14 Material Requirements
Planning (MRP) and ERP
PowerPoint presentation to accompanyPowerPoint presentation to accompany
Heizer and RenderHeizer and Render
Operations Management, 10eOperations Management, 10e
Principles of Operations Management, 8ePrinciples of Operations Management, 8e
PowerPoint slides by Jeff Heyl
© 2011 Pearson
14 - 2
OutlineOutline
 Global Company Profile: Wheeled
Coach
 Dependent Demand
 Dependent Inventory Model
Requirements
 Master Production Schedule
 Bills of Material
 Accurate Inventory Records
 Purchase Orders Outstanding
 Lead Times for Components
© 2011 Pearson
14 - 3
Outline – ContinuedOutline – Continued
 MRP Structure
 MRP Management
 MRP Dynamics
 MRP and JIT
 Lot-Sizing Techniques
© 2011 Pearson
14 - 4
Outline – ContinuedOutline – Continued
 Extensions of MRP
 Material Requirements Planning II
(MRP II)
 Closed-Loop MRP
 Capacity Planning
 MRP In Services
 Distribution Resource Planning
(DRP)
© 2011 Pearson
14 - 5
Outline – ContinuedOutline – Continued
 Enterprise Resource Planning (ERP)
 Advantages and Disadvantages of
ERP Systems
 ERP in the Service Sector
© 2011 Pearson
14 - 6
Learning ObjectivesLearning Objectives
When you complete this chapter youWhen you complete this chapter you
should be able to:should be able to:
1. Develop a product structure
2. Build a gross requirements plan
3. Build a net requirements plan
4. Determine lot sizes for lot-for-lot,
EOQ, and PPB
© 2011 Pearson
14 - 7
Learning ObjectivesLearning Objectives
When you complete this chapter youWhen you complete this chapter you
should be able to:should be able to:
5. Describe MRP II
6. Describe closed-loop MRP
7. Describe ERP
© 2011 Pearson
14 - 8
Wheeled CoachWheeled Coach
 Largest manufacturer of
ambulances in the world
 International competitor
 12 major ambulance designs
 18,000 different inventory items
 6,000 manufactured parts
 12,000 purchased parts
© 2011 Pearson
14 - 9
Wheeled CoachWheeled Coach
 Four Key Tasks
 Material plan must meet both the
requirements of the master schedule
and the capabilities of the
production facility
 Plan must be executed as designed
 Minimize inventory investment
 Maintain excellent record integrity
© 2011 Pearson
14 - 10
Dependent DemandDependent Demand
For any product for which a scheduleFor any product for which a schedule
can be established, dependentcan be established, dependent
demand techniques should be useddemand techniques should be used
© 2011 Pearson
14 - 11
Dependent DemandDependent Demand
Benefits of MRP
1. Better response to customer
orders
2. Faster response to market
changes
3. Improved utilization of facilities
and labor
4. Reduced inventory levels
© 2011 Pearson
14 - 12
Dependent DemandDependent Demand
 The demand for one item is related
to the demand for another item
 Given a quantity for the end item,
the demand for all parts and
components can be calculated
 In general, used whenever a
schedule can be established for an
item
 MRP is the common technique
© 2011 Pearson
14 - 13
Dependent DemandDependent Demand
1. Master production schedule
2. Specifications or bill of material
3. Inventory availability
4. Purchase orders outstanding
5. Lead times
Effective use of dependent demand
inventory models requires the
following
© 2011 Pearson
14 - 14
Master Production ScheduleMaster Production Schedule
(MPS)(MPS)
 Specifies what is to be made and when
 Must be in accordance with the aggregate
production plan
 Inputs from financial plans, customer
demand, engineering, supplier performance
 As the process moves from planning to
execution, each step must be tested for
feasibility
 The MPS is the result of the production
planning process
© 2011 Pearson
14 - 15
Master Production ScheduleMaster Production Schedule
(MPS)(MPS)
 MPS is established in terms of specific
products
 Schedule must be followed for a
reasonable length of time
 The MPS is quite often fixed or frozen in
the near term part of the plan
 The MPS is a rolling schedule
 The MPS is a statement of what is to be
produced, not a forecast of demand
© 2011 Pearson
14 - 16
Figure 14.1
Change
production
plan?Master production
schedule
Management
Return on
investment
Capital
Engineering
Design
completion
Aggregate
production
plan
Procurement
Supplier
performance
Human resources
Manpower
planning
Production
Capacity
Inventory
Marketing
Customer
demand
Finance
Cash flow
The Planning ProcessThe Planning Process
© 2011 Pearson
14 - 17
The Planning ProcessThe Planning Process
Figure 14.1
Is capacity
plan being
met?
Is
execution
meeting the
plan?
Change
master
production
schedule?
Change
capacity?
Change
requirements?
No
Execute
material plans
Execute capacity
plans
Yes
Realistic?
Capacity
requirements plan
Material
requirements plan
Master production
schedule
© 2011 Pearson
14 - 18
AggregateAggregate
Production PlanProduction Plan
Months January February
Aggregate Production Plan 1,500 1,200
(Shows the total
quantity of amplifiers)
Weeks 1 2 3 4 5 6 7 8
Master Production Schedule
(Shows the specific type and
quantity of amplifier to be
produced
240-watt amplifier 100 100 100 100
150-watt amplifier 500 500 450 450
75-watt amplifier 300 100
Figure 14.2
© 2011 Pearson
14 - 19
Master Production ScheduleMaster Production Schedule
(MPS)(MPS)
1. A customer order in a job shop (make-
to-order) company
2. Modules in a repetitive (assemble-to-
order or forecast) company
3. An end item in a continuous (stock-to-
forecast) company
Can be expressed in any of the
following terms:
© 2011 Pearson
14 - 20
Focus for DifferentFocus for Different
Process StrategiesProcess Strategies
Stock to Forecast
(Product Focus)
Schedule finished
product
Assemble to Order
or Forecast
(Repetitive)
Schedule modules
Make to Order
(Process Focus)
Schedule orders
Examples: Print shop Motorcycles Steel, Beer, Bread
Machine shop Autos, TVs Lightbulbs
Fine-dining restaurant Fast-food restaurant Paper
Typical focus of the
master production
schedule
Number of
inputs
Number of
end items
Figure 14.3
© 2011 Pearson
14 - 21
MPS ExamplesMPS Examples
Gross Requirements for Crabmeat Quiche
Gross Requirements for Spinach Quiche
Day 6 7 8 9 10 11 12 13 14 and so on
Amount 50 100 47 60 110 75
Day 7 8 9 10 11 12 13 14 15 16 and so on
Amount 100 200 150 60 75 100
Table 14.1
For Nancy’s Specialty Foods
© 2011 Pearson
14 - 22
Bills of MaterialBills of Material
 List of components, ingredients,
and materials needed to make
product
 Provides product structure
 Items above given level are called
parents
 Items below given level are called
children
© 2011 Pearson
14 - 23
BOM ExampleBOM Example
B(2) Std. 12” Speaker kit C(3)
Std. 12” Speaker kit w/
amp-booster1
E(2)E(2) F(2)
Packing box and
installation kit of wire,
bolts, and screws
Std. 12” Speaker
booster assembly
2
D(2)
12” Speaker
D(2)
12” Speaker
G(1)
Amp-booster
3
Product structure for “Awesome” (A)
A
Level
0
© 2011 Pearson
14 - 24
BOM ExampleBOM Example
B(2) Std. 12” Speaker kit C(3)
Std. 12” Speaker kit w/
amp-booster1
E(2)E(2) F(2)
Packing box and
installation kit of wire,
bolts, and screws
Std. 12” Speaker
booster assembly
2
D(2)
12” Speaker
D(2)
12” Speaker
G(1)
Amp-booster
3
Product structure for “Awesome” (A)
A
Level
0
Part B: 2 x number of As = (2)(50) = 100
Part C: 3 x number of As = (3)(50) = 150
Part D: 2 x number of Bs
+ 2 x number of Fs = (2)(100) + (2)(300) = 800
Part E: 2 x number of Bs
+ 2 x number of Cs = (2)(100) + (2)(150) = 500
Part F: 2 x number of Cs = (2)(150) = 300
Part G: 1 x number of Fs = (1)(300) = 300
© 2011 Pearson
14 - 25
Bills of MaterialBills of Material
 Modular Bills
 Modules are not final products but
components that can be assembled
into multiple end items
 Can significantly simplify planning
and scheduling
© 2011 Pearson
14 - 26
Bills of MaterialBills of Material
 Planning Bills
 Also called “pseudo” or super bills
 Created to assign an artificial parent
to the BOM
 Used to group subassemblies to
reduce the number of items planned
and scheduled
 Used to create standard “kits” for
production
© 2011 Pearson
14 - 27
Bills of MaterialBills of Material
 Phantom Bills
Describe subassemblies that exist
only temporarily
Are part of another assembly and
never go into inventory
 Low-Level Coding
Item is coded at the lowest level at
which it occurs
BOMs are processed one level at a time
© 2011 Pearson
14 - 28
Accurate RecordsAccurate Records
 Accurate inventory records are
absolutely required for MRP (or
any dependent demand system) to
operate correctly
 Generally MRP systems require
more than 99% accuracy
 Outstanding purchase orders must
accurately reflect quantities and
scheduled receipts
© 2011 Pearson
14 - 29
Lead TimesLead Times
 The time required to purchase,
produce, or assemble an item
 For production – the sum of the
order, wait, move, setup, store,
and run times
 For purchased items – the time
between the recognition of a need
and the availability of the item for
production
© 2011 Pearson
14 - 30
Time-Phased ProductTime-Phased Product
StructureStructure
| | | | | | | |
1 2 3 4 5 6 7 8
Time in weeks
F
2 weeks
3 weeks
1 week
A
2 weeks
1 week
D
E
2 weeks
D
G
1 week
Start production of D
Must have D and E
completed here so
production can
begin on B
Figure 14.4
1 week
2 weeks to
produce
B
C
E
© 2011 Pearson
14 - 31
MRP StructureMRP Structure
Figure 14.5
Output Reports
MRP by
period report
MRP by
date report
Planned order
report
Purchase advice
Exception reports
Order early or late
or not needed
Order quantity too
small or too large
Data Files
Purchasing data
BOM
Lead times
(Item master file)
Inventory data
Master
production schedule
Material
requirement
planning
programs
(computer and
software)
© 2011 Pearson
14 - 32
