Power system operating reliability is a constant challenge. Despite the existing
lines of defence at the level of the different power systems, the latter are not
shielded from widespread incidents, leading to large-scale customer load
shedding operations.
No-one has forgotten the incident that the French system sustained on 19
December 1978, when 75% of national load was affected. This incident, not a
recent one to be sure, is the most serious that EDF has experienced since the
end of the post-war period of shortage.
Less than a decade later, the incident of 12 January 1987, initiated by the
successive tripping of the generation units at Cordemais, near Nantes, where
the power supply to the west of France was interrupted, was a reminder to
power system operators to be watchful.
Since then, several other widespread incidents have occurred all over the world
and deprived millions of customers of electricity. Particular mention can be
made of the sizeable power failures that hit Quebec in 1988, the southern half
of Italy in 1994, the west of the United States in 1996 and, more recently, the
incidents in 2003 which affected the eastern part of the United States and
Canada, as well as southern Switzerland and the whole of Italy.
In 1895 the Westinghouse Company completed the construction of the Niagara Falls
power station with a capacity of roughly 7.5 megawatts, produced from hydro turbines,
using patents and designs by Nikola Tesla. The following year General Electric, who had
been awarded the contract for the transmission and distribution lines, completed the
transmission system necessary to carry the power to the nearby city of Buffalo. This
polyphase ac system was perhaps the greatest of its time and one of the first true power
systems in the world. Today the North American power system spans the countries of the
United States, Canada and Mexico. This system incorporates tens of thousands of
transmission lines, generating stations, transformers, complex power electronic
transmission equipment, and a myriad of automatic control and protection systems which
keep this vastly complex system operating twenty-four hours a day, seven days a week,
year after year.
The document summarizes standards for insulation levels of power system equipment. It includes tables outlining basic lightning impulse insulation levels (BIL) and wet switching impulse levels for transformers, circuit breakers, bushings and cables at different voltage classes. It also lists creepage distances and withstand voltage test requirements specified by standards like IEEE and IEC.
In early days, there was a little demand for electrical energy so that small power stations were built to supply lighting and heating loads. However, the widespread use of electrical energy by modern civilisation has necessitated to produce bulk electrical energy economically and efficiently.
The increased demand of electrical energy can be met by building big power stations at favourable places where fuel (coal or gas) or water energy is available in abundance.
This document provides an overview of a 469MW combined cycle power plant located in Samalkot, India. It describes the plant's capacity and inputs/outputs. The plant uses a combination of gas and steam cycles with two gas turbines and one steam turbine. It also includes details on the electrical equipment such as generators, transformers, circuit breakers and isolators. Protection schemes, ratings, and alternative systems such as diesel generators and UPS systems are covered as well.
MCP202x - LIN Transceivers with Voltage RegulatorPremier Farnell
The document introduces the MCP202x LIN transceivers from Microchip. It provides an overview of LIN networks and the key features of the MCP202x transceivers, including a built-in voltage regulator, ESD protection, and various protection modes. Applications for the MCP202x transceivers include automotive, industrial, and medical devices that require LIN network connectivity and voltage regulation.
This document provides an electrical one-line diagram for a multi-floor commercial building. It shows the locations and ratings of electrical equipment including utility transformers and meters, switchboards, panelboards, generators, and other components. Electrical equipment is shown on each floor and electrical rooms are labeled. Notes provide information on equipment specifications and installation requirements.
Electric fault at forsmark nuclear power plantAbdul Soomro
The document summarizes a electrical fault event that occurred at the Forsmark Unit 1 nuclear power plant in Sweden on July 25, 2005. The fault caused a grid voltage fluctuation that tripped the main generator circuit breakers, disconnecting the plant from the grid. This led to overvoltage transients that caused two uninterruptible power supply systems to fail. This in turn prevented two of the four emergency diesel generators from connecting to their buses, reducing safety systems availability. The reactor scrammed safely and was cooled down over 30 minutes. The event was rated a level 2 on the International Nuclear Event Scale due to potential common cause failure of all generators.
Power Supplies for Electric Motor Driven Fire PumpsJames S Nasby
www.Lucky-Bet.site => Bet on Sports - 50% Deposit Bonus
www.Lucky-Bet.site/casino => Online Casino - 5000$ Welcome Bonus
www.Lucky-Bet.site/lotto247 => Lotto247 - Win Big, Live Free
www.Lucky-Bet.site/eurobet => Best European Bookmaker
www.earnperhit.com/essay => Professional academic writing
Requirements and Application Information.
Both NFPA-20 and Article 695 of NFPA-70 (NEC) are covered.
In 1895 the Westinghouse Company completed the construction of the Niagara Falls
power station with a capacity of roughly 7.5 megawatts, produced from hydro turbines,
using patents and designs by Nikola Tesla. The following year General Electric, who had
been awarded the contract for the transmission and distribution lines, completed the
transmission system necessary to carry the power to the nearby city of Buffalo. This
polyphase ac system was perhaps the greatest of its time and one of the first true power
systems in the world. Today the North American power system spans the countries of the
United States, Canada and Mexico. This system incorporates tens of thousands of
transmission lines, generating stations, transformers, complex power electronic
transmission equipment, and a myriad of automatic control and protection systems which
keep this vastly complex system operating twenty-four hours a day, seven days a week,
year after year.
The document summarizes standards for insulation levels of power system equipment. It includes tables outlining basic lightning impulse insulation levels (BIL) and wet switching impulse levels for transformers, circuit breakers, bushings and cables at different voltage classes. It also lists creepage distances and withstand voltage test requirements specified by standards like IEEE and IEC.
In early days, there was a little demand for electrical energy so that small power stations were built to supply lighting and heating loads. However, the widespread use of electrical energy by modern civilisation has necessitated to produce bulk electrical energy economically and efficiently.
The increased demand of electrical energy can be met by building big power stations at favourable places where fuel (coal or gas) or water energy is available in abundance.
