SlideShare a Scribd company logo
1 of 4
Download to read offline
JULY 2014
Bunker
MENTALITY
A massive steel-framed bunker is the centerpiece of a new gas turbine testing facility.
BY HERMAN MILLER, TODD PHILLIPS AND RICKY DIXON
MITSUBISHI POWER SYSTEMS America (MPSA) is
turning up the heat on its turbine production.
Due to increased demand for its products and services across
the North American market, the company needed to increase
production of its key gas turbine parts, provide complete steam
turbine services and assemble advanced fuel-efficient gas tur-
bines for the gas and steam market. In response, it hired the joint
venture team of H.J. High Construction and Batson-Cook Con-
struction to design and build a new manufacturing and testing
facility near Savannah, Ga. Subsequently, The Austin Company
was hired to provide architectural design and engineering ser-
vices (Batson-Cook is one of Austin’s sister companies).
The 116-acre Machinery Works Premier Service and Man-
ufacturing Center—a comprehensive service and repair center
for gas turbines, steam turbines and generator rotors—was de-
signed and built in several phases over four years and includes
over 440,000 sq. ft of heavy industrial manufacturing facilities,
offices and a turbine balancing and testing facility referred to as
the Balance Bunker; the latter is one of only 12 such facilities
in the world.
The project phases included:
➤ Manufacturing Building – Bays 1 and 2 – 137,500 sq. ft
➤ Manufacturing Building – Bay 3 – 75,600 sq. ft
➤ Manufacturing Building – Bay 4 – 76,300 sq. ft
➤ Manufacturing Building – Bay 5 – 72,000 sq. ft
➤ Balance Bunker Vacuum Chamber – Turbine Balancing/
Testing Facility – 20,000 sq. ft
➤ Office Building – 31,700 sq. ft
➤ Office/Conference Center – 17,000 sq. ft
➤ Guardhouse and Maintenance Building – 10,000 sq. ft
Crane Considerations
The load demand of the multiple bridge cranes, along with
the overall building size, were the factors that drove the deci-
sion to use structural steel framing for this project; the build-
ings feature structural steel framework with 2-in. insulated
metal wall panels. Other types of structures, such as cast-in-
place concrete or precast concrete, were eliminated due to cost.
The manufacturing building required clear heights of over 70
ft and clear spans of up to 90 ft. Bay 2 has a 30-ton crane that
only operates in about 100 ft of the bay, and Bay 3 has two, 150-
ton cranes that run the entire length of the building; they were
designed to be used in tandem for a total lifting capacity of 250
tons. The load requirements in Bay 4 had the most significant
impact on the steel design. This bay is designed to have two 30-
ton cranes running on a lower runway along the entire length of
the building, and two 250-ton bridge cranes that are designed
to be used in tandem when loaded with a complete turbine as-
sembly (weighing a total of 450 tons). Bay 5 was designed for two
30-ton cranes and one 60-ton crane on an upper runway, and
nine 15-ton gantry cranes running on a lower track.
On average, each bay took ten months to construct. In order
to meet the tight timeline and help maintain this momentum, the
steel was fabricated in the order in which it was to be erected. Sev-
eral sequences of steel deliveries were scheduled so that no steel
sat on the ground for more than three days before it was installed.
All photos: The Austin Co. (except upper-left image on p. 27)
Nearly 6,100 tons of steel was used to complete the project, in-
cluding approximately 4,900 tons of wide-flange and 1,200 tons of
steel joists. The manufacturing building required more than 4,500
tons of steel while the Balance Bunker involved more than 1,500
tons, including 62 tons for the sole plates inside the chamber and 16
tons for the base plates for the drive equipment. In addition, nearly
45,000 cubic yards of concrete was cast on the project for equipment
foundations, large slab pours and the Balance Bunker. Coatings in-
cluded Sherwin-Williams Steel-Spec FHP Universal Primer; Finish
(B50WV8000 White) for all exposed steel and as a final coat; and
Carboline Carboguard 890 Cycloaliphatic Amine Epoxy for the inte-
rior of the Balance Bunker.
Repetitive Design
The design-build project used BIM and Tekla 3D modeling to sup-
port project team collaboration, and SteelFab, Inc., the fabricator, used a
Tekla 3D program that was imported into The Austin Company’s Auto-
Cad 3D Model to produce a complete 3D model for the manufacturing
building. In addition, Austin used AutoCad 3D for the Balance Bunker
to help review the structure with the owner and confirm that the build-
ing met its requirements.
➤
 Modern STEEL CONSTRUCTION
Nearly 6,100 tons of steel was used to complete the entire project.
The new facility includes more than 440,000 sq. ft of space spread
out over multiple phases.
➤
Herman Miller (herman.miller@
theaustin.com) is a supervisory
structural engineer with The Austin
Company, Todd Phillips (tphillips@
