REVIEW & ASSESSMENT REPORT:REVIEW & ASSESSMENT REPORT:
A Brief Overview of Best Practices and Measures for Championing Your
SAP Business Transformation Program towards Success
A Brief Overview of Best Practices and Measures for Championing Your
SAP Business Transformation Program towards Success
Mr. Deepak MandrekarMr. Deepak Mandrekar
2 | P a g e
A Brief Overview of Best Practices and Measures for Championing
Your SAP Business Transformation Program towards Success
By Deepak Mandrekar
SAP is a robust technology platform that
allow seamless integration of all your
internal business functions and taking your
external constituents business experience to
next level. These transformations can bring
significant benefits to your organization by
boosting your profitability and also serving
as a catalyst in improving your overall
market position. Typically these initiatives
involve deployment of best in class
solutions, optimization of internal business
operations and technology innovations to
enrich customer experience. A well
implemented program on SAP platform can
provide full operational and financial
visibility to measure the performance of
your organization thus enabling corporate
leaders to calibrate people, processes and
technology to achieve business goals.
These transformations can be very powerful
and corporate leaders can take extra
measures to ensure that these huge
undertaking is successful so that you can
achieve goals that were initially established.
However, these business transformations
could go horribly wrong leading to severe
financial losses, drain on corporate
resources and loss of trust from your
customers. Typically these program
failures are attributed to poor quality of
implementation and lack of business
engagement by IT vendor at various stages
of the program. Sometimes even engaging
Big 4 consulting companies does not
guarantee success as many of the popular
failed IT projects that have been in the news
recently are attributed to the big 4
consulting firms. These companies can
bring discipline and structure to the
program but need to be carefully managed
throughout the duration of the program to
ensure they are delivering what is required
to set a high quality benchmark for the
future phases of your program.
In early 2013, I was approached by an EVP
of a fortune 500 company who was also the
executive sponsor of their transformation
program which was struggling with many
challenges. Their program was about to exit
the blueprint phase and business
stakeholders were concerned for not
knowing the details of the future state. The
business leaders were skeptical if the IT
vendor was leading them on a correct path.
This white paper summarizes the guidance
that I gave them and since then with many
other companies that approached my firm.
The measures and best practices discussed
in this article are independent of the
methodology followed by your IT vendor
and should be applicable to every single
business transformation initiative. Many a
times we hear top IT systems integrators
telling our clients that their methodology
does not allow compliance to some of these
measures but I strongly encourage business
leaders owning these transformations to
enforce these protocols. If your organization
needs assistance and guidance in these
areas then I recommend that you engage a
3 | P a g e
good transformation advisor for your
program.
This article we will stay at a very high level
to provide a quick snapshot of best practices
to leaders undergoing large
transformations. Remember that every
business and IT transformation is unique
and need additional measures to be
introduced during the program execution
phases. However for these are some of the
key measures you need to consider to
ensure your IT vendor is delivering a high
quality product during each of the phases of
the implementation.
Planning
A well run transformation program requires
good vision and planning. Executive board
of the company needs to be clear on the
goals for the program and translate these
goals into quantifiable objectives. In
planning phase it is crucial that you
benchmark your program with a
compelling business case and scope.
Recommendations for Planning Phase:
1. Solid business case for the program
is developed which include tangible
business, operational and
technology driven benefits as
outcome from the transformation.
2. Clear defined scope for the program.
Each business function (Ex. Sales,
HR, Supply Chain, Distribution,
Finance, etc) has produced a scope
document with list of all business
scenarios that are important to
operate your day-to-day business. It
is important that you not only
identify the common scenarios but
also the exceptions and the way
these are handled today. The way
these processes work in future state
could be different but identifying
these business scenarios upfront in
planning phase will ensure that you
are able to run your business after
cutover.
3. Scope and business case should
include enhancements of existing
processes and new solutions to be
deployed in order to eliminate your
current pain points. Think about the
way you can invest in new solutions
like cloud computing, SAP HANA,
etc to enrich your customer
experience. Evaluate your market
competition and consider adding
initiatives to the scope that will help
you stay ahead of your competitors.
4. Project charter should be finalized
and includes program governance,
program success criteria, budget,
timeline and operating structure.
Planning Phase Exit Criteria
 Business case approved by executive
committee
 Project Charter complete and signed
off by the Executive Sponsor and
Advisory Board
 IT vendor selection confirmed and
approved by executive committee
 Business case, scope, budget,
timeline and deliverables approved
by Executive Sponsor and included
in IT vendor’s Statement of Work.
4 | P a g e
Blueprint
Blueprint or the design phase is the
foundation for your transformation
program. Over 90% of transformation
program failures are result of poor quality
blueprint where business was not
adequately engaged and lack of clarity on
future state system and capabilities before
exiting blueprint.
Recommendations for Blueprint Phase:
1. BPD (Business Process Design)
documents are produced by your IT
vendor for each business scenario in
scope. This document should
include mapping of Level 1 to Level
5 process flows and each business
requirement mapped to these
process steps. Your vendor SAP
functional consultants should
conduct a thorough stepwise to-be
process flow review as a pre-
requisite. For greenfield SAP
programs, the to-be process flows
can be conceptual but for global
template or standardized SAP
module deployment this walk
through should be conducted in a
SAP Sandbox or if available an QA
system.
2. Additionally in blueprint, detailed
business requirements should be
produced and added to the HLR
scenarios document. A requirement
traceability matrix should be created
that maps each business
requirement to at least one business
process flow. These flows should
then be mapped to standard solution
or a gap followed by link to at least
one UAT scenario. This approach
will ascertain if each of your
business requirement is tested in
User Acceptance Testing by at least
one UAT scenario.
3. Fit-Gap Analysis – All BPD
documents should include fit-gap
analysis for each process step
against standard SAP solution being
deployed. All gaps should have high
level solution direction that will
serve as the starting point for
functional design of these gap in the
build phase.
4. Solution Inventory – This
deliverable should include summary
of all configuration objects and gaps
in SAP that were identified during
the blueprint phase.
5. Integrated Solution Architecture
document should be created by the
Solution Architect from your IT
vendor. This document should show
layout of SAP system with modules
being deployed along with external
systems that will be integrated with
the new SAP platform. All changes
to standard SAP software specific to
the project should be well
documented in this blueprint phase
deliverable and further updated in
build phase.
Blueprint Phase Exit Criteria
 All BPDs are reviewed and signed
off by Business Leads for each
business function
5 | P a g e
 Solution Inventory approved and
signed off by IT program lead and
approved by Advisory Board
 Solution Architecture reviewed and
approved by IT Program Lead
 Build plan and IT/Business resource
requirements reviewed with
confirmed commitment from all key
stakeholders
 All change requests reviewed by
Change Control Review Board with
documented outcome
 Build milestones and quality gates
approved by Project Board
 Final signoff by the Executive
Sponsor to exit the blueprint phase
based on recommendation from
Advisory Board.
Build Phase
Initially in build phase, IT architects,
technical and functional consultants will
configure, design and build the to-be SAP
solution. However, this phase is not only
about build and IT. Early in build phase the
business and data migration team should
start assessing the quality of data in legacy
systems and also verify the migration tools
along with strategy. Another important task
for business SMEs and key users is to define
comprehensive stepwise UAT scenarios that
should include standalone tests within each
business function as well as end-to-end
scenarios.
Recommendations for Build Phase:
1. All functional and technical design
documents for gaps identified
during the blueprint in the standard
SAP solution should be reviewed by
IT Solution Architect and approved
by IT leadership.
2. Configuration Rationale and Master
Data Design documents should be
created for each configuration set
and master data entity respectively.
These deliverables should be
reviewed by Solution Architect and
business content (if any) should be
signed off by business functional
leads.
3. Data Migration lead should drive
the extraction and cleansing of data
in the legacy systems. The DM lead
should drive preliminary review
and approval of cleansed data from
business data owners.
4. At least two cycles of data migration
simulation runs should be
conducted. These simulation cycles
should be an iterative process until
95-98% data accuracy with data load
is achieved. Each cycle should
involve validation of post migrated
data in QA system by business
stakeholders with signoff from Data
Migration lead. About 2-5% data
should be used for each of these
cycles to allow enough sampling but
also ensuring that you have
sufficient data for future cycles.
5. Each business function should
document UAT scripts covering all
business scenarios defined in the
scoping phase of the project. Each
scenario and business requirement
6 | P a g e
should be covered by at least one
UAT test script. Documentation
should be stepwise with expected
results for each step. Business
Functional Lead should review and
signoff all UAT scripts for
completeness and accuracy. They
should also validate that these UAT
scripts cover all common scenarios
along with variations, exceptions
and negative tests.
6. Internal auditors should review all
UAT scenarios and confirm that all
necessary IT general controls are
included in these scripts. Also
auditors and process owners need to
