AcceleratedSAP Phases
Phase 1 – Project Preparation
Phase 2 – Business Blueprint
Phase 3 – Realization
Phase 4 – Final Preparation
Phase 5 – Go Live and Support
The ASAP Roadmap was developed by SAP to help customers implement SAP software in a
quick, cost-effective manner. Utilizing this approach:
 minimizes the length of implementation,
 maximizes the utilization of TeamSAP and customer resources,
 results in a “Repetitive Model” that can be used with other implementations of SAP modules
or systems, and
 provides a process-oriented approach to Product Training.

Nineapps software services

Ravikiran0
Key Implementation Activities and Deliverables:
Accelerated SAP
Table D.2-2 Project Preparation Key Activities and Deliverables
Key Activities
Deliverables
 Finalize Project Team Organization
 Project Team Structure Organization Chart


Finalize Project Team Training Plan



Project Team Training Schedule




Develop Project Plans



Develop Project Strategies and Scope



Review Existing Implementations



Define Project Management Standards and
Procedures








Define Post-Implementation Support

Perform Technical Requirements Gathering 




Define Quality Assurance Plan





Prepare for Project Kickoff












Nineapps software services









Baseline Project Plans
Initial Activities Planned
Resource Plan
Draft:
o Implementation Strategy
o End-User Training Strategy
o Development Strategies
o Testing Strategy
o Technical Strategies
o Security and Controls Strategy
o High-level Project Scope Document
List of Lessons Learned
Project Management Standards and
Procedures (Issue Mgt Plan, Status Report
Format, Change Control Forms,
Documentation standards, etc,)

Post-Implementation Support Approach
Complete Technical Questionnaires
Define Technical Infrastructure Needs

Quality Assurance Plan

Kickoff Meeting

Ravikiran1
Key Implementation Activities and Deliverables:
Accelerated SAP

Nineapps software services

Ravikiran2
Key Implementation Activities and Deliverables:
Accelerated SAP
Table D.2-3 Business Blueprint Key Activities and Deliverables
Key Activities
Deliverables
 Conduct Project Team Training
 Execute Project Team Training Schedule




Define SAP Organizational Structure
Define Global Parameters
Prepare for Blueprint Workshops



SAP R/3 Hierarchy Definitions





Blueprint Workshop Schedule
List of Blueprint Workshop Participants
Blueprint Workshop Agendas



Conduct Blueprint Workshops





Finalize Project Scope






Finalize Development Scope





Finalize End-User Training Strategy



Business Blueprint Report
o Business Process Flows
o Policies and Procedures
o Gaps Identified
Business Process Master List (BPML)
Finalized Scope Document Signed off by
Customer
Development Scope: Reporting, Interfaces,
Conversions, Enhancements
End-User Training Strategy Signed-Off by
Customer
End User Training Requirements and
Materials Standards document
















Perform Cycle Planning for Prototyping
Develop Knowledge Transfer Plan





Create Technical Design
Develop Non-functional Requirements








Setup and Install Development
Environment
Conduct Peer/Solution/Technical Reviews



Nineapps software services






Cycle Plan for Prototyping
Knowledge Transfer Plan signed off by
Customer

Technical Design Document
Non-functional Requirements
Specifications Documentation
Installed Development System

Solution/Technical Review Findings
Reports



Ravikiran3
Key Implementation Activities and Deliverables:
Accelerated SAP


Business Blueprint Sign-off

Nineapps software services



Business Blueprint Documentation and
Phase completion signed-off by Customer

Ravikiran4
Key Implementation Activities and Deliverables:
Accelerated SAP
Table D.2-4

Realization Key Activities and Deliverables
Key Activities
Deliverables
 Define Master Data
 Master Data Definitions
 Baseline Configuration Completed
 Baseline Configuration and Documentation
 Conduct Unit Testing
 Completed Unit Testing and Associated
Scripts and Results


Final Configuration Completed






Create Security Authorizations
Develop Custom Design Specifications
(functional spec’s)
Develop Technical and Functional
Specifications
Coding and Unit Test for Conversions,
Reports, Interfaces and Enhancements
























Conversion Planning (Cutover) and
Preparation
Develop New Procedures and Policies

Finalize End-User Training Strategy
Establish Training Environment
Train Power Users
Plan SAP early watch Go-Live Quality
Assurance / Check
Plan and Execute System Test
Execute Cycle Testing
Develop Integration Test Plan(s)
Execute Integration Test
Design and Deliver Instructor Training
Material (if applicable)
Create End-User Training Programs and
Training Materials

Create Technical Design
Setup and Install Quality Assurance (QA)
Environment

Nineapps software services








Configured SAP System and Related
Documentation
Configured SAP User Profiles and Roles
Functional Specifications
Technical and Functional Specifications
Documentation and Associated Approvals
Completed Unit Testing for Development
Objects
Object Code for Development Objects
Initial Conversion (Cutover) Plan
Draft Legacy Retirement Plan
New Procedures and Policies
Documented/Approved