This document provides an overview of a 469MW combined cycle power plant located in Samalkot, India. It describes the plant's capacity and inputs/outputs. The plant uses a combination of gas and steam cycles with two gas turbines and one steam turbine. It also includes details on the electrical equipment such as generators, transformers, circuit breakers and isolators. Protection schemes, ratings, and alternative systems such as diesel generators and UPS systems are covered as well.
MCP202x - LIN Transceivers with Voltage RegulatorPremier Farnell
The document introduces the MCP202x LIN transceivers from Microchip. It provides an overview of LIN networks and the key features of the MCP202x transceivers, including a built-in voltage regulator, ESD protection, and various protection modes. Applications for the MCP202x transceivers include automotive, industrial, and medical devices that require LIN network connectivity and voltage regulation.
This document provides an electrical one-line diagram for a multi-floor commercial building. It shows the locations and ratings of electrical equipment including utility transformers and meters, switchboards, panelboards, generators, and other components. Electrical equipment is shown on each floor and electrical rooms are labeled. Notes provide information on equipment specifications and installation requirements.
Electric fault at forsmark nuclear power plantAbdul Soomro
The document summarizes a electrical fault event that occurred at the Forsmark Unit 1 nuclear power plant in Sweden on July 25, 2005. The fault caused a grid voltage fluctuation that tripped the main generator circuit breakers, disconnecting the plant from the grid. This led to overvoltage transients that caused two uninterruptible power supply systems to fail. This in turn prevented two of the four emergency diesel generators from connecting to their buses, reducing safety systems availability. The reactor scrammed safely and was cooled down over 30 minutes. The event was rated a level 2 on the International Nuclear Event Scale due to potential common cause failure of all generators.
Power Supplies for Electric Motor Driven Fire PumpsJames S Nasby
www.Lucky-Bet.site => Bet on Sports - 50% Deposit Bonus
www.Lucky-Bet.site/casino => Online Casino - 5000$ Welcome Bonus
www.Lucky-Bet.site/lotto247 => Lotto247 - Win Big, Live Free
www.Lucky-Bet.site/eurobet => Best European Bookmaker
www.earnperhit.com/essay => Professional academic writing
Requirements and Application Information.
Both NFPA-20 and Article 695 of NFPA-70 (NEC) are covered.
This document outlines the design of a 400kV transmission network from Karuma to Tororo in Uganda. It discusses Uganda's energy policy goals of increasing transmission voltages. Distance and overcurrent relay protection schemes were designed for the transmission lines, transformers, and busbars. Settings were calculated and tables of results presented. Challenges obtaining information from the transmission company and recommending further protection studies were described. The objectives of designing the transmission network and protection relay system were achieved.
The document discusses modifying two electric mining shovels to achieve Arc Flash Category 0 (CAT 0). It presents the single line diagram of one shovel and describes a three step analysis process to determine arc flash risks: 1) develop the single line diagram, 2) calculate fault currents, incident energies and isolation times using IEEE 1584, 3) determine mitigation measures to achieve CAT 0 at all locations. The modifications included adjusting protective device settings and selecting new equipment to reduce trip times in order to lower incident energy levels.
Power system stability issues and Defence Mechanism in Indian GridChandan Kumar
The document discusses various power system stability issues and remedial actions. It covers topics like frequency stability, angular stability, and voltage stability. It describes examples of instability events like lack of synchronizing torque leading to pole slip/out of step and lack of damping torque leading to low frequency oscillations. Remedial measures discussed include ensuring adequate reactive support, tuning power system stabilizers, and implementing special protection schemes. The document emphasizes the importance of maintaining power system stability through operational planning and controls.
The document discusses electrical installation in buildings. It begins by differentiating between single-phase and three-phase electrical supply, noting that three-phase is used for large buildings due to higher electrical loads. It then covers types of electrical wiring including open, hidden, and conduit wiring. Equipment used in electrical wiring such as fuses, earth circuits, and lightning conductors is also explained. Finally, common electrical symbols used in building plans are presented along with general safety guidelines for electrical work.
Electrical system design of garden project at belhaven (10 Storey High Rise B...Nithya Susan Varghese
High Rise Buildings require advanced System Design. Electrical System Design was done for a 10 storey building in Trivandrum. It included 2 floors for parking, 2 floors for Commercial purpose, 2 floors for Owner's Penthouse, and the remaining as residential apartments.
The document provides information about Kota Super Thermal Power Station (KSTPS) in Rajasthan, India. It discusses that KSTPS has a total installed capacity of 1240 MW and was the first coal-based power station in Rajasthan. KSTPS is designed in 5 stages with 7 units ranging from 110 MW to 195 MW each. The power station uses coal from nearby mines to generate steam which powers turbines connected to generators to produce electricity. Ash produced is utilized in building materials and construction. The control room monitors and regulates the power generation process.
This document discusses the analysis and design of a solar photovoltaic distributed generation system connected to the distribution network. It first introduces distributed generation and the advantages of integrating solar PV systems. It then describes the methodology used for optimally placing and sizing a solar PV system on the 33-bus and 69-bus test feeders to minimize power losses while improving voltage profiles. The results show that a 3.15 MW solar PV system placed at bus 6 of the 33-bus system reduces losses by 95.75 kW. Similarly, a 1.81 MW system at bus 61 of the 69-bus feeder reduces losses by 141.6 kW.
Fire Pumps, Controllers & Associated Electrical Distribution AspectsJames S Nasby
www.Lucky-Bet.site => Bet on Sports - 50% Deposit Bonus
www.Lucky-Bet.site/casino => Online Casino - 5000$ Welcome Bonus
www.Lucky-Bet.site/lotto247 => Lotto247 - Win Big, Live Free
www.Lucky-Bet.site/eurobet => Best European Bookmaker
www.earnperhit.com/essay => Professional academic writing
Electric Motor Driven Fire Pump Considerations
- Power Supply requirements of NFPA-20 - 2007
- NFPA-70 (NEC®) Article 695
- Changes to Articles 700 & 701 in the NEC
- Selective Coordination
- New §708 - Critical Operations Power Systems
- Junction boxes and wiring protective systems.
