SlideShare a Scribd company logo
1 of 31
CASING DESIGN
Attention!!
➢ Please note that this presentation is for your understanding the process of
designing casing.
➢ There are any designing updated methods and tools for casing design.
➢ Operators/Companies have their own design methodologies , safety factors
that may defer from this presentation.
➢ There have been many development in casing manufacturing technologies
and their pressure ratings and specs may be superior.
➢ Casing manufacturers provide their own casing tables that may differ due to
material specs and manufacturing technology.
Thank you.
Casing
1. Prevent hole from caving
2. Prevent contamination of fresh water sands
3. Prevent water migration to producing formation
4. Confine production to the wellbore
5. Control pressures during drilling
6. Environment for subsurface equipment in producing wells
7. Drilling to total depth (TD)
Casing
Cement
Casing Functions
Drive/Conductor pipe
Provides a mud return path
Prevents erosion of ground below rig
Supports the weight of subsequent casing strings
Isolates very weak formations
Surface casing
– Means of installing WH/BOP
– Strong casing seat (close in a well -kick case).
– Protection of fresh water sands
– Provides wellbore stabilization
– WH: Wellhead
– BOP: Blow Out Preventors
Surface Casing
1. offshore 150’-300’
( BML: below mudline).
2. Conductor string. 100’ - 1,600’
(BSL; Below Sea Level)
3. Surface pipe. 2,000’ - 4,000’
(BSL)
Diameter Example
16”-60” 30”
16”-48” 20”
8 5/8”-20” 13 3/8”
Intermediate/Contingency/ production/Tubing Strings
4. Intermediate String/Line
5. Contingency string/Liner(s)
6. Production String/Liner
7. Tubing String(s)
• Contingency String: Run if drilling
conditions require (HPHT).
• String/Liner: Run as either full casing
string or liner depending on well design.
• Tubing string: Run for well completion( if
required)
7 5/8”-16” 9 5/8”
Diameter Example
9 5/8”-11”. 105/8”
4 1/2”-9 5/8” 7”
2 1/8”- 5”. 2 3/8”
Well Configuration (Example)
Drive pipe
Conductor string
Surface pipe
IntermediateString
Production Liner
Hole Size
30”
20”
13 3/8
9 5/8
7
Pipe Size
36”
26”
17 1/2
12 1/4
8 3/4
Well Configuration (Example)
Structural casing
Conductor string
Contingency String
(Optional)
Surface pipe
Intermediate String
Production Liner
Structural Pipe/conductor pipe( optional)
250’
1,000’
4,000’
SL
Intermediate or protective casing/Liner
– Compete well program to TD/abnormally pressured zone
– Isolation of potentially troublesome formations/zones
– Withstandmud weights to next Csg. seat/TD
Contingency Csg String/Liner
- Run as required as per hazardous drilling conditions (HPHT, Salt/Coal
etc)
➢ Production casing/Liner
– Zonal isolation
o Migration of water to producing zones
o Isolates production zones
– Confines production to wellbore
– Install subsurface completion equipment
➢ Production casing/Liner
– Zonal isolation
o Migration of water to producing zones
o Isolates production zones
– Confines production to wellbore
– Install subsurface completion equipment
Liners Types
– Drilling liners
• Same as Intermediate or protective casing
– Production liners
• Same as production casing
– Tieback liners
• Tie back drilling or production liner to the surface.
• Converts liner to full string of casing
Casing Specs
1. Casing Outside Diameter(OD); (e.g. 9 5/8”)
2. Casing Wall Thickness (T); (e.g. 1/2”)
3. Casing Material Grade, (e.g. N-80)
4. Threads and Couplings (TLC) Type, (e.g. API LCSG)
5. Length of each joint (RANGE), (e.g. Range 3)
6. Nominal weight (Avg. wt/ft incl. coupling weight), (e.g. 47 lb./ft)
s
e
Grade/yield/Tensile
Casing Joints Lengths & Threads
Casing Joint Length:
RANGE 1 16-25 ft
RANGE 2 25-34 ft
RANGE 3 > 34 ft.
Coupling Thread:
API round threads - short ( CSG)
API round thread - long (LCSG )
Buttress (BCSG)
Extreme line (XCSG )
Xtreme Line
Vam
Etc.
RecommendedAPI Casing Design Factors
Collapse 1.125
Tension 1.8
Burst 1.1
Required Prrssure
10,000 psi
100,000 lbf
10,000 psi
Design Pressure
11,250 psi
180,000 lbf
11,000 psi
API Design Factor
(Operators may set their own Safety Factors)
API Recommendations
Burst
➢ Design for maximum pressure on the inside of the casing.
o Worst case scenario: Empty casing
o No external pressure.
➢ Design Pressure:- Formation pressure at TD
Collapse
➢ Worst case scenario:-,
o No pressure inside the casing,
o Maximum mud weight at casing depth.
➢ Reduction of collapse rating due to weight of casing/liner hanging below.
Tension
➢ worst case:
o No buoyancy effect.
o Weight of casing string.
Normal Pore Pressure Abnormal Pore Pressure
0.433 - 0.465 psi/ft gp > normal
Normal
Abnormal
Design Pressure (Formation Pressure)
Burst: Reservoir pressure along the wellbore.
Collapse: Hydrostatic pressure (increases with depth)
Tension: Tensile stress *weight of string at top)
STRESS
Tension
Burst
Collapse
Collapse
Tension
Depth
Casing Design-Burst
Example
Design a 7” Csg. String to 10,000 ft.
Pore pressure gradient = 0.5 psi/ft
Design factor, Ni=1.1
Burst Design only.
Internal Yield Pressure for pipe
 Internal Yield Pressure for couplings
 Internal pressure leak resistance
Formation pressure:-
psi
000
,
5
ft
000
,
10
*
ft
psi
5
.
0
pres =
=
Required pipe internal yield:-
psi
500
,
5
1
.
1
*
000
,
5
N
*
p
p i
res
i =
=
=
Ni = API Design BURST Factor= 1.1
From Casing Tables:-
7”, J-55, 26 lb./ft : BURST Pressure= 4,980 psi
7”, N-80, 23 lb./ft : BURST Pressure= 6,340 psi
7”, N-80, 26 lb./ft. : BURST Pressure= 7,249 psi
Choose N-80 Csg., 23lb/ft > 5500. Psi
Collapse Pressure


