Approved End-User Training Strategy
Installed Training System
Trained Power Users and Trainers








System Test Plan
Volume and Stress Tested System
Cycle Testing Complete
Integration Test Plan
Integration Test Complete
Instructor Training Material









End-User Training Curriculum
End-User Training Materials
End-User Training Schedule
Facilities Reservations
Technical Design Document
Installed Quality Assurance System

Ravikiran5
Key Implementation Activities and Deliverables:
Accelerated SAP




Execute Communications Plan



Conduct Peer/Solution/Technical Reviews



Nineapps software services







Presentations
Newsletters
Solution/Technical Review Findings
Reports



Ravikiran6
Key Implementation Activities and Deliverables:
Accelerated SAP
Table D.2-5
Key Activities
 Perform System Tests




















Final Preparation Key Activities and Deliverables
Deliverables
 Execute Stress, Volume, Disaster Recovery
and Backup Tests
 Technical Processes Tested
Assess Going-Live Check
 Implement Going-Live Check
Recommendations
Recommendations
Finalize Cutover (Conversion) Plan
 Cutover Workplan

Refine and Execute Production Support
Plan

Perform Training Program Evaluation
Deliver End-User Training

Setup and Install Production
Environment(s)
Configure and Execute System
Administrator Functionality
Establish Service Level Agreements
Risk Assessment Measurement
Conduct Peer/Solution/Technical Reviews

Final Preparation Sign-off

Nineapps software services



Commence Initial Production Support
Activities (which occur prior to go-live)












Training Program Evaluation
Trained End Users



Tuned SAP System





Service Level Agreements
Revised Risk Assessment
Solution/Technical Review Findings
Reports




Installed Production System(s)

Go-Live Approved

Ravikiran7
Key Implementation Activities and Deliverables:
Accelerated SAP
Table D.2-6 Go-Live and Support Key Activities and Deliverables
Key Activities
Deliverables
 Provide Production Support (Help Desk)
 Production Support (Help Desk)
Established
 Execute Daily Operation Support and
 Production-Ready Systems Environment
Administration
 Optimize System Tuning
 Validate Live Business Process Results
 Business Process Results
 Monitor Transactions, Interfaces and
 System tuning and Procedural Updates
Procedures
 Execute Ongoing Security Administration
 Security Administration
 Provide Ongoing Training Support
 Execute Ongoing Training Support
 Develop Continuous Improvement Plan
 Continuous Improvement Plan
 Produce and Deliver Program Management  Completed Status Report
Status Reports
 Updated Issues Log
 Post Implementation Review
 Post Implementation Findings Reports

