SlideShare a Scribd company logo
1 of 3
Download to read offline
December 13, 2011


Hanford Waste Treatment Plant completes concrete design
                  for largest facility
MEDIA CONTACTS:
Suzanne Heaston, Bechtel National, Inc., (509) 371-2329
Carrie Meyer, Department of Energy, (509) 372-0810

   Richland, Wash. -- The Hanford Waste Treatment Plant Project, also known as the
“Vit Plant,” recently issued the final design detailing the structural concrete for the
Pretreatment Facility. The final drawing represents the completion of the facility’s
concrete floors and results from more than 15,000 pages of calculations and 500 other
drawings. These calculations and drawings provide the details that enable crews to
construct the massive concrete structure.
   “Completing the structural concrete design for the Pretreatment Facility--the largest
Vit Plant facility--is the culmination of more than 500 Vit Plant engineers’ and designers’
working over several years,” Tom Patterson, manager of engineering at the Vit Plant,
said. “It is an important milestone that enables us to fully support the Vit Plant’s
construction schedule.”
   The Pretreatment Facility structural concrete design includes calculations and
drawings that are upheld to the highest nuclear safety and quality standards. Every inch
of concrete design--wall or floor--underwent extensive review to ensure it met all
regulations and requirements.
   When complete, the Pretreatment Facility will be composed of 113,000 cubic yards of
concrete and approximately 20,000 tons of steel. It will include five concrete floor
elevations, which start at ground level and extend to 98 feet above ground. A single
concrete floor ranges from 1 to 8 feet thick and spans 40 to 50 feet, depending on its
location within the facility.
   Each floor is reinforced with a complex rebar grid, composed of more than one-inch-
thick rebar. Many of the floors are also supported by structural steel.
   “Thanks to the hard work of the Vit Plant engineers and designers, design of the
Pretreatment Facility is more than 75 percent complete, and we are steadily progressing
toward Vit Plant construction complete in 2016, commissioning in 2019 and full
operations in 2022,” Wahed Abdul, federal area project manager, said.
   The Pretreatment Facility walls will reach a total height of 109 feet when finished.
Steel columns and roof trusses will extend beyond the walls to an overall height of 120
feet, and the emissions stack will reach nearly 200 feet.

                                       (continued)
The Pretreatment Facility is the largest Vit Plant facility and will include five concrete
floor elevations. It will reach a total height of 109 feet when finished. Steel columns and
roof trusses will extend beyond the walls to an overall height of 120 feet, and the
emissions stack will reach nearly 200 feet. (Photo 1 of 2)




When complete, the Pretreatment Facility will be composed of 113,000 cubic yards of
concrete and more than 20,700 tons of steel. (Photo 2 of 2)

   Bechtel National, Inc. is designing and building the world’s largest radioactive waste
treatment plant for the U.S. Department of Energy at the Hanford Site in southeastern
Washington state. The $12.2 billion Waste Treatment and Immobilization Plant, also
known as the “Vit Plant,” will immobilize the radioactive liquid waste currently stored in
177 underground tanks using a process called “vitrification.”

                                        (continued)
Vitrification involves blending the waste with molten glass and heating it to high
temperatures. The mixture is then poured into stainless steel canisters. In this glass form,
the waste is stable and impervious to the environment, and its radioactivity will dissipate
over hundreds to thousands of years.
   The Vit Plant will cover 65 acres with four nuclear facilities -- Pretreatment,
Low-Activity Waste Vitrification, High-Level Waste Vitrification and Analytical
Laboratory -- as well as operations and maintenance buildings, utilities and office space.
   Construction of the Vit Plant began in 2001 and is more than 60 percent complete.
The project is scheduled to complete construction in 2016; will reach commissioning in
2019 and achieve full operations in 2022.

