SlideShare a Scribd company logo
OBJETIVE:
The objective is to present the replacement and
re-connection job (doing Live Line Work) of an
SF6 breaker unit, from S&C, in the 115 kW & 20
MW substation of Join Operations, in SUG oil
field, Kuwait.
DEVELOPMENT:
After more than 5 years working for different
utilities, ELESA S.A., which is a company
dedicated to maintenance, consulting and Live
Line training in both local and international
levels, did contact with IMCO company which
carries out construction and maintenance
projects in Kuwait and other Middle East
countries. An agreement between companies
was established, that allow us to complement
and enrich ourselves.
In this opportunity the challenge was to replace
an SF6 breaker unit, from S&C, that was failed
due to gas leakage.
It was located in a radial substation that supplies
20 MW to the high production SUG Oil Field.
In the emergency, and in order to restore the
power supply, the complete circuit-switcher was
by-passed, and a shutdown was programmed to
replace the interrupter.
1
COMISIÓN DE INTEGRACIÓN ENERGÉTICA REGIONAL
REPLACEMENT OF CIRCUIT-SWITCHER IN 115 KV SUBSTATION
Author/s: Carlos Arata
Company: ELESA International S.A.
Author/s: Jalal Mohesen – Pablo Jurado
Company: IMCO Engineering & Construction Co.
COMPANY INFORMATION
ELESA SA
Telephone: (54) 93461 512966
E-mail: info@elesa.com.ar
c.arata@elesa.com.ar
IMCO
Address: P.O. Box 9309 Ahmadi, Kuwait
Zip Cod: 61004
Telephone: (965) 2398 1661
Fax: (965) 2398 4708
E-Mail: pjurado@imcokw.com
jmohsen@imcokw.com
KEY-WORDS: Uninterrupted production
– Innovation – Complementation
between companies
COMPANY: ELESA SA - IMCO Engineering & Construction Co.
COUNTRY: Kuwait
Type: Technical Paper
Kuwait, May 2011.
By-passed circuit-switcher
By chance I was giving training and refreshment
course to the Live Line crews when I knew about
the equipment failure. It seems to me and
interesting challenge, and us when to see the
substation.
The job to be carried out was similar to others
that we have already made at the 66 kV
substation of EDEN Company in Argentina.
But the two main differences were, by one side,
the unavailability in Kuwait of the equipment that
ELESA has for substation jobs, and by the other
side, the generous safety distances in the
substation portal structure.
After discussing the possibility of doing the job
by applying Live Line Work, the scheduled
shutdown was suspended.
The similar jobs previously done consisted in by-
passing measurement and operation
equipments, for maintenance, which avoided the
replacement of them, thing that made no sense
at that time. We did these types of jobs since
2002, when we finished the construction of the
prototype for working in substations.
By-pass 66 kV Substation, EDEN, October
2003
Steps of the task
Basically the Live Line Work in this case
consisted of 4 main steps which are:
1) Replacement of the failed breaker unit
2) Circuit-Switcher-to-Surge Arrester
jumpers installation
3) Circuit-Switcher-to-Line jumpers
installation
4) Removal of the temporary by-pass
jumpers and old jumpers from line-to-
circuit switcher (having close the
circuit-switcher previously)
1) Replacement of failed breaker
unit
The failed unit was the middle one, which is the
most difficult to work on, for all steps.
Two Class A, approved to work up to 132 kV,
insulated lift, were used to do the job.
We had to study carefully the safety distance to
work on the installation.
2
COMISIÓN DE INTEGRACIÓN ENERGÉTICA REGIONAL
General view and distances
The lift trucks that we used have two articulated
booms, with the upper one telescopic (Class A).
These features make them quite versatile to
work in complicated installations, giving as good
flexibility to find the most suitable position.
Besides this, they have a material handling
system with 700 lbs capacity in the worst
condition. We used this feature to remove the
failed unit and to install the new one (Step 1, see
the following picture)
Installing the new SF6 unit
2) Transformer side jumper
installation
One again here the more complicated to
install was the central phase jumper, to
which we had access by positioning the
bucket between the insulators of the circuit-
switcher. In order to connect the circuit-
breaker with the jumpers on the surge
arrester, and due to there wasn’t enough
room to work by barehand method, we
installed a jumper by using hotsticks, made
of extra-flexible cooper conductor (120 mm²)
mechanically reinforced with an extra-
flexible steel wire, and with two duckbill
clamps of 400 A capacity each one, which
was much more than we need, an also this
feature allowed us to handle the jumper by
using two sticks, therefore improving the
safety at the work.
3) Circuit-switcher-to-line
jumpers installation
The jumpers to be installed were 6 m long. First
they were installed in the pedestal insulator of
the open switch, and then in the lug of the
tension clamp.
3
COMISIÓN DE INTEGRACIÓN ENERGÉTICA REGIONAL
