SlideShare a Scribd company logo
©RTE 2004
A.4.1 Introduction
A.4.2 France: incident of 19 December 1978
A.4.3 France: incident of 12 January 1987
A.4.4 Quebec: incident of 18 April 1988
A.4.5 Italy: incident of 24 August 1994
A.4.6 United States: major power failures
of summer 1996
A.4.7 Major power failures of 2003
251
A4 Annex 4
Major incidents
throughout the world
A4 Annex 4
Major incidents
throughout the world
©RTE 2004
252
EDF - Cordemais fossil-fired power plant
©RTE 2004
253
Annex 4 - Major incidents
throughout the worldA
A.4.1 INTRODUCTION
Power system operating reliability is a constant challenge. Despite the existing
lines of defence at the level of the different power systems, the latter are not
shielded from widespread incidents, leading to large-scale customer load
shedding operations.
No-one has forgotten the incident that the French system sustained on 19
December 1978, when 75% of national load was affected. This incident, not a
recent one to be sure, is the most serious that EDF has experienced since the
end of the post-war period of shortage.
Less than a decade later, the incident of 12 January 1987, initiated by the
successive tripping of the generation units at Cordemais, near Nantes, where
the power supply to the west of France was interrupted, was a reminder to
power system operators to be watchful.
Since then, several other widespread incidents have occurred all over the world
and deprived millions of customers of electricity. Particular mention can be
made of the sizeable power failures that hit Quebec in 1988, the southern half
of Italy in 1994, the west of the United States in 1996 and, more recently, the
incidents in 2003 which affected the eastern part of the United States and
Canada, as well as southern Switzerland and the whole of Italy.
These events remind us how more or less important anomalies in the system
of defence can combine to seriously jeopardise System reliability, due to the
four phenomena described in § 2.3 and often a combination of them:
- cascade tripping,
- voltage collapse,
- frequency collapse,
- loss of synchronism.
Analysing how some of these major incidents occurred helps illustrate these
phenomena and gain a better understanding of their causes.
Although the defence systems and the measures taken by the various
companies differ, an in-depth look at these incidents and the succession of
events that led to the total or partial collapse of the network generally provides
many lessons about malfunctions that arose on the lines of defence set up, as
well as on the improvements that it would be advisable to make.
©RTE 2004
254
Part of the French grid still live
at 8.26 a.m. on 19 December 1978
immediately after the first collapse
Voltage trend on the 400 kV grid
in the west of France
during the incident of 12 January 1987
BELGIUM
MERY
MARMAGNE
BAYET
EGUZON
TRICASTIN
GERMANY
SWITZERLAND
ITALY
SPAIN
Voltage
t (min)
©RTE 2004
255
A
A.4.2 FRANCE: INCIDENT OF 19 DECEMBER 1978
(CASCADE OVERLOADS AND COLLAPSE OF MOST OF THE NETWORK)
On a day that was cold and overcast, the load escalation proved to be more rapid
and higher than forecast (38,500 MW dispatched). All available generating
facilities were used to the maximum of their possibilities (active and reactive) and
over 3,500 MW were imported from neighbouring countries, mainly Germany.
The rise of the load increased the already high transits, from the east to the Paris
region and, as a result, voltages turned out to be extremely low in a large part of
the network (Paris region, west).
Starting at 8 a.m., overloads were observed on the grid and, at 8.06 a.m., an
alarm "overload 20 minutes" appeared on the Bézaumont-Creney 400 kV line in
the east of France. Despite various switching operations on the network topology,
this overload was unable to be reduced and the line tripped due to the action of
its protection at 8.26 a.m.
Upon load transfer, three 225 kV lines tripped due to overload.The four generation
units at Revin were subsequently disconnected from the grid (due to their current
protection). A 400 kV interconnection with Belgium then tripped and the voltage
dropped further.The tripping (hard to explain) of a new 400 kV interconnection
with Belgium was accompanied by a further voltage drop and the loss of stability
of a large part of the grid.The next phase witnessed the opening of lines and
tripping of generation units (notably due to their voltage minimum and frequency
minimum protection devices). Isolated sub-networks formed, where the
generation-load balance could not be restored (insufficient load shedding,
generation unit outages).
75% of consumers were disconnected, although the south-eastern part of France
and areas in the vicinity of the northern and eastern borders remained connected.
Many generation units did not successfully trip to house load.
An initial power restoration was too rapid and led to a further collapse of the
network at 9.08 a.m. A more careful recovery, relying on hydro generation units
and imported power permitted almost complete network restoration at about
midday. Customers sustained power cuts lasting between 30 minutes and 10
hours.
This incident, resulting from a tight management of the network (high transits
and low voltages in some areas) and a cascade of overloads, clearly showed that
the defence plan at that time was unable to cope: automatic load shedding
operations were insufficient, the tripping of generation units occurred too soon
on voltage minimum criteria and the dividing up of the network was not
successful. Service restoration was also not satisfactory.
A great many actions were undertaken after this incident to improve all these
deficient areas.
Annex 4 - Major incidents
throughout the world
256
©RTE 2004
A
A.4.3 FRANCE: INCIDENT OF 12 JANUARY 1987
(VOLTAGE COLLAPSE AND POWER CUTS IN THE WEST)
Although 12 January was a particularly cold day (the "extreme cold" alert had
been sent out since the previous Friday), all available generation units started up
and managed to ensure a satisfactory generation margin (5,900 MW) and normal
voltage in the west (405 kV at Cordemais).
Then, in the space of a single hour, from 10.55 to 11.42 a.m., Cordemais generation
units 1, 2 and 3 broke down due to independent causes (failure of a sensor,
explosion of an electric coupler pole, shutdown due to a fire). The last unit
available, which would have been sufficient to maintain the voltage in the zone,
tripped as a result of inappropriate adjustment of the maximum rotor current
protection and the disturbance created by the outage of unit n° 3.
The loss of Cordemais generation led to a sudden drop of voltage to 380 kV in the
area. It stabilised for about 30 seconds, but the automatic on-load tap changers of
the 225 kV/HV and HV/MV transformers, while attempting to restore a normal
voltage, triggered a rise in load and the voltage again began to drop quickly. In a
matter of minutes, nine thermal generation units near the area tripped
successively, giving rise to a loss of power of 9,000 MW and maintaining the
voltage downward trend. Load shedding was then carried out and, at 11.50 a.m.,
the voltage steadied, but at a very low level in the west, less than 300 kV. In view
of this extremely precarious situation, which jeopardised the national grid, the
dispatching centre decided to shed a load of 1,500 MW in Brittany and the region
of Angers, bringing the network voltage back to its normal level.
As of noon, the situation was well under control and the voltage of the network
could now be restored. It would be lengthy because of the difficulty in
reconnecting a sufficient number of generation units close to Brittany and
Normandy, which did not trip to house load during the incident. It took until night-
time to fully restore the power supply to these regions, when two and
subsequently three generation units were again in operation at Cordemais. At the
most serious time, the outages reached a capacity of about 8,000 MW.
The main cause of this incident can be attributed to a lack of quality of adjustment
of some System components, in particular of the voltage regulators and
associated protection devices of generation units.The corresponding functions
are now dealt with under quality assurance. The automation of some actions
(blocking of on-load tap changers), the reduction of load shedding execution time
(by means of remote load shedding) also appeared indispensable following this
incident.
Annex 4 - Major incidents
throughout the world
©RTE 2004
A.4.4 QUEBEC: INCIDENT OF 18 APRIL 1988
(LOAD SHEDDING OUTAGE AND COMPLETE COLLAPSE OF THE NETWORK)
All day long on 18 April 1988, a strong storm beat down on the northern coast
of Quebec. In the evening, at about 8.10 p.m., a series of short-circuits, due to
snow and ice covering insulators, occurred at the Arnaud 735 kV substation,
causing the separation of the Churchill Falls power plant from the Hydro-
Québec network.The network load at that time was 18,500 MW (to which must
be added 2,600 MW in exports to neighbouring grids) and the power generated
by Churchill Falls 3,800 MW.
The safety automatic control devices intended to initiate load shedding did not
work. The Chamouchuane-Saguenay line tripped in a matter of seconds
following the start of the incident. Other generation units tripped in turn and
the whole network collapsed like a house of cards.
Load restoration took a total of over 8 hours.
QUEBEC: 18/04/88
A Annex 4 - Major incidents
throughout the world
257
COMPLEXE LA GRANDE
CHURCHILL
ARNAUD
CHAMOUCHOUANE
SAGENAY
QUEBECAREA
MONTREALAREA
2,600 MW
TOTHE
UNITED STATES
258
©RTE 2004
A
At 8.30 a.m. the next day, a similar fault occurred, again depriving the grid of
power from Churchill Falls. Fortunately, the remote load shedding automatic
control device had been repaired during the night and worked correctly this
time, avoiding a further collapse of the network. Although different customers
had to be cut off in turn for five hours to shed a load of 600 MW, this operation
helped confine the event.
Of course, the Quebec power system is quite different from the French system.
This incident nevertheless highlights the determining role played by customer
load shedding actions so as to limit the extension of major incidents. These
actions serve to supplement the fundamental action of the frequency primary
control installed on the generation units, the purpose of which is to reduce the
imbalance between and generation and load and avoid the collapse of the
frequency (and of the network). In similar cases, cutting off a few customers
very rapidly can avoid losing all of them and facilitate restoring supply to those
who had been disconnected due to the initial incident.
A relatively similar incident occurred in Egypt on 24 April 1994, where the much
weaker action than expected of the frequency load shedding led to the complete
collapse of the network.
A.4.5 ITALY: INCIDENT OF 24 AUGUST 1994
(SEPARATION OF THE NETWORK AND COLLAPSE IN THE SOUTH)
The incident of 24 August 1994, at 11.28 a.m., in southern Italy, occurred in a
degraded operation situation during which the operators had decided not to
comply with the "N-1" principle in view of external conditions considered as
propitious: summer period, favourable weather conditions.
The connections linking southern Italy to northern Italy (Rome South) were made
up of (cf. map):
- a 400 kV line Latina - Garigliano,
- a 400 kV lineValmontone - Presenzano,
- a 400 kV lineVillanova - Foggia,
- and a 225 kV line Popoli - Capriati.
Generation aspect:
- the three generation units of the Brindisi North power plant (each with a unit
capacity of 300 MW) were limited to 220 MW each owing to cooling water
temperature problems.The Brindisi South power plant (four 600 MW generation
units) was not allowed to operate;
- for the same reasons, the Rossano power plant (four 300 MW generation sets)
