SlideShare a Scribd company logo
Industrial Process in a Gear
Box Manufacturing
Organization
Submitted By
Nikhita Kumar
E-31
PRN- 15020441157
Overview of the company
• The company under study was incorporated in 1958 .
• The company started its operations with the manufacture of
Air Compressors and Pneumatic Tools. New product lines
were then added, including Gearboxes , Air Conditioning
and Refrigeration systems, etc. The company has also
earned an enviable reputation for its Systems Engineering
and Turnkey Project expertise.
• Over the years, the Company has developed various
sophisticated and high-tech products in the above categories
to cater to the demands of various industrial sectors.
• The Company has also established a number of joint
ventures and technology partnerships across the globe.
The Standard Industrial Process for gear
manufacturing in the organization has three
sub processes
1. Inquiry Handling Process
2. Order Execution Process
3. ERP process
The first process is followed by the second
Inquiry Handling Order Execution
ERP integrates these processes
Inquiry handling process flow is given below:
1. Inquiry receipt given to marketing dept.
2. Inquiry forwarded to design dept.
3. Design dept. will provide the correct recommendation (what to be
technically offered) with a cost estimation sheet. Cost estimation sheet
consist of various inputs to the solution.
4. Costing is done with the help of estimation sheet.
5. Offer preparation is done and it is forwarded to Customer.
6. Follow-up & Negotiation (technically & commercially).
7. Either order received or order lost.
8. If the order is received, Then order execution will follow.
Order
received
Order
Review
Design
output
Making of
GA drawing
Sending for
approval
Making Specs of
bought out, raw
material,
accessories
PO placement of
bought out, raw
material,
accessories
Receipt of
forgings
Manufacturing of
rotating
components
Receipt
of casing
Machining
& finishing
of casing
Receipt of bearings,
bought out &
accessories
Assembly
Trial
(Internal)
Post trial
inspection
Painting &
preservation
Dispatch
Gearbox Order Execution Process
Flow Chart
Improvements in Order
Execution Process
• Initially order review was immediately followed by design output which led to a
lot of errors in the later stage and to was quite a task to rectify the errors at a later
stage. So after order review, Design plan, review and verification was added to
validate the design before finalizing the design output. This led to overall increased
efficiency of the process. The Design plan, review and verification is done
according to the following standards
• In the earlier followed process, after making Specs and PO placement of bought
out, raw material, accessories, receipt of forging was generated without consulting
the availability of required jigs and fixtures from ME dept. So a new step was
added before generation of receipt of forging, Pass on data to ME for feasibility
check & fixtures arrangement. This reduced the scope of any rework of later
outsourcing of material.
*The Improvised Order Execution Process is shown in the next slide.
Revised Order Execution Process
Order
received
Order
Review
Design plan,
Review &
verification
Design
output
Making of
GA drawing
Sending for
approval
Making Specs of
bought out, raw
material, accessories
PO placement of
bought out, raw
material,
accessories
Pass on data to ME for
feasibility check &
fixtures arrangement
Receipt of
forgings
Manufacturing of
rotating
components
Receipt of
casing
Machining &
finishing of casing
Receipt of bearings,
bought out & accessoriesAssembly
Trial
(Internal)
Post trial
inspection
Painting &
preservation
Dispatch
Integration of the processes
 The company is using ERP process by implementing key modules from the
Oracle E-Business Suite and Oracle Knowledge Management to meet
its system and data integration needs across its various departments.
 The implementation of Oracle Applications is a strategic initiative and a
knowledge management tool to streamline existing operations across
different locations. This provides an integrated view of information across
the various departments to help our decision-making process.
 So all the processes discussed before are integrated using Oracle.
 When the order receipt is generated in oracle by Marketing Dept, the other
departments get notified in Oracle. Since different steps in the order
execution process are performed by different departments and they are
interdependent. So this ERP tool(ORACLE) helps in storing, distributing
and application of data across depts.
Final integrated process
R&E dept.
Marketing
dept
Production &
Quality dept
Procurement
dept
Manufacturing
Engineering
dept
Inquiry
Handling
Order
Execution
ORACLE
Thank you

More Related Content

What's hot

Betty Deck resume 10.2016
Betty Deck resume 10.2016Betty Deck resume 10.2016
Betty Deck resume 10.2016Betty Deck
 