Leaving the lug free
But as n the lug there was the existing
permanent jumper still connected forming a loop
in which the by-pass was installed, before
connecting the new jumper a piece of the old
jumper had to be removed.
In this case, due to the distances at the portal
side are wide enough there is no difference in
starting to work in the middle phase or in the
lateral ones.
Going up with the new jumper
The new jumper was attached first to the main
conductor using a short flexible jumper, before
connecting both lugs. This short jumper took the
capacitive load of the new jumper and
mechanically insures the connection to avoid an
unexpected drop of the jumper.
Fixing the new jumper to the dead-end
terminal
4) Removal of the temporary
by-pass jumpers and old
jumpers from line-to-circuit
switcher (having closed the
circuit-switcher previously)
Once the new permanent jumpers have been
connected, it was missing to remove the
temporary by-pass jumpers installed during the
emergency, and the original jumpers from line-
to-switch that were tied back forming a loop.
This task was done working with simultaneously
with two insulated lifts, due to they were
available as well as the necessary personnel.
The synchronization of the task was in charge of
the supervisor on ground, and the good
communication was insured by using walkie-
talkies.
4
COMISIÓN DE INTEGRACIÓN ENERGÉTICA REGIONAL
The operation of disconnection of the by-pass
was made with hotsticks according to the
fundamentals of the barehand method, in order
to eliminate any possibility of one lineman to be
in series with the circuit.
Preparation to disconnect the by-pass
The by-pass jumper to be removed was still
attached to the old piece of jumper by an
insulated rope, which is lately removed, while the
other crew picked-up the by-pass jumper.
The other crew removes the by-pass jumper
Removal of the by-pass jumper with two crews
working together
Having completed the above mentioned step, the
last thing to do was to remove the old permanent
jumpers, which were cut in three pieces to avoid
they were opened due to their elastic memory
while removing, since, we must remember, these
jumpers were 6 m long.
5
COMISIÓN DE INTEGRACIÓN ENERGÉTICA REGIONAL
CONCLUSIONS
The technician that was sent by S&C (the
manufacturer of the equipment to be replaced)
didn’t know about the possibility to do this job
Live, although it could done in a safe way and
according to the previously developed
procedure.
The execution of this Live Line Work avoided a
costly shutdown to the oil company, that was
planned to be of at least 8 hours with a loss of
approximately u$s 1 million in differed oil.
In addition the execution of this job is an
important precedent to introduce the concept of
Live Line Work in Substations that had never
been considered before in this country.
LESSON LERNT
The conjunction of qualified personnel, and
necessary equipment together with the team
work for the development of the procedure and
the explanation of it to the people who make the
decisions (which showed reluctant at the
beginning), allowed the completion of a this kind
of job for the first time in the country and
probably in all Gulf area.
RECOMENDATION
Start thinking that a Live Line Work in
Substation is possible until the contrary is
demonstrated, don’t think in the reverse way.
Site work team
ELESA SA
Carlos Arata
IMCO
Pablo Jurado
Khaled Alí Manssur
Mohamed Abou Elenin
Nabil Abd el Mohesen
Ahmed Sultan Mohamed
Mohamed Abdul Ghani
Mohamed Khalaf Shakoor
Rheda Mohamed
V. Perumal
6
COMISIÓN DE INTEGRACIÓN ENERGÉTICA REGIONAL
CONCLUSIONS
The technician that was sent by S&C (the
manufacturer of the equipment to be replaced)
didn’t know about the possibility to do this job
Live, although it could done in a safe way and
according to the previously developed
procedure.
The execution of this Live Line Work avoided a
costly shutdown to the oil company, that was
planned to be of at least 8 hours with a loss of
approximately u$s 1 million in differed oil.
In addition the execution of this job is an
important precedent to introduce the concept of
Live Line Work in Substations that had never
been considered before in this country.
LESSON LERNT
The conjunction of qualified personnel, and
necessary equipment together with the team
work for the development of the procedure and
the explanation of it to the people who make the
decisions (which showed reluctant at the
beginning), allowed the completion of a this kind
of job for the first time in the country and
probably in all Gulf area.
RECOMENDATION
Start thinking that a Live Line Work in
Substation is possible until the contrary is
demonstrated, don’t think in the reverse way.
Site work team
ELESA SA
Carlos Arata
IMCO
Pablo Jurado
Khaled Alí Manssur
Mohamed Abou Elenin
Nabil Abd el Mohesen
Ahmed Sultan Mohamed
Mohamed Abdul Ghani
Mohamed Khalaf Shakoor
Rheda Mohamed
V. Perumal
6
COMISIÓN DE INTEGRACIÓN ENERGÉTICA REGIONAL