was limited to 170 MW per unit.
Annex 4 - Major incidents
throughout the world
©RTE 2004
During the night of 23 to 24 August 1994, a current transformer of the Latina -
Garigliano 400 kV line exploded at Latina, damaging the circuit breakers of other
400 kV lines, notably those of the outgoing feeders toValmontone and RomeWest.
The Rome South - Latina line was shut down for works.
At 11.28 a.m. on 24August, a fire beneath theValmontone - Presenzano line caused
this connection to trip. High oscillations between the north and south of Italy were
observed.The Villanova - Foggia 400 kV and Popoli - Capriati 225 kV lines then
tripped, likely due to overload or loss of synchronism, bringing about the formation
of an insufficient separate network in southern Italy.
The frequency variation within this network was about 2 Hz per second, or even
higher, which probably made part of the load shedding frequency drift relays
ineffective and led to the outage of all generation on this network.
This incident caused customers to be cut off (about 4,500 MW) for a period of from
two to two and a half hours.
Even if the Italian network is not so fully meshed as the French grid, the operating
conditions which our transalpine colleagues have to face are not very different
from those encountered at certain periods on the French network near the
Mediterranean.They highlight in particular the importance of the "N-1" rule.
Roma/O
Brindisi/S
Brindisi/N
Roma/S
Latina
Garigliano
Presenzano
Villanova
Popoli
Valmontone
Capriati Foggia
Rossano
ITALY
ITALY: 24/08/94
A Annex 4 - Major incidents
throughout the world
259
260
©RTE 2004
A
A.4.6 UNITED STATES: MAJOR POWER FAILURES OF SUMMER 1996
Three major incidents affected the American western network in the summer of
1996, causing its partial break-up and cutting off millions of customers.
It all began on 2 July, in the early afternoon, by a single-phase fault -electric arc
due to contact with a tree- on one of the three 345 kV lines which transmit
electricity from the Jim Bridger power plant inWyoming (four generation units,
total capacity 2,000 MW) to the State of ldaho (cf. map).This incident occurred
when temperatures are very high in the west of the United States and when
loads and transits between different States are therefore substantial.
During the fault clearance sequence, a second line transmitting power from the
plant tripped due to a faulty protection operation.To avoid the overload of the
last remaining line, a programmable logic controller shut down 1,000 MW of
power plant output. This immediately brought about a considerable voltage
drop in Idaho and initiated a slower voltage drop with oscillations on Pacific
Inertie, made up of all the 500 kV AC and DC interconnection lines linking the
North-West (Washington-Oregon) to the South-West (California).
Twenty-four seconds later, the long Mill Creek-Antelope line tripped due to
overload because of the inappropriate setting of its distance protective system
and, in a matter of seconds, triggered a voltage drop in Oregon.
The incident then became widespread and a cascade of trippings led to the
formation of five separate networks. Thirty-five seconds after the initial fault,
two million customers, representing 12 GW of power, found themselves
without electricity.
On 3 July, this incident occurred again in the same way, but remained confined
to the Boise region, thanks to the load shedding command issued by the control
centre.
On 10 August, a similar incident took place, cutting off 7.5 million customers
representing a load of about 30 GW.
Several factors are the cause of these incidents:
- system operation at the maximum limits,
- faulty maintenance (pruning, protective devices),
- poor performance of generation units under transient operating conditions,
- insufficient exchange of information between partners at the forecast level,
- poor quality of setting of some protective devices.
Annex 4 - Major incidents
throughout the world
261
©RTE 2004
A report was submitted to the President of the United States, defining five main
lines of progress together with action plans:
- ensure the responsibility of all sectors;
- place stress on System reliability;
- improve information on power system reliability;
- extend the scope of the analyses;
- enhance the professionalism of all those concerned.
On the other hand, these incidents showed that dividing up the networks was an
efficient measure to avoid complete collapse and facilitate service restoration.
UNITED STATES: 2 July 1996
A Annex 4 - Major incidents
throughout the world
262
©RTE 2004
A
A.4.6 MAJOR POWER FAILURES OF 2003
A number of incident occurrences in 2003 highlighted the issues of security of
supply and of the reliability of power systems.
Concerning the first issue, the revolving load shedding operations that Italy
experienced on 26 June 2003, confirming the California crisis in 2000-2001,
show how failures inescapably occur when generation and transmission
capacities no longer match the load to be supplied.
As for the issue of effective operating reliability, it is illustrated by the two
spectacular power failures presented hereafter.
A.4.7.1 THE AMERICAN INCIDENT (UNITED STATES AND CANADA) OF 14 AUGUST 2003
This power failure affected the Eastern Interconnection (one of the three
synchronous zones of the United States) and part of Canada.The grid concerned
stretches from Dakota to the East coast. Its organisation is complex. Supervised
by the operator Midwest ISO, it is intersected by networks covered by PJM. A
report on the incident referred to the grid as a "Swiss cheese network".
The situation before the incident was said to be sound, although the voltages
were low on First Energy’s network, while remaining above acceptable
minimum values (0.92 pu). The load was high (air conditioning), but the
operators managed to cope with more constraining situations on the previous
days. However, several control centres sustained information system failures,
which hampered the assessment of the risks run and the reaction of the
operators.
At 2.02 p.m., the Stuart - Atlanta 345 kV line tripped due to a contact with a tree,
causing a short-circuit to ground, and locked out.This fact of little importance in
itself was to disrupt a state estimator then in the course of reactivation.
From 3.05 to 3.41 p.m., three 345 kV lines connecting the northern and eastern
parts of Ohio tripped due to electric arcs between these lines and the
surrounding vegetation. The substantial load transfers and weakening of the
voltage plan brought about the tripping of lines and generation units which, as
of 4.10 p.m., occurred successively at intervals of a few seconds. A transit loop
was created from Pennsylvania to NewYork State, then Ontario and Michigan,
so as to get around the missing links.
The Eastern Interconnection network cut itself off along an east-west line.The
south remained unaffected, but the now isolated north was to sustain new
separations and collapse completely at 4.13 p.m., except for a few islands where
the performance of generation units and load shedding operations managed to
save the situation.
Annex 4 - Major incidents
throughout the world
263
A
©RTE 2004
Service restoration was difficult; 19 hours after the incident, 20% of the load still
had to be re-supplied.Two days were needed to restore supply to some parts of
the United States, owing in particular to problems in restarting some generation
units.
The incident affected a total of 50 million people and resulted in the loss of
about 62,000 MW in load in seven American states and Ontario.
The investigation commission attributed the collapse to the combination of:
- an inadequate assessment of the degraded state of the network at First
Energy;
- the application of criteria unsuited to the risks of collapse of First Energy’s
system;
- a lack in dealing with pruning requirements at First Energy;
- the failure of the organisations responsible for the safety of the
interconnected network to make a diagnosis in real time.
A.4.7.2 THE SWITZERLAND - ITALY INCIDENT OF 28 SEPTEMBER 2003
The incident occurred at around 3 a.m., when Italy had a high import balance
and when the exchange capacity with Switzerland and the rest of Europe was
saturated. The Mettlen - Lavorgo 380 kV line in Switzerland was 86% loaded.
According to the reliability studies carried out by the operator ETRANS, the
outage of this line would require curative actions within 15 minutes, including
actions to be carried out by the Italian system operator GRTN.
At 3.01 a.m., there was an electric arc between the line and the surrounding
vegetation and subsequent tripping; reclosing proved to be impossible due to
a too wide transmission angle (42°). Because of a load transfer, another Swiss
line went over to overload. In 24 minutes time, it came into contact with a tree
and tripped.
The incident then got out of control with, in a matter of seconds, the tripping of
another Swiss line due to overload and the automatic disconnection of the
Lienz - Soverzene line connecting Switzerland and Austria. Italy sustained loss
of synchronism and was separated from the rest of the European grid through
the action of distance protection devices on the cross-border lines: considering
the low voltages and high currents, the impedances measured by these
protection devices correspond to the tripping criteria.
In Italy, the frequency immediately fell to 49.1 Hz and the voltage collapsed.
Some generating facilities connected to the distribution networks tripped,
followed by 21 of the 50 main generation units connected to the transmission
network. Frequency load shedding was unable to save the situation; 2mn30s
after the separation, the Italian network was completely dead.
Annex 4 - Major incidents
throughout the world
264
©RTE 2004
An aerial view of Europe during the Italian black-out
of 28 September 2003
265
A
In the rest of the UCTE network, the frequency rose, but steadied at 50.2 Hz
through the action of automatic primary and secondary frequency controls.
Despite the tripping of some generation units, the incident was contained
thanks to the mostly appropriate reaction of the various power system
components and players.
Italy’s gradual reconnection with its neighbouring countries from 4.05 a.m. to
12.45 p.m. allowed the progressive resumption of imports and network
restoration, from 6 a.m. to 4 p.m. Re-supplying some southern areas took about
twenty hours.
Globally, the collapse affected 57 million people, with a power failure of 28,000
MW lasting several hours.
A.4.7.3 LESSONS DRAWN FROM THE INCIDENTS OF 2003
Feedback from these new incidents has shown the following noteworthy points:
- the way reliability is controlled may differ depending on whether theTSO is
in charge of the transmission infrastructures (case of France) or not (case of
Italy now and of the United States);
- the need to affirm the TSO’s role as conductor, particularly in the most
extreme situations where its orders must be executed without discussion
and delay;
- the indispensable nature of the independence of TSOs with respect to the
other players of the market;
- the need for an adapted reliability reference guide, in its different dimensions:
directives, laws, regulatory provisions, technical reference guide applying to
theTSO as to the other players (producers, distributors, consumers, traders,
etc.);
- the importance of the contractual relations between the TSO and the
producers, distributors and consumers, which require compliance with the
reliability provisions from the stage of connection to the grid to that of
control, by clearly stipulating the commitments of each party and the means
of monitoring these commitments;
- finally, the absolute necessity for strong coordination between TSOs, at the
different time scales concerned.
©RTE 2004
Annex 4 - Major incidents
throughout the world