NR11-25                                       ###

More Related Content

What's hot

Csir -STRUCTURAL ENGINEERING RESEARCH CENTRE (SERC) CHENNAI,INDIA.
Csir -STRUCTURAL ENGINEERING RESEARCH CENTRE (SERC) CHENNAI,INDIA.Csir -STRUCTURAL ENGINEERING RESEARCH CENTRE (SERC) CHENNAI,INDIA.
Csir -STRUCTURAL ENGINEERING RESEARCH CENTRE (SERC) CHENNAI,INDIA.kyru ega
 
I.a.fletcher c.v. may 2016
I.a.fletcher c.v.  may 2016I.a.fletcher c.v.  may 2016
I.a.fletcher c.v. may 2016ivan fletcher
 
Analyzing Double Skin Façades for Different Global Climate Regions
Analyzing Double Skin Façades for Different Global Climate RegionsAnalyzing Double Skin Façades for Different Global Climate Regions
Analyzing Double Skin Façades for Different Global Climate RegionsIES VE
 
Item #6 PPT 140 E Edgewood
Item #6   PPT 140 E EdgewoodItem #6   PPT 140 E Edgewood
Item #6 PPT 140 E Edgewoodahcitycouncil
 
Item # 7 PPT 224 W. Elmview
Item # 7 PPT 224 W. ElmviewItem # 7 PPT 224 W. Elmview
Item # 7 PPT 224 W. Elmviewahcitycouncil
 
Bringing Atlanta into Plain View
Bringing Atlanta into Plain ViewBringing Atlanta into Plain View
Bringing Atlanta into Plain ViewMcKenney's Inc
 
Mark Brock Project list
Mark Brock Project listMark Brock Project list
Mark Brock Project listMark Brock
 
223 Williams St ANCR Article
223 Williams St ANCR Article223 Williams St ANCR Article
223 Williams St ANCR ArticlePaul Saly
 
Rick Stinnett Projects
Rick Stinnett ProjectsRick Stinnett Projects
Rick Stinnett Projectsrstinnett
 
Where Does Recycled Scrap Metal Go?
Where Does Recycled Scrap Metal Go?Where Does Recycled Scrap Metal Go?
Where Does Recycled Scrap Metal Go?Elder Demolition
 
CCM 03.27.17 Item #6 212 Alamo Heights Blvd
CCM 03.27.17 Item #6  212 Alamo Heights BlvdCCM 03.27.17 Item #6  212 Alamo Heights Blvd
CCM 03.27.17 Item #6 212 Alamo Heights BlvdMarian Vargas Mendoza
 
EBS_CaseHistory_LakeshoreDrive
EBS_CaseHistory_LakeshoreDriveEBS_CaseHistory_LakeshoreDrive
EBS_CaseHistory_LakeshoreDriveBrian Huber
 
How Local Authorities can meet Net-Zero Carbon targets by 2030: Niall Gibson ...
How Local Authorities can meet Net-Zero Carbon targets by 2030: Niall Gibson ...How Local Authorities can meet Net-Zero Carbon targets by 2030: Niall Gibson ...
How Local Authorities can meet Net-Zero Carbon targets by 2030: Niall Gibson ...IES VE
 
Marie Reed School Construction Project Update (April 21, 2017)
Marie Reed School Construction Project Update (April 21, 2017)Marie Reed School Construction Project Update (April 21, 2017)
Marie Reed School Construction Project Update (April 21, 2017)DC Department of General Services
 

What's hot (20)

Csir -STRUCTURAL ENGINEERING RESEARCH CENTRE (SERC) CHENNAI,INDIA.
Csir -STRUCTURAL ENGINEERING RESEARCH CENTRE (SERC) CHENNAI,INDIA.Csir -STRUCTURAL ENGINEERING RESEARCH CENTRE (SERC) CHENNAI,INDIA.
Csir -STRUCTURAL ENGINEERING RESEARCH CENTRE (SERC) CHENNAI,INDIA.
 