More Related Content

What's hot

Siva relay engg
Siva relay enggSiva relay engg
Siva relay engg
siva kumar
 
MY CV
MY CVMY CV
Testing & Commissioning Engineer
Testing & Commissioning EngineerTesting & Commissioning Engineer
Testing & Commissioning Engineer
KumaresanT7
 
CV
CVCV
Engr. Ayaz Khan CV11 (1)
Engr.  Ayaz Khan CV11 (1)Engr.  Ayaz Khan CV11 (1)
Engr. Ayaz Khan CV11 (1)
Engr.ayaz khan
 
Resume 2016
Resume 2016Resume 2016
Resume 2016
Aaron Cooper
 
Resume 2016
Resume 2016Resume 2016
Resume 2016
Aaron Cooper
 
Ashok Resume-2015
Ashok Resume-2015Ashok Resume-2015
Ashok Resume-2015
ashok kumar
 
Updated resume
Updated resumeUpdated resume
Updated resume
kalimuthuchinnathamb
 
Kumar RESUME
Kumar RESUMEKumar RESUME
Kumar RESUME
Kumar murugesan
 
ELEC.ENG CV
ELEC.ENG CVELEC.ENG CV
ELEC.ENG CV
Muhammad Asim
 
UPDATED CV-1
UPDATED CV-1UPDATED CV-1
UPDATED CV-1
Girish Prajapati
 
PRAVASH _PANDA RESUME....2015
PRAVASH _PANDA RESUME....2015PRAVASH _PANDA RESUME....2015
PRAVASH _PANDA RESUME....2015
pravash panda
 
Demolition of a former mine site - Luke Egan and David Wood
Demolition of a former mine site - Luke Egan and David WoodDemolition of a former mine site - Luke Egan and David Wood
Demolition of a former mine site - Luke Egan and David Wood
NSW Environment and Planning
 
Equipment failure - a liability or an asset? - Roger Costanzi
Equipment failure - a liability or an asset? - Roger CostanziEquipment failure - a liability or an asset? - Roger Costanzi
Equipment failure - a liability or an asset? - Roger Costanzi
NSW Environment and Planning
 
sivachandran resume
sivachandran resumesivachandran resume
sivachandran resume
siva karnan
 
Mohamed ElGazzar Egypt
Mohamed ElGazzar EgyptMohamed ElGazzar Egypt
Mohamed ElGazzar Egypt
Mohamed ElGazzar
 
POH seminar ppt bhusawal
POH seminar ppt bhusawalPOH seminar ppt bhusawal
POH seminar ppt bhusawal
Dhiraj Mahajan
 

What's hot (18)

Siva relay engg
Siva relay enggSiva relay engg
Siva relay engg
 
MY CV
MY CVMY CV
MY CV
 
Testing & Commissioning Engineer
Testing & Commissioning EngineerTesting & Commissioning Engineer
Testing & Commissioning Engineer
 
CV
CVCV
CV
 
Engr. Ayaz Khan CV11 (1)
Engr.  Ayaz Khan CV11 (1)Engr.  Ayaz Khan CV11 (1)
Engr. Ayaz Khan CV11 (1)
 
