SlideShare a Scribd company logo
1 of 141
Drilling Preliminaries
Kartikeya Pandey Prof Anil Kumar
MBA IFM (HOD Power & Infrastructure
500021353 Management)
Submitted by Submitted to
Steps to Drill A Gas/Oil Well
1. Complete or obtain seismic, log,
scouting information or other
data.
2. Lease the land or obtain
concession.
3. Calculate reserves or estimate
from best data available.
Steps to Drill A Gas/Oil Well
4. If reserve estimates show
payout, proceed with
well.
5. Obtain permits from
conservation / national
authority.
6. Prepare drilling and completion
program.
Steps to Drill a Well - cont’d
7. Ask for bids on footage, day work,
or combination from selected
drilling contractors based on
drilling program.
8. If necessary, modify program to fit
selected contractor equipment.
9. Construct road, location/platforms
and other marine equipment
necessary for access to site.
Steps to Drill a Well - cont’d
10. Gather all personnel concerned for
meeting prior to commencing
drilling (pre-spud meeting).
11. If necessary, further modify
program.
12. Drill well.
Introduction
When a suitable
structure, sufficiently large, so as
to give economically viable reserves
of HCs) is discovered for the
presence of HCs by
geological, geochemical &
geophysical methods, a location for
drilling of an exploratory / wild cat
well is decided.
Classification of Wells
Exploratory Well / WildCat
Well:
They are drilled purely for
exploratory purposes i.e. for
gathering information. The well is
drilled to find and produce oil or
gas in an unproven area, or to find
a new reservoir in fields, or to
extend a known reservoir.
Classification of Wells
Discovery Well:
If the well does discover a new
field, it is called the discovery well
for that field.
Classification of Wells
Appraisal Well/ Delineation
Well:
After the discovery, the size of the field
must be determined. Field size is
determined by “step out” or
“Delineation” or “Appraisal” well that
are drilled to the sides of the discovery
well.
Classification of Wells
Developmental Wells:
Wells drilled in the known extent of
the field are called Developmental
Wells.
Classification of Wells
Infill Wells:
Wells that are drilled in between
producing wells in an established
field to increase the production
rate are called Infill wells.
Classification of Wells
Production Wells:
They are drilled primarily for
producing oil and gas, once the
producing structure and
characteristics are determined.
The well is created by drilling a hole of
5 – 36 inches (127.0 – 914.4 mm) in
diameter into the earth with a drilling
rig that rotates a drill string with bit
attached.
• The cost of drilling is very great. On
an offshore rig, it may cost $10,000
for each metre drilled.
• A company incurs vast losses for
every “dry hole” drilled.
Drilling A Well
A drilling rig is the machine which
creates holes (usually called
boreholes) in the ground.
Drilling Rig
Drilling rigs can be:
• Small and portable, such as those
used in mineral exploration
drilling, water wells and
environmental investigations.
• Huge, capable of drilling through
thousands of meters of the Earth's
crust.
Drilling Rig
Drilling rigs can be mobile equipment
mounted on trucks, or trailers, or more
permanent land or marine-based
structures (such as oil platforms,
commonly called 'offshore oil rigs).
The term "rig" therefore generally
refers to the complex of equipment
that is used to penetrate the surface of
the Earth's crust.
Primarily in onshore oil & gas
fields, once a well has been
drilled, the drilling rig is moved
off of the well and a service rig ( a
smaller rig) for completions is
placed for well completion.
This frees up the drilling rig to
drill another hole and streamlines
the operation.
In early oil exploration, drilling
rigs were semi-permanent in
nature and the derricks were
often built on site and left in
place after the completion of
the well.
Cable Tool Drilling
Cable Drilling is a pioneer
method and the first oil wells in
the United States were drilled
with cable tools to a depth of
20 mts.
Cable Tool Drilling
An engine , originally a steam
engine, causes a wooden
beam to pivot up & down.
The bit, is made up of solid
steel rod about 4 ft. (1 & 1/3m)
long with a chisel point on it.
Drilling Rig
Steam
Engine
Walking
Beam
Derrick
Drawworks
Pulley
Bit
Drill collar
Drill ing Line
Cable Tool Drilling ( Cont…..)
As the walking beam pivots, it
causes the bit to rise and fall.
The bit pounds the well down
by pulverizing the rock.
Drilling Rig
Cable Tool Drilling ( Cont…..)
After drilling 3 - 8 ft., (1 – 2 ½ m),
the bottom of the well becomes
clogged with rock chips.
The bit is raised and a bailer is
lowered into the well to remove
the rock chips and water.
Drilling Rig
Cable Tool Drilling ( Cont…..)
After the bailer is raised and
emptied, the bit is lowered into
the well to pound deeper.
Drilling Rig
Cable Tool Drilling ( Cont…..)
Heavy casing ( large diameter
pipe) is run down the well to
keep water from filling the well
and to prevent the sides from
caving in.
Drilling Rig
Cable Tool Drilling ( Cont…..)
Cable tool drilling is very slow –
25ft. ( 7 ½ m) per day (average)
and 60 ft. (20m) being very
good.
Drilling Rig
Rotary Drilling
Today, almost all well are drilled
with rotary drilling rigs.
The rotary drilling rig rotates a
long length of steel pipe with a
bit on the end of it to cut a hole
called the well bore.
Drilling Rig
Rotary Drilling
The rotary rig consists of four major
systems.
(1) Power System : Diesel Engine
(2) Hoisting System : Derrick / Mast,
Draw work
(3) Rotating System : Swivel, Kelly,
Rotary table, Drill string, Drill Pipe,
Drill Collar, Bit etc.
(4) Circulating system: Mud Tanks
Drilling Rig
Introduction
Derrick
Crown Block
Shale Shaker
Mud tank
Swivel
Drill Line
BOP
Mud Pump
Motor/ Power Source
Drill Bit
Kelly
Rotary Table
Crown Block:
 A fixed, steel frame with steel
wheels on a horizontal shaft. It is
located at the top of a derrick or
Mast.
 Is an assembly of pulleys
mounted on beams at the top of
derrick
CROWN BLOCKS
Derrick:
The derrick or Mast is the tower directly
above the well that supports the crown
block at the top & provides support for
the drill pipe to be stacked vertically as
it is pulled from the well.
It is generally 40m in height strong
enough to hold the weight of the drill as
it goes deeper & deeper into the rock.
The derrick can support a weight of
about 50 tonnes or more.
Kelly :
The kelly is a square rod
attached to swivel.
The kelly turns all the pipe
below it to drill the hole.
To the lower end of the kelly, a
10 m pipe is screwed in.
Kelly
Kelly
Bushing
Drillpipe
Pin
Box
DrilPipe:
The drillpipe (which, when joined
together, forms the drillstring)
consists of 30ft. (10m) sections
of heavy steel pipe. The pipes
are threaded so that they can
interlock together.
As the drill goes deeper, a new
pipe is added to the end of the
first pipe and so on.
Drill Collars
Swivel :
The swivel allows the kelly to
rotate freely.
SWIVEL
Rotary Table:
The kelly along with the pipe &
drilling bit is rotated by a rotor
known as “Rotary Table”.
It is a circular table in the derrick
floor that is turned clockwise by
the prime movers. If it were
turned in the opposite direction,
the drillpipe would unscrew.
DRAWWORKS DRIVEN ROTARY
TABLE
Drill stem:
3 main components are Kelly,
Drillstring & the Bit.
Drill string:
It is made up of steel pipes called drill
pipes, drill collars (below the drill pipes
are thicker – walled, heavier, stronger pipes
to put weight on the bottom of the drills
string to drill straight down and prevent the
drill pipe from kinking & breaking) and bit
in the well.
Drill string:
It is made up of steel pipes called drill
pipes, drill collars (below the drill pipes
are thicker – walled, heavier, stronger pipes
to put weight on the bottom of the drills
string to drill straight down and prevent the
drill pipe from kinking & breaking) and bit
in the well.
Drill Bit :
It is located at the bottom end of
the drill string. The drill bit is
responsible for breaking up and
dislodging rock, sediment, and
anything else that may be
encountered while drilling. There
are dozens of different drill bit
types, each designed for different
subsurface drilling conditions:
1.Steel Tooth Rotary Bits are
the most basic type of drill
bit used today.
2. Insert Bits are steel tooth
bits with tungsten carbide
inserts.
Disadvantages of Insert Bit
• Inserts dig deeply into formation.
Cones can hit the formation and
transmit shock loads to bearings and
damage bearings
• Abrasive mud containing sands can
erode cutters base and let them fall
in the well
• Much more expensive
• Can not drill soft to soft-medium hard
formations as fast as steel-tooth bits
3. Polycrystalline Diamond
Compact Bits have
polycrystalline diamond
inserts attached to the
carbide inserts found in
Insert Bits.
4. Diamond Bits have industrial
diamonds implanted in
them, to drill through
extremely hard rock
formations. Diamond bits are
forty to fifty times harder than
traditional steel bits, and can
thus be used to drill through
extremely hard rock without
dulling overly quickly.
Drilling Mud:
When the drilling goes on , a special
type of drilling fluid known as mud is
pumped down by a hose through the
drilling pipe to keep the bit cool.
(The mud flows just like ink flows out of a pen)
A viscous mixture of clay (usually
bentonite) and additives with either
water or oil or an emulsion of water
with droplets of oil or a synthetic
organic fluid.
Drilling Mud ( Cont…..)
The mud squirts out of the drilling bit
and flows back through the annular
