SlideShare a Scribd company logo
1 of 28
Build a 40 tones cement silo at narrow space
Author : Chandra Manik
Date : October 2016
Build a 40 tones cement silo at narrow
space
1
Table of contents
1. Objective
2. Project risks
3. Technical consideration to build cement silo
4. Summary and result
5. Appendix
Appendix 1-Foundation using bore pile
Appendix 2-Stress analysis 3D Model
Appendix 3-On site erection method
Build a 40 tones cement silo at narrow
space
2
1. Project objective
The project objective is to build a 40 tones cement silo without technically disturb the
existing equipments nearby. The location of this new silo is 5 meters c/c to existing
silo with limited space available for mechanized erection and installation. The silo is
designed by utilizing the load cell to measure the cement weight for easier daily
reporting on cement consumption.
Build a 40 tones cement silo at narrow
space
3
2. Project risks
Build a 40 tones cement silo at narrow
space
4
NO RISK RISK LEVEL MITIGATION ACTIONS
P E S R
1 Foundation
Soil must stable 6 10 40 2400 High Perform soil test and seek advices for civil engineer
Water must drained 2 10 30 600 High Provide submersible pump during construction
2 Steel Structure
Safety factor 4 to 6 2 6 40 480 High Do analysis using manual calculation or
finite element method
Welding quality 6 10 30 1800 High Hire only certified welder and check work
result regularly
3 Loadcell
Loadcell capacity 1 6 7 42 Medium Choose a loadcell with total capacity 2 times
of total load. Example : silo dead load 40 tns
Using 4 loadcell then each loadcell at least 20 tns
capacity, in total become 80 tonnes versus 45 tns
4 Erection & Installation
Silo inclination 6 6 15 540 High Check and perform field measurement to ensure
silo inclination
R (Risk index) = P (probability) * E ( exposure) * S (Severity)
3. Technical consideration to build cement silo
Build a 40 tones cement silo at narrow
space
5
ITEMS WHAT TO DO
Foundation 1. Perform soil test
2. Consult the foundation depth and foundation type to be use with civil work consultant
Steel Structure 1. Design the steel structure with safety factor in the range 4 to 6
2. Do stress analysis using finite element method using static or buckling condition
Loadcell 1. Total loadcell capacity at least 2 times of silo capacity
2. Location of loadcell is best above center gravity of silo or at least coicident
Erection & Installation 1. Using hoist crane if space is possible
2. Using onsite construction for narrow space as shown in this presentation
4. Summary and result
Build a 40 tones cement silo at narrow
space
6
ITEMS WHAT TO DO
Foundation 1. Soil test performed on field and the result being used to build foundation
2. Foundation spesification shown at appendix 1, 18 meter depth and 1 meter bore pile
Steel Structure 1. Stress analysis simulation using finite element method showing a good result
with safety factor from 4 to 60 with displacement maximum 1.6 mm and elongation 0.02%
Loadcell 1. Dead load of silo is 45 tonnes, using 4 load cells with each loadcell has 20 tonnes capacity
Erection & Installation 1. On site erection as shown in appendix 3 was succesfull
Build a 40 tones cement silo at narrow
space
7
APPENDIX
Appendix 1- Foundation using bore pile
Build a 40 tones cement silo at narrow
space
8
The bore pile foundation with depth 18
meters & diameter 1 m.The foundation cap
depth 1.5 m. Bore pile using reinforced steel
diameter 19 mm ( following Indonesian
Standard)
Appendix 2- Stress analysis 3D Model
Build a 40 tones cement silo at narrow
space
9
Appendix 2- Stress analysis load and assumptions
Build a 40 tones cement silo at narrow
space
10
Load is distributed equally at
four support as shown at the
left right. The load amount as
below :
1. Silo main body load 4.4
tonnes
2. Cement material load
maximum 40 tonnes
3. Total load 44.4, rounded to
45 tonnes.
4. 45 toness converted to
weight (multiply gravity 9,8
m/s2) become 441 kN.
5. Each support receive load
110,25 kNAssumptions :
1. Static analisys
2. Buckling effect not included due to software
license liitation
Appendix 2- Stress analysis fixtures location
Build a 40 tones cement silo at narrow
space
11
The four legs bottom surface where
anchors bolt attached are assigned
as fixtures and fix.
Appendix 2- Stress analysis mesh and material
Build a 40 tones cement silo at narrow
space
12
Mesh type is blended curvature with 8
nodes Jacobian. Total nodes 350k and
aspect ratio 221. Material is AISI 1202
with yield strength 3.51 * E+8 N/m2
Appendix 2- Stress distirbution on silo structure
Build a 40 tones cement silo at narrow
space
13
In general, stress
distirbution is higher at
the top section but still
half of yield strength
and getting smaller at
the lower section
(near the structure
foundation).
Appendix 2- Critical stress distribution on silo structure
Build a 40 tones cement silo at narrow
space
14
The maximum stress
location is at loadcell
support, almost half of
the material yield