batson-cook.com) is a project
manager with Batson-Cook Company
and Ricky Dixon (rdixon@steelfab-
inc.com) is a vice president/project
manager with SteelFab, Inc.
➤
The balance bunker uses more than 1,500 tons of structural
steel, including 62 tons for the sole plates inside the chamber
and 16 tons for the base plates for the drive equipment.
➤
SteelFab, Inc.
The Tekla 3D model was reviewed
during meetings with the design team
as a visual aid to illustrate design issues
and to develop solutions. Overall, the
project did not involve complex ge-
ometry, but it did have a high degree
of repetitious framing. As subsequent
bays were released for construction,
the team was able to quickly build on
to the previous Tekla 3D model. The
team was able to copy elements from
similarly designed areas of the legacy
model, make the requisite modifica-
tions to conform to the current bays’
design—typically due to different
crane requirements—and quickly pro-
duce approval documents.
Having the previous bays’ model
information was also useful when co-
ordinating the connection of a new
bay to the existing structure. The
team was able to visualize the out-
come and avoid clashes and accessi-
bility issues that may have gone un-
noticed until erection commenced.
Critical Balance
One of the most critical compo-
nents of the overall project was the
Balance Bunker.This complex vacuum
chamber facility involved the design
and construction of 7-ft, 3-in.-thick
bunker walls consisting of steel fram-
ing and ½-in.-thick inner and outer
steel linear plates with a reinforced
concrete infill. An 8,000-hp electric
motor turns the 22-ft-diameter rotors
during balancing at speeds of 4,000
rpm, and a 400-ton, 3-ft, 6-in.-thick
steel frame door with reinforced con-
crete infill seals the Bunker during
testing. Railcars move the turbine ro-
tors from Bay 3 into the Balance Bun-
ker for testing. Following testing, the
rotors are then moved to Bays 4 and 5
for final assembly and finishing.
Blast design was a major consid-
eration for the Balance Bunker. The
thick concrete, steel plate-lined walls
of the Bunker protected the outside
area from the risk of projectiles that
could occur if there was a malfunction
JULY 2014
➤
The new facility sits on 116 acres.
➤
The manufacturing building has five bays in all.
On average, each bay took ten months to construct.
➤
JULY 2014
of the rotor during the testing and balancing operation. As such,
a stray part during testing would be contained within the Bun-
ker and not damage any of the surrounding building or endan-
ger anyone in the Bunker area.
The Bunker’s chamber is designed to maintain a near-abso-
lute vacuum during balancing and testing, which necessitated
that the thousands of feet of internal welds were designed and
tested to maintain an airtight seal. The Balance Bunker walls
are reinforced with two layers of #10 rebar at 6-in. vertical and
horizontal on each face, and the inner steel plates were fully
welded (and each millimeter of weld was vacuum tested). The
internal steel linear plating anchoring was designed to resist a
2,100 psf vacuum load and a thermal design load resulting from
a 100 °F rise in internal surface temperature during testing.
The massive Bunker door was developed to roll along a
hydraulic track, be pushed into place horizontally using hy-
draulic cylinders and vacuum-sealed with a specially designed,
bunker-sized rubber gasket. In addition, two stairways and a
railcar bridge leading into the Bunker were designed with hy-
draulic lifts to move out of the door’s way when closing. Due
to its mass, the door was built in sections and transported to
the jobsite to be installed piece by piece. The door was made
of ½-in.-thick steel plate and fully welded like the inner cham-
ber, then filled with concrete; it also had rebar installed at 6
in. on center.
Following more than four years of design and construc-
tion work, the MPSA facilities were successfully completed on
schedule and opened last summer. While the project involved
numerous challenges, including the many unique design as-
pects of the Balance Bunker, the team’s approach resulted in a
world-class facility that enables MPSA to provide high-quality
parts and services across the continent.  ■
Owner
Mitsubishi Power Systems America, Pooler, Ga.
Design-Build General Contractor
H.J. High Construction, Orlando, Fla., and 		
Batson-Cook Construction, Atlanta (joint venture)
Architect
The Austin Company, Cleveland, Ohio
Structural Engineer
The Austin Company (Balance Bunker and Manufacturing
Building foundations)
KingGuinn Associates, Charlotte, N.C. (Manufacturing
Building framing)
Steel Fabricator, Detailer and Erector
SteelFab, Inc., Charlotte (AISC Member/AISC Certified
Fabricator)
The manufacturing building required clear heights of over 70
ft and clear spans of up to 90 ft.
➤
➤
The turbine balancing and testing facility is referred to
as the Balance Bunker; there are only 12 such facilities
in the world.
➤
➤