Determining GrossDetermining Gross
RequirementsRequirements
 Starts with a production schedule for the
end item – 50 units of Item A in week 8
 Using the lead time for the item,
determine the week in which the order
should be released – a 1 week lead time
means the order for 50 units should be
released in week 7
 This step is often called “lead time
offset” or “time phasing”
© 2011 Pearson
14 - 33
Determining GrossDetermining Gross
RequirementsRequirements
 From the BOM, every Item A requires 2
Item Bs – 100 Item Bs are required in
week 7 to satisfy the order release for
Item A
 The lead time for the Item B is 2 weeks –
release an order for 100 units of Item B in
week 5
 The timing and quantity for component
requirements are determined by the order
release of the parent(s)
© 2011 Pearson
14 - 34
Determining GrossDetermining Gross
RequirementsRequirements
 The process continues through the entire
BOM one level at a time – often called
“explosion”
 By processing the BOM by level, items
with multiple parents are only processed
once, saving time and resources and
reducing confusion
 Low-level coding ensures that each item
appears at only one level in the BOM
© 2011 Pearson
14 - 35
Gross Requirements PlanGross Requirements Plan
Table 14.3
Week
1 2 3 4 5 6 7 8 Lead Time
A. Required date 50
Order release date 50 1 week
B. Required date 100
Order release date 100 2 weeks
C. Required date 150
Order release date 150 1 week
E. Required date 200 300
Order release date 200 300 2 weeks
F. Required date 300
Order release date 300 3 weeks
D. Required date 600 200
Order release date 600 200 1 week
G. Required date 300
Order release date 300 2 weeks
© 2011 Pearson
14 - 36
Net Requirements PlanNet Requirements Plan
© 2011 Pearson
14 - 37
Net Requirements PlanNet Requirements Plan
© 2011 Pearson
14 - 38
Determining NetDetermining Net
RequirementsRequirements
 Starts with a production schedule for the
end item – 50 units of Item A in week 8
 Because there are 10 Item As on hand,
only 40 are actually required – (net
requirement) = (gross requirement - on-
hand inventory)
 The planned order receipt for Item A in
week 8 is 40 units – 40 = 50 - 10
© 2011 Pearson
14 - 39
Determining NetDetermining Net
RequirementsRequirements
 Following the lead time offset procedure,
the planned order release for Item A is
now 40 units in week 7
 The gross requirement for Item B is now
80 units in week 7
 There are 15 units of Item B on hand, so
the net requirement is 65 units in week 7
 A planned order receipt of 65 units in
week 7 generates a planned order release
of 65 units in week 5
© 2011 Pearson
14 - 40
Determining NetDetermining Net
RequirementsRequirements
 A planned order receipt of 65 units in
week 7 generates a planned order release
of 65 units in week 5
 The on-hand inventory record for Item B
is updated to reflect the use of the 15
items in inventory and shows no on-hand
inventory in week 8
 This is referred to as the Gross-to-Net
calculation and is the third basic function
of the MRP process
© 2011 Pearson
14 - 41
S
B C
12 138 9 10 11
20 3040
Lead time = 6 for S
Master schedule for S
Gross RequirementsGross Requirements
ScheduleSchedule
Figure 14.6
1 2 3
10 10
Master schedule
for B
sold directly
Periods
Therefore, these
are the gross
requirements for B
Gross requirements: B 10 40 50 2040+10 15+30
=50 =45
1 2 3 4 5 6 7 8Periods
A
B C
Lead time = 4 for A
Master schedule for A
5 6 7 8 9 10 11
40 1550
© 2011 Pearson
14 - 42
Net Requirements PlanNet Requirements Plan
The logic of net requirementsThe logic of net requirements
Available inventory
Net
requirements
On
hand
Scheduled
receipts+– =
Total
requirements
Gross
requirements
Allocations+
© 2011 Pearson
14 - 43
MRP Planning SheetMRP Planning Sheet
Figure 14.7
© 2011 Pearson
14 - 44
Safety StockSafety Stock
 BOMs, inventory records, purchase and
production quantities may not be perfect
 Consideration of safety stock may be
prudent
 Should be minimized and ultimately
eliminated
 Typically built into projected on-hand
inventory
© 2011 Pearson
14 - 45
MRP ManagementMRP Management
 MRP is a dynamic system
 Facilitates replanning when changes occur
 Regenerating
 Net change
 System nervousness can result from too
many changes
 Time fences put limits on replanning
 Pegging links each item to its parent
allowing effective analysis of changes
© 2011 Pearson
14 - 46
MRP and JITMRP and JIT
 MRP is a planning system that
does not do detailed scheduling
 MRP requires fixed lead times
which might actually vary with
batch size
 JIT excels at rapidly moving small
batches of material through the
system
© 2011 Pearson
14 - 47
Finite Capacity SchedulingFinite Capacity Scheduling
 MRP systems do not consider
capacity during normal planning
cycles
 Finite capacity scheduling (FCS)
recognizes actual capacity limits
 By merging MRP and FCS, a finite
schedule is created with feasible
capacities which facilitates rapid
material movement
© 2011 Pearson
14 - 48
Small Bucket ApproachSmall Bucket Approach
1. MRP “buckets” are reduced to daily or hourly
2. Planned receipts are used internally to
sequence production
3. Inventory is moved through the plant on a JIT
basis
4. Completed products are moved to finished
goods inventory which reduces required
quantities for subsequent planned orders
5. Back flushing based on the BOM is used to
deduct inventory that was used in production
© 2011 Pearson
14 - 49
Balanced FlowBalanced Flow
 Used in repetitive operations
 MRP plans are
executed using
JIT techniques
based on “pull”
principles
 Flows are carefully
balanced with
small lot sizes
© 2011 Pearson
14 - 50
SupermarketSupermarket
 Items used by many products are
held in a common area often called
a supermarket
 Items are withdrawn as needed
 Inventory is maintained using JIT
systems and procedures
 Common items are not planned by
the MRP system
© 2011 Pearson
14 - 51
Lot-Sizing TechniquesLot-Sizing Techniques
 Lot-for-lot techniques order just
what is required for production
based on net requirements
 May not always be feasible
 If setup costs are high, lot-for-lot can
be expensive
 Economic order quantity (EOQ)
 EOQ expects a known constant
demand and MRP systems often deal
with unknown and variable demand
© 2011 Pearson
14 - 52
Lot-Sizing TechniquesLot-Sizing Techniques
 Part Period Balancing (PPB) looks at
future orders to determine most
economic lot size
 The Wagner-Whitin algorithm is a
complex dynamic programming
technique
 Assumes a finite time horizon
 Effective, but computationally
burdensome
© 2011 Pearson
14 - 53
Lot-for-Lot ExampleLot-for-Lot Example
1 2 3 4 5 6 7 8 9 10
Gross
requirements
35 30 40 0 10 40 30 0 30 55
Scheduled
receipts
Projected on
hand
35 35 0 0 0 0 0 0 0 0 0
Net
requirements
0 30 40 0 10 40 30 0 30 55
Planned order
receipts
30 40 10 40 30 30 55
Planned order
releases 30 40 10 40 30 30 55
Holding cost = $1/week; Setup cost = $100; Lead time = 1 week
© 2011 Pearson
14 - 54
Lot-for-Lot ExampleLot-for-Lot Example
1 2 3 4 5 6 7 8 9 10
Gross
requirements
35 30 40 0 10 40 30 0 30 55
Scheduled
receipts
Projected on
hand
35 35 0 0 0 0 0 0 0 0 0
Net
requirements
0 30 40 0 10 40 30 0 30 55
Planned order
receipts
30 40 10 40 30 30 55
Planned order
releases 30 40 10 40 30 30 55
Holding cost = $1/week; Setup cost = $100; Lead time = 1 week
No on-hand inventory is carried through the system
Total holding cost = $0
There are seven setups for this item in this plan
Total ordering cost = 7 x $100 = $700
© 2011 Pearson
14 - 55
EOQ Lot Size ExampleEOQ Lot Size Example
1 2 3 4 5 6 7 8 9 10
Gross
requirements
35 30 40 0 10 40 30 0 30 55
Scheduled
receipts
Projected on
hand
35 35 0 43 3 3 66 26 69 69 39
Net
requirements
0 30 0 0 7 0 4 0 0 16
Planned order
receipts
73 73 73 73
Planned order
releases 73 73 73 73
Holding cost = $1/week; Setup cost = $100; Lead time = 1
week
Average weekly gross requirements = 27; EOQ = 73 units
© 2011 Pearson
14 - 56
EOQ Lot Size ExampleEOQ Lot Size Example
1 2 3 4 5 6 7 8 9 10
Gross
requirements
35 30 40 0 10 40 30 0 30 55
Scheduled
receipts
Projected on
hand
35 35 0 0 0 0 0 0 0 0 0
Net
requirements
0 30 0 0 7 0 4 0 0 16
Planned order
receipts
73 73 73 73
Planned order
releases 73 73 73 73
Holding cost = $1/week; Setup cost = $100; Lead time = 1 week
Average weekly gross requirements = 27; EOQ = 73 units
Annual demand = 1,404
Total cost = setup cost + holding cost
Total cost = (1,404/73) x $100 + (73/2) x ($1 x 52 weeks)
Total cost = $3,798
Cost for 10 weeks = $3,798 x (10 weeks/52 weeks) =
$730
© 2011 Pearson
14 - 57
PPB ExamplePPB Example
1 2 3 4 5 6 7 8 9 10
Gross
requirements
35 30 40 0 10 40 30 0 30 55
Scheduled
receipts
Projected on
hand
35
Net
requirements
Planned order
receipts
Planned order
releases
Holding cost = $1/week; Setup cost = $100; Lead time = 1 week
EPP = 100 units
© 2011 Pearson
14 - 58
PPB ExamplePPB Example
1 2 3 4 5 6 7 8 9 10
Gross
requirements
35 30 40 0 10 40 30 0 30 55
Scheduled
receipts
Projected on
hand
35
Net
requirements
Planned order
receipts
Planned order
releases
Holding cost = $1/week; Setup cost = $100;
EPP = 100 units
2 30 0
2, 3 70 40 = 40 x 1
2, 3, 4 70 40
2, 3, 4, 5 80 70 = 40 x 1 + 10 x 3 100 70 170
2, 3, 4, 5, 6 120 230 = 40 x 1 + 10 x 3
+ 40 x 4
+ =
Combine periods 2 - 5 as this results in the Part Period
closest to the EPP
Combine periods 6 - 9 as this results in the Part Period
closest to the EPP
6 40 0
6, 7 70 30 = 30 x 1
6, 7, 8 70 30 = 30 x 1 + 0 x 2
6, 7, 8, 9 100 120 = 30 x 1 + 30 x 3 100 120 220+ =
10 55 0 100 0 100
Total cost 300 190 490
+ =
+ =
Trial Lot Size
Periods (cumulative net Costs
Combined requirements) Part Periods Setup Holding Total
© 2011 Pearson
14 - 59
