SlideShare a Scribd company logo
1
Achieving Cost Reduction
through Optimising &
Rationalising Spares Parts
2
Too many companies do a very poor job in managing
effectively their spare parts. The issues start in the plan phase
(due to poor processes) and continue through the Do, Check
and Act phase.
Looking from another perspective the issues arise in the
project phase and are rarely corrected in the operation phase
This presentation shows where Ramsoft (UK) can support
companies to optimise and reduce stock level and hence the
costs tied up in holding spare parts
The services available are training and consultancy support
Introduction
3
Plan
DoCheck
Act
Do
Establish
cataloging &
inventory
management
in CMMS
Effective Inventory Management
Plan
Develop
strategic plans
and
procedures
Improve (Act)
Optimise &
rationalise to
achieve cost
reduction
Analyse (Check)
Audit processes,
CMMS data
quality, stock
parameter
effectiveness
4
Plan
Data
Standards
Initial Data
Requirements
Initial
Spares
Process
Strategic Plans and Procedures to
Support ISO55000
5
Do
This phase includes:
Cataloguing
Short Descriptions
Buying Descriptions
Establish Attributes
Establishing Inventory Parameters
Challenge Vendors recommendations
Assign criticality & service levels
Determining the best strategy (ROP, Min-Max, Constant Vendor
Delivery
Establish replenishment criteria
Establish various classification codes
Cataloguing & Part Set-Up
6
Check
This phase includes auditing:
Plans and Processes
Option 1 Fast Track (see screen shot from AMy
software)
Option 2 In-depth (can include all aspects of inventory
management)
Data Quality (short descriptions, manufacturers part
numbers
Effectiveness of inventory parameters
Auditing
7
Extract from AMy Self Auditing Tool
- Inventory Management
8
This case study from a CMMS Data Upload file audit showed
the bearing spares data build to be extremely poor. To correct
this poor build 8 actions were recommended
Case Study Poor Data Quality
9
The recommended quantities recommended by Vendors are
rarely challenged in a structured manner.
This screen shot from our software shows how this done
The 2nd item in the list is only operating 50% of the time,
therefore the calculated ADR (Annual Demand Rate) is 50%
less
Challenging the Quantities
Recommended By Vendors
10
Examples of stock levels too high or too low
Inventory too high or too low
11
These line items are excessively over stocked, depicted by the
very high K factor. A 95% service level would have a 1.65 K
factor. The K factor is used to set safety stock levels
Excess Stocking
12
The following chart shows how safety stock levels increase
rapidly when too high a Service Level is selected
Excess Stocking
% Service Level
13
Another example of excessive stocking using the Number of
Years of Stock
Excess Stocking
14
Challenging stocking of slow movers, is based on analysis on
costs
Identifying & Challenging Slow Movers
15
Identifying where an ROP/EOQ policy is not valid, i.e. EOQ is
less than the lead time demand rate:
Wrong Replenishment Policy
16
Here are two example of distribution charts
Distribution Charts & Missing Data
Fig 1 shows that 10% of the line
items have no lead time data
If Lead time, Service Level, Unit
Cost is missing no analysis can
be carried out
Fig 2 shows that 40% of the line
items have had no demand since
purchase.
Fig 1
Fig 2
17
Improve
This phase includes fixing the issues identified in Audit/CHECK
phase:
Improving existing Plans and Processes
Rectifying inadequate cataloguing
Remove duplicates
Assign spare classifications
Evaluate current service levels
Seek rationalisation opportunities
Evaluate the most appropriate stocking policy
Challenge stocking of slow moving items
Analyse & propose changes to stocking and replenishment
parameters
Optimisation & Stock Reduction
18
There are number of options to fix poor data quality, e.g. short
and long descriptions, e.g.
Simple data clean up conducted in a MS Access based
data clean up tool
Build attribute by copying and pasting into the templates
and then auto creating new short and long descriptions –
this is done in commercial off-the shelf software. Physical