strength. Additional
ribs at the joint will
make this support
more safer.
Appendix 2- Safety factor distribution of silo structure
Build a 40 tones cement silo at narrow
space
15
Overall safety factor is
high with maximum
65. The lowest is 3.9
located where the
loadcell attached.
Adding more ribs will
increase the safety at
this location.
Appendix 2- Critical safety factor distribution of silo structure
Build a 40 tones cement silo at narrow
space
16
A close zoom
showing the area
where its safety
factor in the range
3.9 to 10.
Appendix 2- Displacement distribution of silo structure
Build a 40 tones cement silo at narrow
space
17
Stee structure
displacement is in
the range of yield
strength. Maximum
displacement is 1.36
mm at the top
section of structure.
Appendix 2 - Magnified zoom on high displacement on silo
structure
Build a 40 tones cement silo at narrow
space
18
A closer zoom showing
the are where structure
displament is high ( 1.3
mm).
Appendix 2- Elongation distribution of silo structure
Build a 40 tones cement silo at narrow
space
19
Elongation is one of
the critical properties of
material before it
reaches ultimate point.
The ultimate point
material mostly at 0.2%
elongation. Based on
the simulation,
maximum elongation
here is 0.028% located
at silo loadcell support.
Appedix 2-Magnified elongation of silo structure
Build a 40 tones cement silo at narrow
space
20
A closer look on
maximum elongation
of steel structure.
Appendix 3- On site erection method
Build a 40 tones cement silo at narrow
space
21
After foundation mature and
the pile cap strength has been
measured and meet quality
with strength 250 kgf/cm2 then
raise 3 main coloumb of the H
beam 300 x 300 and then joint
them with bracing per design
as shown at left picture
1
Appendix 3- On site erection method
Build a 40 tones cement silo at narrow
space
22
Weld the silo main body
(circular shell ) directly at the
center of silo structure. Raise
the finished shell and then joint
with next circular shell. To
supper this activity, a hoist at
top side of coulomb is needed.
The welding shall follow the
American Standard or
Indonesian standard . Welding
shall be performed V but joint
both inside and outside of
circular shell.
2
Appendix 3- On site erection method
Build a 40 tones cement silo at narrow
space
23
As shown, almost finish shell
joint of silo. At this stage
careful must be provided to
ensure the shell will not
collapse to other side. .
3
Appendix 3- On site erection method
Build a 40 tones cement silo at narrow
space
24
The final stage of joint has
been reached. Add circular ring
to increase the strength of joint
between adjacent shell. Also all
bracing at 4 columns has been
welded.
4
Appendix 3 - On site erection method
Build a 40 tones cement silo at narrow
space
25
At shown, the final stage has been reached. The
silo straightness must be measured and its contact
joint for load cell must be lock securely. Next step
will be installing the screw conveyors, filters and
pressure relief valve
5
Appendix 3- On site erection method
Build a 40 tones cement silo at narrow
space
26
Silo now in finishing stage, as
shown far left pictures
complete with maintenance
deck.
The pictures at the right is load
cell with jacking housing for
easy maintenance, this image
was taken after 2 years in
service, due to close to sea the
rusty is growing faster. Need
repainting with marine
application on structure to
reduce the rusty.
At bottom side is contact joint
of load cell .
References
Build a 40 tones cement silo at narrow
space
27
1. Solidworks 2016, Linear stress analysis, viewed 4 October 2016,
http://www.solidworks.com/sw/products/simulation/stress-analysis.htm
2. Marklew, CM. Silo weighing. Bulk 96 design seminar.
3. Carson, J.W., Jenkyn,R.T. Load development and structural consideration in silo
design. Reliable flow of particulate solid II, August 1993
4. Scale manufacturer assosication, Loadcell application and test guideline, Ohio 2010
THANK YOU !
You can reach the autor at below :
chandr4_mnk@yahoo.com
chandramanik777@gmail.com
About the author :
Graduated from Mechanical Engineering Faculty of
Institute Technology of Bandung (ITB). At final year of
education focusing on fluid mechanic topic related to
Kaplan turbine performance, laminar and turbulent flow
in piping, positive displacement compressor and wind
turbine design. Finally choosing the topic on design of
centrifugal pump by utilizing Computational Fluid
Dynamic-Fluent as thesis for final exam.
More than 12 years experiences in various disciplines of
Engineering covering : Project Management, New
product development, Operation Management,
Continuous Development, Machine Maintenance.
Have been working in Global company such as :
SANYO Indonesia, KSB Indonesia and Monier
International membership for Project Management
Institute (www.pmi.org) . Manufacturing Engineering
Society ( www.sme.org) . American Society for Quality
(www.asq.org) .
Build a 40 tones cement silo at narrow
space
28

