  Hanford Waste Treatment Plant completes fifth concrete
            wall elevation for largest facility
MEDIA CONTACTS:
Suzanne Heaston, Bechtel National, Inc., (509) 371-2329
Carrie Meyer, Department of Energy, (509) 372-0810

   Richland, Wash. -- Last week, crews at the Hanford Waste Treatment Plant, also
known as the “Vit Plant,” finished installing the Pretreatment Facility’s fifth elevation of
concrete walls. The fifth elevation reaches 96 feet at the top.
   To place the final walls, crews used a specialized concrete pumping truck with an
extendable arm that reaches approximately 200 feet vertically or horizontally.
   The Pretreatment Facility, the largest of the Vit Plant’s four major nuclear facilities,
comprises six elevated concrete sections and more than 113,000 cubic yards of concrete.
Work on the sixth and final elevation is already in progress, and only four small wall
sections remain before all concrete walls in the Pretreatment Facility are complete.
   When complete, the building’s walls will reach a total height of 109 feet. Steel
columns and roof trusses will extend beyond the walls to an overall height of 120 feet.




(Photo 1 of 3)
                                        (continued)
(Photo 2 of 3)




(Photo 3 of 3)

   Bechtel National, Inc. is designing and building the world’s largest radioactive waste
treatment plant for the U.S. Department of Energy at the Hanford Site in southeastern
Washington state. The $12.2 billion Waste Treatment and Immobilization Plant, also
known as the “Vit Plant,” will immobilize the radioactive liquid waste currently stored in
177 underground tanks using a process called “vitrification.”

                                       (continued)
Vitrification involves blending the waste with molten glass and heating it to high
temperatures. The mixture is then poured into stainless steel canisters. In this glass form,
the waste is stable and impervious to the environment, and its radioactivity will dissipate
over hundreds to thousands of years.
   The Vit Plant will cover 65 acres with four nuclear facilities -- Pretreatment,
Low-Activity Waste Vitrification, High-Level Waste Vitrification and Analytical
Laboratory -- as well as operations and maintenance buildings, utilities and office space.
   Construction of the Vit Plant began in 2001 and is more than 60 percent complete.
The project is scheduled to complete construction in 2016; will reach commissioning in
2019 and achieve full operations in 2022.

NR11-20                                       ###

More Related Content

Viewers also liked (7)

ORP 2011 Cleanup Caucus Presentation
ORP 2011 Cleanup Caucus PresentationORP 2011 Cleanup Caucus Presentation
ORP 2011 Cleanup Caucus Presentation
 
Memory management for i os dev
Memory management for i os devMemory management for i os dev
Memory management for i os dev
 
Best presentation
Best presentationBest presentation
Best presentation
 
IHS McCloskey Nuclear business
IHS McCloskey Nuclear businessIHS McCloskey Nuclear business
IHS McCloskey Nuclear business
 
Hanford Waste Treatment Plant receives and sets key air-filtration equipment ...
Hanford Waste Treatment Plant receives and sets key air-filtration equipment ...Hanford Waste Treatment Plant receives and sets key air-filtration equipment ...
Hanford Waste Treatment Plant receives and sets key air-filtration equipment ...
 
Vamos contar
Vamos contarVamos contar
Vamos contar
 
Navicat
NavicatNavicat
Navicat
 

Similar to Hanford Waste Treatment Plant completes fifth concrete wall elevation for largest facility

Rick Stinnett Projects
Rick Stinnett ProjectsRick Stinnett Projects
Rick Stinnett Projects
rstinnett
 
223 Williams St ANCR Article
223 Williams St ANCR Article223 Williams St ANCR Article
223 Williams St ANCR Article
Paul Saly
 
CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1
Dan Caouette
 
2443-rags-to-riches-how-chicagos-111-west-wacker-finally-got-built
2443-rags-to-riches-how-chicagos-111-west-wacker-finally-got-built2443-rags-to-riches-how-chicagos-111-west-wacker-finally-got-built
2443-rags-to-riches-how-chicagos-111-west-wacker-finally-got-built
Stephen Matkovits
 
Rodney Hibbard CV_Construction Manager
Rodney Hibbard CV_Construction ManagerRodney Hibbard CV_Construction Manager
Rodney Hibbard CV_Construction Manager
Rodney Hibbard
 
ICE Case Study 2016
ICE Case Study 2016ICE Case Study 2016
ICE Case Study 2016
Steve Edgson
 
Lenny Roderick's Resume
Lenny Roderick's ResumeLenny Roderick's Resume
Lenny Roderick's Resume
Lenny Roderick
 
DETROIT HOUSING SPREADS 8.5 x 10
DETROIT HOUSING SPREADS 8.5 x 10 DETROIT HOUSING SPREADS 8.5 x 10
DETROIT HOUSING SPREADS 8.5 x 10
Dillon Clarke
 
Recent Project List 4-2015
Recent Project List 4-2015Recent Project List 4-2015
Recent Project List 4-2015
Chip Lowe
 

Similar to Hanford Waste Treatment Plant completes fifth concrete wall elevation for largest facility (20)

Hanford Waste Treatment Plant completes concrete design for largest facility
Hanford Waste Treatment Plant completes concrete design for largest facilityHanford Waste Treatment Plant completes concrete design for largest facility
Hanford Waste Treatment Plant completes concrete design for largest facility
 
Waste Treatment & Immobilization Plant Project
Waste Treatment & Immobilization Plant ProjectWaste Treatment & Immobilization Plant Project
Waste Treatment & Immobilization Plant Project
 
072014_Bunker Mentality
072014_Bunker Mentality072014_Bunker Mentality
072014_Bunker Mentality
 
8_SakhalinReleaseENR
8_SakhalinReleaseENR8_SakhalinReleaseENR
8_SakhalinReleaseENR
 
Manufacturing Facility Hits the Floor Running - Process Piping and HVAC Syste...
Manufacturing Facility Hits the Floor Running - Process Piping and HVAC Syste...Manufacturing Facility Hits the Floor Running - Process Piping and HVAC Syste...
Manufacturing Facility Hits the Floor Running - Process Piping and HVAC Syste...
 