inventory checks will be necessary to collect mandatory
missing data
As above but attributes are build automatically using data
mining techniques
Fixing Poor Cataloguing
19
Line Item Reduction
Initial Findings - 119 SWG (Spiral Wound Gaskets)
Multiple searches to identify all the SWGs
Stock existing while POs had been raised on duplicates
material in other bins
18 Gaskets supplied by Solar, Fisher Controls, Union
Pumps
Standardisation Norms Developed after discussions with
Inspection Engineers
Action & Benefit 60% Reduction in line items through:
Removing Duplicates
Combining SS304 & 316
Standardising in supplier
20
This case study shows that the proposed changes to the
replenishment parameters reduces the actual average stock
level value by over 50%
Optimisation & Stock Value Reduction
Note:
the Calculated
values are the
Optimal values
21
Evaluating Insurance Spares Decisions
RAM software such as Reliasoft’s
Blocksim is ideal to support
decisions whether to stock high
value – long lead time items
22
Insurance Spares Summary Costs
Stock 0 Stock 1 Stock 2
Availability 98.58 99.86 99.86
No of Failures 1.152 1.167 1.167
Downtime 14.7 1.48 1.48
Item Cost 68,889 60,684 60,684
Holding Cost 0 111,823 267,823
Penalty Cost 49,437,350 4,974,039 4,974,039
20 year Total 49,506,270 5,146,547 5,302,547
Annualised Cost 2,475,313 257,327 265,127
Analysis summary for options stock 0,1 or 2
23
Training
24
As a result of attending this Spares Optimisation & Cost Reduction workshop delegates
will understand:
ISO5500 and what it means for inventory management
How to achieve consistent cataloguing
The different costs associated with spares management
Learn techniques to improve reliability resulting in less spares usage
How to select the right inventory policy for fast and slow moving parts
Good practices related to SPIR forms or RSPL forms
How to evaluate safety stocks scientifically
How to determine how many to buy
Learn many strategies to minimise stock (Follow the 20point action plan)
How to justify the financial case for high value spares
How to measure inventory performance using KPIs at line item level
Understand the benefits of a MS Access Analysis Solution
Have an appreciation of how reliability analysis tools support the evaluation of high
value spares
NEW to UK & Europe 4 Day Course
25
Section A Introduction and Initial Spares Processes
Topic 1: Introduction to Spares Management
Topic 2: Improving Vendor’s Spares Data (recommended spare parts
data)
Topic 3: Challenge Vendors Recommended Quantities
Topic 4: Building an Effective Spares Cataloguing
Topic 5: Completing the CMMS Spares Build
Section B Inventory Control
Topic 6: Spare Part Costs
Topic 7: Reliability Concepts and Spares
Topic 8: Setting Re-Order Points, Safety Stock
Topic 9: How Many to Order? Determining the EOQ
Topic 10: Establish ROP, Safety Stock and Order Quantities for Initial
Spares
Typical 4 Day Course Contents 1
26
Section C Stock Optimisation
Topic 11: Inventory 20 Point Cost Reduction Programme
Topic 12: Audit Current Inventory Effectiveness
Topic 13: Database Solution for Inventory Effectiveness
Topic 14: Alternate Inventory Strategies
Topic 15: Evaluate Policies for Insurance Spares
Section D Management Processes
Topic 16. Auditing Inventory Management Plans & Processes
Topic 17: In-depth Auditing of a Business Processes
Topic 18: KPI Reporting
Typical 4 Day Course Contents 2
27
For more information, including a sample data audit
contact
David Thompson
Senior Consultant (maintenance, reliability &
spares)
Ramsoft (UK) Ltd
Lancs, UK
Dave@Ramsoftuk.com
www.linkedin.com/in/davidthompsonreliability
Reliability ODL External Tutor & Project Supervisor at
Robert Gordon University
Established in 2004
28
David has spent the whole of his career (over 50 years) in
maintenance and asset management
Has worked for many blue chip companies either direct of through
a consultancy role
Experienced in many industrial sectors, oil & gas, petrochemical,
mining, beverage, pharmaceutical, utilities and power
Worked in Europe, South & North America, Africa, Asia, Middle
east
Worked both in offshore and onshore facilities
12 Courses conducted in Asia & 2 in Africa
David Thompson