Dynamic Strategies Iso Implementation Corporate Presentation Ii
Dynamic Strategies   Iso Implementation   Corporate Presentation   IiDynamic Strategies   Iso Implementation   Corporate Presentation   Ii
Dynamic Strategies Iso Implementation Corporate Presentation Ii
dynamic67
 
Metrology manager resume
Metrology manager resumeMetrology manager resume
Metrology manager resume
Karthick G
 
Hany Mohammed mahmoud Amer new1
Hany Mohammed mahmoud Amer new1Hany Mohammed mahmoud Amer new1
Hany Mohammed mahmoud Amer new1hany amer
 
James a.hinkle resume quality manufacturing 1976 - 2016
James a.hinkle resume quality   manufacturing 1976 - 2016James a.hinkle resume quality   manufacturing 1976 - 2016
James a.hinkle resume quality manufacturing 1976 - 2016
James Hinkle
 
CV - SUNIL VISHWAKARMA
CV - SUNIL VISHWAKARMACV - SUNIL VISHWAKARMA
CV - SUNIL VISHWAKARMA
Sunil Vishwakarma
 
ManufacturingProcessEngineerResume (4.1)
ManufacturingProcessEngineerResume (4.1)ManufacturingProcessEngineerResume (4.1)
ManufacturingProcessEngineerResume (4.1)Michael Baril
 
NBQC Company Brochure - 11
NBQC Company Brochure - 11NBQC Company Brochure - 11
NBQC Company Brochure - 11Neil Bennett
 
Resume_for_Mike_Baker_05-31-15
Resume_for_Mike_Baker_05-31-15Resume_for_Mike_Baker_05-31-15
Resume_for_Mike_Baker_05-31-15Michael Baker
 

What's hot (20)

KBM resume18102015
KBM resume18102015KBM resume18102015
KBM resume18102015
 
C v a.madrigal ingles
C v a.madrigal inglesC v a.madrigal ingles
C v a.madrigal ingles
 
Francisco Guerrero
Francisco GuerreroFrancisco Guerrero
Francisco Guerrero
 
RobertWhiteheadResume2015
RobertWhiteheadResume2015RobertWhiteheadResume2015
RobertWhiteheadResume2015
 
Betty Deck resume 10.2016
Betty Deck resume 10.2016Betty Deck resume 10.2016
Betty Deck resume 10.2016
 
Dynamic Strategies Iso Implementation Corporate Presentation Ii
Dynamic Strategies   Iso Implementation   Corporate Presentation   IiDynamic Strategies   Iso Implementation   Corporate Presentation   Ii
Dynamic Strategies Iso Implementation Corporate Presentation Ii
 
Metrology manager resume
Metrology manager resumeMetrology manager resume
Metrology manager resume
 
osama cv 2015
osama cv 2015osama cv 2015
osama cv 2015
 
CV JAVED
CV JAVEDCV JAVED
CV JAVED
 
resume luis lopez
resume luis lopezresume luis lopez
resume luis lopez
 
Steve Isaac CV
Steve Isaac  CVSteve Isaac  CV
Steve Isaac CV
 
Resume
ResumeResume
Resume
 
Hany Mohammed mahmoud Amer new1
Hany Mohammed mahmoud Amer new1Hany Mohammed mahmoud Amer new1
Hany Mohammed mahmoud Amer new1
 
Chandrasekaran
ChandrasekaranChandrasekaran
Chandrasekaran
 
James a.hinkle resume quality manufacturing 1976 - 2016
James a.hinkle resume quality   manufacturing 1976 - 2016James a.hinkle resume quality   manufacturing 1976 - 2016
James a.hinkle resume quality manufacturing 1976 - 2016
 
CV - SUNIL VISHWAKARMA
CV - SUNIL VISHWAKARMACV - SUNIL VISHWAKARMA
CV - SUNIL VISHWAKARMA
 
ManufacturingProcessEngineerResume (4.1)
ManufacturingProcessEngineerResume (4.1)ManufacturingProcessEngineerResume (4.1)
ManufacturingProcessEngineerResume (4.1)
 
Fabrication CV
Fabrication CVFabrication CV
Fabrication CV
 
NBQC Company Brochure - 11
NBQC Company Brochure - 11NBQC Company Brochure - 11
NBQC Company Brochure - 11
 
Resume_for_Mike_Baker_05-31-15
Resume_for_Mike_Baker_05-31-15Resume_for_Mike_Baker_05-31-15
Resume_for_Mike_Baker_05-31-15
 