space between the outer side of the
pipe and the drilled hole carrying with
it chips of rocks that are cut.
Drilling Mud ( Cont…..)
Geologists work day and night to
record the sequence in which the
different types of rocks come out.
After studying the rocks, the
geologists prepare a map showing the
vertical distribution of rocks
underground.
Drilling Mud ( Cont…..)
From this map, it is possible to find
out :
(1) The type of rock
(2) The depths at which different rock
types occur
(3) The thickness of the bed of each
rock type.
The geologists also note if the rocks
give any sign of oil.
3) the mixture of drilling
mud and drill cuttings are
circulated up the annulusscreens
5) the drill cuttings are
removed, and form a cuttings
pile. This can be hauled off and
4) the mixture is
circulated across
screens at surface
1) Clean drilling mud is
taken from the steel mud
tanks and pumped down the
inside of the drill pipe.
2) the mud is circulated through
the drill bit into the
annulus, lifting the cuttings
removed by the drill bit.
6) Clean mud
falls through
the screens and
is returned to
the pits
The Drilling Mud Cycle
mud pump
The drilling mud is circulated
on a rotary drilling rig to :
1.Cool & lubricate the drillstem.
2. remove cuttings from the
hole.
3. control subsurface
pressures.
4. Seal permeable formations.
Safety System
Various safety devices are
used at the wellhead to cope
with dangerous situations
that may occur during a
drilling operations:
Safety System
Reservoirs penetrated by the
drill may contain pressures
higher than the mud weight can
control and the well may
show a tendency to erupt and
blowout.
Safety System
 When oil is struck, the oil gushes out.
 Sometimes the oil gushes out with
such tremendous force that it becomes
dangerous.
 The “Blow – Out” can kill men and
damage the oil rig.
 To reduce the risk of oil gushing
out, there is a strong cap in every
well.
The cap is used as a “BLOW OUT
PREVENTER” or “BOP”.
WELL COMPLETION
Once a natural gas or oil is drilled , and it
has been verified that commercially viable
quantities of crudes are present, for
extraction, the well must be “completed”.
Completion is done to allow for the flow of
crude out of the formation and up to the
surface.
WELL COMPLETION ( Cont…..)
Completion includes strengthening
the well hole with casing, evaluating
the P & T of the formation and then
installing the proper equipment to
ensure an efficient flow of the crudes.
WELL COMPLETION ( Cont…..)
Completing a well consists of :
 Installing the well casing
 Completing the well
 Installing the wellhead
 Installing lifting equipment
 Treating the formation.
Well Casing
Installing well casing is an important
part of the drilling and completion
process.
Well casing consists of a series of
metal tubes installed in the freshly
drilled hole.
Objectives of Casing:
1. Supports the walls of the wells.
2. Prevents caving tendencies of
unconsolidated formation.
3. Prevents water from entering the
oil and gas yielding strata from
overlying or underlying formations.
Gas & oil must be confined within the
well casing so that they may not
escape into overlying / underlying
formation.
If the hole is uncased, oil and gas
could escape through the well into a
permeable horizon having a lower
pressure and thus, can be dissipated
through them so that desired
recovery can never be effected.
In oil well drilling, the cost of casing is
usually the greatest single item of
expense and selection of pipe weight ,
size and planning and design of
casing installation etc. are amongst
the most important problems
encountered in well drilling.
WHY???
 The casing required to be lowered in
the well should be effectively serve
the purpose.
 It must be of sufficient strength,
adequate to withstand the stresses
to which it is subjected in the well.
 It should be water tight and it
should be made of material that
resists corrosion or be protected
against corrosion (particularly when it
is in contact with saline ground water)
 The material of which the casing is
made should be hard & tough and
rigid enough to resist abrasion and
distortion by contact with the rock
walls of the well or drilling tools.
TYPES OF CASING
Casing types involve the
character of the material from
which the tubes are made, the
method of their manufacture, the
design of the joints and especially
the method of connecting one
individual section to another.
TYPES OF CASING
 In recent years, economy and safety of
operation at increased depths have
necessitated still further changes and
improvements in the casing designs.
 Resulted in the use of alloy steels having
tensile strength of 80.000 lbs / inch2 or
more with further changes in thread and
coupling designs.
 There are four grades of seamless alloy
steel casing in use.
In most wells, the diameter of the well
hole decreases the deeper it is drilled,
leading to a type of conical shape that
must be taken into account when
installing casing.
A well commonly has 3 or more
concentric casing string.
Shallow wells can have 2 or just 1
casing string.
The largest diam. & shortest length
string is on the outside.
The smallest diam. & longest length
string is on the inside.
The outside string is cemented first
and the inside string last.
A well commonly has 3 or more
concentric casing string.
Shallow wells can have 2 or just 1
casing string.
The largest diam. & shortest length
string is on the outside.
The smallest diam. & longest length
string is on the inside.
The outside string is cemented first
and the inside string last.
There are five different types of well
casing:
• Conductor Casing
• Surface Casing
• Intermediate Casing
• Liner String
• Production Casing
Conductor Casing
• Conductor casing is installed first,
usually prior to the arrival of the
drilling rig.
• The hole for conductor casing is
often drilled with a small auger drill,
mounted on the back of a truck.
Conductor Casing
• Conductor pipe is the largest diam.
Casing string :
 Offshore : 30 – 42 inch. or 76 – 107 cm
 Onshore: 16 inch. or 40 ½ cm
• Conductor Casing is usually no
more than 20 to 50 feet long.
Conductor Casing
• It is installed to prevent the top of the
well from caving in & isolates any
near surface & fresh water.
• It serves as a route for the drilling
mud coming from the well to the mud
tanks.
Surface Casing
• Surface casing is the next type of
casing to be installed after conductor
casing.
• It can be anywhere from a few
hundred to 2,000 feet long, and is
smaller in diameter than the
conductor casing ( 13 ¼ inch or 35
cm.)
Surface Casing
• The primary purpose of surface
casing is to prevent soft, near
surface sediments from caving into
the well.
• It also protects fresh water
reservoirs from further
contaminating by drilling mud.
Surface Casing
• It also serves as a conduit for
drilling mud returning to the surface.
• It helps protect the drill hole from
being damaged during drilling.
Intermediate Casing
• Intermediate casing is can be set to
isolate problem zones in the well
such as abnormal high pressure
, lost circulation, or a salt layer.
• It is typically 85/8inch ( 22 cm) .
Production Casing
• Production casing, alternatively
called the 'oil string' or 'long string,’
is installed last and is the deepest
section of casing in a well.
• This is the casing that provides a
conduit from the surface of the well
to the petroleum-producing
formation.
Production Casing
• The final string of casing is the
“Production Casing” or “Oil String”
that runs down to the producing
zone.
• It is typically 5 ½ inch (14cm) in
diameter.
Well casing is a very important part of
the completed well.
In addition to strengthening the well
hole, it provides a conduit to allow
hydrocarbons to be extracted without
intermingling with other fluids and
formations found underground.
Instead of a casing string, a liner
string can be set on the bottom of the
well to save money.
While a liner string is very similar to
casing string in that it is made up of
separate joints of tubing, the liner
string is not run the complete length
of the well.
A liner string is hung in the well by a
liner hanger, and then cemented into
place.
The section of the liner in the pay zone
may be wire wrapped screen pipe
with openings as small as (0.008 inch)
or perforated pipe may be used with
openings as large as ½ inch or above.
The liner may extend up into the
production casing only a short
distance and be sealed to the
production casing with a packer , or if
desired, may be extended to the
casing head on the surface, thus
forming an inner producing string.
Casing Programs
• Sometimes the well is drilled in
stages called a casing program.
• A well is drilled to a certain
depth, cased and cemented, and
then the well is drilled to a deeper
depth, cased and cemented
again, and so on.
• Each time the well is cased, a smaller
diameter casing is used.
Cementing
After running in the casing string to
the desired depth, it is cemented
place.
A cement slurry is then pumped down
the casing and up around the outside
of the casing in the annular space in
the hole to the height desired and
there the cement is allowed to set &
harden to permanently fix the casing
in place.
The wall of hardened cement keeps
the hole from caving, which might
collapse the casing and to make the
secure in the hole.
After the casing is installed, tubing is
inserted inside the casing, running
from the opening well at the top to the
formation at the bottom.
The hydrocarbons that are extracted
go up this tubing to the surface.
Tubing
Small diameter pipe called tubing is
run into the well to just above the