More Related Content

What's hot

The Visual Workplace
The Visual WorkplaceThe Visual Workplace
The Visual Workplace
Creative Safety Supply
 
Kaizen PDCA Cycle Process PowerPoint Presentation Slides
Kaizen PDCA Cycle Process PowerPoint Presentation Slides Kaizen PDCA Cycle Process PowerPoint Presentation Slides
Kaizen PDCA Cycle Process PowerPoint Presentation Slides
SlideTeam
 
Iso Process Audit Training
Iso Process Audit TrainingIso Process Audit Training
Iso Process Audit Training
srmortensen
 
Lean Manufacturing PowerPoint Presentation Sample
Lean Manufacturing PowerPoint Presentation SampleLean Manufacturing PowerPoint Presentation Sample
Lean Manufacturing PowerPoint Presentation Sample
Andrew Schwartz
 
Lean Inventory
Lean Inventory Lean Inventory
Lean Inventory
Tom Craig
 
Six Sigma and Its Implementation
Six Sigma and Its ImplementationSix Sigma and Its Implementation
Six Sigma and Its Implementation
Ansar Lawi
 
Autonomous Maintenance (AM)
Autonomous Maintenance (AM)Autonomous Maintenance (AM)
Autonomous Maintenance (AM)
Pramod A
 
Continuous Improvement Powerpoint Presentation Slides
Continuous Improvement Powerpoint Presentation SlidesContinuous Improvement Powerpoint Presentation Slides
Continuous Improvement Powerpoint Presentation Slides
SlideTeam
 
KAIZEN COSTING
KAIZEN COSTINGKAIZEN COSTING
KAIZEN COSTING
ANMOL GULATI
 
Lean Value Stream Mapping (VSM) Training Module
Lean Value Stream Mapping (VSM) Training ModuleLean Value Stream Mapping (VSM) Training Module
Lean Value Stream Mapping (VSM) Training Module
Frank-G. Adler
 
03.chapter3.4.spares.criticality
03.chapter3.4.spares.criticality03.chapter3.4.spares.criticality
03.chapter3.4.spares.criticality
Amirul Faiz Amil Azman
 
Lean Materials Management - Parts presentation at the line - November 2016
Lean Materials Management - Parts presentation at the line - November 2016Lean Materials Management - Parts presentation at the line - November 2016
Lean Materials Management - Parts presentation at the line - November 2016
W3 Group Canada Inc.
 
Lean manufacturing
Lean manufacturing Lean manufacturing
Lean manufacturing
Andrew Schwartz
 
Kaizen Innovation in Manufacturing
Kaizen Innovation in ManufacturingKaizen Innovation in Manufacturing
Kaizen Innovation in Manufacturing
Timothy Wooi
 
Spare parts management
Spare parts management Spare parts management
Spare parts management
Smita Sinha
 
Control systems for spare parts.
Control systems for spare parts.Control systems for spare parts.
Control systems for spare parts.
Medha Yadav
 
Process Capability - Cp, Cpk. Pp, Ppk
Process Capability - Cp, Cpk. Pp, Ppk Process Capability - Cp, Cpk. Pp, Ppk
Process Capability - Cp, Cpk. Pp, Ppk
J. García - Verdugo
 
How to implement Single minute exchange of die
How to implement Single minute exchange of die How to implement Single minute exchange of die
How to implement Single minute exchange of die
Nikunj Rana
 
Kaizen
KaizenKaizen
Kaizen
Amit Upadhye
 

What's hot (20)

The Visual Workplace
The Visual WorkplaceThe Visual Workplace
The Visual Workplace
 
Kaizen PDCA Cycle Process PowerPoint Presentation Slides
Kaizen PDCA Cycle Process PowerPoint Presentation Slides Kaizen PDCA Cycle Process PowerPoint Presentation Slides
Kaizen PDCA Cycle Process PowerPoint Presentation Slides
 
Iso Process Audit Training
Iso Process Audit TrainingIso Process Audit Training
Iso Process Audit Training
 
Lean Manufacturing PowerPoint Presentation Sample
Lean Manufacturing PowerPoint Presentation SampleLean Manufacturing PowerPoint Presentation Sample
Lean Manufacturing PowerPoint Presentation Sample
 
Lean Inventory
Lean Inventory Lean Inventory
Lean Inventory
 
Six Sigma and Its Implementation
Six Sigma and Its ImplementationSix Sigma and Its Implementation
Six Sigma and Its Implementation
 
Autonomous Maintenance (AM)
Autonomous Maintenance (AM)Autonomous Maintenance (AM)
Autonomous Maintenance (AM)
 
Continuous Improvement Powerpoint Presentation Slides
Continuous Improvement Powerpoint Presentation SlidesContinuous Improvement Powerpoint Presentation Slides
Continuous Improvement Powerpoint Presentation Slides
 
KAIZEN COSTING
KAIZEN COSTINGKAIZEN COSTING
KAIZEN COSTING
 
Lean Value Stream Mapping (VSM) Training Module
Lean Value Stream Mapping (VSM) Training ModuleLean Value Stream Mapping (VSM) Training Module
Lean Value Stream Mapping (VSM) Training Module
 
03.chapter3.4.spares.criticality
03.chapter3.4.spares.criticality03.chapter3.4.spares.criticality
03.chapter3.4.spares.criticality
 
Lean Materials Management - Parts presentation at the line - November 2016
Lean Materials Management - Parts presentation at the line - November 2016Lean Materials Management - Parts presentation at the line - November 2016
Lean Materials Management - Parts presentation at the line - November 2016
 
Kaizen
KaizenKaizen
Kaizen
 
Lean manufacturing
Lean manufacturing Lean manufacturing
Lean manufacturing
 
Kaizen Innovation in Manufacturing
Kaizen Innovation in ManufacturingKaizen Innovation in Manufacturing
Kaizen Innovation in Manufacturing
 
Spare parts management
Spare parts management Spare parts management
Spare parts management
 
Control systems for spare parts.
Control systems for spare parts.Control systems for spare parts.
Control systems for spare parts.
 