confirm that all applicable
compliance checks (eg. Sarbanes-
Oxley) are included in the UAT
scripts where necessary. In addition,
IT Security Lead should signoff
confirming all user roles and
authorizations are properly setup
with no conflicts in segregation of
duties.
7. Business Migration Strategy draft
should be prepared and reviewed by
all business stakeholders in build
phase. This deliverables can be
finalized and signed off about 4-6
weeks before entering final
preparation phase.
8. Integrated cutover strategy draft
should be reviewed with all cutover
stakeholders before exiting the build
phase. Cutover strategy should
include detailed cutover tasks
showing interdependencies between
cutover activities with an owner
against each cutover task.
9. GoLive success markers provided in
the project business case should be
reviewed with the business key
users in conjunction with KPIs,
benchmarks. Tools and reports to be
used after cutover to measure these
KPIs should be reviewed with
business SMEs and confirmed by
Business Functional Lead.
10. End user training plan and
documentation should be produced
by IT vendor in collaboration with
business SME. These training
documents should be approved by
each business functional lead.
11. Org Change Management Strategy
draft should be reviewed with
business stakeholders along with
internal stakeholders that interact
with external constituents in order
to understand the impact on external
community. This document should
include all change impacts to
processes, internal operations,
people and external constituents
including customers, suppliers,
business partners, affiliates,
distributors and other third parties.
It is important that change impact is
reviewed early with all the above
stakeholders so that any necessary
calibration to the program can be
considered before exiting build
phase.
12. A full suite of regression tests
should be executed once the build is
complete for Global Template or
standard SAP module(s)
deployment to confirm that any
modifications to the template core
7 | P a g e
system processes did not break
existing standard template
functionality. IT Project Manager
should signoff indicating successful
completion of regression tests.
Regression testing should be ideally
completed prior to UAT and can be
conducted simultaneously with SIT.
Build Phase Exit Criteria
 All configurations are complete and
gaps in standard SAP solution are
resolved. IT Project Manager and
Solution Architect has signed off on
these build deliverables.
 Systems Integration Testing (SIT) is
completed successfully by IT vendor
and the output is signed off by the
IT Program Lead, IT Project
Manager and also the Solution
Architect.
 Data Migration approach and tools
are verified with simulation runs
and signed off by Data Migration
lead.
 All other deliverables discussed in
the above recommendations are
completed and approved by
respective owners.
User Acceptance Testing (UAT)
In my view, UAT should not only test but
confirm the quality of your blueprint and
build phases. Some transformation
programs fail because they consider UAT as
the first instance of verification of to be
processes. In UAT business should confirm
that processes reviewed in blueprint phase
are working exactly as anticipated. It is a
best practice to include as many business
critical end users as participants in UAT
along with SMEs so that they have enough
time to understand the new system
processes and capabilities.
Recommendations for UAT:
1. Ensure in UAT kickoff that all
testers having a clear understanding
of UAT structure and daily goals to
be achieved. Tools to log UAT
output and issues tracking should be
reviewed with all participants.
2. Step-by-step output of each UAT
script should be logged with
confirmation from SME or business
lead that script was successfully
completed. All E2E UAT scenarios
should be signed off by the process
owners.
3. All updates to master data source
arising out of UAT issues should be
done by data migration team and
signed off by Data Migration Lead.
4. Business functional leads along with
Executive Sponsor should sign off
on UAT completion only when all
UAT scenarios are successfully
completed and all defects are
resolved with re-tests.
5. IT Project Manager should ensure a
new QA system is setup prior to
UAT completion which will be used
to perform migration dry run.
8 | P a g e
Exit Criteria for UAT
All UAT scenarios should be successfully
completed and signed off. All defects
should be resolved and retested. Any
exceptions should be aligned with business
program leader and documented in UAT
signoff document.
Cutover Preparation Phase
Cutover Preparation phase is the time to
verify that all cutover prerequisites are
fulfilled and your entire organization is
ready to cutover onto the new system.
Recommendations for Cutover Preparation
Phase:
1. Conduct reviews of cutover,
business migration, data migration
and org change strategies with final
approvals on each of these
documents from respective owners.
2. Confirm pre-cutover and post
GoLive communication plan with
internal and external constituents.
3. Disaster recovery and rollback plan
should be finalized and signed off
by your IT infrastructure and IT
Program Lead.
4. For large SAP transformation
programs involving multi-business
functions and large data entity
conversions, it is important to
conduct a pre-cutover dry run in
new QA environment with inclusion
of at least 95% data set that will be
actually used during the cutover.
This will simulate your ECC cutover
tasks to ensure that you can
smoothly migrate the data and also
execute key transactions in within
this QA system. The 5% allowance is
for master data and transactions that
may change between the dry run
and GoLive. Business SMEs should
perform pre-load and post-load
validations in this QA system
followed by approval from each
business functional lead that own
these data objects and transactional
data.
5. Confirm ownership and protocols to
monitor SOX compliance and IT
controls in the new environment.
Cutover Period
Cutover period is time sensitive period that
include execution of all pre-cutover
activities leading up to the day of GoLive.
Daily all hands review of cutover tasks are
conducted by IT Project Manager and
Cutover Lead. All cutover tasks should be
sequentially planned considering the
dependencies between master data objects
and transaction data.
Some Recommendations for Cutover:
1. Schedule at least four Go-NoGo
checkpoints during the cutover
period. First checkpoint to confirm
the master data is loaded correctly
with post-load validation approval
from business data owners. Second
checkpoint should be scheduled
when primary transaction data sets
are loaded like inventories, policies,
financials, etc. Third check point
9 | P a g e
held when all transactional data is
loaded into production and verified
by business owners of these entities.
And finally the last Go-NoGo
checkpoint scheduled when pilot
processing of few select transactions
is conducted in the new live
production system. A separate
Steering Committee ‘Go-NoGo’
should be scheduled between third
and final checkpoint discussed
above. Additional checkpoints
should be considered depending on
the magnitude and complexity of
your business transformation
program.
2. Each master data entity should be
validated and signed off by the
business owner after migration into
the production system.
3. All open transactional entities like
open claims, open sales orders, open
policies, open purchase orders,
collections, AR/AP etc should be
validated and approved by business
functional owners after migration to
production.
4. Any manual corrections should be
documented and pre-approved by
business and Cutover Lead.
5. A centralized cutover directory
should be created that includes all
business and IT contact person for
each area of the program along with
first and second level of escalation
points. There should be a functional
email address and hotline for all
customers, third parties, partners
and other external stakeholders to
reach out in case they have issues
working with the newly deployed
systems.
Post Cutover Stabilization
Now that you are live it is important to
keep an open channel of communication
with entire business community to ensure
smooth operations in the new production
system. IT vendor project team should be in
place to support the cutover for at least 3-5
months after GoLive depending on the
magnitude and complexity of the cutover.
Business teams for large transformations
may require operational guidance and
support from IT SAP experts for extended
period ranging from 8-12 months. Confirm
capabilities of internal support staff if your
IT vendor has already transitioned the
project to your IT Center of Excellence. This
period could involve new post-cutover
enhancements to production systems in
order to address pain-points, bottlenecks
and efficiency improvements.
Recommendations for Post Cutover
Stabilization:
1. Verify all GoLive issues are logged
and reviewed in all hands meeting
at least once every day after cutover
for a few weeks until the number of
open issues have subsided to pre-
determined acceptable level.
2. Business functional leads along with
Business program manager should
review the success markers (incl.
KPIs) regularly to ensure
operational benchmarks are
achieved.
10 | P a g e
3. IT Project Manager should monitor
and report system performance
statistics to Project Board along with
technical KPIs.
If you have outsourced your IT services to
another third party company then extra
precaution should be taken to confirm the
capabilities and readiness of the provider.
The Project Manager of your outsourced IT
provider should confirm that complete
knowledge transfer has been received by
their support personnel for each business
function. Final signoff on readiness should
be sought from the IT Project Manager and
Transition Lead from the program IT
vendor.
With these measures you can reduce risks
associated with complex business
transformation programs and keep your
implementation on track for a successful
deployment.
About the Author
Deepak Mandrekar is an
Executive SAP Program
Leader and also the
Founder of iii
Technologies. For last 8
years he has led six SAP business
transformation programs as a Trusted
Advisor and Executive Program Leader
primarily engaged by the CIO, CFO and
Executive Sponsors heading these
implementations. Overall he has been part
of 14 SAP transformations in North
America throughout his career starting as
SAP Solution Architect in early years and
quickly moving into program leadership
roles. Some of these transformations have
included global template deployments and
select others involved significant custom
development. He is widely recognized in
the industry for turnaround of struggling
transformation programs with customized
best practices and strategic direction.
Deepak holds a Master of Science in
Engineering from Purdue University.
 deepak.mandrekar@iiitech.com
 (609) 901-8000
Copyright © 2013 iii Technologies. All rights
reserved.
This document is for private circulation only and
may not be reproduced without written consent from
the author and iii Technologies.