Resume 2016
Resume 2016Resume 2016
Resume 2016
 
Resume 2016
Resume 2016Resume 2016
Resume 2016
 
Ashok Resume-2015
Ashok Resume-2015Ashok Resume-2015
Ashok Resume-2015
 
Updated resume
Updated resumeUpdated resume
Updated resume
 
Kumar RESUME
Kumar RESUMEKumar RESUME
Kumar RESUME
 
ELEC.ENG CV
ELEC.ENG CVELEC.ENG CV
ELEC.ENG CV
 
UPDATED CV-1
UPDATED CV-1UPDATED CV-1
UPDATED CV-1
 
PRAVASH _PANDA RESUME....2015
PRAVASH _PANDA RESUME....2015PRAVASH _PANDA RESUME....2015
PRAVASH _PANDA RESUME....2015
 
Demolition of a former mine site - Luke Egan and David Wood
Demolition of a former mine site - Luke Egan and David WoodDemolition of a former mine site - Luke Egan and David Wood
Demolition of a former mine site - Luke Egan and David Wood
 
Equipment failure - a liability or an asset? - Roger Costanzi
Equipment failure - a liability or an asset? - Roger CostanziEquipment failure - a liability or an asset? - Roger Costanzi
Equipment failure - a liability or an asset? - Roger Costanzi
 
sivachandran resume
sivachandran resumesivachandran resume
sivachandran resume
 
Mohamed ElGazzar Egypt
Mohamed ElGazzar EgyptMohamed ElGazzar Egypt
Mohamed ElGazzar Egypt
 
POH seminar ppt bhusawal
POH seminar ppt bhusawalPOH seminar ppt bhusawal
POH seminar ppt bhusawal
 

Similar to Replacement and reconnection of breaker in 115 kV substation - Final (English)

Report on Madras Atomic Power Station Emass Coolant Channel Replacement
Report on Madras Atomic Power Station Emass Coolant Channel ReplacementReport on Madras Atomic Power Station Emass Coolant Channel Replacement
Report on Madras Atomic Power Station Emass Coolant Channel Replacement
Sujit Tharakan
 
33 kV towerline roadcrossing design modification - Final (English)
33 kV towerline roadcrossing design modification - Final (English)33 kV towerline roadcrossing design modification - Final (English)
33 kV towerline roadcrossing design modification - Final (English)
Pablo Miguel Jurado
 
Innovative solution for line uprating
Innovative solution for line upratingInnovative solution for line uprating
Innovative solution for line uprating
Harish Agarwal
 
Innovative solution for line uprating
Innovative solution for line upratingInnovative solution for line uprating
Innovative solution for line uprating
Harish Agarwal
 
Harish aggarwal
Harish aggarwalHarish aggarwal
Harish aggarwal
Harish Agarwal
 
Sayan CESC LT Report.pdf
Sayan  CESC LT Report.pdfSayan  CESC LT Report.pdf
Sayan CESC LT Report.pdf
SayanBasak15
 
Kanchrapara Railway workshop Project(Short)
Kanchrapara Railway workshop Project(Short)Kanchrapara Railway workshop Project(Short)
Kanchrapara Railway workshop Project(Short)
babai das
 
Michael Wood - Loader electric shocks, a case study
Michael Wood - Loader electric shocks, a case studyMichael Wood - Loader electric shocks, a case study
Michael Wood - Loader electric shocks, a case study
NSW Environment and Planning
 
Remediation of Old Substations for Arc Flash hazard
Remediation of Old Substations for Arc Flash hazardRemediation of Old Substations for Arc Flash hazard
Remediation of Old Substations for Arc Flash hazard
IJAPEJOURNAL
 
resume_2015_11_19_11_22_24_986
resume_2015_11_19_11_22_24_986resume_2015_11_19_11_22_24_986
resume_2015_11_19_11_22_24_986
sheik syedali
 
132 k v-substation-training-for-students
132 k v-substation-training-for-students132 k v-substation-training-for-students
132 k v-substation-training-for-students
Sanjay Kumar Sharma
 
Final Presentation Talha (1).pptx
Final Presentation Talha (1).pptxFinal Presentation Talha (1).pptx
Final Presentation Talha (1).pptx
TalhaAbdulRehman2
 
Wind Power Plant Planning And Commisioning
Wind Power Plant  Planning  And CommisioningWind Power Plant  Planning  And Commisioning
Wind Power Plant Planning And Commisioning
Suraj Naik
 
Tutuka Power Station
Tutuka Power StationTutuka Power Station
Tutuka Power Station
Site Web
 
POH seminar bhusawal
POH seminar bhusawal POH seminar bhusawal
POH seminar bhusawal
Dhiraj Mahajan
 
EXPLINER
EXPLINEREXPLINER
AEP texas project edison award winner
AEP texas project edison award winnerAEP texas project edison award winner
AEP texas project edison award winner
Dave Bryant
 