Basic Mechanical & Electrical Application in Construction IndustryHassanulHadiZakaria
Electricity is a form of energy produced by the movement of electrons through a conductor. It can be generated and stored in batteries, and is essential for powering appliances, heating homes, cooking, communication, and transportation. Electricity makes modern life more convenient, organized, and safe. It is typically generated as alternating current and transmitted long distances at high voltages before being stepped down for distribution to homes and businesses.
Size a circuit breaker for a fire pumpBassam Gomaa
1. The NEC establishes requirements to ensure continuous power for fire pumps, permitting an overcurrent device between a remote power source and fire pump controller. However, an instantaneous trip circuit breaker alone does not comply as it is an unlisted component without a short-circuit rating.
2. For a generator-backed fire pump, NEC 430.62 allows sizing the overcurrent device at 250% of the largest motor instead of locked rotor, then adding the full-load current of other motors.
3. Proper sizing of the overcurrent device for a generator-backed fire pump to comply with NEC 695.4(B) requires referencing NEC 430.62 for s
This document provides an index and overview of the layout of a substation.
1. The index lists 14 topics that will be covered, ranging from bus bars and isolators to transformers and circuit breakers.
2. The introduction explains that electric power is transmitted through a network of substations, which change characteristics of the electric supply like voltage.
3. Outdoor substations like the 220KV GSS Sanganer are described, which have one and half breaker schemes and feed power to locations like KTPS and Sakatpura.
The document discusses various power system stability issues and remedial actions. It covers four aspects of power system stability: frequency stability, angular stability, voltage stability, and issues related to renewable integration. For each stability aspect, it provides examples of potential instability events, such as pole slip due to delayed fault clearance. It also outlines remedial actions that can be taken, such as improving reactive support and protection coordination, to prevent or mitigate instability events. Overall, the document aims to educate about power system stability challenges and effective measures to maintain reliable grid operations.
This document summarizes several major blackouts that have occurred worldwide. It provides details on the number of people affected, location, duration and key causes and lessons learned from each event. Some of the major blackouts discussed include the Northeast Blackout of 1965 affecting 30 million people in the US and Canada for 12 hours due to human error. The Southern Brazil Blackout of 1999 left 97 million without power for 30 hours after a lightning strike caused protective systems to fail. The Northeast Blackout of 2003 was caused by inadequate grid monitoring and affected 55 million for 16 hours, highlighting the need for mandatory reliability standards.
This document discusses and compares international and North American electrical standards. It provides an overview of standards organizations like IEC, UL, and ANSI and their respective standards. Key points covered include test sequences defined in standards like IEC 947-2, UL 489, and ANSI C37-50. The document also outlines requirements for circuit breakers, like short circuit and overload testing, and notes both standards ensure safety while allowing for different cultural and historical approaches.
FFC-MM Plantsite Power System Protectionfarazrafi87
The document discusses protection coordination at an electrical substation. It provides an overview of protection coordination and selective coordination. It also details the data required for a coordination study including single line diagrams, system voltages, impedances, and fault current data. The document analyzes several fault scenarios and observations regarding protection coordination and makes recommendations for further audit and testing to improve coordination.
SLD-LINE LENGTH-NAMEPLATE DETAILS OF 765/400/220KV EQUIPMENT DETAILS-TYPES OF...Pavan choudhary
This document provides details about various high voltage equipment used in substations, including:
1) Single line diagrams showing 765kV and 400kV transmission lines and a one and a half breaker scheme.
2) Explanations of how protection systems like differential protection and line protection work using current transformers on breakers and isolators.
3) Descriptions of equipment like 400kV and 245kV circuit breakers, 800kV, 420kV, and 245kV current transformers, 765kV, 420kV, and 245kV isolators, and surge arrestors.
4) Technical specifications for the equipment such as voltage levels, current ratings, and
IIN 1895, THE WESTINGHOUSE COMPANY COMPLETED THE CONSTRUCTION OF THE NIAGARA
Falls power station with a capacity of roughly 7.5 MW, produced from hydro turbines, using patents and
designs by Nikola Tesla. The following year, General Electric, which had been awarded the contract for the
transmission and distribution lines, completed the transmission system necessary to carry the power to the
nearby city of Buffalo. This polyphase ac system was perhaps the greatest of its time and one of the first true
power systems in the world. Today, the North American power system spans the United States, Canada, and
Mexico. This system incorporates tens of thousands of transmission lines, generating stations, transformers,
complex power electronic transmission equipment, and myriad automatic control and protection systems
that keep this vastly complex system operating 24 hours a day, seven days a week, year after year. Similarly
vast and complex power systems span continental Europe, Asia, South America, and other parts of the
world. This constant delivery of electrical power is such an integral part of modern human life that it is, for
the most part, taken for granted until, suddenly and without prior warning, a blackout occurs, resulting in a
complete disruption of power supply to entire regions or countries!
A single transmission line from Niagara generating station tripped due to faulty relay setting
•
Within 2.5 seconds, five other transmission lines became overloaded and tripped, isolating 1,800 MW of generation at Niagara Station
‒
Generation then became unstable and tripped
•
Northeast became unstable and separated into islands within 4 seconds
•
Outages and islanding occurred throughout New York, Ontario, most of New England and parts of New Jersey and Pennsylvania
This document outlines the design of a 400kV transmission network from Karuma to Tororo in Uganda. It discusses Uganda's energy policy goals of increasing transmission voltages. Distance and overcurrent relay protection schemes were designed for the transmission lines, transformers, and busbars. Settings were calculated and tables of results presented. Challenges obtaining information from the transmission company and recommending further protection studies were described. The objectives of designing the transmission network and protection relay system were achieved.
The document discusses modifying two electric mining shovels to achieve Arc Flash Category 0 (CAT 0). It presents the single line diagram of one shovel and describes a three step analysis process to determine arc flash risks: 1) develop the single line diagram, 2) calculate fault currents, incident energies and isolation times using IEEE 1584, 3) determine mitigation measures to achieve CAT 0 at all locations. The modifications included adjusting protective device settings and selecting new equipment to reduce trip times in order to lower incident energy levels.