More Related Content

What's hot

Business Analyst Role in Hybrid Agile Waterfall
Business Analyst Role in Hybrid Agile WaterfallBusiness Analyst Role in Hybrid Agile Waterfall
Business Analyst Role in Hybrid Agile WaterfallStephen Williamson
 
Gartner Shares the Most Important PPM Trends for 2014 - 051214
Gartner Shares the Most Important PPM Trends for 2014 - 051214Gartner Shares the Most Important PPM Trends for 2014 - 051214
Gartner Shares the Most Important PPM Trends for 2014 - 051214UMT360
 
Technique To Prioritize Key Tasks In Agile Process Powerpoint Presentation Sl...
Technique To Prioritize Key Tasks In Agile Process Powerpoint Presentation Sl...Technique To Prioritize Key Tasks In Agile Process Powerpoint Presentation Sl...
Technique To Prioritize Key Tasks In Agile Process Powerpoint Presentation Sl...SlideTeam
 
Why Erp Implementations Fail
Why Erp Implementations FailWhy Erp Implementations Fail
Why Erp Implementations FailPhilKeet
 
Project Management Professional (PMP) Fundamentals
Project Management Professional (PMP) FundamentalsProject Management Professional (PMP) Fundamentals
Project Management Professional (PMP) FundamentalsSowmak Bardhan
 
Salesforce CRM 7 domains of Success
Salesforce CRM 7 domains of SuccessSalesforce CRM 7 domains of Success
Salesforce CRM 7 domains of SuccessKevin Sherman
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaGlen Alleman
 
