grassland habitats: Alone
and in combination No LSE
30. Severn Estuary SMP2 – Appendix I – Part B – Habitats Regulation Assessment
Severn Estuary SMP Review 27
Habitat Loss/ Physical
Damage
All Options: No loss of wet grassland habitat
within the site will occur: Alone and in
combination No LSE
Birds of lowland
freshwaters and
their margins (3.6)
Bewick’s swan, Teal,
Widgeon, Pintail,
Shovler,
Waterfowl(>20, 000),
Change in physical
regime, flow or velocity
regime
All Options: The preferred SMP2 policies will not
increase tidal flood risk to the site; physical
processes operating on the site will remain
unaltered: Alone and in combination No LSE
Changes in water
chemistry
All Options: The preferred SMP2 policies will not
affect water quality on the site: Alone and in
combination No LSE
Habitat Severance All Options: The preferred SMP2 policies will not
sever any habitats within the site: Alone and in
combination No LSE
Disturbance All Options: The preferred SMP2 policies will not
disturb birds using lowland freshwater habitats: No
Alone and in combination LSE
Habitat Loss/ Physical
Damage
All Options: No loss of lowland freshwater habitat
within the site will occur: Alone and in
combination No LSE
Birds of farmland
(3.7)
Bewick’s swan,
Lapwing, Widgeon
Change in physical
regime, flow or velocity
regime
All Options: The preferred SMP2 policies will not
increase tidal flood risk to the site; physical
processes operating on the site will remain
unaltered: Alone and in combination No LSE
Changes in water
chemistry
All Options: The preferred SMP2 policies will not
affect water quality on the site: Alone and in
combination No LSE
Habitat Severance All Options: The preferred SMP2 policies will not
sever any habitats within the site: No LSE
Disturbance All Options: The preferred SMP2 policies will not
disturb birds using farmland habitats: Alone and
in combination No LSE
Habitat Loss/ Physical
Damage
All Options: No loss of farmland habitat within the
site will occur: Alone and in combination No LSE
Birds of coastal
habitats (3.8)
Bewick’s Swan,
Golden Plover, Teal,
Widgeon, Pintail,
Waterfowl(>20, 000)
Change in physical
regime, flow or velocity
regime
No Active Intervention and/or Managed
Realignment: physical processes likely to result
in an increase in coastal and intertidal habitats:
Alone and in combination No LSE
Hold the Line increased sea level and coastal
squeeze could alter physical processes along the
Severn foreshore potentially affecting intertidal
habitats. This could adversely affect feeding and
roosting habitats which support bird populations
on the site potentially altering bird population size,
density and distribution on the Somerset Levels
and Moors: Alone and in combination (with
North Devon and Somerset and Swansea and
Carmarthen Bay SMP2s) LSE
Changes in water
chemistry
All Options: No major changes in the water
quality of the Severn Estuary will result from the
implementation of the SMP2, due the limited
extent of contamination present around the
estuary and the large volume of water flowing
through the estuary on each tidal cycle which
would serve to dilute any local pollution event.
Water quality on the or the Levels and Moors will
be unaffected : Alone and in combination No
LSE
Habitat Severance All Options: no severance of coastal habitats or
the levels and Moors sites will occur: Alone and
in combination No LSE
31. Severn Estuary SMP2 – Appendix I – Part B – Habitats Regulation Assessment
Severn Estuary SMP Review 28
Disturbance Improvement or maintenance works under a Hold
the Line or Managed Realignment option have
the potential to disturb birds using the foreshore
(outside the SPA/Ramsar) during construction.
Works will only be permitted at the appropriate
time of year (only between April – September) to
avoid the most sensitive period : Alone and in
combination No LSE
No Active Intervention : Alone and in
combination No LSE
No disturbance will occur on the sites themselves:
Alone and in combination No LSE
Habitat Loss/ Physical
Damage
No Active Intervention/Managed Realignment:
Extent of coastal and intertidal habitat would
increase : Alone and in combination No LSE
Hold the line: sea level rise and coastal squeeze
would result in the loss of intertidal habitats,
potentially reducing bird feeding areas: Alone and
in combination (with North Devon and Somerset
and Swansea and Carmarthen Bay SMP2s) LSE
Potential for some minor habitat loss as a
consequence of the increased footprint of the
defence- if SoP increased. Also potential for more
significant cumulative and in combination effects
when all defences around the estuary are taken
into consideration. The SMP2 does not specify
how the HTL policy will be implemented so it is
not possible to identify whether any impacts could
occur or not. Further assessment to be
undertaken as part of the FRMS. Alone and in
combination Uncertain – it is not possible to
rule out the likelihood of LSE at SMP2 level,
further review to be undertaken at FRMS
stage.
