SlideShare a Scribd company logo
1
Technical Training
MRO Spare Parts Optimisation &
Inventory Reduction
Robinsons Brewery Visitors & Conference Centre, Stockport
13-15th November 2017
2
Too many companies do a very poor job in managing effectively
their spare parts. The issues start in the project phase (due to
poor processes) and continue through to the Do, Check and Act
phase.
The issues arise in the project phase and are rarely corrected in
the operation phase
This presentation highlight some of the techniques, we will
discuss in our 3 day training course.
NB. we don’t just tell you how to optimise, we give you
worksheets containing all the spares optimisation formula and
hold your hand though exercises
Introduction
3
Cost reduction will arise from
Eliminating duplicates
Replacing OEM with OPM items
Identifying obsolete and other unwanted items
Prioritising purchasing
Optimising inventory parameters
Remember, the benefits from an improvement in just a single
line item, can easily pay for this 3 day course
Cost Reduction
4
Benefits gained by past delegates
60 – 70% reduction in some line item class groups
Identification of duplicate up to 9,000 euro per item
50-60% reduction in average stock level
6,000 duplicates identified
Ease of identification of spare parts through better
cataloguing
Improved reliability leading to reduction in usage levels
Improved documentation
Better initial spares selection
Benefits
5
Plan
DoCheck
Act
Do (Execute)
Purchase Initial
Spares
Establish
cataloging &
inventory
management in
CMMS
PDCA Effective Inventory Management
Plan
Develop strategic
plans, procedures
and guides
Improve (Act)
Optimise &
rationalise to
achieve cost
reduction
Identify Duplicates
Training
Analyse (Check)
Audit spares
management
processes,
CMMS data
quality,
inventory
effectiveness
6
Course Topics
01 Introduction to Spares Management
02 Improving Vendor Spare’s Data Quality
03 Spare Part Costs
04 Inventory Cost Reduction Programme (25 tactics)
05 Building an Effective Spares Cataloguing
06 Reliability & Failure Statistics
07 Challenging Vendors Recommended Quantities
08 When to Order
09 How Many to Buy
10 Auditing Inventory Control Effectiveness
7
Course Topics…Continued
11 Database Solutions
12 Dealing with High Value Spares
13 Alternative Strategies
14 KPIs for Inventory Management
Course Review and Delegates Action Plan
8
Course Covers the following Stock
Reduction Tactics
9
Course Covers the following Stock
Reduction Tactics ..continued
10
This case study extracted from a CMMS Data Upload file shows
the spares data build to be extremely poor. To correct this poor
data build, 8 actions were recommended.
Has your data been created consistently?
1. Spares Data Quality Audit
11
Under the ISO55000 a company must:
Develop a set of structured documents,
These documents must cover the life of the assets from
the project to the end of life
Assets under ISO55000 include equipment, data,
information, costs and people
Demonstrate decision making based on risk
Demonstrate continuous improvement
A framework to support the above for effective spare
management will be part of the workshop, as well as how to
ensure cataloguing consistency
2. Strategic Plans
12
3. Do We Need To Stock?
We will cover a number of questions that we need to ask, before
we decide to purchase, such as:
What are the costs of not having it (infers criticality analysis)?
Is it required for a major PM or shutdown? Can we order just in time
Is it required because of failure, what is the probability of failure ?
Can we predict the failure, what is the P-F interval?, have we
enough warning to obtain the spare before failure occurs
What is our philosophy (repair, replace, recondition, use a
specialist)? e.g. mechanical seals, engine overhauls,
What is our philosophy for project material e.g. flanges, fittings, etc.
is this always to be provided by a contractor
etc
13
The recommended quantities recommended by Vendors are
rarely challenged in a technical manner.
This screen shot from our TAMS software shows how this done
The 1st item in the list is only operating 50% of the time, therefore,
the calculated ADR (Annual Demand Rate) is 50% less. The
Vendor may not have been provided with this information.
4. Challenge Vendors Recommended
Quantities?
14
5. Spares Criticality
As a default spares criticality is based on the criticality of the
equipment, i.e. if the equipment is critical then the spares are
critical and then reduce the criticality based on operating
context e.g. similar equipment operating that have a less
critical function
Once the spares criticality is assigned a default % service
level is selected
The service level for a spare part can be further redefined by
considering the spares demand rate
15
7. Identify Duplicate Items
Example duplicates from our various data reviews.
16
8. 80-20 Rule Applied to AIV
AIV is easily calculated and can be uploaded to the CMMS for
immediate benefits
Annual Issue
Value in $
Percentage of line items
A
B C
High level of
attention
Auto Generate
replenishment
orders
Some
attention
17
9. Demand Codes - Why Important
Demand codes are based on the lead time demand rate
(LTDR)
The demand code is important as:
Fast movers can have a lower service level, and hence
reduced safety stock – we discuss further later
Support the obsolete programme
Slow movers need to be analysed … NEED to review if
worthwhile to reorder??
18
10. Unwanted Stock Items
A poor write-off policy will result in unnecessary stock being
carried
Items that should be written of are:
1) Obsolete items
2) Damaged items through poor preservation