More Related Content

What's hot

Utilization of Synchrophasors during Synchronization and Operation of Large ...
Utilization of Synchrophasors during  Synchronization and Operation of Large ...Utilization of Synchrophasors during  Synchronization and Operation of Large ...
Utilization of Synchrophasors during Synchronization and Operation of Large ...
Chandan Kumar
 
Grid Restoration Challneges and Strategy
Grid Restoration Challneges and Strategy Grid Restoration Challneges and Strategy
Grid Restoration Challneges and Strategy
Chandan Kumar
 
Design of a 400kv Transmission network
Design of a 400kv Transmission networkDesign of a 400kv Transmission network
Design of a 400kv Transmission network
Isaac Muyinza
 
Cat 0 shovel Alan Mason
Cat 0 shovel Alan MasonCat 0 shovel Alan Mason
Cat 0 shovel Alan Mason
NSW Environment and Planning
 
Power system stability issues and Defence Mechanism in Indian Grid
Power system stability issues and Defence Mechanism in Indian GridPower system stability issues and Defence Mechanism in Indian Grid
Power system stability issues and Defence Mechanism in Indian Grid
Chandan Kumar
 
Bs bab 1
Bs bab 1Bs bab 1
Bs bab 1
Natalie Ulza
 
Electrical system design of garden project at belhaven (10 Storey High Rise B...
Electrical system design of garden project at belhaven (10 Storey High Rise B...Electrical system design of garden project at belhaven (10 Storey High Rise B...
Electrical system design of garden project at belhaven (10 Storey High Rise B...
Nithya Susan Varghese
 
Kstps ppt
Kstps  pptKstps  ppt
Power systems (2)
Power systems (2)Power systems (2)
Power systems (2)
Satish Kansal
 
Fire Pumps, Controllers & Associated Electrical Distribution Aspects
Fire Pumps, Controllers & Associated Electrical Distribution AspectsFire Pumps, Controllers & Associated Electrical Distribution Aspects
Fire Pumps, Controllers & Associated Electrical Distribution Aspects
James S Nasby
 
Basic Mechanical & Electrical Application in Construction Industry
Basic Mechanical & Electrical Application in Construction IndustryBasic Mechanical & Electrical Application in Construction Industry
Basic Mechanical & Electrical Application in Construction Industry
HassanulHadiZakaria
 
Size a circuit breaker for a fire pump
Size a circuit breaker for a fire pumpSize a circuit breaker for a fire pump
Size a circuit breaker for a fire pump
Bassam Gomaa
 
Gss herapura report
Gss herapura reportGss herapura report
HIGH VOLTAGE PANEL SWITCHGEAR PRESENTATION
HIGH VOLTAGE PANEL SWITCHGEAR PRESENTATIONHIGH VOLTAGE PANEL SWITCHGEAR PRESENTATION
HIGH VOLTAGE PANEL SWITCHGEAR PRESENTATION
SenthilVenkat2
 
Power System Stability Issues
Power System Stability IssuesPower System Stability Issues
Power System Stability Issues
Chandan Kumar
 
industrial training ppt from 33 kv substation UPCL
industrial training ppt from 33 kv substation UPCLindustrial training ppt from 33 kv substation UPCL
industrial training ppt from 33 kv substation UPCL
surendra rawat
 
Major blackout in the world
Major blackout in the worldMajor blackout in the world
Major blackout in the world
Chandan Kumar
 
Standards
StandardsStandards
Standards
Mustafa Ismail
 
FFC-MM Plantsite Power System Protection
FFC-MM Plantsite Power System ProtectionFFC-MM Plantsite Power System Protection
FFC-MM Plantsite Power System Protection
farazrafi87
 
SLD-LINE LENGTH-NAMEPLATE DETAILS OF 765/400/220KV EQUIPMENT DETAILS-TYPES OF...
SLD-LINE LENGTH-NAMEPLATE DETAILS OF 765/400/220KV EQUIPMENT DETAILS-TYPES OF...SLD-LINE LENGTH-NAMEPLATE DETAILS OF 765/400/220KV EQUIPMENT DETAILS-TYPES OF...
SLD-LINE LENGTH-NAMEPLATE DETAILS OF 765/400/220KV EQUIPMENT DETAILS-TYPES OF...
Pavan choudhary
 

What's hot (20)

Utilization of Synchrophasors during Synchronization and Operation of Large ...
Utilization of Synchrophasors during  Synchronization and Operation of Large ...Utilization of Synchrophasors during  Synchronization and Operation of Large ...
Utilization of Synchrophasors during Synchronization and Operation of Large ...
 
Grid Restoration Challneges and Strategy
Grid Restoration Challneges and Strategy Grid Restoration Challneges and Strategy
Grid Restoration Challneges and Strategy
 
Design of a 400kv Transmission network
Design of a 400kv Transmission networkDesign of a 400kv Transmission network
Design of a 400kv Transmission network
 
Cat 0 shovel Alan Mason
Cat 0 shovel Alan MasonCat 0 shovel Alan Mason
Cat 0 shovel Alan Mason
 
Power system stability issues and Defence Mechanism in Indian Grid
Power system stability issues and Defence Mechanism in Indian GridPower system stability issues and Defence Mechanism in Indian Grid
Power system stability issues and Defence Mechanism in Indian Grid
 
Bs bab 1
Bs bab 1Bs bab 1
Bs bab 1
 
Electrical system design of garden project at belhaven (10 Storey High Rise B...
Electrical system design of garden project at belhaven (10 Storey High Rise B...Electrical system design of garden project at belhaven (10 Storey High Rise B...
Electrical system design of garden project at belhaven (10 Storey High Rise B...
 