More Related Content

What's hot

Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)
AJAY SHAHU
 
Multi story building construction training report anshul
Multi story building construction training report anshulMulti story building construction training report anshul
Multi story building construction training report anshul
Anshul Shakya
 

What's hot (20)

Railway over bridge
Railway over bridgeRailway over bridge
Railway over bridge
 
Segmental bridge constructin techniques
Segmental bridge constructin techniquesSegmental bridge constructin techniques
Segmental bridge constructin techniques
 
Construction of well foundation
Construction of well foundation Construction of well foundation
Construction of well foundation
 
Boq piling works
Boq   piling worksBoq   piling works
Boq piling works
 
Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)
 
Slip formwork for chimney
Slip formwork for chimneySlip formwork for chimney
Slip formwork for chimney
 
Slip form
Slip formSlip form
Slip form
 
IRJET- A Review on Box Pushing Technique
IRJET- A Review on Box Pushing TechniqueIRJET- A Review on Box Pushing Technique
IRJET- A Review on Box Pushing Technique
 
Spine and wing method for box girders
Spine and wing method for box girdersSpine and wing method for box girders
Spine and wing method for box girders
 
FORM WORK & SLIPFORM
FORM WORK & SLIPFORMFORM WORK & SLIPFORM
FORM WORK & SLIPFORM
 
civil enginnering industrial training report
civil enginnering industrial training report civil enginnering industrial training report
civil enginnering industrial training report
 
Slipform
SlipformSlipform
Slipform
 
19-6-818-00-A
19-6-818-00-A19-6-818-00-A
19-6-818-00-A
 
Segmental bridge construction
Segmental bridge constructionSegmental bridge construction
Segmental bridge construction
 
Case study steel composite structure
Case study  steel composite structureCase study  steel composite structure
Case study steel composite structure
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
Svp field training report final
Svp field training report finalSvp field training report final
Svp field training report final
 
Presentation on prestressing prepared by Rais Uddin
Presentation on prestressing prepared by Rais UddinPresentation on prestressing prepared by Rais Uddin
Presentation on prestressing prepared by Rais Uddin
 
Viaduct
Viaduct Viaduct
Viaduct
 
Multi story building construction training report anshul
Multi story building construction training report anshulMulti story building construction training report anshul
Multi story building construction training report anshul
 

