SlideShare a Scribd company logo
1 of 73
ANALYSIS AND DESIGN OF
SLOAR PHOTOVOLTAIC TYPE DG
CONNECTED TO DISTRIBUTION
SYSTEM
Presented By:
Dr. Satish Kansal
Department of Electrical Engineering
BHSBIET Lehragaga
Power Systems
2
Introduction
 Objective-to meet the demand at all the locations within
power network as economically and reliably as possible.
 Traditional electric power system- utilize the
conventional energy resources for electricity generation
 Operation-such traditional generation systems is based on
centralized control utility generators to deliver power to widely
dispersed users through an extensive transmission and
distribution network
 Present Environment- the justification for large central-station
plants is weakening due to depleting conventional energy
sources.
3
Distributed Generation
Distributed Generation (DG), a term commonly used for
small-scale generations, offer solution to many of these
new challenges
Recent developments in small renewable generation
technologies such as wind turbines, photovoltaic, fuel cells,
micro turbines and so on has drawn distribution utilities’
attention to possible changes in the distribution system
infrastructure.
4
 The DG’s can be characterized into different types as:
Type I: DG capable of injecting real power only, like
photovoltaic, fuel cells etc.
Type II: DG capable of injecting reactive power only, e.g. kvar
compensator, synchronous compensator, capacitors
etc.
Type III: DG capable of injecting both real and reactive power,
e.g. synchronous machines,
Type IV: DG capable of injecting real but consuming reactive
power, e.g. induction generators.
 CIGRE :Define DG as the generation, which has the
following characteristics
 Not centrally planned
 Not centrally dispatched at present
 Usually connected to the distribution networks
 Smaller then 50 MW.
 International Energy Agency (IEA) :
 serving a customer on-site
 providing support to a distribution network,
 connected to the grid
5
6
Distributed Generation
 Embedded Generations
 Disperse Generations
 depends upon many technologies
 depends upon many applications
 Increasing DG penetration- Growing share of
distributed generators (DGs)
 Policy initiatives to promote DG throughout the world
Advantages of DG Integration
 Reduction in line losses
 Improvement in voltage profile
 Deferred network extension
 Improvement in system efficiency
 Enhanced peak shaving capacity
 System reliability and security
7
Motivation for the Present Work
 India is fastest growing economics
 availability of quality supply is very crucial for the sustained growth
 Electricity demand increasing rapidly
 generating capacity in 1950 is 1,712 MW
 Presently 2,11,766.22 MW
 per capita per year only 860.72 kWh
 triple by 2020, with 6.3% annual growth.
9
 India is in power deficient state
 power deficiency is nearly 12.2% of peak demand.
 In UP, MP, Maharashtra, Bihar, and Punjab; it is more than 20%.
 results in power cuts, blackouts, etc.
 The above mentioned causes make the Distribution Generation from
fuel cells, wind turbines, photovoltaic and small/micro hydro plants
for continuous growth of the country.
10
11
Optimal Placement of
Photovoltaic Type DG
12
 DG supplying real power
 loss reduction and voltage profile improvement
 operational constraints
Optimal Placement of DG
13
LOCATION AND SIZING ISSUES
0
10
20
30
40
50
60
70
0102030405060708090100
0.005
0.01
0.015
0.02
0.025
0.03
0.035
0.04
0.045
0.05
0.055
Loss
(MW)
%DG Size Bus No.
Effect of size and location of DG on system loss
Approaches
14
 Analytical approach
 PSO Technique
 Analytical approach
 Optimal size of PV
 Optimal Location
Results and Discussions
 Test systems
 33-bus with total load of 3.72 MW and 2.3 MVAr
 69-bus with total load of 3.80 MW and 2.69 MVAr
 Beaver conductors
 base voltage is 12.66 kV.
15
16
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33
0
0.5
1
1.5
2
2.5
3
3.5
4
Bus Number
SizeofDGinMW
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33
0.1
0.12
0.14
0.16
0.18
0.2
0.22
Bus Number
LossinMW
Method
Optimum
location
Optimum DG size
(MW)
Power loss (KW)
Without
DG
With DG
Analytical Method Bus 6 3.15 210.97 115.2
PSO approach Bus 7 2.91 210.97 115.1
17
Power loss with and without DG for 33-bus system with constraints
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33
0.9
0.95
1
Bus Number
VoltageProfileinp.u.
With DG
Without DG
18
5 10 15 20 25 30 35 40 45 50 55 60 65 70
0
0.5
1
1.5
2
2.5
3
3.5
4
4.5
Bus Number
SizeofDGinMW
1 6 11 16 21 26 31 36 41 46 51 56 61 66 70
0.08
0.1
0.12
0.14
0.16
0.18
0.2
0.22
0.24
Bus Number
LossinMW
19
Method
Optimum
location
Optimum DG size
(MW)
Power loss (KW)
Without
DG
With DG
Analytical Method Bus 61 1.81 225 83.4
PSO approach Bus 61 1.81 225 83.4
Power loss with and without DG for 69-bus system with constraints
1 4 7 10 13 16 19 22 25 28 31 34 37 40 43 46 49 52 55 58 61 64 67 69
0.9
0.95
1
Bus Number
ViltageProfileinp.u.
With DG
Without DG
Conclusions
 minimize the real power loss.
 Improvement in voltage profile
 minimizing the DG size
20
Renewable and Non- Renewable
Energy Sources.
21
Energy Scenario In India
22
Energy source Estimated Potential Cumulative
Installed capacity/ number
Wind power 45,000 MW 18321.10 MW
Small Hydro
(upto 25 MW)
15,000 MW 3464.59 MW
Biomass Power 16,000 MW 1242.60 MW
Bagasse Cogeneration 3,500 MW 2199.33 MW
Waste to energy 2,700 MW 93.68 MW
Solar Power (SPV) ----- 1047.16 MW
Family size Biogas Plants 12 million 45.45 Lakh
Solar street lighting system ----- 1,19,634 nos.
Home lighting system ----- 6,03,307 nos.
Solar Lanterns ----- 7, 97,344 nos.
Solar photovoltaic power plants 2.92 MWp
Solar water heating systems 140 million m2
of collector area
5.63 Million m2 of collector area
Solar photovoltaic pumps ----- 7334 nos.
Biomass gasifiers ----- 153.04 MW
23
Table 1.1 Renewable Energy Potential in India AND actual progress achieved up to 30.11.2012
 Renewable sources already contribute to about 5% of
the total power generating capacity in the country.
 Prospects for renewable are steadily improving in India
(% of total installed capacity is expected to be 10% by
2020).
24
Solar power as a solution to the
Indian power scenario
25
Why Solar Renewable energy
Sources Preferred
26
Solar PV Applications in PUNJAB
27
Converting Solar Energy into
Electrical Energy
28
29
30
Small units in the kilowatt range.
Economical point of view less
aggressive .
No cost reduction
Covers a wide range from less than one Watt to
several megawatts.
more aggressive .
Its cost decreasing day by day
Photovoltaic Cell
 “Photo” meaning light.
 “voltaic,” which refers to producing electricity.
 A device that produces an electric reaction to light,
producing electricity.
 A typical PV cell made of crystalline silicon is 12
centimetres in diameter and 0.25 millimetres thick. In full
sunlight, it generates 4 amperes of direct current at 0.5
volts or 2 watts of electrical power.
31
Photovoltaic Module
 Cells are interconnected and their
electrical connections are then
sandwiched between a top layer of
glass or clear plastic and a lower
level of plastic or plastic and metal.
An outer frame is attached to
increase mechanical strength, and
to provide a way to mount the unit.
This package is called a "module" or
"panel".
32
Photovoltaic Modules Performance
33
Impact of solar radiation on V-I characteristic
curve of Photovoltaic Module
34
Impact of temperature on V-I
characteristic curve of Photovoltaic
Module
35
PHOTOVOLAIC ARRAY
36
Types of Solar Photovoltaic System
37
 Stand alone PV system
 Grid Connected PV Systems