Power system stability issues and Defence Mechanism in Indian GridChandan Kumar
The document discusses various power system stability issues and remedial actions. It covers topics like frequency stability, angular stability, and voltage stability. It describes examples of instability events like lack of synchronizing torque leading to pole slip/out of step and lack of damping torque leading to low frequency oscillations. Remedial measures discussed include ensuring adequate reactive support, tuning power system stabilizers, and implementing special protection schemes. The document emphasizes the importance of maintaining power system stability through operational planning and controls.
The document discusses electrical installation in buildings. It begins by differentiating between single-phase and three-phase electrical supply, noting that three-phase is used for large buildings due to higher electrical loads. It then covers types of electrical wiring including open, hidden, and conduit wiring. Equipment used in electrical wiring such as fuses, earth circuits, and lightning conductors is also explained. Finally, common electrical symbols used in building plans are presented along with general safety guidelines for electrical work.
Electrical system design of garden project at belhaven (10 Storey High Rise B...Nithya Susan Varghese
High Rise Buildings require advanced System Design. Electrical System Design was done for a 10 storey building in Trivandrum. It included 2 floors for parking, 2 floors for Commercial purpose, 2 floors for Owner's Penthouse, and the remaining as residential apartments.
The document provides information about Kota Super Thermal Power Station (KSTPS) in Rajasthan, India. It discusses that KSTPS has a total installed capacity of 1240 MW and was the first coal-based power station in Rajasthan. KSTPS is designed in 5 stages with 7 units ranging from 110 MW to 195 MW each. The power station uses coal from nearby mines to generate steam which powers turbines connected to generators to produce electricity. Ash produced is utilized in building materials and construction. The control room monitors and regulates the power generation process.
This document discusses the analysis and design of a solar photovoltaic distributed generation system connected to the distribution network. It first introduces distributed generation and the advantages of integrating solar PV systems. It then describes the methodology used for optimally placing and sizing a solar PV system on the 33-bus and 69-bus test feeders to minimize power losses while improving voltage profiles. The results show that a 3.15 MW solar PV system placed at bus 6 of the 33-bus system reduces losses by 95.75 kW. Similarly, a 1.81 MW system at bus 61 of the 69-bus feeder reduces losses by 141.6 kW.
Fire Pumps, Controllers & Associated Electrical Distribution AspectsJames S Nasby
www.Lucky-Bet.site => Bet on Sports - 50% Deposit Bonus
www.Lucky-Bet.site/casino => Online Casino - 5000$ Welcome Bonus
www.Lucky-Bet.site/lotto247 => Lotto247 - Win Big, Live Free
www.Lucky-Bet.site/eurobet => Best European Bookmaker
www.earnperhit.com/essay => Professional academic writing
Electric Motor Driven Fire Pump Considerations
- Power Supply requirements of NFPA-20 - 2007
- NFPA-70 (NEC®) Article 695
- Changes to Articles 700 & 701 in the NEC
- Selective Coordination
- New §708 - Critical Operations Power Systems
- Junction boxes and wiring protective systems.
Basic Mechanical & Electrical Application in Construction IndustryHassanulHadiZakaria
Electricity is a form of energy produced by the movement of electrons through a conductor. It can be generated and stored in batteries, and is essential for powering appliances, heating homes, cooking, communication, and transportation. Electricity makes modern life more convenient, organized, and safe. It is typically generated as alternating current and transmitted long distances at high voltages before being stepped down for distribution to homes and businesses.
Size a circuit breaker for a fire pumpBassam Gomaa
1. The NEC establishes requirements to ensure continuous power for fire pumps, permitting an overcurrent device between a remote power source and fire pump controller. However, an instantaneous trip circuit breaker alone does not comply as it is an unlisted component without a short-circuit rating.
2. For a generator-backed fire pump, NEC 430.62 allows sizing the overcurrent device at 250% of the largest motor instead of locked rotor, then adding the full-load current of other motors.
3. Proper sizing of the overcurrent device for a generator-backed fire pump to comply with NEC 695.4(B) requires referencing NEC 430.62 for s
This document provides an index and overview of the layout of a substation.
1. The index lists 14 topics that will be covered, ranging from bus bars and isolators to transformers and circuit breakers.
2. The introduction explains that electric power is transmitted through a network of substations, which change characteristics of the electric supply like voltage.
3. Outdoor substations like the 220KV GSS Sanganer are described, which have one and half breaker schemes and feed power to locations like KTPS and Sakatpura.
The document discusses various power system stability issues and remedial actions. It covers four aspects of power system stability: frequency stability, angular stability, voltage stability, and issues related to renewable integration. For each stability aspect, it provides examples of potential instability events, such as pole slip due to delayed fault clearance. It also outlines remedial actions that can be taken, such as improving reactive support and protection coordination, to prevent or mitigate instability events. Overall, the document aims to educate about power system stability challenges and effective measures to maintain reliable grid operations.
This document summarizes several major blackouts that have occurred worldwide. It provides details on the number of people affected, location, duration and key causes and lessons learned from each event. Some of the major blackouts discussed include the Northeast Blackout of 1965 affecting 30 million people in the US and Canada for 12 hours due to human error. The Southern Brazil Blackout of 1999 left 97 million without power for 30 hours after a lightning strike caused protective systems to fail. The Northeast Blackout of 2003 was caused by inadequate grid monitoring and affected 55 million for 16 hours, highlighting the need for mandatory reliability standards.
This document discusses and compares international and North American electrical standards. It provides an overview of standards organizations like IEC, UL, and ANSI and their respective standards. Key points covered include test sequences defined in standards like IEC 947-2, UL 489, and ANSI C37-50. The document also outlines requirements for circuit breakers, like short circuit and overload testing, and notes both standards ensure safety while allowing for different cultural and historical approaches.
FFC-MM Plantsite Power System Protectionfarazrafi87
The document discusses protection coordination at an electrical substation. It provides an overview of protection coordination and selective coordination. It also details the data required for a coordination study including single line diagrams, system voltages, impedances, and fault current data. The document analyzes several fault scenarios and observations regarding protection coordination and makes recommendations for further audit and testing to improve coordination.