bottom to conduct the water, gas and
oil ( produced fluids) to the surface.
Tubing protects the casing from
corrosion by the producing fluids.
Since the casing is cemented in the
wall, it is very difficult to repair the
casing.
The tubing string is suspended in the
well, so, it can be pulled from the well
to repair or replace it during a “work
over”
WELL COMPLETIONS
Well completion commonly
refers to the process of
finishing a well so that it is
ready to produce oil & NG.
There are a number of types of
completion depending on the
characteristics and location of the HC
formation to be mined:
 Open Hole Completion
 Conventional Perforated Completion
• Sand Exclusion Completion
• Permanent Completion
• Multiple Zone Completion
• Drain hole Completion
Open Hole Completion
• Used in very competent formations.
• Consists of simply running the
casing directly down into the
formation, leaving the end of the
piping open.
• There is no production casing over
the oil or gas zone.
• This is a very primitive way to
complete a well.
Conventional Perforated Completion
• A modern well is completed with
steel casing set over the oil zone.
• It consists of production casing
being run through the formation.
• The sides of this casing are
perforated with tiny holes along the
sides facing the formation, which
allows for the flow of HCs into the
well hole.
Conventional Perforated Completion
• Perforation involves the use of
specialized equipment designed to
make tiny holes through the
casing, & cementing lying in
between the formation and the open
hole.
Conventional Perforated Completion
• In the past, “bullet perforators” were
used which were essentially small
guns lowered into the well.
• The guns were when fired from the
surface, sent off small bullets that
penetrated the casing and cement.
• Today, “jet perforating” is preferred
consisting of small, electrically ignited
charges that are lowered into the well.
When ignited, these charges poke tiny
holes through the formation.
Then a device called a "perforating gun"
(A) is lowered into the hole at the depth
where the oil or gas formation is
found. This may be anywhere from
several hundred feet down to tens of
thousands of feet.
After the gun is lined up properly, powerful
shaped explosive charges are fired (B) from
the control panel in the truck located up at
ground level. These explosives blast a hole
in the steel casing and cement, up to
several feet out into the rock. Finally, the oil
and gas fluids flow into the holes and up
the well to the surface (C).
This method of completion is much
better than the old open-hole method
shown in the first picture.
The PG is able to control exactly where
the perforations go.
This helps to limit the amount of
undesirable fluids, like salt water,
entering the hole, and maximize the
amount of hydrocarbons that can be
extracted from the well.
Sand Exclusion Completion
• Sand exclusion completions are
designed for production in an area that
contains a large amount of loose sand.
• This completion is designed to allow
for the flow of natural gas and oil into
the well, but at the same time, prevent
sand from entering the well as the
sand inside the well can cause many
complications (erosion of casing &
other equipment).
Sand Exclusion Completion
• The most common method of keeping
sand out of the well hole are:
 Screening or Filtering system.
• This includes analyzing the sand and
installing a screen or filter to keep the
sand particles out.
• This filter may either be a type of screen
hung inside the casing, or adding a layer
of specially sized gravel outside the
casing to filter out the sand. Both of these
types of sand barriers can be used in
open hole & perforated completions
Permanent Completion
• In this, the completion and wellhead
are assembled and installed only
once.
• The tubing is lowered to the desired
depth before perforation and not
removed during the life of the well.
All other operations are carried out
through tubing.
• Completing a well in this way can
lead to a significant cost savings.
Multiple Zone Completion
• In this practice, the HCs from two or
more formations may be produced
simultaneously, without mixing with
each other.
• eg. A well may be drilled that
passes through a number of
formations on its way, it may be
efficient in a horizontal well to add
multiple completions to drain the
formation most effectively.
Multiple Zone Completion
• Although it is common to separate
multiple completions so that the
fluids from the different formations
do not intermingle.
• If the different formations being
drilled are close enough in nature to
allow fluids to intermingle in the well
hole and it is necessary to separate
different completions, hard rubber
“packing” are used .
Drain hole Completion
• It is a form of horizontal or slant
drilling.
• It consists of drilling out
horizontally into the formations from
a vertical well, essentially providing
a “drain” for the HCs to run down
into the well.
WELL HEAD
The well head consists of equipments
on the surface that:
 supports the various pipe strings
 seals off the well to prevent leaking
of oil or NG out of the well.
 controls the flow rates of reservoir
fluids.
• Each string of casing usually hangs
from a casing head.
• The casing heads consists of heavy
steel fitting at the surface.
• It support the entire length of casing
that is run all the way down the well.
• “Metal and rubber seals” in the
casing head prevent fluids from
moving within the wellhead or
escaping to the atmosphere.
• Each casing head also has a place
for a pressure gauge to warn of
leaks.
• This typically contains a gripping
mechanism that ensures a tight seal
between the head and the casing
itself.
• “The Tubing head” is much like the
casing head.
• It provides a seal between the
tubing , which is run inside the
casing.
• It provides connections at the
surface, which allow the flow of
fluids out of the well to be controlled.
• The tubing head stacks above the
uppermost casing head.
• “The Christmas Tree” fits atop the
casing & tubing heads.
• It contains tubes and valves that
serve to control the flow of HCs and
other fluids out of the well.
• It commonly contains many branches
and is shaped somewhat like a
tree, thus its name, Christmas Tree .
• This is the most visible part of a
producing well and allows for surface
monitoring & regulation of the HC
production from producing well.
“The Christmas Tree” or "tree", is not
not "wellhead" as sometimes
incorrectly referred to.
• Note that a tree and wellhead are
separate pieces of equipment not to
be mistaken as the same piece.
• A wellhead must be present in order
to utilize a Christmas tree and a
wellhead is used without a
Christmas tree during drilling
operations etc.,
Lifting and Well Treatment
Once the well is completed, it begins to
produce.
HCs existing in pressurized formations
will naturally rise up through the well to
the surface. This is most commonly the
case with natural gas and light crude.
Since natural gas is lighter than air,
once a conduit to the surface is opened,
the pressurized gas will rise to the
surface.
Thus, once the CT is installed, the NG
will flow to the surface on its own
When a well is first drilled, the
formation is under pressure and
produces O&G at a very rate.
However, as more & more crude is
extracted from the formation, the
production rate of the well is decreased.
This is known as the “decline rate”.
During this time, application of certain
techniques including “Lifting
Equipment” & “Well Stimulation” can
increase the production rate of a well.
Lifting equipment consists of a variety
of specialized equipment that are used
to help “lift” petroleum out of a
formation .
This is most commonly used to extract
oil from a formation.
When oil is found as a viscous liquid, it
becomes difficult to extract it from
underground.
Various types of lifting equipment are
available, but the most common lifting
method is known as “Rod Pumping”.
Rod pumping is powered by a surface
pump that moves a cable and a rod up
and down in the well, providing the
lifting pressure required in the
well, providing the lifting pressure
required to bring the oil to the surface.
WELL TREATMENT
Well Treatment or Stimulation is
another method of ensuring the efficient
flow of HCs out of a formation.
Essentially, this type of well stimulation
consists of injecting stimulation
consists of injecting acid, water or
gases into the well to open up the
formation and allow the crude to flow
through the formation more easily.
“Acidizing” a well consists of injecting
acid (usually HCl acid) into the well.
In Limestone or Carbonate formations,
the acid dissolves portions of the rock
in the formation, opening up existing
spaces to allow for the flow of
petroleum.
“Fracturing” consists of injecting a fluid
into the well, the pressure of which
“cracks” or opens up fractures already
present in the formation.
In addition to the fluid being injected,
“propping agents” are also used. These
propping agents can consists of sand,
glass beads, silica sand etc. and serve
to prop open the newly widened
fissures in the formation.
“Hydraulic Fracturing” involves the
injection of water into the formation,
while CO2 fracturing uses gaseous .
Fracturing, Acidizing and Lifting
Equipment may all be used on the same
well to increase permeability.
These techniques are mostly used in oil
wells, but have also been used to
increase the extraction rate of gas wells.
Drilling Preliminaries Steps
Drilling Preliminaries Steps
Drilling Preliminaries Steps
Drilling Preliminaries Steps