I.a.fletcher c.v. may 2016
I.a.fletcher c.v.  may 2016I.a.fletcher c.v.  may 2016
I.a.fletcher c.v. may 2016
 
Analyzing Double Skin Façades for Different Global Climate Regions
Analyzing Double Skin Façades for Different Global Climate RegionsAnalyzing Double Skin Façades for Different Global Climate Regions
Analyzing Double Skin Façades for Different Global Climate Regions
 
Narrow Pavement Widening - San Angelo District
Narrow Pavement Widening - San Angelo DistrictNarrow Pavement Widening - San Angelo District
Narrow Pavement Widening - San Angelo District
 
Item #6 PPT 140 E Edgewood
Item #6   PPT 140 E EdgewoodItem #6   PPT 140 E Edgewood
Item #6 PPT 140 E Edgewood
 
Item # 7 PPT 224 W. Elmview
Item # 7 PPT 224 W. ElmviewItem # 7 PPT 224 W. Elmview
Item # 7 PPT 224 W. Elmview
 
russell resume
russell resumerussell resume
russell resume
 
Linkedin-Doc
Linkedin-DocLinkedin-Doc
Linkedin-Doc
 
Bringing Atlanta into Plain View
Bringing Atlanta into Plain ViewBringing Atlanta into Plain View
Bringing Atlanta into Plain View
 
Mark Brock Project list
Mark Brock Project listMark Brock Project list
Mark Brock Project list
 
Uniworld garden-2 up date
Uniworld garden-2 up dateUniworld garden-2 up date
Uniworld garden-2 up date
 
223 Williams St ANCR Article
223 Williams St ANCR Article223 Williams St ANCR Article
223 Williams St ANCR Article
 
Rick Stinnett Projects
Rick Stinnett ProjectsRick Stinnett Projects
Rick Stinnett Projects
 
Where Does Recycled Scrap Metal Go?
Where Does Recycled Scrap Metal Go?Where Does Recycled Scrap Metal Go?
Where Does Recycled Scrap Metal Go?
 
CCM 03.27.17 Item #6 212 Alamo Heights Blvd
CCM 03.27.17 Item #6  212 Alamo Heights BlvdCCM 03.27.17 Item #6  212 Alamo Heights Blvd
CCM 03.27.17 Item #6 212 Alamo Heights Blvd
 
EBS_CaseHistory_LakeshoreDrive
EBS_CaseHistory_LakeshoreDriveEBS_CaseHistory_LakeshoreDrive
EBS_CaseHistory_LakeshoreDrive
 
VECTOR APARTMENTS
VECTOR APARTMENTSVECTOR APARTMENTS
VECTOR APARTMENTS
 
How Local Authorities can meet Net-Zero Carbon targets by 2030: Niall Gibson ...
How Local Authorities can meet Net-Zero Carbon targets by 2030: Niall Gibson ...How Local Authorities can meet Net-Zero Carbon targets by 2030: Niall Gibson ...
How Local Authorities can meet Net-Zero Carbon targets by 2030: Niall Gibson ...
 
Marie Reed School Construction Project Update (April 21, 2017)
Marie Reed School Construction Project Update (April 21, 2017)Marie Reed School Construction Project Update (April 21, 2017)
Marie Reed School Construction Project Update (April 21, 2017)
 
AAMIR - PROFILE
AAMIR - PROFILEAAMIR - PROFILE
AAMIR - PROFILE
 

Viewers also liked

Bakheng mount
Bakheng mountBakheng mount
Bakheng mountLon Vong
 
Best presentation
Best presentationBest presentation
Best presentationChan Choi
 
Hanford Waste Treatment Plant completes fifth concrete wall elevation for lar...
Hanford Waste Treatment Plant completes fifth concrete wall elevation for lar...Hanford Waste Treatment Plant completes fifth concrete wall elevation for lar...
Hanford Waste Treatment Plant completes fifth concrete wall elevation for lar...DOE Office of River Protection
 
Hanford Waste Treatment Plant completes fifth concrete wall elevation for lar...
Hanford Waste Treatment Plant completes fifth concrete wall elevation for lar...Hanford Waste Treatment Plant completes fifth concrete wall elevation for lar...
Hanford Waste Treatment Plant completes fifth concrete wall elevation for lar...DOE Office of River Protection
 
Algumas Praças de Belo Horizonte
Algumas Praças de Belo HorizonteAlgumas Praças de Belo Horizonte
Algumas Praças de Belo HorizonteMarilene Terra
 
