SlideShare a Scribd company logo
1 of 7
RESUME
Name: ROBERT L. ESCHENBURG
Title: Construction Manager
Education: B.S., 1981, Construction Engineering Technology
Texas Tech University
Mr. Eschenburg has more than 30 years construction management experience in the
petrochemical and petroleum refining industries. He has executed projects as Site
Construction Manager responsible for overall management of site engineering, procurement,
and construction.
Representative assignments include:
• Home Office Constructability and Interface Coordinator, Shell Independent Mobile
Modular Liquefaction System (iMMLS) Project, Houston, Texas. Responsibilities include
Constructability input during completion of Front End Engineering and Detailed Design.
Also during this time, served as Interface Coordinator. This involved managing flow of
information and questions between the selected LNG facility sites in Louisiana and
Canada, a Chinese module fabricator, major equipment vendors and engineering
disciplines. The Project was designed to provide a base LNG plant utilizing an “over the
road”, transportable module concept. All modules were designed around a 12’ x 12’ x
50’ “truckable” envelope. The project includes for over 115 modules, plus stand-alone
equipment. The sites provided storage and loading facilities and basic utilities.
 Horizontal and Pre-commissioning Contracts – Construction Area Manager, Crude
Expansion Project, Motiva, Port Arthur, Texas. Responsibilities include daily
management and oversight of 10 Horizontal Subcontractors, with peak labor of 2,000
craft, working in nine units, both existing and new; managed a field non-manual staff of
16 superintendents, project controls, and contract administrators, supervising and
administering these contracts. The horizontal contractors installed insulation, heat
tracing, fireproofing, cooling towers, deluge system, smoke and fire detection, cathodic
protection, closed circuit TV, oil mist and railroad spurs. During the same period
directed close out operations for Pre-commissioning activities including: steam blows,
hydraulic bolt tensioning and torqueing, flushes, and punch list items enlisting over 1000
direct and indirect forces. Same contractor had over 3.4 million man hours without a
LTA. The overall Project construction effort ran four years, with manpower peaking over
14,000 men and 30 million workhours installing: 1400 miles of wire/cable, 336 miles of
pipe, 325,000 cubic yards of concrete and 40,000 tons of steel.
 Module Yard JV Site Construction Manager, Crude Expansion Project, Motiva, Brewer,
Maine. Responsibilities included management, fabrication, and shipment of 51 Pipe
rack and Process Modules to Port Arthur, Texas. Module assembly in Brewer was part
of a 306 module Crude Expansion Project. Brewer assembled modules contained:
8,830 tons of structural steel, 180,000 linear feet of piping. Over 800,000 direct
workhours were expended, by the subcontractors, in structural, piping, instrumentation,
electrical, paint, insulation and heat tracing crafts. The largest module assembled was
120’ L x 36’ W x 62’ H and weighed 690 tons.
JACOBS
RESUME
ROBERT L. ESCHENBURG (2/4)
 Area Coordinator, San Juan Methane Project, BP, Durango, Colorado. Responsibilities
included management and execution of multiple well sites in an overall 800 plus well
sites upstream project. Managing multiple local construction companies to coordinate
deliveries and installation of skid mounted separators, power units, tanks, piping,
electrical and instrumentation on well pads; challenging and successful implementation
of Jacobs enhanced safety culture on local contractors; continuous coordination efforts
between client, engineering, and vendor representatives to maintain cost and schedule
requirements.
 Site Construction Turnaround Manager, FCC Reactor Replacement Project, ExxonMobil,
Beaumont, Texas. Responsibilities included management and execution of Turnaround
portion of an EPCM project. Turnaround scope involved removal of old, and installation
of new, field erected, FCC Reactor/Stripper, Riser, Transfer Lines, and Overhead Vapor
Line. In addition, coordinating and management of associated structural, piping,
electrical, instrumentation, paint, insulation, and scaffolding activities.
 Site Construction Manager, Silane Plant Major Two Phase Expansion, MEMC,
Pasadena, Texas. Responsible for field construction activities; coordinated daily T&M
and lump sum activities of four main contractors installing 7,000 CY foundations, 1,700
tons of structural steel, 175,000 LF of pipe and 780,000 LF of cable and wire; peak
manpower exceeded 1,000 direct, indirect and staff; fast track project involving daily
coordination of corporate engineering, procurement and field construction activities;
recorded more that a million workhours without a recordable safety incident.
 Construction Manager, Flue Gas Scrubber (FGS) and Gasoline Desulfurization Unit
(GDU) Projects, Valero, Houston, Texas. The FGS project focused on installation of a
Belco Scrubber Tower and Treatment System. The GDU project involved substantial
upgrades to the B-Feed, D-SHU, B-Compressor and FCC areas. This work was
scheduled and executed to support a plant wide shutdown; scope of work involved the
installation of 122 pieces of equipment, 57,000 LF of piping, 650 tons of structural steel
and 30,000 LF of cable tray and conduit; coordination of day-to-day activities of
operations, engineering and multiple construction subcontractors in an operating
refinery.
Also coordinated construction activities involved with the FCC Regenerator Vessel
Revamp. The head and 6 pairs of cyclones were replaced with 11 sets and an