PPB ExamplePPB Example
1 2 3 4 5 6 7 8 9 10
Gross
requirements
35 30 40 0 10 40 30 0 30 55
Scheduled
receipts
Projected on
hand
35 35 0 50 10 10 0 60 30 30 0
Net
requirements
0 30 0 0 0 40 0 0 0 55
Planned order
receipts
80 100 55
Planned order
releases 80 100 55
Holding cost = $1/week; Setup cost = $100; Lead time = 1 week
EPP = 100 units
© 2011 Pearson
14 - 60
Lot-Sizing SummaryLot-Sizing Summary
For these three examples
Lot-for-lot $700
EOQ $730
PPB $490
Wagner-Whitin would have yielded a
plan with a total cost of $455
© 2011 Pearson
14 - 61
Lot-Sizing SummaryLot-Sizing Summary
 In theory, lot sizes should be recomputed
whenever there is a lot size or order
quantity change
 In practice, this results in system
nervousness and instability
 Lot-for-lot should
be used when
low-cost JIT can
be achieved
© 2011 Pearson
14 - 62
Lot-Sizing SummaryLot-Sizing Summary
 Lot sizes can be modified to allow for
scrap, process constraints, and purchase
lots
 Use lot-sizing with care as it can cause
considerable distortion of requirements
at lower levels of the BOM
 When setup costs are significant and
demand is reasonably smooth, PPB,
Wagner-Whitin, or EOQ should give
reasonable results
© 2011 Pearson
14 - 63
Extensions of MRPExtensions of MRP
 MRP II
 Closed-Loop MRP
 MRP system provides input to the capacity
plan, MPS, and production planning process
 Capacity Planning
 MRP system generates a load report which
details capacity requirements
 This is used to drive the capacity planning
process
 Changes pass back through the MRP system
for rescheduling
© 2011 Pearson
14 - 64
Material RequirementsMaterial Requirements
Planning IIPlanning II
 Requirement data can be enriched by
other resources
 Generally called MRP II or Material
Resource Planning
 Outputs include
 Scrap
 Packaging waste
 Carbon emissions
 Data used by purchasing, production
scheduling, capacity planning, inventory
© 2011 Pearson
14 - 65
Material Resource PlanningMaterial Resource Planning
Weeks
LT 5 6 7 8
Computer 1 100
Labor Hrs: .2 each 20
Machine Hrs: .2 each 20
Scrap: 1 ounce fiberglass each 6.25 lbs
Payables: $0 each $0
PC Board (1 each) 2 100
Labor Hrs: .15 each 15
Machine Hrs: .1 each 10
Scrap: .5 ounces copper each 3.125 lb
Payables: raw material at $5 each $500
Processor (5 each) 4 500
Labor Hrs: .2 each 100
Machine Hrs: .2 each 100
Scrap: .01 ounces of acid waste each 0.3125 lb
Payables: processors at $10 each $5,000
Table 14.4
© 2011 Pearson
14 - 66
Closed-Loop MRP SystemClosed-Loop MRP System
Figure 14.8
Priority Management
Develop Master Production
Schedule
Prepare Materials
Requirements Pan
Detailed Production
Activity Control
(Shop Scheduling/Dispatching)
Capacity Management
Evaluate Resource Availability
(Rough Cut)
Determine Capacity Availability
Implement Input/Output Control
Aggregate Production Plan
OK?OK?
NONO
OK?OK?
NONO OK? YESOK? YES
OK? YESOK? YES
Planning
Execution
(in repetitive
systems JIT
techniques
are used)
© 2011 Pearson
14 - 67
Capacity PlanningCapacity Planning
 Feedback from the MRP system
 Load reports show resource
requirements for work centers
 Work can be moved between work
centers to smooth the load or bring
it within capacity
© 2011 Pearson
14 - 68
Smoothing TacticsSmoothing Tactics
1. Overlapping
 Sends part of the work to following
operations before the entire lot is complete
 Reduces lead time
2. Operations splitting
 Sends the lot to two different machines for
the same operation
 Shorter throughput time but increased setup
costs
3. Order or lot splitting
 Breaking up the order into smaller lots and
running part earlier (or later) in the schedule
© 2011 Pearson
14 - 69
Order SplittingOrder Splitting
 Develop a capacity plan for a work cell at
Wiz Products
 There are 12 hours available each day
 Each order requires 1 hour
Day 1 2 3 4 5
Orders 10 14 13 10 14
© 2011 Pearson
14 - 70
Order SplittingOrder Splitting
Day
Units
Ordered
Capacity
Required
(hours)
Capacity
Available
(hours)
Utilization:
Over/
(Under)
(hours)
Production
Planner’s Action
New
Production
Schedule
1 10 10 12 (2) 12
2 14 14 12 2 Split order:
move 2 units to
day 1
12
3 13 13 12 1 Split order:
move one unit
to day 6 or
request
overtime
13
4 10 10 12 (2) 12
5 14 14 12 2 Split order:
move 2 units to
day 4
12
61
© 2011 Pearson
14 - 71
Order SplittingOrder Splitting
Figure 14.9
Available
capacity
Capacity exceeded
on days 2, 3, and 5
2 orders moved to day 1 from
day 2 (a day early)
1 order forced to overtime
or to day 6
2 orders moved to
day 4 (a day early)
14 –
12 –
10 –
8 –
6 –
4 –
2 –
0 –
1 2 3 4 5
Days
(b)
Standardlabor-Hours
14 –
12 –
10 –
8 –
6 –
4 –
2 –
0 –
1 2 3 4 5
Days
(a)
Standardlabor-Hours
© 2011 Pearson
14 - 72
MRP in ServicesMRP in Services
 Some services or service items are
directly linked to demand for other
services
 These can be treated as dependent
demand services or items
 Restaurants
 Hospitals
 Hotels
© 2011 Pearson
14 - 73
Uncooked
linguini
#30004
Sauce
#30006
Veal
#30005
MRP in ServicesMRP in Services
Chef;
Work
Center #1
Helper one;
Work
Center #2
Asst. Chef;
Work
Center #3
Cooked
linguini
#20002
Spinach
#20004
Prepared veal
and sauce
#20003
(a) PRODUCT STRUCTURE TREE
Veal
picante
#10001
Figure 14.10
© 2011 Pearson
14 - 74
MRP in ServicesMRP in Services
(b) BILL OF MATERIALS
Part
Number Description Quantity
Unit of
Measure
Unit
cost
10001 Veal picante 1 Serving —
20002 Cooked linguini 1 Serving —
20003 Prepared veal and sauce 1 Serving —
20004 Spinach 0.1 Bag 0.94
30004 Uncooked linguini 0.5 Pound —
30005 Veal 1 Serving 2.15
30006 Sauce 1 Serving 0.80
© 2011 Pearson
14 - 75
MRP in ServicesMRP in Services
(c) BILL OF LABOR FOR VEAL PICANTE
Labor Hours
Work Center Operation Labor Type Setup Time Run Time
1 Assemble dish Chef .0069 .0041
2 Cook linguini Helper one .0005 .0022
3 Cook veal
and sauce
Assistant Chef
.0125 .0500
© 2011 Pearson
14 - 76
Distribution ResourceDistribution Resource
Planning (DRP)Planning (DRP)
Using dependent demand techniques
through the supply chain
 Expected demand or sales forecasts
become gross requirements
 Minimum levels of inventory to meet
customer service levels
 Accurate lead times
 Definition of the distribution structure
© 2011 Pearson
14 - 77
Enterprise ResourceEnterprise Resource
Planning (ERP)Planning (ERP)
 An extension of the MRP system to
tie in customers and suppliers
 Allows automation and integration of
many business processes
 Shares common data bases and
business practices
 Produces information in real time
 Coordinates business from supplier
evaluation to customer invoicing
© 2011 Pearson
14 - 78
Enterprise ResourceEnterprise Resource
Planning (ERP)Planning (ERP)
 ERP modules include
 Basic MRP
 Finance
 Human resources
 Supply chain management (SCM)
 Customer relationship management
(CRM)
© 2011 Pearson
14 - 79
ERP and MRPERP and MRP
Figure 14.11
© 2011 Pearson
14 - 80
ERP and MRPERP and MRP
Figure 14.11
Customer Relationship Management
Invoicing
Shipping
Distributors,
retailers,
and end users
Sales Order
(order entry,
product configuration,
sales management)
© 2011 Pearson
14 - 81
Table 13.6
Bills of
Material
Work
Orders
Purchasing
and
Lead Times
Routings
and
Lead Times
Master
Production
Schedule
Inventory
Management
ERP and MRPERP and MRP
Figure 14.11
MRP
© 2011 Pearson
14 - 82
ERP and MRPERP and MRP
Figure 14.11
Supply Chain Management
Vendor Communication
(schedules, EDI, advanced shipping notice,
e-commerce, etc.)
© 2011 Pearson
14 - 83
ERP and MRPERP and MRP
Figure 14.11Table 13.6
Finance/
Accounting
General
Ledger
Accounts
Receivable
Payroll
Accounts
Payable
© 2011 Pearson
14 - 84
Enterprise ResourceEnterprise Resource
Planning (ERP)Planning (ERP)
 ERP can be highly customized to
meet specific business requirements
 Enterprise application integration
software (EAI) allows ERP systems
to be integrated with
 Warehouse management
 Logistics
 Electronic catalogs
 Quality management
© 2011 Pearson
14 - 85
Enterprise ResourceEnterprise Resource
Planning (ERP)Planning (ERP)
 ERP systems have the potential to
 Reduce transaction costs
 Increase the speed and accuracy of
information
 Facilitates a strategic emphasis on
JIT systems and integration
© 2011 Pearson
14 - 86
SAP’s ERP ModulesSAP’s ERP Modules
Figure 14.12
© 2011 Pearson
14 - 87
Advantages of ERPAdvantages of ERP
SystemsSystems
1. Provides integration of the supply chain,
production, and administration
2. Creates commonality of databases
3. Can incorporate improved best processes
4. Increases communication and
collaboration between business units and
sites
5. Has an off-the-shelf software database
6. May provide a strategic advantage
© 2011 Pearson
14 - 88
Disadvantages of ERPDisadvantages of ERP
SystemsSystems
1. Is very expensive to purchase and even
more so to customize
2. Implementation may require major changes
in the company and its processes
3. Is so complex that many companies cannot
adjust to it
4. Involves an ongoing, possibly never
completed, process for implementation
5. Expertise is limited with ongoing staffing
problems
© 2011 Pearson
14 - 89
ERP in the Service SectorERP in the Service Sector
 ERP systems have been developed
for health care, government, retail
stores, hotels, and financial
services
 Also called efficient consumer
response (ECR) systems
 Objective is to tie sales to buying,
inventory, logistics, and production
© 2011 Pearson
14 - 90
All rights reserved. No part of this publication may be reproduced, stored in a retrieval
system, or transmitted, in any form or by any means, electronic, mechanical, photocopying,
recording, or otherwise, without the prior written permission of the publisher.
Printed in the United States of America.