Kstps ppt
Kstps  pptKstps  ppt
Kstps ppt
 
Power systems (2)
Power systems (2)Power systems (2)
Power systems (2)
 
Fire Pumps, Controllers & Associated Electrical Distribution Aspects
Fire Pumps, Controllers & Associated Electrical Distribution AspectsFire Pumps, Controllers & Associated Electrical Distribution Aspects
Fire Pumps, Controllers & Associated Electrical Distribution Aspects
 
Basic Mechanical & Electrical Application in Construction Industry
Basic Mechanical & Electrical Application in Construction IndustryBasic Mechanical & Electrical Application in Construction Industry
Basic Mechanical & Electrical Application in Construction Industry
 
Size a circuit breaker for a fire pump
Size a circuit breaker for a fire pumpSize a circuit breaker for a fire pump
Size a circuit breaker for a fire pump
 
Gss herapura report
Gss herapura reportGss herapura report
Gss herapura report
 
HIGH VOLTAGE PANEL SWITCHGEAR PRESENTATION
HIGH VOLTAGE PANEL SWITCHGEAR PRESENTATIONHIGH VOLTAGE PANEL SWITCHGEAR PRESENTATION
HIGH VOLTAGE PANEL SWITCHGEAR PRESENTATION
 
Power System Stability Issues
Power System Stability IssuesPower System Stability Issues
Power System Stability Issues
 
industrial training ppt from 33 kv substation UPCL
industrial training ppt from 33 kv substation UPCLindustrial training ppt from 33 kv substation UPCL
industrial training ppt from 33 kv substation UPCL
 
Major blackout in the world
Major blackout in the worldMajor blackout in the world
Major blackout in the world
 
Standards
StandardsStandards
Standards
 
FFC-MM Plantsite Power System Protection
FFC-MM Plantsite Power System ProtectionFFC-MM Plantsite Power System Protection
FFC-MM Plantsite Power System Protection
 
SLD-LINE LENGTH-NAMEPLATE DETAILS OF 765/400/220KV EQUIPMENT DETAILS-TYPES OF...
SLD-LINE LENGTH-NAMEPLATE DETAILS OF 765/400/220KV EQUIPMENT DETAILS-TYPES OF...SLD-LINE LENGTH-NAMEPLATE DETAILS OF 765/400/220KV EQUIPMENT DETAILS-TYPES OF...
SLD-LINE LENGTH-NAMEPLATE DETAILS OF 765/400/220KV EQUIPMENT DETAILS-TYPES OF...
 

Similar to Major incidents throughout the world

PSA Anatomy of Blackouts
PSA Anatomy of BlackoutsPSA Anatomy of Blackouts
PSA Anatomy of Blackouts
Power System Operation
 
System Restoration lesson learned
System Restoration lesson learned System Restoration lesson learned
System Restoration lesson learned
Power System Operation
 
System Restoration
System RestorationSystem Restoration
System Restoration
Power System Operation
 
Darfield to Dunsandel and Beyond - The Development of the Ground Fault Neutra...
Darfield to Dunsandel and Beyond - The Development of the Ground Fault Neutra...Darfield to Dunsandel and Beyond - The Development of the Ground Fault Neutra...
Darfield to Dunsandel and Beyond - The Development of the Ground Fault Neutra...
Dennis Keen
 
Blackout white paper_by_ieee_pes_ad_comm_final_082504
Blackout white paper_by_ieee_pes_ad_comm_final_082504Blackout white paper_by_ieee_pes_ad_comm_final_082504
Blackout white paper_by_ieee_pes_ad_comm_final_082504
Shraddha Dwivedi
 
Brett Roberts - Some aspects of electrical power system protection in undergr...
Brett Roberts - Some aspects of electrical power system protection in undergr...Brett Roberts - Some aspects of electrical power system protection in undergr...
Brett Roberts - Some aspects of electrical power system protection in undergr...
NSW Environment and Planning
 
Not our fault! - earth faults, past, present, and future, and their mitigation
Not our fault! - earth faults, past, present, and future, and their mitigationNot our fault! - earth faults, past, present, and future, and their mitigation
Not our fault! - earth faults, past, present, and future, and their mitigation
Dennis Keen
 
NRC Meeting 512 - Power Uprate via Plutonium
NRC Meeting 512 - Power Uprate via PlutoniumNRC Meeting 512 - Power Uprate via Plutonium
NRC Meeting 512 - Power Uprate via Plutonium
syottovasikka
 
methods-to-improve-the-reliability-in-24kv-boscan-field-distribution-lines
methods-to-improve-the-reliability-in-24kv-boscan-field-distribution-linesmethods-to-improve-the-reliability-in-24kv-boscan-field-distribution-lines
methods-to-improve-the-reliability-in-24kv-boscan-field-distribution-lines
Jesus A Borjas P.E., California
 
Wide Area Blackouts Causes and Prevention
Wide Area Blackouts Causes and PreventionWide Area Blackouts Causes and Prevention
Wide Area Blackouts Causes and Prevention
Power System Operation
 
Determining Multiple Fault Ride-Through Requirements for Generating Systems i...
Determining Multiple Fault Ride-Through Requirements for Generating Systems i...Determining Multiple Fault Ride-Through Requirements for Generating Systems i...
Determining Multiple Fault Ride-Through Requirements for Generating Systems i...
Power System Operation
 
INTERIM SUMMARY REPORT ON THE ANALYSIS OF THE 19 SEPTEMBER 2008 INCIDENT AT T...
INTERIM SUMMARY REPORT ON THE ANALYSIS OF THE 19 SEPTEMBER 2008 INCIDENT AT T...INTERIM SUMMARY REPORT ON THE ANALYSIS OF THE 19 SEPTEMBER 2008 INCIDENT AT T...
INTERIM SUMMARY REPORT ON THE ANALYSIS OF THE 19 SEPTEMBER 2008 INCIDENT AT T...
Fausto Intilla
 
1 txh000247c0202 opr_lightning_protection_systems
1 txh000247c0202 opr_lightning_protection_systems1 txh000247c0202 opr_lightning_protection_systems
1 txh000247c0202 opr_lightning_protection_systems
Tra Thanh
 
Risks of Nuclear Ageing
Risks of Nuclear AgeingRisks of Nuclear Ageing
Risks of Nuclear Ageing
Oeko-Institut
 
High voltage truck protection and fire prevention Paul Edwards
High voltage truck protection and fire prevention   Paul EdwardsHigh voltage truck protection and fire prevention   Paul Edwards
High voltage truck protection and fire prevention Paul Edwards
NSW Environment and Planning
 
Electrical protection in mines John Ainsworth
Electrical protection in mines   John AinsworthElectrical protection in mines   John Ainsworth
Electrical protection in mines John Ainsworth
NSW Environment and Planning
 
Identifying SmartGrid Opportunities to Aid a Low-Carbon Future in the UK
Identifying SmartGrid Opportunities to Aid a Low-Carbon Future in the UKIdentifying SmartGrid Opportunities to Aid a Low-Carbon Future in the UK
Identifying SmartGrid Opportunities to Aid a Low-Carbon Future in the UK
IMDEA Energia
 
Abb helita external lightning protection
Abb helita external lightning protectionAbb helita external lightning protection
Abb helita external lightning protection
Tarek Aboukhadra
 
Michael Wood - Loader electric shocks, a case study
Michael Wood - Loader electric shocks, a case studyMichael Wood - Loader electric shocks, a case study
Michael Wood - Loader electric shocks, a case study
NSW Environment and Planning
 
Mini grid design manual
Mini grid design manualMini grid design manual
Mini grid design manual
SolarReference
 

Similar to Major incidents throughout the world (20)

PSA Anatomy of Blackouts
PSA Anatomy of BlackoutsPSA Anatomy of Blackouts
PSA Anatomy of Blackouts
 
System Restoration lesson learned
System Restoration lesson learned System Restoration lesson learned
System Restoration lesson learned
 
System Restoration
System RestorationSystem Restoration
System Restoration
 
Darfield to Dunsandel and Beyond - The Development of the Ground Fault Neutra...
Darfield to Dunsandel and Beyond - The Development of the Ground Fault Neutra...Darfield to Dunsandel and Beyond - The Development of the Ground Fault Neutra...
Darfield to Dunsandel and Beyond - The Development of the Ground Fault Neutra...
 