 Hybrid System
Stand alone PV system
38
Grid Connected PV Systems
39
Hybrid System
40
Grid Connected PV Systems is
Preferred
 No use of battery reduces its capital cost
 More reliable than other PV system.
 To install Grid connected SPV system the
following points are taken into consideration
41
GRID CONNECTED SOLAR
PHOTOVOLTAIC SYSTEM
42
Grid Connected PV Systems
 Estimate the solar potential available
 Develop a system based on the potential estimations
made for a chosen area of 100, 200, 500 m².
 Annual energy generation by designed plant.
 In the last cost estimation of grid connected SPV power
plant to show whether it is economically viable or not.
43
Estimation of Solar Potential
 The solar radiation over different months measured.
 The diurnal variations, average monthly output , yearly
output are find out and related graphs are plot for
showing the variation in different season and time.
 Peak variation and possible plant rating also calculated.
44
How Solar Radiation measured
 Estimation the solar potential
 Reading of solar radiation of given site.
 It should have the ability to store the data which
it measure for at least three months.
45
METHODOLOGY
 Calculated the daily energy output and monthly
energy output for different months .
 For better understanding, the measured solar
radiation data sheet for the month of April 2010
has been given as a sample of Electrical
Engineering Department, IIT Roorkee site.
46
Time 9:00am
47
Time10:00am
48
Time11:00am and so on
49
Variations for April Month 2010
50
Variations for the month of Jan 2010 to Feb
2010
Variations for the month of
September to December 2010
52
Total Output
53
Daily & Monthly Energy Outputs
(Watt/ mtr²-hr)
54
Peak Variation and Possible Plant
Rating
55
Condition for Grid inter facing
 Phase sequence matching: For a three phase system
three phases should be 120 deg phase apart from each
other for both the system.
 Frequency matching : Frequency of the SPV system
should be same as grid. Generally grid is of 50 Hz
frequency capacity, now if SPV systems frequency is
slightly higher than grid frequency (0.1 to 0.5)
synchronization is possible but SPV system frequency
should not be less than grid frequency
 Voltage matching: Voltage level of both the system
should same, otherwise synchronization is not possible.
56
9 kWp Grid connected PV system
 Solar Panel Specification
57
Solar PV Power Plant Specification
58
Cost analysis for 9kWp SPV Grid
Connected Power Plant
 Total cost for 50 panels : Rs.14,40000/-
 Cost of 3-φ Inverter : Rs. 2,50000/-
 Cost of 3-φ step up Transformer : Rs. 2,00000/-
 Subtotal: Rs.18,90000/-
 Multiply the subtotal above by 0.2 (20%) to cover
balance of system cost. Cost Estimate for Balance of
System: (1890000 × 0.2) Rs. 3,78000/-.
 Total Estimated PV System Cost is Rs.22,68000/-.
59
Thanks
60
Illustration of PSO algorithm
This presentation is for the
understanding of PSO method applied
in DG Placement.
Step 1 : Initialize random values into particles which correspond to
bus numbers(or locations of DGs) and sizes to be kept at respective
locations of the chosen network
For Ex. Assume
 there are 3 DGs to be placed and
 the number of particles be 10
 33 bus data taken into consideration
then,
Note : All the values are assumed. They don't correspond to original values
Step 1 : Initialize random values into particles which correspond to
bus numbers(or locations of DGs) and sizes to be kept at respective
locations of the chosen network
For Ex. Assume
 there are 3 DGs to be placed and
 the number of particles be 10
 33 bus data taken into consideration
then,
Note : All the values are assumed. They don't correspond to original values
Locations of 3 DGs Sizes of 3 DGs
Step 1 : Initialize random values into particles which correspond to
bus numbers(or locations of DGs) and sizes to be kept at respective
locations of the chosen network
For Ex. Assume
 there are 3 DGs to be placed and
 the number of particles be 10
 33 bus data taken into consideration
then,
Note : All the values are assumed. They don't correspond to original values
Locations of 3 DGs Sizes of 3 DGs
10 Combinations
Or
10 particles
Step 1 : Initialize random values into particles which correspond to
bus numbers(or locations of DGs) and sizes to be kept at respective
locations of the chosen network
For Ex. Assume
 there are 3 DGs to be placed and
 the number of particles be 10
 33 bus data taken into consideration
then,
Note : All the values are assumed. They don't correspond to original values
1.1MW at 5th bus
Step 1 : Initialize random values into particles which correspond to
bus numbers(or locations of DGs) and sizes to be kept at respective
locations of the chosen network
For Ex. Assume
 there are 3 DGs to be placed and
 the number of particles be 10
 33 bus data taken into consideration
then,
Note : All the values are assumed. They don't correspond to original values
0.4MW at 4th bus
Step 1 : Initialize random values into particles which correspond to
bus numbers(or locations of DGs) and sizes to be kept at respective
locations of the chosen network
For Ex. Assume
 there are 3 DGs to be placed and
 the number of particles be 10
 33 bus data taken into consideration
then,
Note : All the values are assumed. They don't correspond to original values
2.1MW at 31st bus
Step 2 : For each Particle (or each combination of Buses), apply DG
sizes in the particle at locations given in the particle and calculate
loss using exact loss formula.
Sizes of
DGs
Locations of
DGs
Apply Exact
Loss equation PL = 0.132
Note : All the values are assumed. They don't correspond to original values
Step 2 : For each Particle (or each combination of Buses), apply DG
sizes in the particle at locations given in the particle and calculate
loss using exact loss formula.
Sizes of
DGs
Locations of
DGs
Apply Exact
Loss equation PL = 0.132
Note : All the values are assumed. They don't correspond to original values
Apply Exact
Loss equation PL = 0.114
Apply Exact
Loss equation PL = 0.122
Apply Exact
Loss equation PL = 0.199
. . .
. . .
. . .
. . .
. . .
. . .
. .
. . .
. . .
. . .
. . .
. . .
. . .
. .
Step 2 : For each Particle (or each combination of Buses), apply DG
sizes in the particle at locations given in the particle and calculate
loss using exact loss formula.
Note : All the values are assumed. They don't correspond to original values
Apply Exact
Loss equation PL = 0.114
Step 3 : Depending on the respective loss choose the minimum one as
global best.
update the personal best also.
Note : All the values are assumed. They don't correspond to original values
Assume That the following combination has the best value i.e. lowest
PL
Then,
Global
Best
Particle
Fitness of
Global
Best
Apply Exact
Loss equation PL = 0.114
Step 3 : Depending on the respective loss choose the minimum one as
global best.
update the personal best also.
Note : All the values are assumed. They don't correspond to original values
Global
Best
Particle
Fitness of
Global
Best
Apply Exact
Loss equation PL = 0.114
Personal Best is also updated similarly. The only change is that it is
compared to its own previous value of the respective Particle.
Step 4 : Update the velocities and positions of the Particles using PSO
update equations.
Note : All the values are assumed. They don't correspond to original values
After using
both
equations
and
updating,
The array
transforms
into
Step 5: Do steps 2,3,4 until the particles converge to a point where
Global best does not get updated.
Note : All the values are assumed. They don't correspond to original values