−
















−
=
P
A
2
/
1
2
P
A
P
PA
Y
S
5
.
0
Y
S
75
.
0
1
Y
Y
YPA = yield strength of axial stress equivalentgrade, psi
YP = minimum yield strength of pipe, psi
SA = Axial stress, psi (tension is positive)
SA
SA
Collapse Example
P
p
A
2
p
A
PA Y
Y
S
5
.
0
Y
S
75
.
0
1
Y


















−








−
=
( )
psi
Area
F
S A
A 820
,
24
012
.
5
5
.
5
4
000
,
100
2
2
=
−
=
=

Axial tension reduces collapse pressure:
psi
216
,
38
000
,
55
000
,
55
820
,
24
5
.
0
000
,
55
820
,
24
75
.
0
1
Y
2
PA
=














−






−
=
Designing 9 5/8”Casing
Design: 9 5/8-in Casing.
• Setting Depth= 8,000’
• Mud Weight 12.5 ppg
• Formation pore pressure - 6,000 psi.
• Available Casing :- N-80, all weights.
• API design factors.
• Combination Casing String
• Design for “worst conditions.”
API design Factors:
• Tension and Joint Strength: NT = 1.8
• Collapse (from external pressure): Nc= 1.125
• Burst (from internal pressure): Ni = 1.1
Notes:-
1.To design a string of 100,000 lbf, select pipe with Joint strength of 100,000 * 1.8 = 180,000 lbf.
2.Casing tables provide joint strength values with no safety factors.
3.Always check the connection strength when designing casing for tension.
4.Casing tables provide connection strength values with no safety factors.
psi
600
,
6
P
1
.
1
*
psi
000
,
6
Factor
Design
*
pressure
pore
P
B
B
=
=
=
severe
less
are
ts
requiremen
collapse
the
hole
the
up
Further
.
bottom
the
at
d
'
req
psi
850
,
5
P
125
.
1
*
000
,
8
*
5
.
12
*
052
.
0
factor
design
*
depth
*
weight
mud
*
052
.
0
P
c
c

=
=
=
Design Burst Pressure: 6,600 psi
Design Collapse Pressure: 5,850 psi
Casing Tables:-
N-80 53.5 Lb./ft Burst = 7930 Psi
Collapse = 6620 Psi
PlainArea = 15.547 Sq in.
Design Burst: 6,600 psi
Design Collapse: 5,850 psi
N-80 53.5 Lb./ft satisfy collapse requirements.
N-80 47 #/ft
Can be run to depth:
psi
231
,
4
125
.
1
760
,
4
factor
design
pipe
of
pressure
Collapse
Pc =
=
=
ft
509
,
6
5
.
12
*
052
.
0
231
,
4
5
.
12
*
052
.
0
P
h
h
*
5
.
12
*
052
.
0
P
c
1
1
c
=
=
=

=
(8,000 - 6,509) = 1,491’ of 53.5 #/ft
The weight of this pipe will reduce the collapse resistance of the 47.0
#/ft pipe!
Weight, W1 = 53.5 #/ft * 1,491 ft = 79,769 lbf
Axial stress in 47 #/ft pipe
psi
877
,
5
in
13.572
lbf
769
,
79
area
end
weight
S
of 2
1 =
=
=
API tables:- stress will reduce the collapse resistance from 4,760 to
somewhere between 4,680 psi (with 5,000 psi stress) and 4,600 psi
(with 10,000 psi stress)
( )
2
1
1
2
1
1
c1
P P
P
S
S
S
S
P −








−
−
−
=
Interpolation between these values shows that the collapse resistance at 5,877 psi
axial stress is:
psi
148
,
4
125
.
1
666
,
4
P
psi
666
,
4
)
600
,
4
680
,
4
(
*
)
000
,
5
000
,
10
(
)
000
,
5
877
,
5
(
680
,
4
P
cc1
1
c
=
=
=
−
−
−
−
=
With the design factor,
( )
2
1
1
2
1
1
c1
P P
P
S
S
S
S
P −