Viewers also liked

Manufacturing Process - Powder Metallurgy
Manufacturing Process - Powder MetallurgyManufacturing Process - Powder Metallurgy
Manufacturing Process - Powder Metallurgy
Audi Naufal Ramadhian
 
machining and machine tool by alakshendra Unit v
machining and machine tool by alakshendra Unit vmachining and machine tool by alakshendra Unit v
machining and machine tool by alakshendra Unit v
alakshendra pratap singh
 
Powder metallurgy for Sintered Products
Powder metallurgy for Sintered ProductsPowder metallurgy for Sintered Products
Powder metallurgy for Sintered Products
Payas Bharadwaj
 
Powder metallurgy final
Powder metallurgy finalPowder metallurgy final
Powder metallurgy final
Kevin Pereira
 
U1 p4 production & characteristics of metal powders
U1 p4 production & characteristics of metal powdersU1 p4 production & characteristics of metal powders
U1 p4 production & characteristics of metal powders
gautam buddha university
 
Geometric dimensioning and tolerancing
Geometric dimensioning and tolerancingGeometric dimensioning and tolerancing
Geometric dimensioning and tolerancing
R.P.M - Engineering and Project Management
 
Gear manufacturing methods
Gear manufacturing methodsGear manufacturing methods
Gear manufacturing methods
Toufik123
 
Powder Metallurgy - PROCESS
Powder Metallurgy - PROCESSPowder Metallurgy - PROCESS
Powder Metallurgy - PROCESS
Rona Mae Taduyo
 
POWDER METALLURGY
POWDER METALLURGYPOWDER METALLURGY
POWDER METALLURGY
DENNY OTTARACKAL
 
Ppt of gear manufacturing
Ppt of gear manufacturingPpt of gear manufacturing
Ppt of gear manufacturing
indreshswt
 
Powder metallurgy
Powder metallurgyPowder metallurgy
Powder metallurgy
Shailendra Pratap Singh
 
Benchmarking ppt
Benchmarking pptBenchmarking ppt
Benchmarking ppt
AMARAYYA
 
ppt of gears manufacturing processes
ppt of gears manufacturing processesppt of gears manufacturing processes
ppt of gears manufacturing processes
Ayush Upadhyay
 
Gd & t datum targets
Gd & t datum targetsGd & t datum targets
Gd & t datum targetsTarunJujare
 

Viewers also liked (18)

Manufacturing Process - Powder Metallurgy
Manufacturing Process - Powder MetallurgyManufacturing Process - Powder Metallurgy
Manufacturing Process - Powder Metallurgy
 
machining and machine tool by alakshendra Unit v
machining and machine tool by alakshendra Unit vmachining and machine tool by alakshendra Unit v
machining and machine tool by alakshendra Unit v
 
Powder metallurgy for Sintered Products
Powder metallurgy for Sintered ProductsPowder metallurgy for Sintered Products
Powder metallurgy for Sintered Products
 
Powder metallurgy final
Powder metallurgy finalPowder metallurgy final
Powder metallurgy final
 
U1 p4 production & characteristics of metal powders
U1 p4 production & characteristics of metal powdersU1 p4 production & characteristics of metal powders
U1 p4 production & characteristics of metal powders
 
Geometric dimensioning and tolerancing
Geometric dimensioning and tolerancingGeometric dimensioning and tolerancing
Geometric dimensioning and tolerancing
 
Gear manufacturing methods
Gear manufacturing methodsGear manufacturing methods
Gear manufacturing methods
 
4. gear manufacturing
4. gear manufacturing4. gear manufacturing
4. gear manufacturing
 
Powder Metallurgy - PROCESS
Powder Metallurgy - PROCESSPowder Metallurgy - PROCESS
Powder Metallurgy - PROCESS
 
POWDER METALLURGY
POWDER METALLURGYPOWDER METALLURGY
POWDER METALLURGY
 
Ppt of gear manufacturing
Ppt of gear manufacturingPpt of gear manufacturing
Ppt of gear manufacturing
 
Benchmarking TQM
Benchmarking TQMBenchmarking TQM
Benchmarking TQM
 
Powder metallurgy
Powder metallurgyPowder metallurgy
Powder metallurgy
 
Benchmarking ppt
Benchmarking pptBenchmarking ppt
Benchmarking ppt
 
ppt of gears manufacturing processes
ppt of gears manufacturing processesppt of gears manufacturing processes
ppt of gears manufacturing processes
 
