BILFINGER SALAMIS UK
LOBO System Scaffold
Bacton Site Visit 28/09/2016
Introduction:
Further to our visit to LOBO’s premises to witness demonstrations of the systems being erected. A
site visit by LOBO to Bacton Gas plant to demonstrate the system was carried out on Wednesday,
28/09/2016.
LOBO was provided with five different scenarios to which they provided detailed drawings in
preparation to erect on site. A site visit was arranged and LOBO attended site to demonstrate
erecting and dismantling the system. This report details the type of scenario where LOBO can be
used and provides advantages / disadvantages of the system. This report goes into detail on erect
and dismantles times where major cost savings can be gained.
The LOBO system also has the added benefits that it doesn’t need to be erected by trained
scaffolders. Training can be carried for any individual to be competent to erect and dismantle.
Who attended?
LOBO,
Paul Timson, National Sales Manager
Jason Currie, LOBO Technician
Andrew Roznowski, Senior LOBO Technician
Bilfinger,
B*** G***, Operations Manager
S**** D*****, Bacton Maintenance Focal Point
A*** F********, Jacobs BRP Focal Point
E**** B****, Multi-Discipline Foreman
D*** R******, Scaffold Foreman
Shell,
M*** H***, FM Coordinator
C**** C***, FM QA/QC Engineer
AJS
J** P*****, Senior Work Prep
What was built?
Tower 1 - 1.8 x 1.7 x 4m, Erected in clear area between K2710 Flash Gas Skid and
K40 Compressor:
 LOBO Scaffold;
2 men x 1 hour to erect
2 men x 15 minutes to dismantle
Total hours 2.5 man hours
 Conventional Scaffold; Tube and fitting would take;
3 men x 5 hours to erect
3 men x 2.5 hours to dismantle
Total hours 22.5 man hours
No problems apart from the recurring issue of WAH controls
during the transition of placing the guard rail on from the
seated/kneeling position when the boards are placed. A discussion was held with the team and this
can be alleviated by using an advanced guard rail.
Tower 2 - 2.4 x 1.4 x 4m, 2 Standards offset on gantry of Compressor K40:
 LOBO Scaffold;
2 men x 1 hour, 20 mins to erect
2 men x 20 minutes to dismantle
Total hours 3.3 man hours
 Tube and fitting would take;
3 men x 5 hours to erect
3 men x 2.5 to dismantle
Total hours 22.5 man hours
Some minor problems with getting around the obstruction
of the guard rail on the gantry, which was eventually
overcome by the demo team. Initially I was concerned
about the stability, but after climbing the ladders to the top
lift I discovered it was no more unstable than a tube and
fitting tower of the same size. There is also an option to use
longer stabilizers/outriggers to provide added stability.
Tower 3 - 1.8 x 2 x 4m, Erected over K710 Flash Gas Skid:
 LOBO Scaffold;
2 men x 50 minutes to erect
2 men x 15 minutes to dismantle
Total hours 2.1 man hours
 Tube and fitting would take;
3 men x 5 hours to erect
3 men x 2.5 hours to dismantle
Total hours 22.5 man hours
Task was deliberately set with the obstacle of the skid and low level pipework hindering the base
out of the tower, but was duly overcome.
Tower 4 - 1.8 x 0.8 x 4m, Erected in clear area between K710 Skid and K10
compressor:
 LOBO Scaffold;
2 men x 40 minutes to erect
2 men x 15 minutes to dismantle
Total hours 1.8 man hours
 Tube and fitting would take;
3 men x 4 hours to erect
3 men x 2 hours to dismantle
Total hours 18 man hours
This tower is an example of where LOBO can be used in narrow areas. There were no issues
whatsoever erecting this tower. The fact that we were on our 4th job within a matter of hours gives