3) Items beyond their shelf life
4) Excess stocked items
5) Items stocked that are not covered by current repair and
contracting strategies
How effective is your unwanted stock programme?
19
11. Lead Time
Lead time has a big effect on stock levels and costs, most
CMMS populated data shows the vendor time to deliver and
not the total lead time from highlighting a need to order until
the items are on the shelf available to be issued
Reduction in lead time will lead to:
Reduction in safety stock
Reduction in Reorder Point
Reduction in stock-holding levels
Reduction in inventory (stock-holding) costs
20
12. Optimise Inventory Parameters
The diagrams below show the opportunities to identify
excessive costs.
Note the Calulated values for ROP and Max stock infers
optimised values
Act
Max
Cal
Max
Excess
Holding
Cost
Act
ROP
Cal
ROP
Excess
Holding
Cost
Cal
ROP
Act
ROP
Stock-
Out Cost
21
Opportunities to Reduce Costs
Buying too frequently Buying too many & excess
holding stock
Cal
OQ
Act
OQ
Excess
Buying
Cost
Act
OQ
Cal
OQ
Excess
Holding
Cost
Here are similar models for order quantities
22
Ths example from a Pharmaceutical company shows excessive
stocking. The metric is the Number of Years of Stock.
We calculate this value at line item value
Inventory Control Parameters Audit
23
The following chart shows how safety stock levels increase
rapidly when the Service Level is too high
Excess Stocking
% Service Level
Safety Stock
Level
24
This case study shows that the proposed changes to the
replenishment parameters reduces the actual average stock
level $ value by over 50%
Optimisation & Stock Value Reduction
Proposed
£15,600
reduction in
average
stockholding
value
25
The default replenishment strategy is the Reorder Point Policy
(a fixed order quantity). Although many call this a Min-Max
For this policy to be valid, the EOQ has to be greater than the
lead time demand rate (LTDR):
When this condition exists as shown below, then a more cost
effective replenishment strategy is required
13. Select Right Replenishment Strategy
Other options to be considered are:
Min-Max (Variable order quantity)
Constant Vendor Quantity
26
Challenging stocking of slow movers, is based on indirect
costs
14. Identifying & Challenging Slow
Movers
27
Evaluating Insurance Spares Decisions
RAM software such as Reliasoft’s
Blocksim is ideal to support
decisions whether to stock high
value – long lead time items
28
16. Standardisation, e.g. avoid
multiple OPMs
In this company, where we conducted a rationalisation study,
there were spiral wound gaskets stocked from 5 different
vendors.
This policy typically, lead to duplicate line items:
Flexitallic
James Walker
Lamons
Garlock
Cefilac
29
Interchangability Bolts
This example shows how often we don’t know the full details of
the part when we do our cataloguing.
It is possible there will be duplicates usually 12-15%
SAP # Short Description
1356731 BOLT,DBLE HEX HD. F/3" BALL VALVE
1356730 BOLT,DBLE HEX HD. 3" BALL VALVE M1025-3
1352851 BOLT,DBLE HEX HD. DANIEL P/N 555-44-112
1345084 BOLT,DBLE HEX HD. FISHER P/N 1U625631192
1352840 BOLT,DBLE HEX HD. DIVERTER P/N M1225-2
1352843 BOLT,DBLE HEX HD. 3/8"x3/4" DANIEL METER
1352833 BOLT,DBLE HEX HD. 2" BALL VALVE
1352836 BOLT,DBLE HEX HD. 3" DIVERTER VALVE
30
Case Study Ring Type Joints (RTJs)
Case study, this is what can be achieved by scandalisation and
rationalisation programme, a 70% reduction in line items
Initial Findings - 163 SAP Line Items
RTJ Types – R_Oval and Octagonal, BX and RX
Material - Soft Iron, Carbon Steel, SS304, SS316
Reduction achieved through:
Removing Duplicates
Combining R Type Oval & Octagonal
Combining SS304 & 316
Transferring unwanted items, i.e. Soft Iron, Cast Steel
31
19. Monitoring Issues & Stock Balance
It is essential to monitor:
a) The number of issues per year versus the estimated annual
demand rate (ADR)….
We will show a number of examples where poor reliability has
influenced the number of items used significantly
Equally we could have situations where reliability has
improved and we can then reduce the ROP
a) The stock balance and if always above the safety stock level,
then the desired service level can be reduced. Note: the
criticality will remain the same
32
20. Root Cause Analysis
RCA/RCFA is a big topic on its own
There are many approaches to RCA:
5 why
Cause and effect or why tree
Sequence of events and
Additional techniques including failure analysis to support
the data collection phase
We will show two case studies where actual usage was
significantly more than estimated and had not been highlighted
through monitoring
33
23. Database Solutions
Database solutions support more effective analysis for:
Initial spare part planning & procurement
Data cleansing and cataloguing
Spare part inventory parameters analysis
BOM development
Spend Analysis
34
Want to Learn More?
Next Training Course:
Venue: Robinson Brewery and Visitors Centre, Stockport, UK
Date: Nov 13-15th 2017
For more information contact dave@ramsoftuk.com
David Thompson
Senior Consultant (maintenance, reliability & spares)
Ramsoft (UK) Ltd
Lancs, UK
www.ramsoftuk.com
www.linkedin.com/in/davidthompsonreliability
External Tutor & Project Supervisor in Reliability at Robert Gordon University
Over 50 years experience in Maintenance, Reliability and Spares and in diverse
industries
35
Future Courses
Asia
Jan 17-19th Miri, Sarawak
Jan 22nd – 24th Hanoi, Vietnam
Jan 29-31st Bangkok, Thailand
For more information on the above Asian courses contact:
Harn@petro1.com.my
For on-site courses contact:
dave@ramsoftuk.com
Middle East
Dec 17-21st Define Management Consultancy & Training