Process Capability - Cp, Cpk. Pp, Ppk
Process Capability - Cp, Cpk. Pp, Ppk Process Capability - Cp, Cpk. Pp, Ppk
Process Capability - Cp, Cpk. Pp, Ppk
 
How to implement Single minute exchange of die
How to implement Single minute exchange of die How to implement Single minute exchange of die
How to implement Single minute exchange of die
 
Kaizen
KaizenKaizen
Kaizen
 

Similar to Reducing Costs of Spares and Inventory Levels

3 Day Spares Optimisation Course (Multiple Venues)
3 Day Spares Optimisation Course (Multiple Venues)3 Day Spares Optimisation Course (Multiple Venues)
3 Day Spares Optimisation Course (Multiple Venues)
David Thompson
 
Mro spare parts optimisation and inventory reduction uk 2017 11
Mro spare parts optimisation and inventory reduction uk 2017 11Mro spare parts optimisation and inventory reduction uk 2017 11
Mro spare parts optimisation and inventory reduction uk 2017 11
David Thompson
 
C3 3 day spares optimisation rationalisation 2017 01
C3 3 day spares optimisation rationalisation 2017 01C3 3 day spares optimisation rationalisation 2017 01
C3 3 day spares optimisation rationalisation 2017 01
Martyn Thompson
 
C3 3 day spares optimisation rationalisation 2017 01
C3 3 day spares optimisation  rationalisation 2017 01C3 3 day spares optimisation  rationalisation 2017 01
C3 3 day spares optimisation rationalisation 2017 01
David Thompson
 
Spc assignment
Spc assignmentSpc assignment
Spc assignment
Dibyajyoti Laha
 
A company has actual unit demand for three consecutive years
A company has actual unit demand for three consecutive yearsA company has actual unit demand for three consecutive years
A company has actual unit demand for three consecutive years
johann11369
 
New for 2018 MRO master data auditing and cleansing
New for 2018 MRO  master data auditing and cleansingNew for 2018 MRO  master data auditing and cleansing
New for 2018 MRO master data auditing and cleansing
David Thompson
 
An assumption of learning curve theory is which of the following
An assumption of learning curve theory is which of the followingAn assumption of learning curve theory is which of the following
An assumption of learning curve theory is which of the following
johann11370
 
Supply Chain Management Review PowerPoint Presentation Slides
Supply Chain Management Review PowerPoint Presentation Slides Supply Chain Management Review PowerPoint Presentation Slides
Supply Chain Management Review PowerPoint Presentation Slides
SlideTeam
 
What is transaction processing
What is transaction processingWhat is transaction processing
What is transaction processing
johann11372
 
In designing a lean production facility layout
In designing a lean production facility layoutIn designing a lean production facility layout
In designing a lean production facility layout
johann11371
 
UOPOPS571 You can do it--uopops571.com
UOPOPS571 You can do it--uopops571.comUOPOPS571 You can do it--uopops571.com
UOPOPS571 You can do it--uopops571.com
agathachristie218
 
You have been called in as a consultant to set up a kanban control system
You have been called in as a consultant to set up a kanban control systemYou have been called in as a consultant to set up a kanban control system
You have been called in as a consultant to set up a kanban control system
johann11374
 
Lean Portfolio - A.Mckew (FINAL)
Lean Portfolio - A.Mckew (FINAL)Lean Portfolio - A.Mckew (FINAL)
Lean Portfolio - A.Mckew (FINAL)Andrew Mckew
 
For an infinite queuing situation
For an infinite queuing situationFor an infinite queuing situation
For an infinite queuing situation
johann11370
 
If the actual output of a piece of equipment
If the actual output of a piece of equipmentIf the actual output of a piece of equipment
If the actual output of a piece of equipment
johann11371
 
Reduce mro inventory costs ppt
Reduce mro inventory costs pptReduce mro inventory costs ppt
Reduce mro inventory costs ppt
David Thompson
 
Supply Chain Management Review Powerpoint Presentation Slides
Supply Chain Management Review Powerpoint Presentation SlidesSupply Chain Management Review Powerpoint Presentation Slides
Supply Chain Management Review Powerpoint Presentation Slides
SlideTeam
 