some indication of how easy the system is to use. LOBO also showed us how we can 'butt up'
against adjacent structures / walls to make the structure more secure. This was achieved using the
components contained with the demo kit with no issues.
Tower 5 (Mobile) - 1.2 x 0.8 x 1.6m, Erected in same area as Tower 4:
 LOBO Scaffold;
2 men x 30 minutes to erect
2 men x 15 minutes to dismantle
Total hours 1.5 man hours
 Tube and fitting would take;
3 x 2.5 hours to erect
3 x 1 hour to dismantle
Total hours 10.5 man hours
We only got as far as the board on the first lift with
this one, as time didn’t permit completion The dual castors however were quick to assemble and
easy to attach and detach. During erection the first lift was reached within 15 minutes. The tower
was very stable even though it was mobile.
General Overview
A couple of concerns - one was around the components themselves, with the smaller attachments
and fittings potentially being lost or mislaid, or even damaged, so we would need to keep the
materials in a secure area or use a LOBO Towestore container. The compressor house or generator
building where the system might be primarily used would be an ideal area to use LOBO. As a time
comparison, only 2 towers would have been erected using tube and fitting, with no dismantle. In
the same time span 5 jobs were erected and dismantled with the LOBO system.
There were issues with the gap between the top guard rail and the lift you are accessing from the
internal ladder. This could easily be overcome with additional components fixed utilising the
bracket clamps. The LOBO system, as with any system has its advantages, time factor, easy to
assemble etc. it really comes into its own when there are no obstructions to negotiate on upper
levels, however the system is versatile to work around obstructions if the erection is planned.
Summary
Man Hours it takes to erect, LOBO vs Conventional
Man Hours
LOBO System Conventional Scaffold
Erect Dismantle Erect Dismantle
Tower 1 2 0.5 15 7.5
Tower 2 2.7 0.6 15 7.5
Tower 3 1.6 0.5 15 7.5
Tower 4 1.3 0.5 12 6
Tower 5 1 0.5 7.5 3
Total Hours 11.2 96
Labour Cost, based on £31.00 per man hour (this rate is used for comparison only).
Labour Cost
LOBO System Conventional Scaffold
Erect Dismantle Erect Dismantle
Tower 1 £ 62.00 £ 15.50 £465.00 £232.50
Tower 2 £ 83.70 £ 18.60 £465.00 £232.50
Tower 3 £ 49.60 £ 15.50 £465.00 £232.50
Tower 4 £ 40.30 £ 15.50 £372.00 £186.00
Tower 5 £ 31.00 £ 15.50 £232.50 £93.00
Total Cost £347.20 £2,976.00
LOBO Scaffolding Cost’s:
To build all five towers without dismantle
Tower 1 £5,805.00 Tower 4 £3,688.00
Tower 2 £6,317.00 Tower 5 £2,254.00
Tower 3 £4,556.00 Total: £22,620.00
The cost to purchase enough LOBO materials to erect and dismantle each tower on an individually
(to build all platforms duplication of all components would be required). £7,907.00
Train the trainer course, (up to 8 delegates): £3,045.00
Galvanised Scaffolding:
There is currently 9 tonne erected in this location, costing £10.26 per day this equates to a total
cost of £3,744.90 per annum.
Benefits of LOBO
The benefit of using LOBO is the labour time saved to erect and dismantle. Based on the towers
erected an average saving of £525 per tower was achieved on man hours. At a purchase price of
£7,907 to purchase the materials a total of 15 towers would need to be completed for the cost
saving to be realised. The hire cost of the conventional scaffold would also not apply during this
period. In addition to the labour time saved any trade can be trained in erecting and dismantling
the system which reduces manpower numbers on site.