More Related Content

What's hot

Sequence of well drilling part 1
Sequence of well drilling part 1Sequence of well drilling part 1
Sequence of well drilling part 1Elsayed Amer
 
Well completion and stimulation
Well completion and stimulation Well completion and stimulation
Well completion and stimulation kaleem ullah
 
3. sequances of drilling operations
3. sequances of drilling operations3. sequances of drilling operations
3. sequances of drilling operationsElsayed Amer
 
Drilling Engineering - Directional Drilling
Drilling Engineering - Directional DrillingDrilling Engineering - Directional Drilling
Drilling Engineering - Directional DrillingJames Craig
 
Sand Problem in Oil Wells
Sand Problem in Oil WellsSand Problem in Oil Wells
Sand Problem in Oil Wellsthe_duke7
 
Fundamentals of Petroleum Engineering Module 4
Fundamentals of Petroleum Engineering Module 4Fundamentals of Petroleum Engineering Module 4
Fundamentals of Petroleum Engineering Module 4Aijaz Ali Mooro
 
Fundamentals of Petroleum Engineering Module 5
Fundamentals of Petroleum Engineering Module 5Fundamentals of Petroleum Engineering Module 5
Fundamentals of Petroleum Engineering Module 5Aijaz Ali Mooro
 
Basic drilling engineering
Basic drilling engineeringBasic drilling engineering
Basic drilling engineeringSaad Raja
 
Drillstring & BHA Design
Drillstring & BHA DesignDrillstring & BHA Design
Drillstring & BHA DesignM.T.H Group
 
Directional drilling Introduction
Directional drilling IntroductionDirectional drilling Introduction
Directional drilling IntroductionGEx OliNesia
 
Drilling Problems.pdf
Drilling Problems.pdfDrilling Problems.pdf
Drilling Problems.pdfTinaMarey
 
Drilling Fluids Mud
Drilling Fluids MudDrilling Fluids Mud
Drilling Fluids MudM.T.H Group
 
Casing Design | Tubing | Well Control | Drilling | Gaurav Singh Rajput
Casing Design | Tubing | Well Control | Drilling | Gaurav Singh RajputCasing Design | Tubing | Well Control | Drilling | Gaurav Singh Rajput
Casing Design | Tubing | Well Control | Drilling | Gaurav Singh RajputGaurav Singh Rajput
 
Well control and blowout preventer
Well control  and blowout preventerWell control  and blowout preventer
Well control and blowout preventerShamim Akram
 
Dst (Drill Stem Test)
Dst (Drill Stem Test)Dst (Drill Stem Test)
Dst (Drill Stem Test)Mubarik Rao
 

What's hot (20)

Sequence of well drilling part 1
Sequence of well drilling part 1Sequence of well drilling part 1
Sequence of well drilling part 1
 
Well completion and stimulation
Well completion and stimulation Well completion and stimulation
Well completion and stimulation
 
Tubing string
Tubing stringTubing string
Tubing string
 
3. sequances of drilling operations
3. sequances of drilling operations3. sequances of drilling operations
3. sequances of drilling operations
 
Drilling Engineering - Directional Drilling
Drilling Engineering - Directional DrillingDrilling Engineering - Directional Drilling
Drilling Engineering - Directional Drilling
 
Sand Problem in Oil Wells
Sand Problem in Oil WellsSand Problem in Oil Wells
Sand Problem in Oil Wells
 
Fundamentals of Petroleum Engineering Module 4
Fundamentals of Petroleum Engineering Module 4Fundamentals of Petroleum Engineering Module 4
Fundamentals of Petroleum Engineering Module 4
 
Fundamentals of Petroleum Engineering Module 5
Fundamentals of Petroleum Engineering Module 5Fundamentals of Petroleum Engineering Module 5
Fundamentals of Petroleum Engineering Module 5
 
Rig types.
Rig types.Rig types.
Rig types.
 
Stuck pipe
Stuck pipeStuck pipe
Stuck pipe
 
Basic drilling engineering
Basic drilling engineeringBasic drilling engineering
Basic drilling engineering
 
Cementation
CementationCementation
Cementation
 
Drillstring & BHA Design
Drillstring & BHA DesignDrillstring & BHA Design
Drillstring & BHA Design
 
Directional drilling Introduction
Directional drilling IntroductionDirectional drilling Introduction
Directional drilling Introduction
 
Drilling Problems.pdf
Drilling Problems.pdfDrilling Problems.pdf
Drilling Problems.pdf
 
Drilling Fluids Mud
Drilling Fluids MudDrilling Fluids Mud
Drilling Fluids Mud
 
Well completion fundamentals
Well completion fundamentalsWell completion fundamentals
Well completion fundamentals
 
Casing Design | Tubing | Well Control | Drilling | Gaurav Singh Rajput
Casing Design | Tubing | Well Control | Drilling | Gaurav Singh RajputCasing Design | Tubing | Well Control | Drilling | Gaurav Singh Rajput
Casing Design | Tubing | Well Control | Drilling | Gaurav Singh Rajput
 
Well control and blowout preventer
Well control  and blowout preventerWell control  and blowout preventer
Well control and blowout preventer
 
Dst (Drill Stem Test)
Dst (Drill Stem Test)Dst (Drill Stem Test)
Dst (Drill Stem Test)
 

Viewers also liked

New Drilling Technology by Dipl.Ing., MBA Thorsten Weimann
New Drilling Technology by Dipl.Ing., MBA Thorsten WeimannNew Drilling Technology by Dipl.Ing., MBA Thorsten Weimann
New Drilling Technology by Dipl.Ing., MBA Thorsten WeimannGerd Tarand
 
Service Operator Surface Well Testing
Service Operator Surface Well TestingService Operator Surface Well Testing
Service Operator Surface Well TestingJason Situmorang
 
GreenRig From Comprehensive Power - Drilling and Production with Lower Fuel C...
GreenRig From Comprehensive Power - Drilling and Production with Lower Fuel C...GreenRig From Comprehensive Power - Drilling and Production with Lower Fuel C...
GreenRig From Comprehensive Power - Drilling and Production with Lower Fuel C...Jeff Sable
 
CS Unitec Woodboring Air Drills
CS Unitec Woodboring Air DrillsCS Unitec Woodboring Air Drills
CS Unitec Woodboring Air DrillsCS Unitec
 
Apresentação - Sonda de Perfuração (onshore)
Apresentação - Sonda de Perfuração (onshore)Apresentação - Sonda de Perfuração (onshore)
Apresentação - Sonda de Perfuração (onshore)Indepedent Freelancer
 
Apostila desenho mecanico i
Apostila   desenho mecanico iApostila   desenho mecanico i
Apostila desenho mecanico iRafael Mendes
 
أنواع آبراج الحفر
أنواع آبراج الحفرأنواع آبراج الحفر
أنواع آبراج الحفرMahmoud Abdelkader
 
Oil 101 - What is Midstream?
Oil 101 - What is Midstream?Oil 101 - What is Midstream?
Oil 101 - What is Midstream?EKT Interactive
 
محطات عزل الغاز حقل كركوك
محطات عزل الغاز  حقل كركوك محطات عزل الغاز  حقل كركوك
محطات عزل الغاز حقل كركوك balean gili
 
Oil 101 - Introduction to Supply and Trading
Oil 101 - Introduction to Supply and TradingOil 101 - Introduction to Supply and Trading
Oil 101 - Introduction to Supply and TradingEKT Interactive
 
Oil 101 - Introduction to Refining
Oil 101 - Introduction to RefiningOil 101 - Introduction to Refining
Oil 101 - Introduction to RefiningEKT Interactive
 
Oil 101 - What is Downstream?
Oil 101 - What is Downstream?Oil 101 - What is Downstream?
Oil 101 - What is Downstream?EKT Interactive
 
Oil 101 - Introduction to Production
Oil 101 - Introduction to ProductionOil 101 - Introduction to Production
Oil 101 - Introduction to ProductionEKT Interactive
 
تركيز النفط الخام
تركيز النفط الخام تركيز النفط الخام
تركيز النفط الخام balean gili
 

Viewers also liked (20)

New Drilling Technology by Dipl.Ing., MBA Thorsten Weimann
New Drilling Technology by Dipl.Ing., MBA Thorsten WeimannNew Drilling Technology by Dipl.Ing., MBA Thorsten Weimann
New Drilling Technology by Dipl.Ing., MBA Thorsten Weimann
 
Service Operator Surface Well Testing
Service Operator Surface Well TestingService Operator Surface Well Testing
Service Operator Surface Well Testing
 
GreenRig From Comprehensive Power - Drilling and Production with Lower Fuel C...
GreenRig From Comprehensive Power - Drilling and Production with Lower Fuel C...GreenRig From Comprehensive Power - Drilling and Production with Lower Fuel C...
GreenRig From Comprehensive Power - Drilling and Production with Lower Fuel C...
 
CS Unitec Woodboring Air Drills
CS Unitec Woodboring Air DrillsCS Unitec Woodboring Air Drills
CS Unitec Woodboring Air Drills
 
Apresentação - Sonda de Perfuração (onshore)
Apresentação - Sonda de Perfuração (onshore)Apresentação - Sonda de Perfuração (onshore)
Apresentação - Sonda de Perfuração (onshore)
 
Apostila desenho mecanico i
Apostila   desenho mecanico iApostila   desenho mecanico i
Apostila desenho mecanico i
 
أنواع آبراج الحفر
أنواع آبراج الحفرأنواع آبراج الحفر
أنواع آبراج الحفر
 
Apostila de brocas
Apostila de brocasApostila de brocas
Apostila de brocas
 
Oil and costs
Oil and costsOil and costs
Oil and costs
 
Gaz
GazGaz
Gaz
 
Apostila de brocas
Apostila de brocasApostila de brocas
Apostila de brocas
 
Oil 101 - What is Midstream?
Oil 101 - What is Midstream?Oil 101 - What is Midstream?
Oil 101 - What is Midstream?
 