IBM Rational Software Conference 2009: Process, Project and Portfolio Managem...
IBM Rational Software Conference 2009: Process, Project and Portfolio Managem...IBM Rational Software Conference 2009: Process, Project and Portfolio Managem...
IBM Rational Software Conference 2009: Process, Project and Portfolio Managem...Kathy (Kat) Mandelstein
 
PM detail
PM detailPM detail
PM detailvbkish
 
Kalypso Strategic Roadmapping Deck Mar Webinarv4
Kalypso Strategic Roadmapping Deck Mar Webinarv4Kalypso Strategic Roadmapping Deck Mar Webinarv4
Kalypso Strategic Roadmapping Deck Mar Webinarv4Brsurf2001
 
Salesforce implementation guide 2021 here’s everything business owner should ...
Salesforce implementation guide 2021 here’s everything business owner should ...Salesforce implementation guide 2021 here’s everything business owner should ...
Salesforce implementation guide 2021 here’s everything business owner should ...Katy Slemon
 
3. Project Management A Case Study Of A Successful Erp Implementation
3. Project Management A Case Study Of A Successful Erp Implementation3. Project Management A Case Study Of A Successful Erp Implementation
3. Project Management A Case Study Of A Successful Erp ImplementationDonovan Mulder
 
ITIL Practical Guide - Service Transition
ITIL Practical Guide - Service TransitionITIL Practical Guide - Service Transition
ITIL Practical Guide - Service TransitionAxios Systems
 
If you dont know where you are going any road will do visioning for implement...
If you dont know where you are going any road will do visioning for implement...If you dont know where you are going any road will do visioning for implement...
If you dont know where you are going any road will do visioning for implement...p6academy
 
Capabilities based planning (v2)
Capabilities based planning (v2)Capabilities based planning (v2)
Capabilities based planning (v2)Glen Alleman
 
Product development kaizen (pdk)
Product  development kaizen (pdk)Product  development kaizen (pdk)
Product development kaizen (pdk)Glen Alleman
 
Agile in enterprise resource planning a myth no more
Agile in enterprise resource planning a myth no moreAgile in enterprise resource planning a myth no more
Agile in enterprise resource planning a myth no moreMauricio Rivadeneira
 

What's hot (20)

Business Analyst Role in Hybrid Agile Waterfall
Business Analyst Role in Hybrid Agile WaterfallBusiness Analyst Role in Hybrid Agile Waterfall
Business Analyst Role in Hybrid Agile Waterfall
 
BIS11 ERP
BIS11 ERPBIS11 ERP
BIS11 ERP
 
Gartner Shares the Most Important PPM Trends for 2014 - 051214
Gartner Shares the Most Important PPM Trends for 2014 - 051214Gartner Shares the Most Important PPM Trends for 2014 - 051214
Gartner Shares the Most Important PPM Trends for 2014 - 051214
 
Technique To Prioritize Key Tasks In Agile Process Powerpoint Presentation Sl...
Technique To Prioritize Key Tasks In Agile Process Powerpoint Presentation Sl...Technique To Prioritize Key Tasks In Agile Process Powerpoint Presentation Sl...
Technique To Prioritize Key Tasks In Agile Process Powerpoint Presentation Sl...
 
Why Erp Implementations Fail
Why Erp Implementations FailWhy Erp Implementations Fail
Why Erp Implementations Fail
 
Project Management Professional (PMP) Fundamentals
Project Management Professional (PMP) FundamentalsProject Management Professional (PMP) Fundamentals
Project Management Professional (PMP) Fundamentals
 
Salesforce CRM 7 domains of Success
Salesforce CRM 7 domains of SuccessSalesforce CRM 7 domains of Success
Salesforce CRM 7 domains of Success
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
 
IBM Rational Software Conference 2009: Process, Project and Portfolio Managem...
IBM Rational Software Conference 2009: Process, Project and Portfolio Managem...IBM Rational Software Conference 2009: Process, Project and Portfolio Managem...
IBM Rational Software Conference 2009: Process, Project and Portfolio Managem...
 
Kpi 1 day
Kpi 1 dayKpi 1 day
Kpi 1 day
 
PM detail
PM detailPM detail
PM detail
 
Kalypso Strategic Roadmapping Deck Mar Webinarv4
Kalypso Strategic Roadmapping Deck Mar Webinarv4Kalypso Strategic Roadmapping Deck Mar Webinarv4
Kalypso Strategic Roadmapping Deck Mar Webinarv4
 
Salesforce implementation guide 2021 here’s everything business owner should ...
Salesforce implementation guide 2021 here’s everything business owner should ...Salesforce implementation guide 2021 here’s everything business owner should ...
Salesforce implementation guide 2021 here’s everything business owner should ...
 
3. Project Management A Case Study Of A Successful Erp Implementation
3. Project Management A Case Study Of A Successful Erp Implementation3. Project Management A Case Study Of A Successful Erp Implementation
3. Project Management A Case Study Of A Successful Erp Implementation
 
ITIL Practical Guide - Service Transition
ITIL Practical Guide - Service TransitionITIL Practical Guide - Service Transition
ITIL Practical Guide - Service Transition
 
If you dont know where you are going any road will do visioning for implement...
If you dont know where you are going any road will do visioning for implement...If you dont know where you are going any road will do visioning for implement...
If you dont know where you are going any road will do visioning for implement...
 
Capabilities based planning (v2)
Capabilities based planning (v2)Capabilities based planning (v2)
Capabilities based planning (v2)
 
Product development kaizen (pdk)
Product  development kaizen (pdk)Product  development kaizen (pdk)
Product development kaizen (pdk)
 
Agile in enterprise resource planning a myth no more
Agile in enterprise resource planning a myth no moreAgile in enterprise resource planning a myth no more
Agile in enterprise resource planning a myth no more
 
Strategy map 16
Strategy map 16Strategy map 16
Strategy map 16
 

Viewers also liked

Aries Slide Deck 12-27-2015
Aries Slide Deck 12-27-2015Aries Slide Deck 12-27-2015
Aries Slide Deck 12-27-2015Aaron Gillingham
 
Importancia acerca del uso correcto de la computadora
Importancia acerca del uso correcto de la computadoraImportancia acerca del uso correcto de la computadora
Importancia acerca del uso correcto de la computadoragustavo lorza
 
Teuku Habibie Syahputra_DS_02MW_1
Teuku Habibie Syahputra_DS_02MW_1Teuku Habibie Syahputra_DS_02MW_1
Teuku Habibie Syahputra_DS_02MW_1Habibie Syahputra
 
Satya_latest_resume.doc
Satya_latest_resume.docSatya_latest_resume.doc
Satya_latest_resume.docSatya .
 