More Related Content

What's hot

Power systems voltage and power control
Power systems voltage and power controlPower systems voltage and power control
Power systems voltage and power controlCaner Göksel Sonuzun
 
Choice of converter configuration
Choice of converter configurationChoice of converter configuration
Choice of converter configurationjawaharramaya
 
Basic types of facts controllers
Basic types of facts controllersBasic types of facts controllers
Basic types of facts controllersAyyarao T S L V
 
Comparision of svc and statcom
Comparision of svc and statcomComparision of svc and statcom
Comparision of svc and statcomjawaharramaya
 
Input output , heat rate characteristics and Incremental cost
Input output , heat rate characteristics and Incremental costInput output , heat rate characteristics and Incremental cost
Input output , heat rate characteristics and Incremental costEklavya Sharma
 
Planning and modern trends in hvdc
Planning and modern trends in hvdcPlanning and modern trends in hvdc
Planning and modern trends in hvdcjawaharramaya
 
High Voltage Dc (HVDC) transmission
High Voltage Dc (HVDC) transmissionHigh Voltage Dc (HVDC) transmission
High Voltage Dc (HVDC) transmissionZunAib Ali
 
Classification of transmission lines
Classification of transmission linesClassification of transmission lines
Classification of transmission linesHamzaAbbas43
 
