Measures and Equipment
for Optimal Efficiency
at Thermal Power Stations
January 30, 2015
Japan Coal Energy Center (JCOAL)
International Seminar on
"Implementation of PAT Scheme in Thermal Power Stations
- Issues and Challenges“
India Habitat Centre
1
1. Profile and Activities of Japan Coal Energy Center
(JCOAL)
2. O&M Practices and Effective Solutions for BOP
Systems, Kyushu Electric Power Co., Inc.
3. Coal Quality Evaluation System(CQES),
Idemitsu Kosan Co., Ltd.
4. Numerical Simulation of Pulverized Coal
Combustion, Idemitsu Kosan Co., Ltd.
5. Summary
Overview
2
1. Profile and Activities of Japan Coal Energy
Center (JCOAL)
3
Japan Coal Energy Center (JCOAL)
• Established as a foundation in 1990, with
its origin back to 1948
• Covers all coal related issues from
upstream to downstream of the coal chain
• Members: 119 incl. major public-listed
companies and main players in energy and
relevant sectors
• Supervision by METI (Ministry of
Economy, Trade and Industry of Japan)
4
Exploration
Facilitation and promotion of cleaner
utilization of coal
Mining & Preparation
Coal utilization technology development
Upstream Activities
CCT Transfer Program on coal preparation Technologies
5
CCT transfer project on coal preparation technology
 Coal preparation technology was set as the main topic of technology
exchange in India considering the importance of high ash coal processing.
 1,305 trainees were invited to Japan including 150 Indian experts by the
end of JFY2011
 Technology exchange programs dispatching Japanese experts to target
countries were also commenced
Vari-Wave Jig (KCM) Control panel (KCM) Port facilities (Kushiro) Dry separation facility
(Nagata Eng.)
High efficiency coal preparation plant in Odisha
 High efficiency coal preparation plant has been commissioned on July 25th, 2014 in
Angul, Odisha using latest vari-wave jig technology with a capacity of 350t/h.
Source: NEDO website
The Project on Efficiency and Environmental
Improvement of Coal fired Power Stations
A MOU of Pre-primary Study of Efficiency and Environmental
Improvement of Coal-fired Power Stations was signed on April 30,
2010, in the presence of Deputy Chairman, Planning Commission
of India, and Minister of Economy, Trade and Industry of Japan.
Diagnostic activities for two (2) state owned, one (1) NTPC owned
TPS
Durgapur
Unchahar
Badarpur
2010, 2011
Wanakbori
2010
Ramagundam
2011
Kahalgaon
2010, 2011, 2012
Dr. Narla Tata Rao
(Vijayawada)
A MOU for the Project on Efficiency and
Environmental Improvement
of Coal fired Power Station
was signed on June 11, 2012.
Diagnostic activities for Durgapur of DVC,
Unchahar & Badarpur of NTPC; all of which
were referred to in the Joint Statement on the
occasion of the 6th Japan-India Energy Dialogue
between the Ministry of Economy, Trade and
Industry of Japan and the Planning
Commission of India on October 10, 2012. CCT
workshop in Delhi
2011
2012
Diagnostic activities for two (2) state owned,
one (1) NTPC owned TPS
R&M Workshop in Delhi
2010
2013
Follow up activities for all TPS are ongoing
for all diagnosed TPS.
CCT Transfer program for the delegates from
India power sector was carried out.
CCT workshop in Delhi 6
Typical Example of R & M Proposal
COAL
P Air S Air
Feed Water Heater
SH Steam
RH
Steam
Steam Turbine
Generator
Cooling Tower
Stack
Condenser
ESP
IDF
PA
F
FD
F
Mill
Boile
r
Feed
Pump
Air Pre-
Heater
Fly Ash
Bottom Ash
Coal
Bunke
r
Coal Yard
Ash Pond※
※
Transformer
Circuit Breaker
Plan-A:LE Replacement of worn parts only
Plan-B:R&M
Replacement of worn
parts + Reuse of
casing, replacement of
HP,IP,LP turbine, D-
EHC improvement
and ESP
rehabilitation
Plan-C:R&M
Plan-B+ generator
improvement
Plan-D:R&M
Plan-C+ condenser
and feedwater heater
improvement
7
8
Mitsubishi Hitachi
Power Systems,
Nagasaki Works
( 31st Oct. ) J-POWER, Isogo TPS
( 30th Oct., 3rd Dec.)
J-POWER
Tachibanawan
TPS ( 04th Nov. )
CCT program - Site Visit -
Open-Ended Meeting
Embassy of India
Mitsubishi Hitachi Power Systems,
Hitachi Works (4th Dec.)
Joban Joint Power Company
Nakoso IGCC (5th Dec.)
Chubu Electric
Power, Hekinan
TPS ( 8th Dec.)
Idemitsu Coal & Environment
Research Laboratory, Idemitsu
Bulk Terminal ( 26th Sept.)
Toshiba Keihin Work ( 25th Sept. )
J-POWER Takasago
TPS ( 29 Sept. )
8
99
Discussion -Topics-
Issues around
materialization of
R&M
Efficiency
Improvement through
enhancement of O&M
Coal blending as one of
the key measures for
domestic coal
shortages
Group1 R&M Group2 USC1 Group3 USC2
Possible barriers for Japanese players to work for India power sector
Issues around materialization of Proposed New
Project
Technical Target and/or Guideline for
introduction of USC
Road map for high
efficiency advanced
technology
2. O&M Practices and Effective Solutions for
BOP Systems,
Kyushu Electric Power Co., Inc.