Nineapps software services

Ravikiran8

Key implementation activities_asap

  • 1.
    Key Implementation Activitiesand Deliverables: Accelerated SAP Table D.2-1 ASAP Phases AcceleratedSAP Phases Phase 1 – Project Preparation Phase 2 – Business Blueprint Phase 3 – Realization Phase 4 – Final Preparation Phase 5 – Go Live and Support The ASAP Roadmap was developed by SAP to help customers implement SAP software in a quick, cost-effective manner. Utilizing this approach:  minimizes the length of implementation,  maximizes the utilization of TeamSAP and customer resources,  results in a “Repetitive Model” that can be used with other implementations of SAP modules or systems, and  provides a process-oriented approach to Product Training. Nineapps software services Ravikiran0
  • 2.
    Key Implementation Activitiesand Deliverables: Accelerated SAP Table D.2-2 Project Preparation Key Activities and Deliverables Key Activities Deliverables  Finalize Project Team Organization  Project Team Structure Organization Chart  Finalize Project Team Training Plan  Project Team Training Schedule   Develop Project Plans  Develop Project Strategies and Scope  Review Existing Implementations  Define Project Management Standards and Procedures       Define Post-Implementation Support  Perform Technical Requirements Gathering      Define Quality Assurance Plan      Prepare for Project Kickoff           Nineapps software services       Baseline Project Plans Initial Activities Planned Resource Plan Draft: o Implementation Strategy o End-User Training Strategy o Development Strategies o Testing Strategy o Technical Strategies o Security and Controls Strategy o High-level Project Scope Document List of Lessons Learned Project Management Standards and Procedures (Issue Mgt Plan, Status Report Format, Change Control Forms, Documentation standards, etc,) Post-Implementation Support Approach Complete Technical Questionnaires Define Technical Infrastructure Needs Quality Assurance Plan Kickoff Meeting Ravikiran1
  • 3.
    Key Implementation Activitiesand Deliverables: Accelerated SAP Nineapps software services Ravikiran2
  • 4.
    Key Implementation Activitiesand Deliverables: Accelerated SAP Table D.2-3 Business Blueprint Key Activities and Deliverables Key Activities Deliverables  Conduct Project Team Training  Execute Project Team Training Schedule    Define SAP Organizational Structure Define Global Parameters Prepare for Blueprint Workshops  SAP R/3 Hierarchy Definitions    Blueprint Workshop Schedule List of Blueprint Workshop Participants Blueprint Workshop Agendas  Conduct Blueprint Workshops   Finalize Project Scope    Finalize Development Scope   Finalize End-User Training Strategy  Business Blueprint Report o Business Process Flows o Policies and Procedures o Gaps Identified Business Process Master List (BPML) Finalized Scope Document Signed off by Customer Development Scope: Reporting, Interfaces, Conversions, Enhancements End-User Training Strategy Signed-Off by Customer End User Training Requirements and Materials Standards document               Perform Cycle Planning for Prototyping Develop Knowledge Transfer Plan    Create Technical Design Develop Non-functional Requirements       Setup and Install Development Environment Conduct Peer/Solution/Technical Reviews  Nineapps software services     Cycle Plan for Prototyping Knowledge Transfer Plan signed off by Customer Technical Design Document Non-functional Requirements Specifications Documentation Installed Development System Solution/Technical Review Findings Reports  Ravikiran3
  • 5.
    Key Implementation Activitiesand Deliverables: Accelerated SAP  Business Blueprint Sign-off Nineapps software services  Business Blueprint Documentation and Phase completion signed-off by Customer Ravikiran4
  • 6.
    Key Implementation Activitiesand Deliverables: Accelerated SAP Table D.2-4 Realization Key Activities and Deliverables Key Activities Deliverables  Define Master Data  Master Data Definitions  Baseline Configuration Completed  Baseline Configuration and Documentation  Conduct Unit Testing  Completed Unit Testing and Associated Scripts and Results  Final Configuration Completed    Create Security Authorizations Develop Custom Design Specifications (functional spec’s) Develop Technical and Functional Specifications Coding and Unit Test for Conversions, Reports, Interfaces and Enhancements                     Conversion Planning (Cutover) and Preparation Develop New Procedures and Policies Finalize End-User Training Strategy Establish Training Environment Train Power Users Plan SAP early watch Go-Live Quality Assurance / Check Plan and Execute System Test Execute Cycle Testing Develop Integration Test Plan(s) Execute Integration Test Design and Deliver Instructor Training Material (if applicable) Create End-User Training Programs and Training Materials Create Technical Design Setup and Install Quality Assurance (QA) Environment Nineapps software services       Configured SAP System and Related Documentation Configured SAP User Profiles and Roles Functional Specifications Technical and Functional Specifications Documentation and Associated Approvals Completed Unit Testing for Development Objects Object Code for Development Objects Initial Conversion (Cutover) Plan Draft Legacy Retirement Plan New Procedures and Policies Documented/Approved      Approved End-User Training Strategy Installed Training System Trained Power Users and Trainers       System Test Plan Volume and Stress Tested System Cycle Testing Complete Integration Test Plan Integration Test Complete Instructor Training Material        End-User Training Curriculum End-User Training Materials End-User Training Schedule Facilities Reservations Technical Design Document Installed Quality Assurance System Ravikiran5
  • 7.
    Key Implementation Activitiesand Deliverables: Accelerated SAP    Execute Communications Plan  Conduct Peer/Solution/Technical Reviews  Nineapps software services      Presentations Newsletters Solution/Technical Review Findings Reports  Ravikiran6
  • 8.
    Key Implementation Activitiesand Deliverables: Accelerated SAP Table D.2-5 Key Activities  Perform System Tests                    Final Preparation Key Activities and Deliverables Deliverables  Execute Stress, Volume, Disaster Recovery and Backup Tests  Technical Processes Tested Assess Going-Live Check  Implement Going-Live Check Recommendations Recommendations Finalize Cutover (Conversion) Plan  Cutover Workplan  Refine and Execute Production Support Plan Perform Training Program Evaluation Deliver End-User Training Setup and Install Production Environment(s) Configure and Execute System Administrator Functionality Establish Service Level Agreements Risk Assessment Measurement Conduct Peer/Solution/Technical Reviews Final Preparation Sign-off Nineapps software services  Commence Initial Production Support Activities (which occur prior to go-live)           Training Program Evaluation Trained End Users  Tuned SAP System    Service Level Agreements Revised Risk Assessment Solution/Technical Review Findings Reports   Installed Production System(s) Go-Live Approved Ravikiran7
  • 9.
    Key Implementation Activitiesand Deliverables: Accelerated SAP Table D.2-6 Go-Live and Support Key Activities and Deliverables Key Activities Deliverables  Provide Production Support (Help Desk)  Production Support (Help Desk) Established  Execute Daily Operation Support and  Production-Ready Systems Environment Administration  Optimize System Tuning  Validate Live Business Process Results  Business Process Results  Monitor Transactions, Interfaces and  System tuning and Procedural Updates Procedures  Execute Ongoing Security Administration  Security Administration  Provide Ongoing Training Support  Execute Ongoing Training Support  Develop Continuous Improvement Plan  Continuous Improvement Plan  Produce and Deliver Program Management  Completed Status Report Status Reports  Updated Issues Log  Post Implementation Review  Post Implementation Findings Reports Nineapps software services Ravikiran8