additional 10’ shell and new head. This work included substantial additions and
deletions of structural, piping and I/E scope in the FCC unit; 12-month project.
 Assistant Construction Manager, Co-Enzyme Q10 Pharmaceutical Project, Kaneka
Nutrients Limited, Pasadena, Texas. This was a grass root facility; filling roles as both
Site Construction Manager/Resident Engineer. Project involved installation of over
90,000 LF of piping and over 500 pieces of equipment; erection of three large buildings
including a 4-story Purification Building; coordinated day-to-day construction operations
and engineering activities with numerous subcontractors.
120213 JACOBS
RESUME
ROBERT L. ESCHENBURG (3/4)
 Senior Resident Engineer, PMDI-Phoenix Project, Dow Chemical, Freeport, Texas.
Project was a grass root effort; field forces erected over 260,000 LF of piping, 4,300 tons
of structural steel and set over 500 pieces of equipment. Responsible for all site
engineering, survey, turnover and document control activities; coordinated all Requests
for Information (RFI) and Change Order (CO) development and tracking; managed and
coordinated staff for above mentioned disciplines; technical development of site
subcontractor bid packages.
 Construction Advisor, FCC Reactor, PEMEX, Madera Refinery, Tampico, Mexico.
Provided construction sequence advice and schedule input to their Korean mechanical
contractor for the head and cyclone removal and replacement of their FCC Reactor.
 Construction Advisor, Caspian to Mediterranean Sea Pipeline, BP. Provided
construction support and input to the analysis of an 1100 kilometer, 42-inch crude
pipeline project. This project included an export terminal and jetty, four pumping stations
and two intermediate pigging stations. The contract required six in-country reports
developed and submitted over the life of the 4-year project.
 Site Construction Manager/Resident Engineer, BDP Project, Akzo-Nobel Chemicals,
Gallipolis Ferry, West Virginia. This was a chemical plant capital project. Field forces
expended over 121,000 workhours with one LTD; provided construction management of
subcontractors, coordinating an executing field engineering activities, schedule
development and maintenance, and interfacing with client representatives; directed field
portion of project constructability program; worked closely with company, Akzo and
subcontractor quality programs to promote and maintain quality focus.
 Home Office Construction Coordinator, Robinson Optimization Project, Marathon-Ashland
Petroleum, Robinson, Illinois. Scope included an FCC and Gas Plant capital improvement
project; provided coordination between our engineering and MAP construction
management team; main scope of work involved the replacement of the existing reactor
with a new reactor; responsible for constructability process between client, engineering
and subcontractors; participated in detailed Front End Loading (FEL) development of
project scope; developed the major construction bid packages and schedules to ensure
compatibility between construction needs and engineering deliverables; served as
construction liaison between major equipment suppliers and MAP.
 Site Construction Advisor, Major Polyethylene Unit Revamp, Resilin, Maracaibo,
Venezuela. Responsibilities included providing onsite construction advisory and
coordination for substantial mechanical modifications, upgrading an existing plant during
a five week outage. The revamp had over 80,000 field workhours expended. Major
milestones included setting numerous new vessels, adding a new head and ten foot
shell extension to the existing Stripper Column, and adding an aluminum blender and
associated transfer piping, blowers, etc.; directed improvements to safety program
significantly improving working conditions and reducing incident rates.
 Home Office Construction Coordinator, Olefins Portion, TPPI Petrochemical Complex,
Tuban, West Java, Indonesia. This was a world class ethylene facility. Responsible for
120213 JACOBS
RESUME
ROBERT L. ESCHENBURG (4/4)
coordinating and optimizing engineering output to support field construction activities.
120213 JACOBS
RESUME
ROBERT L. ESCHENBURG (5/4)
 Home Office Construction Advisor to FCC Division. Provided constructability input to
sequencing, construction, and erection methods; estimating and scheduling on Amoco
and Lyondell-CITGO projects.
 Project Engineer, FCC Expansion Project, HESS Oil, St. Croix, USVI. Responsibilities
included managing and coordinating duties of field engineering staff during two year
construction of the Regenerator/Reactor Area, Wet Gas Scrubber, Ground Flare and
numerous pieces of equipment. This work was a portion of the grass root FCC Project.
Responsibilities included project scheduling, field design changes, coordinating
subcontractors, etc.
Employment History:
Jacobs 2008 – Date
Site Construction Manager
CDI Engineering Solutions 2004 – 2008
Site Construction Manager
Stone & Webster Engineering 2000 – 2004
Senior Resident Engineer
Stone & Webster Engineering 1996 – 2000
Resident Engineer
Chicago Bridge and Iron Company 1993 – 1996
Project Manager
Chicago Bridge and Iron Company 1989 - 1993
Project Engineer
Huitt – Zollars, Inc. 1986 – 1989
Project Engineer
Nagler, Pitt and Merritt, Inc. 1985 – 1986
Staff Engineer
ABC Coating, Inc. 1984 – 1985
Assistant Manager
Dennick and Harris Engineers 1983 – 1984
Staff Engineer
Chicago Bridge and Iron Company 1981 – 1983
Field Engineer
References:
120213 JACOBS
RESUME
ROBERT L. ESCHENBURG (6/4)
Available Upon Request
120213 JACOBS
RESUME
ROBERT L. ESCHENBURG (6/4)
Available Upon Request
120213 JACOBS