10
11
Supply
Facilities
Hydro142places3,582MWPumpedStorage3places2,300MW
※
Coal3places2,460MW
Thermal9places10,680MW
LNG2places4,090MW
※
Geothermal6places212MWOil5places4,130MW
Nuclear2places5,258MW
※
Thetotalofplacesdoesnotmatch,
becausetheunit1ofKaritapower
Internalcombustion34places399MWstationiscountedascoalandthe
unit2iscountedasoil.
Wind2places3MW
Solar1places3MW
(asofMarch31,2013)
Total196places20,137MW
Establishment May1,1951
Paid-inCapital 237.3billionyen
#ofShareholders 174,293
#ofSharesIssued
andOutstanding
474,183,951
#ofContracts
Lighting:7.69million
Power:0.93million
#ofEmployees 13,102
IT/telecom
Electricity Sales
VolumeSpecific-
83.8 billion kWh
Kyushu Electric Power Co., Inc.
Breakdown of Electricity Sales Volume
(FY2012)
Domestic Share of Electricity Sales Volume
(FY2012)
(Lighting
35.2%)
Other than
Specific-scale
demand
41.4%
(Power
scale
demand
58.6%
Customers under Liberalization 6.2%)
Over 6,000V , 50kW
Tokyo
31.6%
Tohoku
9.1%
Kyushu
9.8%
Other
17.9%
Domestic Share
of Electricity Sales
Volume
(10EPCOs)
851.6billion kWh
Kansai
Chubu 16.6%
14.9%
Consolidated Sales (FY2012)
Other
5.6% 1.6%
Energy-
related
9.5%
Consolidated
Revenue
1,545.9billion
Electricity
83.3%
KYUSHU‐EPCO Profiles
12
Kyushu Electric Power Co., Inc.
Exchange Program with NTPC
In Feb. 2007
The signing ceremony of exchange agreement with NTPC
13
Kyushu Electric Power Co., Inc.
In Nov. 2012
ATTEND 5th INDIA POWER AWARD
14
Kyushu Electric Power Co., Inc.
J‐COAL Study
Diagnosis work NTPC Unchahar PS in FY 2012
Diagnosis Purpose
Improving plant efficiency of coal fired thermal power station
for effective utilization of coal and reducing environmental load
Schedule
Site survey : 2012. 12. 11 – 12. 14 (at Unchahar PS)
Presentation : 2013. 3. 11 (at Unchahar PS)
15
Maintenance
Preventive
Maintenance
Breakdown
Maintenance
Time Based
Maintenance
Condition Based
Maintenance
Emergency
Maintenance
Ordinary Corrective
Categorized Equipment Maintenance Management
PeriodicInspection
Aging
Equipment
Inspection
Maintenance
・High Plant Availability possible through Preventive Maintenance
・Higher economic efficiency requires shift to Condition Based Maintenance
Kyushu Electric Power Co., Inc.
16
Kyushu Electric Power Co., Inc.
Periodical maintenance
Maintaining thermal efficiency
Introduction of high‐
efficiency equipment
Improvement of thermal efficiency
Improvement of thermal
efficiency
How to Keep High Availability, Efficiencies, Clean ?
Improvement Concept of thermal efficiency
Grasping periodically the facility performance
Economic evaluation
17
ScheduledMaintenanceSystem
Inspection and replacement
Annual/Long-term Maintenance program
Maintenance Standards
Categorize maintenance activities into
- TBM (Time-based Maintenance)
- CBM (Condition Based Maintenance)
- BM(Breakdown Maintenance)
based on analysis of past problems and judgment criteria
Introduced into Matsuura PS in 2004 and Reihoku PS in 2006
Kyushu Electric Power Co., Inc.
Concept of Equipment Maintenance Management
Maintaining power supply Availability
18
Plant Life Cycle Maintenance
▽50▽Operation Start ▽20∼25 Years
Target of Plant Life Time (50YEARS)
Daily maintenance/Periodical maintenance
Replace PlanInitial failure Long Term Maintenance Plan
Condition Monitoring
R&M LTE Work
Procedure of Long Term Maintenance Plan
Select Target Items with O&M conditions
Planning of Diagnosis methods ,Sample No(SN)
Tools (Online/Offline), Cost, Timing, etc.
Data acquisition and analysis of representative
point and trends analysis
Predict and Judgments for R&M/LTE Work with
Experimental Criteria
Readjustment of Period of measures, SN
Planning of next timing of monitor (Off line)
Kyushu Electric Power Co., Inc.
Target items for Overhaul or Replacement
Steam Turbine (HP,IP), Cylinders (inner/outer)
Major Valves for Steam Turbine (MSV,RSV)
FW Heaters
Air Pre Heater, Gas Heater (APH/GGH)
Electrostatic Precipitator (ESP)
Generator (Stator/Rotor)
Transformers
HV Motors
Control Systems
19
Secondary
superheater
Tertiary
superheater
Burnernozzle
Boiler
Burnernozzle
Silencer
New soot blower (4 (drum left) + 4 (drum right) = 8)
Kyushu Electric Power Co., Inc.
1. Washing the boiler generating surface
2. Primary superheater soot blow executed
(Measure for abrasion due to pressure reduction of
injection steam)
Soot blower
3. Economizer soot blower newly built
4. Washing the air preheater element and
replacing the defective element
Induced
draft fan
Chimney
Electric
dust
collector
Remarks
Polluted by ash, etc.
Run soot blower (9 (drum left) + 9 (drum right) = 18)
Run/stop soot blower (4 (drum left) + 4 (drum right) =
8)
Quaternary
superheater
Re-
heater
6. Burner nozzle automatic operation 5. Repairing steam leakage of
steam type air preheater
Primary
superheater
Economizer
Air preheater
Forced
draft fanSteam type air preheater
Improvement typical Measures for Boiler
20
Kyushu Electric Power Co., Inc.