Blackout white paper_by_ieee_pes_ad_comm_final_082504
Blackout white paper_by_ieee_pes_ad_comm_final_082504Blackout white paper_by_ieee_pes_ad_comm_final_082504
Blackout white paper_by_ieee_pes_ad_comm_final_082504
 
Brett Roberts - Some aspects of electrical power system protection in undergr...
Brett Roberts - Some aspects of electrical power system protection in undergr...Brett Roberts - Some aspects of electrical power system protection in undergr...
Brett Roberts - Some aspects of electrical power system protection in undergr...
 
Not our fault! - earth faults, past, present, and future, and their mitigation
Not our fault! - earth faults, past, present, and future, and their mitigationNot our fault! - earth faults, past, present, and future, and their mitigation
Not our fault! - earth faults, past, present, and future, and their mitigation
 
NRC Meeting 512 - Power Uprate via Plutonium
NRC Meeting 512 - Power Uprate via PlutoniumNRC Meeting 512 - Power Uprate via Plutonium
NRC Meeting 512 - Power Uprate via Plutonium
 
methods-to-improve-the-reliability-in-24kv-boscan-field-distribution-lines
methods-to-improve-the-reliability-in-24kv-boscan-field-distribution-linesmethods-to-improve-the-reliability-in-24kv-boscan-field-distribution-lines
methods-to-improve-the-reliability-in-24kv-boscan-field-distribution-lines
 
Wide Area Blackouts Causes and Prevention
Wide Area Blackouts Causes and PreventionWide Area Blackouts Causes and Prevention
Wide Area Blackouts Causes and Prevention
 
Determining Multiple Fault Ride-Through Requirements for Generating Systems i...
Determining Multiple Fault Ride-Through Requirements for Generating Systems i...Determining Multiple Fault Ride-Through Requirements for Generating Systems i...
Determining Multiple Fault Ride-Through Requirements for Generating Systems i...
 
INTERIM SUMMARY REPORT ON THE ANALYSIS OF THE 19 SEPTEMBER 2008 INCIDENT AT T...
INTERIM SUMMARY REPORT ON THE ANALYSIS OF THE 19 SEPTEMBER 2008 INCIDENT AT T...INTERIM SUMMARY REPORT ON THE ANALYSIS OF THE 19 SEPTEMBER 2008 INCIDENT AT T...
INTERIM SUMMARY REPORT ON THE ANALYSIS OF THE 19 SEPTEMBER 2008 INCIDENT AT T...
 
1 txh000247c0202 opr_lightning_protection_systems
1 txh000247c0202 opr_lightning_protection_systems1 txh000247c0202 opr_lightning_protection_systems
1 txh000247c0202 opr_lightning_protection_systems
 
Risks of Nuclear Ageing
Risks of Nuclear AgeingRisks of Nuclear Ageing
Risks of Nuclear Ageing
 
High voltage truck protection and fire prevention Paul Edwards
High voltage truck protection and fire prevention   Paul EdwardsHigh voltage truck protection and fire prevention   Paul Edwards
High voltage truck protection and fire prevention Paul Edwards
 
Electrical protection in mines John Ainsworth
Electrical protection in mines   John AinsworthElectrical protection in mines   John Ainsworth
Electrical protection in mines John Ainsworth
 
Identifying SmartGrid Opportunities to Aid a Low-Carbon Future in the UK
Identifying SmartGrid Opportunities to Aid a Low-Carbon Future in the UKIdentifying SmartGrid Opportunities to Aid a Low-Carbon Future in the UK
Identifying SmartGrid Opportunities to Aid a Low-Carbon Future in the UK
 
Abb helita external lightning protection
Abb helita external lightning protectionAbb helita external lightning protection
Abb helita external lightning protection
 
Michael Wood - Loader electric shocks, a case study
Michael Wood - Loader electric shocks, a case studyMichael Wood - Loader electric shocks, a case study
Michael Wood - Loader electric shocks, a case study
 
Mini grid design manual
Mini grid design manualMini grid design manual
Mini grid design manual
 

More from Power System Operation

ENERGY TRANSITION OUTLOOK 2021
ENERGY TRANSITION OUTLOOK  2021ENERGY TRANSITION OUTLOOK  2021
ENERGY TRANSITION OUTLOOK 2021
Power System Operation
 
Thermography test of electrical panels
Thermography test of electrical panelsThermography test of electrical panels
Thermography test of electrical panels
Power System Operation
 
What does peak shaving mean
What does peak shaving meanWhat does peak shaving mean
What does peak shaving mean
Power System Operation
 
What's short circuit level
What's short circuit levelWhat's short circuit level
What's short circuit level
Power System Operation
 
Power System Restoration Guide
Power System Restoration Guide  Power System Restoration Guide
Power System Restoration Guide
Power System Operation
 
Big Data Analytics for Power Grid Operations
Big Data Analytics for Power Grid OperationsBig Data Analytics for Power Grid Operations
Big Data Analytics for Power Grid Operations
Power System Operation
 
SPS to RAS Special Protection Scheme Remedial Action Scheme
SPS to RAS Special Protection Scheme  Remedial Action SchemeSPS to RAS Special Protection Scheme  Remedial Action Scheme
SPS to RAS Special Protection Scheme Remedial Action Scheme
Power System Operation
 
Substation Neutral Earthing
Substation Neutral EarthingSubstation Neutral Earthing
Substation Neutral Earthing
Power System Operation
 
SVC PLUS Frequency Stabilizer Frequency and voltage support for dynamic grid...
SVC PLUS Frequency Stabilizer Frequency and voltage support for  dynamic grid...SVC PLUS Frequency Stabilizer Frequency and voltage support for  dynamic grid...
SVC PLUS Frequency Stabilizer Frequency and voltage support for dynamic grid...
Power System Operation
 
Principles & Testing Methods Of Earth Ground Resistance
Principles & Testing Methods Of Earth Ground ResistancePrinciples & Testing Methods Of Earth Ground Resistance
Principles & Testing Methods Of Earth Ground Resistance
Power System Operation
 
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)
Power System Operation
 
Electrical Transmission Tower Types - Design & Parts
Electrical Transmission Tower  Types - Design & PartsElectrical Transmission Tower  Types - Design & Parts
Electrical Transmission Tower Types - Design & Parts
Power System Operation
 
What is load management
What is load managementWhat is load management
What is load management
Power System Operation
 
What does merit order mean
What does merit order meanWhat does merit order mean
What does merit order mean
Power System Operation
 
What are Balancing Services ?
What are  Balancing Services ?What are  Balancing Services ?
What are Balancing Services ?
Power System Operation
 
The Need for Enhanced Power System Modelling Techniques & Simulation Tools
The Need for Enhanced  Power System  Modelling Techniques  &  Simulation Tools The Need for Enhanced  Power System  Modelling Techniques  &  Simulation Tools
The Need for Enhanced Power System Modelling Techniques & Simulation Tools
Power System Operation
 
Power Quality Trends in the Transition to Carbon-Free Electrical Energy System
Power Quality  Trends in the Transition to  Carbon-Free Electrical Energy SystemPower Quality  Trends in the Transition to  Carbon-Free Electrical Energy System
Power Quality Trends in the Transition to Carbon-Free Electrical Energy System
Power System Operation
 
Power Purchase Agreement PPA
Power Purchase Agreement PPA Power Purchase Agreement PPA
Power Purchase Agreement PPA
Power System Operation
 
Harmonic study and analysis
Harmonic study and analysisHarmonic study and analysis
Harmonic study and analysis
Power System Operation
 
What is leakage current testing
What is leakage current testingWhat is leakage current testing
What is leakage current testing
Power System Operation
 

More from Power System Operation (20)

ENERGY TRANSITION OUTLOOK 2021
ENERGY TRANSITION OUTLOOK  2021ENERGY TRANSITION OUTLOOK  2021
ENERGY TRANSITION OUTLOOK 2021
 
Thermography test of electrical panels
Thermography test of electrical panelsThermography test of electrical panels
Thermography test of electrical panels
 
What does peak shaving mean
What does peak shaving meanWhat does peak shaving mean
What does peak shaving mean
 
What's short circuit level
What's short circuit levelWhat's short circuit level
What's short circuit level
 
Power System Restoration Guide
Power System Restoration Guide  Power System Restoration Guide
Power System Restoration Guide
 
Big Data Analytics for Power Grid Operations
Big Data Analytics for Power Grid OperationsBig Data Analytics for Power Grid Operations
Big Data Analytics for Power Grid Operations
 
SPS to RAS Special Protection Scheme Remedial Action Scheme
SPS to RAS Special Protection Scheme  Remedial Action SchemeSPS to RAS Special Protection Scheme  Remedial Action Scheme
SPS to RAS Special Protection Scheme Remedial Action Scheme
 
Substation Neutral Earthing
Substation Neutral EarthingSubstation Neutral Earthing
Substation Neutral Earthing
 
SVC PLUS Frequency Stabilizer Frequency and voltage support for dynamic grid...
SVC PLUS Frequency Stabilizer Frequency and voltage support for  dynamic grid...SVC PLUS Frequency Stabilizer Frequency and voltage support for  dynamic grid...
SVC PLUS Frequency Stabilizer Frequency and voltage support for dynamic grid...
 