More Related Content

What's hot

Spare parts management
Spare parts managementSpare parts management
Spare parts management
Medha Yadav
 
Spares criticality assessment methods & equipment overhaul replacementrepairs...
Spares criticality assessment methods & equipment overhaul replacementrepairs...Spares criticality assessment methods & equipment overhaul replacementrepairs...
Spares criticality assessment methods & equipment overhaul replacementrepairs...Amirul Faiz Amil Azman
 
Inventory management
Inventory managementInventory management
Inventory management
AngelaMaurya
 
03.chapter3.4.spares.criticality
03.chapter3.4.spares.criticality03.chapter3.4.spares.criticality
03.chapter3.4.spares.criticality
Amirul Faiz Amil Azman
 
KEY TO PROFITABILITY: SPARE PART MANAGEMENT
KEY TO PROFITABILITY: SPARE PART MANAGEMENTKEY TO PROFITABILITY: SPARE PART MANAGEMENT
KEY TO PROFITABILITY: SPARE PART MANAGEMENT
Dr. V.N. Tikku
 
Capacity Requirement Planning, Rough Cut Capacity Planning
Capacity Requirement Planning, Rough Cut Capacity PlanningCapacity Requirement Planning, Rough Cut Capacity Planning
Capacity Requirement Planning, Rough Cut Capacity Planning
Raju Pegada
 
XYZ ABC Analysis
XYZ ABC AnalysisXYZ ABC Analysis
XYZ ABC Analysis
Kiran Varri CHT/ CHIA
 
How to improve order picking efficiency
How to improve order picking efficiencyHow to improve order picking efficiency
How to improve order picking efficiency
SILVER LINING STORAGE SOLUTIONS
 
Top 10 Procurement KPI\'s
Top 10 Procurement KPI\'sTop 10 Procurement KPI\'s
Top 10 Procurement KPI\'samberkar
 
Inventory control and management
Inventory control and managementInventory control and management
Maintenace management and TPM
Maintenace management and TPMMaintenace management and TPM
Maintenace management and TPM
Mohieudeen Mohamed
 
Best practises of inventory optimization
Best practises of inventory optimizationBest practises of inventory optimization
Best practises of inventory optimization
BatchMaster Software Pvt. Ltd.
 
SAP MATERIAL MANAGEMENT(MM) ONLINE TRAINING IN USA|AUSTRALIA
SAP MATERIAL MANAGEMENT(MM) ONLINE TRAINING IN USA|AUSTRALIASAP MATERIAL MANAGEMENT(MM) ONLINE TRAINING IN USA|AUSTRALIA
SAP MATERIAL MANAGEMENT(MM) ONLINE TRAINING IN USA|AUSTRALIA
SAP Training
 
Inventory and inventory management
Inventory and inventory managementInventory and inventory management
Inventory and inventory management
Mohammed Jasir PV
 
Reducing Costs of Spares and Inventory Levels
Reducing Costs of Spares and Inventory LevelsReducing Costs of Spares and Inventory Levels
Reducing Costs of Spares and Inventory Levels
David Thompson
 
Control systems for spare parts.
Control systems for spare parts.Control systems for spare parts.
Control systems for spare parts.
Medha Yadav
 
INVENTORY MANAGEMENT
INVENTORY MANAGEMENT INVENTORY MANAGEMENT
INVENTORY MANAGEMENT
Zamri Yahya
 
Material Control- techniques
Material Control- techniquesMaterial Control- techniques
Material Control- techniques
monikakansal
 
Inventory management
Inventory managementInventory management
Inventory management
saurabhsabiba
 

What's hot (20)

Spare parts management
Spare parts managementSpare parts management
Spare parts management
 
Spares criticality assessment methods & equipment overhaul replacementrepairs...
Spares criticality assessment methods & equipment overhaul replacementrepairs...Spares criticality assessment methods & equipment overhaul replacementrepairs...
Spares criticality assessment methods & equipment overhaul replacementrepairs...
 
Inventory management
Inventory managementInventory management
Inventory management
 
Operations MRP
Operations MRPOperations MRP
Operations MRP
 
03.chapter3.4.spares.criticality
03.chapter3.4.spares.criticality03.chapter3.4.spares.criticality
03.chapter3.4.spares.criticality
 
KEY TO PROFITABILITY: SPARE PART MANAGEMENT
KEY TO PROFITABILITY: SPARE PART MANAGEMENTKEY TO PROFITABILITY: SPARE PART MANAGEMENT
KEY TO PROFITABILITY: SPARE PART MANAGEMENT
 
Capacity Requirement Planning, Rough Cut Capacity Planning
Capacity Requirement Planning, Rough Cut Capacity PlanningCapacity Requirement Planning, Rough Cut Capacity Planning
Capacity Requirement Planning, Rough Cut Capacity Planning
 
XYZ ABC Analysis
XYZ ABC AnalysisXYZ ABC Analysis
XYZ ABC Analysis
 
How to improve order picking efficiency
How to improve order picking efficiencyHow to improve order picking efficiency
How to improve order picking efficiency
 
Top 10 Procurement KPI\'s
Top 10 Procurement KPI\'sTop 10 Procurement KPI\'s
Top 10 Procurement KPI\'s
 
Inventory control and management
Inventory control and managementInventory control and management
Inventory control and management
 
Maintenace management and TPM
Maintenace management and TPMMaintenace management and TPM
Maintenace management and TPM
 
Best practises of inventory optimization
Best practises of inventory optimizationBest practises of inventory optimization
Best practises of inventory optimization
 
SAP MATERIAL MANAGEMENT(MM) ONLINE TRAINING IN USA|AUSTRALIA
SAP MATERIAL MANAGEMENT(MM) ONLINE TRAINING IN USA|AUSTRALIASAP MATERIAL MANAGEMENT(MM) ONLINE TRAINING IN USA|AUSTRALIA
SAP MATERIAL MANAGEMENT(MM) ONLINE TRAINING IN USA|AUSTRALIA
 
Inventory and inventory management
Inventory and inventory managementInventory and inventory management
Inventory and inventory management
 
Reducing Costs of Spares and Inventory Levels
Reducing Costs of Spares and Inventory LevelsReducing Costs of Spares and Inventory Levels
Reducing Costs of Spares and Inventory Levels
 
Control systems for spare parts.
Control systems for spare parts.Control systems for spare parts.
Control systems for spare parts.
 
