Project Scope Management
PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
Project Scope Management
Scope management is the process in which we identify, define and control the outputs, outcomes and
benefits of a Project
Product
Scope
Project
Scope
Copyright © 2018, edureka and/or its affiliates. All rights reserved.
Scope Management Overview
PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
Tailoring Considerations
PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
Governance
5
Stability of
Requirements
4
Development
Approach
3
Validation &
Control
2
Knowledge & Requirements
Management
1
Copyright © 2018, edureka and/or its affiliates. All rights reserved.
Scope Management Processes
PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
Scope Management Processes
Plan Scope Management1
Collect Requirements2
Define Scope3
Create WBS4
Validate Scope5
Control Scope6
www.edureka.co/pmp
Plan Scope Management
PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
Plan Scope Management
• Plan Scope Management is the process of creating a scope management plan that
documents how the project and product scope will be defined, validated, and
controlled
• It provides guidance and direction on how scope will be managed throughout the
project
• This process is performed once at predefined points in the project
Description
PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
Inputs
Project Charter
Project
Management Plan
Enterprise
Environmental Factors
Organizational
Process Assets
Plan Scope Management
PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
Tools &
Techniques
Expert Judgement
Meetings
Data Analysis
Plan Scope Management
PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
21
Scope Management
Plan
Requirement
Management Plan
Outputs
Plan Scope Management
Collect Requirements
PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
Collect Requirement
• Collect Requirements is the process of determining, documenting, and managing
stakeholder needs and requirements to meet objectives
• It provides the basis for defining the product scope and project scope
• This process is performed once at predefined points in the project
Description
PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
Inputs
Collect Requirement
Organizational
Process Assets
Enterprise
Environmental Factors
Agreements
Project
Documents
Project
Management Plan
Business
Documents
Project Charter
PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
Tools &
Techniques
Expert Judgement
Data Gathering
Data Analysis
Decision Making
Prototypes
Data Representation
Context Diagram
Interpersonal & Team
Skills
Collect Requirement
PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
Outputs
Collect Requirement
21
Requirements
Documentation
Requirement
Traceability Matrix
Define Scope
PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
Define Scope
• Define Scope is the process of developing a detailed description of the project and
product
• It describes the product, service, or result boundaries and acceptance criteria
Description
PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
Inputs
Define Scope
Project Charter
Project
Management Plan
Project
Documents
Organizational Process
Assets
Enterprise
Environmental Factors
PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
Tools &
Techniques
Expert Judgement
Decision Making
Data Analysis
Interpersonal & Team
Skills
Product Analysis
Define Scope
PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
Outputs
Define Scope
21
Project Scope
Statement
Project Documents
Updates
Create WBS
PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
Create WBS
• Create WBS is the process of subdividing project deliverables and project work into
smaller, more manageable components
• It provides a framework of what has to be delivered
• This process is performed once at predefined points in the project
Description
PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
Inputs
Create WBS
Project
Documents
Enterprise
Environmental Factors
Organizational
Process Assets
Project
Management Plan
PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
Tools &
Techniques
Expert Judgement
Decomposition
Create WBS
PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
Outputs
21
Scope Baseline
Project Documents
Updates
Create WBS
Validate Scope
PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
Validate Scope
• Validate Scope is the process of formalizing acceptance of the completed project
deliverables
• it brings objectivity to the acceptance process and increases the probability of final
product, service, or result
• This process is performed periodically throughout the project as needed
Description
PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
Inputs
Validate Scope
Project
Documents
Verified
Deliverables
Work Performance
Data
Project
Management Plan
PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
Tools &
Techniques
Inspection
Decision Making
Validate Scope
PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
Outputs
Validate Scope
32 41
Accepted Deliverables
Work Performance
Information
Change Requests
Project Document
Updates
Control Scope
PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
Control Scope
• Control Scope is the process of monitoring the status of the project and product
scope
• it manages the changes incorporated to the scope baseline that is maintained
throughout the project.
• This process is performed throughout the project.
Description
PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
Inputs
Project
Documents
Work
Performance Data
Organizational
Process Assets
Project
Management Plan
Control Scope
PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
Tools &
Techniques
Data Analysis
Control Scope
PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
Outputs
32 41
Work Performance
Change Requests
Project Management
Plan Updates
Project Documents
Updates
Control Scope
PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
Summary
Product
Scope
Project
Scope
Project Scope Management | Project Management Tutorial | PMP® Certification Training | Edureka

Project Scope Management | Project Management Tutorial | PMP® Certification Training | Edureka

  • 1.
    PMP® CERTIFICATION EXAMTRAINING www.edureka.co/pmp
  • 2.
    PMP® CERTIFICATION EXAMTRAINING www.edureka.co/pmp Topics For Today’s Discussion Project Scope Management Scope Management Overview Scope Management Processes Ref: A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition
  • 3.
    Copyright © 2018,edureka and/or its affiliates. All rights reserved. Project Scope Management
  • 4.
    PMP® CERTIFICATION EXAMTRAINING www.edureka.co/pmp Project Scope Management Scope management is the process in which we identify, define and control the outputs, outcomes and benefits of a Project Product Scope Project Scope
  • 5.
    Copyright © 2018,edureka and/or its affiliates. All rights reserved. Scope Management Overview
  • 6.
    PMP® CERTIFICATION EXAMTRAINING www.edureka.co/pmp Tailoring Considerations PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp Governance 5 Stability of Requirements 4 Development Approach 3 Validation & Control 2 Knowledge & Requirements Management 1
  • 7.
    Copyright © 2018,edureka and/or its affiliates. All rights reserved. Scope Management Processes
  • 8.