محطات عزل الغاز حقل كركوك
محطات عزل الغاز  حقل كركوك محطات عزل الغاز  حقل كركوك
محطات عزل الغاز حقل كركوك
 
Oil 101 - Introduction to Supply and Trading
Oil 101 - Introduction to Supply and TradingOil 101 - Introduction to Supply and Trading
Oil 101 - Introduction to Supply and Trading
 
Casing Accessories , completion tools, liner hanger system
Casing Accessories , completion tools, liner hanger systemCasing Accessories , completion tools, liner hanger system
Casing Accessories , completion tools, liner hanger system
 
Oil 101 - Introduction to Refining
Oil 101 - Introduction to RefiningOil 101 - Introduction to Refining
Oil 101 - Introduction to Refining
 
Oil 101 - What is Downstream?
Oil 101 - What is Downstream?Oil 101 - What is Downstream?
Oil 101 - What is Downstream?
 
Oil 101 - Introduction to Production
Oil 101 - Introduction to ProductionOil 101 - Introduction to Production
Oil 101 - Introduction to Production
 
Al pitrol e
Al pitrol eAl pitrol e
Al pitrol e
 
تركيز النفط الخام
تركيز النفط الخام تركيز النفط الخام
تركيز النفط الخام
 

Similar to Drilling Preliminaries Steps

Wel Planing
Wel PlaningWel Planing
Wel Planingsaqib129
 
shaftab-170524171214.pdf
shaftab-170524171214.pdfshaftab-170524171214.pdf
shaftab-170524171214.pdfSaimHaq
 
01_Rig Components & Personel.pdf
01_Rig Components & Personel.pdf01_Rig Components & Personel.pdf
01_Rig Components & Personel.pdfDrilling Manual
 
Rock Drilling and Types of Rock Drilling
Rock Drilling and Types of Rock DrillingRock Drilling and Types of Rock Drilling
Rock Drilling and Types of Rock DrillingMOHAMMED SOHEL AHMED
 
well site geology for oil and gas sector.pptx
well site geology for oil and gas sector.pptxwell site geology for oil and gas sector.pptx
well site geology for oil and gas sector.pptxsyedmehdi99
 
Introduction to Advanced Construction Equipments
Introduction to Advanced Construction EquipmentsIntroduction to Advanced Construction Equipments
Introduction to Advanced Construction EquipmentsATUL DONGRE
 
Drilling Operations
Drilling OperationsDrilling Operations
Drilling OperationsTarek Saati
 
Drilling Operations of Ground Water Wells Up-Geologist Team Zagazig Univ 06-0...
Drilling Operations of Ground Water Wells Up-Geologist Team Zagazig Univ 06-0...Drilling Operations of Ground Water Wells Up-Geologist Team Zagazig Univ 06-0...
Drilling Operations of Ground Water Wells Up-Geologist Team Zagazig Univ 06-0...Mohamed _el_shora
 
Drilling methods
Drilling methodsDrilling methods
Drilling methodshudayu
 
Driven & Bored Piles
Driven & Bored PilesDriven & Bored Piles
Driven & Bored PilesAhmed Zanaty
 
LEC 15hsjsjjsjdjjdjdnnhdhdhdbdhdndd F C.ptx
LEC 15hsjsjjsjdjjdjdnnhdhdhdbdhdndd  F C.ptxLEC 15hsjsjjsjdjjdjdnnhdhdhdbdhdndd  F C.ptx
LEC 15hsjsjjsjdjjdjdnnhdhdhdbdhdndd F C.ptxkrishnarajgire71
 
Drilling and producing well
Drilling and  producing wellDrilling and  producing well
Drilling and producing wellRaja Rosenani
 

Similar to Drilling Preliminaries Steps (20)

Wel Planing
Wel PlaningWel Planing
Wel Planing
 
shaftab-170524171214.pdf
shaftab-170524171214.pdfshaftab-170524171214.pdf
shaftab-170524171214.pdf
 
01_Rig Components & Personel.pdf
01_Rig Components & Personel.pdf01_Rig Components & Personel.pdf
01_Rig Components & Personel.pdf
 
Shaft
Shaft Shaft
Shaft
 
Rock Drilling and Types of Rock Drilling
Rock Drilling and Types of Rock DrillingRock Drilling and Types of Rock Drilling
Rock Drilling and Types of Rock Drilling
 
Machineries and Maintenance Question Patterns for Mining students
Machineries and Maintenance Question Patterns for Mining studentsMachineries and Maintenance Question Patterns for Mining students
Machineries and Maintenance Question Patterns for Mining students
 
pile_foundation_1.ppt
pile_foundation_1.pptpile_foundation_1.ppt
pile_foundation_1.ppt
 
well site geology for oil and gas sector.pptx
well site geology for oil and gas sector.pptxwell site geology for oil and gas sector.pptx
well site geology for oil and gas sector.pptx
 
Introduction to Advanced Construction Equipments
Introduction to Advanced Construction EquipmentsIntroduction to Advanced Construction Equipments
Introduction to Advanced Construction Equipments
 
Drilling Operations
Drilling OperationsDrilling Operations
Drilling Operations
 
rig types and its components
rig types and its componentsrig types and its components
rig types and its components
 
Drilling engineering zaidi
Drilling engineering zaidiDrilling engineering zaidi
Drilling engineering zaidi
 
Drilling Operations of Ground Water Wells Up-Geologist Team Zagazig Univ 06-0...
Drilling Operations of Ground Water Wells Up-Geologist Team Zagazig Univ 06-0...Drilling Operations of Ground Water Wells Up-Geologist Team Zagazig Univ 06-0...
Drilling Operations of Ground Water Wells Up-Geologist Team Zagazig Univ 06-0...
 
Drilling methods
Drilling methodsDrilling methods
Drilling methods
 
Drilling methods
Drilling methodsDrilling methods
Drilling methods
 
Coring chapter 5
Coring   chapter 5Coring   chapter 5
Coring chapter 5
 
Driven & Bored Piles
Driven & Bored PilesDriven & Bored Piles
Driven & Bored Piles
 
LEC 15hsjsjjsjdjjdjdnnhdhdhdbdhdndd F C.ptx
LEC 15hsjsjjsjdjjdjdnnhdhdhdbdhdndd  F C.ptxLEC 15hsjsjjsjdjjdjdnnhdhdhdbdhdndd  F C.ptx
LEC 15hsjsjjsjdjjdjdnnhdhdhdbdhdndd F C.ptx
 
Cast in situ Pile
Cast in situ PileCast in situ Pile
Cast in situ Pile
 
Drilling and producing well
Drilling and  producing wellDrilling and  producing well
Drilling and producing well
 

More from Kartikeya Pandey

More from Kartikeya Pandey (20)

Water and sanitation
Water and sanitationWater and sanitation
Water and sanitation
 
Supplementary benefits
Supplementary benefitsSupplementary benefits
Supplementary benefits
 
Property tax
Property taxProperty tax
Property tax
 
Metros summary by Kartikeya Pandey
Metros summary by Kartikeya PandeyMetros summary by Kartikeya Pandey
Metros summary by Kartikeya Pandey
 
Marketing product placement strategies
Marketing product placement strategiesMarketing product placement strategies
Marketing product placement strategies
 
seven cs
seven csseven cs
seven cs
 
Indian ports (1)
Indian ports (1)Indian ports (1)
Indian ports (1)
 
Human resource planning ppt.
Human resource planning ppt.Human resource planning ppt.
Human resource planning ppt.
 
Gis
GisGis
Gis
 
Fire d project
Fire d projectFire d project
Fire d project
 
Alandur sewerage proj arun
Alandur sewerage proj   arunAlandur sewerage proj   arun
Alandur sewerage proj arun
 
24 x7 water in three states of karnataka
24 x7 water in three states of karnataka24 x7 water in three states of karnataka
24 x7 water in three states of karnataka
 
4
44
4
 
Land adjustment Land value capture
Land adjustment Land value captureLand adjustment Land value capture
Land adjustment Land value capture
 
Solid waste management practices in dehradun under jn nurm
Solid waste management practices in dehradun under jn nurmSolid waste management practices in dehradun under jn nurm
Solid waste management practices in dehradun under jn nurm
 
Infrastructure unbundling in south africa
Infrastructure unbundling in south africaInfrastructure unbundling in south africa
Infrastructure unbundling in south africa
 
Indian accounting standard (ind as) 27
Indian accounting standard (ind as) 27Indian accounting standard (ind as) 27
Indian accounting standard (ind as) 27
 
Hr presentation
Hr presentationHr presentation
Hr presentation
 
Going & seeing in construction
Going & seeing in constructionGoing & seeing in construction
Going & seeing in construction
 
