Robert Eschenburg has over 30 years of experience in construction management in the petrochemical and petroleum industries. He has a B.S. in Construction Engineering Technology from Texas Tech University. His experience includes managing large capital projects as Site Construction Manager and executing projects on schedule and budget. Some of his representative assignments include managing module fabrication for an LNG project, overseeing horizontal and pre-commissioning contracts for a crude expansion project, and managing site construction for major plant expansions.
1. RESUME
Name: ROBERT L. ESCHENBURG
Title: Construction Manager
Education: B.S., 1981, Construction Engineering Technology
Texas Tech University
Mr. Eschenburg has more than 30 years construction management experience in the
petrochemical and petroleum refining industries. He has executed projects as Site
Construction Manager responsible for overall management of site engineering, procurement,
and construction.
Representative assignments include:
• Home Office Constructability and Interface Coordinator, Shell Independent Mobile
Modular Liquefaction System (iMMLS) Project, Houston, Texas. Responsibilities include
Constructability input during completion of Front End Engineering and Detailed Design.
Also during this time, served as Interface Coordinator. This involved managing flow of
information and questions between the selected LNG facility sites in Louisiana and
Canada, a Chinese module fabricator, major equipment vendors and engineering
disciplines. The Project was designed to provide a base LNG plant utilizing an “over the
road”, transportable module concept. All modules were designed around a 12’ x 12’ x
50’ “truckable” envelope. The project includes for over 115 modules, plus stand-alone
equipment. The sites provided storage and loading facilities and basic utilities.
Horizontal and Pre-commissioning Contracts – Construction Area Manager, Crude
Expansion Project, Motiva, Port Arthur, Texas. Responsibilities include daily
management and oversight of 10 Horizontal Subcontractors, with peak labor of 2,000
craft, working in nine units, both existing and new; managed a field non-manual staff of
16 superintendents, project controls, and contract administrators, supervising and
administering these contracts. The horizontal contractors installed insulation, heat
tracing, fireproofing, cooling towers, deluge system, smoke and fire detection, cathodic
protection, closed circuit TV, oil mist and railroad spurs. During the same period
directed close out operations for Pre-commissioning activities including: steam blows,
hydraulic bolt tensioning and torqueing, flushes, and punch list items enlisting over 1000
direct and indirect forces. Same contractor had over 3.4 million man hours without a
LTA. The overall Project construction effort ran four years, with manpower peaking over
14,000 men and 30 million workhours installing: 1400 miles of wire/cable, 336 miles of
pipe, 325,000 cubic yards of concrete and 40,000 tons of steel.
Module Yard JV Site Construction Manager, Crude Expansion Project, Motiva, Brewer,
Maine. Responsibilities included management, fabrication, and shipment of 51 Pipe
rack and Process Modules to Port Arthur, Texas. Module assembly in Brewer was part
of a 306 module Crude Expansion Project. Brewer assembled modules contained:
8,830 tons of structural steel, 180,000 linear feet of piping. Over 800,000 direct
workhours were expended, by the subcontractors, in structural, piping, instrumentation,
electrical, paint, insulation and heat tracing crafts. The largest module assembled was
120’ L x 36’ W x 62’ H and weighed 690 tons.
JACOBS
2. RESUME
ROBERT L. ESCHENBURG (2/4)
Area Coordinator, San Juan Methane Project, BP, Durango, Colorado. Responsibilities
included management and execution of multiple well sites in an overall 800 plus well
sites upstream project. Managing multiple local construction companies to coordinate
deliveries and installation of skid mounted separators, power units, tanks, piping,
electrical and instrumentation on well pads; challenging and successful implementation
of Jacobs enhanced safety culture on local contractors; continuous coordination efforts
between client, engineering, and vendor representatives to maintain cost and schedule
requirements.
Site Construction Turnaround Manager, FCC Reactor Replacement Project, ExxonMobil,
Beaumont, Texas. Responsibilities included management and execution of Turnaround
portion of an EPCM project. Turnaround scope involved removal of old, and installation
of new, field erected, FCC Reactor/Stripper, Riser, Transfer Lines, and Overhead Vapor
Line. In addition, coordinating and management of associated structural, piping,
electrical, instrumentation, paint, insulation, and scaffolding activities.
Site Construction Manager, Silane Plant Major Two Phase Expansion, MEMC,
Pasadena, Texas. Responsible for field construction activities; coordinated daily T&M
and lump sum activities of four main contractors installing 7,000 CY foundations, 1,700
tons of structural steel, 175,000 LF of pipe and 780,000 LF of cable and wire; peak
manpower exceeded 1,000 direct, indirect and staff; fast track project involving daily
coordination of corporate engineering, procurement and field construction activities;
recorded more that a million workhours without a recordable safety incident.
Construction Manager, Flue Gas Scrubber (FGS) and Gasoline Desulfurization Unit
(GDU) Projects, Valero, Houston, Texas. The FGS project focused on installation of a
Belco Scrubber Tower and Treatment System. The GDU project involved substantial
upgrades to the B-Feed, D-SHU, B-Compressor and FCC areas. This work was
scheduled and executed to support a plant wide shutdown; scope of work involved the
installation of 122 pieces of equipment, 57,000 LF of piping, 650 tons of structural steel
and 30,000 LF of cable tray and conduit; coordination of day-to-day activities of
operations, engineering and multiple construction subcontractors in an operating
refinery.