More Related Content

Similar to LOBO System - Bilfinger report November 2016

Basic system scaffold
Basic system scaffoldBasic system scaffold
Basic system scaffold
Alliver Revilla
 
Experimental study of precast portal frame
Experimental study of precast portal frameExperimental study of precast portal frame
Experimental study of precast portal frame
Satish Kambaliya
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System
ashleyyeap
 
Tripping out automatic
Tripping out automaticTripping out automatic
Tripping out automatic
Ruba Alsoheil
 
the kajima cut and take down method
the kajima cut and take down methodthe kajima cut and take down method
the kajima cut and take down method
Darshan Parakhiya
 
CIVIL CONSTRUCTION IN FATIMA FERTILIZER COMPANY LIMITED
CIVIL CONSTRUCTION INFATIMA FERTILIZER COMPANY LIMITEDCIVIL CONSTRUCTION INFATIMA FERTILIZER COMPANY LIMITED
CIVIL CONSTRUCTION IN FATIMA FERTILIZER COMPANY LIMITED
Water Birds (Ali)
 
AAC Block Plant Consultant
AAC Block Plant ConsultantAAC Block Plant Consultant
AAC Block Plant Consultant
gubbiseo
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System
ashleyyeap
 
2015 CRW - Fagioli Rigging Job of the Year
2015 CRW - Fagioli Rigging Job of the Year2015 CRW - Fagioli Rigging Job of the Year
2015 CRW - Fagioli Rigging Job of the Year
Specialized Carriers & Rigging Association
 
IRJET- Experimental Investigation of Fly Ash based Geopolymer Concrete
IRJET- Experimental Investigation of Fly Ash based Geopolymer ConcreteIRJET- Experimental Investigation of Fly Ash based Geopolymer Concrete
IRJET- Experimental Investigation of Fly Ash based Geopolymer Concrete
IRJET Journal
 
Corium q&a 2020
Corium q&a 2020Corium q&a 2020
Corium q&a 2020
Blair Davies, P.Eng., M.B.A.
 
Efficient belt extension_process in Room and Pillar mining method
Efficient belt extension_process in Room and Pillar mining methodEfficient belt extension_process in Room and Pillar mining method
Efficient belt extension_process in Room and Pillar mining method
Elvidge Radithongwa
 
railway_plant_layout
railway_plant_layoutrailway_plant_layout
railway_plant_layout
Rajshree Tiwari
 
Prefabricated Structure and its installation process
Prefabricated Structure and its installation processPrefabricated Structure and its installation process
Prefabricated Structure and its installation process
Udayram Patil
 
ENGINEERING AND DESIGN PORTFOLIO
ENGINEERING AND DESIGN PORTFOLIOENGINEERING AND DESIGN PORTFOLIO
ENGINEERING AND DESIGN PORTFOLIO
Keith Anderson Anderson
 
Fox Blocks ICF Guidebook
Fox Blocks ICF GuidebookFox Blocks ICF Guidebook
Fox Blocks ICF Guidebook
Western-Building-Center
 
Report about the repairation of the Raw mill Slide Ring and shell (Modificat...
Report about the repairation of the Raw mill Slide Ring and  shell (Modificat...Report about the repairation of the Raw mill Slide Ring and  shell (Modificat...
Report about the repairation of the Raw mill Slide Ring and shell (Modificat...
Moaz Emad gaber
 
2016 Fakro Loft Ladder Catalogue
2016 Fakro Loft Ladder Catalogue2016 Fakro Loft Ladder Catalogue
2016 Fakro Loft Ladder Catalogue
Jagjeet Singh Bath
 
A10_TeamPrime
A10_TeamPrimeA10_TeamPrime
A10_TeamPrime
Taylor Martell
 
Replacement and reconnection of breaker in 115 kV substation - Final (English)
Replacement and reconnection of breaker in 115 kV substation - Final (English)Replacement and reconnection of breaker in 115 kV substation - Final (English)
Replacement and reconnection of breaker in 115 kV substation - Final (English)
Pablo Miguel Jurado
 

Similar to LOBO System - Bilfinger report November 2016 (20)

Basic system scaffold
Basic system scaffoldBasic system scaffold
Basic system scaffold
 
Experimental study of precast portal frame
Experimental study of precast portal frameExperimental study of precast portal frame
Experimental study of precast portal frame
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System
 
Tripping out automatic
Tripping out automaticTripping out automatic
Tripping out automatic
 
the kajima cut and take down method
the kajima cut and take down methodthe kajima cut and take down method
the kajima cut and take down method
 
CIVIL CONSTRUCTION IN FATIMA FERTILIZER COMPANY LIMITED
CIVIL CONSTRUCTION INFATIMA FERTILIZER COMPANY LIMITEDCIVIL CONSTRUCTION INFATIMA FERTILIZER COMPANY LIMITED
CIVIL CONSTRUCTION IN FATIMA FERTILIZER COMPANY LIMITED
 