Elementos básicos de la comunicación
Elementos básicos de la comunicaciónElementos básicos de la comunicación
Elementos básicos de la comunicaciónJailene Marin
 
NGEK01.Susanne.DeBourg_final
NGEK01.Susanne.DeBourg_finalNGEK01.Susanne.DeBourg_final
NGEK01.Susanne.DeBourg_finalSusanne De Bourg
 
Parque internacional la amistad
Parque internacional la amistadParque internacional la amistad
Parque internacional la amistadlisg99
 
Herramientas de presentaciones
Herramientas de presentacionesHerramientas de presentaciones
Herramientas de presentacionesJacqueline Santana
 

Viewers also liked (17)

Aries Slide Deck 12-27-2015
Aries Slide Deck 12-27-2015Aries Slide Deck 12-27-2015
Aries Slide Deck 12-27-2015
 
Importancia acerca del uso correcto de la computadora
Importancia acerca del uso correcto de la computadoraImportancia acerca del uso correcto de la computadora
Importancia acerca del uso correcto de la computadora
 
Teuku Habibie Syahputra_DS_02MW_1
Teuku Habibie Syahputra_DS_02MW_1Teuku Habibie Syahputra_DS_02MW_1
Teuku Habibie Syahputra_DS_02MW_1
 
sun 2016@uibe
sun 2016@uibesun 2016@uibe
sun 2016@uibe
 
Taller
TallerTaller
Taller
 
Nardelli1
Nardelli1Nardelli1
Nardelli1
 
Lorza2299
Lorza2299Lorza2299
Lorza2299
 
WCEE2012_1941
WCEE2012_1941WCEE2012_1941
WCEE2012_1941
 
Satya_latest_resume.doc
Satya_latest_resume.docSatya_latest_resume.doc
Satya_latest_resume.doc
 
Elementos básicos de la comunicación
Elementos básicos de la comunicaciónElementos básicos de la comunicación
Elementos básicos de la comunicación
 
Power Point- Informatica UDCA
Power Point- Informatica UDCAPower Point- Informatica UDCA
Power Point- Informatica UDCA
 
Michael 901
Michael 901Michael 901
Michael 901
 
NGEK01.Susanne.DeBourg_final
NGEK01.Susanne.DeBourg_finalNGEK01.Susanne.DeBourg_final
NGEK01.Susanne.DeBourg_final
 
Hiperbola_teoría
Hiperbola_teoríaHiperbola_teoría
Hiperbola_teoría
 
Parque internacional la amistad
Parque internacional la amistadParque internacional la amistad
Parque internacional la amistad
 
Herramientas de presentaciones
Herramientas de presentacionesHerramientas de presentaciones
Herramientas de presentaciones
 
040-Imran Ki Moot_2
040-Imran Ki Moot_2040-Imran Ki Moot_2
040-Imran Ki Moot_2
 

Similar to SAP Business Transformations - Mandrekar

Asap implementation methodology (2)
Asap implementation methodology (2)Asap implementation methodology (2)
Asap implementation methodology (2)Pradipta Mallick
 
Erp Asap implementation 1214825612078403-9
Erp Asap implementation 1214825612078403-9Erp Asap implementation 1214825612078403-9
Erp Asap implementation 1214825612078403-9Hari Krishna
 
Erpasapimplementation 1214825612078403-9
Erpasapimplementation 1214825612078403-9Erpasapimplementation 1214825612078403-9
Erpasapimplementation 1214825612078403-9Hari Krishna
 
SAP Managed Services Best Practices and Implementation Strategies
SAP Managed Services Best Practices and Implementation StrategiesSAP Managed Services Best Practices and Implementation Strategies
SAP Managed Services Best Practices and Implementation StrategiesSkillmine Technology Consulting
 
Steps to blueprint successful erp projects immortal
Steps to blueprint successful erp projects immortalSteps to blueprint successful erp projects immortal
Steps to blueprint successful erp projects immortalImmortal Technologies
 
Removing the barriers to business transformation with ArchiMate
Removing the barriers to business transformation with ArchiMateRemoving the barriers to business transformation with ArchiMate
Removing the barriers to business transformation with ArchiMateCorso
 
Unlocking Business Potential How SAP Implementation Services Drive Success.pdf
Unlocking Business Potential How SAP Implementation Services Drive Success.pdfUnlocking Business Potential How SAP Implementation Services Drive Success.pdf
Unlocking Business Potential How SAP Implementation Services Drive Success.pdfAmity Software Systems Limited
 
5 essential tips for successful digital transformation strategies in 2021
5 essential tips for successful digital transformation strategies in 20215 essential tips for successful digital transformation strategies in 2021
5 essential tips for successful digital transformation strategies in 2021OrangeMantra Tech
 
The key to successful Digital Transformation
The key to successful Digital TransformationThe key to successful Digital Transformation
The key to successful Digital TransformationMegan Hunter
 
Build Or Subscribe For Spm 3
Build Or Subscribe For Spm  3Build Or Subscribe For Spm  3
Build Or Subscribe For Spm 3pstakenas
 
11 mistakes to_avoid_when_upgrading_sap
11 mistakes to_avoid_when_upgrading_sap11 mistakes to_avoid_when_upgrading_sap
11 mistakes to_avoid_when_upgrading_sapVasudev Reddy
 
Outside Brand Data Audit
Outside Brand Data AuditOutside Brand Data Audit
Outside Brand Data AuditDaniel McKean
 
ERP - it's not (only) about IT
ERP - it's not (only) about ITERP - it's not (only) about IT
ERP - it's not (only) about ITDina Beer
 

Similar to SAP Business Transformations - Mandrekar (20)

Asap implementation methodology (2)
Asap implementation methodology (2)Asap implementation methodology (2)
Asap implementation methodology (2)
 
ASAP Methodology in Implementing ERP
ASAP Methodology in Implementing ERPASAP Methodology in Implementing ERP
ASAP Methodology in Implementing ERP
 
Erp Asap implementation 1214825612078403-9
Erp Asap implementation 1214825612078403-9Erp Asap implementation 1214825612078403-9
Erp Asap implementation 1214825612078403-9
 