INVENTORY MANAGEMENT
INVENTORY MANAGEMENT INVENTORY MANAGEMENT
INVENTORY MANAGEMENT
 
Material Control- techniques
Material Control- techniquesMaterial Control- techniques
Material Control- techniques
 
Inventory management
Inventory managementInventory management
Inventory management
 

Similar to Mro spare parts optimisation and inventory reduction uk 2017 11

3 Day Spares Optimisation Course (Multiple Venues)
3 Day Spares Optimisation Course (Multiple Venues)3 Day Spares Optimisation Course (Multiple Venues)
3 Day Spares Optimisation Course (Multiple Venues)
David Thompson
 
C3 3 day spares optimisation rationalisation 2017 01
C3 3 day spares optimisation rationalisation 2017 01C3 3 day spares optimisation rationalisation 2017 01
C3 3 day spares optimisation rationalisation 2017 01
Martyn Thompson
 
C3 3 day spares optimisation rationalisation 2017 01
C3 3 day spares optimisation  rationalisation 2017 01C3 3 day spares optimisation  rationalisation 2017 01
C3 3 day spares optimisation rationalisation 2017 01
David Thompson
 
Is your mro spare parts reduction program compliant with iso55000 rev 3
Is your mro spare parts reduction program compliant with iso55000 rev 3Is your mro spare parts reduction program compliant with iso55000 rev 3
Is your mro spare parts reduction program compliant with iso55000 rev 3
David Thompson
 
MRO Spare Parts Improvement Programme Conforms to ISO55000
MRO Spare Parts Improvement Programme Conforms to ISO55000MRO Spare Parts Improvement Programme Conforms to ISO55000
MRO Spare Parts Improvement Programme Conforms to ISO55000
David Thompson
 
Inventory Management And Mrp Erp
Inventory Management And Mrp   ErpInventory Management And Mrp   Erp
Inventory Management And Mrp Erp
Joanmaines
 
Including Multi-Echelon Inventory in your SiOP cycle - Our vision at Solventure
Including Multi-Echelon Inventory in your SiOP cycle - Our vision at SolventureIncluding Multi-Echelon Inventory in your SiOP cycle - Our vision at Solventure
Including Multi-Echelon Inventory in your SiOP cycle - Our vision at Solventure
Solventure
 
Four Quick Ways To Unlock Hidden Manufacturing Capacity
Four Quick Ways To Unlock Hidden Manufacturing CapacityFour Quick Ways To Unlock Hidden Manufacturing Capacity
Four Quick Ways To Unlock Hidden Manufacturing Capacity
Global Business Professor
 
UOPOPS571 You can do it--uopops571.com
UOPOPS571 You can do it--uopops571.comUOPOPS571 You can do it--uopops571.com
UOPOPS571 You can do it--uopops571.com
agathachristie218
 
Increase production through improved spare parts availability
Increase production through improved spare parts availabilityIncrease production through improved spare parts availability
Increase production through improved spare parts availability
IMAFS
 
Inventory management system power pount presentation).pptx
Inventory management system power pount presentation).pptxInventory management system power pount presentation).pptx
Inventory management system power pount presentation).pptx
VivekaKumar10
 
APICS- Spare Parts Strengthen the Whole
APICS- Spare Parts Strengthen the WholeAPICS- Spare Parts Strengthen the Whole
APICS- Spare Parts Strengthen the WholeShawn Tay
 
Giacomo Squintani, PTC presenation at Spare Parts 2013
Giacomo Squintani, PTC presenation at Spare Parts 2013Giacomo Squintani, PTC presenation at Spare Parts 2013
Giacomo Squintani, PTC presenation at Spare Parts 2013
Copperberg
 
OPS 571 GENIUS You can do it--ops571genius.com
OPS 571 GENIUS You can do it--ops571genius.comOPS 571 GENIUS You can do it--ops571genius.com
OPS 571 GENIUS You can do it--ops571genius.com
agathachristie218
 
OPS 571 HELP You can do it--ops571help.com
OPS 571 HELP You can do it--ops571help.comOPS 571 HELP You can do it--ops571help.com
OPS 571 HELP You can do it--ops571help.com
agathachristie218
 
Bba501 & production and operations management
Bba501 & production and operations managementBba501 & production and operations management
Bba501 & production and operations management
smumbahelp
 
For an infinite queuing situation, if the arrival rate for loading trucks is ...
For an infinite queuing situation, if the arrival rate for loading trucks is ...For an infinite queuing situation, if the arrival rate for loading trucks is ...
For an infinite queuing situation, if the arrival rate for loading trucks is ...
ramuaa126
 
For an infinite queuing situation, if the arrival rate for loading trucks is ...
For an infinite queuing situation, if the arrival rate for loading trucks is ...For an infinite queuing situation, if the arrival rate for loading trucks is ...
For an infinite queuing situation, if the arrival rate for loading trucks is ...
yearstart2
 
Sample sem 2 winter 2015
Sample sem 2 winter 2015Sample sem 2 winter 2015
Sample sem 2 winter 2015
naveen kumar
 