Concrete technology
Concrete technologyConcrete technology
Concrete technology
 

Recently uploaded

2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis UsageNeil Kimberley
 
Non Text Magic Studio Magic Design for Presentations L&P.pptx
Non Text Magic Studio Magic Design for Presentations L&P.pptxNon Text Magic Studio Magic Design for Presentations L&P.pptx
Non Text Magic Studio Magic Design for Presentations L&P.pptxAbhayThakur200703
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024christinemoorman
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewasmakika9823
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfpollardmorgan
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Tina Ji
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdfOrient Homes
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Roomdivyansh0kumar0
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in managementchhavia330
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsApsara Of India
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 

Recently uploaded (20)

2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage
 
Non Text Magic Studio Magic Design for Presentations L&P.pptx
Non Text Magic Studio Magic Design for Presentations L&P.pptxNon Text Magic Studio Magic Design for Presentations L&P.pptx
Non Text Magic Studio Magic Design for Presentations L&P.pptx
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
 
KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdf
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in management
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 

Drilling Preliminaries Steps

  • 1. Drilling Preliminaries Kartikeya Pandey Prof Anil Kumar MBA IFM (HOD Power & Infrastructure 500021353 Management) Submitted by Submitted to
  • 2. Steps to Drill A Gas/Oil Well 1. Complete or obtain seismic, log, scouting information or other data. 2. Lease the land or obtain concession. 3. Calculate reserves or estimate from best data available.
  • 3. Steps to Drill A Gas/Oil Well 4. If reserve estimates show payout, proceed with well. 5. Obtain permits from conservation / national authority. 6. Prepare drilling and completion program.
  • 4. Steps to Drill a Well - cont’d 7. Ask for bids on footage, day work, or combination from selected drilling contractors based on drilling program. 8. If necessary, modify program to fit selected contractor equipment. 9. Construct road, location/platforms and other marine equipment necessary for access to site.
  • 5. Steps to Drill a Well - cont’d 10. Gather all personnel concerned for meeting prior to commencing drilling (pre-spud meeting). 11. If necessary, further modify program. 12. Drill well.
  • 6. Introduction When a suitable structure, sufficiently large, so as to give economically viable reserves of HCs) is discovered for the presence of HCs by geological, geochemical & geophysical methods, a location for drilling of an exploratory / wild cat well is decided.
  • 7. Classification of Wells Exploratory Well / WildCat Well: They are drilled purely for exploratory purposes i.e. for gathering information. The well is drilled to find and produce oil or gas in an unproven area, or to find a new reservoir in fields, or to extend a known reservoir.
  • 8. Classification of Wells Discovery Well: If the well does discover a new field, it is called the discovery well for that field.
  • 9. Classification of Wells Appraisal Well/ Delineation Well: After the discovery, the size of the field must be determined. Field size is determined by “step out” or “Delineation” or “Appraisal” well that are drilled to the sides of the discovery well.
  • 10. Classification of Wells Developmental Wells: Wells drilled in the known extent of the field are called Developmental Wells.
  • 11. Classification of Wells Infill Wells: Wells that are drilled in between producing wells in an established field to increase the production rate are called Infill wells.
  • 12. Classification of Wells Production Wells: They are drilled primarily for producing oil and gas, once the producing structure and characteristics are determined.
  • 13. The well is created by drilling a hole of 5 – 36 inches (127.0 – 914.4 mm) in diameter into the earth with a drilling rig that rotates a drill string with bit attached. • The cost of drilling is very great. On an offshore rig, it may cost $10,000 for each metre drilled. • A company incurs vast losses for every “dry hole” drilled. Drilling A Well
  • 14. A drilling rig is the machine which creates holes (usually called boreholes) in the ground. Drilling Rig
  • 15. Drilling rigs can be: • Small and portable, such as those used in mineral exploration drilling, water wells and environmental investigations. • Huge, capable of drilling through thousands of meters of the Earth's crust. Drilling Rig
  • 16. Drilling rigs can be mobile equipment mounted on trucks, or trailers, or more permanent land or marine-based structures (such as oil platforms, commonly called 'offshore oil rigs). The term "rig" therefore generally refers to the complex of equipment that is used to penetrate the surface of the Earth's crust.
  • 17. Primarily in onshore oil & gas fields, once a well has been drilled, the drilling rig is moved off of the well and a service rig ( a smaller rig) for completions is placed for well completion. This frees up the drilling rig to drill another hole and streamlines the operation.
  • 18. In early oil exploration, drilling rigs were semi-permanent in nature and the derricks were often built on site and left in place after the completion of the well.
  • 19. Cable Tool Drilling Cable Drilling is a pioneer method and the first oil wells in the United States were drilled with cable tools to a depth of 20 mts.
  • 20. Cable Tool Drilling An engine , originally a steam engine, causes a wooden beam to pivot up & down. The bit, is made up of solid steel rod about 4 ft. (1 & 1/3m) long with a chisel point on it. Drilling Rig
  • 22. Cable Tool Drilling ( Cont…..) As the walking beam pivots, it causes the bit to rise and fall. The bit pounds the well down by pulverizing the rock. Drilling Rig
  • 23. Cable Tool Drilling ( Cont…..) After drilling 3 - 8 ft., (1 – 2 ½ m), the bottom of the well becomes clogged with rock chips. The bit is raised and a bailer is lowered into the well to remove the rock chips and water. Drilling Rig
  • 24. Cable Tool Drilling ( Cont…..) After the bailer is raised and emptied, the bit is lowered into the well to pound deeper. Drilling Rig
  • 25. Cable Tool Drilling ( Cont…..) Heavy casing ( large diameter pipe) is run down the well to keep water from filling the well and to prevent the sides from caving in. Drilling Rig
  • 26. Cable Tool Drilling ( Cont…..) Cable tool drilling is very slow – 25ft. ( 7 ½ m) per day (average) and 60 ft. (20m) being very good. Drilling Rig
  • 27. Rotary Drilling Today, almost all well are drilled with rotary drilling rigs. The rotary drilling rig rotates a long length of steel pipe with a bit on the end of it to cut a hole called the well bore. Drilling Rig
  • 28. Rotary Drilling The rotary rig consists of four major systems. (1) Power System : Diesel Engine (2) Hoisting System : Derrick / Mast, Draw work (3) Rotating System : Swivel, Kelly, Rotary table, Drill string, Drill Pipe, Drill Collar, Bit etc. (4) Circulating system: Mud Tanks
  • 31.
  • 32. Derrick Crown Block Shale Shaker Mud tank Swivel Drill Line BOP Mud Pump Motor/ Power Source Drill Bit Kelly Rotary Table
  • 33. Crown Block:  A fixed, steel frame with steel wheels on a horizontal shaft. It is located at the top of a derrick or Mast.  Is an assembly of pulleys mounted on beams at the top of derrick
  • 35. Derrick: The derrick or Mast is the tower directly above the well that supports the crown block at the top & provides support for the drill pipe to be stacked vertically as it is pulled from the well. It is generally 40m in height strong enough to hold the weight of the drill as it goes deeper & deeper into the rock. The derrick can support a weight of about 50 tonnes or more.
  • 36. Kelly : The kelly is a square rod attached to swivel. The kelly turns all the pipe below it to drill the hole. To the lower end of the kelly, a 10 m pipe is screwed in.
  • 37. Kelly
  • 40. DrilPipe: The drillpipe (which, when joined together, forms the drillstring) consists of 30ft. (10m) sections of heavy steel pipe. The pipes are threaded so that they can interlock together. As the drill goes deeper, a new pipe is added to the end of the first pipe and so on.
  • 42. Swivel : The swivel allows the kelly to rotate freely.
  • 44. Rotary Table: The kelly along with the pipe & drilling bit is rotated by a rotor known as “Rotary Table”. It is a circular table in the derrick floor that is turned clockwise by the prime movers. If it were turned in the opposite direction, the drillpipe would unscrew.
  • 46. Drill stem: 3 main components are Kelly, Drillstring & the Bit. Drill string: It is made up of steel pipes called drill pipes, drill collars (below the drill pipes are thicker – walled, heavier, stronger pipes to put weight on the bottom of the drills string to drill straight down and prevent the drill pipe from kinking & breaking) and bit in the well.
  • 47. Drill string: It is made up of steel pipes called drill pipes, drill collars (below the drill pipes are thicker – walled, heavier, stronger pipes to put weight on the bottom of the drills string to drill straight down and prevent the drill pipe from kinking & breaking) and bit in the well.
  • 48. Drill Bit : It is located at the bottom end of the drill string. The drill bit is responsible for breaking up and dislodging rock, sediment, and anything else that may be encountered while drilling. There are dozens of different drill bit types, each designed for different subsurface drilling conditions:
  • 49. 1.Steel Tooth Rotary Bits are the most basic type of drill bit used today.
  • 50. 2. Insert Bits are steel tooth bits with tungsten carbide inserts.
  • 51. Disadvantages of Insert Bit • Inserts dig deeply into formation. Cones can hit the formation and transmit shock loads to bearings and damage bearings • Abrasive mud containing sands can erode cutters base and let them fall in the well • Much more expensive • Can not drill soft to soft-medium hard formations as fast as steel-tooth bits
  • 52. 3. Polycrystalline Diamond Compact Bits have polycrystalline diamond inserts attached to the carbide inserts found in Insert Bits.