More Related Content

What's hot

What's hot (20)

Rusty Adkins Resume
Rusty Adkins ResumeRusty Adkins Resume
Rusty Adkins Resume
 
AMIR PIA_Resume_7-16
AMIR PIA_Resume_7-16AMIR PIA_Resume_7-16
AMIR PIA_Resume_7-16
 
SLFraley Resumeex 2015
SLFraley Resumeex 2015SLFraley Resumeex 2015
SLFraley Resumeex 2015
 
KDK RES 2016 Sunoco
KDK RES 2016 SunocoKDK RES 2016 Sunoco
KDK RES 2016 Sunoco
 
Resume_Bobby_Horan
Resume_Bobby_HoranResume_Bobby_Horan
Resume_Bobby_Horan
 
CLARK PE RESUME
CLARK PE RESUMECLARK PE RESUME
CLARK PE RESUME
 
Ahmad mousa cv consulting jun 2016 for linkedin
Ahmad mousa cv consulting jun 2016 for linkedinAhmad mousa cv consulting jun 2016 for linkedin
Ahmad mousa cv consulting jun 2016 for linkedin
 
Ahmad mousa project list
Ahmad mousa   project listAhmad mousa   project list
Ahmad mousa project list
 
Darrell Resume2014
Darrell Resume2014Darrell Resume2014
Darrell Resume2014
 
JUNDEE MAR TEJEDO
JUNDEE MAR TEJEDOJUNDEE MAR TEJEDO
JUNDEE MAR TEJEDO
 
G_Clifford_resume_Feb 15
G_Clifford_resume_Feb 15G_Clifford_resume_Feb 15
G_Clifford_resume_Feb 15
 
David's CV, 2017
David's CV, 2017David's CV, 2017
David's CV, 2017
 
CVAQ5
CVAQ5CVAQ5
CVAQ5
 
ENR MOUNTAIN STATES 2013 BEST PROJECTS AWARD
ENR MOUNTAIN STATES 2013 BEST PROJECTS AWARDENR MOUNTAIN STATES 2013 BEST PROJECTS AWARD
ENR MOUNTAIN STATES 2013 BEST PROJECTS AWARD
 