Results of DigitArc Electrode Regulator and SmartArc power input optimization...
Results of DigitArc Electrode Regulator and SmartArc power input optimization...Results of DigitArc Electrode Regulator and SmartArc power input optimization...
Results of DigitArc Electrode Regulator and SmartArc power input optimization...
AMI GE International
 
Fibre installation - Athene and Duffs Road Station[12].doc
Fibre installation - Athene and Duffs Road Station[12].docFibre installation - Athene and Duffs Road Station[12].doc
Fibre installation - Athene and Duffs Road Station[12].doc
Thandabantu Magengelele
 
laos-tj-2016
laos-tj-2016laos-tj-2016
laos-tj-2016
Omar Ferro
 

Similar to Replacement and reconnection of breaker in 115 kV substation - Final (English) (20)

Report on Madras Atomic Power Station Emass Coolant Channel Replacement
Report on Madras Atomic Power Station Emass Coolant Channel ReplacementReport on Madras Atomic Power Station Emass Coolant Channel Replacement
Report on Madras Atomic Power Station Emass Coolant Channel Replacement
 
33 kV towerline roadcrossing design modification - Final (English)
33 kV towerline roadcrossing design modification - Final (English)33 kV towerline roadcrossing design modification - Final (English)
33 kV towerline roadcrossing design modification - Final (English)
 
Innovative solution for line uprating
Innovative solution for line upratingInnovative solution for line uprating
Innovative solution for line uprating
 
Innovative solution for line uprating
Innovative solution for line upratingInnovative solution for line uprating
Innovative solution for line uprating
 
Harish aggarwal
Harish aggarwalHarish aggarwal
Harish aggarwal
 
Sayan CESC LT Report.pdf
Sayan  CESC LT Report.pdfSayan  CESC LT Report.pdf
Sayan CESC LT Report.pdf
 
Kanchrapara Railway workshop Project(Short)
Kanchrapara Railway workshop Project(Short)Kanchrapara Railway workshop Project(Short)
Kanchrapara Railway workshop Project(Short)
 
Michael Wood - Loader electric shocks, a case study
Michael Wood - Loader electric shocks, a case studyMichael Wood - Loader electric shocks, a case study
Michael Wood - Loader electric shocks, a case study
 
Remediation of Old Substations for Arc Flash hazard
Remediation of Old Substations for Arc Flash hazardRemediation of Old Substations for Arc Flash hazard
Remediation of Old Substations for Arc Flash hazard
 
resume_2015_11_19_11_22_24_986
resume_2015_11_19_11_22_24_986resume_2015_11_19_11_22_24_986
resume_2015_11_19_11_22_24_986
 
132 k v-substation-training-for-students
132 k v-substation-training-for-students132 k v-substation-training-for-students
132 k v-substation-training-for-students
 
Final Presentation Talha (1).pptx
Final Presentation Talha (1).pptxFinal Presentation Talha (1).pptx
Final Presentation Talha (1).pptx
 
Wind Power Plant Planning And Commisioning
Wind Power Plant  Planning  And CommisioningWind Power Plant  Planning  And Commisioning
Wind Power Plant Planning And Commisioning
 
Tutuka Power Station
Tutuka Power StationTutuka Power Station
Tutuka Power Station
 
POH seminar bhusawal
POH seminar bhusawal POH seminar bhusawal
POH seminar bhusawal
 
EXPLINER
EXPLINEREXPLINER
EXPLINER
 
AEP texas project edison award winner
AEP texas project edison award winnerAEP texas project edison award winner
AEP texas project edison award winner
 
Results of DigitArc Electrode Regulator and SmartArc power input optimization...
Results of DigitArc Electrode Regulator and SmartArc power input optimization...Results of DigitArc Electrode Regulator and SmartArc power input optimization...
Results of DigitArc Electrode Regulator and SmartArc power input optimization...
 