Improvement of high‐pressure turbine
aged deteriorated part
・Replacing seal fin, etc.
・Removing scale, etc.
Measures for low‐pressure turbine
・Moving blade and stationary blade newly
made. Fin installed on moving blade.
・Replacing the diaphram
・Replacing the inner casing
Improvement typical Measures for Turbine
Outer casing
Inner casing
Turbine rotor
21
OperationHours
Kyushu Electric Power Co., Inc.
CEA‐JCOAL Workshop FY2014
Turbine Rotor Replacement timing
Mapping of Rotor Replacement timing
Elapsed Years
Op Rate:70%Op Rate:90%
Av.181,600Hr / 26.2yrs
5Years Range Circle
★
22
InsulationStrength(%)
Kyushu Electric Power Co., Inc.
Sample Chart of Generator Stator Coil
Inspection and Replacement timing
Operation Hours
Max.
Ave.
Min.
Regression lines
99.9% Confidence interval
Temp.Corr
Line of Monitoring Start
Limit of Operation
Monitoring Period
★
23
Inspectionitems
Monthlycheck LubricatetheGrease
Routinecheck Visualinspection,cleaning,
windinginsulationmeasurement,
etc.
OverHaul CategorizedtoTBM/BDM,Cycles,
etc.(on/off-site,Spares,
Redundancy,SeverityoftheBD)
Condition
Monitoring
Insulationresistancetest,
Polarizationindextest,Tanδ
test
Whenneeded SupplementaryInsulation,
Rewinding
Kyushu Electric Power Co., Inc.
Condition Monitoring for MV Motors
• Due to old installation (20 years back),
deterioration of insulation is a matter of
concern.
24
Wearlevel(degreeofdegradation)
Kyushu Electric Power Co., Inc.
Running in Stable operation Advanced stage
Time
Temperature
diagnosis
Vibration
diagnosis
Possible to catch abnormalities at
early stage
Lubricant diagnosis
Condition Monitoring for Rotating Machines
Process to Failure of ROTATING MACHINES
Failure
3. Coal Quality Evaluation System(CQES),
Idemitsu Kosan Co., Ltd.
25
26PROPERTY OF IDEMITSU KOSAN CO., LTD. TO BE REPRODUCED AND USED ONLY IN ACCORDANCE WITH WRITTEN PERMISSION OF IDEMITSU KOSAN CO., LTD.
Coal
Production
&
Procurement
Transportation
Marketing
Boiler
Operation
PF boilers
CFBC boiler
(Aichi & Tokuyama refineries)
(Chiba refinery)
10.6 Million tons (2013)
* Idemitsu’s equity
Coal mine operation in Australia
Acquired coal mine in Indonesia
Coal supply from Australia, Indonesia, Russia, China, etc.
Idemitsu bulk terminal (Chiba)
Shunan bulk terminal
Total sales : 14.8 Million tons (2013)
Japan : 6.8 Million tons (2013)
Other : 8.0 Million tons (2013)
資料整理番号:14067
Our Coal Business
27
資料整理番号:14067
1-11. Coal Analysis Centre
Calorific Value Ultimate Analysis
Ash Fusion Temperature Ash Composition
PROPERTY OF IDEMITSU KOSAN CO., LTD. TO BE REPRODUCED AND USED ONLY IN ACCORDANCE WITH WRITTEN PERMISSION OF IDEMITSU KOSAN CO., LTD.
28
資料整理番号:14067
1-12. Coal Quality Evaluation Tests
Ash deposition
<Turbulent flow furnace>
<SEM/EDX>
PROPERTY OF IDEMITSU KOSAN CO., LTD. TO BE REPRODUCED AND USED ONLY IN ACCORDANCE WITH WRITTEN PERMISSION OF IDEMITSU KOSAN CO., LTD.
NOx emission
Combustion Furnace
Unburned carbon
We have carried out many evaluation tests for various kinds of coals
and collected the test results into our database.
We can provide technical services by applying these abundant data.
Handling
Spontaneous comb.
Durham cone test
Mill
Grindability
資料整理番号:14067
1-13. Technical Products
29
Dust dispersion
inhibitor
Numerical computer
simulation
Coal analysis
& evaluation tests
Spontaneous
combustion simulator
High temperature
furnace scope
Ash utilization
simulator
Trace element simulator
Coal quality
evaluation system
Evaluation tests on
handling properties
Spontaneous
combustion tester
資料整理番号:14067
Bunker
Boiler
SCR
EP
FGD
Mill
Stock Pile
Ash Gypsum
Increase of
mill load
Slagging and
fouling
Increase
NOx emission
Increase
dust emission
Decrease
De-SOx activity
Decrease
gypsum purity
Difficulty of
ash utilization
Spontaneous
combustion
Dust emission
Excess trace
element regulations
Decrease
Efficiency
Increase
unburned carbon
Coal quality affects the performance of each facility
in a coal-fired power plant.
2-1. Coal Quality Impacts on Power Plant
30
31PROPERTY OF IDEMITSU KOSAN CO., LTD. TO BE REPRODUCED AND USED ONLY IN ACCORDANCE WITH WRITTEN PERMISSION OF IDEMITSU KOSAN CO., LTD.
)
Operating
Condition
CQES
1. Quick and accurate prediction of plant performance for new coal
2. Prior prediction of problems, which helps to prevent trouble
3. Investigation of optimum blending conditions
4. Abundant technical information
(Evaluation technology, Trouble examples, Coal analysis data, etc.)