Cochran Resume June 2016
Cochran Resume June 2016Cochran Resume June 2016
Cochran Resume June 2016
 
number 1 Res 2013 Rod Taylor-2
number 1 Res 2013    Rod  Taylor-2number 1 Res 2013    Rod  Taylor-2
number 1 Res 2013 Rod Taylor-2
 
2016-07-28 Martin Jacobs
2016-07-28 Martin Jacobs2016-07-28 Martin Jacobs
2016-07-28 Martin Jacobs
 
INDIAZI CV
INDIAZI CVINDIAZI CV
INDIAZI CV
 
Ravi's CV
Ravi's CVRavi's CV
Ravi's CV
 
Epw Cv 2009
Epw Cv 2009Epw Cv 2009
Epw Cv 2009
 

Viewers also liked

WBE Nassau County Certificate
WBE Nassau County CertificateWBE Nassau County Certificate
WBE Nassau County CertificateBarbara Bendlin
 
Lety essay final project
Lety essay final projectLety essay final project
Lety essay final projectPerlaDelgado
 
Effect of Material Texture on fatigue crack growth and fracture toughness
Effect of Material Texture on fatigue crack growth and fracture toughnessEffect of Material Texture on fatigue crack growth and fracture toughness
Effect of Material Texture on fatigue crack growth and fracture toughnessSum K
 
Duas Palestras magicas para sua empresa
Duas Palestras magicas para sua empresaDuas Palestras magicas para sua empresa
Duas Palestras magicas para sua empresaAndré Hypolito
 
The Art of Teaching
The Art of TeachingThe Art of Teaching
The Art of TeachingPeter Bowles
 
4 6 industria_aeroespacial_motores
4 6 industria_aeroespacial_motores4 6 industria_aeroespacial_motores
4 6 industria_aeroespacial_motoresEdwin Serrano
 
WBE Suffolk County Certificate
WBE Suffolk County CertificateWBE Suffolk County Certificate
WBE Suffolk County CertificateBarbara Bendlin
 
Evidence about Social Work Outcomes from Cohort and Panel Studies
Evidence about Social Work Outcomes from Cohort and Panel StudiesEvidence about Social Work Outcomes from Cohort and Panel Studies
Evidence about Social Work Outcomes from Cohort and Panel StudiesBASPCAN
 
Planeacion español
Planeacion españolPlaneacion español
Planeacion españolPpyoung
 
Bienvenidos, estudiantes!
Bienvenidos, estudiantes!Bienvenidos, estudiantes!
Bienvenidos, estudiantes!Dany Barreno
 

Viewers also liked (20)

Talleres junio 2015
Talleres junio  2015Talleres junio  2015
Talleres junio 2015
 
Actividad 4. las nif
Actividad 4. las nifActividad 4. las nif
Actividad 4. las nif
 
WBE Nassau County Certificate
WBE Nassau County CertificateWBE Nassau County Certificate
WBE Nassau County Certificate
 
Lety essay final project
Lety essay final projectLety essay final project
Lety essay final project
 
Rejal shams
Rejal shamsRejal shams
Rejal shams
 
Resume_JeremyBelliston
Resume_JeremyBellistonResume_JeremyBelliston
Resume_JeremyBelliston
 
Effect of Material Texture on fatigue crack growth and fracture toughness
Effect of Material Texture on fatigue crack growth and fracture toughnessEffect of Material Texture on fatigue crack growth and fracture toughness
Effect of Material Texture on fatigue crack growth and fracture toughness
 
Duas Palestras magicas para sua empresa
Duas Palestras magicas para sua empresaDuas Palestras magicas para sua empresa
Duas Palestras magicas para sua empresa
 
The Art of Teaching
The Art of TeachingThe Art of Teaching
The Art of Teaching
 
4 6 industria_aeroespacial_motores
4 6 industria_aeroespacial_motores4 6 industria_aeroespacial_motores
4 6 industria_aeroespacial_motores
 
WBE Suffolk County Certificate
WBE Suffolk County CertificateWBE Suffolk County Certificate
WBE Suffolk County Certificate
 