Fibre installation - Athene and Duffs Road Station[12].doc
Fibre installation - Athene and Duffs Road Station[12].docFibre installation - Athene and Duffs Road Station[12].doc
Fibre installation - Athene and Duffs Road Station[12].doc
 
laos-tj-2016
laos-tj-2016laos-tj-2016
laos-tj-2016
 

Replacement and reconnection of breaker in 115 kV substation - Final (English)

  • 1. OBJETIVE: The objective is to present the replacement and re-connection job (doing Live Line Work) of an SF6 breaker unit, from S&C, in the 115 kW & 20 MW substation of Join Operations, in SUG oil field, Kuwait. DEVELOPMENT: After more than 5 years working for different utilities, ELESA S.A., which is a company dedicated to maintenance, consulting and Live Line training in both local and international levels, did contact with IMCO company which carries out construction and maintenance projects in Kuwait and other Middle East countries. An agreement between companies was established, that allow us to complement and enrich ourselves. In this opportunity the challenge was to replace an SF6 breaker unit, from S&C, that was failed due to gas leakage. It was located in a radial substation that supplies 20 MW to the high production SUG Oil Field. In the emergency, and in order to restore the power supply, the complete circuit-switcher was by-passed, and a shutdown was programmed to replace the interrupter. 1 COMISIÓN DE INTEGRACIÓN ENERGÉTICA REGIONAL REPLACEMENT OF CIRCUIT-SWITCHER IN 115 KV SUBSTATION Author/s: Carlos Arata Company: ELESA International S.A. Author/s: Jalal Mohesen – Pablo Jurado Company: IMCO Engineering & Construction Co. COMPANY INFORMATION ELESA SA Telephone: (54) 93461 512966 E-mail: info@elesa.com.ar c.arata@elesa.com.ar IMCO Address: P.O. Box 9309 Ahmadi, Kuwait Zip Cod: 61004 Telephone: (965) 2398 1661 Fax: (965) 2398 4708 E-Mail: pjurado@imcokw.com jmohsen@imcokw.com KEY-WORDS: Uninterrupted production – Innovation – Complementation between companies COMPANY: ELESA SA - IMCO Engineering & Construction Co. COUNTRY: Kuwait Type: Technical Paper Kuwait, May 2011.
  • 2. By-passed circuit-switcher By chance I was giving training and refreshment course to the Live Line crews when I knew about the equipment failure. It seems to me and interesting challenge, and us when to see the substation. The job to be carried out was similar to others that we have already made at the 66 kV substation of EDEN Company in Argentina. But the two main differences were, by one side, the unavailability in Kuwait of the equipment that ELESA has for substation jobs, and by the other side, the generous safety distances in the substation portal structure. After discussing the possibility of doing the job by applying Live Line Work, the scheduled shutdown was suspended. The similar jobs previously done consisted in by- passing measurement and operation equipments, for maintenance, which avoided the replacement of them, thing that made no sense at that time. We did these types of jobs since 2002, when we finished the construction of the prototype for working in substations. By-pass 66 kV Substation, EDEN, October 2003 Steps of the task Basically the Live Line Work in this case consisted of 4 main steps which are: 1) Replacement of the failed breaker unit 2) Circuit-Switcher-to-Surge Arrester jumpers installation 3) Circuit-Switcher-to-Line jumpers installation 4) Removal of the temporary by-pass jumpers and old jumpers from line-to- circuit switcher (having close the circuit-switcher previously) 1) Replacement of failed breaker unit The failed unit was the middle one, which is the most difficult to work on, for all steps. Two Class A, approved to work up to 132 kV, insulated lift, were used to do the job. We had to study carefully the safety distance to work on the installation. 2 COMISIÓN DE INTEGRACIÓN ENERGÉTICA REGIONAL
  • 3. General view and distances The lift trucks that we used have two articulated booms, with the upper one telescopic (Class A). These features make them quite versatile to work in complicated installations, giving as good flexibility to find the most suitable position. Besides this, they have a material handling system with 700 lbs capacity in the worst condition. We used this feature to remove the failed unit and to install the new one (Step 1, see the following picture) Installing the new SF6 unit 2) Transformer side jumper installation One again here the more complicated to install was the central phase jumper, to which we had access by positioning the bucket between the insulators of the circuit- switcher. In order to connect the circuit- breaker with the jumpers on the surge arrester, and due to there wasn’t enough room to work by barehand method, we installed a jumper by using hotsticks, made of extra-flexible cooper conductor (120 mm²) mechanically reinforced with an extra- flexible steel wire, and with two duckbill clamps of 400 A capacity each one, which was much more than we need, an also this feature allowed us to handle the jumper by using two sticks, therefore improving the safety at the work. 3) Circuit-switcher-to-line jumpers installation The jumpers to be installed were 6 m long. First they were installed in the pedestal insulator of the open switch, and then in the lug of the tension clamp. 3 COMISIÓN DE INTEGRACIÓN ENERGÉTICA REGIONAL