資料整理番号:140672-2. Coal Quality Evaluation System(CQES)
Idemitsu developed the computer software which can quantitatively
estimate the impacts of coal quality on power plant performance. This
system is used in many Japanese and overseas power companies for
expanding coal brands.
Coal
Analysis
Data
Boiler
32
資料整理番号:14067
PROPERTY OF IDEMITSU KOSAN CO., LTD. TO BE REPRODUCED AND USED ONLY IN ACCORDANCE WITH WRITTEN PERMISSION OF IDEMITSU KOSAN CO., LTD.
2-3. Plant Performance(Outline)
33
資料整理番号:14067
Available
Not available
PROPERTY OF IDEMITSU KOSAN CO., LTD. TO BE REPRODUCED AND USED ONLY IN ACCORDANCE WITH WRITTEN PERMISSION OF IDEMITSU KOSAN CO., LTD.
2-4. Selection of Suitable Blending Ratio
4. Numerical Simulation of Pulverized Coal
Combustion, Idemitsu Kosan Co., Ltd.
34
35
資料整理番号:14067
We can clearly grasp combustion states in the boiler and investigate its
optimum operating conditions, which increase boiler efficiency and reduce
NOx emissions. This tool is also useful for the solution of slagging trouble.
PROPERTY OF IDEMITSU KOSAN CO., LTD. TO BE REPRODUCED AND USED ONLY IN ACCORDANCE WITH WRITTEN PERMISSION OF IDEMITSU KOSAN CO., LTD.
Gas velocity TemperatureParticle trajectory Oxygen conc.Boiler geometry
3-1. Numerical Simulation
3D simulator optimizes boiler operating conditions
without hardware modification.
36
資料整理番号:14067
Increase in O2
Present Improved
0
FF
F
E
DE
Coal-D
CD
Coal-C
BC
BC2
BC1
Coal-B
AB
Coal-A
AA
20 40 60 80
Air Flow Rate(m/s)
PROPERTY OF IDEMITSU KOSAN CO., LTD. TO BE REPRODUCED AND USED ONLY IN ACCORDANCE WITH WRITTEN PERMISSION OF IDEMITSU KOSAN CO., LTD.
Change of damper opening Change of O2 concentration
Increase
Improved
O2 conc.
(%)
10.0
9.0
8.0
7.0
6.0
5.0
4.0
3.0
2.0
1.0
Present
Increase
Decrease
Increase
Decrease
3-4. Improvement of Boiler Efficiency
37
資料整理番号:14067
Coal Burner A B C D E Total
Present condition 1.3 4.1 5.7 11.0 1.1 5.2
Improved condition 1.7 4.3 1.3 2.3 0.7 2.5
PROPERTY OF IDEMITSU KOSAN CO., LTD. TO BE REPRODUCED AND USED ONLY IN ACCORDANCE WITH WRITTEN PERMISSION OF IDEMITSU KOSAN CO., LTD.
3-5. Reducing Unburned Carbon
Improved condition
OFA Layer
Coal-D Burner Layer
O2 conc.
(%)
10.0
9.0
8.0
7.0
6.0
5.0
4.0
3.0
2.0
1.0
0.0
Present condition
Optimization of
Air Damper Settings
OFA Layer
Coal-D Burner Layer
38
資料整理番号:14067
ParticleGas FlowGas Temp. Collision with Boiler Wall
Before
(Trouble)
OFA Tilt
-16 deg.
Improved
OFA Tilt
+16 deg.
PROPERTY OF IDEMITSU KOSAN CO., LTD. TO BE REPRODUCED AND USED ONLY IN ACCORDANCE WITH WRITTEN PERMISSION OF IDEMITSU KOSAN CO., LTD.
3-6. Solution of Slagging Trouble
39
資料整理番号:14067
Coal B
Coal A+B
Coal B
Coal A
Coal B
Belt Blending
Coal A
In-furnace blending
Coal A
In-furnace blending has to choose a suitable blending
condition from among many patterns.
Boiler performance such as unburned carbon, NOx
emission and furnace outlet temperature can be
improved compared to the belt blending.
PROPERTY OF IDEMITSU KOSAN CO., LTD. TO BE REPRODUCED AND USED ONLY IN ACCORDANCE WITH WRITTEN PERMISSION OF IDEMITSU KOSAN CO., LTD.
3-7. In-Furnace Blending
40
Summary
1. JCOAL is conducting several projects under Indi Japan mutual cooperation
in both coal and power sector. Joint declarations at both past and the latest
India-Japan Energy Dialogues acknowledged such significance and
achievement of the Cooperation.
2. CEA-JCOAL Cooperation provided a good opportunity for materialization of
R&M as well as fruitful discussion and information exchange in CCT
transfer program.
3. In a targeted long plant life of nearly 50 years, high plant availability
possible through preventive maintenance. Higher economic efficiency
requires shift to condition based maintenance
4. Idemitsu has been providing technical services to coal users, creating the
further demand of coal, and making the most effective use of coal resources.
5. Applying our products and services, we propose optimum coal-blending and
boiler-operating conditions which lead to improved efficiency and trouble-
free operation in a boiler.
6. We, especially Japanese players in the coal power subsector in India are
anxious to work together with our Indian partners toward sustainable
development of Indian power sector.
41
We look forward to working with you
Website:
http://www.jcoal.or.jp/index-en.html
Contacts:
Mr. K. Murakami (kzmurakami@jcoal.or.jp)
[Contact]
Engineering Group
International Business Division
Kyushu Electric Power Co. Inc.