Evidence about Social Work Outcomes from Cohort and Panel Studies
Evidence about Social Work Outcomes from Cohort and Panel StudiesEvidence about Social Work Outcomes from Cohort and Panel Studies
Evidence about Social Work Outcomes from Cohort and Panel Studies
 
Planeacion español
Planeacion españolPlaneacion español
Planeacion español
 
Parte final del sílabo
Parte final del sílaboParte final del sílabo
Parte final del sílabo
 
Resume_JeremyBelliston
Resume_JeremyBellistonResume_JeremyBelliston
Resume_JeremyBelliston
 
Bienvenidos, estudiantes!
Bienvenidos, estudiantes!Bienvenidos, estudiantes!
Bienvenidos, estudiantes!
 
Numbers 0 9_
Numbers 0 9_Numbers 0 9_
Numbers 0 9_
 
Diapositivas aida sarahi
Diapositivas aida sarahiDiapositivas aida sarahi
Diapositivas aida sarahi
 
01 ofdm intro
01 ofdm intro01 ofdm intro
01 ofdm intro
 
xxxxx
xxxxxxxxxx
xxxxx
 

Similar to Eschenburg Resume 1

Construction Manager Resume
Construction Manager ResumeConstruction Manager Resume
Construction Manager ResumeJack Dickerson
 
William Faoro - 4pResumeM1
William Faoro - 4pResumeM1William Faoro - 4pResumeM1
William Faoro - 4pResumeM1William Faoro PE
 
PaulR.Blaetz021816RR
PaulR.Blaetz021816RRPaulR.Blaetz021816RR
PaulR.Blaetz021816RRPaul Blaetz
 
Linkedin Summary
Linkedin SummaryLinkedin Summary
Linkedin SummaryIlyas Ahsan
 
Wicker, L.W. July 2016
Wicker, L.W. July 2016Wicker, L.W. July 2016
Wicker, L.W. July 2016Larry Wicker
 
Thomas Cleveland Resume'- June 20th 2015
Thomas Cleveland Resume'- June 20th 2015Thomas Cleveland Resume'- June 20th 2015
Thomas Cleveland Resume'- June 20th 2015Thomas Cleveland
 
Davis Gary 0415 PM-LIR
Davis Gary 0415 PM-LIRDavis Gary 0415 PM-LIR
Davis Gary 0415 PM-LIRGary Davis
 
Newby Resume 2015
Newby Resume 2015Newby Resume 2015
Newby Resume 2015Steve Newby
 
Kiper,_Malcolm_Resume_Current 6 1 2015
Kiper,_Malcolm_Resume_Current 6 1 2015Kiper,_Malcolm_Resume_Current 6 1 2015
Kiper,_Malcolm_Resume_Current 6 1 2015Malcolm Kiper
 
Bmartin_Resume_Feb_2015.GRNO
Bmartin_Resume_Feb_2015.GRNOBmartin_Resume_Feb_2015.GRNO
Bmartin_Resume_Feb_2015.GRNOBrent Martin
 
Current Public Resume
Current Public ResumeCurrent Public Resume
Current Public ResumeLee Riopel
 
Nikolai Tim (01-24-11) (3)
Nikolai Tim (01-24-11) (3)Nikolai Tim (01-24-11) (3)
Nikolai Tim (01-24-11) (3)Timothy Nikolai
 
Cover Letter & Resume
Cover Letter & ResumeCover Letter & Resume
Cover Letter & ResumeRichard Rask
 
Combine cover letter and resume
Combine cover letter and resumeCombine cover letter and resume
Combine cover letter and resumeRich St.Cyr
 

Similar to Eschenburg Resume 1 (20)

Construction Manager Resume
Construction Manager ResumeConstruction Manager Resume
Construction Manager Resume
 
Resume 3-16-15docx
Resume 3-16-15docxResume 3-16-15docx
Resume 3-16-15docx
 
William Faoro - 4pResumeM1
William Faoro - 4pResumeM1William Faoro - 4pResumeM1
William Faoro - 4pResumeM1
 
PaulR.Blaetz021816RR
PaulR.Blaetz021816RRPaulR.Blaetz021816RR
PaulR.Blaetz021816RR
 