SLD-LINE LENGTH-NAMEPLATE DETAILS OF 765/400/220KV EQUIPMENT DETAILS-TYPES OF...Pavan choudhary
This document provides details about various high voltage equipment used in substations, including:
1) Single line diagrams showing 765kV and 400kV transmission lines and a one and a half breaker scheme.
2) Explanations of how protection systems like differential protection and line protection work using current transformers on breakers and isolators.
3) Descriptions of equipment like 400kV and 245kV circuit breakers, 800kV, 420kV, and 245kV current transformers, 765kV, 420kV, and 245kV isolators, and surge arrestors.
4) Technical specifications for the equipment such as voltage levels, current ratings, and
IIN 1895, THE WESTINGHOUSE COMPANY COMPLETED THE CONSTRUCTION OF THE NIAGARA
Falls power station with a capacity of roughly 7.5 MW, produced from hydro turbines, using patents and
designs by Nikola Tesla. The following year, General Electric, which had been awarded the contract for the
transmission and distribution lines, completed the transmission system necessary to carry the power to the
nearby city of Buffalo. This polyphase ac system was perhaps the greatest of its time and one of the first true
power systems in the world. Today, the North American power system spans the United States, Canada, and
Mexico. This system incorporates tens of thousands of transmission lines, generating stations, transformers,
complex power electronic transmission equipment, and myriad automatic control and protection systems
that keep this vastly complex system operating 24 hours a day, seven days a week, year after year. Similarly
vast and complex power systems span continental Europe, Asia, South America, and other parts of the
world. This constant delivery of electrical power is such an integral part of modern human life that it is, for
the most part, taken for granted until, suddenly and without prior warning, a blackout occurs, resulting in a
complete disruption of power supply to entire regions or countries!
A single transmission line from Niagara generating station tripped due to faulty relay setting
•
Within 2.5 seconds, five other transmission lines became overloaded and tripped, isolating 1,800 MW of generation at Niagara Station
‒
Generation then became unstable and tripped
•
Northeast became unstable and separated into islands within 4 seconds
•
Outages and islanding occurred throughout New York, Ontario, most of New England and parts of New Jersey and Pennsylvania
At the end of this module the Student will be able to:
•
Identify the different causes of some of the major blackouts that have occurred
•
Describe some of the actions that could have been taken to prevent the blackouts
•
Identify the effects significant blackouts have on society
Darfield to Dunsandel and Beyond - The Development of the Ground Fault Neutra...Dennis Keen
This document provides an overview of the development of ground fault neutralizers in New Zealand. It discusses how Orion NZ first implemented a ground fault neutralizer system in Darfield in 2007 using technology from Swedish Neutral. However, issues with high harmonic levels on Orion's network were discovered in 2007 that caused the system to allow cable re-striking. The document then outlines Orion's work with Swedish Neutral to develop solutions to compensate for harmonics and allow the continued safe use of the ground fault neutralizer technology. It provides context on the development of resonant earthing internationally and its advantages in reducing bushfire risks and maintaining supply during faults.
Blackout white paper_by_ieee_pes_ad_comm_final_082504Shraddha Dwivedi
The document summarizes presentations given at an IEEE panel session on major power grid blackouts in 2003 in North America and Europe. It describes the root causes of 3 major blackouts:
1) The August 2003 North American blackout affected 50 million people and was caused by inadequate system understanding, low situation awareness at FirstEnergy, poor vegetation management, and lack of coordination between reliability entities.
2) The September 2003 blackout in Sweden and Denmark was caused when maintenance outages reduced transmission capacity, then contingencies overloaded remaining lines, causing voltage collapse and separation of an unbalanced region.
3) The September 2003 Italian blackout was triggered by transmission line outages from weather that isolated Italy from power imports, causing
This document discusses some of the challenges of electrical power system protection in underground mining environments. It notes that underground mines have unique features like continuous cable installation/retraction, reliance on reticulated earth conductors, and risk of fault energy causing explosions. Some specific challenges mentioned include increasing X/R ratios from larger transformers which can exceed equipment ratings, outdated dashpot overload relays still in use, inadequate instantaneous settings on overload relays, and issues with protection coordination across multiple lines of protection involving earth fault limitation. Trailing cable semiconductive screens and repairs are also identified as potential risks if faults progress to phase-to-phase arcs.
Not our fault! - earth faults, past, present, and future, and their mitigationDennis Keen
This paper examines the technology development of different types of arc suppression coils, including dry and oil filled types. The tuning methods used including switched capacitances or reactance and moving coil types. How this method of earth fault protection compares with other methods and what options can be added to the arc suppression coil to improve the performance as an earth fault minimization system.
This paper also considers the wider electricity industry’s attitude to Arc Suppression Coils or Rapid Earth Fault Current Limiters (REFCL) and applications to safety including Earth Potential Rise (EPR) and induction effects. Mitigation of bush fires and forest fire risks and the use of REFCL’s in transmission and distribution systems up to 110kV. Also their application for generators, wind turbine and network systems to allow continued use in fault conditions whilst still maintaining public safety and minimising asset damage.
NRC Meeting 512 - Power Uprate via Plutoniumsyottovasikka
NRC 512th Meeting - Public discussion archive revealed with illustrations.
Read how Catastrophic failures due to uprating (adding Plutonium) cause only mild discussion. All 'Catastrophic' upratings rubber stamped by G.E. mules... Shaky control processes, including banal G.E. fraud - revealed. Causes no action...
Readability enhanced Public Domain documrent derived from NRC archives.
Nuclear Regulatory Commission http://www.nrc.gov/
1) The document discusses methods to improve reliability of 24kV distribution lines for an oil field in Venezuela that experience high failure rates due to lightning strikes and bird interactions.
2) Analysis found that 60% of failures were from lightning and 20% from birds, with most failures on distribution lines.
3) Proposed solutions included improving grounding, installing bird deterrents, and increasing load immunity through devices like reclosers and transient voltage surge suppressors.
4) Grounding improvements and bird deterrents installed in 2005 achieved successful initial results in reducing failures.