−
−
−
=
ft
382
,
6
5
.
12
*
052
.
0
148
,
4
h2 =
=
Which differs considerably from
the initial depth of 6,509 ft, so a
second iteration is required.
Run 47 #/ft pipe to 6,382 ft.
psi
378
,
6
in
572
.
13
lbf
563
,
86
S
lbf
563
,
86
5
.
53
*
)
382
,
6
000
,
8
(
W
2
2
2
=
=
=
−
=
( )








−








−
−
−
= 2
1
1
2
1
1
c1
D.F.
1
P P
P
S
S
S
S
P
( ) psi
pcc 140
,
4
600
,
4
680
,
4
*
5000
5000
378
,
6
680
,
4
125
.
1
1
2 =












−
−
−
=
ft
369
,
6
5
.
12
*
052
.
0
140
,
4
h3 =
=
Interpolating
Pressure at depth of:
13 ft short of 6382Ft.
psi
429
,
6
572
.
13
259
,
87
S
lbf
259
,
87
5
.
53
*
)
369
,
6
000
,
8
(
W
'
369
,
6
h
3
3
3
=
=
=
−
=
=
Pcc3 = ?
2
3
140
,
4
)
600
,
4
680
,
4
(
*
000
,
5
000
,
5
429
,
6
680
,
4
125
.
1
1
cc
cc
P
psi
P
thus
=
=






−
−
−
=
Run 47 #/ft N-80 to 6,369 ft- Surface.
53.5 #/ft: 6,369 -8,000 ft.
43.5 #/ft pipe?: Do not meet burst requirements.
Tension Check
Weight on casing top joint :-
Design factor of 1.8 for tension, a pipe strength of
weight
actual
602
,
386
)
/
#
5
.
53
*
631
,
1
(
)
/
#
0
.
47
*
369
,
6
(
lbs
ft
ft
ft
ft
=
+
required
is
lbf
080
,
695
602
,
386
*
8
.
1 =
surface
to
OK
is
ft
/
#
0
.
47

Casing Tables:-Yield strength of 1,086,000 lbf for pipe body
and a joint strength of 905,000 lbf for LT & C.

More Related Content

What's hot

Wellhead and christmas tree components, functions and more
Wellhead and christmas tree components, functions and moreWellhead and christmas tree components, functions and more
Wellhead and christmas tree components, functions and moreMohamed Abdelshafy Abozeima
 
Well completion and stimulation
Well completion and stimulation Well completion and stimulation
Well completion and stimulation kaleem ullah
 
Coiled Tubing Conveyed Perforations
Coiled Tubing Conveyed PerforationsCoiled Tubing Conveyed Perforations
Coiled Tubing Conveyed PerforationsKamel Elsayed
 
Skin Factor and Formation Damage
Skin Factor and Formation DamageSkin Factor and Formation Damage
Skin Factor and Formation DamageNouh Almandhari
 
Side sliding door ssd
Side sliding door ssdSide sliding door ssd
Side sliding door ssdElsayed Amer
 
Casing Seat depth and Basic casing design lecture 4.pdf
Casing Seat depth and Basic casing design  lecture 4.pdfCasing Seat depth and Basic casing design  lecture 4.pdf
Casing Seat depth and Basic casing design lecture 4.pdfssuserfec9d8
 
140717 artificial lift
140717 artificial lift140717 artificial lift
140717 artificial liftAli Okasha
 
Q913 re1 w3 lec 11
Q913 re1 w3 lec 11Q913 re1 w3 lec 11
Q913 re1 w3 lec 11AFATous
 
Q922+de2+l07 v1
Q922+de2+l07 v1Q922+de2+l07 v1
Q922+de2+l07 v1AFATous
 
Drillstring & BHA Design
Drillstring & BHA DesignDrillstring & BHA Design
Drillstring & BHA DesignM.T.H Group
 
To Study Well Design Aspects in HPHT Environment
To  Study Well Design Aspects in HPHT EnvironmentTo  Study Well Design Aspects in HPHT Environment
To Study Well Design Aspects in HPHT EnvironmentNikhil Barshettiwar
 
reservoir engineering
reservoir engineeringreservoir engineering
reservoir engineeringbehnamproeng
 
Presentation 6 casing design
Presentation 6 casing designPresentation 6 casing design
Presentation 6 casing designAli Trichelli
 
One day gas lift system course
One day gas lift system course One day gas lift system course
One day gas lift system course Giuseppe Moricca
 
Drilling Engineering - Casing Design
Drilling Engineering - Casing DesignDrilling Engineering - Casing Design
Drilling Engineering - Casing DesignJames Craig
 
Well Completion Design.pdf
Well Completion Design.pdfWell Completion Design.pdf
Well Completion Design.pdfmmody4
 
Basic Well Control
Basic Well ControlBasic Well Control
Basic Well ControlM.T.H Group
 

What's hot (20)

Wellhead and christmas tree components, functions and more
Wellhead and christmas tree components, functions and moreWellhead and christmas tree components, functions and more
Wellhead and christmas tree components, functions and more
 
Well completion and stimulation
Well completion and stimulation Well completion and stimulation
Well completion and stimulation
 