More Related Content

What's hot

Application of Engineering Technology in Strengthening of RCC Frames Structures
Application of Engineering Technology in Strengthening of RCC Frames StructuresApplication of Engineering Technology in Strengthening of RCC Frames Structures
Application of Engineering Technology in Strengthening of RCC Frames StructuresSagar Acharya
 
High rise building case study
High rise building case study High rise building case study
High rise building case study VISHAKA BOTHRA
 
BTECHN PROJECT 2 Final report (GROUP)
BTECHN PROJECT 2 Final report (GROUP)BTECHN PROJECT 2 Final report (GROUP)
BTECHN PROJECT 2 Final report (GROUP)ong93
 
Aldar Headquarters Dubai
Aldar Headquarters DubaiAldar Headquarters Dubai
Aldar Headquarters DubaiNeha Rampuria
 
Petronas twin towers, taipei 101, burj al-arab
Petronas twin towers, taipei 101, burj al-arabPetronas twin towers, taipei 101, burj al-arab
Petronas twin towers, taipei 101, burj al-arabRajat Nainwal
 
The taipei 101 tower
The taipei 101 towerThe taipei 101 tower
The taipei 101 towersvrohith 9
 
One Museum Park West (Post-Tensioning case study)
One Museum Park West (Post-Tensioning case study)One Museum Park West (Post-Tensioning case study)
One Museum Park West (Post-Tensioning case study)AMSYSCO Inc.
 
Linkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian GnysinskiLinkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian GnysinskiKrystian Gnysinski
 
Design of Precast Elements
Design of Precast ElementsDesign of Precast Elements
Design of Precast ElementsRahul Biswas
 
Building Construction 2 Project 2 Report
Building Construction 2 Project 2 ReportBuilding Construction 2 Project 2 Report
Building Construction 2 Project 2 ReportWilden How
 
seismic retrofitting using precast elements
seismic retrofitting using precast elementsseismic retrofitting using precast elements
seismic retrofitting using precast elementsdiscorajan
 
accelerated bridge construction(ABC)
accelerated bridge construction(ABC)accelerated bridge construction(ABC)
accelerated bridge construction(ABC)varun km
 

What's hot (20)

Application of Engineering Technology in Strengthening of RCC Frames Structures
Application of Engineering Technology in Strengthening of RCC Frames StructuresApplication of Engineering Technology in Strengthening of RCC Frames Structures
Application of Engineering Technology in Strengthening of RCC Frames Structures
 
Taipei 101
Taipei 101Taipei 101
Taipei 101
 
Taipei 101
Taipei 101Taipei 101
Taipei 101
 
High rise building case study
High rise building case study High rise building case study
High rise building case study
 
BTECHN PROJECT 2 Final report (GROUP)
BTECHN PROJECT 2 Final report (GROUP)BTECHN PROJECT 2 Final report (GROUP)
BTECHN PROJECT 2 Final report (GROUP)
 
Aldar Headquarters Dubai
Aldar Headquarters DubaiAldar Headquarters Dubai
Aldar Headquarters Dubai
 
Al dar hq
Al dar hqAl dar hq
Al dar hq
 
Petronas twin towers, taipei 101, burj al-arab
Petronas twin towers, taipei 101, burj al-arabPetronas twin towers, taipei 101, burj al-arab
Petronas twin towers, taipei 101, burj al-arab
 
The taipei 101 tower
The taipei 101 towerThe taipei 101 tower
The taipei 101 tower
 
One Museum Park West (Post-Tensioning case study)
One Museum Park West (Post-Tensioning case study)One Museum Park West (Post-Tensioning case study)
One Museum Park West (Post-Tensioning case study)
 
petronas twin tower
petronas twin towerpetronas twin tower
petronas twin tower
 
Taipei 101
Taipei 101Taipei 101
Taipei 101
 
Burj al Arab Constuction
Burj al Arab ConstuctionBurj al Arab Constuction
Burj al Arab Constuction
 
Linkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian GnysinskiLinkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian Gnysinski
 
Design of Precast Elements
Design of Precast ElementsDesign of Precast Elements
Design of Precast Elements
 
Burj al arab
Burj al arabBurj al arab
Burj al arab
 
Building Construction 2 Project 2 Report
Building Construction 2 Project 2 ReportBuilding Construction 2 Project 2 Report
Building Construction 2 Project 2 Report
 
seismic retrofitting using precast elements
seismic retrofitting using precast elementsseismic retrofitting using precast elements
seismic retrofitting using precast elements
 
accelerated bridge construction(ABC)
accelerated bridge construction(ABC)accelerated bridge construction(ABC)
accelerated bridge construction(ABC)
 
Taipei 101
Taipei 101Taipei 101
Taipei 101
 

Viewers also liked

Вторая проповедь Петра
Вторая проповедь ПетраВторая проповедь Петра
Вторая проповедь Петраunastik
 
The Boatyard Grill Media Plan
The Boatyard Grill Media PlanThe Boatyard Grill Media Plan
The Boatyard Grill Media PlanIthaca College
 
Chuyen nho-trong-the-gioi-lon
Chuyen nho-trong-the-gioi-lonChuyen nho-trong-the-gioi-lon
Chuyen nho-trong-the-gioi-lonLionel Nguyen
 
Feed Forward Stories: towards open research and policy making for better publ...
Feed Forward Stories: towards open research and policy making for better publ...Feed Forward Stories: towards open research and policy making for better publ...
Feed Forward Stories: towards open research and policy making for better publ...Kennisland
 

Viewers also liked (6)

Вторая проповедь Петра
Вторая проповедь ПетраВторая проповедь Петра
Вторая проповедь Петра
 
The Boatyard Grill Media Plan
The Boatyard Grill Media PlanThe Boatyard Grill Media Plan
The Boatyard Grill Media Plan
 
Chuyen nho-trong-the-gioi-lon
Chuyen nho-trong-the-gioi-lonChuyen nho-trong-the-gioi-lon
Chuyen nho-trong-the-gioi-lon
 
Rajiiiiiiiiiiiiiiiiiiiiiiii
RajiiiiiiiiiiiiiiiiiiiiiiiiRajiiiiiiiiiiiiiiiiiiiiiiii
Rajiiiiiiiiiiiiiiiiiiiiiiii
 
Presentation1
Presentation1Presentation1
Presentation1
 
Feed Forward Stories: towards open research and policy making for better publ...
Feed Forward Stories: towards open research and policy making for better publ...Feed Forward Stories: towards open research and policy making for better publ...
Feed Forward Stories: towards open research and policy making for better publ...
 

Similar to 072014_Bunker Mentality

Cast in situ bridge superstracture
Cast in situ bridge superstractureCast in situ bridge superstracture
Cast in situ bridge superstracturekhushal tadas
 
foundation and structural system of the shard building
foundation and structural system  of the shard buildingfoundation and structural system  of the shard building
foundation and structural system of the shard buildingBirukYared3
 
Show reviewing the standards issues n requirements for tall buildings.ppsx (1)
Show reviewing the standards issues n requirements for tall buildings.ppsx (1)Show reviewing the standards issues n requirements for tall buildings.ppsx (1)
Show reviewing the standards issues n requirements for tall buildings.ppsx (1)Sanjay Srivastava
 
The petronas twin towers
The petronas twin towersThe petronas twin towers
The petronas twin towersaman shukla
 
SCS -SOQ January 2015 II
SCS -SOQ January 2015 IISCS -SOQ January 2015 II
SCS -SOQ January 2015 IIHal Forsyth
 
Surtreat Construction Services -SOQ January 2015
Surtreat Construction Services -SOQ January 2015Surtreat Construction Services -SOQ January 2015
Surtreat Construction Services -SOQ January 2015Hal Forsyth
 
Chhatrapati Shivaji International Airport—Integrated Terminal Building
Chhatrapati Shivaji International Airport—Integrated Terminal BuildingChhatrapati Shivaji International Airport—Integrated Terminal Building
Chhatrapati Shivaji International Airport—Integrated Terminal BuildingAnupama Krishnan
 