Erpasapimplementation 1214825612078403-9
Erpasapimplementation 1214825612078403-9Erpasapimplementation 1214825612078403-9
Erpasapimplementation 1214825612078403-9
 
SAP Managed Services Best Practices and Implementation Strategies
SAP Managed Services Best Practices and Implementation StrategiesSAP Managed Services Best Practices and Implementation Strategies
SAP Managed Services Best Practices and Implementation Strategies
 
Steps to blueprint successful erp projects immortal
Steps to blueprint successful erp projects immortalSteps to blueprint successful erp projects immortal
Steps to blueprint successful erp projects immortal
 
Removing the barriers to business transformation with ArchiMate
Removing the barriers to business transformation with ArchiMateRemoving the barriers to business transformation with ArchiMate
Removing the barriers to business transformation with ArchiMate
 
Unlocking Business Potential How SAP Implementation Services Drive Success.pdf
Unlocking Business Potential How SAP Implementation Services Drive Success.pdfUnlocking Business Potential How SAP Implementation Services Drive Success.pdf
Unlocking Business Potential How SAP Implementation Services Drive Success.pdf
 
5 essential tips for successful digital transformation strategies in 2021
5 essential tips for successful digital transformation strategies in 20215 essential tips for successful digital transformation strategies in 2021
5 essential tips for successful digital transformation strategies in 2021
 
SAP and Change Management
SAP and Change ManagementSAP and Change Management
SAP and Change Management
 
Basics of ERP
Basics of ERPBasics of ERP
Basics of ERP
 
The key to successful Digital Transformation
The key to successful Digital TransformationThe key to successful Digital Transformation
The key to successful Digital Transformation
 
Build Or Subscribe For Spm 3
Build Or Subscribe For Spm  3Build Or Subscribe For Spm  3
Build Or Subscribe For Spm 3
 
11 mistakes to_avoid_when_upgrading_sap
11 mistakes to_avoid_when_upgrading_sap11 mistakes to_avoid_when_upgrading_sap
11 mistakes to_avoid_when_upgrading_sap
 
The World of Agility
The World of Agility The World of Agility
The World of Agility
 
Introduction to ERP Concept
Introduction to ERP ConceptIntroduction to ERP Concept
Introduction to ERP Concept
 
Mis unit iv PIMR
Mis unit iv PIMRMis unit iv PIMR
Mis unit iv PIMR
 
Outside Brand Data Audit
Outside Brand Data AuditOutside Brand Data Audit
Outside Brand Data Audit
 
ERP - it's not (only) about IT
ERP - it's not (only) about ITERP - it's not (only) about IT
ERP - it's not (only) about IT
 
Software for Optimal Operations
Software for Optimal OperationsSoftware for Optimal Operations
Software for Optimal Operations
 