More Related Content

What's hot

beas for process and regulated industries 14.2
beas for process and regulated industries 14.2beas for process and regulated industries 14.2
beas for process and regulated industries 14.2
beasgroup
 
Resource Requirement Planning
Resource Requirement PlanningResource Requirement Planning
Mp cn6 master production schedule
Mp cn6  master production scheduleMp cn6  master production schedule
Mp cn6 master production schedulepatiltushar96
 
Mrp MRPII Erp Implementation
Mrp MRPII Erp ImplementationMrp MRPII Erp Implementation
Mrp MRPII Erp ImplementationAnand Subramaniam
 
Sap exec summary
Sap exec summarySap exec summary
Sap exec summary
hopperdev
 
Report w13
Report w13Report w13
Report w13
Thanh Luan Nguyen
 
Sap pp dinakar skype himbuj
Sap pp  dinakar skype himbujSap pp  dinakar skype himbuj
Sap pp dinakar skype himbuj
SAPQM ONLINE TRAINING FROM DIRECT TRAINER
 
Erp for manufacturing industry
Erp   for manufacturing industryErp   for manufacturing industry
Erp for manufacturing industry
Siva Subramanian TS
 
Duncan Mills Mastering SAP PM 2011
Duncan Mills Mastering SAP PM 2011Duncan Mills Mastering SAP PM 2011
Duncan Mills Mastering SAP PM 2011
duncanmills
 
be.as Manufacturing for SAP Business One
be.as Manufacturing for SAP Business Onebe.as Manufacturing for SAP Business One
be.as Manufacturing for SAP Business One
Blue Ocean Systems Pte Ltd
 
Bn1010 demo ppt sap pp
Bn1010 demo ppt sap ppBn1010 demo ppt sap pp
Bn1010 demo ppt sap pp
conline training
 
Material and capacity requirements planning (mrp and crp) part 1
Material and capacity requirements planning (mrp and crp) part  1Material and capacity requirements planning (mrp and crp) part  1
Material and capacity requirements planning (mrp and crp) part 1
Dr. Mahmoud Al-Naimi
 
Om lect 05_a(r0-aug-08)_manufacturing planning & scheduling_mms_sies
Om lect 05_a(r0-aug-08)_manufacturing planning & scheduling_mms_siesOm lect 05_a(r0-aug-08)_manufacturing planning & scheduling_mms_sies
Om lect 05_a(r0-aug-08)_manufacturing planning & scheduling_mms_siesvideoaakash15
 
MRP Theory: Master Production Schedule, Bill of Material and Lead Times
MRP Theory: Master Production Schedule, Bill of Material and Lead TimesMRP Theory: Master Production Schedule, Bill of Material and Lead Times
MRP Theory: Master Production Schedule, Bill of Material and Lead Times
ejalgfer
 
SAP Production Planning
SAP Production PlanningSAP Production Planning
SAP Production Planning
Rupesh Brahmankar
 
Material and capacity requirements planning (mrp and crp) part 2
Material and capacity requirements planning (mrp and crp) part  2Material and capacity requirements planning (mrp and crp) part  2
Material and capacity requirements planning (mrp and crp) part 2
Dr. Mahmoud Al-Naimi
 
Preparing cost estimation
Preparing cost estimationPreparing cost estimation
Preparing cost estimation
Somashekar S.M
 
Sap production planning
Sap production planningSap production planning
Sap production planning
Sourav Dass
 
Cutomize sap webinar
Cutomize sap webinarCutomize sap webinar
Cutomize sap webinar
gabrielsyst
 

What's hot (20)

beas for process and regulated industries 14.2
beas for process and regulated industries 14.2beas for process and regulated industries 14.2
beas for process and regulated industries 14.2
 
Resource Requirement Planning
Resource Requirement PlanningResource Requirement Planning
Resource Requirement Planning
 
Mp cn6 master production schedule
Mp cn6  master production scheduleMp cn6  master production schedule
Mp cn6 master production schedule
 
Mrp MRPII Erp Implementation
Mrp MRPII Erp ImplementationMrp MRPII Erp Implementation
Mrp MRPII Erp Implementation
 
Sap exec summary
Sap exec summarySap exec summary
Sap exec summary
 
Report w13
Report w13Report w13
Report w13
 
Sap pp dinakar skype himbuj
Sap pp  dinakar skype himbujSap pp  dinakar skype himbuj
Sap pp dinakar skype himbuj
 
Erp for manufacturing industry
Erp   for manufacturing industryErp   for manufacturing industry
Erp for manufacturing industry
 
Mrp ppt.
Mrp ppt.Mrp ppt.
Mrp ppt.
 
Duncan Mills Mastering SAP PM 2011
Duncan Mills Mastering SAP PM 2011Duncan Mills Mastering SAP PM 2011
Duncan Mills Mastering SAP PM 2011
 
be.as Manufacturing for SAP Business One
be.as Manufacturing for SAP Business Onebe.as Manufacturing for SAP Business One
be.as Manufacturing for SAP Business One
 
Bn1010 demo ppt sap pp
Bn1010 demo ppt sap ppBn1010 demo ppt sap pp
Bn1010 demo ppt sap pp
 
Material and capacity requirements planning (mrp and crp) part 1
Material and capacity requirements planning (mrp and crp) part  1Material and capacity requirements planning (mrp and crp) part  1
Material and capacity requirements planning (mrp and crp) part 1
 
Om lect 05_a(r0-aug-08)_manufacturing planning & scheduling_mms_sies
Om lect 05_a(r0-aug-08)_manufacturing planning & scheduling_mms_siesOm lect 05_a(r0-aug-08)_manufacturing planning & scheduling_mms_sies
Om lect 05_a(r0-aug-08)_manufacturing planning & scheduling_mms_sies
 
MRP Theory: Master Production Schedule, Bill of Material and Lead Times
MRP Theory: Master Production Schedule, Bill of Material and Lead TimesMRP Theory: Master Production Schedule, Bill of Material and Lead Times
MRP Theory: Master Production Schedule, Bill of Material and Lead Times
 
SAP Production Planning
SAP Production PlanningSAP Production Planning
SAP Production Planning
 
Material and capacity requirements planning (mrp and crp) part 2
Material and capacity requirements planning (mrp and crp) part  2Material and capacity requirements planning (mrp and crp) part  2
Material and capacity requirements planning (mrp and crp) part 2
 
Preparing cost estimation
Preparing cost estimationPreparing cost estimation
Preparing cost estimation
 
Sap production planning
Sap production planningSap production planning
Sap production planning
 
Cutomize sap webinar
Cutomize sap webinarCutomize sap webinar
Cutomize sap webinar
 