Wide area blackouts can occur due to natural causes, technical failures, human error, or terrorism. Major blackouts in recent history have affected millions of people across multiple countries. Key factors that increase blackout risk include the liberalization of electricity markets and increased use of renewable energy sources. An optimization model is presented that can divide a power network into sections to isolate potential faults and maximize power delivered during a blackout situation. The model has been tested on power grid test cases of varying sizes.
Determining Multiple Fault Ride-Through Requirements for Generating Systems i...Power System Operation
Enhanced standards have recently been implemented
in Australia’s National Electricity Market (NEM)
requiring utility-scale generation to remain connected
to the grid during and after a number of voltage
disturbances occurring in quick succession. These new
standards currently apply prospectively to all generation
technologies and aim to strike a balance between power
system security requirements and maintenance of plant
integrity.
The criteria forming the basis of an assessment against
the proposed requirements were:
• The total number of disturbances within pre-
defined sliding time windows (NF);
• The accumulated disturbance duration (Δt); and
• The sum of changes in voltage by the duration of
the disturbance (ΔV x Δt).
Power system modelling and analysis demonstrates
that these standards can be met by a range of new and
existing synchronous and inverter-connected generation
technologies accounting for their actual connection
points to the wider network. Specific advice on the
types of disturbances that should be investigated is also
provided, accounting for actual fault patterns observed
in transmission and distribution networks. These results
indicate that the standards are practical and achievable
with full consideration of limitations of the power
system and different generation technologies.
INTERIM SUMMARY REPORT ON THE ANALYSIS OF THE 19 SEPTEMBER 2008 INCIDENT AT T...Fausto Intilla
An electrical fault occurred in the LHC on September 19, 2008 during powering tests, resulting in damage to a magnet and the release of helium. An investigation found that an electrical arc developed and punctured the helium enclosure, causing a pressure rise and damage to surrounding magnets and equipment. Approximately 6 tons of helium was lost before systems could isolate the fault. Inspections found damage to insulation and contamination requiring the replacement of up to 5 quadrupoles and 24 dipoles. Recommendations to improve safety systems and reinforce structures were made to prevent future incidents from causing further damage.
This document provides information on OPR lightning protection systems, including:
- An overview of lightning mechanisms and how different lightning protection systems work.
- Descriptions of early streamer emission air terminals, single rod air terminals, meshed cages, and stretched wires.
- Details on how to perform risk analysis and technical studies to design a lightning protection system.
- The procedure for measuring the early streamer emission of air terminals according to industry standards.
- Information on surge protection devices to protect against indirect lightning effects.
- The importance of equipotential bonding and maintaining separation distances between the lightning protection system and building components.
Technical characteristics of ageing processes and their possible impacts on nuclear safety in Spain
Vortrag von S. Mohr und S. Kurth für Greenpeace, Valencia, November 2014
A high voltage truck caught fire while traveling to the dump. An investigation found arcing between cable phases due to cable rub caused by loose clamps. This likely occurred during maintenance work. To prevent future fires, corrective actions included standardizing cable and hose routing, separating high pressure lines further, and improving fire suppression systems. Key learnings were to educate maintainers on cable/hose rub risks, engage original equipment manufacturers to improve design, and focus on electrical/mechanical interface risks.
This document provides an overview of electrical protection in mines and quarries, with reference to the forthcoming Australian Standard HB 119 "Mines and Quarries Electrical Protection". It discusses key principles of protection including having a primary and independent back-up protection system with complete coverage. Protection is important for safety and depends on factors like dependability, coverage, and speed of fault clearance. Specialized training is required for protection work. Standards like AS 2067 and AS 3000 contain basic protection requirements.
Identifying SmartGrid Opportunities to Aid a Low-Carbon Future in the UKIMDEA Energia
This document discusses opportunities for a smart grid to aid a low-carbon future in the UK. It summarizes that by 2020, 35% of UK energy demand will be supplied by renewables and by 2030 the electricity system will be decarbonized while incorporating heat and transport sectors. A smart grid uses demand response and network technologies to provide flexibility instead of building redundant generation assets. The document outlines various transmission, distribution and demand-related issues that a smart grid could help address to enable high renewable penetration at lowest cost.
The document is a catalog describing ABB hélita® lightning protection systems. It provides information on lightning mechanisms, protection technologies like early streamer emission air terminals and meshed cages, standards, and installation procedures. Lightning protection systems aim to provide a preferred path for lightning to be conducted safely to ground to prevent damage to structures. Early streamer emission technology enhances the formation of upward streamers to better intercept downward lightning leaders. Meshed cages divide the lightning current over multiple conductors.
This document discusses electric shocks experienced by workers at Northparkes Mines from loader equipment. An investigation was conducted to understand the root causes and level of shock received in 3 incidents over 6 months. Modeling of cable breakage scenarios found the most likely breakage would result in a painful shock but not ventricular fibrillation. Preventative actions included raising cable replacement standards, implementing a cable management plan, and installing new switchgear panels compliant with relevant standards. The modeling also found shocks from unplugging an energized cable were caused by a phase imbalance and transient earth current. Clear isolation points and visual indicators were implemented to prevent future shocks from unplugging.
For direct download link, visit:
http://solarreference.com/what-you-need-to-design-rural-mini-grids/
The “Mini Grid Design Manual” would be useful to anyone wanting to design generation-to-house wiring systems for simple village level grids. With detailed theory as well as practical advice, it is very much relevant today as it was when published back in 2000.
Similar to Major incidents throughout the world (20)
The document provides highlights and key insights from the DNV Energy Transition Outlook 2021 report. It finds that:
1) Global emissions are not decreasing fast enough to meet Paris Agreement goals, and warming is projected to reach 2.3°C by 2100 despite renewable growth.
2) Electrification is surging, with renewables like solar and wind outcompeting other sources by 2030 and providing over 80% of power by 2050, supported by technologies like storage.
3) Energy efficiency gains lead to flat global energy demand after the 2030s, with a 2.4% annual improvement in energy intensity outpacing economic growth.