Similar to Mro spare parts optimisation and inventory reduction uk 2017 11 (20)

3 Day Spares Optimisation Course (Multiple Venues)
3 Day Spares Optimisation Course (Multiple Venues)3 Day Spares Optimisation Course (Multiple Venues)
3 Day Spares Optimisation Course (Multiple Venues)
 
C3 3 day spares optimisation rationalisation 2017 01
C3 3 day spares optimisation rationalisation 2017 01C3 3 day spares optimisation rationalisation 2017 01
C3 3 day spares optimisation rationalisation 2017 01
 
C3 3 day spares optimisation rationalisation 2017 01
C3 3 day spares optimisation  rationalisation 2017 01C3 3 day spares optimisation  rationalisation 2017 01
C3 3 day spares optimisation rationalisation 2017 01
 
Is your mro spare parts reduction program compliant with iso55000 rev 3
Is your mro spare parts reduction program compliant with iso55000 rev 3Is your mro spare parts reduction program compliant with iso55000 rev 3
Is your mro spare parts reduction program compliant with iso55000 rev 3
 
MRO Spare Parts Improvement Programme Conforms to ISO55000
MRO Spare Parts Improvement Programme Conforms to ISO55000MRO Spare Parts Improvement Programme Conforms to ISO55000
MRO Spare Parts Improvement Programme Conforms to ISO55000
 
Inventory Management And Mrp Erp
Inventory Management And Mrp   ErpInventory Management And Mrp   Erp
Inventory Management And Mrp Erp
 
Including Multi-Echelon Inventory in your SiOP cycle - Our vision at Solventure
Including Multi-Echelon Inventory in your SiOP cycle - Our vision at SolventureIncluding Multi-Echelon Inventory in your SiOP cycle - Our vision at Solventure
Including Multi-Echelon Inventory in your SiOP cycle - Our vision at Solventure
 
Four Quick Ways To Unlock Hidden Manufacturing Capacity
Four Quick Ways To Unlock Hidden Manufacturing CapacityFour Quick Ways To Unlock Hidden Manufacturing Capacity
Four Quick Ways To Unlock Hidden Manufacturing Capacity
 
UOPOPS571 You can do it--uopops571.com
UOPOPS571 You can do it--uopops571.comUOPOPS571 You can do it--uopops571.com
UOPOPS571 You can do it--uopops571.com
 
Increase production through improved spare parts availability
Increase production through improved spare parts availabilityIncrease production through improved spare parts availability
Increase production through improved spare parts availability
 
Inventory management system power pount presentation).pptx
Inventory management system power pount presentation).pptxInventory management system power pount presentation).pptx
Inventory management system power pount presentation).pptx
 
APICS- Spare Parts Strengthen the Whole
APICS- Spare Parts Strengthen the WholeAPICS- Spare Parts Strengthen the Whole
APICS- Spare Parts Strengthen the Whole
 
Giacomo Squintani, PTC presenation at Spare Parts 2013
Giacomo Squintani, PTC presenation at Spare Parts 2013Giacomo Squintani, PTC presenation at Spare Parts 2013
Giacomo Squintani, PTC presenation at Spare Parts 2013
 
OPS 571 GENIUS You can do it--ops571genius.com
OPS 571 GENIUS You can do it--ops571genius.comOPS 571 GENIUS You can do it--ops571genius.com
OPS 571 GENIUS You can do it--ops571genius.com
 
OPS 571 HELP You can do it--ops571help.com
OPS 571 HELP You can do it--ops571help.comOPS 571 HELP You can do it--ops571help.com
OPS 571 HELP You can do it--ops571help.com
 
Bba501 & production and operations management
Bba501 & production and operations managementBba501 & production and operations management
Bba501 & production and operations management
 
Chapter 12
Chapter 12Chapter 12
Chapter 12
 
For an infinite queuing situation, if the arrival rate for loading trucks is ...
For an infinite queuing situation, if the arrival rate for loading trucks is ...For an infinite queuing situation, if the arrival rate for loading trucks is ...
For an infinite queuing situation, if the arrival rate for loading trucks is ...
 
For an infinite queuing situation, if the arrival rate for loading trucks is ...
For an infinite queuing situation, if the arrival rate for loading trucks is ...For an infinite queuing situation, if the arrival rate for loading trucks is ...
For an infinite queuing situation, if the arrival rate for loading trucks is ...
 
Sample sem 2 winter 2015
Sample sem 2 winter 2015Sample sem 2 winter 2015
Sample sem 2 winter 2015
 

More from David Thompson

Using UNSPSC codes in the MRO Inventory System
Using UNSPSC codes in the MRO Inventory SystemUsing UNSPSC codes in the MRO Inventory System
Using UNSPSC codes in the MRO Inventory System
David Thompson
 
Using UNSPSC codes in the MRO Inventory System
Using UNSPSC codes in the MRO Inventory SystemUsing UNSPSC codes in the MRO Inventory System
Using UNSPSC codes in the MRO Inventory System
David Thompson
 
Using UNSPSC codes in the MRO Inventory System
Using UNSPSC codes in the MRO Inventory SystemUsing UNSPSC codes in the MRO Inventory System
Using UNSPSC codes in the MRO Inventory System
David Thompson
 
Using UNSPSC codes in the MRO Inventory System
Using UNSPSC codes in the MRO Inventory SystemUsing UNSPSC codes in the MRO Inventory System
Using UNSPSC codes in the MRO Inventory System
David Thompson
 
Using UNSPSC codes in the MRO Inventory System
Using UNSPSC codes in the MRO Inventory SystemUsing UNSPSC codes in the MRO Inventory System
Using UNSPSC codes in the MRO Inventory System
David Thompson
 