No habitat loss on the SPA/Ramsar sites
themselves will occur: Alone and in combination
No LSE
Birds of estuarine
habitats (3.9)
Golden Plover, Teal,
Lapwing, Mute Swan,
Widgeon, Pintail,
Shovler,
Waterfowl(>20, 000)
Change in physical
regime, flow or velocity
regime
No Active Intervention and/or Managed
Realignment: physical processes likely to result
in an increase in coastal and intertidal habitats:
Alone and in combination No LSE
Hold the Line increased sea level and coastal
squeeze could alter physical processes along the
Severn foreshore potentially affecting intertidal
habitats. This could adversely affect feeding and
roosting habitat which support birds populations
on the site potentially altering bird population size,
density and distribution on the Somerset Levels
and Moors: Alone and in combination (with
North Devon and Somerset and Swansea and
Carmarthen Bay SMP2s) LSE
32. Severn Estuary SMP2 – Appendix I – Part B – Habitats Regulation Assessment
Severn Estuary SMP Review 29
Changes in water
chemistry
All Options: No major changes in the water
quality of the Severn Estuary will result from the
implementation of the SMP2, due the limited
extent of contamination present around the
estuary and the large volume of water flowing
through the estuary on each tidal cycle which
would serve to dilute any local pollution event.
Water quality on the or the Levels and Moors will
be unaffected : Alone and in combination No
LSE
Habitat Severance All Options: no severance of coastal habitats or
the levels and Moors sites will occur: Alone and
in combination No LSE
Disturbance Improvement or maintenance works under a Hold
the Line or Managed Realignment option have
the potential to disturb birds using the foreshore
(outside the SPA/Ramsar) during construction.
Works will only be permitted at the appropriate
time of year (only between April – September) to
avoid the most sensitive period : Alone and in
combination No LSE
No Active Intervention : Alone and in
combination No LSE
No disturbance will occur on the sites themselves:
Alone and in combination No LSE
Habitat Loss/ Physical
Damage
No Active Intervention/Managed Realignment:
Extent of coastal and intertidal habitat would
increase : Alone and in combination No LSE
Hold the line: sea level rise and coastal squeeze
would result in the loss of intertidal habitats,
potentially reducing bird feeding areas: Alone and
in combination (with North Devon and Somerset
and Swansea and Carmarthen Bay SMP2s) LSE
Potential for some minor habitat loss as a
consequence of the increased footprint of the
defence - if SoP increased. Also potential for
more significant cumulative and in combination
effects when all defences around the estuary are
taken into consideration. The SMP2 does not
specify how the HTL policy will be implemented so
it is not possible to identify whether any impacts
could occur or not. Further assessment to be
undertaken as part of the FRMS: Alone and in
combination (with North Devon and Somerset
and Swansea and Carmarthen Bay SMP2s)
Uncertain – it is not possible to rule out the
likelihood of LSE at SMP2 level, further review
to be undertaken at FRMS stage.