Also coordinated construction activities involved with the FCC Regenerator Vessel
Revamp. The head and 6 pairs of cyclones were replaced with 11 sets and an
additional 10’ shell and new head. This work included substantial additions and
deletions of structural, piping and I/E scope in the FCC unit; 12-month project.
Assistant Construction Manager, Co-Enzyme Q10 Pharmaceutical Project, Kaneka
Nutrients Limited, Pasadena, Texas. This was a grass root facility; filling roles as both
Site Construction Manager/Resident Engineer. Project involved installation of over
90,000 LF of piping and over 500 pieces of equipment; erection of three large buildings
including a 4-story Purification Building; coordinated day-to-day construction operations
and engineering activities with numerous subcontractors.
120213 JACOBS
3. RESUME
ROBERT L. ESCHENBURG (3/4)
Senior Resident Engineer, PMDI-Phoenix Project, Dow Chemical, Freeport, Texas.
Project was a grass root effort; field forces erected over 260,000 LF of piping, 4,300 tons
of structural steel and set over 500 pieces of equipment. Responsible for all site
engineering, survey, turnover and document control activities; coordinated all Requests
for Information (RFI) and Change Order (CO) development and tracking; managed and
coordinated staff for above mentioned disciplines; technical development of site
subcontractor bid packages.
Construction Advisor, FCC Reactor, PEMEX, Madera Refinery, Tampico, Mexico.
Provided construction sequence advice and schedule input to their Korean mechanical
contractor for the head and cyclone removal and replacement of their FCC Reactor.
Construction Advisor, Caspian to Mediterranean Sea Pipeline, BP. Provided
construction support and input to the analysis of an 1100 kilometer, 42-inch crude
pipeline project. This project included an export terminal and jetty, four pumping stations
and two intermediate pigging stations. The contract required six in-country reports
developed and submitted over the life of the 4-year project.
Site Construction Manager/Resident Engineer, BDP Project, Akzo-Nobel Chemicals,
Gallipolis Ferry, West Virginia. This was a chemical plant capital project. Field forces
expended over 121,000 workhours with one LTD; provided construction management of
subcontractors, coordinating an executing field engineering activities, schedule
development and maintenance, and interfacing with client representatives; directed field
portion of project constructability program; worked closely with company, Akzo and
subcontractor quality programs to promote and maintain quality focus.
Home Office Construction Coordinator, Robinson Optimization Project, Marathon-Ashland
Petroleum, Robinson, Illinois. Scope included an FCC and Gas Plant capital improvement
project; provided coordination between our engineering and MAP construction
management team; main scope of work involved the replacement of the existing reactor
with a new reactor; responsible for constructability process between client, engineering
and subcontractors; participated in detailed Front End Loading (FEL) development of
project scope; developed the major construction bid packages and schedules to ensure
compatibility between construction needs and engineering deliverables; served as
construction liaison between major equipment suppliers and MAP.
Site Construction Advisor, Major Polyethylene Unit Revamp, Resilin, Maracaibo,
Venezuela. Responsibilities included providing onsite construction advisory and
coordination for substantial mechanical modifications, upgrading an existing plant during
a five week outage. The revamp had over 80,000 field workhours expended. Major
milestones included setting numerous new vessels, adding a new head and ten foot
shell extension to the existing Stripper Column, and adding an aluminum blender and
associated transfer piping, blowers, etc.; directed improvements to safety program
significantly improving working conditions and reducing incident rates.
Home Office Construction Coordinator, Olefins Portion, TPPI Petrochemical Complex,
Tuban, West Java, Indonesia. This was a world class ethylene facility. Responsible for
120213 JACOBS
4. RESUME
ROBERT L. ESCHENBURG (4/4)
coordinating and optimizing engineering output to support field construction activities.
120213 JACOBS
5. RESUME
ROBERT L. ESCHENBURG (5/4)
Home Office Construction Advisor to FCC Division. Provided constructability input to
sequencing, construction, and erection methods; estimating and scheduling on Amoco
and Lyondell-CITGO projects.
Project Engineer, FCC Expansion Project, HESS Oil, St. Croix, USVI. Responsibilities
included managing and coordinating duties of field engineering staff during two year
construction of the Regenerator/Reactor Area, Wet Gas Scrubber, Ground Flare and
numerous pieces of equipment. This work was a portion of the grass root FCC Project.
Responsibilities included project scheduling, field design changes, coordinating
subcontractors, etc.
Employment History:
Jacobs 2008 – Date
Site Construction Manager
CDI Engineering Solutions 2004 – 2008
Site Construction Manager
Stone & Webster Engineering 2000 – 2004
Senior Resident Engineer
Stone & Webster Engineering 1996 – 2000
Resident Engineer
Chicago Bridge and Iron Company 1993 – 1996
Project Manager
Chicago Bridge and Iron Company 1989 - 1993
Project Engineer
Huitt – Zollars, Inc. 1986 – 1989
Project Engineer
Nagler, Pitt and Merritt, Inc. 1985 – 1986
Staff Engineer
ABC Coating, Inc. 1984 – 1985
Assistant Manager
Dennick and Harris Engineers 1983 – 1984
Staff Engineer
Chicago Bridge and Iron Company 1981 – 1983
Field Engineer
References:
120213 JACOBS