Similar to Heizer om10 ch14

Heizer om10 ch14
Heizer om10 ch14Heizer om10 ch14
Heizer om10 ch14ryaekle
 
heizer_om12_ch014 final (1).pptx
heizer_om12_ch014 final (1).pptxheizer_om12_ch014 final (1).pptx
heizer_om12_ch014 final (1).pptx
kikikikiyowooo
 
Material requirements planning & erp ppt @ bec doms
Material requirements planning & erp  ppt @ bec domsMaterial requirements planning & erp  ppt @ bec doms
Material requirements planning & erp ppt @ bec doms
Babasab Patil
 
Fred Duchow Resume 2015
Fred Duchow Resume 2015Fred Duchow Resume 2015
Fred Duchow Resume 2015Fred Duchow
 
Lecture 12_Enterprise Resourse Planning.pdf
Lecture 12_Enterprise Resourse Planning.pdfLecture 12_Enterprise Resourse Planning.pdf
Lecture 12_Enterprise Resourse Planning.pdf
MaiLinh301193
 
Operations Management Material Requirements Planning (MRP)
Operations ManagementMaterial Requirements Planning (MRP)Operations ManagementMaterial Requirements Planning (MRP)
Operations Management Material Requirements Planning (MRP)Mostafa Ewees
 
Session 5
Session 5Session 5
Session 5thangv
 
Alcatel lucent planning optimization proposal presentation
Alcatel lucent planning optimization proposal   presentationAlcatel lucent planning optimization proposal   presentation
Alcatel lucent planning optimization proposal presentation
Lewis Wang
 
360_ch04
360_ch04360_ch04
360_ch04ryaekle
 
Heizer om10 ch13
Heizer om10 ch13Heizer om10 ch13
Heizer om10 ch13ryaekle
 
ERP Key Success Factors Series 2
ERP Key Success Factors Series 2ERP Key Success Factors Series 2
ERP Key Success Factors Series 2
velcomerp
 
QCC - QIC Presentation, Mission Possible Team
QCC - QIC Presentation, Mission Possible TeamQCC - QIC Presentation, Mission Possible Team
QCC - QIC Presentation, Mission Possible Team
Arief M Ridwan
 
Does APO Really Work? - An APO Case Study
Does APO Really Work? - An APO Case StudyDoes APO Really Work? - An APO Case Study
Does APO Really Work? - An APO Case Study
President Stephen Crane Consulting, LLC
 
Heizer om10 ch07
Heizer om10 ch07Heizer om10 ch07
Heizer om10 ch07ryaekle
 
Mba ii pmom_unit-2.4 aggregate planning a
Mba ii pmom_unit-2.4 aggregate planning aMba ii pmom_unit-2.4 aggregate planning a
Mba ii pmom_unit-2.4 aggregate planning a
Rai University
 
Sales and capacity planning ppt @ doms
Sales and capacity planning ppt @ domsSales and capacity planning ppt @ doms
Sales and capacity planning ppt @ doms
Babasab Patil
 
Material Requirement Planning (MRP)
Material Requirement Planning (MRP)Material Requirement Planning (MRP)
Material Requirement Planning (MRP)
Konok Mondal
 
Building a Credible Performance Measurement Baseline (v3)
Building a Credible Performance Measurement Baseline (v3)Building a Credible Performance Measurement Baseline (v3)
Building a Credible Performance Measurement Baseline (v3)
Glen Alleman
 

Similar to Heizer om10 ch14 (20)

Heizer om10 ch14
Heizer om10 ch14Heizer om10 ch14
Heizer om10 ch14
 
heizer_om12_ch014 final (1).pptx
heizer_om12_ch014 final (1).pptxheizer_om12_ch014 final (1).pptx
heizer_om12_ch014 final (1).pptx
 
Heizer 14
Heizer 14Heizer 14
Heizer 14
 
Material requirements planning & erp ppt @ bec doms
Material requirements planning & erp  ppt @ bec domsMaterial requirements planning & erp  ppt @ bec doms
Material requirements planning & erp ppt @ bec doms
 
Fred Duchow Resume 2015
Fred Duchow Resume 2015Fred Duchow Resume 2015
Fred Duchow Resume 2015
 
Lecture 12_Enterprise Resourse Planning.pdf
Lecture 12_Enterprise Resourse Planning.pdfLecture 12_Enterprise Resourse Planning.pdf
Lecture 12_Enterprise Resourse Planning.pdf
 
Operations Management Material Requirements Planning (MRP)
Operations ManagementMaterial Requirements Planning (MRP)Operations ManagementMaterial Requirements Planning (MRP)
Operations Management Material Requirements Planning (MRP)
 
Session 5
Session 5Session 5
Session 5
 
Chapter 5_OM
Chapter 5_OMChapter 5_OM
Chapter 5_OM
 
Alcatel lucent planning optimization proposal presentation
Alcatel lucent planning optimization proposal   presentationAlcatel lucent planning optimization proposal   presentation
Alcatel lucent planning optimization proposal presentation
 
360_ch04
360_ch04360_ch04
360_ch04
 
Heizer om10 ch13
Heizer om10 ch13Heizer om10 ch13
Heizer om10 ch13
 
ERP Key Success Factors Series 2
ERP Key Success Factors Series 2ERP Key Success Factors Series 2
ERP Key Success Factors Series 2
 
QCC - QIC Presentation, Mission Possible Team
QCC - QIC Presentation, Mission Possible TeamQCC - QIC Presentation, Mission Possible Team
QCC - QIC Presentation, Mission Possible Team
 
Does APO Really Work? - An APO Case Study
Does APO Really Work? - An APO Case StudyDoes APO Really Work? - An APO Case Study
Does APO Really Work? - An APO Case Study
 
Heizer om10 ch07
Heizer om10 ch07Heizer om10 ch07
Heizer om10 ch07
 
Mba ii pmom_unit-2.4 aggregate planning a
Mba ii pmom_unit-2.4 aggregate planning aMba ii pmom_unit-2.4 aggregate planning a
Mba ii pmom_unit-2.4 aggregate planning a
 
Sales and capacity planning ppt @ doms
Sales and capacity planning ppt @ domsSales and capacity planning ppt @ doms
Sales and capacity planning ppt @ doms
 
Material Requirement Planning (MRP)
Material Requirement Planning (MRP)Material Requirement Planning (MRP)
Material Requirement Planning (MRP)
 
Building a Credible Performance Measurement Baseline (v3)
Building a Credible Performance Measurement Baseline (v3)Building a Credible Performance Measurement Baseline (v3)
Building a Credible Performance Measurement Baseline (v3)
 

Recently uploaded

ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
SupreethSP4
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 

Recently uploaded (20)

ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 

Heizer om10 ch14

  • 1. © 2011 Pearson 14 - 1 14 Material Requirements Planning (MRP) and ERP PowerPoint presentation to accompanyPowerPoint presentation to accompany Heizer and RenderHeizer and Render Operations Management, 10eOperations Management, 10e Principles of Operations Management, 8ePrinciples of Operations Management, 8e PowerPoint slides by Jeff Heyl
  • 2. © 2011 Pearson 14 - 2 OutlineOutline  Global Company Profile: Wheeled Coach  Dependent Demand  Dependent Inventory Model Requirements  Master Production Schedule  Bills of Material  Accurate Inventory Records  Purchase Orders Outstanding  Lead Times for Components
  • 3. © 2011 Pearson 14 - 3 Outline – ContinuedOutline – Continued  MRP Structure  MRP Management  MRP Dynamics  MRP and JIT  Lot-Sizing Techniques
  • 4. © 2011 Pearson 14 - 4 Outline – ContinuedOutline – Continued  Extensions of MRP  Material Requirements Planning II (MRP II)  Closed-Loop MRP  Capacity Planning  MRP In Services  Distribution Resource Planning (DRP)
  • 5. © 2011 Pearson 14 - 5 Outline – ContinuedOutline – Continued  Enterprise Resource Planning (ERP)  Advantages and Disadvantages of ERP Systems  ERP in the Service Sector
  • 6. © 2011 Pearson 14 - 6 Learning ObjectivesLearning Objectives When you complete this chapter youWhen you complete this chapter you should be able to:should be able to: 1. Develop a product structure 2. Build a gross requirements plan 3. Build a net requirements plan 4. Determine lot sizes for lot-for-lot, EOQ, and PPB
  • 7. © 2011 Pearson 14 - 7 Learning ObjectivesLearning Objectives When you complete this chapter youWhen you complete this chapter you should be able to:should be able to: 5. Describe MRP II 6. Describe closed-loop MRP 7. Describe ERP
  • 8. © 2011 Pearson 14 - 8 Wheeled CoachWheeled Coach  Largest manufacturer of ambulances in the world  International competitor  12 major ambulance designs  18,000 different inventory items  6,000 manufactured parts  12,000 purchased parts
  • 9. © 2011 Pearson 14 - 9 Wheeled CoachWheeled Coach  Four Key Tasks  Material plan must meet both the requirements of the master schedule and the capabilities of the production facility  Plan must be executed as designed  Minimize inventory investment  Maintain excellent record integrity
  • 10. © 2011 Pearson 14 - 10 Dependent DemandDependent Demand For any product for which a scheduleFor any product for which a schedule can be established, dependentcan be established, dependent demand techniques should be useddemand techniques should be used
  • 11. © 2011 Pearson 14 - 11 Dependent DemandDependent Demand Benefits of MRP 1. Better response to customer orders 2. Faster response to market changes 3. Improved utilization of facilities and labor 4. Reduced inventory levels
  • 12. © 2011 Pearson 14 - 12 Dependent DemandDependent Demand  The demand for one item is related to the demand for another item  Given a quantity for the end item, the demand for all parts and components can be calculated  In general, used whenever a schedule can be established for an item  MRP is the common technique
  • 13. © 2011 Pearson 14 - 13 Dependent DemandDependent Demand 1. Master production schedule 2. Specifications or bill of material 3. Inventory availability 4. Purchase orders outstanding 5. Lead times Effective use of dependent demand inventory models requires the following
  • 14. © 2011 Pearson 14 - 14 Master Production ScheduleMaster Production Schedule (MPS)(MPS)  Specifies what is to be made and when  Must be in accordance with the aggregate production plan  Inputs from financial plans, customer demand, engineering, supplier performance  As the process moves from planning to execution, each step must be tested for feasibility  The MPS is the result of the production planning process
  • 15. © 2011 Pearson 14 - 15 Master Production ScheduleMaster Production Schedule (MPS)(MPS)  MPS is established in terms of specific products  Schedule must be followed for a reasonable length of time  The MPS is quite often fixed or frozen in the near term part of the plan  The MPS is a rolling schedule  The MPS is a statement of what is to be produced, not a forecast of demand
  • 16. © 2011 Pearson 14 - 16 Figure 14.1 Change production plan?Master production schedule Management Return on investment Capital Engineering Design completion Aggregate production plan Procurement Supplier performance Human resources Manpower planning Production Capacity Inventory Marketing Customer demand Finance Cash flow The Planning ProcessThe Planning Process
  • 17. © 2011 Pearson 14 - 17 The Planning ProcessThe Planning Process Figure 14.1 Is capacity plan being met? Is execution meeting the plan? Change master production schedule? Change capacity? Change requirements? No Execute material plans Execute capacity plans Yes Realistic? Capacity requirements plan Material requirements plan Master production schedule
  • 18. © 2011 Pearson 14 - 18 AggregateAggregate Production PlanProduction Plan Months January February Aggregate Production Plan 1,500 1,200 (Shows the total quantity of amplifiers) Weeks 1 2 3 4 5 6 7 8 Master Production Schedule (Shows the specific type and quantity of amplifier to be produced 240-watt amplifier 100 100 100 100 150-watt amplifier 500 500 450 450 75-watt amplifier 300 100 Figure 14.2
  • 19. © 2011 Pearson 14 - 19 Master Production ScheduleMaster Production Schedule (MPS)(MPS) 1. A customer order in a job shop (make- to-order) company 2. Modules in a repetitive (assemble-to- order or forecast) company 3. An end item in a continuous (stock-to- forecast) company Can be expressed in any of the following terms:
  • 20. © 2011 Pearson 14 - 20 Focus for DifferentFocus for Different Process StrategiesProcess Strategies Stock to Forecast (Product Focus) Schedule finished product Assemble to Order or Forecast (Repetitive) Schedule modules Make to Order (Process Focus) Schedule orders Examples: Print shop Motorcycles Steel, Beer, Bread Machine shop Autos, TVs Lightbulbs Fine-dining restaurant Fast-food restaurant Paper Typical focus of the master production schedule Number of inputs Number of end items Figure 14.3
  • 21. © 2011 Pearson 14 - 21 MPS ExamplesMPS Examples Gross Requirements for Crabmeat Quiche Gross Requirements for Spinach Quiche Day 6 7 8 9 10 11 12 13 14 and so on Amount 50 100 47 60 110 75 Day 7 8 9 10 11 12 13 14 15 16 and so on Amount 100 200 150 60 75 100 Table 14.1 For Nancy’s Specialty Foods
  • 22. © 2011 Pearson 14 - 22 Bills of MaterialBills of Material  List of components, ingredients, and materials needed to make product  Provides product structure  Items above given level are called parents  Items below given level are called children
  • 23. © 2011 Pearson 14 - 23 BOM ExampleBOM Example B(2) Std. 12” Speaker kit C(3) Std. 12” Speaker kit w/ amp-booster1 E(2)E(2) F(2) Packing box and installation kit of wire, bolts, and screws Std. 12” Speaker booster assembly 2 D(2) 12” Speaker D(2) 12” Speaker G(1) Amp-booster 3 Product structure for “Awesome” (A) A Level 0
  • 24. © 2011 Pearson 14 - 24 BOM ExampleBOM Example B(2) Std. 12” Speaker kit C(3) Std. 12” Speaker kit w/ amp-booster1 E(2)E(2) F(2) Packing box and installation kit of wire, bolts, and screws Std. 12” Speaker booster assembly 2 D(2) 12” Speaker D(2) 12” Speaker G(1) Amp-booster 3 Product structure for “Awesome” (A) A Level 0 Part B: 2 x number of As = (2)(50) = 100 Part C: 3 x number of As = (3)(50) = 150 Part D: 2 x number of Bs + 2 x number of Fs = (2)(100) + (2)(300) = 800 Part E: 2 x number of Bs + 2 x number of Cs = (2)(100) + (2)(150) = 500 Part F: 2 x number of Cs = (2)(150) = 300 Part G: 1 x number of Fs = (1)(300) = 300
  • 25. © 2011 Pearson 14 - 25 Bills of MaterialBills of Material  Modular Bills  Modules are not final products but components that can be assembled into multiple end items  Can significantly simplify planning and scheduling
  • 26. © 2011 Pearson 14 - 26 Bills of MaterialBills of Material  Planning Bills  Also called “pseudo” or super bills  Created to assign an artificial parent to the BOM  Used to group subassemblies to reduce the number of items planned and scheduled  Used to create standard “kits” for production
  • 27. © 2011 Pearson 14 - 27 Bills of MaterialBills of Material  Phantom Bills Describe subassemblies that exist only temporarily Are part of another assembly and never go into inventory  Low-Level Coding Item is coded at the lowest level at which it occurs BOMs are processed one level at a time
  • 28. © 2011 Pearson 14 - 28 Accurate RecordsAccurate Records  Accurate inventory records are absolutely required for MRP (or any dependent demand system) to operate correctly  Generally MRP systems require more than 99% accuracy  Outstanding purchase orders must accurately reflect quantities and scheduled receipts
  • 29. © 2011 Pearson 14 - 29 Lead TimesLead Times  The time required to purchase, produce, or assemble an item  For production – the sum of the order, wait, move, setup, store, and run times  For purchased items – the time between the recognition of a need and the availability of the item for production
  • 30. © 2011 Pearson 14 - 30 Time-Phased ProductTime-Phased Product StructureStructure | | | | | | | | 1 2 3 4 5 6 7 8 Time in weeks F 2 weeks 3 weeks 1 week A 2 weeks 1 week D E 2 weeks D G 1 week Start production of D Must have D and E completed here so production can begin on B Figure 14.4 1 week 2 weeks to produce B C E
  • 31. © 2011 Pearson 14 - 31 MRP StructureMRP Structure Figure 14.5 Output Reports MRP by period report MRP by date report Planned order report Purchase advice Exception reports Order early or late or not needed Order quantity too small or too large Data Files Purchasing data BOM Lead times (Item master file) Inventory data Master production schedule Material requirement planning programs (computer and software)
  • 32. © 2011 Pearson 14 - 32 Determining GrossDetermining Gross RequirementsRequirements  Starts with a production schedule for the end item – 50 units of Item A in week 8  Using the lead time for the item, determine the week in which the order should be released – a 1 week lead time means the order for 50 units should be released in week 7  This step is often called “lead time offset” or “time phasing”