Viewers also liked

013 YES Catalog Web Plus Worksheet 10-11-13
013 YES Catalog Web Plus Worksheet 10-11-13013 YES Catalog Web Plus Worksheet 10-11-13
013 YES Catalog Web Plus Worksheet 10-11-13
Ben Yager
 
Brennan - Soil Survey Applications of LiDAR Data
Brennan - Soil Survey Applications of LiDAR DataBrennan - Soil Survey Applications of LiDAR Data
Brennan - Soil Survey Applications of LiDAR Data
Jose A. Hernandez
 
Brandel - Planning County Ditch Projects
Brandel - Planning County Ditch ProjectsBrandel - Planning County Ditch Projects
Brandel - Planning County Ditch Projects
Jose A. Hernandez
 
Mill 14-1-15 - Sheet - A107 - PROPOSED EAST & SOUTH ELEVATIONS
Mill 14-1-15 - Sheet - A107 - PROPOSED EAST & SOUTH ELEVATIONSMill 14-1-15 - Sheet - A107 - PROPOSED EAST & SOUTH ELEVATIONS
Mill 14-1-15 - Sheet - A107 - PROPOSED EAST & SOUTH ELEVATIONS
Sin Byrne
 
E n e r g o Cement Plant - Projects
E n e r g o Cement Plant - ProjectsE n e r g o Cement Plant - Projects
E n e r g o Cement Plant - Projects
Daniel DRAGOSIN
 
Vibrating machinery steel skid on piles
Vibrating machinery steel skid on pilesVibrating machinery steel skid on piles
Vibrating machinery steel skid on piles
r2d22
 
Sap tutorial for dynamics
Sap tutorial for dynamicsSap tutorial for dynamics
Sap tutorial for dynamics
colosimoricardo
 
Construction Methodology Scheduling1
Construction Methodology Scheduling1Construction Methodology Scheduling1
Construction Methodology Scheduling1
Allan Leyte
 

Viewers also liked (20)

Cement silo
Cement siloCement silo
Cement silo
 
013 YES Catalog Web Plus Worksheet 10-11-13
013 YES Catalog Web Plus Worksheet 10-11-13013 YES Catalog Web Plus Worksheet 10-11-13
013 YES Catalog Web Plus Worksheet 10-11-13
 
Same time, different channel
Same time, different channelSame time, different channel
Same time, different channel
 
Brennan - Soil Survey Applications of LiDAR Data
Brennan - Soil Survey Applications of LiDAR DataBrennan - Soil Survey Applications of LiDAR Data
Brennan - Soil Survey Applications of LiDAR Data
 
Brandel - Planning County Ditch Projects
Brandel - Planning County Ditch ProjectsBrandel - Planning County Ditch Projects
Brandel - Planning County Ditch Projects
 
Mill 14-1-15 - Sheet - A107 - PROPOSED EAST & SOUTH ELEVATIONS
Mill 14-1-15 - Sheet - A107 - PROPOSED EAST & SOUTH ELEVATIONSMill 14-1-15 - Sheet - A107 - PROPOSED EAST & SOUTH ELEVATIONS
Mill 14-1-15 - Sheet - A107 - PROPOSED EAST & SOUTH ELEVATIONS
 
E n e r g o Cement Plant - Projects
E n e r g o Cement Plant - ProjectsE n e r g o Cement Plant - Projects
E n e r g o Cement Plant - Projects
 
Vibrating machinery steel skid on piles
Vibrating machinery steel skid on pilesVibrating machinery steel skid on piles
Vibrating machinery steel skid on piles
 
Comparison of lateral analysis of reinforced concrete and steel silo
Comparison of lateral analysis of reinforced concrete and steel siloComparison of lateral analysis of reinforced concrete and steel silo
Comparison of lateral analysis of reinforced concrete and steel silo
 
The Ins & Outs of Concrete Silo Inspection
The Ins & Outs of Concrete Silo InspectionThe Ins & Outs of Concrete Silo Inspection
The Ins & Outs of Concrete Silo Inspection
 