CIVIL CONSTRUCTION IN FATIMA FERTILIZER COMPANY LIMITED
CIVIL CONSTRUCTION INFATIMA FERTILIZER COMPANY LIMITEDCIVIL CONSTRUCTION INFATIMA FERTILIZER COMPANY LIMITED
CIVIL CONSTRUCTION IN FATIMA FERTILIZER COMPANY LIMITEDWater Birds (Ali)
 
Final Report BSp
Final Report BSpFinal Report BSp
Final Report BSpArpit Dubey
 
Bandra Worli sea link
Bandra Worli sea linkBandra Worli sea link
Bandra Worli sea linkKAVYA H
 
Ralls ncc meeting-san_antonio_04-01-09
Ralls ncc meeting-san_antonio_04-01-09Ralls ncc meeting-san_antonio_04-01-09
Ralls ncc meeting-san_antonio_04-01-09zaff69
 
Dominic Holder Portfolio
Dominic Holder PortfolioDominic Holder Portfolio
Dominic Holder PortfolioDominic Holder
 

Similar to 072014_Bunker Mentality (20)

Projects MeerkatII Copy
Projects MeerkatII CopyProjects MeerkatII Copy
Projects MeerkatII Copy
 
Linkedin
LinkedinLinkedin
Linkedin
 
Cast in situ bridge superstracture
Cast in situ bridge superstractureCast in situ bridge superstracture
Cast in situ bridge superstracture
 
foundation and structural system of the shard building
foundation and structural system  of the shard buildingfoundation and structural system  of the shard building
foundation and structural system of the shard building
 
Show reviewing the standards issues n requirements for tall buildings.ppsx (1)
Show reviewing the standards issues n requirements for tall buildings.ppsx (1)Show reviewing the standards issues n requirements for tall buildings.ppsx (1)
Show reviewing the standards issues n requirements for tall buildings.ppsx (1)
 
burj khalifa
burj khalifaburj khalifa
burj khalifa
 
The petronas twin towers
The petronas twin towersThe petronas twin towers
The petronas twin towers
 
SCS -SOQ January 2015 II
SCS -SOQ January 2015 IISCS -SOQ January 2015 II
SCS -SOQ January 2015 II
 
Surtreat Construction Services -SOQ January 2015
Surtreat Construction Services -SOQ January 2015Surtreat Construction Services -SOQ January 2015
Surtreat Construction Services -SOQ January 2015
 
Chhatrapati Shivaji International Airport—Integrated Terminal Building
Chhatrapati Shivaji International Airport—Integrated Terminal BuildingChhatrapati Shivaji International Airport—Integrated Terminal Building
Chhatrapati Shivaji International Airport—Integrated Terminal Building
 
CIVIL CONSTRUCTION IN FATIMA FERTILIZER COMPANY LIMITED
CIVIL CONSTRUCTION INFATIMA FERTILIZER COMPANY LIMITEDCIVIL CONSTRUCTION INFATIMA FERTILIZER COMPANY LIMITED
CIVIL CONSTRUCTION IN FATIMA FERTILIZER COMPANY LIMITED
 
Pm burj case
Pm burj casePm burj case
Pm burj case
 
Resume sol_2016
Resume sol_2016Resume sol_2016
Resume sol_2016
 
Resume_SOl_2016
Resume_SOl_2016Resume_SOl_2016
Resume_SOl_2016
 
Resume_SOl_2016
Resume_SOl_2016Resume_SOl_2016
Resume_SOl_2016
 
Final Report BSp
Final Report BSpFinal Report BSp
Final Report BSp
 
Bandra Worli sea link
Bandra Worli sea linkBandra Worli sea link
Bandra Worli sea link
 
Ralls ncc meeting-san_antonio_04-01-09
Ralls ncc meeting-san_antonio_04-01-09Ralls ncc meeting-san_antonio_04-01-09
Ralls ncc meeting-san_antonio_04-01-09
 
Dominic Holder Portfolio
Dominic Holder PortfolioDominic Holder Portfolio
Dominic Holder Portfolio
 