  • 33. © 2011 Pearson 14 - 33 Determining GrossDetermining Gross RequirementsRequirements  From the BOM, every Item A requires 2 Item Bs – 100 Item Bs are required in week 7 to satisfy the order release for Item A  The lead time for the Item B is 2 weeks – release an order for 100 units of Item B in week 5  The timing and quantity for component requirements are determined by the order release of the parent(s)
  • 34. © 2011 Pearson 14 - 34 Determining GrossDetermining Gross RequirementsRequirements  The process continues through the entire BOM one level at a time – often called “explosion”  By processing the BOM by level, items with multiple parents are only processed once, saving time and resources and reducing confusion  Low-level coding ensures that each item appears at only one level in the BOM
  • 35. © 2011 Pearson 14 - 35 Gross Requirements PlanGross Requirements Plan Table 14.3 Week 1 2 3 4 5 6 7 8 Lead Time A. Required date 50 Order release date 50 1 week B. Required date 100 Order release date 100 2 weeks C. Required date 150 Order release date 150 1 week E. Required date 200 300 Order release date 200 300 2 weeks F. Required date 300 Order release date 300 3 weeks D. Required date 600 200 Order release date 600 200 1 week G. Required date 300 Order release date 300 2 weeks
  • 36. © 2011 Pearson 14 - 36 Net Requirements PlanNet Requirements Plan
  • 37. © 2011 Pearson 14 - 37 Net Requirements PlanNet Requirements Plan
  • 38. © 2011 Pearson 14 - 38 Determining NetDetermining Net RequirementsRequirements  Starts with a production schedule for the end item – 50 units of Item A in week 8  Because there are 10 Item As on hand, only 40 are actually required – (net requirement) = (gross requirement - on- hand inventory)  The planned order receipt for Item A in week 8 is 40 units – 40 = 50 - 10
  • 39. © 2011 Pearson 14 - 39 Determining NetDetermining Net RequirementsRequirements  Following the lead time offset procedure, the planned order release for Item A is now 40 units in week 7  The gross requirement for Item B is now 80 units in week 7  There are 15 units of Item B on hand, so the net requirement is 65 units in week 7  A planned order receipt of 65 units in week 7 generates a planned order release of 65 units in week 5
  • 40. © 2011 Pearson 14 - 40 Determining NetDetermining Net RequirementsRequirements  A planned order receipt of 65 units in week 7 generates a planned order release of 65 units in week 5  The on-hand inventory record for Item B is updated to reflect the use of the 15 items in inventory and shows no on-hand inventory in week 8  This is referred to as the Gross-to-Net calculation and is the third basic function of the MRP process
  • 41. © 2011 Pearson 14 - 41 S B C 12 138 9 10 11 20 3040 Lead time = 6 for S Master schedule for S Gross RequirementsGross Requirements ScheduleSchedule Figure 14.6 1 2 3 10 10 Master schedule for B sold directly Periods Therefore, these are the gross requirements for B Gross requirements: B 10 40 50 2040+10 15+30 =50 =45 1 2 3 4 5 6 7 8Periods A B C Lead time = 4 for A Master schedule for A 5 6 7 8 9 10 11 40 1550
  • 42. © 2011 Pearson 14 - 42 Net Requirements PlanNet Requirements Plan The logic of net requirementsThe logic of net requirements Available inventory Net requirements On hand Scheduled receipts+– = Total requirements Gross requirements Allocations+
  • 43. © 2011 Pearson 14 - 43 MRP Planning SheetMRP Planning Sheet Figure 14.7
  • 44. © 2011 Pearson 14 - 44 Safety StockSafety Stock  BOMs, inventory records, purchase and production quantities may not be perfect  Consideration of safety stock may be prudent  Should be minimized and ultimately eliminated  Typically built into projected on-hand inventory
  • 45. © 2011 Pearson 14 - 45 MRP ManagementMRP Management  MRP is a dynamic system  Facilitates replanning when changes occur  Regenerating  Net change  System nervousness can result from too many changes  Time fences put limits on replanning  Pegging links each item to its parent allowing effective analysis of changes
  • 46. © 2011 Pearson 14 - 46 MRP and JITMRP and JIT  MRP is a planning system that does not do detailed scheduling  MRP requires fixed lead times which might actually vary with batch size  JIT excels at rapidly moving small batches of material through the system
  • 47. © 2011 Pearson 14 - 47 Finite Capacity SchedulingFinite Capacity Scheduling  MRP systems do not consider capacity during normal planning cycles  Finite capacity scheduling (FCS) recognizes actual capacity limits  By merging MRP and FCS, a finite schedule is created with feasible capacities which facilitates rapid material movement
  • 48. © 2011 Pearson 14 - 48 Small Bucket ApproachSmall Bucket Approach 1. MRP “buckets” are reduced to daily or hourly 2. Planned receipts are used internally to sequence production 3. Inventory is moved through the plant on a JIT basis 4. Completed products are moved to finished goods inventory which reduces required quantities for subsequent planned orders 5. Back flushing based on the BOM is used to deduct inventory that was used in production
  • 49. © 2011 Pearson 14 - 49 Balanced FlowBalanced Flow  Used in repetitive operations  MRP plans are executed using JIT techniques based on “pull” principles  Flows are carefully balanced with small lot sizes
  • 50. © 2011 Pearson 14 - 50 SupermarketSupermarket  Items used by many products are held in a common area often called a supermarket  Items are withdrawn as needed  Inventory is maintained using JIT systems and procedures  Common items are not planned by the MRP system
  • 51. © 2011 Pearson 14 - 51 Lot-Sizing TechniquesLot-Sizing Techniques  Lot-for-lot techniques order just what is required for production based on net requirements  May not always be feasible  If setup costs are high, lot-for-lot can be expensive  Economic order quantity (EOQ)  EOQ expects a known constant demand and MRP systems often deal with unknown and variable demand
  • 52. © 2011 Pearson 14 - 52 Lot-Sizing TechniquesLot-Sizing Techniques  Part Period Balancing (PPB) looks at future orders to determine most economic lot size  The Wagner-Whitin algorithm is a complex dynamic programming technique  Assumes a finite time horizon  Effective, but computationally burdensome
  • 53. © 2011 Pearson 14 - 53 Lot-for-Lot ExampleLot-for-Lot Example 1 2 3 4 5 6 7 8 9 10 Gross requirements 35 30 40 0 10 40 30 0 30 55 Scheduled receipts Projected on hand 35 35 0 0 0 0 0 0 0 0 0 Net requirements 0 30 40 0 10 40 30 0 30 55 Planned order receipts 30 40 10 40 30 30 55 Planned order releases 30 40 10 40 30 30 55 Holding cost = $1/week; Setup cost = $100; Lead time = 1 week
  • 54. © 2011 Pearson 14 - 54 Lot-for-Lot ExampleLot-for-Lot Example 1 2 3 4 5 6 7 8 9 10 Gross requirements 35 30 40 0 10 40 30 0 30 55 Scheduled receipts Projected on hand 35 35 0 0 0 0 0 0 0 0 0 Net requirements 0 30 40 0 10 40 30 0 30 55 Planned order receipts 30 40 10 40 30 30 55 Planned order releases 30 40 10 40 30 30 55 Holding cost = $1/week; Setup cost = $100; Lead time = 1 week No on-hand inventory is carried through the system Total holding cost = $0 There are seven setups for this item in this plan Total ordering cost = 7 x $100 = $700
  • 55. © 2011 Pearson 14 - 55 EOQ Lot Size ExampleEOQ Lot Size Example 1 2 3 4 5 6 7 8 9 10 Gross requirements 35 30 40 0 10 40 30 0 30 55 Scheduled receipts Projected on hand 35 35 0 43 3 3 66 26 69 69 39 Net requirements 0 30 0 0 7 0 4 0 0 16 Planned order receipts 73 73 73 73 Planned order releases 73 73 73 73 Holding cost = $1/week; Setup cost = $100; Lead time = 1 week Average weekly gross requirements = 27; EOQ = 73 units
  • 56. © 2011 Pearson 14 - 56 EOQ Lot Size ExampleEOQ Lot Size Example 1 2 3 4 5 6 7 8 9 10 Gross requirements 35 30 40 0 10 40 30 0 30 55 Scheduled receipts Projected on hand 35 35 0 0 0 0 0 0 0 0 0 Net requirements 0 30 0 0 7 0 4 0 0 16 Planned order receipts 73 73 73 73 Planned order releases 73 73 73 73 Holding cost = $1/week; Setup cost = $100; Lead time = 1 week Average weekly gross requirements = 27; EOQ = 73 units Annual demand = 1,404 Total cost = setup cost + holding cost Total cost = (1,404/73) x $100 + (73/2) x ($1 x 52 weeks) Total cost = $3,798 Cost for 10 weeks = $3,798 x (10 weeks/52 weeks) = $730
  • 57. © 2011 Pearson 14 - 57 PPB ExamplePPB Example 1 2 3 4 5 6 7 8 9 10 Gross requirements 35 30 40 0 10 40 30 0 30 55 Scheduled receipts Projected on hand 35 Net requirements Planned order receipts Planned order releases Holding cost = $1/week; Setup cost = $100; Lead time = 1 week EPP = 100 units
  • 58. © 2011 Pearson 14 - 58 PPB ExamplePPB Example 1 2 3 4 5 6 7 8 9 10 Gross requirements 35 30 40 0 10 40 30 0 30 55 Scheduled receipts Projected on hand 35 Net requirements Planned order receipts Planned order releases Holding cost = $1/week; Setup cost = $100; EPP = 100 units 2 30 0 2, 3 70 40 = 40 x 1 2, 3, 4 70 40 2, 3, 4, 5 80 70 = 40 x 1 + 10 x 3 100 70 170 2, 3, 4, 5, 6 120 230 = 40 x 1 + 10 x 3 + 40 x 4 + = Combine periods 2 - 5 as this results in the Part Period closest to the EPP Combine periods 6 - 9 as this results in the Part Period closest to the EPP 6 40 0 6, 7 70 30 = 30 x 1 6, 7, 8 70 30 = 30 x 1 + 0 x 2 6, 7, 8, 9 100 120 = 30 x 1 + 30 x 3 100 120 220+ = 10 55 0 100 0 100 Total cost 300 190 490 + = + = Trial Lot Size Periods (cumulative net Costs Combined requirements) Part Periods Setup Holding Total
  • 59. © 2011 Pearson 14 - 59 PPB ExamplePPB Example 1 2 3 4 5 6 7 8 9 10 Gross requirements 35 30 40 0 10 40 30 0 30 55 Scheduled receipts Projected on hand 35 35 0 50 10 10 0 60 30 30 0 Net requirements 0 30 0 0 0 40 0 0 0 55 Planned order receipts 80 100 55 Planned order releases 80 100 55 Holding cost = $1/week; Setup cost = $100; Lead time = 1 week EPP = 100 units
  • 60. © 2011 Pearson 14 - 60 Lot-Sizing SummaryLot-Sizing Summary For these three examples Lot-for-lot $700 EOQ $730 PPB $490 Wagner-Whitin would have yielded a plan with a total cost of $455