No habitat loss on the SPA/Ramsar sites
themselves will occur: Alone and in combination
No LSE
33. Severn Estuary SMP2 – Appendix I – Part B – Habitats Regulation Assessment
Severn Estuary SMP Review 30
Somerset Levels Ramsar Only
The site lies outside the study area, (located approximately 15km downstream) but is potentially
hydraulically linked to the study area via flooding from the estuary. The levels are currently at risk
from extreme flood events from the estuary (e.g. 1 in 1000 year events). The preferred SMP2 policies
will not increase flood risk to the site
Sensitive Interest
Feature
Potential Hazard Potential exposure to Hazard and mechanism of
effect/impact if known
Red data book
invertebrates
(freshwater)
Change in physical
regime, flow or velocity
regime
All Options: The preferred SMP2 policies will not
significantly increase tidal flood risk to the site;
physical processes operating on the site will
remain unaltered. Increased tide locking of the
site may occur, increasing fluvial water levels on
the site, however this would be as a result of sea
level rise rather than implementation of the
Strategy: Alone and in combination No LSE
Changes in water
chemistry
All Options: The preferred SMP2 policies will not
affect water quality on the site: Alone and in
combination No LSE
Habitat Severance All Options: The preferred SMP2 policies will not
sever any habitats within the site: Alone and in
combination No LSE
Disturbance All Options: The preferred SMP2 policies will not
disturb invertebrate species on the site: Alone
and in combination No LSE
Habitat Loss/ Physical
Damage
All Options: No loss of habitat within the site will
occur; increased tide locking of the site may
occur, increasing fluvial water levels on the site,
however this would be as a result of sea level rise
rather than implementation of the Strategy: Alone
and in combination No LSE
North Somerset and Mendip Bat SAC
The site lies outside the study area, (located approximately 15km inland) however horseshoe bats
are known to feed on the levels with hedges used to shelter while feeding
Sensitive Interest
Feature
Potential Hazard Potential exposure to Hazard and mechanism of
effect/impact if known
1.7 Dry Grasslands
(6210 Semi-natural
dry grasslands and
scrubland facies: on
calcareous substrates
(Festuco-Brometalia))
Change in physical
regime, flow or velocity
regime
All Options: These habitats are not currently at
flood risk; this will not change under the preferred
SMP2 policies: Alone and in combination No
LSE
Changes in water
chemistry
All Options: These habitats are not currently at
flood risk; this will not change under the preferred
SMP2 policies; water quality n the vicinity of the
will be unaffected : Alone and in combination
No LSE
Habitat Severance All Options: These habitats are not currently at
flood risk; this will not change under the preferred
SMP2 policies; habitats will be unaffected by the
SMP2: Alone and in combination No LSE
Disturbance N/A
Habitat Loss/ Physical
Damage
All Options: No loss of habitat within the site will
occur: Alone and in combination No LSE
1.6 Dry Woodlands
and Scrub (9180
Tilio-Acerion forests of
slopes, screes and
ravines (Priority
feature)
Change in physical
regime, flow or velocity
regime
All Options: These habitats are not currently at
flood risk; this will not change under the preferred
SMP2 policies: Alone and in combination : No
LSE
Changes in water
chemistry
All Options: These habitats are not currently at
flood risk; this will not change under the preferred
SMP2 policies; water quality n the vicinity of the
will be unaffected : Alone and in combination
No LSE
34. Severn Estuary SMP2 – Appendix I – Part B – Habitats Regulation Assessment
Severn Estuary SMP Review 31
Habitat Severance All Options: These habitats are not currently at
flood risk; this will not change under the preferred
SMP2 policies; habitats will be unaffected by the
SMP2: Alone and in combination No LSE
Disturbance N/A
Habitat Loss/ Physical
Damage
All Options: No loss of habitat within the site will
occur: Alone and in combination No LSE
8310 Caves not open
to the public
Change in physical
regime, flow or velocity
regime
All Options: These habitats are not currently at
flood risk; this will not change under the preferred
SMP2 policies: Alone and in combination No
LSE
Changes in water
chemistry
All Options: These habitats are not currently at
flood risk; this will not change under the preferred
SMP2 policies; water quality n the vicinity of the
will be unaffected : Alone and in combination
No LSE
Habitat Severance All Options: These habitats are not currently at
flood risk; this will not change under the preferred
SMP2 policies; habitats will be unaffected by the
SMP2: Alone and in combination No LSE