AAC Block Plant Consultant
AAC Block Plant ConsultantAAC Block Plant Consultant
AAC Block Plant Consultant
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System
 
2015 CRW - Fagioli Rigging Job of the Year
2015 CRW - Fagioli Rigging Job of the Year2015 CRW - Fagioli Rigging Job of the Year
2015 CRW - Fagioli Rigging Job of the Year
 
IRJET- Experimental Investigation of Fly Ash based Geopolymer Concrete
IRJET- Experimental Investigation of Fly Ash based Geopolymer ConcreteIRJET- Experimental Investigation of Fly Ash based Geopolymer Concrete
IRJET- Experimental Investigation of Fly Ash based Geopolymer Concrete
 
Corium q&a 2020
Corium q&a 2020Corium q&a 2020
Corium q&a 2020
 
Efficient belt extension_process in Room and Pillar mining method
Efficient belt extension_process in Room and Pillar mining methodEfficient belt extension_process in Room and Pillar mining method
Efficient belt extension_process in Room and Pillar mining method
 
railway_plant_layout
railway_plant_layoutrailway_plant_layout
railway_plant_layout
 
Prefabricated Structure and its installation process
Prefabricated Structure and its installation processPrefabricated Structure and its installation process
Prefabricated Structure and its installation process
 
ENGINEERING AND DESIGN PORTFOLIO
ENGINEERING AND DESIGN PORTFOLIOENGINEERING AND DESIGN PORTFOLIO
ENGINEERING AND DESIGN PORTFOLIO
 
Fox Blocks ICF Guidebook
Fox Blocks ICF GuidebookFox Blocks ICF Guidebook
Fox Blocks ICF Guidebook
 
Report about the repairation of the Raw mill Slide Ring and shell (Modificat...
Report about the repairation of the Raw mill Slide Ring and  shell (Modificat...Report about the repairation of the Raw mill Slide Ring and  shell (Modificat...
Report about the repairation of the Raw mill Slide Ring and shell (Modificat...
 
2016 Fakro Loft Ladder Catalogue
2016 Fakro Loft Ladder Catalogue2016 Fakro Loft Ladder Catalogue
2016 Fakro Loft Ladder Catalogue
 
A10_TeamPrime
A10_TeamPrimeA10_TeamPrime
A10_TeamPrime
 
Replacement and reconnection of breaker in 115 kV substation - Final (English)
Replacement and reconnection of breaker in 115 kV substation - Final (English)Replacement and reconnection of breaker in 115 kV substation - Final (English)
Replacement and reconnection of breaker in 115 kV substation - Final (English)
 

Recently uploaded

学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
171ticu
 
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
shadow0702a
 
Transformers design and coooling methods
Transformers design and coooling methodsTransformers design and coooling methods
Transformers design and coooling methods
Roger Rozario
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
VICTOR MAESTRE RAMIREZ
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
Madan Karki
 
Software Quality Assurance-se412-v11.ppt
Software Quality Assurance-se412-v11.pptSoftware Quality Assurance-se412-v11.ppt
Software Quality Assurance-se412-v11.ppt
TaghreedAltamimi
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
Madan Karki
 
Material for memory and display system h
Material for memory and display system hMaterial for memory and display system h
Material for memory and display system h
gowrishankartb2005
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
MDSABBIROJJAMANPAYEL
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
Yasser Mahgoub
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
co23btech11018
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
insn4465
 
Curve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods RegressionCurve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods Regression
Nada Hikmah
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
KrishnaveniKrishnara1
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
IJECEIAES
 
CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1
PKavitha10
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
IJECEIAES
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
Divyanshu
 
Data Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason WebinarData Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason Webinar
UReason
 
cnn.pptx Convolutional neural network used for image classication
cnn.pptx Convolutional neural network used for image classicationcnn.pptx Convolutional neural network used for image classication
cnn.pptx Convolutional neural network used for image classication
SakkaravarthiShanmug
 