DOE submits safety culture plan to the Defense Nuclear Facilities Safety Board
DOE submits safety culture plan to the Defense Nuclear Facilities Safety BoardDOE submits safety culture plan to the Defense Nuclear Facilities Safety Board
DOE submits safety culture plan to the Defense Nuclear Facilities Safety BoardDOE Office of River Protection
 
Hanford Waste Treatment Plant receives and sets key air-filtration equipment ...
Hanford Waste Treatment Plant receives and sets key air-filtration equipment ...Hanford Waste Treatment Plant receives and sets key air-filtration equipment ...
Hanford Waste Treatment Plant receives and sets key air-filtration equipment ...DOE Office of River Protection
 
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...DOE Office of River Protection
 
Memory management for i os dev
Memory management for i os devMemory management for i os dev
Memory management for i os devAnton Krokhmalyuk
 

Viewers also liked (17)

Bakheng mount
Bakheng mountBakheng mount
Bakheng mount
 
Vamos contar
Vamos contarVamos contar
Vamos contar
 
Best presentation
Best presentationBest presentation
Best presentation
 
Hanford Waste Treatment Plant completes fifth concrete wall elevation for lar...
Hanford Waste Treatment Plant completes fifth concrete wall elevation for lar...Hanford Waste Treatment Plant completes fifth concrete wall elevation for lar...
Hanford Waste Treatment Plant completes fifth concrete wall elevation for lar...
 
Hanford Waste Treatment Plant completes fifth concrete wall elevation for lar...
Hanford Waste Treatment Plant completes fifth concrete wall elevation for lar...Hanford Waste Treatment Plant completes fifth concrete wall elevation for lar...
Hanford Waste Treatment Plant completes fifth concrete wall elevation for lar...
 
Algumas Praças de Belo Horizonte
Algumas Praças de Belo HorizonteAlgumas Praças de Belo Horizonte
Algumas Praças de Belo Horizonte
 
DOE submits safety culture plan to the Defense Nuclear Facilities Safety Board
DOE submits safety culture plan to the Defense Nuclear Facilities Safety BoardDOE submits safety culture plan to the Defense Nuclear Facilities Safety Board
DOE submits safety culture plan to the Defense Nuclear Facilities Safety Board
 
ORP 2011 Cleanup Caucus Presentation
ORP 2011 Cleanup Caucus PresentationORP 2011 Cleanup Caucus Presentation
ORP 2011 Cleanup Caucus Presentation
 
Hanford Waste Treatment Plant receives and sets key air-filtration equipment ...
Hanford Waste Treatment Plant receives and sets key air-filtration equipment ...Hanford Waste Treatment Plant receives and sets key air-filtration equipment ...
Hanford Waste Treatment Plant receives and sets key air-filtration equipment ...
 
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...
 
IHS McCloskey Nuclear business
IHS McCloskey Nuclear businessIHS McCloskey Nuclear business
IHS McCloskey Nuclear business
 
Objective-c memory
Objective-c memoryObjective-c memory
Objective-c memory
 
ADCSpb 4. PostPC World
ADCSpb 4. PostPC WorldADCSpb 4. PostPC World
ADCSpb 4. PostPC World
 
Cocos2D
Cocos2DCocos2D
Cocos2D
 
Escola antigamente
Escola antigamenteEscola antigamente
Escola antigamente
 
Crime
CrimeCrime
Crime
 
Memory management for i os dev
Memory management for i os devMemory management for i os dev
Memory management for i os dev
 

Similar to Hanford Waste Treatment Plant completes concrete design for largest facility

74 77 global project focus EPC Age magazine 2008
74 77 global project focus EPC Age magazine 200874 77 global project focus EPC Age magazine 2008
74 77 global project focus EPC Age magazine 2008Remona Divekar
 
Christian AKL CV-typ.DOC
Christian AKL CV-typ.DOCChristian AKL CV-typ.DOC
Christian AKL CV-typ.DOCChristian Akl
 
Christian akl cv typ
Christian akl cv typChristian akl cv typ
Christian akl cv typChristian Akl
 
Christian akl cv typ
Christian akl cv typChristian akl cv typ
Christian akl cv typChristian Akl
 
CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1Dan Caouette
 
Eric Buck resume 2017
Eric Buck resume 2017Eric Buck resume 2017
Eric Buck resume 2017Eric Buck
 
HansonOverview
HansonOverviewHansonOverview
HansonOverviewPeggy Burt
 
Waste Treatment & Immobilization Plant Project
Waste Treatment & Immobilization Plant ProjectWaste Treatment & Immobilization Plant Project
Waste Treatment & Immobilization Plant Projecthaysqaammudlwp
 
State of the Art and Practice Geotechnical Design
State of the Art and Practice Geotechnical DesignState of the Art and Practice Geotechnical Design
State of the Art and Practice Geotechnical DesignDr Mazin Alhamrany
 
Seminar on capital gate building
Seminar on capital gate buildingSeminar on capital gate building
Seminar on capital gate buildingNayan Rao
 
Dana Farber Yawkey Center for Cancer Care wins ACEC Silver
Dana Farber Yawkey Center for Cancer Care wins ACEC SilverDana Farber Yawkey Center for Cancer Care wins ACEC Silver
Dana Farber Yawkey Center for Cancer Care wins ACEC SilverWilliam Wieners
 

Similar to Hanford Waste Treatment Plant completes concrete design for largest facility (20)

8_SakhalinReleaseENR
8_SakhalinReleaseENR8_SakhalinReleaseENR
8_SakhalinReleaseENR
 
072014_Bunker Mentality
072014_Bunker Mentality072014_Bunker Mentality
072014_Bunker Mentality
 
74 77 global project focus EPC Age magazine 2008
74 77 global project focus EPC Age magazine 200874 77 global project focus EPC Age magazine 2008
74 77 global project focus EPC Age magazine 2008
 
Christian AKL CV-typ.DOC
Christian AKL CV-typ.DOCChristian AKL CV-typ.DOC
Christian AKL CV-typ.DOC
 
Christian akl cv typ
Christian akl cv typChristian akl cv typ
Christian akl cv typ
 
Christian akl cv typ
Christian akl cv typChristian akl cv typ
Christian akl cv typ
 
CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1
 
Eric Buck resume 2017
Eric Buck resume 2017Eric Buck resume 2017
Eric Buck resume 2017
 
HansonOverview
HansonOverviewHansonOverview
HansonOverview
 
Eschenburg Resume 1
Eschenburg  Resume 1Eschenburg  Resume 1
Eschenburg Resume 1
 
Waste Treatment & Immobilization Plant Project
Waste Treatment & Immobilization Plant ProjectWaste Treatment & Immobilization Plant Project
Waste Treatment & Immobilization Plant Project
 
Burj al arab
Burj al arabBurj al arab
Burj al arab
 
State of the Art and Practice Geotechnical Design
State of the Art and Practice Geotechnical DesignState of the Art and Practice Geotechnical Design
State of the Art and Practice Geotechnical Design
 
RCS Project Profiles
RCS Project ProfilesRCS Project Profiles
RCS Project Profiles
 
Seminar on capital gate building
Seminar on capital gate buildingSeminar on capital gate building
Seminar on capital gate building
 
Dana Farber Yawkey Center for Cancer Care wins ACEC Silver
Dana Farber Yawkey Center for Cancer Care wins ACEC SilverDana Farber Yawkey Center for Cancer Care wins ACEC Silver
Dana Farber Yawkey Center for Cancer Care wins ACEC Silver
 
Final_Capstone_2016
Final_Capstone_2016Final_Capstone_2016
Final_Capstone_2016
 
Resume sol_2016
Resume sol_2016Resume sol_2016
Resume sol_2016
 
Resume_SOl_2016
Resume_SOl_2016Resume_SOl_2016
Resume_SOl_2016
 
Resume_SOl_2016
Resume_SOl_2016Resume_SOl_2016
Resume_SOl_2016
 

Recently uploaded

[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdfhans926745
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024The Digital Insurer
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘RTylerCroy
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking MenDelhi Call girls
 
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUnderstanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUK Journal
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsMaria Levchenko
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptxHampshireHUG
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerThousandEyes
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreternaman860154
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024The Digital Insurer
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationSafe Software
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxKatpro Technologies
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxMalak Abu Hammad
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsJoaquim Jorge
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationMichael W. Hawkins
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfsudhanshuwaghmare1
 
Advantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your BusinessAdvantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your BusinessPixlogix Infotech
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountPuma Security, LLC
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Drew Madelung
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc
 

Recently uploaded (20)

[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men
 
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUnderstanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreter
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptx
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and Myths
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 
Advantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your BusinessAdvantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your Business
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path Mount
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 

Hanford Waste Treatment Plant completes concrete design for largest facility

  • 1. December 13, 2011 Hanford Waste Treatment Plant completes concrete design for largest facility MEDIA CONTACTS: Suzanne Heaston, Bechtel National, Inc., (509) 371-2329 Carrie Meyer, Department of Energy, (509) 372-0810 Richland, Wash. -- The Hanford Waste Treatment Plant Project, also known as the “Vit Plant,” recently issued the final design detailing the structural concrete for the Pretreatment Facility. The final drawing represents the completion of the facility’s concrete floors and results from more than 15,000 pages of calculations and 500 other drawings. These calculations and drawings provide the details that enable crews to construct the massive concrete structure. “Completing the structural concrete design for the Pretreatment Facility--the largest Vit Plant facility--is the culmination of more than 500 Vit Plant engineers’ and designers’ working over several years,” Tom Patterson, manager of engineering at the Vit Plant, said. “It is an important milestone that enables us to fully support the Vit Plant’s construction schedule.” The Pretreatment Facility structural concrete design includes calculations and drawings that are upheld to the highest nuclear safety and quality standards. Every inch of concrete design--wall or floor--underwent extensive review to ensure it met all regulations and requirements. When complete, the Pretreatment Facility will be composed of 113,000 cubic yards of concrete and approximately 20,000 tons of steel. It will include five concrete floor elevations, which start at ground level and extend to 98 feet above ground. A single concrete floor ranges from 1 to 8 feet thick and spans 40 to 50 feet, depending on its location within the facility. Each floor is reinforced with a complex rebar grid, composed of more than one-inch- thick rebar. Many of the floors are also supported by structural steel. “Thanks to the hard work of the Vit Plant engineers and designers, design of the Pretreatment Facility is more than 75 percent complete, and we are steadily progressing toward Vit Plant construction complete in 2016, commissioning in 2019 and full operations in 2022,” Wahed Abdul, federal area project manager, said. The Pretreatment Facility walls will reach a total height of 109 feet when finished. Steel columns and roof trusses will extend beyond the walls to an overall height of 120 feet, and the emissions stack will reach nearly 200 feet. (continued)
  • 2. The Pretreatment Facility is the largest Vit Plant facility and will include five concrete floor elevations. It will reach a total height of 109 feet when finished. Steel columns and roof trusses will extend beyond the walls to an overall height of 120 feet, and the emissions stack will reach nearly 200 feet. (Photo 1 of 2) When complete, the Pretreatment Facility will be composed of 113,000 cubic yards of concrete and more than 20,700 tons of steel. (Photo 2 of 2) Bechtel National, Inc. is designing and building the world’s largest radioactive waste treatment plant for the U.S. Department of Energy at the Hanford Site in southeastern Washington state. The $12.2 billion Waste Treatment and Immobilization Plant, also known as the “Vit Plant,” will immobilize the radioactive liquid waste currently stored in 177 underground tanks using a process called “vitrification.” (continued)
  • 3. Vitrification involves blending the waste with molten glass and heating it to high temperatures. The mixture is then poured into stainless steel canisters. In this glass form, the waste is stable and impervious to the environment, and its radioactivity will dissipate over hundreds to thousands of years. The Vit Plant will cover 65 acres with four nuclear facilities -- Pretreatment, Low-Activity Waste Vitrification, High-Level Waste Vitrification and Analytical Laboratory -- as well as operations and maintenance buildings, utilities and office space. Construction of the Vit Plant began in 2001 and is more than 60 percent complete. The project is scheduled to complete construction in 2016; will reach commissioning in 2019 and achieve full operations in 2022. NR11-25 ###