Linkedin Summary
Linkedin SummaryLinkedin Summary
Linkedin Summary
 
chesbro resume
chesbro resumechesbro resume
chesbro resume
 
Wicker, L.W. July 2016
Wicker, L.W. July 2016Wicker, L.W. July 2016
Wicker, L.W. July 2016
 
Thomas Cleveland Resume'- June 20th 2015
Thomas Cleveland Resume'- June 20th 2015Thomas Cleveland Resume'- June 20th 2015
Thomas Cleveland Resume'- June 20th 2015
 
Davis Gary 0415 PM-LIR
Davis Gary 0415 PM-LIRDavis Gary 0415 PM-LIR
Davis Gary 0415 PM-LIR
 
JM Portfolio 04-2016
JM Portfolio 04-2016JM Portfolio 04-2016
JM Portfolio 04-2016
 
Jack Oldrin RS2
Jack Oldrin RS2Jack Oldrin RS2
Jack Oldrin RS2
 
Newby Resume 2015
Newby Resume 2015Newby Resume 2015
Newby Resume 2015
 
Kiper,_Malcolm_Resume_Current 6 1 2015
Kiper,_Malcolm_Resume_Current 6 1 2015Kiper,_Malcolm_Resume_Current 6 1 2015
Kiper,_Malcolm_Resume_Current 6 1 2015
 
Tringale Resume 9-2-14
Tringale Resume 9-2-14Tringale Resume 9-2-14
Tringale Resume 9-2-14
 
Bmartin_Resume_Feb_2015.GRNO
Bmartin_Resume_Feb_2015.GRNOBmartin_Resume_Feb_2015.GRNO
Bmartin_Resume_Feb_2015.GRNO
 
Current Public Resume
Current Public ResumeCurrent Public Resume
Current Public Resume
 
Nikolai Tim (01-24-11) (3)
Nikolai Tim (01-24-11) (3)Nikolai Tim (01-24-11) (3)
Nikolai Tim (01-24-11) (3)
 
Cover Letter & Resume
Cover Letter & ResumeCover Letter & Resume
Cover Letter & Resume
 
Long Resume
Long ResumeLong Resume
Long Resume
 
Combine cover letter and resume
Combine cover letter and resumeCombine cover letter and resume
Combine cover letter and resume
 