  • 53. 4. Diamond Bits have industrial diamonds implanted in them, to drill through extremely hard rock formations. Diamond bits are forty to fifty times harder than traditional steel bits, and can thus be used to drill through extremely hard rock without dulling overly quickly.
  • 54. Drilling Mud: When the drilling goes on , a special type of drilling fluid known as mud is pumped down by a hose through the drilling pipe to keep the bit cool. (The mud flows just like ink flows out of a pen) A viscous mixture of clay (usually bentonite) and additives with either water or oil or an emulsion of water with droplets of oil or a synthetic organic fluid.
  • 55. Drilling Mud ( Cont…..) The mud squirts out of the drilling bit and flows back through the annular space between the outer side of the pipe and the drilled hole carrying with it chips of rocks that are cut.
  • 56. Drilling Mud ( Cont…..) Geologists work day and night to record the sequence in which the different types of rocks come out. After studying the rocks, the geologists prepare a map showing the vertical distribution of rocks underground.
  • 57. Drilling Mud ( Cont…..) From this map, it is possible to find out : (1) The type of rock (2) The depths at which different rock types occur (3) The thickness of the bed of each rock type. The geologists also note if the rocks give any sign of oil.
  • 58. 3) the mixture of drilling mud and drill cuttings are circulated up the annulusscreens 5) the drill cuttings are removed, and form a cuttings pile. This can be hauled off and 4) the mixture is circulated across screens at surface 1) Clean drilling mud is taken from the steel mud tanks and pumped down the inside of the drill pipe. 2) the mud is circulated through the drill bit into the annulus, lifting the cuttings removed by the drill bit. 6) Clean mud falls through the screens and is returned to the pits The Drilling Mud Cycle mud pump
  • 59. The drilling mud is circulated on a rotary drilling rig to : 1.Cool & lubricate the drillstem. 2. remove cuttings from the hole. 3. control subsurface pressures. 4. Seal permeable formations.
  • 60. Safety System Various safety devices are used at the wellhead to cope with dangerous situations that may occur during a drilling operations:
  • 61. Safety System Reservoirs penetrated by the drill may contain pressures higher than the mud weight can control and the well may show a tendency to erupt and blowout.
  • 62. Safety System  When oil is struck, the oil gushes out.  Sometimes the oil gushes out with such tremendous force that it becomes dangerous.  The “Blow – Out” can kill men and damage the oil rig.  To reduce the risk of oil gushing out, there is a strong cap in every well. The cap is used as a “BLOW OUT PREVENTER” or “BOP”.
  • 63. WELL COMPLETION Once a natural gas or oil is drilled , and it has been verified that commercially viable quantities of crudes are present, for extraction, the well must be “completed”. Completion is done to allow for the flow of crude out of the formation and up to the surface.
  • 64. WELL COMPLETION ( Cont…..) Completion includes strengthening the well hole with casing, evaluating the P & T of the formation and then installing the proper equipment to ensure an efficient flow of the crudes.
  • 65. WELL COMPLETION ( Cont…..) Completing a well consists of :  Installing the well casing  Completing the well  Installing the wellhead  Installing lifting equipment  Treating the formation.
  • 66. Well Casing Installing well casing is an important part of the drilling and completion process. Well casing consists of a series of metal tubes installed in the freshly drilled hole.
  • 67. Objectives of Casing: 1. Supports the walls of the wells. 2. Prevents caving tendencies of unconsolidated formation. 3. Prevents water from entering the oil and gas yielding strata from overlying or underlying formations.
  • 68. Gas & oil must be confined within the well casing so that they may not escape into overlying / underlying formation.
  • 69. If the hole is uncased, oil and gas could escape through the well into a permeable horizon having a lower pressure and thus, can be dissipated through them so that desired recovery can never be effected.
  • 70. In oil well drilling, the cost of casing is usually the greatest single item of expense and selection of pipe weight , size and planning and design of casing installation etc. are amongst the most important problems encountered in well drilling. WHY???
  • 71.  The casing required to be lowered in the well should be effectively serve the purpose.  It must be of sufficient strength, adequate to withstand the stresses to which it is subjected in the well.  It should be water tight and it should be made of material that resists corrosion or be protected against corrosion (particularly when it is in contact with saline ground water)
  • 72.  The material of which the casing is made should be hard & tough and rigid enough to resist abrasion and distortion by contact with the rock walls of the well or drilling tools.
  • 73. TYPES OF CASING Casing types involve the character of the material from which the tubes are made, the method of their manufacture, the design of the joints and especially the method of connecting one individual section to another.
  • 74. TYPES OF CASING  In recent years, economy and safety of operation at increased depths have necessitated still further changes and improvements in the casing designs.  Resulted in the use of alloy steels having tensile strength of 80.000 lbs / inch2 or more with further changes in thread and coupling designs.  There are four grades of seamless alloy steel casing in use.
  • 75. In most wells, the diameter of the well hole decreases the deeper it is drilled, leading to a type of conical shape that must be taken into account when installing casing.
  • 76. A well commonly has 3 or more concentric casing string. Shallow wells can have 2 or just 1 casing string. The largest diam. & shortest length string is on the outside. The smallest diam. & longest length string is on the inside. The outside string is cemented first and the inside string last.
  • 77. A well commonly has 3 or more concentric casing string. Shallow wells can have 2 or just 1 casing string. The largest diam. & shortest length string is on the outside. The smallest diam. & longest length string is on the inside. The outside string is cemented first and the inside string last.
  • 78. There are five different types of well casing: • Conductor Casing • Surface Casing • Intermediate Casing • Liner String • Production Casing
  • 79. Conductor Casing • Conductor casing is installed first, usually prior to the arrival of the drilling rig. • The hole for conductor casing is often drilled with a small auger drill, mounted on the back of a truck.
  • 80. Conductor Casing • Conductor pipe is the largest diam. Casing string :  Offshore : 30 – 42 inch. or 76 – 107 cm  Onshore: 16 inch. or 40 ½ cm • Conductor Casing is usually no more than 20 to 50 feet long.
  • 81. Conductor Casing • It is installed to prevent the top of the well from caving in & isolates any near surface & fresh water. • It serves as a route for the drilling mud coming from the well to the mud tanks.
  • 82. Surface Casing • Surface casing is the next type of casing to be installed after conductor casing. • It can be anywhere from a few hundred to 2,000 feet long, and is smaller in diameter than the conductor casing ( 13 ¼ inch or 35 cm.)
  • 83. Surface Casing • The primary purpose of surface casing is to prevent soft, near surface sediments from caving into the well. • It also protects fresh water reservoirs from further contaminating by drilling mud.
  • 84. Surface Casing • It also serves as a conduit for drilling mud returning to the surface. • It helps protect the drill hole from being damaged during drilling.
  • 85. Intermediate Casing • Intermediate casing is can be set to isolate problem zones in the well such as abnormal high pressure , lost circulation, or a salt layer. • It is typically 85/8inch ( 22 cm) .
  • 86. Production Casing • Production casing, alternatively called the 'oil string' or 'long string,’ is installed last and is the deepest section of casing in a well. • This is the casing that provides a conduit from the surface of the well to the petroleum-producing formation.
  • 87. Production Casing • The final string of casing is the “Production Casing” or “Oil String” that runs down to the producing zone. • It is typically 5 ½ inch (14cm) in diameter.
  • 88.
  • 89. Well casing is a very important part of the completed well. In addition to strengthening the well hole, it provides a conduit to allow hydrocarbons to be extracted without intermingling with other fluids and formations found underground.
  • 90. Instead of a casing string, a liner string can be set on the bottom of the well to save money. While a liner string is very similar to casing string in that it is made up of separate joints of tubing, the liner string is not run the complete length of the well. A liner string is hung in the well by a liner hanger, and then cemented into place.
  • 91. The section of the liner in the pay zone may be wire wrapped screen pipe with openings as small as (0.008 inch) or perforated pipe may be used with openings as large as ½ inch or above.
  • 92. The liner may extend up into the production casing only a short distance and be sealed to the production casing with a packer , or if desired, may be extended to the casing head on the surface, thus forming an inner producing string.
  • 93.
  • 94. Casing Programs • Sometimes the well is drilled in stages called a casing program. • A well is drilled to a certain depth, cased and cemented, and then the well is drilled to a deeper depth, cased and cemented again, and so on. • Each time the well is cased, a smaller diameter casing is used.
  • 95.
  • 97. After running in the casing string to the desired depth, it is cemented place. A cement slurry is then pumped down the casing and up around the outside of the casing in the annular space in the hole to the height desired and there the cement is allowed to set & harden to permanently fix the casing in place.
  • 98. The wall of hardened cement keeps the hole from caving, which might collapse the casing and to make the secure in the hole.
  • 99. After the casing is installed, tubing is inserted inside the casing, running from the opening well at the top to the formation at the bottom. The hydrocarbons that are extracted go up this tubing to the surface.