Principles & Testing Methods Of Earth Ground Resistance
Principles & Testing Methods Of Earth Ground ResistancePrinciples & Testing Methods Of Earth Ground Resistance
Principles & Testing Methods Of Earth Ground Resistance
 
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)
 
Electrical Transmission Tower Types - Design & Parts
Electrical Transmission Tower  Types - Design & PartsElectrical Transmission Tower  Types - Design & Parts
Electrical Transmission Tower Types - Design & Parts
 
What is load management
What is load managementWhat is load management
What is load management
 
What does merit order mean
What does merit order meanWhat does merit order mean
What does merit order mean
 
What are Balancing Services ?
What are  Balancing Services ?What are  Balancing Services ?
What are Balancing Services ?
 
The Need for Enhanced Power System Modelling Techniques & Simulation Tools
The Need for Enhanced  Power System  Modelling Techniques  &  Simulation Tools The Need for Enhanced  Power System  Modelling Techniques  &  Simulation Tools
The Need for Enhanced Power System Modelling Techniques & Simulation Tools
 
Power Quality Trends in the Transition to Carbon-Free Electrical Energy System
Power Quality  Trends in the Transition to  Carbon-Free Electrical Energy SystemPower Quality  Trends in the Transition to  Carbon-Free Electrical Energy System
Power Quality Trends in the Transition to Carbon-Free Electrical Energy System
 
Power Purchase Agreement PPA
Power Purchase Agreement PPA Power Purchase Agreement PPA
Power Purchase Agreement PPA
 
Harmonic study and analysis
Harmonic study and analysisHarmonic study and analysis
Harmonic study and analysis
 
What is leakage current testing
What is leakage current testingWhat is leakage current testing
What is leakage current testing
 

Recently uploaded

132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
co23btech11018
 
VARIABLE FREQUENCY DRIVE. VFDs are widely used in industrial applications for...
VARIABLE FREQUENCY DRIVE. VFDs are widely used in industrial applications for...VARIABLE FREQUENCY DRIVE. VFDs are widely used in industrial applications for...
VARIABLE FREQUENCY DRIVE. VFDs are widely used in industrial applications for...
PIMR BHOPAL
 
AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...
AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...
AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...
Paris Salesforce Developer Group
 
Generative AI Use cases applications solutions and implementation.pdf
Generative AI Use cases applications solutions and implementation.pdfGenerative AI Use cases applications solutions and implementation.pdf
Generative AI Use cases applications solutions and implementation.pdf
mahaffeycheryld
 
Object Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOADObject Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOAD
PreethaV16
 
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
upoux
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
Design and optimization of ion propulsion drone
Design and optimization of ion propulsion droneDesign and optimization of ion propulsion drone
Design and optimization of ion propulsion drone
bjmsejournal
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
ijaia
 
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
Gino153088
 
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
shadow0702a
 
Applications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdfApplications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdf
Atif Razi
 
Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...
Prakhyath Rai
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
IJECEIAES
 
Software Engineering and Project Management - Software Testing + Agile Method...
Software Engineering and Project Management - Software Testing + Agile Method...Software Engineering and Project Management - Software Testing + Agile Method...
Software Engineering and Project Management - Software Testing + Agile Method...
Prakhyath Rai
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
ecqow
 
ITSM Integration with MuleSoft.pptx
ITSM  Integration with MuleSoft.pptxITSM  Integration with MuleSoft.pptx
ITSM Integration with MuleSoft.pptx
VANDANAMOHANGOUDA
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
VICTOR MAESTRE RAMIREZ
 
Engineering Standards Wiring methods.pdf
Engineering Standards Wiring methods.pdfEngineering Standards Wiring methods.pdf
Engineering Standards Wiring methods.pdf
edwin408357
 

Recently uploaded (20)

132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
 
VARIABLE FREQUENCY DRIVE. VFDs are widely used in industrial applications for...
VARIABLE FREQUENCY DRIVE. VFDs are widely used in industrial applications for...VARIABLE FREQUENCY DRIVE. VFDs are widely used in industrial applications for...
VARIABLE FREQUENCY DRIVE. VFDs are widely used in industrial applications for...
 
AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...
AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...
AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...
 
Generative AI Use cases applications solutions and implementation.pdf
Generative AI Use cases applications solutions and implementation.pdfGenerative AI Use cases applications solutions and implementation.pdf
Generative AI Use cases applications solutions and implementation.pdf
 
Object Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOADObject Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOAD
 
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
Design and optimization of ion propulsion drone
Design and optimization of ion propulsion droneDesign and optimization of ion propulsion drone
Design and optimization of ion propulsion drone
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
 
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
 
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
 
Applications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdfApplications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdf
 
Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
 
Software Engineering and Project Management - Software Testing + Agile Method...
Software Engineering and Project Management - Software Testing + Agile Method...Software Engineering and Project Management - Software Testing + Agile Method...
Software Engineering and Project Management - Software Testing + Agile Method...
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
 
ITSM Integration with MuleSoft.pptx
ITSM  Integration with MuleSoft.pptxITSM  Integration with MuleSoft.pptx
ITSM Integration with MuleSoft.pptx
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
 
Engineering Standards Wiring methods.pdf
Engineering Standards Wiring methods.pdfEngineering Standards Wiring methods.pdf
Engineering Standards Wiring methods.pdf
 