Harthill footbridge
Harthill footbridgeHarthill footbridge
Harthill footbridge
 

072014_Bunker Mentality

  • 1. JULY 2014 Bunker MENTALITY A massive steel-framed bunker is the centerpiece of a new gas turbine testing facility. BY HERMAN MILLER, TODD PHILLIPS AND RICKY DIXON MITSUBISHI POWER SYSTEMS America (MPSA) is turning up the heat on its turbine production. Due to increased demand for its products and services across the North American market, the company needed to increase production of its key gas turbine parts, provide complete steam turbine services and assemble advanced fuel-efficient gas tur- bines for the gas and steam market. In response, it hired the joint venture team of H.J. High Construction and Batson-Cook Con- struction to design and build a new manufacturing and testing facility near Savannah, Ga. Subsequently, The Austin Company was hired to provide architectural design and engineering ser- vices (Batson-Cook is one of Austin’s sister companies). The 116-acre Machinery Works Premier Service and Man- ufacturing Center—a comprehensive service and repair center for gas turbines, steam turbines and generator rotors—was de- signed and built in several phases over four years and includes over 440,000 sq. ft of heavy industrial manufacturing facilities, offices and a turbine balancing and testing facility referred to as the Balance Bunker; the latter is one of only 12 such facilities in the world. The project phases included: ➤ Manufacturing Building – Bays 1 and 2 – 137,500 sq. ft ➤ Manufacturing Building – Bay 3 – 75,600 sq. ft ➤ Manufacturing Building – Bay 4 – 76,300 sq. ft ➤ Manufacturing Building – Bay 5 – 72,000 sq. ft ➤ Balance Bunker Vacuum Chamber – Turbine Balancing/ Testing Facility – 20,000 sq. ft ➤ Office Building – 31,700 sq. ft ➤ Office/Conference Center – 17,000 sq. ft ➤ Guardhouse and Maintenance Building – 10,000 sq. ft Crane Considerations The load demand of the multiple bridge cranes, along with the overall building size, were the factors that drove the deci- sion to use structural steel framing for this project; the build- ings feature structural steel framework with 2-in. insulated metal wall panels. Other types of structures, such as cast-in- place concrete or precast concrete, were eliminated due to cost. The manufacturing building required clear heights of over 70 ft and clear spans of up to 90 ft. Bay 2 has a 30-ton crane that only operates in about 100 ft of the bay, and Bay 3 has two, 150- ton cranes that run the entire length of the building; they were designed to be used in tandem for a total lifting capacity of 250 tons. The load requirements in Bay 4 had the most significant impact on the steel design. This bay is designed to have two 30- ton cranes running on a lower runway along the entire length of the building, and two 250-ton bridge cranes that are designed to be used in tandem when loaded with a complete turbine as- sembly (weighing a total of 450 tons). Bay 5 was designed for two 30-ton cranes and one 60-ton crane on an upper runway, and nine 15-ton gantry cranes running on a lower track. On average, each bay took ten months to construct. In order to meet the tight timeline and help maintain this momentum, the steel was fabricated in the order in which it was to be erected. Sev- eral sequences of steel deliveries were scheduled so that no steel sat on the ground for more than three days before it was installed. All photos: The Austin Co. (except upper-left image on p. 27)
  • 2. Nearly 6,100 tons of steel was used to complete the project, in- cluding approximately 4,900 tons of wide-flange and 1,200 tons of steel joists. The manufacturing building required more than 4,500 tons of steel while the Balance Bunker involved more than 1,500 tons, including 62 tons for the sole plates inside the chamber and 16 tons for the base plates for the drive equipment. In addition, nearly 45,000 cubic yards of concrete was cast on the project for equipment foundations, large slab pours and the Balance Bunker. Coatings in- cluded Sherwin-Williams Steel-Spec FHP Universal Primer; Finish (B50WV8000 White) for all exposed steel and as a final coat; and Carboline Carboguard 890 Cycloaliphatic Amine Epoxy for the inte- rior of the Balance Bunker. Repetitive Design The design-build project used BIM and Tekla 3D modeling to sup- port project team collaboration, and SteelFab, Inc., the fabricator, used a Tekla 3D program that was imported into The Austin Company’s Auto- Cad 3D Model to produce a complete 3D model for the manufacturing building. In addition, Austin used AutoCad 3D for the Balance Bunker to help review the structure with the owner and confirm that the build- ing met its requirements. ➤ Modern STEEL CONSTRUCTION Nearly 6,100 tons of steel was used to complete the entire project. The new facility includes more than 440,000 sq. ft of space spread out over multiple phases. ➤ Herman Miller (herman.miller@ theaustin.com) is a supervisory structural engineer with The Austin Company, Todd Phillips (tphillips@ batson-cook.com) is a project manager with Batson-Cook Company and Ricky Dixon (rdixon@steelfab- inc.com) is a vice president/project manager with SteelFab, Inc. ➤ The balance bunker uses more than 1,500 tons of structural steel, including 62 tons for the sole plates inside the chamber and 16 tons for the base plates for the drive equipment. ➤ SteelFab, Inc.