From an operational perspective, yield management is most effective under whi...
From an operational perspective, yield management is most effective under whi...From an operational perspective, yield management is most effective under whi...
From an operational perspective, yield management is most effective under whi...
johann11371
 
Uop ops-571-final-exam-guide- april-2018--new
Uop ops-571-final-exam-guide- april-2018--newUop ops-571-final-exam-guide- april-2018--new
Uop ops-571-final-exam-guide- april-2018--new
indi7257
 

Similar to Reducing Costs of Spares and Inventory Levels (20)

3 Day Spares Optimisation Course (Multiple Venues)
3 Day Spares Optimisation Course (Multiple Venues)3 Day Spares Optimisation Course (Multiple Venues)
3 Day Spares Optimisation Course (Multiple Venues)
 
Mro spare parts optimisation and inventory reduction uk 2017 11
Mro spare parts optimisation and inventory reduction uk 2017 11Mro spare parts optimisation and inventory reduction uk 2017 11
Mro spare parts optimisation and inventory reduction uk 2017 11
 
C3 3 day spares optimisation rationalisation 2017 01
C3 3 day spares optimisation rationalisation 2017 01C3 3 day spares optimisation rationalisation 2017 01
C3 3 day spares optimisation rationalisation 2017 01
 
C3 3 day spares optimisation rationalisation 2017 01
C3 3 day spares optimisation  rationalisation 2017 01C3 3 day spares optimisation  rationalisation 2017 01
C3 3 day spares optimisation rationalisation 2017 01
 
Spc assignment
Spc assignmentSpc assignment
Spc assignment
 
A company has actual unit demand for three consecutive years
A company has actual unit demand for three consecutive yearsA company has actual unit demand for three consecutive years
A company has actual unit demand for three consecutive years
 
New for 2018 MRO master data auditing and cleansing
New for 2018 MRO  master data auditing and cleansingNew for 2018 MRO  master data auditing and cleansing
New for 2018 MRO master data auditing and cleansing
 
An assumption of learning curve theory is which of the following
An assumption of learning curve theory is which of the followingAn assumption of learning curve theory is which of the following
An assumption of learning curve theory is which of the following
 
Supply Chain Management Review PowerPoint Presentation Slides
Supply Chain Management Review PowerPoint Presentation Slides Supply Chain Management Review PowerPoint Presentation Slides
Supply Chain Management Review PowerPoint Presentation Slides
 
What is transaction processing
What is transaction processingWhat is transaction processing
What is transaction processing
 
In designing a lean production facility layout
In designing a lean production facility layoutIn designing a lean production facility layout
In designing a lean production facility layout
 
UOPOPS571 You can do it--uopops571.com
UOPOPS571 You can do it--uopops571.comUOPOPS571 You can do it--uopops571.com
UOPOPS571 You can do it--uopops571.com
 
You have been called in as a consultant to set up a kanban control system
You have been called in as a consultant to set up a kanban control systemYou have been called in as a consultant to set up a kanban control system
You have been called in as a consultant to set up a kanban control system
 
Lean Portfolio - A.Mckew (FINAL)
Lean Portfolio - A.Mckew (FINAL)Lean Portfolio - A.Mckew (FINAL)
Lean Portfolio - A.Mckew (FINAL)
 
For an infinite queuing situation
For an infinite queuing situationFor an infinite queuing situation
For an infinite queuing situation
 
If the actual output of a piece of equipment
If the actual output of a piece of equipmentIf the actual output of a piece of equipment
If the actual output of a piece of equipment
 
Reduce mro inventory costs ppt
Reduce mro inventory costs pptReduce mro inventory costs ppt
Reduce mro inventory costs ppt
 
Supply Chain Management Review Powerpoint Presentation Slides
Supply Chain Management Review Powerpoint Presentation SlidesSupply Chain Management Review Powerpoint Presentation Slides
Supply Chain Management Review Powerpoint Presentation Slides
 
From an operational perspective, yield management is most effective under whi...
From an operational perspective, yield management is most effective under whi...From an operational perspective, yield management is most effective under whi...
From an operational perspective, yield management is most effective under whi...
 