Coiled Tubing Conveyed Perforations
Coiled Tubing Conveyed PerforationsCoiled Tubing Conveyed Perforations
Coiled Tubing Conveyed Perforations
 
Skin Factor and Formation Damage
Skin Factor and Formation DamageSkin Factor and Formation Damage
Skin Factor and Formation Damage
 
Side sliding door ssd
Side sliding door ssdSide sliding door ssd
Side sliding door ssd
 
Casing Seat depth and Basic casing design lecture 4.pdf
Casing Seat depth and Basic casing design  lecture 4.pdfCasing Seat depth and Basic casing design  lecture 4.pdf
Casing Seat depth and Basic casing design lecture 4.pdf
 
140717 artificial lift
140717 artificial lift140717 artificial lift
140717 artificial lift
 
Q913 re1 w3 lec 11
Q913 re1 w3 lec 11Q913 re1 w3 lec 11
Q913 re1 w3 lec 11
 
Q922+de2+l07 v1
Q922+de2+l07 v1Q922+de2+l07 v1
Q922+de2+l07 v1
 
well control (1)
 well control (1) well control (1)
well control (1)
 
Well completion fundamentals
Well completion fundamentalsWell completion fundamentals
Well completion fundamentals
 
Drillstring & BHA Design
Drillstring & BHA DesignDrillstring & BHA Design
Drillstring & BHA Design
 
To Study Well Design Aspects in HPHT Environment
To  Study Well Design Aspects in HPHT EnvironmentTo  Study Well Design Aspects in HPHT Environment
To Study Well Design Aspects in HPHT Environment
 
reservoir engineering
reservoir engineeringreservoir engineering
reservoir engineering
 
Presentation 6 casing design
Presentation 6 casing designPresentation 6 casing design
Presentation 6 casing design
 
Casing design
Casing designCasing design
Casing design
 
One day gas lift system course
One day gas lift system course One day gas lift system course
One day gas lift system course
 
Drilling Engineering - Casing Design
Drilling Engineering - Casing DesignDrilling Engineering - Casing Design
Drilling Engineering - Casing Design
 
Well Completion Design.pdf
Well Completion Design.pdfWell Completion Design.pdf
Well Completion Design.pdf
 
Basic Well Control
Basic Well ControlBasic Well Control
Basic Well Control
 

Similar to Casing Design | Tubing | Well Control | Drilling | Gaurav Singh Rajput

Casing Design 1.ppt
Casing Design 1.pptCasing Design 1.ppt
Casing Design 1.pptYibingYu3
 
FL AWWA Steel Pipelines_0.pdf
FL AWWA Steel Pipelines_0.pdfFL AWWA Steel Pipelines_0.pdf
FL AWWA Steel Pipelines_0.pdfad_gordon
 
Q922+de2+l06 v1
Q922+de2+l06 v1Q922+de2+l06 v1
Q922+de2+l06 v1AFATous
 
production casing design considerations
production casing design considerationsproduction casing design considerations
production casing design considerationskillergog
 
Lecture 8_MDPE_Design of Nozzles & Flange.pdf
Lecture 8_MDPE_Design of Nozzles & Flange.pdfLecture 8_MDPE_Design of Nozzles & Flange.pdf
Lecture 8_MDPE_Design of Nozzles & Flange.pdfPatelDhruvil20
 
An introduction to pressure vessels
An introduction to pressure vesselsAn introduction to pressure vessels
An introduction to pressure vesselsRajendra Prajapati
 
FIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPT
FIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPTFIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPT
FIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPTMUHAMMAD NOMAN KHAN
 
Stiffening Ring Design on PV Elite for External Pressure Acting on Thin Walle...
Stiffening Ring Design on PV Elite for External Pressure Acting on Thin Walle...Stiffening Ring Design on PV Elite for External Pressure Acting on Thin Walle...
Stiffening Ring Design on PV Elite for External Pressure Acting on Thin Walle...IRJET Journal
 
Lowerin Laying & Jointing of Pipelie.pptx
Lowerin Laying & Jointing of Pipelie.pptxLowerin Laying & Jointing of Pipelie.pptx
Lowerin Laying & Jointing of Pipelie.pptxBharat Somani
 

Similar to Casing Design | Tubing | Well Control | Drilling | Gaurav Singh Rajput (20)

Casing_Design(1).ppt
Casing_Design(1).pptCasing_Design(1).ppt
Casing_Design(1).ppt
 
3440551.ppt
3440551.ppt3440551.ppt
3440551.ppt
 
EBSE + ES3 Commercial Presentation
EBSE + ES3 Commercial PresentationEBSE + ES3 Commercial Presentation
EBSE + ES3 Commercial Presentation
 
Casing Design 1.ppt
Casing Design 1.pptCasing Design 1.ppt
Casing Design 1.ppt
 
FL AWWA Steel Pipelines_0.pdf
FL AWWA Steel Pipelines_0.pdfFL AWWA Steel Pipelines_0.pdf
FL AWWA Steel Pipelines_0.pdf
 
Field Services: Problem Resolution
Field Services: Problem ResolutionField Services: Problem Resolution
Field Services: Problem Resolution
 
Pipe Support Field Examples & Case Studies
Pipe Support Field Examples & Case StudiesPipe Support Field Examples & Case Studies
Pipe Support Field Examples & Case Studies
 