SAP Business Transformations - Mandrekar

  • 1. iii Technologiesiii Technologies REVIEW & ASSESSMENT REPORT:REVIEW & ASSESSMENT REPORT: A Brief Overview of Best Practices and Measures for Championing Your SAP Business Transformation Program towards Success A Brief Overview of Best Practices and Measures for Championing Your SAP Business Transformation Program towards Success Mr. Deepak MandrekarMr. Deepak Mandrekar
  • 2. 2 | P a g e A Brief Overview of Best Practices and Measures for Championing Your SAP Business Transformation Program towards Success By Deepak Mandrekar SAP is a robust technology platform that allow seamless integration of all your internal business functions and taking your external constituents business experience to next level. These transformations can bring significant benefits to your organization by boosting your profitability and also serving as a catalyst in improving your overall market position. Typically these initiatives involve deployment of best in class solutions, optimization of internal business operations and technology innovations to enrich customer experience. A well implemented program on SAP platform can provide full operational and financial visibility to measure the performance of your organization thus enabling corporate leaders to calibrate people, processes and technology to achieve business goals. These transformations can be very powerful and corporate leaders can take extra measures to ensure that these huge undertaking is successful so that you can achieve goals that were initially established. However, these business transformations could go horribly wrong leading to severe financial losses, drain on corporate resources and loss of trust from your customers. Typically these program failures are attributed to poor quality of implementation and lack of business engagement by IT vendor at various stages of the program. Sometimes even engaging Big 4 consulting companies does not guarantee success as many of the popular failed IT projects that have been in the news recently are attributed to the big 4 consulting firms. These companies can bring discipline and structure to the program but need to be carefully managed throughout the duration of the program to ensure they are delivering what is required to set a high quality benchmark for the future phases of your program. In early 2013, I was approached by an EVP of a fortune 500 company who was also the executive sponsor of their transformation program which was struggling with many challenges. Their program was about to exit the blueprint phase and business stakeholders were concerned for not knowing the details of the future state. The business leaders were skeptical if the IT vendor was leading them on a correct path. This white paper summarizes the guidance that I gave them and since then with many other companies that approached my firm. The measures and best practices discussed in this article are independent of the methodology followed by your IT vendor and should be applicable to every single business transformation initiative. Many a times we hear top IT systems integrators telling our clients that their methodology does not allow compliance to some of these measures but I strongly encourage business leaders owning these transformations to enforce these protocols. If your organization needs assistance and guidance in these areas then I recommend that you engage a
  • 3. 3 | P a g e good transformation advisor for your program. This article we will stay at a very high level to provide a quick snapshot of best practices to leaders undergoing large transformations. Remember that every business and IT transformation is unique and need additional measures to be introduced during the program execution phases. However for these are some of the key measures you need to consider to ensure your IT vendor is delivering a high quality product during each of the phases of the implementation. Planning A well run transformation program requires good vision and planning. Executive board of the company needs to be clear on the goals for the program and translate these goals into quantifiable objectives. In planning phase it is crucial that you benchmark your program with a compelling business case and scope. Recommendations for Planning Phase: 1. Solid business case for the program is developed which include tangible business, operational and technology driven benefits as outcome from the transformation. 2. Clear defined scope for the program. Each business function (Ex. Sales, HR, Supply Chain, Distribution, Finance, etc) has produced a scope document with list of all business scenarios that are important to operate your day-to-day business. It is important that you not only identify the common scenarios but also the exceptions and the way these are handled today. The way these processes work in future state could be different but identifying these business scenarios upfront in planning phase will ensure that you are able to run your business after cutover. 3. Scope and business case should include enhancements of existing processes and new solutions to be deployed in order to eliminate your current pain points. Think about the way you can invest in new solutions like cloud computing, SAP HANA, etc to enrich your customer experience. Evaluate your market competition and consider adding initiatives to the scope that will help you stay ahead of your competitors. 4. Project charter should be finalized and includes program governance, program success criteria, budget, timeline and operating structure. Planning Phase Exit Criteria  Business case approved by executive committee  Project Charter complete and signed off by the Executive Sponsor and Advisory Board  IT vendor selection confirmed and approved by executive committee  Business case, scope, budget, timeline and deliverables approved by Executive Sponsor and included in IT vendor’s Statement of Work.
  • 4. 4 | P a g e Blueprint Blueprint or the design phase is the foundation for your transformation program. Over 90% of transformation program failures are result of poor quality blueprint where business was not adequately engaged and lack of clarity on future state system and capabilities before exiting blueprint. Recommendations for Blueprint Phase: 1. BPD (Business Process Design) documents are produced by your IT vendor for each business scenario in scope. This document should include mapping of Level 1 to Level 5 process flows and each business requirement mapped to these process steps. Your vendor SAP functional consultants should conduct a thorough stepwise to-be process flow review as a pre- requisite. For greenfield SAP programs, the to-be process flows can be conceptual but for global template or standardized SAP module deployment this walk through should be conducted in a SAP Sandbox or if available an QA system. 2. Additionally in blueprint, detailed business requirements should be produced and added to the HLR scenarios document. A requirement traceability matrix should be created that maps each business requirement to at least one business process flow. These flows should then be mapped to standard solution or a gap followed by link to at least one UAT scenario. This approach will ascertain if each of your business requirement is tested in User Acceptance Testing by at least one UAT scenario. 3. Fit-Gap Analysis – All BPD documents should include fit-gap analysis for each process step against standard SAP solution being deployed. All gaps should have high level solution direction that will serve as the starting point for functional design of these gap in the build phase. 4. Solution Inventory – This deliverable should include summary of all configuration objects and gaps in SAP that were identified during the blueprint phase. 5. Integrated Solution Architecture document should be created by the Solution Architect from your IT vendor. This document should show layout of SAP system with modules being deployed along with external systems that will be integrated with the new SAP platform. All changes to standard SAP software specific to the project should be well documented in this blueprint phase deliverable and further updated in build phase. Blueprint Phase Exit Criteria  All BPDs are reviewed and signed off by Business Leads for each business function
  • 5. 5 | P a g e  Solution Inventory approved and signed off by IT program lead and approved by Advisory Board  Solution Architecture reviewed and approved by IT Program Lead  Build plan and IT/Business resource requirements reviewed with confirmed commitment from all key stakeholders  All change requests reviewed by Change Control Review Board with documented outcome  Build milestones and quality gates approved by Project Board  Final signoff by the Executive Sponsor to exit the blueprint phase based on recommendation from Advisory Board. Build Phase Initially in build phase, IT architects, technical and functional consultants will configure, design and build the to-be SAP solution. However, this phase is not only about build and IT. Early in build phase the business and data migration team should start assessing the quality of data in legacy systems and also verify the migration tools along with strategy. Another important task for business SMEs and key users is to define comprehensive stepwise UAT scenarios that should include standalone tests within each business function as well as end-to-end scenarios. Recommendations for Build Phase: 1. All functional and technical design documents for gaps identified during the blueprint in the standard SAP solution should be reviewed by IT Solution Architect and approved by IT leadership. 2. Configuration Rationale and Master Data Design documents should be created for each configuration set and master data entity respectively. These deliverables should be reviewed by Solution Architect and business content (if any) should be signed off by business functional leads. 3. Data Migration lead should drive the extraction and cleansing of data in the legacy systems. The DM lead should drive preliminary review and approval of cleansed data from business data owners. 4. At least two cycles of data migration simulation runs should be conducted. These simulation cycles should be an iterative process until 95-98% data accuracy with data load is achieved. Each cycle should involve validation of post migrated data in QA system by business stakeholders with signoff from Data Migration lead. About 2-5% data should be used for each of these cycles to allow enough sampling but also ensuring that you have sufficient data for future cycles. 5. Each business function should document UAT scripts covering all business scenarios defined in the scoping phase of the project. Each scenario and business requirement