Thermography test of electrical panels Thermography test of electrical panelThermography test of electrical panelThermography test of electrical panelThermography test of electrical panelThermography test of electrical panelThermography test of electrical panelThermography test of electrical panelThermography test of electrical panelThermography test of electrical panelThermography test of electrical panelThermography test of electrical panelThermography test of electrical panelThermography test of electrical panelThermography test of electrical panelThermography test of electrical panelThermography test of electrical panel
What does peak shaving meanWhat does peak shaving meanWhat does peak shaving meanWhat does peak shaving meanWhat does peak shaving meanWhat does peak shaving meanWhat does peak shaving meanWhat does peak shaving meanWhat does peak shaving meanWhat does peak shaving meanWhat does peak shaving meanWhat does peak shaving meanWhat does peak shaving meanWhat does peak shaving mean
Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide
Big data analytics Big data analyticsBig data analyticsBig data analyticsBig data analyticsBig data analyticsBig data analyticsBig data analyticsBig data analyticsBig data analyticsBig data analyticsBig data analyticsBig data analyticsBig data analyticsBig data analyticsBig data analyticsBig data analyticsBig data analyticsBig data analyticsBig data analytics
Special Protection Scheme Remedial Action Scheme
SPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action Scheme
SVC PLUS Frequency Stabilizer Frequency and voltage support for dynamic grid...Power System Operation
SVC PLUS
Frequency Stabilizer
Frequency and voltage support for dynamic grid stability
SVC PLUS Frequency Stabilizer FrequencySVC PLUS Frequency Stabilizer FrequencySVC PLUS Frequency Stabilizer FrequencySVC PLUS Frequency Stabilizer FrequencySVC PLUS Frequency Stabilizer FrequencySVC PLUS Frequency Stabilizer FrequencySVC PLUS Frequency Stabilizer FrequencySVC PLUS Frequency Stabilizer FrequencySVC PLUS Frequency Stabilizer FrequencySVC PLUS Frequency Stabilizer FrequencySVC PLUS Frequency Stabilizer FrequencySVC PLUS Frequency Stabilizer FrequencySVC PLUS Frequency Stabilizer FrequencySVC PLUS Frequency Stabilizer FrequencySVC PLUS Frequency Stabilizer FrequencySVC PLUS Frequency Stabilizer FrequencySVC PLUS Frequency Stabilizer FrequencySVC PLUS Frequency Stabilizer FrequencySVC PLUS Frequency Stabilizer FrequencySVC PLUS Frequency Stabilizer Frequency
What is load management What is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load management
What does merit order mean What does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order mean
Balancing services help maintain the frequency of the power grid by providing short-term energy or capacity reserves. They include balancing energy, which system operators use to maintain grid frequency, and balancing capacity, which providers agree to keep available. Different balancing services have varying activation speeds to respond to frequency deviations. Harmonization efforts in Europe are working to establish common balancing markets and platforms for cross-border exchange of reserves.
The Need for Enhanced Power System Modelling Techniques & Simulation Tools Power System Operation
The Need for Enhanced Power System Modelling Techniques & Simulation Tools The Need for Enhanced Power System Modelling Techniques The Need for Enhanced Power System Modelling Techniques & Simulation Tools The Need for Enhanced Power System Modelling Techniques & Simulation Tools & Simulation Tools
Power Quality Trends in the Transition to Carbon-Free Electrical Energy SystemPower System Operation
Power Quality
Trends in the Transition to
Carbon-Free Electrical Energy System Carbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy System
A Power Purchase Agreement (PPA) is a long-term contract between an electricity generator and purchaser that defines the conditions for the sale of electricity. PPAs provide price stability and help finance renewable energy projects by guaranteeing revenue. There are physical PPAs, which deliver electricity directly, and virtual PPAs, which financially settle the contract without physical delivery. PPAs benefit both renewable developers by enabling project financing, and buyers seeking long-term electricity price certainty and renewable attributes.
Harmonic study and analysis Harmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysis
What is leakage current testing What is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testing
VARIABLE FREQUENCY DRIVE. VFDs are widely used in industrial applications for...PIMR BHOPAL
Variable frequency drive .A Variable Frequency Drive (VFD) is an electronic device used to control the speed and torque of an electric motor by varying the frequency and voltage of its power supply. VFDs are widely used in industrial applications for motor control, providing significant energy savings and precise motor operation.
Build the Next Generation of Apps with the Einstein 1 Platform.
Rejoignez Philippe Ozil pour une session de workshops qui vous guidera à travers les détails de la plateforme Einstein 1, l'importance des données pour la création d'applications d'intelligence artificielle et les différents outils et technologies que Salesforce propose pour vous apporter tous les bénéfices de l'IA.
Generative AI Use cases applications solutions and implementation.pdfmahaffeycheryld
Generative AI solutions encompass a range of capabilities from content creation to complex problem-solving across industries. Implementing generative AI involves identifying specific business needs, developing tailored AI models using techniques like GANs and VAEs, and integrating these models into existing workflows. Data quality and continuous model refinement are crucial for effective implementation. Businesses must also consider ethical implications and ensure transparency in AI decision-making. Generative AI's implementation aims to enhance efficiency, creativity, and innovation by leveraging autonomous generation and sophisticated learning algorithms to meet diverse business challenges.
https://www.leewayhertz.com/generative-ai-use-cases-and-applications/
Embedded machine learning-based road conditions and driving behavior monitoringIJECEIAES
Car accident rates have increased in recent years, resulting in losses in human lives, properties, and other financial costs. An embedded machine learning-based system is developed to address this critical issue. The system can monitor road conditions, detect driving patterns, and identify aggressive driving behaviors. The system is based on neural networks trained on a comprehensive dataset of driving events, driving styles, and road conditions. The system effectively detects potential risks and helps mitigate the frequency and impact of accidents. The primary goal is to ensure the safety of drivers and vehicles. Collecting data involved gathering information on three key road events: normal street and normal drive, speed bumps, circular yellow speed bumps, and three aggressive driving actions: sudden start, sudden stop, and sudden entry. The gathered data is processed and analyzed using a machine learning system designed for limited power and memory devices. The developed system resulted in 91.9% accuracy, 93.6% precision, and 92% recall. The achieved inference time on an Arduino Nano 33 BLE Sense with a 32-bit CPU running at 64 MHz is 34 ms and requires 2.6 kB peak RAM and 139.9 kB program flash memory, making it suitable for resource-constrained embedded systems.