Pipe Support & EJ Field Examples & Case Studies
Pipe Support & EJ Field Examples & Case StudiesPipe Support & EJ Field Examples & Case Studies
Pipe Support & EJ Field Examples & Case Studies
 
Q922+de2+l06 v1
Q922+de2+l06 v1Q922+de2+l06 v1
Q922+de2+l06 v1
 
production casing design considerations
production casing design considerationsproduction casing design considerations
production casing design considerations
 
Lecture 8_MDPE_Design of Nozzles & Flange.pdf
Lecture 8_MDPE_Design of Nozzles & Flange.pdfLecture 8_MDPE_Design of Nozzles & Flange.pdf
Lecture 8_MDPE_Design of Nozzles & Flange.pdf
 
Product of the Week Showcase - May
Product of the Week Showcase - MayProduct of the Week Showcase - May
Product of the Week Showcase - May
 
Field Service: Problem Resolution - Feb. 2010
Field Service: Problem Resolution - Feb. 2010Field Service: Problem Resolution - Feb. 2010
Field Service: Problem Resolution - Feb. 2010
 
An introduction to pressure vessels
An introduction to pressure vesselsAn introduction to pressure vessels
An introduction to pressure vessels
 
FIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPT
FIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPTFIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPT
FIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPT
 
Stiffening Ring Design on PV Elite for External Pressure Acting on Thin Walle...
Stiffening Ring Design on PV Elite for External Pressure Acting on Thin Walle...Stiffening Ring Design on PV Elite for External Pressure Acting on Thin Walle...
Stiffening Ring Design on PV Elite for External Pressure Acting on Thin Walle...
 
pv_rules.pdf
pv_rules.pdfpv_rules.pdf
pv_rules.pdf
 
pv_rules.pdf
pv_rules.pdfpv_rules.pdf
pv_rules.pdf
 
Lowerin Laying & Jointing of Pipelie.pptx
Lowerin Laying & Jointing of Pipelie.pptxLowerin Laying & Jointing of Pipelie.pptx
Lowerin Laying & Jointing of Pipelie.pptx
 
Equipment question bank
Equipment question bankEquipment question bank
Equipment question bank
 

More from Gaurav Singh Rajput

Site Emergency Response | Gaurav Singh Rajput
Site Emergency Response | Gaurav Singh RajputSite Emergency Response | Gaurav Singh Rajput
Site Emergency Response | Gaurav Singh RajputGaurav Singh Rajput
 
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh Rajput
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh RajputQuantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh Rajput
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh RajputGaurav Singh Rajput
 
Basic of Instrumentation and Control | Gaurav Singh Rajput
Basic of Instrumentation and Control | Gaurav Singh RajputBasic of Instrumentation and Control | Gaurav Singh Rajput
Basic of Instrumentation and Control | Gaurav Singh RajputGaurav Singh Rajput
 
Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...
Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...
Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...Gaurav Singh Rajput
 
Fire Protection System | Gaurav Singh Rajput
Fire Protection System | Gaurav Singh RajputFire Protection System | Gaurav Singh Rajput
Fire Protection System | Gaurav Singh RajputGaurav Singh Rajput
 
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh Rajput
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh RajputBasic Instrumentation Symbols | P&ID | PFD | Gaurav Singh Rajput
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh RajputGaurav Singh Rajput
 
Hzard Communication | Gaurav Singh Rajput
Hzard Communication | Gaurav Singh RajputHzard Communication | Gaurav Singh Rajput
Hzard Communication | Gaurav Singh RajputGaurav Singh Rajput
 
Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput Gaurav Singh Rajput
 
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh RajputInspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh RajputGaurav Singh Rajput
 
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh Rajput
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh RajputBasic LNG Training | Liquefied Natural Gas | Gaurav Singh Rajput
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh RajputGaurav Singh Rajput
 
Noise Analysis | Gaurav Singh Rajput
Noise Analysis | Gaurav Singh Rajput Noise Analysis | Gaurav Singh Rajput
Noise Analysis | Gaurav Singh Rajput Gaurav Singh Rajput
 
BBS - Behaviour Based Safety | Gaurav Singh Rajput
BBS - Behaviour Based Safety | Gaurav Singh RajputBBS - Behaviour Based Safety | Gaurav Singh Rajput
BBS - Behaviour Based Safety | Gaurav Singh RajputGaurav Singh Rajput
 
HAZID | Hazard Indentification | Gaurav Singh Rajput
HAZID | Hazard Indentification | Gaurav Singh RajputHAZID | Hazard Indentification | Gaurav Singh Rajput
HAZID | Hazard Indentification | Gaurav Singh RajputGaurav Singh Rajput
 
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...Gaurav Singh Rajput
 
Accident & Incident Investigation | Gaurav Singh Rajput
Accident & Incident Investigation | Gaurav Singh RajputAccident & Incident Investigation | Gaurav Singh Rajput
Accident & Incident Investigation | Gaurav Singh RajputGaurav Singh Rajput
 
Calculating Scaffold Loads | Gaurav Singh Rajput
Calculating Scaffold Loads | Gaurav Singh RajputCalculating Scaffold Loads | Gaurav Singh Rajput
Calculating Scaffold Loads | Gaurav Singh RajputGaurav Singh Rajput
 