Storage design for corn yp
Storage design for corn ypStorage design for corn yp
Storage design for corn yp
 
Seismic response of reinforced concrete silos
Seismic response of reinforced concrete silosSeismic response of reinforced concrete silos
Seismic response of reinforced concrete silos
 
Steel silo failure case study
Steel silo failure case study  Steel silo failure case study
Steel silo failure case study
 
Sap tutorial for dynamics
Sap tutorial for dynamicsSap tutorial for dynamics
Sap tutorial for dynamics
 
Post Tensioning System Utracon Structural system Pvt Ltd
Post Tensioning System Utracon Structural system Pvt LtdPost Tensioning System Utracon Structural system Pvt Ltd
Post Tensioning System Utracon Structural system Pvt Ltd
 
Company presentation fabricator feb20_2016
Company presentation fabricator feb20_2016Company presentation fabricator feb20_2016
Company presentation fabricator feb20_2016
 
Grain quality preservation: A Powerful & Revolutionary technology
Grain quality preservation: A Powerful & Revolutionary technologyGrain quality preservation: A Powerful & Revolutionary technology
Grain quality preservation: A Powerful & Revolutionary technology
 
Aeration of storage structures
Aeration of storage structuresAeration of storage structures
Aeration of storage structures
 
Analysis of warehouse in staad pro.
Analysis of warehouse in staad pro. Analysis of warehouse in staad pro.
Analysis of warehouse in staad pro.
 
Construction Methodology Scheduling1
Construction Methodology Scheduling1Construction Methodology Scheduling1
Construction Methodology Scheduling1
 

Similar to Silo at narrow space

CE4410 Final Design Report
CE4410 Final Design ReportCE4410 Final Design Report
CE4410 Final Design Report
Chase Bowman
 
07 a80101 advanced structural design
07 a80101 advanced structural design07 a80101 advanced structural design
07 a80101 advanced structural design
imaduddin91
 
Pt slab design philosophy with slides and pictures showing benefit
Pt slab design philosophy  with slides and pictures showing benefitPt slab design philosophy  with slides and pictures showing benefit
Pt slab design philosophy with slides and pictures showing benefit
Perwez Ahmad
 
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEWRE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
Jaspreet singh
 
CIVIL CONSTRUCTION IN FATIMA FERTILIZER COMPANY LIMITED
CIVIL CONSTRUCTION INFATIMA FERTILIZER COMPANY LIMITEDCIVIL CONSTRUCTION INFATIMA FERTILIZER COMPANY LIMITED
CIVIL CONSTRUCTION IN FATIMA FERTILIZER COMPANY LIMITED
Water Birds (Ali)
 

Similar to Silo at narrow space (20)

The hanging basket stress calculation and stability analysis during cantileve...
The hanging basket stress calculation and stability analysis during cantileve...The hanging basket stress calculation and stability analysis during cantileve...
The hanging basket stress calculation and stability analysis during cantileve...
 
KUY Limeng,e20190482(I4GCI-B)_4.pdf
KUY Limeng,e20190482(I4GCI-B)_4.pdfKUY Limeng,e20190482(I4GCI-B)_4.pdf
KUY Limeng,e20190482(I4GCI-B)_4.pdf
 
CE4410 Final Design Report
CE4410 Final Design ReportCE4410 Final Design Report
CE4410 Final Design Report
 
Retrofitting of Bridge with Voided Slab to raise the Deck Level
Retrofitting of Bridge with Voided Slab to raise the Deck LevelRetrofitting of Bridge with Voided Slab to raise the Deck Level
Retrofitting of Bridge with Voided Slab to raise the Deck Level
 
Fettucine truss bridge
Fettucine truss bridgeFettucine truss bridge
Fettucine truss bridge
 
bridge report
bridge reportbridge report
bridge report
 
Building Structure Project 1 Report
Building Structure Project 1 ReportBuilding Structure Project 1 Report
Building Structure Project 1 Report
 