Design and optimization of ion propulsion dronebjmsejournal
Electric propulsion technology is widely used in many kinds of vehicles in recent years, and aircrafts are no exception. Technically, UAVs are electrically propelled but tend to produce a significant amount of noise and vibrations. Ion propulsion technology for drones is a potential solution to this problem. Ion propulsion technology is proven to be feasible in the earth’s atmosphere. The study presented in this article shows the design of EHD thrusters and power supply for ion propulsion drones along with performance optimization of high-voltage power supply for endurance in earth’s atmosphere.
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELijaia
As digital technology becomes more deeply embedded in power systems, protecting the communication
networks of Smart Grids (SG) has emerged as a critical concern. Distributed Network Protocol 3 (DNP3)
represents a multi-tiered application layer protocol extensively utilized in Supervisory Control and Data
Acquisition (SCADA)-based smart grids to facilitate real-time data gathering and control functionalities.
Robust Intrusion Detection Systems (IDS) are necessary for early threat detection and mitigation because
of the interconnection of these networks, which makes them vulnerable to a variety of cyberattacks. To
solve this issue, this paper develops a hybrid Deep Learning (DL) model specifically designed for intrusion
detection in smart grids. The proposed approach is a combination of the Convolutional Neural Network
(CNN) and the Long-Short-Term Memory algorithms (LSTM). We employed a recent intrusion detection
dataset (DNP3), which focuses on unauthorized commands and Denial of Service (DoS) cyberattacks, to
train and test our model. The results of our experiments show that our CNN-LSTM method is much better
at finding smart grid intrusions than other deep learning algorithms used for classification. In addition,
our proposed approach improves accuracy, precision, recall, and F1 score, achieving a high detection
accuracy rate of 99.50%.
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...shadow0702a
This document serves as a comprehensive step-by-step guide on how to effectively use PyCharm for remote debugging of the Windows Subsystem for Linux (WSL) on a local Windows machine. It meticulously outlines several critical steps in the process, starting with the crucial task of enabling permissions, followed by the installation and configuration of WSL.
The guide then proceeds to explain how to set up the SSH service within the WSL environment, an integral part of the process. Alongside this, it also provides detailed instructions on how to modify the inbound rules of the Windows firewall to facilitate the process, ensuring that there are no connectivity issues that could potentially hinder the debugging process.
The document further emphasizes on the importance of checking the connection between the Windows and WSL environments, providing instructions on how to ensure that the connection is optimal and ready for remote debugging.
It also offers an in-depth guide on how to configure the WSL interpreter and files within the PyCharm environment. This is essential for ensuring that the debugging process is set up correctly and that the program can be run effectively within the WSL terminal.
Additionally, the document provides guidance on how to set up breakpoints for debugging, a fundamental aspect of the debugging process which allows the developer to stop the execution of their code at certain points and inspect their program at those stages.
Finally, the document concludes by providing a link to a reference blog. This blog offers additional information and guidance on configuring the remote Python interpreter in PyCharm, providing the reader with a well-rounded understanding of the process.
Applications of artificial Intelligence in Mechanical Engineering.pdfAtif Razi
Historically, mechanical engineering has relied heavily on human expertise and empirical methods to solve complex problems. With the introduction of computer-aided design (CAD) and finite element analysis (FEA), the field took its first steps towards digitization. These tools allowed engineers to simulate and analyze mechanical systems with greater accuracy and efficiency. However, the sheer volume of data generated by modern engineering systems and the increasing complexity of these systems have necessitated more advanced analytical tools, paving the way for AI.
AI offers the capability to process vast amounts of data, identify patterns, and make predictions with a level of speed and accuracy unattainable by traditional methods. This has profound implications for mechanical engineering, enabling more efficient design processes, predictive maintenance strategies, and optimized manufacturing operations. AI-driven tools can learn from historical data, adapt to new information, and continuously improve their performance, making them invaluable in tackling the multifaceted challenges of modern mechanical engineering.
Software Engineering and Project Management - Introduction, Modeling Concepts...Prakhyath Rai
Introduction, Modeling Concepts and Class Modeling: What is Object orientation? What is OO development? OO Themes; Evidence for usefulness of OO development; OO modeling history. Modeling
as Design technique: Modeling, abstraction, The Three models. Class Modeling: Object and Class Concept, Link and associations concepts, Generalization and Inheritance, A sample class model, Navigation of class models, and UML diagrams
Building the Analysis Models: Requirement Analysis, Analysis Model Approaches, Data modeling Concepts, Object Oriented Analysis, Scenario-Based Modeling, Flow-Oriented Modeling, class Based Modeling, Creating a Behavioral Model.
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...IJECEIAES
Climate change's impact on the planet forced the United Nations and governments to promote green energies and electric transportation. The deployments of photovoltaic (PV) and electric vehicle (EV) systems gained stronger momentum due to their numerous advantages over fossil fuel types. The advantages go beyond sustainability to reach financial support and stability. The work in this paper introduces the hybrid system between PV and EV to support industrial and commercial plants. This paper covers the theoretical framework of the proposed hybrid system including the required equation to complete the cost analysis when PV and EV are present. In addition, the proposed design diagram which sets the priorities and requirements of the system is presented. The proposed approach allows setup to advance their power stability, especially during power outages. The presented information supports researchers and plant owners to complete the necessary analysis while promoting the deployment of clean energy. The result of a case study that represents a dairy milk farmer supports the theoretical works and highlights its advanced benefits to existing plants. The short return on investment of the proposed approach supports the paper's novelty approach for the sustainable electrical system. In addition, the proposed system allows for an isolated power setup without the need for a transmission line which enhances the safety of the electrical network
Software Engineering and Project Management - Software Testing + Agile Method...Prakhyath Rai
Software Testing: A Strategic Approach to Software Testing, Strategic Issues, Test Strategies for Conventional Software, Test Strategies for Object -Oriented Software, Validation Testing, System Testing, The Art of Debugging.
Agile Methodology: Before Agile – Waterfall, Agile Development.