Disturbance N/A
Habitat Loss/ Physical
Damage
All Options: No loss of habitat within the site will
occur: Alone and in combination No LSE
2.8 Mammals of
Wooded habitats 1303
Lesser horseshoe bat
(Rhinolophus
hipposideros)
1304 Greater
horseshoe bat
(Rhinolophus
ferrumequinum)
Change in physical
regime, flow or velocity
regime
Physical processes on the site will remain
unaffected: Alone and in combination No LSE
Changes in water
chemistry
N/A
Habitat Severance No habitats will be severed: Alone and in
combination No LSE
Disturbance N/A
Habitat Loss/ Physical
Damage
All Options: Increased tidal flooding of the bat
feeding areas on the Levels could result in loss of
invertebrates and also hedges used to shelter
while feeding. Alone and in combination (with
South Devon and Dorset SMP2): Uncertain – it is
not possible to rule out the likelihood of LSE
at the SMP2 level, further review to be
undertaken at FRMS stage
Mendip Limestone Grasslands SAC
The site lies outside the study area, (located approximately 15km inland) however horseshoe bats
are known to feed on the levels with hedges used to shelter while feeding
Sensitive Interest
Feature
Potential Hazard Potential exposure to Hazard and mechanism of
effect/impact if known
1.7 Dry Grasslands
(6210 Semi-natural
dry grasslands and
scrubland facies: on
calcareous substrates
(Festuco-Brometalia))
Change in physical
regime, flow or velocity
regime
All Options: These habitats are not currently at
flood risk; this will not change under the preferred
SMP2 policies: Alone and in combination No
LSE
Changes in water
chemistry
All Options: These habitats are not currently at
flood risk; this will not change under the preferred
SMP2 policies; water quality n the vicinity of the
will be unaffected : Alone and in combination
No LSE
Habitat Severance All Options: These habitats are not currently at
flood risk; this will not change under the preferred
SMP2 policies; habitats will be unaffected by the
SMP2: Alone and in combination No LSE
Disturbance N/A
Habitat Loss/ Physical
Damage
All Options: No loss of habitat within the site will
occur: Alone and in combination No LSE
35. Severn Estuary SMP2 – Appendix I – Part B – Habitats Regulation Assessment
Severn Estuary SMP Review 32
1.6 Dry Woodlands
and Scrub (9180
Tilio-Acerion forests of
slopes, screes and
ravines (Priority
feature))
Change in physical
regime, flow or velocity
regime
All Options: These habitats are not currently at
flood risk; this will not change under the preferred
SMP2 policies: Alone and in combination No
LSE
Changes in water
chemistry
All Options: These habitats are not currently at
flood risk; this will not change under the preferred
SMP2 policies; water quality n the vicinity of the
will be unaffected : Alone and in combination
No LSE
Habitat Severance All Options: These habitats are not currently at
flood risk; this will not change under the preferred
SMP2 policies; habitats will be unaffected by the
SMP2: Alone and in combination No LSE
Disturbance N/A
Habitat Loss/ Physical
Damage
All Options: No loss of habitat within the site will
occur: Alone and in combination No LSE
1.8 Dry heathland
habitats
(4030 European dry
heaths)
Change in physical
regime, flow or velocity
regime
All Options: These habitats are not currently at
flood risk; this will not change under the preferred
SMP2 policies: Alone and in combination No
LSE
Changes in water
chemistry
All Options: These habitats are not currently at
flood risk; this will not change under the preferred
SMP2 policies; water quality n the vicinity of the
will be unaffected : Alone and in combination
No LSE
Habitat Severance All Options: These habitats are not currently at
flood risk; this will not change under the preferred
SMP2 policies; habitats will be unaffected by the
SMP2: Alone and in combination No LSE
Disturbance N/A
Habitat Loss/ Physical
Damage
All Options: No loss of habitat within the site will
occur: Alone and in combination No LSE
8310 Caves not open
to the public
Change in physical
regime, flow or velocity
regime
All Options: These habitats are not currently at
flood risk; this will not change under the preferred
SMP2 policies: Alone and in combination No
LSE
Changes in water
chemistry
All Options: These habitats are not currently at
flood risk; this will not change under the preferred
SMP2 policies; water quality n the vicinity of the
will be unaffected : Alone and in combination
No LSE
Habitat Severance All Options: These habitats are not currently at
flood risk; this will not change under the preferred
SMP2 policies; habitats will be unaffected by the
SMP2: Alone and in combination No LSE
Disturbance N/A
Habitat Loss/ Physical
Damage
All Options: No loss of habitat within the site will
occur: Alone and in combination No LSE