Gd & t datum targets
Gd & t datum targetsGd & t datum targets
Gd & t datum targets
 
Benchmarking
BenchmarkingBenchmarking
Benchmarking
 
Slideshare ppt
Slideshare pptSlideshare ppt
Slideshare ppt
 

Similar to Nikhita kumar, E 31

Technical Performance Measures
Technical Performance Measures Technical Performance Measures
Technical Performance Measures Jassfer Alina
 
6 Steps to Accelerate the Development Cycle | Life Science Parker Hannifin
6 Steps to Accelerate the Development Cycle | Life Science Parker Hannifin6 Steps to Accelerate the Development Cycle | Life Science Parker Hannifin
6 Steps to Accelerate the Development Cycle | Life Science Parker Hannifin
Parker Hannifin Corporation
 
Advanced Product Quality Planning (APQP) and Production Part Approval Process...
Advanced Product Quality Planning (APQP) and Production Part Approval Process...Advanced Product Quality Planning (APQP) and Production Part Approval Process...
Advanced Product Quality Planning (APQP) and Production Part Approval Process...
AJAYKUMAR836335
 
Jamco_FAI_Training_Materials_AS9102_Rev_B.pdf
Jamco_FAI_Training_Materials_AS9102_Rev_B.pdfJamco_FAI_Training_Materials_AS9102_Rev_B.pdf
Jamco_FAI_Training_Materials_AS9102_Rev_B.pdf
FaizyNoh
 
Discovering New Product Introduction using Autodesk PLM 360 – Rodney Coffey, ...
Discovering New Product Introduction using Autodesk PLM 360 – Rodney Coffey, ...Discovering New Product Introduction using Autodesk PLM 360 – Rodney Coffey, ...
Discovering New Product Introduction using Autodesk PLM 360 – Rodney Coffey, ...
Synergis Engineering Design Solutions
 
Discovering New Product Introduction (NPI) using Autodesk Fusion Lifecycle
Discovering New Product Introduction (NPI) using Autodesk Fusion LifecycleDiscovering New Product Introduction (NPI) using Autodesk Fusion Lifecycle
Discovering New Product Introduction (NPI) using Autodesk Fusion Lifecycle
Razorleaf Corporation
 
Computer Aided Design - Unit I Introduction
Computer Aided Design - Unit I IntroductionComputer Aided Design - Unit I Introduction
Computer Aided Design - Unit I Introduction
JayavendhanJ
 
Shriraam Madanagopal Internship Report
Shriraam Madanagopal Internship ReportShriraam Madanagopal Internship Report
Shriraam Madanagopal Internship Report
shri1984
 
Production Planning & Control Book
Production Planning & Control BookProduction Planning & Control Book
Production Planning & Control Book
Learn With GeekAlign
 
Product innovation & process innovation
Product innovation & process innovationProduct innovation & process innovation
Product innovation & process innovation
VijayKrKhurana
 
Top 10 signs you should do in engineering
Top 10 signs you should do in engineeringTop 10 signs you should do in engineering
Top 10 signs you should do in engineering
vijaya Lakshmi
 
APQP
APQP APQP
CAD _ UNIT 1.pptx
CAD _ UNIT 1.pptxCAD _ UNIT 1.pptx
CAD _ UNIT 1.pptx
jayabal subbaian
 
final no-2 U too brutus persentation[1].pptx
final no-2 U too brutus persentation[1].pptxfinal no-2 U too brutus persentation[1].pptx
final no-2 U too brutus persentation[1].pptx
ssusera46859
 
commissioning.pdf
commissioning.pdfcommissioning.pdf
commissioning.pdf
haris348605
 
Top 10 signs you should do in engineering
Top 10 signs you should do in engineeringTop 10 signs you should do in engineering
Top 10 signs you should do in engineering
vijaya Lakshmi
 
Sow p9
Sow p9Sow p9

Similar to Nikhita kumar, E 31 (20)

Technical Performance Measures
Technical Performance Measures Technical Performance Measures
Technical Performance Measures
 
IT NPI Process
IT NPI ProcessIT NPI Process
IT NPI Process
 
6 Steps to Accelerate the Development Cycle | Life Science Parker Hannifin
6 Steps to Accelerate the Development Cycle | Life Science Parker Hannifin6 Steps to Accelerate the Development Cycle | Life Science Parker Hannifin
6 Steps to Accelerate the Development Cycle | Life Science Parker Hannifin
 
Aim crisp handout
Aim crisp handoutAim crisp handout
Aim crisp handout
 
Advanced Product Quality Planning (APQP) and Production Part Approval Process...
Advanced Product Quality Planning (APQP) and Production Part Approval Process...Advanced Product Quality Planning (APQP) and Production Part Approval Process...
Advanced Product Quality Planning (APQP) and Production Part Approval Process...
 