2-1-82 Watanabe-dori, Chuo-ku, Fukuoka 810-8720 Japan
TEL: +81(92)726-1741 FAX: +81(92)716-4428
http://www.kyuden.co.jp/
Kyushu Electric Power Co., Inc.
Coal & Environment Research Laboratory
Coal Business Department
Idemitsu Kosan Co., Ltd.
Kyushu Electric Power Co., Inc.

Measures and equipment

  • 1.
    Measures and Equipment forOptimal Efficiency at Thermal Power Stations January 30, 2015 Japan Coal Energy Center (JCOAL) International Seminar on "Implementation of PAT Scheme in Thermal Power Stations - Issues and Challenges“ India Habitat Centre 1
  • 2.
    1. Profile andActivities of Japan Coal Energy Center (JCOAL) 2. O&M Practices and Effective Solutions for BOP Systems, Kyushu Electric Power Co., Inc. 3. Coal Quality Evaluation System(CQES), Idemitsu Kosan Co., Ltd. 4. Numerical Simulation of Pulverized Coal Combustion, Idemitsu Kosan Co., Ltd. 5. Summary Overview 2
  • 3.
    1. Profile andActivities of Japan Coal Energy Center (JCOAL) 3
  • 4.
    Japan Coal EnergyCenter (JCOAL) • Established as a foundation in 1990, with its origin back to 1948 • Covers all coal related issues from upstream to downstream of the coal chain • Members: 119 incl. major public-listed companies and main players in energy and relevant sectors • Supervision by METI (Ministry of Economy, Trade and Industry of Japan) 4 Exploration Facilitation and promotion of cleaner utilization of coal Mining & Preparation Coal utilization technology development
  • 5.
    Upstream Activities CCT TransferProgram on coal preparation Technologies 5 CCT transfer project on coal preparation technology  Coal preparation technology was set as the main topic of technology exchange in India considering the importance of high ash coal processing.  1,305 trainees were invited to Japan including 150 Indian experts by the end of JFY2011  Technology exchange programs dispatching Japanese experts to target countries were also commenced Vari-Wave Jig (KCM) Control panel (KCM) Port facilities (Kushiro) Dry separation facility (Nagata Eng.) High efficiency coal preparation plant in Odisha  High efficiency coal preparation plant has been commissioned on July 25th, 2014 in Angul, Odisha using latest vari-wave jig technology with a capacity of 350t/h. Source: NEDO website
  • 6.
    The Project onEfficiency and Environmental Improvement of Coal fired Power Stations A MOU of Pre-primary Study of Efficiency and Environmental Improvement of Coal-fired Power Stations was signed on April 30, 2010, in the presence of Deputy Chairman, Planning Commission of India, and Minister of Economy, Trade and Industry of Japan. Diagnostic activities for two (2) state owned, one (1) NTPC owned TPS Durgapur Unchahar Badarpur 2010, 2011 Wanakbori 2010 Ramagundam 2011 Kahalgaon 2010, 2011, 2012 Dr. Narla Tata Rao (Vijayawada) A MOU for the Project on Efficiency and Environmental Improvement of Coal fired Power Station was signed on June 11, 2012. Diagnostic activities for Durgapur of DVC, Unchahar & Badarpur of NTPC; all of which were referred to in the Joint Statement on the occasion of the 6th Japan-India Energy Dialogue between the Ministry of Economy, Trade and Industry of Japan and the Planning Commission of India on October 10, 2012. CCT workshop in Delhi 2011 2012 Diagnostic activities for two (2) state owned, one (1) NTPC owned TPS R&M Workshop in Delhi 2010 2013 Follow up activities for all TPS are ongoing for all diagnosed TPS. CCT Transfer program for the delegates from India power sector was carried out. CCT workshop in Delhi 6
  • 7.
    Typical Example ofR & M Proposal COAL P Air S Air Feed Water Heater SH Steam RH Steam Steam Turbine Generator Cooling Tower Stack Condenser ESP IDF PA F FD F Mill Boile r Feed Pump Air Pre- Heater Fly Ash Bottom Ash Coal Bunke r Coal Yard Ash Pond※ ※ Transformer Circuit Breaker Plan-A:LE Replacement of worn parts only Plan-B:R&M Replacement of worn parts + Reuse of casing, replacement of HP,IP,LP turbine, D- EHC improvement and ESP rehabilitation Plan-C:R&M Plan-B+ generator improvement Plan-D:R&M Plan-C+ condenser and feedwater heater improvement 7
  • 8.
    8 Mitsubishi Hitachi Power Systems, NagasakiWorks ( 31st Oct. ) J-POWER, Isogo TPS ( 30th Oct., 3rd Dec.) J-POWER Tachibanawan TPS ( 04th Nov. ) CCT program - Site Visit - Open-Ended Meeting Embassy of India Mitsubishi Hitachi Power Systems, Hitachi Works (4th Dec.) Joban Joint Power Company Nakoso IGCC (5th Dec.) Chubu Electric Power, Hekinan TPS ( 8th Dec.) Idemitsu Coal & Environment Research Laboratory, Idemitsu Bulk Terminal ( 26th Sept.) Toshiba Keihin Work ( 25th Sept. ) J-POWER Takasago TPS ( 29 Sept. ) 8
  • 9.
    99 Discussion -Topics- Issues around materializationof R&M Efficiency Improvement through enhancement of O&M Coal blending as one of the key measures for domestic coal shortages Group1 R&M Group2 USC1 Group3 USC2 Possible barriers for Japanese players to work for India power sector Issues around materialization of Proposed New Project Technical Target and/or Guideline for introduction of USC Road map for high efficiency advanced technology
  • 10.