ENERGY EFFICIENT MOTORS
ENERGY EFFICIENT MOTORSENERGY EFFICIENT MOTORS
ENERGY EFFICIENT MOTORSArigela Harika
 
Underground cables
Underground cablesUnderground cables
Underground cablesAnu71
 
Power control and power flow analysis
Power control and power flow analysisPower control and power flow analysis
Power control and power flow analysisjawaharramaya
 
Bidding strategies in deregulated power market
Bidding strategies in deregulated power marketBidding strategies in deregulated power market
Bidding strategies in deregulated power marketGautham Reddy
 
DISTRIBUTED GENERATION TECHNOLOGIES
DISTRIBUTED GENERATION TECHNOLOGIESDISTRIBUTED GENERATION TECHNOLOGIES
DISTRIBUTED GENERATION TECHNOLOGIESEditor IJMTER
 
Island Detection and Control Techniques
Island Detection and Control Techniques Island Detection and Control Techniques
Island Detection and Control Techniques Tanveer Riaz
 

What's hot (20)

Power systems voltage and power control
Power systems voltage and power controlPower systems voltage and power control
Power systems voltage and power control
 
Unit commitment
Unit commitmentUnit commitment
Unit commitment
 
Electric power system
Electric power systemElectric power system
Electric power system
 
Choice of converter configuration
Choice of converter configurationChoice of converter configuration
Choice of converter configuration
 
Basic types of facts controllers
Basic types of facts controllersBasic types of facts controllers
Basic types of facts controllers
 
Comparision of svc and statcom
Comparision of svc and statcomComparision of svc and statcom
Comparision of svc and statcom
 
Input output , heat rate characteristics and Incremental cost
Input output , heat rate characteristics and Incremental costInput output , heat rate characteristics and Incremental cost
Input output , heat rate characteristics and Incremental cost
 
Planning and modern trends in hvdc
Planning and modern trends in hvdcPlanning and modern trends in hvdc
Planning and modern trends in hvdc
 
High Voltage Dc (HVDC) transmission
High Voltage Dc (HVDC) transmissionHigh Voltage Dc (HVDC) transmission
High Voltage Dc (HVDC) transmission
 
Power flow analysis
Power flow analysisPower flow analysis
Power flow analysis
 
Classification of transmission lines
Classification of transmission linesClassification of transmission lines
Classification of transmission lines
 
Net metering seminar
Net metering seminarNet metering seminar
Net metering seminar
 
ENERGY EFFICIENT MOTORS
ENERGY EFFICIENT MOTORSENERGY EFFICIENT MOTORS
ENERGY EFFICIENT MOTORS
 
Underground cables
Underground cablesUnderground cables
Underground cables
 
Power control and power flow analysis
Power control and power flow analysisPower control and power flow analysis
Power control and power flow analysis
 
Spinning reserve
Spinning reserveSpinning reserve
Spinning reserve
 
Bidding strategies in deregulated power market
Bidding strategies in deregulated power marketBidding strategies in deregulated power market
Bidding strategies in deregulated power market
 
DISTRIBUTED GENERATION TECHNOLOGIES
DISTRIBUTED GENERATION TECHNOLOGIESDISTRIBUTED GENERATION TECHNOLOGIES
DISTRIBUTED GENERATION TECHNOLOGIES
 
Island Detection and Control Techniques
Island Detection and Control Techniques Island Detection and Control Techniques
Island Detection and Control Techniques
 
load flow 1
 load flow 1 load flow 1
load flow 1
 

Similar to Power systems (2)

Reactive Power Sharing Droop Control Strategy for DG Units in an Islanded Mic...
Reactive Power Sharing Droop Control Strategy for DG Units in an Islanded Mic...Reactive Power Sharing Droop Control Strategy for DG Units in an Islanded Mic...
Reactive Power Sharing Droop Control Strategy for DG Units in an Islanded Mic...IJMTST Journal
 
Review of Maximum Power Point Tracking Based PV Array to Produce Electric Energy
Review of Maximum Power Point Tracking Based PV Array to Produce Electric EnergyReview of Maximum Power Point Tracking Based PV Array to Produce Electric Energy
Review of Maximum Power Point Tracking Based PV Array to Produce Electric EnergyIRJET Journal
 
OPTIMAL PLACEMENT OF DISTRIBUTED GENERATION FOR LOSS REDUCTION IN DISTRIBUTIO...
OPTIMAL PLACEMENT OF DISTRIBUTED GENERATION FOR LOSS REDUCTION IN DISTRIBUTIO...OPTIMAL PLACEMENT OF DISTRIBUTED GENERATION FOR LOSS REDUCTION IN DISTRIBUTIO...
OPTIMAL PLACEMENT OF DISTRIBUTED GENERATION FOR LOSS REDUCTION IN DISTRIBUTIO...ijiert bestjournal
 
ppt presentation solar.pptx
ppt presentation solar.pptxppt presentation solar.pptx
ppt presentation solar.pptxDavidStuart61
 
Paper id 25201442
Paper id 25201442Paper id 25201442
Paper id 25201442IJRAT
 
Implementation Of A High-Efficiency, High-Lifetime, And Low-Cost Converter Us...
Implementation Of A High-Efficiency, High-Lifetime, And Low-Cost Converter Us...Implementation Of A High-Efficiency, High-Lifetime, And Low-Cost Converter Us...
Implementation Of A High-Efficiency, High-Lifetime, And Low-Cost Converter Us...irjes
 
Simulation of dcdc converter
Simulation of dcdc converterSimulation of dcdc converter
Simulation of dcdc converterRajesh Pindoriya
 
Study and realization of dc micro-grid for remote areas.
Study and realization of dc micro-grid for remote areas.Study and realization of dc micro-grid for remote areas.
Study and realization of dc micro-grid for remote areas.Umair Hashmi
 