Major incidents throughout the world

  • 1. ©RTE 2004 A.4.1 Introduction A.4.2 France: incident of 19 December 1978 A.4.3 France: incident of 12 January 1987 A.4.4 Quebec: incident of 18 April 1988 A.4.5 Italy: incident of 24 August 1994 A.4.6 United States: major power failures of summer 1996 A.4.7 Major power failures of 2003 251 A4 Annex 4 Major incidents throughout the world A4 Annex 4 Major incidents throughout the world
  • 2. ©RTE 2004 252 EDF - Cordemais fossil-fired power plant
  • 3. ©RTE 2004 253 Annex 4 - Major incidents throughout the worldA A.4.1 INTRODUCTION Power system operating reliability is a constant challenge. Despite the existing lines of defence at the level of the different power systems, the latter are not shielded from widespread incidents, leading to large-scale customer load shedding operations. No-one has forgotten the incident that the French system sustained on 19 December 1978, when 75% of national load was affected. This incident, not a recent one to be sure, is the most serious that EDF has experienced since the end of the post-war period of shortage. Less than a decade later, the incident of 12 January 1987, initiated by the successive tripping of the generation units at Cordemais, near Nantes, where the power supply to the west of France was interrupted, was a reminder to power system operators to be watchful. Since then, several other widespread incidents have occurred all over the world and deprived millions of customers of electricity. Particular mention can be made of the sizeable power failures that hit Quebec in 1988, the southern half of Italy in 1994, the west of the United States in 1996 and, more recently, the incidents in 2003 which affected the eastern part of the United States and Canada, as well as southern Switzerland and the whole of Italy. These events remind us how more or less important anomalies in the system of defence can combine to seriously jeopardise System reliability, due to the four phenomena described in § 2.3 and often a combination of them: - cascade tripping, - voltage collapse, - frequency collapse, - loss of synchronism. Analysing how some of these major incidents occurred helps illustrate these phenomena and gain a better understanding of their causes. Although the defence systems and the measures taken by the various companies differ, an in-depth look at these incidents and the succession of events that led to the total or partial collapse of the network generally provides many lessons about malfunctions that arose on the lines of defence set up, as well as on the improvements that it would be advisable to make.
  • 4. ©RTE 2004 254 Part of the French grid still live at 8.26 a.m. on 19 December 1978 immediately after the first collapse Voltage trend on the 400 kV grid in the west of France during the incident of 12 January 1987 BELGIUM MERY MARMAGNE BAYET EGUZON TRICASTIN GERMANY SWITZERLAND ITALY SPAIN Voltage t (min)
  • 5. ©RTE 2004 255 A A.4.2 FRANCE: INCIDENT OF 19 DECEMBER 1978 (CASCADE OVERLOADS AND COLLAPSE OF MOST OF THE NETWORK) On a day that was cold and overcast, the load escalation proved to be more rapid and higher than forecast (38,500 MW dispatched). All available generating facilities were used to the maximum of their possibilities (active and reactive) and over 3,500 MW were imported from neighbouring countries, mainly Germany. The rise of the load increased the already high transits, from the east to the Paris region and, as a result, voltages turned out to be extremely low in a large part of the network (Paris region, west). Starting at 8 a.m., overloads were observed on the grid and, at 8.06 a.m., an alarm "overload 20 minutes" appeared on the Bézaumont-Creney 400 kV line in the east of France. Despite various switching operations on the network topology, this overload was unable to be reduced and the line tripped due to the action of its protection at 8.26 a.m. Upon load transfer, three 225 kV lines tripped due to overload.The four generation units at Revin were subsequently disconnected from the grid (due to their current protection). A 400 kV interconnection with Belgium then tripped and the voltage dropped further.The tripping (hard to explain) of a new 400 kV interconnection with Belgium was accompanied by a further voltage drop and the loss of stability of a large part of the grid.The next phase witnessed the opening of lines and tripping of generation units (notably due to their voltage minimum and frequency minimum protection devices). Isolated sub-networks formed, where the generation-load balance could not be restored (insufficient load shedding, generation unit outages). 75% of consumers were disconnected, although the south-eastern part of France and areas in the vicinity of the northern and eastern borders remained connected. Many generation units did not successfully trip to house load. An initial power restoration was too rapid and led to a further collapse of the network at 9.08 a.m. A more careful recovery, relying on hydro generation units and imported power permitted almost complete network restoration at about midday. Customers sustained power cuts lasting between 30 minutes and 10 hours. This incident, resulting from a tight management of the network (high transits and low voltages in some areas) and a cascade of overloads, clearly showed that the defence plan at that time was unable to cope: automatic load shedding operations were insufficient, the tripping of generation units occurred too soon on voltage minimum criteria and the dividing up of the network was not successful. Service restoration was also not satisfactory. A great many actions were undertaken after this incident to improve all these deficient areas. Annex 4 - Major incidents throughout the world
  • 6. 256 ©RTE 2004 A A.4.3 FRANCE: INCIDENT OF 12 JANUARY 1987 (VOLTAGE COLLAPSE AND POWER CUTS IN THE WEST) Although 12 January was a particularly cold day (the "extreme cold" alert had been sent out since the previous Friday), all available generation units started up and managed to ensure a satisfactory generation margin (5,900 MW) and normal voltage in the west (405 kV at Cordemais). Then, in the space of a single hour, from 10.55 to 11.42 a.m., Cordemais generation units 1, 2 and 3 broke down due to independent causes (failure of a sensor, explosion of an electric coupler pole, shutdown due to a fire). The last unit available, which would have been sufficient to maintain the voltage in the zone, tripped as a result of inappropriate adjustment of the maximum rotor current protection and the disturbance created by the outage of unit n° 3. The loss of Cordemais generation led to a sudden drop of voltage to 380 kV in the area. It stabilised for about 30 seconds, but the automatic on-load tap changers of the 225 kV/HV and HV/MV transformers, while attempting to restore a normal voltage, triggered a rise in load and the voltage again began to drop quickly. In a matter of minutes, nine thermal generation units near the area tripped successively, giving rise to a loss of power of 9,000 MW and maintaining the voltage downward trend. Load shedding was then carried out and, at 11.50 a.m., the voltage steadied, but at a very low level in the west, less than 300 kV. In view of this extremely precarious situation, which jeopardised the national grid, the dispatching centre decided to shed a load of 1,500 MW in Brittany and the region of Angers, bringing the network voltage back to its normal level. As of noon, the situation was well under control and the voltage of the network could now be restored. It would be lengthy because of the difficulty in reconnecting a sufficient number of generation units close to Brittany and Normandy, which did not trip to house load during the incident. It took until night- time to fully restore the power supply to these regions, when two and subsequently three generation units were again in operation at Cordemais. At the most serious time, the outages reached a capacity of about 8,000 MW. The main cause of this incident can be attributed to a lack of quality of adjustment of some System components, in particular of the voltage regulators and associated protection devices of generation units.The corresponding functions are now dealt with under quality assurance. The automation of some actions (blocking of on-load tap changers), the reduction of load shedding execution time (by means of remote load shedding) also appeared indispensable following this incident. Annex 4 - Major incidents throughout the world
  • 7. ©RTE 2004 A.4.4 QUEBEC: INCIDENT OF 18 APRIL 1988 (LOAD SHEDDING OUTAGE AND COMPLETE COLLAPSE OF THE NETWORK) All day long on 18 April 1988, a strong storm beat down on the northern coast of Quebec. In the evening, at about 8.10 p.m., a series of short-circuits, due to snow and ice covering insulators, occurred at the Arnaud 735 kV substation, causing the separation of the Churchill Falls power plant from the Hydro- Québec network.The network load at that time was 18,500 MW (to which must be added 2,600 MW in exports to neighbouring grids) and the power generated by Churchill Falls 3,800 MW. The safety automatic control devices intended to initiate load shedding did not work. The Chamouchuane-Saguenay line tripped in a matter of seconds following the start of the incident. Other generation units tripped in turn and the whole network collapsed like a house of cards. Load restoration took a total of over 8 hours. QUEBEC: 18/04/88 A Annex 4 - Major incidents throughout the world 257 COMPLEXE LA GRANDE CHURCHILL ARNAUD CHAMOUCHOUANE SAGENAY QUEBECAREA MONTREALAREA 2,600 MW TOTHE UNITED STATES
  • 8. 258 ©RTE 2004 A At 8.30 a.m. the next day, a similar fault occurred, again depriving the grid of power from Churchill Falls. Fortunately, the remote load shedding automatic control device had been repaired during the night and worked correctly this time, avoiding a further collapse of the network. Although different customers had to be cut off in turn for five hours to shed a load of 600 MW, this operation helped confine the event. Of course, the Quebec power system is quite different from the French system. This incident nevertheless highlights the determining role played by customer load shedding actions so as to limit the extension of major incidents. These actions serve to supplement the fundamental action of the frequency primary control installed on the generation units, the purpose of which is to reduce the imbalance between and generation and load and avoid the collapse of the frequency (and of the network). In similar cases, cutting off a few customers very rapidly can avoid losing all of them and facilitate restoring supply to those who had been disconnected due to the initial incident. A relatively similar incident occurred in Egypt on 24 April 1994, where the much weaker action than expected of the frequency load shedding led to the complete collapse of the network. A.4.5 ITALY: INCIDENT OF 24 AUGUST 1994 (SEPARATION OF THE NETWORK AND COLLAPSE IN THE SOUTH) The incident of 24 August 1994, at 11.28 a.m., in southern Italy, occurred in a degraded operation situation during which the operators had decided not to comply with the "N-1" principle in view of external conditions considered as propitious: summer period, favourable weather conditions. The connections linking southern Italy to northern Italy (Rome South) were made up of (cf. map): - a 400 kV line Latina - Garigliano, - a 400 kV lineValmontone - Presenzano, - a 400 kV lineVillanova - Foggia, - and a 225 kV line Popoli - Capriati. Generation aspect: - the three generation units of the Brindisi North power plant (each with a unit capacity of 300 MW) were limited to 220 MW each owing to cooling water temperature problems.The Brindisi South power plant (four 600 MW generation units) was not allowed to operate; - for the same reasons, the Rossano power plant (four 300 MW generation sets) was limited to 170 MW per unit. Annex 4 - Major incidents throughout the world