  • 6. 6 | P a g e should be covered by at least one UAT test script. Documentation should be stepwise with expected results for each step. Business Functional Lead should review and signoff all UAT scripts for completeness and accuracy. They should also validate that these UAT scripts cover all common scenarios along with variations, exceptions and negative tests. 6. Internal auditors should review all UAT scenarios and confirm that all necessary IT general controls are included in these scripts. Also auditors and process owners need to confirm that all applicable compliance checks (eg. Sarbanes- Oxley) are included in the UAT scripts where necessary. In addition, IT Security Lead should signoff confirming all user roles and authorizations are properly setup with no conflicts in segregation of duties. 7. Business Migration Strategy draft should be prepared and reviewed by all business stakeholders in build phase. This deliverables can be finalized and signed off about 4-6 weeks before entering final preparation phase. 8. Integrated cutover strategy draft should be reviewed with all cutover stakeholders before exiting the build phase. Cutover strategy should include detailed cutover tasks showing interdependencies between cutover activities with an owner against each cutover task. 9. GoLive success markers provided in the project business case should be reviewed with the business key users in conjunction with KPIs, benchmarks. Tools and reports to be used after cutover to measure these KPIs should be reviewed with business SMEs and confirmed by Business Functional Lead. 10. End user training plan and documentation should be produced by IT vendor in collaboration with business SME. These training documents should be approved by each business functional lead. 11. Org Change Management Strategy draft should be reviewed with business stakeholders along with internal stakeholders that interact with external constituents in order to understand the impact on external community. This document should include all change impacts to processes, internal operations, people and external constituents including customers, suppliers, business partners, affiliates, distributors and other third parties. It is important that change impact is reviewed early with all the above stakeholders so that any necessary calibration to the program can be considered before exiting build phase. 12. A full suite of regression tests should be executed once the build is complete for Global Template or standard SAP module(s) deployment to confirm that any modifications to the template core
  • 7. 7 | P a g e system processes did not break existing standard template functionality. IT Project Manager should signoff indicating successful completion of regression tests. Regression testing should be ideally completed prior to UAT and can be conducted simultaneously with SIT. Build Phase Exit Criteria  All configurations are complete and gaps in standard SAP solution are resolved. IT Project Manager and Solution Architect has signed off on these build deliverables.  Systems Integration Testing (SIT) is completed successfully by IT vendor and the output is signed off by the IT Program Lead, IT Project Manager and also the Solution Architect.  Data Migration approach and tools are verified with simulation runs and signed off by Data Migration lead.  All other deliverables discussed in the above recommendations are completed and approved by respective owners. User Acceptance Testing (UAT) In my view, UAT should not only test but confirm the quality of your blueprint and build phases. Some transformation programs fail because they consider UAT as the first instance of verification of to be processes. In UAT business should confirm that processes reviewed in blueprint phase are working exactly as anticipated. It is a best practice to include as many business critical end users as participants in UAT along with SMEs so that they have enough time to understand the new system processes and capabilities. Recommendations for UAT: 1. Ensure in UAT kickoff that all testers having a clear understanding of UAT structure and daily goals to be achieved. Tools to log UAT output and issues tracking should be reviewed with all participants. 2. Step-by-step output of each UAT script should be logged with confirmation from SME or business lead that script was successfully completed. All E2E UAT scenarios should be signed off by the process owners. 3. All updates to master data source arising out of UAT issues should be done by data migration team and signed off by Data Migration Lead. 4. Business functional leads along with Executive Sponsor should sign off on UAT completion only when all UAT scenarios are successfully completed and all defects are resolved with re-tests. 5. IT Project Manager should ensure a new QA system is setup prior to UAT completion which will be used to perform migration dry run.
  • 8. 8 | P a g e Exit Criteria for UAT All UAT scenarios should be successfully completed and signed off. All defects should be resolved and retested. Any exceptions should be aligned with business program leader and documented in UAT signoff document. Cutover Preparation Phase Cutover Preparation phase is the time to verify that all cutover prerequisites are fulfilled and your entire organization is ready to cutover onto the new system. Recommendations for Cutover Preparation Phase: 1. Conduct reviews of cutover, business migration, data migration and org change strategies with final approvals on each of these documents from respective owners. 2. Confirm pre-cutover and post GoLive communication plan with internal and external constituents. 3. Disaster recovery and rollback plan should be finalized and signed off by your IT infrastructure and IT Program Lead. 4. For large SAP transformation programs involving multi-business functions and large data entity conversions, it is important to conduct a pre-cutover dry run in new QA environment with inclusion of at least 95% data set that will be actually used during the cutover. This will simulate your ECC cutover tasks to ensure that you can smoothly migrate the data and also execute key transactions in within this QA system. The 5% allowance is for master data and transactions that may change between the dry run and GoLive. Business SMEs should perform pre-load and post-load validations in this QA system followed by approval from each business functional lead that own these data objects and transactional data. 5. Confirm ownership and protocols to monitor SOX compliance and IT controls in the new environment. Cutover Period Cutover period is time sensitive period that include execution of all pre-cutover activities leading up to the day of GoLive. Daily all hands review of cutover tasks are conducted by IT Project Manager and Cutover Lead. All cutover tasks should be sequentially planned considering the dependencies between master data objects and transaction data. Some Recommendations for Cutover: 1. Schedule at least four Go-NoGo checkpoints during the cutover period. First checkpoint to confirm the master data is loaded correctly with post-load validation approval from business data owners. Second checkpoint should be scheduled when primary transaction data sets are loaded like inventories, policies, financials, etc. Third check point
  • 9. 9 | P a g e held when all transactional data is loaded into production and verified by business owners of these entities. And finally the last Go-NoGo checkpoint scheduled when pilot processing of few select transactions is conducted in the new live production system. A separate Steering Committee ‘Go-NoGo’ should be scheduled between third and final checkpoint discussed above. Additional checkpoints should be considered depending on the magnitude and complexity of your business transformation program. 2. Each master data entity should be validated and signed off by the business owner after migration into the production system. 3. All open transactional entities like open claims, open sales orders, open policies, open purchase orders, collections, AR/AP etc should be validated and approved by business functional owners after migration to production. 4. Any manual corrections should be documented and pre-approved by business and Cutover Lead. 5. A centralized cutover directory should be created that includes all business and IT contact person for each area of the program along with first and second level of escalation points. There should be a functional email address and hotline for all customers, third parties, partners and other external stakeholders to reach out in case they have issues working with the newly deployed systems. Post Cutover Stabilization Now that you are live it is important to keep an open channel of communication with entire business community to ensure smooth operations in the new production system. IT vendor project team should be in place to support the cutover for at least 3-5 months after GoLive depending on the magnitude and complexity of the cutover. Business teams for large transformations may require operational guidance and support from IT SAP experts for extended period ranging from 8-12 months. Confirm capabilities of internal support staff if your IT vendor has already transitioned the project to your IT Center of Excellence. This period could involve new post-cutover enhancements to production systems in order to address pain-points, bottlenecks and efficiency improvements. Recommendations for Post Cutover Stabilization: 1. Verify all GoLive issues are logged and reviewed in all hands meeting at least once every day after cutover for a few weeks until the number of open issues have subsided to pre- determined acceptable level. 2. Business functional leads along with Business program manager should review the success markers (incl. KPIs) regularly to ensure operational benchmarks are achieved.
  • 10. 10 | P a g e 3. IT Project Manager should monitor and report system performance statistics to Project Board along with technical KPIs. If you have outsourced your IT services to another third party company then extra precaution should be taken to confirm the capabilities and readiness of the provider. The Project Manager of your outsourced IT provider should confirm that complete knowledge transfer has been received by their support personnel for each business function. Final signoff on readiness should be sought from the IT Project Manager and Transition Lead from the program IT vendor. With these measures you can reduce risks associated with complex business transformation programs and keep your implementation on track for a successful deployment. About the Author Deepak Mandrekar is an Executive SAP Program Leader and also the Founder of iii Technologies. For last 8 years he has led six SAP business transformation programs as a Trusted Advisor and Executive Program Leader primarily engaged by the CIO, CFO and Executive Sponsors heading these implementations. Overall he has been part of 14 SAP transformations in North America throughout his career starting as SAP Solution Architect in early years and quickly moving into program leadership roles. Some of these transformations have included global template deployments and select others involved significant custom development. He is widely recognized in the industry for turnaround of struggling transformation programs with customized best practices and strategic direction. Deepak holds a Master of Science in Engineering from Purdue University.  deepak.mandrekar@iiitech.com  (609) 901-8000 Copyright © 2013 iii Technologies. All rights reserved. This document is for private circulation only and may not be reproduced without written consent from the author and iii Technologies.