Jamco_FAI_Training_Materials_AS9102_Rev_B.pdf
Jamco_FAI_Training_Materials_AS9102_Rev_B.pdfJamco_FAI_Training_Materials_AS9102_Rev_B.pdf
Jamco_FAI_Training_Materials_AS9102_Rev_B.pdf
 
Discovering New Product Introduction using Autodesk PLM 360 – Rodney Coffey, ...
Discovering New Product Introduction using Autodesk PLM 360 – Rodney Coffey, ...Discovering New Product Introduction using Autodesk PLM 360 – Rodney Coffey, ...
Discovering New Product Introduction using Autodesk PLM 360 – Rodney Coffey, ...
 
Discovering New Product Introduction (NPI) using Autodesk Fusion Lifecycle
Discovering New Product Introduction (NPI) using Autodesk Fusion LifecycleDiscovering New Product Introduction (NPI) using Autodesk Fusion Lifecycle
Discovering New Product Introduction (NPI) using Autodesk Fusion Lifecycle
 
Computer Aided Design - Unit I Introduction
Computer Aided Design - Unit I IntroductionComputer Aided Design - Unit I Introduction
Computer Aided Design - Unit I Introduction
 
PI Training July 2015
PI Training July 2015PI Training July 2015
PI Training July 2015
 
Shriraam Madanagopal Internship Report
Shriraam Madanagopal Internship ReportShriraam Madanagopal Internship Report
Shriraam Madanagopal Internship Report
 
Production Planning & Control Book
Production Planning & Control BookProduction Planning & Control Book
Production Planning & Control Book
 
Product innovation & process innovation
Product innovation & process innovationProduct innovation & process innovation
Product innovation & process innovation
 
Top 10 signs you should do in engineering
Top 10 signs you should do in engineeringTop 10 signs you should do in engineering
Top 10 signs you should do in engineering
 
APQP
APQP APQP
APQP
 
CAD _ UNIT 1.pptx
CAD _ UNIT 1.pptxCAD _ UNIT 1.pptx
CAD _ UNIT 1.pptx
 
final no-2 U too brutus persentation[1].pptx
final no-2 U too brutus persentation[1].pptxfinal no-2 U too brutus persentation[1].pptx
final no-2 U too brutus persentation[1].pptx
 
commissioning.pdf
commissioning.pdfcommissioning.pdf
commissioning.pdf
 
Top 10 signs you should do in engineering
Top 10 signs you should do in engineeringTop 10 signs you should do in engineering
Top 10 signs you should do in engineering
 
Sow p9
Sow p9Sow p9
Sow p9
 

Recently uploaded

RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
BBPMedia1
 
Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...
Lviv Startup Club
 
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-indiafalcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
Falcon Invoice Discounting
 
The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...
Adam Smith
 
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Navpack & Print
 
Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...
dylandmeas
 
Improving profitability for small business
Improving profitability for small businessImproving profitability for small business
Improving profitability for small business
Ben Wann
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
anasabutalha2013
 
FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134
LR1709MUSIC
 
BeMetals Presentation_May_22_2024 .pdf
BeMetals Presentation_May_22_2024   .pdfBeMetals Presentation_May_22_2024   .pdf
BeMetals Presentation_May_22_2024 .pdf
DerekIwanaka1
 
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
taqyed
 
VAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and RequirementsVAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and Requirements
uae taxgpt
 
April 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products NewsletterApril 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products Newsletter
NathanBaughman3
 
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
BBPMedia1
 
Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111
zoyaansari11365
 
Enterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdfEnterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdf
KaiNexus
 
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdfikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
agatadrynko
 
Buy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star ReviewsBuy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star Reviews
usawebmarket
 
Digital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and TemplatesDigital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and Templates
Aurelien Domont, MBA
 
3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
tanyjahb
 

Recently uploaded (20)

RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
 
Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...
 
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-indiafalcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
 
The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...
 
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
 
Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...
 