    2. O&M Practicesand Effective Solutions for BOP Systems, Kyushu Electric Power Co., Inc. 10
  • 11.
    11 Supply Facilities Hydro142places3,582MWPumpedStorage3places2,300MW ※ Coal3places2,460MW Thermal9places10,680MW LNG2places4,090MW ※ Geothermal6places212MWOil5places4,130MW Nuclear2places5,258MW ※ Thetotalofplacesdoesnotmatch, becausetheunit1ofKaritapower Internalcombustion34places399MWstationiscountedascoalandthe unit2iscountedasoil. Wind2places3MW Solar1places3MW (asofMarch31,2013) Total196places20,137MW Establishment May1,1951 Paid-inCapital 237.3billionyen #ofShareholders174,293 #ofSharesIssued andOutstanding 474,183,951 #ofContracts Lighting:7.69million Power:0.93million #ofEmployees 13,102 IT/telecom Electricity Sales VolumeSpecific- 83.8 billion kWh Kyushu Electric Power Co., Inc. Breakdown of Electricity Sales Volume (FY2012) Domestic Share of Electricity Sales Volume (FY2012) (Lighting 35.2%) Other than Specific-scale demand 41.4% (Power scale demand 58.6% Customers under Liberalization 6.2%) Over 6,000V , 50kW Tokyo 31.6% Tohoku 9.1% Kyushu 9.8% Other 17.9% Domestic Share of Electricity Sales Volume (10EPCOs) 851.6billion kWh Kansai Chubu 16.6% 14.9% Consolidated Sales (FY2012) Other 5.6% 1.6% Energy- related 9.5% Consolidated Revenue 1,545.9billion Electricity 83.3% KYUSHU‐EPCO Profiles
  • 12.
    12 Kyushu Electric PowerCo., Inc. Exchange Program with NTPC In Feb. 2007 The signing ceremony of exchange agreement with NTPC
  • 13.
    13 Kyushu Electric PowerCo., Inc. In Nov. 2012 ATTEND 5th INDIA POWER AWARD
  • 14.
    14 Kyushu Electric PowerCo., Inc. J‐COAL Study Diagnosis work NTPC Unchahar PS in FY 2012 Diagnosis Purpose Improving plant efficiency of coal fired thermal power station for effective utilization of coal and reducing environmental load Schedule Site survey : 2012. 12. 11 – 12. 14 (at Unchahar PS) Presentation : 2013. 3. 11 (at Unchahar PS)
  • 15.
    15 Maintenance Preventive Maintenance Breakdown Maintenance Time Based Maintenance Condition Based Maintenance Emergency Maintenance OrdinaryCorrective Categorized Equipment Maintenance Management PeriodicInspection Aging Equipment Inspection Maintenance ・High Plant Availability possible through Preventive Maintenance ・Higher economic efficiency requires shift to Condition Based Maintenance Kyushu Electric Power Co., Inc.
  • 16.
    16 Kyushu Electric PowerCo., Inc. Periodical maintenance Maintaining thermal efficiency Introduction of high‐ efficiency equipment Improvement of thermal efficiency Improvement of thermal efficiency How to Keep High Availability, Efficiencies, Clean ? Improvement Concept of thermal efficiency Grasping periodically the facility performance Economic evaluation
  • 17.
    17 ScheduledMaintenanceSystem Inspection and replacement Annual/Long-termMaintenance program Maintenance Standards Categorize maintenance activities into - TBM (Time-based Maintenance) - CBM (Condition Based Maintenance) - BM(Breakdown Maintenance) based on analysis of past problems and judgment criteria Introduced into Matsuura PS in 2004 and Reihoku PS in 2006 Kyushu Electric Power Co., Inc. Concept of Equipment Maintenance Management Maintaining power supply Availability
  • 18.
    18 Plant Life CycleMaintenance ▽50▽Operation Start ▽20∼25 Years Target of Plant Life Time (50YEARS) Daily maintenance/Periodical maintenance Replace PlanInitial failure Long Term Maintenance Plan Condition Monitoring R&M LTE Work Procedure of Long Term Maintenance Plan Select Target Items with O&M conditions Planning of Diagnosis methods ,Sample No(SN) Tools (Online/Offline), Cost, Timing, etc. Data acquisition and analysis of representative point and trends analysis Predict and Judgments for R&M/LTE Work with Experimental Criteria Readjustment of Period of measures, SN Planning of next timing of monitor (Off line) Kyushu Electric Power Co., Inc. Target items for Overhaul or Replacement Steam Turbine (HP,IP), Cylinders (inner/outer) Major Valves for Steam Turbine (MSV,RSV) FW Heaters Air Pre Heater, Gas Heater (APH/GGH) Electrostatic Precipitator (ESP) Generator (Stator/Rotor) Transformers HV Motors Control Systems
  • 19.
    19 Secondary superheater Tertiary superheater Burnernozzle Boiler Burnernozzle Silencer New soot blower(4 (drum left) + 4 (drum right) = 8) Kyushu Electric Power Co., Inc. 1. Washing the boiler generating surface 2. Primary superheater soot blow executed (Measure for abrasion due to pressure reduction of injection steam) Soot blower 3. Economizer soot blower newly built 4. Washing the air preheater element and replacing the defective element Induced draft fan Chimney Electric dust collector Remarks Polluted by ash, etc. Run soot blower (9 (drum left) + 9 (drum right) = 18) Run/stop soot blower (4 (drum left) + 4 (drum right) = 8) Quaternary superheater Re- heater 6. Burner nozzle automatic operation 5. Repairing steam leakage of steam type air preheater Primary superheater Economizer Air preheater Forced draft fanSteam type air preheater Improvement typical Measures for Boiler
  • 20.