Eschenburg Resume 1

  • 1. RESUME Name: ROBERT L. ESCHENBURG Title: Construction Manager Education: B.S., 1981, Construction Engineering Technology Texas Tech University Mr. Eschenburg has more than 30 years construction management experience in the petrochemical and petroleum refining industries. He has executed projects as Site Construction Manager responsible for overall management of site engineering, procurement, and construction. Representative assignments include: • Home Office Constructability and Interface Coordinator, Shell Independent Mobile Modular Liquefaction System (iMMLS) Project, Houston, Texas. Responsibilities include Constructability input during completion of Front End Engineering and Detailed Design. Also during this time, served as Interface Coordinator. This involved managing flow of information and questions between the selected LNG facility sites in Louisiana and Canada, a Chinese module fabricator, major equipment vendors and engineering disciplines. The Project was designed to provide a base LNG plant utilizing an “over the road”, transportable module concept. All modules were designed around a 12’ x 12’ x 50’ “truckable” envelope. The project includes for over 115 modules, plus stand-alone equipment. The sites provided storage and loading facilities and basic utilities.  Horizontal and Pre-commissioning Contracts – Construction Area Manager, Crude Expansion Project, Motiva, Port Arthur, Texas. Responsibilities include daily management and oversight of 10 Horizontal Subcontractors, with peak labor of 2,000 craft, working in nine units, both existing and new; managed a field non-manual staff of 16 superintendents, project controls, and contract administrators, supervising and administering these contracts. The horizontal contractors installed insulation, heat tracing, fireproofing, cooling towers, deluge system, smoke and fire detection, cathodic protection, closed circuit TV, oil mist and railroad spurs. During the same period directed close out operations for Pre-commissioning activities including: steam blows, hydraulic bolt tensioning and torqueing, flushes, and punch list items enlisting over 1000 direct and indirect forces. Same contractor had over 3.4 million man hours without a LTA. The overall Project construction effort ran four years, with manpower peaking over 14,000 men and 30 million workhours installing: 1400 miles of wire/cable, 336 miles of pipe, 325,000 cubic yards of concrete and 40,000 tons of steel.  Module Yard JV Site Construction Manager, Crude Expansion Project, Motiva, Brewer, Maine. Responsibilities included management, fabrication, and shipment of 51 Pipe rack and Process Modules to Port Arthur, Texas. Module assembly in Brewer was part of a 306 module Crude Expansion Project. Brewer assembled modules contained: 8,830 tons of structural steel, 180,000 linear feet of piping. Over 800,000 direct workhours were expended, by the subcontractors, in structural, piping, instrumentation, electrical, paint, insulation and heat tracing crafts. The largest module assembled was 120’ L x 36’ W x 62’ H and weighed 690 tons. JACOBS
  • 2. RESUME ROBERT L. ESCHENBURG (2/4)  Area Coordinator, San Juan Methane Project, BP, Durango, Colorado. Responsibilities included management and execution of multiple well sites in an overall 800 plus well sites upstream project. Managing multiple local construction companies to coordinate deliveries and installation of skid mounted separators, power units, tanks, piping, electrical and instrumentation on well pads; challenging and successful implementation of Jacobs enhanced safety culture on local contractors; continuous coordination efforts between client, engineering, and vendor representatives to maintain cost and schedule requirements.  Site Construction Turnaround Manager, FCC Reactor Replacement Project, ExxonMobil, Beaumont, Texas. Responsibilities included management and execution of Turnaround portion of an EPCM project. Turnaround scope involved removal of old, and installation of new, field erected, FCC Reactor/Stripper, Riser, Transfer Lines, and Overhead Vapor Line. In addition, coordinating and management of associated structural, piping, electrical, instrumentation, paint, insulation, and scaffolding activities.  Site Construction Manager, Silane Plant Major Two Phase Expansion, MEMC, Pasadena, Texas. Responsible for field construction activities; coordinated daily T&M and lump sum activities of four main contractors installing 7,000 CY foundations, 1,700 tons of structural steel, 175,000 LF of pipe and 780,000 LF of cable and wire; peak manpower exceeded 1,000 direct, indirect and staff; fast track project involving daily coordination of corporate engineering, procurement and field construction activities; recorded more that a million workhours without a recordable safety incident.  Construction Manager, Flue Gas Scrubber (FGS) and Gasoline Desulfurization Unit (GDU) Projects, Valero, Houston, Texas. The FGS project focused on installation of a Belco Scrubber Tower and Treatment System. The GDU project involved substantial upgrades to the B-Feed, D-SHU, B-Compressor and FCC areas. This work was scheduled and executed to support a plant wide shutdown; scope of work involved the installation of 122 pieces of equipment, 57,000 LF of piping, 650 tons of structural steel and 30,000 LF of cable tray and conduit; coordination of day-to-day activities of operations, engineering and multiple construction subcontractors in an operating refinery. Also coordinated construction activities involved with the FCC Regenerator Vessel Revamp. The head and 6 pairs of cyclones were replaced with 11 sets and an additional 10’ shell and new head. This work included substantial additions and deletions of structural, piping and I/E scope in the FCC unit; 12-month project.  Assistant Construction Manager, Co-Enzyme Q10 Pharmaceutical Project, Kaneka Nutrients Limited, Pasadena, Texas. This was a grass root facility; filling roles as both Site Construction Manager/Resident Engineer. Project involved installation of over 90,000 LF of piping and over 500 pieces of equipment; erection of three large buildings including a 4-story Purification Building; coordinated day-to-day construction operations and engineering activities with numerous subcontractors. 120213 JACOBS