Inspection of Pressure Vessels as per ASME Sec VIII Division -1
Inspection of Pressure Vessels as per ASME Sec VIII Division -1Inspection of Pressure Vessels as per ASME Sec VIII Division -1
Inspection of Pressure Vessels as per ASME Sec VIII Division -1Gaurav Singh Rajput
 
Process Safety | Process Safety Management | PSM | Gaurav Singh Rajput
Process Safety | Process Safety Management | PSM | Gaurav Singh RajputProcess Safety | Process Safety Management | PSM | Gaurav Singh Rajput
Process Safety | Process Safety Management | PSM | Gaurav Singh RajputGaurav Singh Rajput
 
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh RajputPigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh RajputGaurav Singh Rajput
 
Process Safety Awareness | PSM | Gaurav Singh Rajput
Process Safety Awareness | PSM | Gaurav Singh RajputProcess Safety Awareness | PSM | Gaurav Singh Rajput
Process Safety Awareness | PSM | Gaurav Singh RajputGaurav Singh Rajput
 

More from Gaurav Singh Rajput (20)

Site Emergency Response | Gaurav Singh Rajput
Site Emergency Response | Gaurav Singh RajputSite Emergency Response | Gaurav Singh Rajput
Site Emergency Response | Gaurav Singh Rajput
 
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh Rajput
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh RajputQuantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh Rajput
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh Rajput
 
Basic of Instrumentation and Control | Gaurav Singh Rajput
Basic of Instrumentation and Control | Gaurav Singh RajputBasic of Instrumentation and Control | Gaurav Singh Rajput
Basic of Instrumentation and Control | Gaurav Singh Rajput
 
Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...
Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...
Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...
 
Fire Protection System | Gaurav Singh Rajput
Fire Protection System | Gaurav Singh RajputFire Protection System | Gaurav Singh Rajput
Fire Protection System | Gaurav Singh Rajput
 
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh Rajput
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh RajputBasic Instrumentation Symbols | P&ID | PFD | Gaurav Singh Rajput
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh Rajput
 
Hzard Communication | Gaurav Singh Rajput
Hzard Communication | Gaurav Singh RajputHzard Communication | Gaurav Singh Rajput
Hzard Communication | Gaurav Singh Rajput
 
Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput
 
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh RajputInspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput
 
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh Rajput
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh RajputBasic LNG Training | Liquefied Natural Gas | Gaurav Singh Rajput
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh Rajput
 
Noise Analysis | Gaurav Singh Rajput
Noise Analysis | Gaurav Singh Rajput Noise Analysis | Gaurav Singh Rajput
Noise Analysis | Gaurav Singh Rajput
 
BBS - Behaviour Based Safety | Gaurav Singh Rajput
BBS - Behaviour Based Safety | Gaurav Singh RajputBBS - Behaviour Based Safety | Gaurav Singh Rajput
BBS - Behaviour Based Safety | Gaurav Singh Rajput
 
HAZID | Hazard Indentification | Gaurav Singh Rajput
HAZID | Hazard Indentification | Gaurav Singh RajputHAZID | Hazard Indentification | Gaurav Singh Rajput
HAZID | Hazard Indentification | Gaurav Singh Rajput
 
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...
 
Accident & Incident Investigation | Gaurav Singh Rajput
Accident & Incident Investigation | Gaurav Singh RajputAccident & Incident Investigation | Gaurav Singh Rajput
Accident & Incident Investigation | Gaurav Singh Rajput
 
Calculating Scaffold Loads | Gaurav Singh Rajput
Calculating Scaffold Loads | Gaurav Singh RajputCalculating Scaffold Loads | Gaurav Singh Rajput
Calculating Scaffold Loads | Gaurav Singh Rajput
 
Inspection of Pressure Vessels as per ASME Sec VIII Division -1
Inspection of Pressure Vessels as per ASME Sec VIII Division -1Inspection of Pressure Vessels as per ASME Sec VIII Division -1
Inspection of Pressure Vessels as per ASME Sec VIII Division -1
 
Process Safety | Process Safety Management | PSM | Gaurav Singh Rajput
Process Safety | Process Safety Management | PSM | Gaurav Singh RajputProcess Safety | Process Safety Management | PSM | Gaurav Singh Rajput
Process Safety | Process Safety Management | PSM | Gaurav Singh Rajput
 
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh RajputPigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
 
Process Safety Awareness | PSM | Gaurav Singh Rajput
Process Safety Awareness | PSM | Gaurav Singh RajputProcess Safety Awareness | PSM | Gaurav Singh Rajput
Process Safety Awareness | PSM | Gaurav Singh Rajput
 

Recently uploaded

Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 

Recently uploaded (20)

Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 

Casing Design | Tubing | Well Control | Drilling | Gaurav Singh Rajput

  • 2. Attention!! ➢ Please note that this presentation is for your understanding the process of designing casing. ➢ There are any designing updated methods and tools for casing design. ➢ Operators/Companies have their own design methodologies , safety factors that may defer from this presentation. ➢ There have been many development in casing manufacturing technologies and their pressure ratings and specs may be superior. ➢ Casing manufacturers provide their own casing tables that may differ due to material specs and manufacturing technology. Thank you.
  • 3. Casing 1. Prevent hole from caving 2. Prevent contamination of fresh water sands 3. Prevent water migration to producing formation 4. Confine production to the wellbore 5. Control pressures during drilling 6. Environment for subsurface equipment in producing wells 7. Drilling to total depth (TD) Casing Cement
  • 4. Casing Functions Drive/Conductor pipe Provides a mud return path Prevents erosion of ground below rig Supports the weight of subsequent casing strings Isolates very weak formations Surface casing – Means of installing WH/BOP – Strong casing seat (close in a well -kick case). – Protection of fresh water sands – Provides wellbore stabilization – WH: Wellhead – BOP: Blow Out Preventors
  • 5. Surface Casing 1. offshore 150’-300’ ( BML: below mudline). 2. Conductor string. 100’ - 1,600’ (BSL; Below Sea Level) 3. Surface pipe. 2,000’ - 4,000’ (BSL) Diameter Example 16”-60” 30” 16”-48” 20” 8 5/8”-20” 13 3/8”
  • 6. Intermediate/Contingency/ production/Tubing Strings 4. Intermediate String/Line 5. Contingency string/Liner(s) 6. Production String/Liner 7. Tubing String(s) • Contingency String: Run if drilling conditions require (HPHT). • String/Liner: Run as either full casing string or liner depending on well design. • Tubing string: Run for well completion( if required) 7 5/8”-16” 9 5/8” Diameter Example 9 5/8”-11”. 105/8” 4 1/2”-9 5/8” 7” 2 1/8”- 5”. 2 3/8”
  • 7. Well Configuration (Example) Drive pipe Conductor string Surface pipe IntermediateString Production Liner Hole Size 30” 20” 13 3/8 9 5/8 7 Pipe Size 36” 26” 17 1/2 12 1/4 8 3/4
  • 8. Well Configuration (Example) Structural casing Conductor string Contingency String (Optional) Surface pipe Intermediate String Production Liner Structural Pipe/conductor pipe( optional) 250’ 1,000’ 4,000’ SL
  • 9. Intermediate or protective casing/Liner – Compete well program to TD/abnormally pressured zone – Isolation of potentially troublesome formations/zones – Withstandmud weights to next Csg. seat/TD Contingency Csg String/Liner - Run as required as per hazardous drilling conditions (HPHT, Salt/Coal etc) ➢ Production casing/Liner – Zonal isolation o Migration of water to producing zones o Isolates production zones – Confines production to wellbore – Install subsurface completion equipment
  • 10. ➢ Production casing/Liner – Zonal isolation o Migration of water to producing zones o Isolates production zones – Confines production to wellbore – Install subsurface completion equipment Liners Types – Drilling liners • Same as Intermediate or protective casing – Production liners • Same as production casing – Tieback liners • Tie back drilling or production liner to the surface. • Converts liner to full string of casing
  • 11. Casing Specs 1. Casing Outside Diameter(OD); (e.g. 9 5/8”) 2. Casing Wall Thickness (T); (e.g. 1/2”) 3. Casing Material Grade, (e.g. N-80) 4. Threads and Couplings (TLC) Type, (e.g. API LCSG) 5. Length of each joint (RANGE), (e.g. Range 3) 6. Nominal weight (Avg. wt/ft incl. coupling weight), (e.g. 47 lb./ft)
  • 13. Casing Joints Lengths & Threads Casing Joint Length: RANGE 1 16-25 ft RANGE 2 25-34 ft RANGE 3 > 34 ft. Coupling Thread: API round threads - short ( CSG) API round thread - long (LCSG ) Buttress (BCSG) Extreme line (XCSG ) Xtreme Line Vam Etc.
  • 14. RecommendedAPI Casing Design Factors Collapse 1.125 Tension 1.8 Burst 1.1 Required Prrssure 10,000 psi 100,000 lbf 10,000 psi Design Pressure 11,250 psi 180,000 lbf 11,000 psi API Design Factor (Operators may set their own Safety Factors)
  • 15. API Recommendations Burst ➢ Design for maximum pressure on the inside of the casing. o Worst case scenario: Empty casing o No external pressure. ➢ Design Pressure:- Formation pressure at TD Collapse ➢ Worst case scenario:-, o No pressure inside the casing, o Maximum mud weight at casing depth. ➢ Reduction of collapse rating due to weight of casing/liner hanging below. Tension ➢ worst case: o No buoyancy effect. o Weight of casing string.