    PMP® CERTIFICATION EXAMTRAINING www.edureka.co/pmp Scope Management Processes Plan Scope Management1 Collect Requirements2 Define Scope3 Create WBS4 Validate Scope5 Control Scope6 www.edureka.co/pmp
  • 9.
  • 10.
    PMP® CERTIFICATION EXAMTRAINING www.edureka.co/pmp Plan Scope Management • Plan Scope Management is the process of creating a scope management plan that documents how the project and product scope will be defined, validated, and controlled • It provides guidance and direction on how scope will be managed throughout the project • This process is performed once at predefined points in the project Description
  • 11.
    PMP® CERTIFICATION EXAMTRAINING www.edureka.co/pmp Inputs Project Charter Project Management Plan Enterprise Environmental Factors Organizational Process Assets Plan Scope Management
  • 12.
    PMP® CERTIFICATION EXAMTRAINING www.edureka.co/pmp Tools & Techniques Expert Judgement Meetings Data Analysis Plan Scope Management
  • 13.
    PMP® CERTIFICATION EXAMTRAINING www.edureka.co/pmp 21 Scope Management Plan Requirement Management Plan Outputs Plan Scope Management
  • 14.
  • 15.
    PMP® CERTIFICATION EXAMTRAINING www.edureka.co/pmp Collect Requirement • Collect Requirements is the process of determining, documenting, and managing stakeholder needs and requirements to meet objectives • It provides the basis for defining the product scope and project scope • This process is performed once at predefined points in the project Description
  • 16.
    PMP® CERTIFICATION EXAMTRAINING www.edureka.co/pmp Inputs Collect Requirement Organizational Process Assets Enterprise Environmental Factors Agreements Project Documents Project Management Plan Business Documents Project Charter
  • 17.
    PMP® CERTIFICATION EXAMTRAINING www.edureka.co/pmp Tools & Techniques Expert Judgement Data Gathering Data Analysis Decision Making Prototypes Data Representation Context Diagram Interpersonal & Team Skills Collect Requirement
  • 18.
    PMP® CERTIFICATION EXAMTRAINING www.edureka.co/pmp Outputs Collect Requirement 21 Requirements Documentation Requirement Traceability Matrix
  • 19.
  • 20.
    PMP® CERTIFICATION EXAMTRAINING www.edureka.co/pmp Define Scope • Define Scope is the process of developing a detailed description of the project and product • It describes the product, service, or result boundaries and acceptance criteria Description
  • 21.
    PMP® CERTIFICATION EXAMTRAINING www.edureka.co/pmp Inputs Define Scope Project Charter Project Management Plan Project Documents Organizational Process Assets Enterprise Environmental Factors
  • 22.
    PMP® CERTIFICATION EXAMTRAINING www.edureka.co/pmp Tools & Techniques Expert Judgement Decision Making Data Analysis Interpersonal & Team Skills Product Analysis Define Scope
  • 23.
    PMP® CERTIFICATION EXAMTRAINING www.edureka.co/pmp Outputs Define Scope 21 Project Scope Statement Project Documents Updates
  • 24.
  • 25.
    PMP® CERTIFICATION EXAMTRAINING www.edureka.co/pmp Create WBS • Create WBS is the process of subdividing project deliverables and project work into smaller, more manageable components • It provides a framework of what has to be delivered • This process is performed once at predefined points in the project Description
  • 26.
    PMP® CERTIFICATION EXAMTRAINING www.edureka.co/pmp Inputs Create WBS Project Documents Enterprise Environmental Factors Organizational Process Assets Project Management Plan
  • 27.
    PMP® CERTIFICATION EXAMTRAINING www.edureka.co/pmp Tools & Techniques Expert Judgement Decomposition Create WBS
  • 28.
    PMP® CERTIFICATION EXAMTRAINING www.edureka.co/pmp Outputs 21 Scope Baseline Project Documents Updates Create WBS
  • 29.
  • 30.
    PMP® CERTIFICATION EXAMTRAINING www.edureka.co/pmp Validate Scope • Validate Scope is the process of formalizing acceptance of the completed project deliverables • it brings objectivity to the acceptance process and increases the probability of final product, service, or result • This process is performed periodically throughout the project as needed Description
  • 31.
    PMP® CERTIFICATION EXAMTRAINING www.edureka.co/pmp Inputs Validate Scope Project Documents Verified Deliverables Work Performance Data Project Management Plan
  • 32.
    PMP® CERTIFICATION EXAMTRAINING www.edureka.co/pmp Tools & Techniques Inspection Decision Making Validate Scope
  • 33.
    PMP® CERTIFICATION EXAMTRAINING www.edureka.co/pmp Outputs Validate Scope 32 41 Accepted Deliverables Work Performance Information Change Requests Project Document Updates
  • 34.
  • 35.
    PMP® CERTIFICATION EXAMTRAINING www.edureka.co/pmp Control Scope • Control Scope is the process of monitoring the status of the project and product scope • it manages the changes incorporated to the scope baseline that is maintained throughout the project. • This process is performed throughout the project. Description
  • 36.
    PMP® CERTIFICATION EXAMTRAINING www.edureka.co/pmp Inputs Project Documents Work Performance Data Organizational Process Assets Project Management Plan Control Scope
  • 37.
    PMP® CERTIFICATION EXAMTRAINING www.edureka.co/pmp Tools & Techniques Data Analysis Control Scope
  • 38.
    PMP® CERTIFICATION EXAMTRAINING www.edureka.co/pmp Outputs 32 41 Work Performance Change Requests Project Management Plan Updates Project Documents Updates Control Scope
  • 39.
    PMP® CERTIFICATION EXAMTRAINING www.edureka.co/pmp Summary Product Scope Project Scope