DC micro grid with distributed generation for rural electrification
DC micro grid with distributed generation for rural electrificationDC micro grid with distributed generation for rural electrification
DC micro grid with distributed generation for rural electrificationBrhamesh Alipuria
 
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWP
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWPIRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWP
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWPIRJET Journal
 
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWP
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWPIRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWP
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWPIRJET Journal
 
A Flexible AC Distribution System for a Microgrid with a Photovoltaic System ...
A Flexible AC Distribution System for a Microgrid with a Photovoltaic System ...A Flexible AC Distribution System for a Microgrid with a Photovoltaic System ...
A Flexible AC Distribution System for a Microgrid with a Photovoltaic System ...IJMTST Journal
 
PV to Grid Connected Cascaded T type Multilevel Inverter with Improved Harmon...
PV to Grid Connected Cascaded T type Multilevel Inverter with Improved Harmon...PV to Grid Connected Cascaded T type Multilevel Inverter with Improved Harmon...
PV to Grid Connected Cascaded T type Multilevel Inverter with Improved Harmon...ijtsrd
 
Analysis, Modeling and Implementation of Incremental Conductance Maximum Powe...
Analysis, Modeling and Implementation of Incremental Conductance Maximum Powe...Analysis, Modeling and Implementation of Incremental Conductance Maximum Powe...
Analysis, Modeling and Implementation of Incremental Conductance Maximum Powe...ijtsrd
 
IRJET- Simulation Analysis of Power Control using Droop Control Method in Ac-...
IRJET- Simulation Analysis of Power Control using Droop Control Method in Ac-...IRJET- Simulation Analysis of Power Control using Droop Control Method in Ac-...
IRJET- Simulation Analysis of Power Control using Droop Control Method in Ac-...IRJET Journal
 
IRJET- Simulation of Solar PV and DG based Hybrid Micro Grid
IRJET-  	  Simulation of Solar PV and DG based Hybrid Micro GridIRJET-  	  Simulation of Solar PV and DG based Hybrid Micro Grid
IRJET- Simulation of Solar PV and DG based Hybrid Micro GridIRJET Journal
 
25 KWp SOLAR POWER PLANT IN BIET
25 KWp SOLAR POWER PLANT IN BIET25 KWp SOLAR POWER PLANT IN BIET
25 KWp SOLAR POWER PLANT IN BIETsuraj chowdhury
 

Similar to Power systems (2) (20)

Power systems (1)
Power systems (1)Power systems (1)
Power systems (1)
 
Reactive Power Sharing Droop Control Strategy for DG Units in an Islanded Mic...
Reactive Power Sharing Droop Control Strategy for DG Units in an Islanded Mic...Reactive Power Sharing Droop Control Strategy for DG Units in an Islanded Mic...
Reactive Power Sharing Droop Control Strategy for DG Units in an Islanded Mic...
 
Review of Maximum Power Point Tracking Based PV Array to Produce Electric Energy
Review of Maximum Power Point Tracking Based PV Array to Produce Electric EnergyReview of Maximum Power Point Tracking Based PV Array to Produce Electric Energy
Review of Maximum Power Point Tracking Based PV Array to Produce Electric Energy
 
OPTIMAL PLACEMENT OF DISTRIBUTED GENERATION FOR LOSS REDUCTION IN DISTRIBUTIO...
OPTIMAL PLACEMENT OF DISTRIBUTED GENERATION FOR LOSS REDUCTION IN DISTRIBUTIO...OPTIMAL PLACEMENT OF DISTRIBUTED GENERATION FOR LOSS REDUCTION IN DISTRIBUTIO...
OPTIMAL PLACEMENT OF DISTRIBUTED GENERATION FOR LOSS REDUCTION IN DISTRIBUTIO...
 
ppt presentation solar.pptx
ppt presentation solar.pptxppt presentation solar.pptx
ppt presentation solar.pptx
 
Modeling and Simulation of Grid Connected PV Generation System Using Matlab/S...
Modeling and Simulation of Grid Connected PV Generation System Using Matlab/S...Modeling and Simulation of Grid Connected PV Generation System Using Matlab/S...
Modeling and Simulation of Grid Connected PV Generation System Using Matlab/S...
 
Paper id 25201442
Paper id 25201442Paper id 25201442
Paper id 25201442
 
Implementation Of A High-Efficiency, High-Lifetime, And Low-Cost Converter Us...
Implementation Of A High-Efficiency, High-Lifetime, And Low-Cost Converter Us...Implementation Of A High-Efficiency, High-Lifetime, And Low-Cost Converter Us...
Implementation Of A High-Efficiency, High-Lifetime, And Low-Cost Converter Us...
 
Simulation of dcdc converter
Simulation of dcdc converterSimulation of dcdc converter
Simulation of dcdc converter
 
Study and realization of dc micro-grid for remote areas.
Study and realization of dc micro-grid for remote areas.Study and realization of dc micro-grid for remote areas.
Study and realization of dc micro-grid for remote areas.
 
DC micro grid with distributed generation for rural electrification
DC micro grid with distributed generation for rural electrificationDC micro grid with distributed generation for rural electrification
DC micro grid with distributed generation for rural electrification
 
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWP
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWPIRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWP
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWP
 
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWP
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWPIRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWP
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWP
 
A Flexible AC Distribution System for a Microgrid with a Photovoltaic System ...
A Flexible AC Distribution System for a Microgrid with a Photovoltaic System ...A Flexible AC Distribution System for a Microgrid with a Photovoltaic System ...
A Flexible AC Distribution System for a Microgrid with a Photovoltaic System ...
 