  • 16. Normal Pore Pressure Abnormal Pore Pressure 0.433 - 0.465 psi/ft gp > normal Normal Abnormal Design Pressure (Formation Pressure)
  • 17. Burst: Reservoir pressure along the wellbore. Collapse: Hydrostatic pressure (increases with depth) Tension: Tensile stress *weight of string at top) STRESS Tension Burst Collapse Collapse Tension Depth
  • 18. Casing Design-Burst Example Design a 7” Csg. String to 10,000 ft. Pore pressure gradient = 0.5 psi/ft Design factor, Ni=1.1 Burst Design only. Internal Yield Pressure for pipe  Internal Yield Pressure for couplings  Internal pressure leak resistance
  • 19. Formation pressure:- psi 000 , 5 ft 000 , 10 * ft psi 5 . 0 pres = = Required pipe internal yield:- psi 500 , 5 1 . 1 * 000 , 5 N * p p i res i = = = Ni = API Design BURST Factor= 1.1 From Casing Tables:- 7”, J-55, 26 lb./ft : BURST Pressure= 4,980 psi 7”, N-80, 23 lb./ft : BURST Pressure= 6,340 psi 7”, N-80, 26 lb./ft. : BURST Pressure= 7,249 psi Choose N-80 Csg., 23lb/ft > 5500. Psi
  • 20. Collapse Pressure                   −                 − = P A 2 / 1 2 P A P PA Y S 5 . 0 Y S 75 . 0 1 Y Y YPA = yield strength of axial stress equivalentgrade, psi YP = minimum yield strength of pipe, psi SA = Axial stress, psi (tension is positive) SA SA
  • 21. Collapse Example P p A 2 p A PA Y Y S 5 . 0 Y S 75 . 0 1 Y                   −         − = ( ) psi Area F S A A 820 , 24 012 . 5 5 . 5 4 000 , 100 2 2 = − = =  Axial tension reduces collapse pressure: psi 216 , 38 000 , 55 000 , 55 820 , 24 5 . 0 000 , 55 820 , 24 75 . 0 1 Y 2 PA =               −       − =
  • 22. Designing 9 5/8”Casing Design: 9 5/8-in Casing. • Setting Depth= 8,000’ • Mud Weight 12.5 ppg • Formation pore pressure - 6,000 psi. • Available Casing :- N-80, all weights. • API design factors. • Combination Casing String • Design for “worst conditions.”
  • 23. API design Factors: • Tension and Joint Strength: NT = 1.8 • Collapse (from external pressure): Nc= 1.125 • Burst (from internal pressure): Ni = 1.1 Notes:- 1.To design a string of 100,000 lbf, select pipe with Joint strength of 100,000 * 1.8 = 180,000 lbf. 2.Casing tables provide joint strength values with no safety factors. 3.Always check the connection strength when designing casing for tension. 4.Casing tables provide connection strength values with no safety factors.
  • 25. Design Burst: 6,600 psi Design Collapse: 5,850 psi N-80 53.5 Lb./ft satisfy collapse requirements.
  • 26. N-80 47 #/ft Can be run to depth: psi 231 , 4 125 . 1 760 , 4 factor design pipe of pressure Collapse Pc = = = ft 509 , 6 5 . 12 * 052 . 0 231 , 4 5 . 12 * 052 . 0 P h h * 5 . 12 * 052 . 0 P c 1 1 c = = =  =
  • 27. (8,000 - 6,509) = 1,491’ of 53.5 #/ft The weight of this pipe will reduce the collapse resistance of the 47.0 #/ft pipe! Weight, W1 = 53.5 #/ft * 1,491 ft = 79,769 lbf Axial stress in 47 #/ft pipe psi 877 , 5 in 13.572 lbf 769 , 79 area end weight S of 2 1 = = = API tables:- stress will reduce the collapse resistance from 4,760 to somewhere between 4,680 psi (with 5,000 psi stress) and 4,600 psi (with 10,000 psi stress) ( ) 2 1 1 2 1 1 c1 P P P S S S S P −         − − − =
  • 28. Interpolation between these values shows that the collapse resistance at 5,877 psi axial stress is: psi 148 , 4 125 . 1 666 , 4 P psi 666 , 4 ) 600 , 4 680 , 4 ( * ) 000 , 5 000 , 10 ( ) 000 , 5 877 , 5 ( 680 , 4 P cc1 1 c = = = − − − − = With the design factor, ( ) 2 1 1 2 1 1 c1 P P P S S S S P −         − − − = ft 382 , 6 5 . 12 * 052 . 0 148 , 4 h2 = = Which differs considerably from the initial depth of 6,509 ft, so a second iteration is required.
  • 29. Run 47 #/ft pipe to 6,382 ft. psi 378 , 6 in 572 . 13 lbf 563 , 86 S lbf 563 , 86 5 . 53 * ) 382 , 6 000 , 8 ( W 2 2 2 = = = − = ( )         −         − − − = 2 1 1 2 1 1 c1 D.F. 1 P P P S S S S P ( ) psi pcc 140 , 4 600 , 4 680 , 4 * 5000 5000 378 , 6 680 , 4 125 . 1 1 2 =             − − − = ft 369 , 6 5 . 12 * 052 . 0 140 , 4 h3 = = Interpolating Pressure at depth of: 13 ft short of 6382Ft.
  • 31. Tension Check Weight on casing top joint :- Design factor of 1.8 for tension, a pipe strength of weight actual 602 , 386 ) / # 5 . 53 * 631 , 1 ( ) / # 0 . 47 * 369 , 6 ( lbs ft ft ft ft = + required is lbf 080 , 695 602 , 386 * 8 . 1 = surface to OK is ft / # 0 . 47  Casing Tables:-Yield strength of 1,086,000 lbf for pipe body and a joint strength of 905,000 lbf for LT & C.