07 a80101 advanced structural design
07 a80101 advanced structural design07 a80101 advanced structural design
07 a80101 advanced structural design
 
Pt slab design philosophy with slides and pictures showing benefit
Pt slab design philosophy  with slides and pictures showing benefitPt slab design philosophy  with slides and pictures showing benefit
Pt slab design philosophy with slides and pictures showing benefit
 
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEWRE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
 
Fettuccine truss bridge report
Fettuccine truss bridge reportFettuccine truss bridge report
Fettuccine truss bridge report
 
A technical seminar bubble deck slab.pptx
A technical seminar bubble deck slab.pptxA technical seminar bubble deck slab.pptx
A technical seminar bubble deck slab.pptx
 
A technical seminar bubble deck slab.pptx
A technical seminar bubble deck slab.pptxA technical seminar bubble deck slab.pptx
A technical seminar bubble deck slab.pptx
 
Site visit report
Site visit reportSite visit report
Site visit report
 
Building Structure Project 1
Building Structure Project 1Building Structure Project 1
Building Structure Project 1
 
Stiffness degradation behavior of retrofitted rc infilled frame under cyclic ...
Stiffness degradation behavior of retrofitted rc infilled frame under cyclic ...Stiffness degradation behavior of retrofitted rc infilled frame under cyclic ...
Stiffness degradation behavior of retrofitted rc infilled frame under cyclic ...
 
Building structuresproject1 fettuccinnefinalm
Building structuresproject1 fettuccinnefinalmBuilding structuresproject1 fettuccinnefinalm
Building structuresproject1 fettuccinnefinalm
 
Fettucine Bridge Report
Fettucine Bridge ReportFettucine Bridge Report
Fettucine Bridge Report
 
Dynamic Analysis and Design of RCC solids storage structure by with ref...
Dynamic Analysis and Design of RCC       solids storage structure by with ref...Dynamic Analysis and Design of RCC       solids storage structure by with ref...
Dynamic Analysis and Design of RCC solids storage structure by with ref...
 
CIVIL CONSTRUCTION IN FATIMA FERTILIZER COMPANY LIMITED
CIVIL CONSTRUCTION INFATIMA FERTILIZER COMPANY LIMITEDCIVIL CONSTRUCTION INFATIMA FERTILIZER COMPANY LIMITED
CIVIL CONSTRUCTION IN FATIMA FERTILIZER COMPANY LIMITED
 