Reduce mro inventory costs ppt
Reduce mro inventory costs pptReduce mro inventory costs ppt
Reduce mro inventory costs ppt
David Thompson
 
New for 2018 MRO master data auditing and cleansing
New for 2018 MRO  master data auditing and cleansingNew for 2018 MRO  master data auditing and cleansing
New for 2018 MRO master data auditing and cleansing
David Thompson
 
MRO spare part case studies master data
MRO spare part case studies   master dataMRO spare part case studies   master data
MRO spare part case studies master data
David Thompson
 
Sap mrp hb and fx 2017 09
Sap mrp hb and fx 2017 09Sap mrp hb and fx 2017 09
Sap mrp hb and fx 2017 09
David Thompson
 
Sap mrp hb ex 2017 09 rev 4
Sap mrp hb ex 2017 09  rev 4Sap mrp hb ex 2017 09  rev 4
Sap mrp hb ex 2017 09 rev 4
David Thompson
 
All books
All booksAll books
All books
David Thompson
 
Reliability books
Reliability booksReliability books
Reliability books
David Thompson
 
Other books
Other booksOther books
Other books
David Thompson
 
Am books
Am booksAm books
Am books
David Thompson
 
Equip mgmt books
Equip mgmt booksEquip mgmt books
Equip mgmt books
David Thompson
 
Ramsoft - Case 4 Spiral Wound Gaskets
Ramsoft - Case 4 Spiral Wound GasketsRamsoft - Case 4 Spiral Wound Gaskets
Ramsoft - Case 4 Spiral Wound Gaskets
David Thompson
 
Food and Drink MRO Spares Data Audit
Food and Drink MRO Spares Data AuditFood and Drink MRO Spares Data Audit
Food and Drink MRO Spares Data Audit
David Thompson
 

More from David Thompson (17)

Using UNSPSC codes in the MRO Inventory System
Using UNSPSC codes in the MRO Inventory SystemUsing UNSPSC codes in the MRO Inventory System
Using UNSPSC codes in the MRO Inventory System
 
Using UNSPSC codes in the MRO Inventory System
Using UNSPSC codes in the MRO Inventory SystemUsing UNSPSC codes in the MRO Inventory System
Using UNSPSC codes in the MRO Inventory System
 
Using UNSPSC codes in the MRO Inventory System
Using UNSPSC codes in the MRO Inventory SystemUsing UNSPSC codes in the MRO Inventory System
Using UNSPSC codes in the MRO Inventory System
 
Using UNSPSC codes in the MRO Inventory System
Using UNSPSC codes in the MRO Inventory SystemUsing UNSPSC codes in the MRO Inventory System
Using UNSPSC codes in the MRO Inventory System
 
Using UNSPSC codes in the MRO Inventory System
Using UNSPSC codes in the MRO Inventory SystemUsing UNSPSC codes in the MRO Inventory System
Using UNSPSC codes in the MRO Inventory System
 
Reduce mro inventory costs ppt
Reduce mro inventory costs pptReduce mro inventory costs ppt
Reduce mro inventory costs ppt
 
New for 2018 MRO master data auditing and cleansing
New for 2018 MRO  master data auditing and cleansingNew for 2018 MRO  master data auditing and cleansing
New for 2018 MRO master data auditing and cleansing
 
MRO spare part case studies master data
MRO spare part case studies   master dataMRO spare part case studies   master data
MRO spare part case studies master data
 
Sap mrp hb and fx 2017 09
Sap mrp hb and fx 2017 09Sap mrp hb and fx 2017 09
Sap mrp hb and fx 2017 09
 
Sap mrp hb ex 2017 09 rev 4
Sap mrp hb ex 2017 09  rev 4Sap mrp hb ex 2017 09  rev 4
Sap mrp hb ex 2017 09 rev 4
 
All books
All booksAll books
All books
 
Reliability books
Reliability booksReliability books
Reliability books
 
Other books
Other booksOther books
Other books
 
Am books
Am booksAm books
Am books
 
Equip mgmt books
Equip mgmt booksEquip mgmt books
Equip mgmt books
 
Ramsoft - Case 4 Spiral Wound Gaskets
Ramsoft - Case 4 Spiral Wound GasketsRamsoft - Case 4 Spiral Wound Gaskets
Ramsoft - Case 4 Spiral Wound Gaskets
 
Food and Drink MRO Spares Data Audit
Food and Drink MRO Spares Data AuditFood and Drink MRO Spares Data Audit
Food and Drink MRO Spares Data Audit
 

Recently uploaded

Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
symbo111
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
Self-Control of Emotions by Slidesgo.pptx
Self-Control of Emotions by Slidesgo.pptxSelf-Control of Emotions by Slidesgo.pptx
Self-Control of Emotions by Slidesgo.pptx
iemerc2024
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Soumen Santra
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Fundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptxFundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptx
manasideore6
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
aqil azizi
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
ssuser7dcef0
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
Swimming pool mechanical components design.pptx
Swimming pool  mechanical components design.pptxSwimming pool  mechanical components design.pptx
Swimming pool mechanical components design.pptx
yokeleetan1
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
nooriasukmaningtyas
 
Online aptitude test management system project report.pdf
Online aptitude test management system project report.pdfOnline aptitude test management system project report.pdf
Online aptitude test management system project report.pdf
Kamal Acharya
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
anoopmanoharan2
 
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.pptPROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
bhadouriyakaku
 
sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
ssuser36d3051
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 

Recently uploaded (20)

Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
Self-Control of Emotions by Slidesgo.pptx
Self-Control of Emotions by Slidesgo.pptxSelf-Control of Emotions by Slidesgo.pptx
Self-Control of Emotions by Slidesgo.pptx
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Fundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptxFundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptx
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
Swimming pool mechanical components design.pptx
Swimming pool  mechanical components design.pptxSwimming pool  mechanical components design.pptx
Swimming pool mechanical components design.pptx
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
 
Online aptitude test management system project report.pdf
Online aptitude test management system project report.pdfOnline aptitude test management system project report.pdf
Online aptitude test management system project report.pdf
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
 
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.pptPROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
 
sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 

Mro spare parts optimisation and inventory reduction uk 2017 11

  • 1. 1 Technical Training MRO Spare Parts Optimisation & Inventory Reduction Robinsons Brewery Visitors & Conference Centre, Stockport 13-15th November 2017 2 Too many companies do a very poor job in managing effectively their spare parts. The issues start in the project phase (due to poor processes) and continue through to the Do, Check and Act phase. The issues arise in the project phase and are rarely corrected in the operation phase This presentation highlight some of the techniques, we will discuss in our 3 day training course. NB. we don’t just tell you how to optimise, we give you worksheets containing all the spares optimisation formula and hold your hand though exercises Introduction
  • 2. 3 Cost reduction will arise from Eliminating duplicates Replacing OEM with OPM items Identifying obsolete and other unwanted items Prioritising purchasing Optimising inventory parameters Remember, the benefits from an improvement in just a single line item, can easily pay for this 3 day course Cost Reduction 4 Benefits gained by past delegates 60 – 70% reduction in some line item class groups Identification of duplicate up to 9,000 euro per item 50-60% reduction in average stock level 6,000 duplicates identified Ease of identification of spare parts through better cataloguing Improved reliability leading to reduction in usage levels Improved documentation Better initial spares selection Benefits
  • 3. 5 Plan DoCheck Act Do (Execute) Purchase Initial Spares Establish cataloging & inventory management in CMMS PDCA Effective Inventory Management Plan Develop strategic plans, procedures and guides Improve (Act) Optimise & rationalise to achieve cost reduction Identify Duplicates Training Analyse (Check) Audit spares management processes, CMMS data quality, inventory effectiveness 6 Course Topics 01 Introduction to Spares Management 02 Improving Vendor Spare’s Data Quality 03 Spare Part Costs 04 Inventory Cost Reduction Programme (25 tactics) 05 Building an Effective Spares Cataloguing 06 Reliability & Failure Statistics 07 Challenging Vendors Recommended Quantities 08 When to Order 09 How Many to Buy 10 Auditing Inventory Control Effectiveness
  • 4. 7 Course Topics…Continued 11 Database Solutions 12 Dealing with High Value Spares 13 Alternative Strategies 14 KPIs for Inventory Management Course Review and Delegates Action Plan 8 Course Covers the following Stock Reduction Tactics
  • 5. 9 Course Covers the following Stock Reduction Tactics ..continued 10 This case study extracted from a CMMS Data Upload file shows the spares data build to be extremely poor. To correct this poor data build, 8 actions were recommended. Has your data been created consistently? 1. Spares Data Quality Audit
  • 6. 11 Under the ISO55000 a company must: Develop a set of structured documents, These documents must cover the life of the assets from the project to the end of life Assets under ISO55000 include equipment, data, information, costs and people Demonstrate decision making based on risk Demonstrate continuous improvement A framework to support the above for effective spare management will be part of the workshop, as well as how to ensure cataloguing consistency 2. Strategic Plans 12 3. Do We Need To Stock? We will cover a number of questions that we need to ask, before we decide to purchase, such as: What are the costs of not having it (infers criticality analysis)? Is it required for a major PM or shutdown? Can we order just in time Is it required because of failure, what is the probability of failure ? Can we predict the failure, what is the P-F interval?, have we enough warning to obtain the spare before failure occurs What is our philosophy (repair, replace, recondition, use a specialist)? e.g. mechanical seals, engine overhauls, What is our philosophy for project material e.g. flanges, fittings, etc. is this always to be provided by a contractor etc
  • 7. 13 The recommended quantities recommended by Vendors are rarely challenged in a technical manner. This screen shot from our TAMS software shows how this done The 1st item in the list is only operating 50% of the time, therefore, the calculated ADR (Annual Demand Rate) is 50% less. The Vendor may not have been provided with this information. 4. Challenge Vendors Recommended Quantities? 14 5. Spares Criticality As a default spares criticality is based on the criticality of the equipment, i.e. if the equipment is critical then the spares are critical and then reduce the criticality based on operating context e.g. similar equipment operating that have a less critical function Once the spares criticality is assigned a default % service level is selected The service level for a spare part can be further redefined by considering the spares demand rate
  • 8. 15 7. Identify Duplicate Items Example duplicates from our various data reviews. 16 8. 80-20 Rule Applied to AIV AIV is easily calculated and can be uploaded to the CMMS for immediate benefits Annual Issue Value in $ Percentage of line items A B C High level of attention Auto Generate replenishment orders Some attention