Uop ops-571-final-exam-guide- april-2018--new
Uop ops-571-final-exam-guide- april-2018--newUop ops-571-final-exam-guide- april-2018--new
Uop ops-571-final-exam-guide- april-2018--new
 

More from David Thompson

Using UNSPSC codes in the MRO Inventory System
Using UNSPSC codes in the MRO Inventory SystemUsing UNSPSC codes in the MRO Inventory System
Using UNSPSC codes in the MRO Inventory System
David Thompson
 
Using UNSPSC codes in the MRO Inventory System
Using UNSPSC codes in the MRO Inventory SystemUsing UNSPSC codes in the MRO Inventory System
Using UNSPSC codes in the MRO Inventory System
David Thompson
 
Using UNSPSC codes in the MRO Inventory System
Using UNSPSC codes in the MRO Inventory SystemUsing UNSPSC codes in the MRO Inventory System
Using UNSPSC codes in the MRO Inventory System
David Thompson
 
Using UNSPSC codes in the MRO Inventory System
Using UNSPSC codes in the MRO Inventory SystemUsing UNSPSC codes in the MRO Inventory System
Using UNSPSC codes in the MRO Inventory System
David Thompson
 
Using UNSPSC codes in the MRO Inventory System
Using UNSPSC codes in the MRO Inventory SystemUsing UNSPSC codes in the MRO Inventory System
Using UNSPSC codes in the MRO Inventory System
David Thompson
 
MRO Spare Parts Improvement Programme Conforms to ISO55000
MRO Spare Parts Improvement Programme Conforms to ISO55000MRO Spare Parts Improvement Programme Conforms to ISO55000
MRO Spare Parts Improvement Programme Conforms to ISO55000
David Thompson
 
Is your mro spare parts reduction program compliant with iso55000 rev 3
Is your mro spare parts reduction program compliant with iso55000 rev 3Is your mro spare parts reduction program compliant with iso55000 rev 3
Is your mro spare parts reduction program compliant with iso55000 rev 3
David Thompson
 
MRO spare part case studies master data
MRO spare part case studies   master dataMRO spare part case studies   master data
MRO spare part case studies master data
David Thompson
 
Sap mrp hb and fx 2017 09
Sap mrp hb and fx 2017 09Sap mrp hb and fx 2017 09
Sap mrp hb and fx 2017 09
David Thompson
 
Sap mrp hb ex 2017 09 rev 4
Sap mrp hb ex 2017 09  rev 4Sap mrp hb ex 2017 09  rev 4
Sap mrp hb ex 2017 09 rev 4
David Thompson
 
All books
All booksAll books
All books
David Thompson
 
Reliability books
Reliability booksReliability books
Reliability books
David Thompson
 
Other books
Other booksOther books
Other books
David Thompson
 
Am books
Am booksAm books
Am books
David Thompson
 
Equip mgmt books
Equip mgmt booksEquip mgmt books
Equip mgmt books
David Thompson
 
Ramsoft - Case 4 Spiral Wound Gaskets
Ramsoft - Case 4 Spiral Wound GasketsRamsoft - Case 4 Spiral Wound Gaskets
Ramsoft - Case 4 Spiral Wound Gaskets
David Thompson
 
Food and Drink MRO Spares Data Audit
Food and Drink MRO Spares Data AuditFood and Drink MRO Spares Data Audit
Food and Drink MRO Spares Data Audit
David Thompson
 

More from David Thompson (17)

Using UNSPSC codes in the MRO Inventory System
Using UNSPSC codes in the MRO Inventory SystemUsing UNSPSC codes in the MRO Inventory System
Using UNSPSC codes in the MRO Inventory System
 
Using UNSPSC codes in the MRO Inventory System
Using UNSPSC codes in the MRO Inventory SystemUsing UNSPSC codes in the MRO Inventory System
Using UNSPSC codes in the MRO Inventory System
 
Using UNSPSC codes in the MRO Inventory System
Using UNSPSC codes in the MRO Inventory SystemUsing UNSPSC codes in the MRO Inventory System
Using UNSPSC codes in the MRO Inventory System
 
Using UNSPSC codes in the MRO Inventory System
Using UNSPSC codes in the MRO Inventory SystemUsing UNSPSC codes in the MRO Inventory System
Using UNSPSC codes in the MRO Inventory System
 
Using UNSPSC codes in the MRO Inventory System
Using UNSPSC codes in the MRO Inventory SystemUsing UNSPSC codes in the MRO Inventory System
Using UNSPSC codes in the MRO Inventory System
 
MRO Spare Parts Improvement Programme Conforms to ISO55000
MRO Spare Parts Improvement Programme Conforms to ISO55000MRO Spare Parts Improvement Programme Conforms to ISO55000
MRO Spare Parts Improvement Programme Conforms to ISO55000
 
Is your mro spare parts reduction program compliant with iso55000 rev 3
Is your mro spare parts reduction program compliant with iso55000 rev 3Is your mro spare parts reduction program compliant with iso55000 rev 3
Is your mro spare parts reduction program compliant with iso55000 rev 3
 
MRO spare part case studies master data
MRO spare part case studies   master dataMRO spare part case studies   master data
MRO spare part case studies master data
 