  • 3. The Tekla 3D model was reviewed during meetings with the design team as a visual aid to illustrate design issues and to develop solutions. Overall, the project did not involve complex ge- ometry, but it did have a high degree of repetitious framing. As subsequent bays were released for construction, the team was able to quickly build on to the previous Tekla 3D model. The team was able to copy elements from similarly designed areas of the legacy model, make the requisite modifica- tions to conform to the current bays’ design—typically due to different crane requirements—and quickly pro- duce approval documents. Having the previous bays’ model information was also useful when co- ordinating the connection of a new bay to the existing structure. The team was able to visualize the out- come and avoid clashes and accessi- bility issues that may have gone un- noticed until erection commenced. Critical Balance One of the most critical compo- nents of the overall project was the Balance Bunker.This complex vacuum chamber facility involved the design and construction of 7-ft, 3-in.-thick bunker walls consisting of steel fram- ing and ½-in.-thick inner and outer steel linear plates with a reinforced concrete infill. An 8,000-hp electric motor turns the 22-ft-diameter rotors during balancing at speeds of 4,000 rpm, and a 400-ton, 3-ft, 6-in.-thick steel frame door with reinforced con- crete infill seals the Bunker during testing. Railcars move the turbine ro- tors from Bay 3 into the Balance Bun- ker for testing. Following testing, the rotors are then moved to Bays 4 and 5 for final assembly and finishing. Blast design was a major consid- eration for the Balance Bunker. The thick concrete, steel plate-lined walls of the Bunker protected the outside area from the risk of projectiles that could occur if there was a malfunction JULY 2014 ➤ The new facility sits on 116 acres. ➤ The manufacturing building has five bays in all. On average, each bay took ten months to construct. ➤
  • 4. JULY 2014 of the rotor during the testing and balancing operation. As such, a stray part during testing would be contained within the Bun- ker and not damage any of the surrounding building or endan- ger anyone in the Bunker area. The Bunker’s chamber is designed to maintain a near-abso- lute vacuum during balancing and testing, which necessitated that the thousands of feet of internal welds were designed and tested to maintain an airtight seal. The Balance Bunker walls are reinforced with two layers of #10 rebar at 6-in. vertical and horizontal on each face, and the inner steel plates were fully welded (and each millimeter of weld was vacuum tested). The internal steel linear plating anchoring was designed to resist a 2,100 psf vacuum load and a thermal design load resulting from a 100 °F rise in internal surface temperature during testing. The massive Bunker door was developed to roll along a hydraulic track, be pushed into place horizontally using hy- draulic cylinders and vacuum-sealed with a specially designed, bunker-sized rubber gasket. In addition, two stairways and a railcar bridge leading into the Bunker were designed with hy- draulic lifts to move out of the door’s way when closing. Due to its mass, the door was built in sections and transported to the jobsite to be installed piece by piece. The door was made of ½-in.-thick steel plate and fully welded like the inner cham- ber, then filled with concrete; it also had rebar installed at 6 in. on center. Following more than four years of design and construc- tion work, the MPSA facilities were successfully completed on schedule and opened last summer. While the project involved numerous challenges, including the many unique design as- pects of the Balance Bunker, the team’s approach resulted in a world-class facility that enables MPSA to provide high-quality parts and services across the continent. ■ Owner Mitsubishi Power Systems America, Pooler, Ga. Design-Build General Contractor H.J. High Construction, Orlando, Fla., and Batson-Cook Construction, Atlanta (joint venture) Architect The Austin Company, Cleveland, Ohio Structural Engineer The Austin Company (Balance Bunker and Manufacturing Building foundations) KingGuinn Associates, Charlotte, N.C. (Manufacturing Building framing) Steel Fabricator, Detailer and Erector SteelFab, Inc., Charlotte (AISC Member/AISC Certified Fabricator) The manufacturing building required clear heights of over 70 ft and clear spans of up to 90 ft. ➤ ➤ The turbine balancing and testing facility is referred to as the Balance Bunker; there are only 12 such facilities in the world. ➤ ➤