2.8 Mammals of
Wooded habitats
(1304 Greater
horseshoe bat
(Rhinolophus
ferrumequinum)
Change in physical
regime, flow or velocity
regime
Physical processes on the site will remain
unaffected: Alone and in combination No LSE
Changes in water
chemistry
N/A
Habitat Severance No habitats will be severed: Alone and in
combination No LSE
Disturbance N/A
36. Severn Estuary SMP2 – Appendix I – Part B – Habitats Regulation Assessment
Severn Estuary SMP Review 33
Habitat Loss/ Physical
Damage
Increased tidal tidal flooding of the bat feeding
areas on the Levels could result in loss of
invertebrates and also hedges used to shelter
while feeding. TheSMP2 does not identify new
defence alignments or the SoP to be provided
under a Hold the Line policy: Alone and in
combination (with South Devon and Dorset
SMP2) Uncertain – it is not possible to rule out
the likelihood of LSE at the SMP2 level, further
review to be undertaken at FRMS stage
Wye SAC
No Active Intervention is the selected SMP2 policy option in the vicinity of the SAC (WYE 1-4)
Sensitive Interest
Feature
Potential Hazard Potential exposure to Hazard and mechanism of
effect/impact if known
Riverine habitats &
running waters (1.1):
Water courses of plain
to montane levels with
the Ranunculion
fluitantis and
Callitricho-Batrachion
vegetation
Change in physical
regime/ flow or velocity
regime
Policy will allow natural processes to continue to
operate ; no increase in flood or erosion risk is
predicted to occur over the lifetime of the SMP2;
the physical characteristics of the Wye, namely
the hard geology of the gorge mean significant
changes to the physical characteristics or
processes are unlikely to result: Alone and in
combination No LSE
Changes in water
chemistry
There are no major areas of contamination known
to exist along the river and the hard geology of the
gorge means negligible erosion is predicted to
occur. No construction works will be undertaken.
No major changes in the water quality of the Wye
will result from the implementation of the SMP2:
Alone and in combination No LSE
Disturbance No works to be undertaken so no disturbance will
result: Alone and in combination No LSE
Habitat Severance No works are proposed and physical process are
unlikely to change significantly; habitats will be
unaffected: Alone and in combination No LSE
Habitat Loss /Physical
Damage
No works are proposed and physical process are
unlikely to change significantly; habitats will be
unaffected: Alone and in combination No LSE
Bogs & wet habitats
(sensitive to
acidification)
(Transition mires and
quaking bogs)
Change in physical
regime/ flow or velocity
regime
This feature is located at the top of the Wye
catchment and is very unlikely to be affected by
the SMP2 polices : Alone and in combination
No LSE
Changes in water
chemistry
This feature is located at the top of the Wye
catchment and is very unlikely to be affected by
the SMP2 polices : Alone and in combination
No LSE
Disturbance No works to be undertaken so no disturbance will
result. In addition, this feature is located at the top
of the Wye catchment and is very unlikely to be
affected by the SMP2 polices : Alone and in
combination No LSE
Habitat Severance No works to be undertaken so no severance will
result. In addition, this feature is located at the top
of the Wye catchment and is very unlikely to be
affected by the SMP2 polices : Alone and in
combination No LSE
Habitat Loss /Physical
Damage
No works to be undertaken so no habitat loss will
result. In addition, this feature is located at the top
of the Wye catchment and is very unlikely to be
affected by the SMP2 polices : Alone and in
combination No LSE
37. Severn Estuary SMP2 – Appendix I – Part B – Habitats Regulation Assessment
Severn Estuary SMP Review 34
Anadromous fish
(2.5) : Allis shad,
Atlantic salmon, River
Lamprey, Sea
lamprey, Twaite shad
Change in physical
regime/flow or velocity
regime
Adoption of a No Active Intervention policy will
allow natural processes to continue to operate no
increase in flood or erosion risk is predicted to
occur over the lifetime of the SMP2; the physical
characteristics of the Wye, namely the hard
geology of the gorge mean significant changes to
the physical characteristics or processes are likely
to result: Alone and in combination No LSE
Changes to water
chemistry
There are no major areas of contamination known
to exist and the hard geology of the gorge mans
negligible erosion is predicted to occur and no
construction works will be undertaken. No major
changes in the water quality of the Wye will result
from the implementation of the SMP2: Alone and
in combination No LSE
Disturbance No works to be undertaken so no disturbance will
result : Alone and in combination No LSE
Habitat Severance No works are proposed and physical process are