Recently uploaded (20)

学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
 
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
 
Transformers design and coooling methods
Transformers design and coooling methodsTransformers design and coooling methods
Transformers design and coooling methods
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
 
Software Quality Assurance-se412-v11.ppt
Software Quality Assurance-se412-v11.pptSoftware Quality Assurance-se412-v11.ppt
Software Quality Assurance-se412-v11.ppt
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
 
Material for memory and display system h
Material for memory and display system hMaterial for memory and display system h
Material for memory and display system h
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
 
Curve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods RegressionCurve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods Regression
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
 
CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
 
Data Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason WebinarData Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason Webinar
 
cnn.pptx Convolutional neural network used for image classication
cnn.pptx Convolutional neural network used for image classicationcnn.pptx Convolutional neural network used for image classication
cnn.pptx Convolutional neural network used for image classication
 

LOBO System - Bilfinger report November 2016

  • 1. BILFINGER SALAMIS UK LOBO System Scaffold Bacton Site Visit 28/09/2016
  • 2. Introduction: Further to our visit to LOBO’s premises to witness demonstrations of the systems being erected. A site visit by LOBO to Bacton Gas plant to demonstrate the system was carried out on Wednesday, 28/09/2016. LOBO was provided with five different scenarios to which they provided detailed drawings in preparation to erect on site. A site visit was arranged and LOBO attended site to demonstrate erecting and dismantling the system. This report details the type of scenario where LOBO can be used and provides advantages / disadvantages of the system. This report goes into detail on erect and dismantles times where major cost savings can be gained. The LOBO system also has the added benefits that it doesn’t need to be erected by trained scaffolders. Training can be carried for any individual to be competent to erect and dismantle. Who attended? LOBO, Paul Timson, National Sales Manager Jason Currie, LOBO Technician Andrew Roznowski, Senior LOBO Technician Bilfinger, B*** G***, Operations Manager S**** D*****, Bacton Maintenance Focal Point A*** F********, Jacobs BRP Focal Point E**** B****, Multi-Discipline Foreman D*** R******, Scaffold Foreman Shell, M*** H***, FM Coordinator C**** C***, FM QA/QC Engineer AJS J** P*****, Senior Work Prep
  • 3. What was built? Tower 1 - 1.8 x 1.7 x 4m, Erected in clear area between K2710 Flash Gas Skid and K40 Compressor:  LOBO Scaffold; 2 men x 1 hour to erect 2 men x 15 minutes to dismantle Total hours 2.5 man hours  Conventional Scaffold; Tube and fitting would take; 3 men x 5 hours to erect 3 men x 2.5 hours to dismantle Total hours 22.5 man hours No problems apart from the recurring issue of WAH controls during the transition of placing the guard rail on from the seated/kneeling position when the boards are placed. A discussion was held with the team and this can be alleviated by using an advanced guard rail. Tower 2 - 2.4 x 1.4 x 4m, 2 Standards offset on gantry of Compressor K40:  LOBO Scaffold; 2 men x 1 hour, 20 mins to erect 2 men x 20 minutes to dismantle Total hours 3.3 man hours  Tube and fitting would take; 3 men x 5 hours to erect 3 men x 2.5 to dismantle Total hours 22.5 man hours Some minor problems with getting around the obstruction of the guard rail on the gantry, which was eventually overcome by the demo team. Initially I was concerned about the stability, but after climbing the ladders to the top lift I discovered it was no more unstable than a tube and fitting tower of the same size. There is also an option to use longer stabilizers/outriggers to provide added stability.