  • 61. © 2011 Pearson 14 - 61 Lot-Sizing SummaryLot-Sizing Summary  In theory, lot sizes should be recomputed whenever there is a lot size or order quantity change  In practice, this results in system nervousness and instability  Lot-for-lot should be used when low-cost JIT can be achieved
  • 62. © 2011 Pearson 14 - 62 Lot-Sizing SummaryLot-Sizing Summary  Lot sizes can be modified to allow for scrap, process constraints, and purchase lots  Use lot-sizing with care as it can cause considerable distortion of requirements at lower levels of the BOM  When setup costs are significant and demand is reasonably smooth, PPB, Wagner-Whitin, or EOQ should give reasonable results
  • 63. © 2011 Pearson 14 - 63 Extensions of MRPExtensions of MRP  MRP II  Closed-Loop MRP  MRP system provides input to the capacity plan, MPS, and production planning process  Capacity Planning  MRP system generates a load report which details capacity requirements  This is used to drive the capacity planning process  Changes pass back through the MRP system for rescheduling
  • 64. © 2011 Pearson 14 - 64 Material RequirementsMaterial Requirements Planning IIPlanning II  Requirement data can be enriched by other resources  Generally called MRP II or Material Resource Planning  Outputs include  Scrap  Packaging waste  Carbon emissions  Data used by purchasing, production scheduling, capacity planning, inventory
  • 65. © 2011 Pearson 14 - 65 Material Resource PlanningMaterial Resource Planning Weeks LT 5 6 7 8 Computer 1 100 Labor Hrs: .2 each 20 Machine Hrs: .2 each 20 Scrap: 1 ounce fiberglass each 6.25 lbs Payables: $0 each $0 PC Board (1 each) 2 100 Labor Hrs: .15 each 15 Machine Hrs: .1 each 10 Scrap: .5 ounces copper each 3.125 lb Payables: raw material at $5 each $500 Processor (5 each) 4 500 Labor Hrs: .2 each 100 Machine Hrs: .2 each 100 Scrap: .01 ounces of acid waste each 0.3125 lb Payables: processors at $10 each $5,000 Table 14.4
  • 66. © 2011 Pearson 14 - 66 Closed-Loop MRP SystemClosed-Loop MRP System Figure 14.8 Priority Management Develop Master Production Schedule Prepare Materials Requirements Pan Detailed Production Activity Control (Shop Scheduling/Dispatching) Capacity Management Evaluate Resource Availability (Rough Cut) Determine Capacity Availability Implement Input/Output Control Aggregate Production Plan OK?OK? NONO OK?OK? NONO OK? YESOK? YES OK? YESOK? YES Planning Execution (in repetitive systems JIT techniques are used)
  • 67. © 2011 Pearson 14 - 67 Capacity PlanningCapacity Planning  Feedback from the MRP system  Load reports show resource requirements for work centers  Work can be moved between work centers to smooth the load or bring it within capacity
  • 68. © 2011 Pearson 14 - 68 Smoothing TacticsSmoothing Tactics 1. Overlapping  Sends part of the work to following operations before the entire lot is complete  Reduces lead time 2. Operations splitting  Sends the lot to two different machines for the same operation  Shorter throughput time but increased setup costs 3. Order or lot splitting  Breaking up the order into smaller lots and running part earlier (or later) in the schedule
  • 69. © 2011 Pearson 14 - 69 Order SplittingOrder Splitting  Develop a capacity plan for a work cell at Wiz Products  There are 12 hours available each day  Each order requires 1 hour Day 1 2 3 4 5 Orders 10 14 13 10 14
  • 70. © 2011 Pearson 14 - 70 Order SplittingOrder Splitting Day Units Ordered Capacity Required (hours) Capacity Available (hours) Utilization: Over/ (Under) (hours) Production Planner’s Action New Production Schedule 1 10 10 12 (2) 12 2 14 14 12 2 Split order: move 2 units to day 1 12 3 13 13 12 1 Split order: move one unit to day 6 or request overtime 13 4 10 10 12 (2) 12 5 14 14 12 2 Split order: move 2 units to day 4 12 61
  • 71. © 2011 Pearson 14 - 71 Order SplittingOrder Splitting Figure 14.9 Available capacity Capacity exceeded on days 2, 3, and 5 2 orders moved to day 1 from day 2 (a day early) 1 order forced to overtime or to day 6 2 orders moved to day 4 (a day early) 14 – 12 – 10 – 8 – 6 – 4 – 2 – 0 – 1 2 3 4 5 Days (b) Standardlabor-Hours 14 – 12 – 10 – 8 – 6 – 4 – 2 – 0 – 1 2 3 4 5 Days (a) Standardlabor-Hours
  • 72. © 2011 Pearson 14 - 72 MRP in ServicesMRP in Services  Some services or service items are directly linked to demand for other services  These can be treated as dependent demand services or items  Restaurants  Hospitals  Hotels
  • 73. © 2011 Pearson 14 - 73 Uncooked linguini #30004 Sauce #30006 Veal #30005 MRP in ServicesMRP in Services Chef; Work Center #1 Helper one; Work Center #2 Asst. Chef; Work Center #3 Cooked linguini #20002 Spinach #20004 Prepared veal and sauce #20003 (a) PRODUCT STRUCTURE TREE Veal picante #10001 Figure 14.10
  • 74. © 2011 Pearson 14 - 74 MRP in ServicesMRP in Services (b) BILL OF MATERIALS Part Number Description Quantity Unit of Measure Unit cost 10001 Veal picante 1 Serving — 20002 Cooked linguini 1 Serving — 20003 Prepared veal and sauce 1 Serving — 20004 Spinach 0.1 Bag 0.94 30004 Uncooked linguini 0.5 Pound — 30005 Veal 1 Serving 2.15 30006 Sauce 1 Serving 0.80
  • 75. © 2011 Pearson 14 - 75 MRP in ServicesMRP in Services (c) BILL OF LABOR FOR VEAL PICANTE Labor Hours Work Center Operation Labor Type Setup Time Run Time 1 Assemble dish Chef .0069 .0041 2 Cook linguini Helper one .0005 .0022 3 Cook veal and sauce Assistant Chef .0125 .0500
  • 76. © 2011 Pearson 14 - 76 Distribution ResourceDistribution Resource Planning (DRP)Planning (DRP) Using dependent demand techniques through the supply chain  Expected demand or sales forecasts become gross requirements  Minimum levels of inventory to meet customer service levels  Accurate lead times  Definition of the distribution structure
  • 77. © 2011 Pearson 14 - 77 Enterprise ResourceEnterprise Resource Planning (ERP)Planning (ERP)  An extension of the MRP system to tie in customers and suppliers  Allows automation and integration of many business processes  Shares common data bases and business practices  Produces information in real time  Coordinates business from supplier evaluation to customer invoicing
  • 78. © 2011 Pearson 14 - 78 Enterprise ResourceEnterprise Resource Planning (ERP)Planning (ERP)  ERP modules include  Basic MRP  Finance  Human resources  Supply chain management (SCM)  Customer relationship management (CRM)
  • 79. © 2011 Pearson 14 - 79 ERP and MRPERP and MRP Figure 14.11
  • 80. © 2011 Pearson 14 - 80 ERP and MRPERP and MRP Figure 14.11 Customer Relationship Management Invoicing Shipping Distributors, retailers, and end users Sales Order (order entry, product configuration, sales management)
  • 81. © 2011 Pearson 14 - 81 Table 13.6 Bills of Material Work Orders Purchasing and Lead Times Routings and Lead Times Master Production Schedule Inventory Management ERP and MRPERP and MRP Figure 14.11 MRP
  • 82. © 2011 Pearson 14 - 82 ERP and MRPERP and MRP Figure 14.11 Supply Chain Management Vendor Communication (schedules, EDI, advanced shipping notice, e-commerce, etc.)
  • 83. © 2011 Pearson 14 - 83 ERP and MRPERP and MRP Figure 14.11Table 13.6 Finance/ Accounting General Ledger Accounts Receivable Payroll Accounts Payable
  • 84. © 2011 Pearson 14 - 84 Enterprise ResourceEnterprise Resource Planning (ERP)Planning (ERP)  ERP can be highly customized to meet specific business requirements  Enterprise application integration software (EAI) allows ERP systems to be integrated with  Warehouse management  Logistics  Electronic catalogs  Quality management
  • 85. © 2011 Pearson 14 - 85 Enterprise ResourceEnterprise Resource Planning (ERP)Planning (ERP)  ERP systems have the potential to  Reduce transaction costs  Increase the speed and accuracy of information  Facilitates a strategic emphasis on JIT systems and integration
  • 86. © 2011 Pearson 14 - 86 SAP’s ERP ModulesSAP’s ERP Modules Figure 14.12
  • 87. © 2011 Pearson 14 - 87 Advantages of ERPAdvantages of ERP SystemsSystems 1. Provides integration of the supply chain, production, and administration 2. Creates commonality of databases 3. Can incorporate improved best processes 4. Increases communication and collaboration between business units and sites 5. Has an off-the-shelf software database 6. May provide a strategic advantage
  • 88. © 2011 Pearson 14 - 88 Disadvantages of ERPDisadvantages of ERP SystemsSystems 1. Is very expensive to purchase and even more so to customize 2. Implementation may require major changes in the company and its processes 3. Is so complex that many companies cannot adjust to it 4. Involves an ongoing, possibly never completed, process for implementation 5. Expertise is limited with ongoing staffing problems
  • 89. © 2011 Pearson 14 - 89 ERP in the Service SectorERP in the Service Sector  ERP systems have been developed for health care, government, retail stores, hotels, and financial services  Also called efficient consumer response (ECR) systems  Objective is to tie sales to buying, inventory, logistics, and production
  • 90. © 2011 Pearson 14 - 90 All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any form or by any means, electronic, mechanical, photocopying, recording, or otherwise, without the prior written permission of the publisher. Printed in the United States of America.

Editor's Notes

  1. <number>
  2. <number>
  3. <number>
  4. <number>
  5. <number>
  6. <number>
  7. <number>
  8. <number>
  9. <number>
  10. <number>
  11. <number>
  12. <number>
  13. <number>
  14. <number>
  15. <number>
  16. <number>
  17. <number>
  18. <number>
  19. <number>
  20. <number>
  21. <number>
  22. <number>
  23. <number>
  24. <number>
  25. <number>
  26. <number>
  27. <number>
  28. <number>
  29. <number>
  30. <number>
  31. <number>
  32. <number>
  33. <number>
  34. <number>
  35. <number>
  36. <number>
  37. <number>
  38. <number>
  39. <number>
  40. <number>
  41. <number>
  42. <number>
  43. <number>
  44. <number>
  45. <number>
  46. <number>
  47. <number>
  48. <number>
  49. <number>
  50. <number>
  51. <number>
  52. <number>
  53. <number>
  54. <number>
  55. <number>
  56. <number>
  57. <number>
  58. <number>
  59. <number>
  60. <number>
  61. <number>
  62. <number>
  63. <number>
  64. <number>
  65. <number>
  66. <number>
  67. <number>
  68. <number>
  69. <number>
  70. <number>