Silo at narrow space

  • 1. Build a 40 tones cement silo at narrow space Author : Chandra Manik Date : October 2016 Build a 40 tones cement silo at narrow space 1
  • 2. Table of contents 1. Objective 2. Project risks 3. Technical consideration to build cement silo 4. Summary and result 5. Appendix Appendix 1-Foundation using bore pile Appendix 2-Stress analysis 3D Model Appendix 3-On site erection method Build a 40 tones cement silo at narrow space 2
  • 3. 1. Project objective The project objective is to build a 40 tones cement silo without technically disturb the existing equipments nearby. The location of this new silo is 5 meters c/c to existing silo with limited space available for mechanized erection and installation. The silo is designed by utilizing the load cell to measure the cement weight for easier daily reporting on cement consumption. Build a 40 tones cement silo at narrow space 3
  • 4. 2. Project risks Build a 40 tones cement silo at narrow space 4 NO RISK RISK LEVEL MITIGATION ACTIONS P E S R 1 Foundation Soil must stable 6 10 40 2400 High Perform soil test and seek advices for civil engineer Water must drained 2 10 30 600 High Provide submersible pump during construction 2 Steel Structure Safety factor 4 to 6 2 6 40 480 High Do analysis using manual calculation or finite element method Welding quality 6 10 30 1800 High Hire only certified welder and check work result regularly 3 Loadcell Loadcell capacity 1 6 7 42 Medium Choose a loadcell with total capacity 2 times of total load. Example : silo dead load 40 tns Using 4 loadcell then each loadcell at least 20 tns capacity, in total become 80 tonnes versus 45 tns 4 Erection & Installation Silo inclination 6 6 15 540 High Check and perform field measurement to ensure silo inclination R (Risk index) = P (probability) * E ( exposure) * S (Severity)
  • 5. 3. Technical consideration to build cement silo Build a 40 tones cement silo at narrow space 5 ITEMS WHAT TO DO Foundation 1. Perform soil test 2. Consult the foundation depth and foundation type to be use with civil work consultant Steel Structure 1. Design the steel structure with safety factor in the range 4 to 6 2. Do stress analysis using finite element method using static or buckling condition Loadcell 1. Total loadcell capacity at least 2 times of silo capacity 2. Location of loadcell is best above center gravity of silo or at least coicident Erection & Installation 1. Using hoist crane if space is possible 2. Using onsite construction for narrow space as shown in this presentation
  • 6. 4. Summary and result Build a 40 tones cement silo at narrow space 6 ITEMS WHAT TO DO Foundation 1. Soil test performed on field and the result being used to build foundation 2. Foundation spesification shown at appendix 1, 18 meter depth and 1 meter bore pile Steel Structure 1. Stress analysis simulation using finite element method showing a good result with safety factor from 4 to 60 with displacement maximum 1.6 mm and elongation 0.02% Loadcell 1. Dead load of silo is 45 tonnes, using 4 load cells with each loadcell has 20 tonnes capacity Erection & Installation 1. On site erection as shown in appendix 3 was succesfull
  • 7. Build a 40 tones cement silo at narrow space 7 APPENDIX
  • 8. Appendix 1- Foundation using bore pile Build a 40 tones cement silo at narrow space 8 The bore pile foundation with depth 18 meters & diameter 1 m.The foundation cap depth 1.5 m. Bore pile using reinforced steel diameter 19 mm ( following Indonesian Standard)
  • 9. Appendix 2- Stress analysis 3D Model Build a 40 tones cement silo at narrow space 9
  • 10. Appendix 2- Stress analysis load and assumptions Build a 40 tones cement silo at narrow space 10 Load is distributed equally at four support as shown at the left right. The load amount as below : 1. Silo main body load 4.4 tonnes 2. Cement material load maximum 40 tonnes 3. Total load 44.4, rounded to 45 tonnes. 4. 45 toness converted to weight (multiply gravity 9,8 m/s2) become 441 kN. 5. Each support receive load 110,25 kNAssumptions : 1. Static analisys 2. Buckling effect not included due to software license liitation
  • 11. Appendix 2- Stress analysis fixtures location Build a 40 tones cement silo at narrow space 11 The four legs bottom surface where anchors bolt attached are assigned as fixtures and fix.
  • 12. Appendix 2- Stress analysis mesh and material Build a 40 tones cement silo at narrow space 12 Mesh type is blended curvature with 8 nodes Jacobian. Total nodes 350k and aspect ratio 221. Material is AISI 1202 with yield strength 3.51 * E+8 N/m2
  • 13. Appendix 2- Stress distirbution on silo structure Build a 40 tones cement silo at narrow space 13 In general, stress distirbution is higher at the top section but still half of yield strength and getting smaller at the lower section (near the structure foundation).
  • 14. Appendix 2- Critical stress distribution on silo structure Build a 40 tones cement silo at narrow space 14 The maximum stress location is at loadcell support, almost half of the material yield strength. Additional ribs at the joint will make this support more safer.