PV to Grid Connected Cascaded T type Multilevel Inverter with Improved Harmon...
PV to Grid Connected Cascaded T type Multilevel Inverter with Improved Harmon...PV to Grid Connected Cascaded T type Multilevel Inverter with Improved Harmon...
PV to Grid Connected Cascaded T type Multilevel Inverter with Improved Harmon...
 
System efficiency prediction of a 1kW capacity grid-tied photovoltaic inverter
System efficiency prediction of a 1kW capacity grid-tied photovoltaic inverterSystem efficiency prediction of a 1kW capacity grid-tied photovoltaic inverter
System efficiency prediction of a 1kW capacity grid-tied photovoltaic inverter
 
Analysis, Modeling and Implementation of Incremental Conductance Maximum Powe...
Analysis, Modeling and Implementation of Incremental Conductance Maximum Powe...Analysis, Modeling and Implementation of Incremental Conductance Maximum Powe...
Analysis, Modeling and Implementation of Incremental Conductance Maximum Powe...
 
IRJET- Simulation Analysis of Power Control using Droop Control Method in Ac-...
IRJET- Simulation Analysis of Power Control using Droop Control Method in Ac-...IRJET- Simulation Analysis of Power Control using Droop Control Method in Ac-...
IRJET- Simulation Analysis of Power Control using Droop Control Method in Ac-...
 
IRJET- Simulation of Solar PV and DG based Hybrid Micro Grid
IRJET-  	  Simulation of Solar PV and DG based Hybrid Micro GridIRJET-  	  Simulation of Solar PV and DG based Hybrid Micro Grid
IRJET- Simulation of Solar PV and DG based Hybrid Micro Grid
 
25 KWp SOLAR POWER PLANT IN BIET
25 KWp SOLAR POWER PLANT IN BIET25 KWp SOLAR POWER PLANT IN BIET
25 KWp SOLAR POWER PLANT IN BIET
 

Recently uploaded

(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 

Recently uploaded (20)

(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 

Power systems (2)