  • 9. ©RTE 2004 During the night of 23 to 24 August 1994, a current transformer of the Latina - Garigliano 400 kV line exploded at Latina, damaging the circuit breakers of other 400 kV lines, notably those of the outgoing feeders toValmontone and RomeWest. The Rome South - Latina line was shut down for works. At 11.28 a.m. on 24August, a fire beneath theValmontone - Presenzano line caused this connection to trip. High oscillations between the north and south of Italy were observed.The Villanova - Foggia 400 kV and Popoli - Capriati 225 kV lines then tripped, likely due to overload or loss of synchronism, bringing about the formation of an insufficient separate network in southern Italy. The frequency variation within this network was about 2 Hz per second, or even higher, which probably made part of the load shedding frequency drift relays ineffective and led to the outage of all generation on this network. This incident caused customers to be cut off (about 4,500 MW) for a period of from two to two and a half hours. Even if the Italian network is not so fully meshed as the French grid, the operating conditions which our transalpine colleagues have to face are not very different from those encountered at certain periods on the French network near the Mediterranean.They highlight in particular the importance of the "N-1" rule. Roma/O Brindisi/S Brindisi/N Roma/S Latina Garigliano Presenzano Villanova Popoli Valmontone Capriati Foggia Rossano ITALY ITALY: 24/08/94 A Annex 4 - Major incidents throughout the world 259
  • 10. 260 ©RTE 2004 A A.4.6 UNITED STATES: MAJOR POWER FAILURES OF SUMMER 1996 Three major incidents affected the American western network in the summer of 1996, causing its partial break-up and cutting off millions of customers. It all began on 2 July, in the early afternoon, by a single-phase fault -electric arc due to contact with a tree- on one of the three 345 kV lines which transmit electricity from the Jim Bridger power plant inWyoming (four generation units, total capacity 2,000 MW) to the State of ldaho (cf. map).This incident occurred when temperatures are very high in the west of the United States and when loads and transits between different States are therefore substantial. During the fault clearance sequence, a second line transmitting power from the plant tripped due to a faulty protection operation.To avoid the overload of the last remaining line, a programmable logic controller shut down 1,000 MW of power plant output. This immediately brought about a considerable voltage drop in Idaho and initiated a slower voltage drop with oscillations on Pacific Inertie, made up of all the 500 kV AC and DC interconnection lines linking the North-West (Washington-Oregon) to the South-West (California). Twenty-four seconds later, the long Mill Creek-Antelope line tripped due to overload because of the inappropriate setting of its distance protective system and, in a matter of seconds, triggered a voltage drop in Oregon. The incident then became widespread and a cascade of trippings led to the formation of five separate networks. Thirty-five seconds after the initial fault, two million customers, representing 12 GW of power, found themselves without electricity. On 3 July, this incident occurred again in the same way, but remained confined to the Boise region, thanks to the load shedding command issued by the control centre. On 10 August, a similar incident took place, cutting off 7.5 million customers representing a load of about 30 GW. Several factors are the cause of these incidents: - system operation at the maximum limits, - faulty maintenance (pruning, protective devices), - poor performance of generation units under transient operating conditions, - insufficient exchange of information between partners at the forecast level, - poor quality of setting of some protective devices. Annex 4 - Major incidents throughout the world
  • 11. 261 ©RTE 2004 A report was submitted to the President of the United States, defining five main lines of progress together with action plans: - ensure the responsibility of all sectors; - place stress on System reliability; - improve information on power system reliability; - extend the scope of the analyses; - enhance the professionalism of all those concerned. On the other hand, these incidents showed that dividing up the networks was an efficient measure to avoid complete collapse and facilitate service restoration. UNITED STATES: 2 July 1996 A Annex 4 - Major incidents throughout the world
  • 12. 262 ©RTE 2004 A A.4.6 MAJOR POWER FAILURES OF 2003 A number of incident occurrences in 2003 highlighted the issues of security of supply and of the reliability of power systems. Concerning the first issue, the revolving load shedding operations that Italy experienced on 26 June 2003, confirming the California crisis in 2000-2001, show how failures inescapably occur when generation and transmission capacities no longer match the load to be supplied. As for the issue of effective operating reliability, it is illustrated by the two spectacular power failures presented hereafter. A.4.7.1 THE AMERICAN INCIDENT (UNITED STATES AND CANADA) OF 14 AUGUST 2003 This power failure affected the Eastern Interconnection (one of the three synchronous zones of the United States) and part of Canada.The grid concerned stretches from Dakota to the East coast. Its organisation is complex. Supervised by the operator Midwest ISO, it is intersected by networks covered by PJM. A report on the incident referred to the grid as a "Swiss cheese network". The situation before the incident was said to be sound, although the voltages were low on First Energy’s network, while remaining above acceptable minimum values (0.92 pu). The load was high (air conditioning), but the operators managed to cope with more constraining situations on the previous days. However, several control centres sustained information system failures, which hampered the assessment of the risks run and the reaction of the operators. At 2.02 p.m., the Stuart - Atlanta 345 kV line tripped due to a contact with a tree, causing a short-circuit to ground, and locked out.This fact of little importance in itself was to disrupt a state estimator then in the course of reactivation. From 3.05 to 3.41 p.m., three 345 kV lines connecting the northern and eastern parts of Ohio tripped due to electric arcs between these lines and the surrounding vegetation. The substantial load transfers and weakening of the voltage plan brought about the tripping of lines and generation units which, as of 4.10 p.m., occurred successively at intervals of a few seconds. A transit loop was created from Pennsylvania to NewYork State, then Ontario and Michigan, so as to get around the missing links. The Eastern Interconnection network cut itself off along an east-west line.The south remained unaffected, but the now isolated north was to sustain new separations and collapse completely at 4.13 p.m., except for a few islands where the performance of generation units and load shedding operations managed to save the situation. Annex 4 - Major incidents throughout the world
  • 13. 263 A ©RTE 2004 Service restoration was difficult; 19 hours after the incident, 20% of the load still had to be re-supplied.Two days were needed to restore supply to some parts of the United States, owing in particular to problems in restarting some generation units. The incident affected a total of 50 million people and resulted in the loss of about 62,000 MW in load in seven American states and Ontario. The investigation commission attributed the collapse to the combination of: - an inadequate assessment of the degraded state of the network at First Energy; - the application of criteria unsuited to the risks of collapse of First Energy’s system; - a lack in dealing with pruning requirements at First Energy; - the failure of the organisations responsible for the safety of the interconnected network to make a diagnosis in real time. A.4.7.2 THE SWITZERLAND - ITALY INCIDENT OF 28 SEPTEMBER 2003 The incident occurred at around 3 a.m., when Italy had a high import balance and when the exchange capacity with Switzerland and the rest of Europe was saturated. The Mettlen - Lavorgo 380 kV line in Switzerland was 86% loaded. According to the reliability studies carried out by the operator ETRANS, the outage of this line would require curative actions within 15 minutes, including actions to be carried out by the Italian system operator GRTN. At 3.01 a.m., there was an electric arc between the line and the surrounding vegetation and subsequent tripping; reclosing proved to be impossible due to a too wide transmission angle (42°). Because of a load transfer, another Swiss line went over to overload. In 24 minutes time, it came into contact with a tree and tripped. The incident then got out of control with, in a matter of seconds, the tripping of another Swiss line due to overload and the automatic disconnection of the Lienz - Soverzene line connecting Switzerland and Austria. Italy sustained loss of synchronism and was separated from the rest of the European grid through the action of distance protection devices on the cross-border lines: considering the low voltages and high currents, the impedances measured by these protection devices correspond to the tripping criteria. In Italy, the frequency immediately fell to 49.1 Hz and the voltage collapsed. Some generating facilities connected to the distribution networks tripped, followed by 21 of the 50 main generation units connected to the transmission network. Frequency load shedding was unable to save the situation; 2mn30s after the separation, the Italian network was completely dead. Annex 4 - Major incidents throughout the world
  • 14. 264 ©RTE 2004 An aerial view of Europe during the Italian black-out of 28 September 2003
  • 15. 265 A In the rest of the UCTE network, the frequency rose, but steadied at 50.2 Hz through the action of automatic primary and secondary frequency controls. Despite the tripping of some generation units, the incident was contained thanks to the mostly appropriate reaction of the various power system components and players. Italy’s gradual reconnection with its neighbouring countries from 4.05 a.m. to 12.45 p.m. allowed the progressive resumption of imports and network restoration, from 6 a.m. to 4 p.m. Re-supplying some southern areas took about twenty hours. Globally, the collapse affected 57 million people, with a power failure of 28,000 MW lasting several hours. A.4.7.3 LESSONS DRAWN FROM THE INCIDENTS OF 2003 Feedback from these new incidents has shown the following noteworthy points: - the way reliability is controlled may differ depending on whether theTSO is in charge of the transmission infrastructures (case of France) or not (case of Italy now and of the United States); - the need to affirm the TSO’s role as conductor, particularly in the most extreme situations where its orders must be executed without discussion and delay; - the indispensable nature of the independence of TSOs with respect to the other players of the market; - the need for an adapted reliability reference guide, in its different dimensions: directives, laws, regulatory provisions, technical reference guide applying to theTSO as to the other players (producers, distributors, consumers, traders, etc.); - the importance of the contractual relations between the TSO and the producers, distributors and consumers, which require compliance with the reliability provisions from the stage of connection to the grid to that of control, by clearly stipulating the commitments of each party and the means of monitoring these commitments; - finally, the absolute necessity for strong coordination between TSOs, at the different time scales concerned. ©RTE 2004 Annex 4 - Major incidents throughout the world