Improving profitability for small business
Improving profitability for small businessImproving profitability for small business
Improving profitability for small business
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
 
FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134
 
BeMetals Presentation_May_22_2024 .pdf
BeMetals Presentation_May_22_2024   .pdfBeMetals Presentation_May_22_2024   .pdf
BeMetals Presentation_May_22_2024 .pdf
 
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
 
VAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and RequirementsVAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and Requirements
 
April 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products NewsletterApril 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products Newsletter
 
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
 
Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111
 
Enterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdfEnterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdf
 
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdfikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
 
Buy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star ReviewsBuy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star Reviews
 
Digital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and TemplatesDigital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and Templates
 
3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
 

Nikhita kumar, E 31

  • 1. Industrial Process in a Gear Box Manufacturing Organization Submitted By Nikhita Kumar E-31 PRN- 15020441157
  • 2. Overview of the company • The company under study was incorporated in 1958 . • The company started its operations with the manufacture of Air Compressors and Pneumatic Tools. New product lines were then added, including Gearboxes , Air Conditioning and Refrigeration systems, etc. The company has also earned an enviable reputation for its Systems Engineering and Turnkey Project expertise. • Over the years, the Company has developed various sophisticated and high-tech products in the above categories to cater to the demands of various industrial sectors. • The Company has also established a number of joint ventures and technology partnerships across the globe.
  • 3. The Standard Industrial Process for gear manufacturing in the organization has three sub processes 1. Inquiry Handling Process 2. Order Execution Process 3. ERP process The first process is followed by the second Inquiry Handling Order Execution ERP integrates these processes
  • 4. Inquiry handling process flow is given below: 1. Inquiry receipt given to marketing dept. 2. Inquiry forwarded to design dept. 3. Design dept. will provide the correct recommendation (what to be technically offered) with a cost estimation sheet. Cost estimation sheet consist of various inputs to the solution. 4. Costing is done with the help of estimation sheet. 5. Offer preparation is done and it is forwarded to Customer. 6. Follow-up & Negotiation (technically & commercially). 7. Either order received or order lost. 8. If the order is received, Then order execution will follow.
  • 5. Order received Order Review Design output Making of GA drawing Sending for approval Making Specs of bought out, raw material, accessories PO placement of bought out, raw material, accessories Receipt of forgings Manufacturing of rotating components Receipt of casing Machining & finishing of casing Receipt of bearings, bought out & accessories Assembly Trial (Internal) Post trial inspection Painting & preservation Dispatch Gearbox Order Execution Process Flow Chart
  • 6. Improvements in Order Execution Process • Initially order review was immediately followed by design output which led to a lot of errors in the later stage and to was quite a task to rectify the errors at a later stage. So after order review, Design plan, review and verification was added to validate the design before finalizing the design output. This led to overall increased efficiency of the process. The Design plan, review and verification is done according to the following standards • In the earlier followed process, after making Specs and PO placement of bought out, raw material, accessories, receipt of forging was generated without consulting the availability of required jigs and fixtures from ME dept. So a new step was added before generation of receipt of forging, Pass on data to ME for feasibility check & fixtures arrangement. This reduced the scope of any rework of later outsourcing of material. *The Improvised Order Execution Process is shown in the next slide.
  • 7. Revised Order Execution Process Order received Order Review Design plan, Review & verification Design output Making of GA drawing Sending for approval Making Specs of bought out, raw material, accessories PO placement of bought out, raw material, accessories Pass on data to ME for feasibility check & fixtures arrangement Receipt of forgings Manufacturing of rotating components Receipt of casing Machining & finishing of casing Receipt of bearings, bought out & accessoriesAssembly Trial (Internal) Post trial inspection Painting & preservation Dispatch
  • 8. Integration of the processes  The company is using ERP process by implementing key modules from the Oracle E-Business Suite and Oracle Knowledge Management to meet its system and data integration needs across its various departments.  The implementation of Oracle Applications is a strategic initiative and a knowledge management tool to streamline existing operations across different locations. This provides an integrated view of information across the various departments to help our decision-making process.  So all the processes discussed before are integrated using Oracle.  When the order receipt is generated in oracle by Marketing Dept, the other departments get notified in Oracle. Since different steps in the order execution process are performed by different departments and they are interdependent. So this ERP tool(ORACLE) helps in storing, distributing and application of data across depts.
  • 9. Final integrated process R&E dept. Marketing dept Production & Quality dept Procurement dept Manufacturing Engineering dept Inquiry Handling Order Execution ORACLE