Sap mrp hb and fx 2017 09
Sap mrp hb and fx 2017 09Sap mrp hb and fx 2017 09
Sap mrp hb and fx 2017 09
 
Sap mrp hb ex 2017 09 rev 4
Sap mrp hb ex 2017 09  rev 4Sap mrp hb ex 2017 09  rev 4
Sap mrp hb ex 2017 09 rev 4
 
All books
All booksAll books
All books
 
Reliability books
Reliability booksReliability books
Reliability books
 
Other books
Other booksOther books
Other books
 
Am books
Am booksAm books
Am books
 
Equip mgmt books
Equip mgmt booksEquip mgmt books
Equip mgmt books
 
Ramsoft - Case 4 Spiral Wound Gaskets
Ramsoft - Case 4 Spiral Wound GasketsRamsoft - Case 4 Spiral Wound Gaskets
Ramsoft - Case 4 Spiral Wound Gaskets
 
Food and Drink MRO Spares Data Audit
Food and Drink MRO Spares Data AuditFood and Drink MRO Spares Data Audit
Food and Drink MRO Spares Data Audit
 

Recently uploaded

Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
aqil azizi
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
ChristineTorrepenida1
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSCW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
veerababupersonal22
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
ssuser7dcef0
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 

Recently uploaded (20)

Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSCW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 