  • 9. 17 9. Demand Codes - Why Important Demand codes are based on the lead time demand rate (LTDR) The demand code is important as: Fast movers can have a lower service level, and hence reduced safety stock – we discuss further later Support the obsolete programme Slow movers need to be analysed … NEED to review if worthwhile to reorder?? 18 10. Unwanted Stock Items A poor write-off policy will result in unnecessary stock being carried Items that should be written of are: 1) Obsolete items 2) Damaged items through poor preservation 3) Items beyond their shelf life 4) Excess stocked items 5) Items stocked that are not covered by current repair and contracting strategies How effective is your unwanted stock programme?
  • 10. 19 11. Lead Time Lead time has a big effect on stock levels and costs, most CMMS populated data shows the vendor time to deliver and not the total lead time from highlighting a need to order until the items are on the shelf available to be issued Reduction in lead time will lead to: Reduction in safety stock Reduction in Reorder Point Reduction in stock-holding levels Reduction in inventory (stock-holding) costs 20 12. Optimise Inventory Parameters The diagrams below show the opportunities to identify excessive costs. Note the Calulated values for ROP and Max stock infers optimised values Act Max Cal Max Excess Holding Cost Act ROP Cal ROP Excess Holding Cost Cal ROP Act ROP Stock- Out Cost
  • 11. 21 Opportunities to Reduce Costs Buying too frequently Buying too many & excess holding stock Cal OQ Act OQ Excess Buying Cost Act OQ Cal OQ Excess Holding Cost Here are similar models for order quantities 22 Ths example from a Pharmaceutical company shows excessive stocking. The metric is the Number of Years of Stock. We calculate this value at line item value Inventory Control Parameters Audit
  • 12. 23 The following chart shows how safety stock levels increase rapidly when the Service Level is too high Excess Stocking % Service Level Safety Stock Level 24 This case study shows that the proposed changes to the replenishment parameters reduces the actual average stock level $ value by over 50% Optimisation & Stock Value Reduction Proposed £15,600 reduction in average stockholding value
  • 13. 25 The default replenishment strategy is the Reorder Point Policy (a fixed order quantity). Although many call this a Min-Max For this policy to be valid, the EOQ has to be greater than the lead time demand rate (LTDR): When this condition exists as shown below, then a more cost effective replenishment strategy is required 13. Select Right Replenishment Strategy Other options to be considered are: Min-Max (Variable order quantity) Constant Vendor Quantity 26 Challenging stocking of slow movers, is based on indirect costs 14. Identifying & Challenging Slow Movers
  • 14. 27 Evaluating Insurance Spares Decisions RAM software such as Reliasoft’s Blocksim is ideal to support decisions whether to stock high value – long lead time items 28 16. Standardisation, e.g. avoid multiple OPMs In this company, where we conducted a rationalisation study, there were spiral wound gaskets stocked from 5 different vendors. This policy typically, lead to duplicate line items: Flexitallic James Walker Lamons Garlock Cefilac
  • 15. 29 Interchangability Bolts This example shows how often we don’t know the full details of the part when we do our cataloguing. It is possible there will be duplicates usually 12-15% SAP # Short Description 1356731 BOLT,DBLE HEX HD. F/3" BALL VALVE 1356730 BOLT,DBLE HEX HD. 3" BALL VALVE M1025-3 1352851 BOLT,DBLE HEX HD. DANIEL P/N 555-44-112 1345084 BOLT,DBLE HEX HD. FISHER P/N 1U625631192 1352840 BOLT,DBLE HEX HD. DIVERTER P/N M1225-2 1352843 BOLT,DBLE HEX HD. 3/8"x3/4" DANIEL METER 1352833 BOLT,DBLE HEX HD. 2" BALL VALVE 1352836 BOLT,DBLE HEX HD. 3" DIVERTER VALVE 30 Case Study Ring Type Joints (RTJs) Case study, this is what can be achieved by scandalisation and rationalisation programme, a 70% reduction in line items Initial Findings - 163 SAP Line Items RTJ Types – R_Oval and Octagonal, BX and RX Material - Soft Iron, Carbon Steel, SS304, SS316 Reduction achieved through: Removing Duplicates Combining R Type Oval & Octagonal Combining SS304 & 316 Transferring unwanted items, i.e. Soft Iron, Cast Steel
  • 16. 31 19. Monitoring Issues & Stock Balance It is essential to monitor: a) The number of issues per year versus the estimated annual demand rate (ADR)…. We will show a number of examples where poor reliability has influenced the number of items used significantly Equally we could have situations where reliability has improved and we can then reduce the ROP a) The stock balance and if always above the safety stock level, then the desired service level can be reduced. Note: the criticality will remain the same 32 20. Root Cause Analysis RCA/RCFA is a big topic on its own There are many approaches to RCA: 5 why Cause and effect or why tree Sequence of events and Additional techniques including failure analysis to support the data collection phase We will show two case studies where actual usage was significantly more than estimated and had not been highlighted through monitoring
  • 17. 33 23. Database Solutions Database solutions support more effective analysis for: Initial spare part planning & procurement Data cleansing and cataloguing Spare part inventory parameters analysis BOM development Spend Analysis 34 Want to Learn More? Next Training Course: Venue: Robinson Brewery and Visitors Centre, Stockport, UK Date: Nov 13-15th 2017 For more information contact dave@ramsoftuk.com David Thompson Senior Consultant (maintenance, reliability & spares) Ramsoft (UK) Ltd Lancs, UK www.ramsoftuk.com www.linkedin.com/in/davidthompsonreliability External Tutor & Project Supervisor in Reliability at Robert Gordon University Over 50 years experience in Maintenance, Reliability and Spares and in diverse industries
  • 18. 35 Future Courses Asia Jan 17-19th Miri, Sarawak Jan 22nd – 24th Hanoi, Vietnam Jan 29-31st Bangkok, Thailand For more information on the above Asian courses contact: Harn@petro1.com.my For on-site courses contact: dave@ramsoftuk.com Middle East Dec 17-21st Define Management Consultancy & Training