  • 15. Appendix 2- Safety factor distribution of silo structure Build a 40 tones cement silo at narrow space 15 Overall safety factor is high with maximum 65. The lowest is 3.9 located where the loadcell attached. Adding more ribs will increase the safety at this location.
  • 16. Appendix 2- Critical safety factor distribution of silo structure Build a 40 tones cement silo at narrow space 16 A close zoom showing the area where its safety factor in the range 3.9 to 10.
  • 17. Appendix 2- Displacement distribution of silo structure Build a 40 tones cement silo at narrow space 17 Stee structure displacement is in the range of yield strength. Maximum displacement is 1.36 mm at the top section of structure.
  • 18. Appendix 2 - Magnified zoom on high displacement on silo structure Build a 40 tones cement silo at narrow space 18 A closer zoom showing the are where structure displament is high ( 1.3 mm).
  • 19. Appendix 2- Elongation distribution of silo structure Build a 40 tones cement silo at narrow space 19 Elongation is one of the critical properties of material before it reaches ultimate point. The ultimate point material mostly at 0.2% elongation. Based on the simulation, maximum elongation here is 0.028% located at silo loadcell support.
  • 20. Appedix 2-Magnified elongation of silo structure Build a 40 tones cement silo at narrow space 20 A closer look on maximum elongation of steel structure.
  • 21. Appendix 3- On site erection method Build a 40 tones cement silo at narrow space 21 After foundation mature and the pile cap strength has been measured and meet quality with strength 250 kgf/cm2 then raise 3 main coloumb of the H beam 300 x 300 and then joint them with bracing per design as shown at left picture 1
  • 22. Appendix 3- On site erection method Build a 40 tones cement silo at narrow space 22 Weld the silo main body (circular shell ) directly at the center of silo structure. Raise the finished shell and then joint with next circular shell. To supper this activity, a hoist at top side of coulomb is needed. The welding shall follow the American Standard or Indonesian standard . Welding shall be performed V but joint both inside and outside of circular shell. 2
  • 23. Appendix 3- On site erection method Build a 40 tones cement silo at narrow space 23 As shown, almost finish shell joint of silo. At this stage careful must be provided to ensure the shell will not collapse to other side. . 3
  • 24. Appendix 3- On site erection method Build a 40 tones cement silo at narrow space 24 The final stage of joint has been reached. Add circular ring to increase the strength of joint between adjacent shell. Also all bracing at 4 columns has been welded. 4
  • 25. Appendix 3 - On site erection method Build a 40 tones cement silo at narrow space 25 At shown, the final stage has been reached. The silo straightness must be measured and its contact joint for load cell must be lock securely. Next step will be installing the screw conveyors, filters and pressure relief valve 5
  • 26. Appendix 3- On site erection method Build a 40 tones cement silo at narrow space 26 Silo now in finishing stage, as shown far left pictures complete with maintenance deck. The pictures at the right is load cell with jacking housing for easy maintenance, this image was taken after 2 years in service, due to close to sea the rusty is growing faster. Need repainting with marine application on structure to reduce the rusty. At bottom side is contact joint of load cell .
  • 27. References Build a 40 tones cement silo at narrow space 27 1. Solidworks 2016, Linear stress analysis, viewed 4 October 2016, http://www.solidworks.com/sw/products/simulation/stress-analysis.htm 2. Marklew, CM. Silo weighing. Bulk 96 design seminar. 3. Carson, J.W., Jenkyn,R.T. Load development and structural consideration in silo design. Reliable flow of particulate solid II, August 1993 4. Scale manufacturer assosication, Loadcell application and test guideline, Ohio 2010
  • 28. THANK YOU ! You can reach the autor at below : chandr4_mnk@yahoo.com chandramanik777@gmail.com About the author : Graduated from Mechanical Engineering Faculty of Institute Technology of Bandung (ITB). At final year of education focusing on fluid mechanic topic related to Kaplan turbine performance, laminar and turbulent flow in piping, positive displacement compressor and wind turbine design. Finally choosing the topic on design of centrifugal pump by utilizing Computational Fluid Dynamic-Fluent as thesis for final exam. More than 12 years experiences in various disciplines of Engineering covering : Project Management, New product development, Operation Management, Continuous Development, Machine Maintenance. Have been working in Global company such as : SANYO Indonesia, KSB Indonesia and Monier International membership for Project Management Institute (www.pmi.org) . Manufacturing Engineering Society ( www.sme.org) . American Society for Quality (www.asq.org) . Build a 40 tones cement silo at narrow space 28