  • 4. Leaving the lug free But as n the lug there was the existing permanent jumper still connected forming a loop in which the by-pass was installed, before connecting the new jumper a piece of the old jumper had to be removed. In this case, due to the distances at the portal side are wide enough there is no difference in starting to work in the middle phase or in the lateral ones. Going up with the new jumper The new jumper was attached first to the main conductor using a short flexible jumper, before connecting both lugs. This short jumper took the capacitive load of the new jumper and mechanically insures the connection to avoid an unexpected drop of the jumper. Fixing the new jumper to the dead-end terminal 4) Removal of the temporary by-pass jumpers and old jumpers from line-to-circuit switcher (having closed the circuit-switcher previously) Once the new permanent jumpers have been connected, it was missing to remove the temporary by-pass jumpers installed during the emergency, and the original jumpers from line- to-switch that were tied back forming a loop. This task was done working with simultaneously with two insulated lifts, due to they were available as well as the necessary personnel. The synchronization of the task was in charge of the supervisor on ground, and the good communication was insured by using walkie- talkies. 4 COMISIÓN DE INTEGRACIÓN ENERGÉTICA REGIONAL
  • 5. The operation of disconnection of the by-pass was made with hotsticks according to the fundamentals of the barehand method, in order to eliminate any possibility of one lineman to be in series with the circuit. Preparation to disconnect the by-pass The by-pass jumper to be removed was still attached to the old piece of jumper by an insulated rope, which is lately removed, while the other crew picked-up the by-pass jumper. The other crew removes the by-pass jumper Removal of the by-pass jumper with two crews working together Having completed the above mentioned step, the last thing to do was to remove the old permanent jumpers, which were cut in three pieces to avoid they were opened due to their elastic memory while removing, since, we must remember, these jumpers were 6 m long. 5 COMISIÓN DE INTEGRACIÓN ENERGÉTICA REGIONAL
  • 6. CONCLUSIONS The technician that was sent by S&C (the manufacturer of the equipment to be replaced) didn’t know about the possibility to do this job Live, although it could done in a safe way and according to the previously developed procedure. The execution of this Live Line Work avoided a costly shutdown to the oil company, that was planned to be of at least 8 hours with a loss of approximately u$s 1 million in differed oil. In addition the execution of this job is an important precedent to introduce the concept of Live Line Work in Substations that had never been considered before in this country. LESSON LERNT The conjunction of qualified personnel, and necessary equipment together with the team work for the development of the procedure and the explanation of it to the people who make the decisions (which showed reluctant at the beginning), allowed the completion of a this kind of job for the first time in the country and probably in all Gulf area. RECOMENDATION Start thinking that a Live Line Work in Substation is possible until the contrary is demonstrated, don’t think in the reverse way. Site work team ELESA SA Carlos Arata IMCO Pablo Jurado Khaled Alí Manssur Mohamed Abou Elenin Nabil Abd el Mohesen Ahmed Sultan Mohamed Mohamed Abdul Ghani Mohamed Khalaf Shakoor Rheda Mohamed V. Perumal 6 COMISIÓN DE INTEGRACIÓN ENERGÉTICA REGIONAL
  • 7. CONCLUSIONS The technician that was sent by S&C (the manufacturer of the equipment to be replaced) didn’t know about the possibility to do this job Live, although it could done in a safe way and according to the previously developed procedure. The execution of this Live Line Work avoided a costly shutdown to the oil company, that was planned to be of at least 8 hours with a loss of approximately u$s 1 million in differed oil. In addition the execution of this job is an important precedent to introduce the concept of Live Line Work in Substations that had never been considered before in this country. LESSON LERNT The conjunction of qualified personnel, and necessary equipment together with the team work for the development of the procedure and the explanation of it to the people who make the decisions (which showed reluctant at the beginning), allowed the completion of a this kind of job for the first time in the country and probably in all Gulf area. RECOMENDATION Start thinking that a Live Line Work in Substation is possible until the contrary is demonstrated, don’t think in the reverse way. Site work team ELESA SA Carlos Arata IMCO Pablo Jurado Khaled Alí Manssur Mohamed Abou Elenin Nabil Abd el Mohesen Ahmed Sultan Mohamed Mohamed Abdul Ghani Mohamed Khalaf Shakoor Rheda Mohamed V. Perumal 6 COMISIÓN DE INTEGRACIÓN ENERGÉTICA REGIONAL