    20 Kyushu Electric PowerCo., Inc. Improvement of high‐pressure turbine aged deteriorated part ・Replacing seal fin, etc. ・Removing scale, etc. Measures for low‐pressure turbine ・Moving blade and stationary blade newly made. Fin installed on moving blade. ・Replacing the diaphram ・Replacing the inner casing Improvement typical Measures for Turbine Outer casing Inner casing Turbine rotor
  • 21.
    21 OperationHours Kyushu Electric PowerCo., Inc. CEA‐JCOAL Workshop FY2014 Turbine Rotor Replacement timing Mapping of Rotor Replacement timing Elapsed Years Op Rate:70%Op Rate:90% Av.181,600Hr / 26.2yrs 5Years Range Circle ★
  • 22.
    22 InsulationStrength(%) Kyushu Electric PowerCo., Inc. Sample Chart of Generator Stator Coil Inspection and Replacement timing Operation Hours Max. Ave. Min. Regression lines 99.9% Confidence interval Temp.Corr Line of Monitoring Start Limit of Operation Monitoring Period ★
  • 23.
    23 Inspectionitems Monthlycheck LubricatetheGrease Routinecheck Visualinspection,cleaning, windinginsulationmeasurement, etc. OverHaulCategorizedtoTBM/BDM,Cycles, etc.(on/off-site,Spares, Redundancy,SeverityoftheBD) Condition Monitoring Insulationresistancetest, Polarizationindextest,Tanδ test Whenneeded SupplementaryInsulation, Rewinding Kyushu Electric Power Co., Inc. Condition Monitoring for MV Motors • Due to old installation (20 years back), deterioration of insulation is a matter of concern.
  • 24.
    24 Wearlevel(degreeofdegradation) Kyushu Electric PowerCo., Inc. Running in Stable operation Advanced stage Time Temperature diagnosis Vibration diagnosis Possible to catch abnormalities at early stage Lubricant diagnosis Condition Monitoring for Rotating Machines Process to Failure of ROTATING MACHINES Failure
  • 25.
    3. Coal QualityEvaluation System(CQES), Idemitsu Kosan Co., Ltd. 25
  • 26.
    26PROPERTY OF IDEMITSUKOSAN CO., LTD. TO BE REPRODUCED AND USED ONLY IN ACCORDANCE WITH WRITTEN PERMISSION OF IDEMITSU KOSAN CO., LTD. Coal Production & Procurement Transportation Marketing Boiler Operation PF boilers CFBC boiler (Aichi & Tokuyama refineries) (Chiba refinery) 10.6 Million tons (2013) * Idemitsu’s equity Coal mine operation in Australia Acquired coal mine in Indonesia Coal supply from Australia, Indonesia, Russia, China, etc. Idemitsu bulk terminal (Chiba) Shunan bulk terminal Total sales : 14.8 Million tons (2013) Japan : 6.8 Million tons (2013) Other : 8.0 Million tons (2013) 資料整理番号:14067 Our Coal Business
  • 27.
    27 資料整理番号:14067 1-11. Coal AnalysisCentre Calorific Value Ultimate Analysis Ash Fusion Temperature Ash Composition PROPERTY OF IDEMITSU KOSAN CO., LTD. TO BE REPRODUCED AND USED ONLY IN ACCORDANCE WITH WRITTEN PERMISSION OF IDEMITSU KOSAN CO., LTD.
  • 28.
    28 資料整理番号:14067 1-12. Coal QualityEvaluation Tests Ash deposition <Turbulent flow furnace> <SEM/EDX> PROPERTY OF IDEMITSU KOSAN CO., LTD. TO BE REPRODUCED AND USED ONLY IN ACCORDANCE WITH WRITTEN PERMISSION OF IDEMITSU KOSAN CO., LTD. NOx emission Combustion Furnace Unburned carbon We have carried out many evaluation tests for various kinds of coals and collected the test results into our database. We can provide technical services by applying these abundant data. Handling Spontaneous comb. Durham cone test Mill Grindability
  • 29.
    資料整理番号:14067 1-13. Technical Products 29 Dustdispersion inhibitor Numerical computer simulation Coal analysis & evaluation tests Spontaneous combustion simulator High temperature furnace scope Ash utilization simulator Trace element simulator Coal quality evaluation system Evaluation tests on handling properties Spontaneous combustion tester
  • 30.
    資料整理番号:14067 Bunker Boiler SCR EP FGD Mill Stock Pile Ash Gypsum Increaseof mill load Slagging and fouling Increase NOx emission Increase dust emission Decrease De-SOx activity Decrease gypsum purity Difficulty of ash utilization Spontaneous combustion Dust emission Excess trace element regulations Decrease Efficiency Increase unburned carbon Coal quality affects the performance of each facility in a coal-fired power plant. 2-1. Coal Quality Impacts on Power Plant 30
  • 31.
    31PROPERTY OF IDEMITSUKOSAN CO., LTD. TO BE REPRODUCED AND USED ONLY IN ACCORDANCE WITH WRITTEN PERMISSION OF IDEMITSU KOSAN CO., LTD. ) Operating Condition CQES 1. Quick and accurate prediction of plant performance for new coal 2. Prior prediction of problems, which helps to prevent trouble 3. Investigation of optimum blending conditions 4. Abundant technical information (Evaluation technology, Trouble examples, Coal analysis data, etc.) 資料整理番号:140672-2. Coal Quality Evaluation System(CQES) Idemitsu developed the computer software which can quantitatively estimate the impacts of coal quality on power plant performance. This system is used in many Japanese and overseas power companies for expanding coal brands. Coal Analysis Data Boiler
  • 32.