  • 100. Tubing
  • 101. Small diameter pipe called tubing is run into the well to just above the bottom to conduct the water, gas and oil ( produced fluids) to the surface.
  • 102. Tubing protects the casing from corrosion by the producing fluids. Since the casing is cemented in the wall, it is very difficult to repair the casing. The tubing string is suspended in the well, so, it can be pulled from the well to repair or replace it during a “work over”
  • 104. Well completion commonly refers to the process of finishing a well so that it is ready to produce oil & NG.
  • 105. There are a number of types of completion depending on the characteristics and location of the HC formation to be mined:  Open Hole Completion  Conventional Perforated Completion • Sand Exclusion Completion • Permanent Completion • Multiple Zone Completion • Drain hole Completion
  • 106. Open Hole Completion • Used in very competent formations. • Consists of simply running the casing directly down into the formation, leaving the end of the piping open. • There is no production casing over the oil or gas zone. • This is a very primitive way to complete a well.
  • 107.
  • 108. Conventional Perforated Completion • A modern well is completed with steel casing set over the oil zone. • It consists of production casing being run through the formation. • The sides of this casing are perforated with tiny holes along the sides facing the formation, which allows for the flow of HCs into the well hole.
  • 109. Conventional Perforated Completion • Perforation involves the use of specialized equipment designed to make tiny holes through the casing, & cementing lying in between the formation and the open hole.
  • 110. Conventional Perforated Completion • In the past, “bullet perforators” were used which were essentially small guns lowered into the well. • The guns were when fired from the surface, sent off small bullets that penetrated the casing and cement. • Today, “jet perforating” is preferred consisting of small, electrically ignited charges that are lowered into the well. When ignited, these charges poke tiny holes through the formation.
  • 111. Then a device called a "perforating gun" (A) is lowered into the hole at the depth where the oil or gas formation is found. This may be anywhere from several hundred feet down to tens of thousands of feet.
  • 112. After the gun is lined up properly, powerful shaped explosive charges are fired (B) from the control panel in the truck located up at ground level. These explosives blast a hole in the steel casing and cement, up to several feet out into the rock. Finally, the oil and gas fluids flow into the holes and up the well to the surface (C).
  • 113. This method of completion is much better than the old open-hole method shown in the first picture. The PG is able to control exactly where the perforations go. This helps to limit the amount of undesirable fluids, like salt water, entering the hole, and maximize the amount of hydrocarbons that can be extracted from the well.
  • 114. Sand Exclusion Completion • Sand exclusion completions are designed for production in an area that contains a large amount of loose sand. • This completion is designed to allow for the flow of natural gas and oil into the well, but at the same time, prevent sand from entering the well as the sand inside the well can cause many complications (erosion of casing & other equipment).
  • 115. Sand Exclusion Completion • The most common method of keeping sand out of the well hole are:  Screening or Filtering system. • This includes analyzing the sand and installing a screen or filter to keep the sand particles out. • This filter may either be a type of screen hung inside the casing, or adding a layer of specially sized gravel outside the casing to filter out the sand. Both of these types of sand barriers can be used in open hole & perforated completions
  • 116. Permanent Completion • In this, the completion and wellhead are assembled and installed only once. • The tubing is lowered to the desired depth before perforation and not removed during the life of the well. All other operations are carried out through tubing. • Completing a well in this way can lead to a significant cost savings.
  • 117. Multiple Zone Completion • In this practice, the HCs from two or more formations may be produced simultaneously, without mixing with each other. • eg. A well may be drilled that passes through a number of formations on its way, it may be efficient in a horizontal well to add multiple completions to drain the formation most effectively.
  • 118. Multiple Zone Completion • Although it is common to separate multiple completions so that the fluids from the different formations do not intermingle. • If the different formations being drilled are close enough in nature to allow fluids to intermingle in the well hole and it is necessary to separate different completions, hard rubber “packing” are used .
  • 119. Drain hole Completion • It is a form of horizontal or slant drilling. • It consists of drilling out horizontally into the formations from a vertical well, essentially providing a “drain” for the HCs to run down into the well.
  • 121. The well head consists of equipments on the surface that:  supports the various pipe strings  seals off the well to prevent leaking of oil or NG out of the well.  controls the flow rates of reservoir fluids.
  • 122. • Each string of casing usually hangs from a casing head. • The casing heads consists of heavy steel fitting at the surface. • It support the entire length of casing that is run all the way down the well. • “Metal and rubber seals” in the casing head prevent fluids from moving within the wellhead or escaping to the atmosphere.
  • 123. • Each casing head also has a place for a pressure gauge to warn of leaks. • This typically contains a gripping mechanism that ensures a tight seal between the head and the casing itself.
  • 124. • “The Tubing head” is much like the casing head. • It provides a seal between the tubing , which is run inside the casing. • It provides connections at the surface, which allow the flow of fluids out of the well to be controlled. • The tubing head stacks above the uppermost casing head.
  • 125. • “The Christmas Tree” fits atop the casing & tubing heads. • It contains tubes and valves that serve to control the flow of HCs and other fluids out of the well. • It commonly contains many branches and is shaped somewhat like a tree, thus its name, Christmas Tree . • This is the most visible part of a producing well and allows for surface monitoring & regulation of the HC production from producing well.
  • 126. “The Christmas Tree” or "tree", is not not "wellhead" as sometimes incorrectly referred to. • Note that a tree and wellhead are separate pieces of equipment not to be mistaken as the same piece. • A wellhead must be present in order to utilize a Christmas tree and a wellhead is used without a Christmas tree during drilling operations etc.,
  • 127.
  • 128. Lifting and Well Treatment
  • 129. Once the well is completed, it begins to produce. HCs existing in pressurized formations will naturally rise up through the well to the surface. This is most commonly the case with natural gas and light crude. Since natural gas is lighter than air, once a conduit to the surface is opened, the pressurized gas will rise to the surface. Thus, once the CT is installed, the NG will flow to the surface on its own
  • 130. When a well is first drilled, the formation is under pressure and produces O&G at a very rate. However, as more & more crude is extracted from the formation, the production rate of the well is decreased. This is known as the “decline rate”. During this time, application of certain techniques including “Lifting Equipment” & “Well Stimulation” can increase the production rate of a well.
  • 131. Lifting equipment consists of a variety of specialized equipment that are used to help “lift” petroleum out of a formation . This is most commonly used to extract oil from a formation. When oil is found as a viscous liquid, it becomes difficult to extract it from underground.
  • 132. Various types of lifting equipment are available, but the most common lifting method is known as “Rod Pumping”. Rod pumping is powered by a surface pump that moves a cable and a rod up and down in the well, providing the lifting pressure required in the well, providing the lifting pressure required to bring the oil to the surface.
  • 134. Well Treatment or Stimulation is another method of ensuring the efficient flow of HCs out of a formation. Essentially, this type of well stimulation consists of injecting stimulation consists of injecting acid, water or gases into the well to open up the formation and allow the crude to flow through the formation more easily.
  • 135. “Acidizing” a well consists of injecting acid (usually HCl acid) into the well. In Limestone or Carbonate formations, the acid dissolves portions of the rock in the formation, opening up existing spaces to allow for the flow of petroleum.
  • 136. “Fracturing” consists of injecting a fluid into the well, the pressure of which “cracks” or opens up fractures already present in the formation. In addition to the fluid being injected, “propping agents” are also used. These propping agents can consists of sand, glass beads, silica sand etc. and serve to prop open the newly widened fissures in the formation.
  • 137. “Hydraulic Fracturing” involves the injection of water into the formation, while CO2 fracturing uses gaseous . Fracturing, Acidizing and Lifting Equipment may all be used on the same well to increase permeability. These techniques are mostly used in oil wells, but have also been used to increase the extraction rate of gas wells.

Editor's Notes

  1. s
  2. s
  3. s
  4. s
  5. s
  6. s
  7. s
  8. s
  9. s
  10. s
  11. s
  12. s
  13. s
  14. s
  15. s
  16. s
  17. s
  18. s
  19. s
  20. s
  21. s
  22. s
  23. s
  24. s
  25. s
  26. s
  27. s
  28. s
  29. s
  30. s
  31. s
  32. s
  33. s
  34. s
  35. s
  36. s
  37. s
  38. s
  39. s
  40. s
  41. s
  42. s
  43. s
  44. s
  45. s
  46. s
  47. s
  48. s
  49. s
  50. s
  51. s
  52. s
  53. s
  54. s
  55. s
  56. s
  57. s
  58. s
  59. s
  60. s
  61. s
  62. s
  63. s
  64. s
  65. s
  66. s
  67. s
  68. S or o
  69. S or o
  70. S or o
  71. S or o
  72. S or o
  73. S or o
  74. S or o
  75. S or o
  76. S or o