  • 1. ANALYSIS AND DESIGN OF SLOAR PHOTOVOLTAIC TYPE DG CONNECTED TO DISTRIBUTION SYSTEM Presented By: Dr. Satish Kansal Department of Electrical Engineering BHSBIET Lehragaga Power Systems
  • 2. 2 Introduction  Objective-to meet the demand at all the locations within power network as economically and reliably as possible.  Traditional electric power system- utilize the conventional energy resources for electricity generation  Operation-such traditional generation systems is based on centralized control utility generators to deliver power to widely dispersed users through an extensive transmission and distribution network  Present Environment- the justification for large central-station plants is weakening due to depleting conventional energy sources.
  • 3. 3 Distributed Generation Distributed Generation (DG), a term commonly used for small-scale generations, offer solution to many of these new challenges Recent developments in small renewable generation technologies such as wind turbines, photovoltaic, fuel cells, micro turbines and so on has drawn distribution utilities’ attention to possible changes in the distribution system infrastructure.
  • 4. 4  The DG’s can be characterized into different types as: Type I: DG capable of injecting real power only, like photovoltaic, fuel cells etc. Type II: DG capable of injecting reactive power only, e.g. kvar compensator, synchronous compensator, capacitors etc. Type III: DG capable of injecting both real and reactive power, e.g. synchronous machines, Type IV: DG capable of injecting real but consuming reactive power, e.g. induction generators.
  • 5.  CIGRE :Define DG as the generation, which has the following characteristics  Not centrally planned  Not centrally dispatched at present  Usually connected to the distribution networks  Smaller then 50 MW.  International Energy Agency (IEA) :  serving a customer on-site  providing support to a distribution network,  connected to the grid 5
  • 6. 6 Distributed Generation  Embedded Generations  Disperse Generations  depends upon many technologies  depends upon many applications  Increasing DG penetration- Growing share of distributed generators (DGs)  Policy initiatives to promote DG throughout the world
  • 7. Advantages of DG Integration  Reduction in line losses  Improvement in voltage profile  Deferred network extension  Improvement in system efficiency  Enhanced peak shaving capacity  System reliability and security 7
  • 8. Motivation for the Present Work  India is fastest growing economics  availability of quality supply is very crucial for the sustained growth  Electricity demand increasing rapidly  generating capacity in 1950 is 1,712 MW  Presently 2,11,766.22 MW  per capita per year only 860.72 kWh  triple by 2020, with 6.3% annual growth. 9
  • 9.  India is in power deficient state  power deficiency is nearly 12.2% of peak demand.  In UP, MP, Maharashtra, Bihar, and Punjab; it is more than 20%.  results in power cuts, blackouts, etc.  The above mentioned causes make the Distribution Generation from fuel cells, wind turbines, photovoltaic and small/micro hydro plants for continuous growth of the country. 10
  • 11. 12  DG supplying real power  loss reduction and voltage profile improvement  operational constraints Optimal Placement of DG
  • 12. 13 LOCATION AND SIZING ISSUES 0 10 20 30 40 50 60 70 0102030405060708090100 0.005 0.01 0.015 0.02 0.025 0.03 0.035 0.04 0.045 0.05 0.055 Loss (MW) %DG Size Bus No. Effect of size and location of DG on system loss
  • 13. Approaches 14  Analytical approach  PSO Technique  Analytical approach  Optimal size of PV  Optimal Location
  • 14. Results and Discussions  Test systems  33-bus with total load of 3.72 MW and 2.3 MVAr  69-bus with total load of 3.80 MW and 2.69 MVAr  Beaver conductors  base voltage is 12.66 kV. 15
  • 15. 16 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 0 0.5 1 1.5 2 2.5 3 3.5 4 Bus Number SizeofDGinMW 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 0.1 0.12 0.14 0.16 0.18 0.2 0.22 Bus Number LossinMW
  • 16. Method Optimum location Optimum DG size (MW) Power loss (KW) Without DG With DG Analytical Method Bus 6 3.15 210.97 115.2 PSO approach Bus 7 2.91 210.97 115.1 17 Power loss with and without DG for 33-bus system with constraints 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 0.9 0.95 1 Bus Number VoltageProfileinp.u. With DG Without DG
  • 17. 18 5 10 15 20 25 30 35 40 45 50 55 60 65 70 0 0.5 1 1.5 2 2.5 3 3.5 4 4.5 Bus Number SizeofDGinMW 1 6 11 16 21 26 31 36 41 46 51 56 61 66 70 0.08 0.1 0.12 0.14 0.16 0.18 0.2 0.22 0.24 Bus Number LossinMW
  • 18. 19 Method Optimum location Optimum DG size (MW) Power loss (KW) Without DG With DG Analytical Method Bus 61 1.81 225 83.4 PSO approach Bus 61 1.81 225 83.4 Power loss with and without DG for 69-bus system with constraints 1 4 7 10 13 16 19 22 25 28 31 34 37 40 43 46 49 52 55 58 61 64 67 69 0.9 0.95 1 Bus Number ViltageProfileinp.u. With DG Without DG
  • 19. Conclusions  minimize the real power loss.  Improvement in voltage profile  minimizing the DG size 20
  • 20. Renewable and Non- Renewable Energy Sources. 21
  • 21. Energy Scenario In India 22
  • 22. Energy source Estimated Potential Cumulative Installed capacity/ number Wind power 45,000 MW 18321.10 MW Small Hydro (upto 25 MW) 15,000 MW 3464.59 MW Biomass Power 16,000 MW 1242.60 MW Bagasse Cogeneration 3,500 MW 2199.33 MW Waste to energy 2,700 MW 93.68 MW Solar Power (SPV) ----- 1047.16 MW Family size Biogas Plants 12 million 45.45 Lakh Solar street lighting system ----- 1,19,634 nos. Home lighting system ----- 6,03,307 nos. Solar Lanterns ----- 7, 97,344 nos. Solar photovoltaic power plants 2.92 MWp Solar water heating systems 140 million m2 of collector area 5.63 Million m2 of collector area Solar photovoltaic pumps ----- 7334 nos. Biomass gasifiers ----- 153.04 MW 23 Table 1.1 Renewable Energy Potential in India AND actual progress achieved up to 30.11.2012
  • 23.  Renewable sources already contribute to about 5% of the total power generating capacity in the country.  Prospects for renewable are steadily improving in India (% of total installed capacity is expected to be 10% by 2020). 24
  • 24. Solar power as a solution to the Indian power scenario 25
  • 25. Why Solar Renewable energy Sources Preferred 26
  • 26. Solar PV Applications in PUNJAB 27
  • 27. Converting Solar Energy into Electrical Energy 28
  • 28. 29
  • 29. 30 Small units in the kilowatt range. Economical point of view less aggressive . No cost reduction Covers a wide range from less than one Watt to several megawatts. more aggressive . Its cost decreasing day by day
  • 30. Photovoltaic Cell  “Photo” meaning light.  “voltaic,” which refers to producing electricity.  A device that produces an electric reaction to light, producing electricity.  A typical PV cell made of crystalline silicon is 12 centimetres in diameter and 0.25 millimetres thick. In full sunlight, it generates 4 amperes of direct current at 0.5 volts or 2 watts of electrical power. 31
  • 31. Photovoltaic Module  Cells are interconnected and their electrical connections are then sandwiched between a top layer of glass or clear plastic and a lower level of plastic or plastic and metal. An outer frame is attached to increase mechanical strength, and to provide a way to mount the unit. This package is called a "module" or "panel". 32
  • 33. Impact of solar radiation on V-I characteristic curve of Photovoltaic Module 34
  • 34. Impact of temperature on V-I characteristic curve of Photovoltaic Module 35
  • 36. Types of Solar Photovoltaic System 37  Stand alone PV system  Grid Connected PV Systems  Hybrid System
