The project completion date was estimated to be November 13th but after leveling work it was delayed to November 21st, increasing the duration to 130 days from 127. The total cost was $943,480 with $844,980 being labor costs and $98,500 for capital costs like workstations. The critical paths included tasks in the software development phase like coding, unit testing, and integration which were at high risk of not being completed on time due to the number of resources allocated and lack of prior experience with the required technologies.