  • 3. RESUME ROBERT L. ESCHENBURG (3/4)  Senior Resident Engineer, PMDI-Phoenix Project, Dow Chemical, Freeport, Texas. Project was a grass root effort; field forces erected over 260,000 LF of piping, 4,300 tons of structural steel and set over 500 pieces of equipment. Responsible for all site engineering, survey, turnover and document control activities; coordinated all Requests for Information (RFI) and Change Order (CO) development and tracking; managed and coordinated staff for above mentioned disciplines; technical development of site subcontractor bid packages.  Construction Advisor, FCC Reactor, PEMEX, Madera Refinery, Tampico, Mexico. Provided construction sequence advice and schedule input to their Korean mechanical contractor for the head and cyclone removal and replacement of their FCC Reactor.  Construction Advisor, Caspian to Mediterranean Sea Pipeline, BP. Provided construction support and input to the analysis of an 1100 kilometer, 42-inch crude pipeline project. This project included an export terminal and jetty, four pumping stations and two intermediate pigging stations. The contract required six in-country reports developed and submitted over the life of the 4-year project.  Site Construction Manager/Resident Engineer, BDP Project, Akzo-Nobel Chemicals, Gallipolis Ferry, West Virginia. This was a chemical plant capital project. Field forces expended over 121,000 workhours with one LTD; provided construction management of subcontractors, coordinating an executing field engineering activities, schedule development and maintenance, and interfacing with client representatives; directed field portion of project constructability program; worked closely with company, Akzo and subcontractor quality programs to promote and maintain quality focus.  Home Office Construction Coordinator, Robinson Optimization Project, Marathon-Ashland Petroleum, Robinson, Illinois. Scope included an FCC and Gas Plant capital improvement project; provided coordination between our engineering and MAP construction management team; main scope of work involved the replacement of the existing reactor with a new reactor; responsible for constructability process between client, engineering and subcontractors; participated in detailed Front End Loading (FEL) development of project scope; developed the major construction bid packages and schedules to ensure compatibility between construction needs and engineering deliverables; served as construction liaison between major equipment suppliers and MAP.  Site Construction Advisor, Major Polyethylene Unit Revamp, Resilin, Maracaibo, Venezuela. Responsibilities included providing onsite construction advisory and coordination for substantial mechanical modifications, upgrading an existing plant during a five week outage. The revamp had over 80,000 field workhours expended. Major milestones included setting numerous new vessels, adding a new head and ten foot shell extension to the existing Stripper Column, and adding an aluminum blender and associated transfer piping, blowers, etc.; directed improvements to safety program significantly improving working conditions and reducing incident rates.  Home Office Construction Coordinator, Olefins Portion, TPPI Petrochemical Complex, Tuban, West Java, Indonesia. This was a world class ethylene facility. Responsible for 120213 JACOBS
  • 4. RESUME ROBERT L. ESCHENBURG (4/4) coordinating and optimizing engineering output to support field construction activities. 120213 JACOBS
  • 5. RESUME ROBERT L. ESCHENBURG (5/4)  Home Office Construction Advisor to FCC Division. Provided constructability input to sequencing, construction, and erection methods; estimating and scheduling on Amoco and Lyondell-CITGO projects.  Project Engineer, FCC Expansion Project, HESS Oil, St. Croix, USVI. Responsibilities included managing and coordinating duties of field engineering staff during two year construction of the Regenerator/Reactor Area, Wet Gas Scrubber, Ground Flare and numerous pieces of equipment. This work was a portion of the grass root FCC Project. Responsibilities included project scheduling, field design changes, coordinating subcontractors, etc. Employment History: Jacobs 2008 – Date Site Construction Manager CDI Engineering Solutions 2004 – 2008 Site Construction Manager Stone & Webster Engineering 2000 – 2004 Senior Resident Engineer Stone & Webster Engineering 1996 – 2000 Resident Engineer Chicago Bridge and Iron Company 1993 – 1996 Project Manager Chicago Bridge and Iron Company 1989 - 1993 Project Engineer Huitt – Zollars, Inc. 1986 – 1989 Project Engineer Nagler, Pitt and Merritt, Inc. 1985 – 1986 Staff Engineer ABC Coating, Inc. 1984 – 1985 Assistant Manager Dennick and Harris Engineers 1983 – 1984 Staff Engineer Chicago Bridge and Iron Company 1981 – 1983 Field Engineer References: 120213 JACOBS
  • 6. RESUME ROBERT L. ESCHENBURG (6/4) Available Upon Request 120213 JACOBS
  • 7. RESUME ROBERT L. ESCHENBURG (6/4) Available Upon Request 120213 JACOBS