  • 4. Tower 3 - 1.8 x 2 x 4m, Erected over K710 Flash Gas Skid:  LOBO Scaffold; 2 men x 50 minutes to erect 2 men x 15 minutes to dismantle Total hours 2.1 man hours  Tube and fitting would take; 3 men x 5 hours to erect 3 men x 2.5 hours to dismantle Total hours 22.5 man hours Task was deliberately set with the obstacle of the skid and low level pipework hindering the base out of the tower, but was duly overcome. Tower 4 - 1.8 x 0.8 x 4m, Erected in clear area between K710 Skid and K10 compressor:  LOBO Scaffold; 2 men x 40 minutes to erect 2 men x 15 minutes to dismantle Total hours 1.8 man hours  Tube and fitting would take; 3 men x 4 hours to erect 3 men x 2 hours to dismantle Total hours 18 man hours This tower is an example of where LOBO can be used in narrow areas. There were no issues whatsoever erecting this tower. The fact that we were on our 4th job within a matter of hours gives some indication of how easy the system is to use. LOBO also showed us how we can 'butt up' against adjacent structures / walls to make the structure more secure. This was achieved using the components contained with the demo kit with no issues.
  • 5. Tower 5 (Mobile) - 1.2 x 0.8 x 1.6m, Erected in same area as Tower 4:  LOBO Scaffold; 2 men x 30 minutes to erect 2 men x 15 minutes to dismantle Total hours 1.5 man hours  Tube and fitting would take; 3 x 2.5 hours to erect 3 x 1 hour to dismantle Total hours 10.5 man hours We only got as far as the board on the first lift with this one, as time didn’t permit completion The dual castors however were quick to assemble and easy to attach and detach. During erection the first lift was reached within 15 minutes. The tower was very stable even though it was mobile.
  • 6. General Overview A couple of concerns - one was around the components themselves, with the smaller attachments and fittings potentially being lost or mislaid, or even damaged, so we would need to keep the materials in a secure area or use a LOBO Towestore container. The compressor house or generator building where the system might be primarily used would be an ideal area to use LOBO. As a time comparison, only 2 towers would have been erected using tube and fitting, with no dismantle. In the same time span 5 jobs were erected and dismantled with the LOBO system. There were issues with the gap between the top guard rail and the lift you are accessing from the internal ladder. This could easily be overcome with additional components fixed utilising the bracket clamps. The LOBO system, as with any system has its advantages, time factor, easy to assemble etc. it really comes into its own when there are no obstructions to negotiate on upper levels, however the system is versatile to work around obstructions if the erection is planned. Summary Man Hours it takes to erect, LOBO vs Conventional Man Hours LOBO System Conventional Scaffold Erect Dismantle Erect Dismantle Tower 1 2 0.5 15 7.5 Tower 2 2.7 0.6 15 7.5 Tower 3 1.6 0.5 15 7.5 Tower 4 1.3 0.5 12 6 Tower 5 1 0.5 7.5 3 Total Hours 11.2 96 Labour Cost, based on £31.00 per man hour (this rate is used for comparison only). Labour Cost LOBO System Conventional Scaffold Erect Dismantle Erect Dismantle Tower 1 £ 62.00 £ 15.50 £465.00 £232.50 Tower 2 £ 83.70 £ 18.60 £465.00 £232.50 Tower 3 £ 49.60 £ 15.50 £465.00 £232.50 Tower 4 £ 40.30 £ 15.50 £372.00 £186.00 Tower 5 £ 31.00 £ 15.50 £232.50 £93.00 Total Cost £347.20 £2,976.00
  • 7. LOBO Scaffolding Cost’s: To build all five towers without dismantle Tower 1 £5,805.00 Tower 4 £3,688.00 Tower 2 £6,317.00 Tower 5 £2,254.00 Tower 3 £4,556.00 Total: £22,620.00 The cost to purchase enough LOBO materials to erect and dismantle each tower on an individually (to build all platforms duplication of all components would be required). £7,907.00 Train the trainer course, (up to 8 delegates): £3,045.00 Galvanised Scaffolding: There is currently 9 tonne erected in this location, costing £10.26 per day this equates to a total cost of £3,744.90 per annum. Benefits of LOBO The benefit of using LOBO is the labour time saved to erect and dismantle. Based on the towers erected an average saving of £525 per tower was achieved on man hours. At a purchase price of £7,907 to purchase the materials a total of 15 towers would need to be completed for the cost saving to be realised. The hire cost of the conventional scaffold would also not apply during this period. In addition to the labour time saved any trade can be trained in erecting and dismantling the system which reduces manpower numbers on site.