    32 資料整理番号:14067 PROPERTY OF IDEMITSUKOSAN CO., LTD. TO BE REPRODUCED AND USED ONLY IN ACCORDANCE WITH WRITTEN PERMISSION OF IDEMITSU KOSAN CO., LTD. 2-3. Plant Performance(Outline)
  • 33.
    33 資料整理番号:14067 Available Not available PROPERTY OFIDEMITSU KOSAN CO., LTD. TO BE REPRODUCED AND USED ONLY IN ACCORDANCE WITH WRITTEN PERMISSION OF IDEMITSU KOSAN CO., LTD. 2-4. Selection of Suitable Blending Ratio
  • 34.
    4. Numerical Simulationof Pulverized Coal Combustion, Idemitsu Kosan Co., Ltd. 34
  • 35.
    35 資料整理番号:14067 We can clearlygrasp combustion states in the boiler and investigate its optimum operating conditions, which increase boiler efficiency and reduce NOx emissions. This tool is also useful for the solution of slagging trouble. PROPERTY OF IDEMITSU KOSAN CO., LTD. TO BE REPRODUCED AND USED ONLY IN ACCORDANCE WITH WRITTEN PERMISSION OF IDEMITSU KOSAN CO., LTD. Gas velocity TemperatureParticle trajectory Oxygen conc.Boiler geometry 3-1. Numerical Simulation 3D simulator optimizes boiler operating conditions without hardware modification.
  • 36.
    36 資料整理番号:14067 Increase in O2 PresentImproved 0 FF F E DE Coal-D CD Coal-C BC BC2 BC1 Coal-B AB Coal-A AA 20 40 60 80 Air Flow Rate(m/s) PROPERTY OF IDEMITSU KOSAN CO., LTD. TO BE REPRODUCED AND USED ONLY IN ACCORDANCE WITH WRITTEN PERMISSION OF IDEMITSU KOSAN CO., LTD. Change of damper opening Change of O2 concentration Increase Improved O2 conc. (%) 10.0 9.0 8.0 7.0 6.0 5.0 4.0 3.0 2.0 1.0 Present Increase Decrease Increase Decrease 3-4. Improvement of Boiler Efficiency
  • 37.
    37 資料整理番号:14067 Coal Burner AB C D E Total Present condition 1.3 4.1 5.7 11.0 1.1 5.2 Improved condition 1.7 4.3 1.3 2.3 0.7 2.5 PROPERTY OF IDEMITSU KOSAN CO., LTD. TO BE REPRODUCED AND USED ONLY IN ACCORDANCE WITH WRITTEN PERMISSION OF IDEMITSU KOSAN CO., LTD. 3-5. Reducing Unburned Carbon Improved condition OFA Layer Coal-D Burner Layer O2 conc. (%) 10.0 9.0 8.0 7.0 6.0 5.0 4.0 3.0 2.0 1.0 0.0 Present condition Optimization of Air Damper Settings OFA Layer Coal-D Burner Layer
  • 38.
    38 資料整理番号:14067 ParticleGas FlowGas Temp.Collision with Boiler Wall Before (Trouble) OFA Tilt -16 deg. Improved OFA Tilt +16 deg. PROPERTY OF IDEMITSU KOSAN CO., LTD. TO BE REPRODUCED AND USED ONLY IN ACCORDANCE WITH WRITTEN PERMISSION OF IDEMITSU KOSAN CO., LTD. 3-6. Solution of Slagging Trouble
  • 39.
    39 資料整理番号:14067 Coal B Coal A+B CoalB Coal A Coal B Belt Blending Coal A In-furnace blending Coal A In-furnace blending has to choose a suitable blending condition from among many patterns. Boiler performance such as unburned carbon, NOx emission and furnace outlet temperature can be improved compared to the belt blending. PROPERTY OF IDEMITSU KOSAN CO., LTD. TO BE REPRODUCED AND USED ONLY IN ACCORDANCE WITH WRITTEN PERMISSION OF IDEMITSU KOSAN CO., LTD. 3-7. In-Furnace Blending
  • 40.
    40 Summary 1. JCOAL isconducting several projects under Indi Japan mutual cooperation in both coal and power sector. Joint declarations at both past and the latest India-Japan Energy Dialogues acknowledged such significance and achievement of the Cooperation. 2. CEA-JCOAL Cooperation provided a good opportunity for materialization of R&M as well as fruitful discussion and information exchange in CCT transfer program. 3. In a targeted long plant life of nearly 50 years, high plant availability possible through preventive maintenance. Higher economic efficiency requires shift to condition based maintenance 4. Idemitsu has been providing technical services to coal users, creating the further demand of coal, and making the most effective use of coal resources. 5. Applying our products and services, we propose optimum coal-blending and boiler-operating conditions which lead to improved efficiency and trouble- free operation in a boiler. 6. We, especially Japanese players in the coal power subsector in India are anxious to work together with our Indian partners toward sustainable development of Indian power sector.
  • 41.
    41 We look forwardto working with you Website: http://www.jcoal.or.jp/index-en.html Contacts: Mr. K. Murakami (kzmurakami@jcoal.or.jp) [Contact] Engineering Group International Business Division Kyushu Electric Power Co. Inc. 2-1-82 Watanabe-dori, Chuo-ku, Fukuoka 810-8720 Japan TEL: +81(92)726-1741 FAX: +81(92)716-4428 http://www.kyuden.co.jp/ Kyushu Electric Power Co., Inc. Coal & Environment Research Laboratory Coal Business Department Idemitsu Kosan Co., Ltd. Kyushu Electric Power Co., Inc.