  • 37. Stand alone PV system 38
  • 38. Grid Connected PV Systems 39
  • 40. Grid Connected PV Systems is Preferred  No use of battery reduces its capital cost  More reliable than other PV system.  To install Grid connected SPV system the following points are taken into consideration 41
  • 42. Grid Connected PV Systems  Estimate the solar potential available  Develop a system based on the potential estimations made for a chosen area of 100, 200, 500 m².  Annual energy generation by designed plant.  In the last cost estimation of grid connected SPV power plant to show whether it is economically viable or not. 43
  • 43. Estimation of Solar Potential  The solar radiation over different months measured.  The diurnal variations, average monthly output , yearly output are find out and related graphs are plot for showing the variation in different season and time.  Peak variation and possible plant rating also calculated. 44
  • 44. How Solar Radiation measured  Estimation the solar potential  Reading of solar radiation of given site.  It should have the ability to store the data which it measure for at least three months. 45
  • 45. METHODOLOGY  Calculated the daily energy output and monthly energy output for different months .  For better understanding, the measured solar radiation data sheet for the month of April 2010 has been given as a sample of Electrical Engineering Department, IIT Roorkee site. 46
  • 49. Variations for April Month 2010 50
  • 50. Variations for the month of Jan 2010 to Feb 2010
  • 51. Variations for the month of September to December 2010 52
  • 53. Daily & Monthly Energy Outputs (Watt/ mtr²-hr) 54
  • 54. Peak Variation and Possible Plant Rating 55
  • 55. Condition for Grid inter facing  Phase sequence matching: For a three phase system three phases should be 120 deg phase apart from each other for both the system.  Frequency matching : Frequency of the SPV system should be same as grid. Generally grid is of 50 Hz frequency capacity, now if SPV systems frequency is slightly higher than grid frequency (0.1 to 0.5) synchronization is possible but SPV system frequency should not be less than grid frequency  Voltage matching: Voltage level of both the system should same, otherwise synchronization is not possible. 56
  • 56. 9 kWp Grid connected PV system  Solar Panel Specification 57
  • 57. Solar PV Power Plant Specification 58
  • 58. Cost analysis for 9kWp SPV Grid Connected Power Plant  Total cost for 50 panels : Rs.14,40000/-  Cost of 3-φ Inverter : Rs. 2,50000/-  Cost of 3-φ step up Transformer : Rs. 2,00000/-  Subtotal: Rs.18,90000/-  Multiply the subtotal above by 0.2 (20%) to cover balance of system cost. Cost Estimate for Balance of System: (1890000 × 0.2) Rs. 3,78000/-.  Total Estimated PV System Cost is Rs.22,68000/-. 59
  • 60. Illustration of PSO algorithm This presentation is for the understanding of PSO method applied in DG Placement.
  • 61. Step 1 : Initialize random values into particles which correspond to bus numbers(or locations of DGs) and sizes to be kept at respective locations of the chosen network For Ex. Assume  there are 3 DGs to be placed and  the number of particles be 10  33 bus data taken into consideration then, Note : All the values are assumed. They don't correspond to original values
  • 62. Step 1 : Initialize random values into particles which correspond to bus numbers(or locations of DGs) and sizes to be kept at respective locations of the chosen network For Ex. Assume  there are 3 DGs to be placed and  the number of particles be 10  33 bus data taken into consideration then, Note : All the values are assumed. They don't correspond to original values Locations of 3 DGs Sizes of 3 DGs
  • 63. Step 1 : Initialize random values into particles which correspond to bus numbers(or locations of DGs) and sizes to be kept at respective locations of the chosen network For Ex. Assume  there are 3 DGs to be placed and  the number of particles be 10  33 bus data taken into consideration then, Note : All the values are assumed. They don't correspond to original values Locations of 3 DGs Sizes of 3 DGs 10 Combinations Or 10 particles
  • 64. Step 1 : Initialize random values into particles which correspond to bus numbers(or locations of DGs) and sizes to be kept at respective locations of the chosen network For Ex. Assume  there are 3 DGs to be placed and  the number of particles be 10  33 bus data taken into consideration then, Note : All the values are assumed. They don't correspond to original values 1.1MW at 5th bus
  • 65. Step 1 : Initialize random values into particles which correspond to bus numbers(or locations of DGs) and sizes to be kept at respective locations of the chosen network For Ex. Assume  there are 3 DGs to be placed and  the number of particles be 10  33 bus data taken into consideration then, Note : All the values are assumed. They don't correspond to original values 0.4MW at 4th bus
  • 66. Step 1 : Initialize random values into particles which correspond to bus numbers(or locations of DGs) and sizes to be kept at respective locations of the chosen network For Ex. Assume  there are 3 DGs to be placed and  the number of particles be 10  33 bus data taken into consideration then, Note : All the values are assumed. They don't correspond to original values 2.1MW at 31st bus
  • 67. Step 2 : For each Particle (or each combination of Buses), apply DG sizes in the particle at locations given in the particle and calculate loss using exact loss formula. Sizes of DGs Locations of DGs Apply Exact Loss equation PL = 0.132 Note : All the values are assumed. They don't correspond to original values
  • 68. Step 2 : For each Particle (or each combination of Buses), apply DG sizes in the particle at locations given in the particle and calculate loss using exact loss formula. Sizes of DGs Locations of DGs Apply Exact Loss equation PL = 0.132 Note : All the values are assumed. They don't correspond to original values Apply Exact Loss equation PL = 0.114 Apply Exact Loss equation PL = 0.122 Apply Exact Loss equation PL = 0.199 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
  • 69. Step 2 : For each Particle (or each combination of Buses), apply DG sizes in the particle at locations given in the particle and calculate loss using exact loss formula. Note : All the values are assumed. They don't correspond to original values Apply Exact Loss equation PL = 0.114
  • 70. Step 3 : Depending on the respective loss choose the minimum one as global best. update the personal best also. Note : All the values are assumed. They don't correspond to original values Assume That the following combination has the best value i.e. lowest PL Then, Global Best Particle Fitness of Global Best Apply Exact Loss equation PL = 0.114
  • 71. Step 3 : Depending on the respective loss choose the minimum one as global best. update the personal best also. Note : All the values are assumed. They don't correspond to original values Global Best Particle Fitness of Global Best Apply Exact Loss equation PL = 0.114 Personal Best is also updated similarly. The only change is that it is compared to its own previous value of the respective Particle.
  • 72. Step 4 : Update the velocities and positions of the Particles using PSO update equations. Note : All the values are assumed. They don't correspond to original values After using both equations and updating, The array transforms into
  • 73. Step 5: Do steps 2,3,4 until the particles converge to a point where Global best does not get updated. Note : All the values are assumed. They don't correspond to original values