Reducing Costs of Spares and Inventory Levels

  • 1. 1 Achieving Cost Reduction through Optimising & Rationalising Spares Parts 2 Too many companies do a very poor job in managing effectively their spare parts. The issues start in the plan phase (due to poor processes) and continue through the Do, Check and Act phase. Looking from another perspective the issues arise in the project phase and are rarely corrected in the operation phase This presentation shows where Ramsoft (UK) can support companies to optimise and reduce stock level and hence the costs tied up in holding spare parts The services available are training and consultancy support Introduction
  • 2. 3 Plan DoCheck Act Do Establish cataloging & inventory management in CMMS Effective Inventory Management Plan Develop strategic plans and procedures Improve (Act) Optimise & rationalise to achieve cost reduction Analyse (Check) Audit processes, CMMS data quality, stock parameter effectiveness 4 Plan Data Standards Initial Data Requirements Initial Spares Process Strategic Plans and Procedures to Support ISO55000
  • 3. 5 Do This phase includes: Cataloguing Short Descriptions Buying Descriptions Establish Attributes Establishing Inventory Parameters Challenge Vendors recommendations Assign criticality & service levels Determining the best strategy (ROP, Min-Max, Constant Vendor Delivery Establish replenishment criteria Establish various classification codes Cataloguing & Part Set-Up 6 Check This phase includes auditing: Plans and Processes Option 1 Fast Track (see screen shot from AMy software) Option 2 In-depth (can include all aspects of inventory management) Data Quality (short descriptions, manufacturers part numbers Effectiveness of inventory parameters Auditing
  • 4. 7 Extract from AMy Self Auditing Tool - Inventory Management 8 This case study from a CMMS Data Upload file audit showed the bearing spares data build to be extremely poor. To correct this poor build 8 actions were recommended Case Study Poor Data Quality
  • 5. 9 The recommended quantities recommended by Vendors are rarely challenged in a structured manner. This screen shot from our software shows how this done The 2nd item in the list is only operating 50% of the time, therefore the calculated ADR (Annual Demand Rate) is 50% less Challenging the Quantities Recommended By Vendors 10 Examples of stock levels too high or too low Inventory too high or too low
  • 6. 11 These line items are excessively over stocked, depicted by the very high K factor. A 95% service level would have a 1.65 K factor. The K factor is used to set safety stock levels Excess Stocking 12 The following chart shows how safety stock levels increase rapidly when too high a Service Level is selected Excess Stocking % Service Level
  • 7. 13 Another example of excessive stocking using the Number of Years of Stock Excess Stocking 14 Challenging stocking of slow movers, is based on analysis on costs Identifying & Challenging Slow Movers
  • 8. 15 Identifying where an ROP/EOQ policy is not valid, i.e. EOQ is less than the lead time demand rate: Wrong Replenishment Policy 16 Here are two example of distribution charts Distribution Charts & Missing Data Fig 1 shows that 10% of the line items have no lead time data If Lead time, Service Level, Unit Cost is missing no analysis can be carried out Fig 2 shows that 40% of the line items have had no demand since purchase. Fig 1 Fig 2
  • 9. 17 Improve This phase includes fixing the issues identified in Audit/CHECK phase: Improving existing Plans and Processes Rectifying inadequate cataloguing Remove duplicates Assign spare classifications Evaluate current service levels Seek rationalisation opportunities Evaluate the most appropriate stocking policy Challenge stocking of slow moving items Analyse & propose changes to stocking and replenishment parameters Optimisation & Stock Reduction 18 There are number of options to fix poor data quality, e.g. short and long descriptions, e.g. Simple data clean up conducted in a MS Access based data clean up tool Build attribute by copying and pasting into the templates and then auto creating new short and long descriptions – this is done in commercial off-the shelf software. Physical inventory checks will be necessary to collect mandatory missing data As above but attributes are build automatically using data mining techniques Fixing Poor Cataloguing
  • 10. 19 Line Item Reduction Initial Findings - 119 SWG (Spiral Wound Gaskets) Multiple searches to identify all the SWGs Stock existing while POs had been raised on duplicates material in other bins 18 Gaskets supplied by Solar, Fisher Controls, Union Pumps Standardisation Norms Developed after discussions with Inspection Engineers Action & Benefit 60% Reduction in line items through: Removing Duplicates Combining SS304 & 316 Standardising in supplier 20 This case study shows that the proposed changes to the replenishment parameters reduces the actual average stock level value by over 50% Optimisation & Stock Value Reduction Note: the Calculated values are the Optimal values
  • 11. 21 Evaluating Insurance Spares Decisions RAM software such as Reliasoft’s Blocksim is ideal to support decisions whether to stock high value – long lead time items 22 Insurance Spares Summary Costs Stock 0 Stock 1 Stock 2 Availability 98.58 99.86 99.86 No of Failures 1.152 1.167 1.167 Downtime 14.7 1.48 1.48 Item Cost 68,889 60,684 60,684 Holding Cost 0 111,823 267,823 Penalty Cost 49,437,350 4,974,039 4,974,039 20 year Total 49,506,270 5,146,547 5,302,547 Annualised Cost 2,475,313 257,327 265,127 Analysis summary for options stock 0,1 or 2
  • 12. 23 Training 24 As a result of attending this Spares Optimisation & Cost Reduction workshop delegates will understand: ISO5500 and what it means for inventory management How to achieve consistent cataloguing The different costs associated with spares management Learn techniques to improve reliability resulting in less spares usage How to select the right inventory policy for fast and slow moving parts Good practices related to SPIR forms or RSPL forms How to evaluate safety stocks scientifically How to determine how many to buy Learn many strategies to minimise stock (Follow the 20point action plan) How to justify the financial case for high value spares How to measure inventory performance using KPIs at line item level Understand the benefits of a MS Access Analysis Solution Have an appreciation of how reliability analysis tools support the evaluation of high value spares NEW to UK & Europe 4 Day Course
  • 13. 25 Section A Introduction and Initial Spares Processes Topic 1: Introduction to Spares Management Topic 2: Improving Vendor’s Spares Data (recommended spare parts data) Topic 3: Challenge Vendors Recommended Quantities Topic 4: Building an Effective Spares Cataloguing Topic 5: Completing the CMMS Spares Build Section B Inventory Control Topic 6: Spare Part Costs Topic 7: Reliability Concepts and Spares Topic 8: Setting Re-Order Points, Safety Stock Topic 9: How Many to Order? Determining the EOQ Topic 10: Establish ROP, Safety Stock and Order Quantities for Initial Spares Typical 4 Day Course Contents 1 26 Section C Stock Optimisation Topic 11: Inventory 20 Point Cost Reduction Programme Topic 12: Audit Current Inventory Effectiveness Topic 13: Database Solution for Inventory Effectiveness Topic 14: Alternate Inventory Strategies Topic 15: Evaluate Policies for Insurance Spares Section D Management Processes Topic 16. Auditing Inventory Management Plans & Processes Topic 17: In-depth Auditing of a Business Processes Topic 18: KPI Reporting Typical 4 Day Course Contents 2
  • 14. 27 For more information, including a sample data audit contact David Thompson Senior Consultant (maintenance, reliability & spares) Ramsoft (UK) Ltd Lancs, UK Dave@Ramsoftuk.com www.linkedin.com/in/davidthompsonreliability Reliability ODL External Tutor & Project Supervisor at Robert Gordon University Established in 2004 28 David has spent the whole of his career (over 50 years) in maintenance and asset management Has worked for many blue chip companies either direct of through a consultancy role Experienced in many industrial sectors, oil & gas, petrochemical, mining, beverage, pharmaceutical, utilities and power Worked in Europe, South & North America, Africa, Asia, Middle east Worked both in offshore and onshore facilities 12 Courses conducted in Asia & 2 in Africa David Thompson