unlikely to change significantly; habitats will be
unaffected: Alone and in combination No LSE
Habitat Loss /Physical
Damage
No works are proposed and physical process are
unlikely to change significantly; habitats will be
unaffected: Alone and in combination No LSE
Non-migratory fish &
invertebrates of
rivers (Atlantic stream
or White-clawed
crayfish, Brook
lamprey, Bullhead
Change in physical
regime/ flow or velocity
regime
Policy will allow natural processes to continue to
operate ; no increase in flood or erosion risk is
predicted to occur over the lifetime of the SMP2;
the physical characteristics of the Wye, namely
the hard geology of the gorge mean significant
changes to the physical characteristics or
processes are likely to result: Alone and in
combination No LSE
Changes in water
chemistry
There are no major areas of contamination known
to exist along the Wye Valley therefore and
therefore No major changes in the water quality of
the Wye will result from the implementation of the
SMP2: Alone and in combination No LSE
Disturbance No works to be undertaken so no disturbance will
result: Alone and in combination No LSE
Habitat Severance No works are proposed and physical process are
unlikely to change significantly; habitats will be
unaffected: No LSE
Habitat Loss /Physical
Damage
No works are proposed and physical process are
unlikely to change significantly; habitats will be
unaffected: Alone and in combination No LSE
Mammals of riverine
habitats (Otter)
Change in physical
regime/ flow or velocity
regime
Adoption of a No Active Intervention policy will
allow natural processes to continue to operate; no
increase in flood or erosion risk is predicted to
occur over the lifetime of the SMP2; the physical
characteristics of the Wye, namely the hard
geology of the gorge mean significant changes to
the physical characteristics or processes are likely
to result: Alone and in combination No LSE
Changes in water
chemistry
There are no major areas of contamination known
to exist along the Wye Valley therefore and
therefore No major changes in the water quality of
the Wye will result from the implementation of the
SMP2: Alone and in combination No LSE
Disturbance No works to be undertaken so no disturbance will
result: Alone and in combination No LSE
38. Severn Estuary SMP2 – Appendix I – Part B – Habitats Regulation Assessment
Severn Estuary SMP Review 35
Habitat Severance No works are proposed and physical process are
unlikely to change significantly; habitats will be
unaffected: Alone and in combination No LSE
Habitat Loss /Physical
Damage
No works are proposed and physical process are
unlikely to change significantly; habitats will be
unaffected : Alone and in combination No LSE
River Usk SAC
SMP2 policy options are as follows:
NEW1 NEW2 NEW3 NEW4 NEW5
HTL HTL NAI/MR HTL HTL
Sensitive Interest
Feature
Potential Hazard Potential exposure to Hazard and mechanism of
effect/impact if known
Riverine habitats &
running waters
(Floating vegetation of
Ranunculus of plain
and submountainous
rivers)
Change in physical
regime/ flow or velocity
regime
Hold the Line: Increase in sea level could result
in tidal incursion further up the Usk estuary
potentially resulting in estuarine sediments being
pushed further up the Usk. Given the existing
estuarine system is already highly dynamic the
resultant impacts on the physical regime are
considered to be negligible: Alone No LSE
In combination : potential for in combination
effects with the Wye and Usk CFMP however
further details at FRMS needed Uncertain – it is
not possible to rule out the likelihood of LSE
at the SMP2 level, further review to be
undertaken at FRMS stage
No Active Intervention/Managed Realignment
(NEW3 only) : In this largely rural reach a policy
of NAI/MR will allow natural processes to
dominate with an increase in tidal flooding and
reintegration of the river with its floodplain: Alone
and in combination No LSE
Changes in water
chemistry
No Active Intervention (NEW 3 only): If no
works are undertaken, there is minimal risk of
existing areas of contamination being disturbed:
Alone and in combination No LSE
Hold the Line or Managed Realignment: The
Usk Valley around Newport has a complex
industrial history and much of the land is
contaminated. Improvement or maintenance
works under a Hold the Line policy and Managed
Realignment have the potential to remobilise
contaminated sediments; this potential impact will
be avoided or mitigated through appropriate
investigations and remediation/mitigation at the
project level as appropriate. In addition more
detailed HRA will be undertaken at the FRMS and
project level with appropriate avoidance or
mitigation measures identified: Alone and in
combination No LSE
Disturbance N/A