Post Harvey Flood Data and the Future of Resilient Infrastructure
Post Harvey Flood Data and the Future of Resilient InfrastructurePost Harvey Flood Data and the Future of Resilient Infrastructure
Post Harvey Flood Data and the Future of Resilient Infrastructure
 
Rick Stinnett Projects
Rick Stinnett ProjectsRick Stinnett Projects
Rick Stinnett Projects
 
Eschenburg Resume 1
Eschenburg  Resume 1Eschenburg  Resume 1
Eschenburg Resume 1
 
223 Williams St ANCR Article
223 Williams St ANCR Article223 Williams St ANCR Article
223 Williams St ANCR Article
 
CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1
 
Park avenue
Park avenuePark avenue
Park avenue
 
2443-rags-to-riches-how-chicagos-111-west-wacker-finally-got-built
2443-rags-to-riches-how-chicagos-111-west-wacker-finally-got-built2443-rags-to-riches-how-chicagos-111-west-wacker-finally-got-built
2443-rags-to-riches-how-chicagos-111-west-wacker-finally-got-built
 
DCTS Brochure
DCTS BrochureDCTS Brochure
DCTS Brochure
 
Rodney Hibbard CV_Construction Manager
Rodney Hibbard CV_Construction ManagerRodney Hibbard CV_Construction Manager
Rodney Hibbard CV_Construction Manager
 
ICE Case Study 2016
ICE Case Study 2016ICE Case Study 2016
ICE Case Study 2016
 
Lenny Roderick's Resume
Lenny Roderick's ResumeLenny Roderick's Resume
Lenny Roderick's Resume
 
DETROIT HOUSING SPREADS 8.5 x 10
DETROIT HOUSING SPREADS 8.5 x 10 DETROIT HOUSING SPREADS 8.5 x 10
DETROIT HOUSING SPREADS 8.5 x 10
 
Recent Project List 4-2015
Recent Project List 4-2015Recent Project List 4-2015
Recent Project List 4-2015
 
Hi-Tech Building Systems
Hi-Tech Building SystemsHi-Tech Building Systems
Hi-Tech Building Systems
 
Hi-Tech Building Systems
Hi-Tech Building SystemsHi-Tech Building Systems
Hi-Tech Building Systems
 

More from DOE Office of River Protection

DOE submits safety culture plan to the Defense Nuclear Facilities Safety Board
DOE submits safety culture plan to the Defense Nuclear Facilities Safety BoardDOE submits safety culture plan to the Defense Nuclear Facilities Safety Board
DOE submits safety culture plan to the Defense Nuclear Facilities Safety Board
DOE Office of River Protection
 
Hanford Waste Treatment Plant completes fifth concrete wall elevation for lar...
Hanford Waste Treatment Plant completes fifth concrete wall elevation for lar...Hanford Waste Treatment Plant completes fifth concrete wall elevation for lar...
Hanford Waste Treatment Plant completes fifth concrete wall elevation for lar...
DOE Office of River Protection
 

More from DOE Office of River Protection (6)

Hanford Waste Treatment Plant receives national safety award for excellent he...
Hanford Waste Treatment Plant receives national safety award for excellent he...Hanford Waste Treatment Plant receives national safety award for excellent he...
Hanford Waste Treatment Plant receives national safety award for excellent he...
 
DOE submits safety culture plan to the Defense Nuclear Facilities Safety Board
DOE submits safety culture plan to the Defense Nuclear Facilities Safety BoardDOE submits safety culture plan to the Defense Nuclear Facilities Safety Board
DOE submits safety culture plan to the Defense Nuclear Facilities Safety Board
 
Hanford Waste Treatment Plant completes fifth concrete wall elevation for lar...
Hanford Waste Treatment Plant completes fifth concrete wall elevation for lar...Hanford Waste Treatment Plant completes fifth concrete wall elevation for lar...
Hanford Waste Treatment Plant completes fifth concrete wall elevation for lar...
 
Hanford Waste Treatment Plant Construction Site Receives Department of Energy...
Hanford Waste Treatment Plant Construction Site Receives Department of Energy...Hanford Waste Treatment Plant Construction Site Receives Department of Energy...
Hanford Waste Treatment Plant Construction Site Receives Department of Energy...
 
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...
 
ORP FY13 Budget Workshop
ORP FY13 Budget WorkshopORP FY13 Budget Workshop
ORP FY13 Budget Workshop
 

Recently uploaded

Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Victor Rentea
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Safe Software
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Safe Software
 
Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native Applications
WSO2
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
?#DUbAI#??##{{(☎️+971_581248768%)**%*]'#abortion pills for sale in dubai@
 

Recently uploaded (20)

Understanding the FAA Part 107 License ..
Understanding the FAA Part 107 License ..Understanding the FAA Part 107 License ..
Understanding the FAA Part 107 License ..
 
CNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In PakistanCNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In Pakistan
 
AWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of Terraform
 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
 
Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...
 
Platformless Horizons for Digital Adaptability
Platformless Horizons for Digital AdaptabilityPlatformless Horizons for Digital Adaptability
Platformless Horizons for Digital Adaptability
 
"I see eyes in my soup": How Delivery Hero implemented the safety system for ...
"I see eyes in my soup": How Delivery Hero implemented the safety system for ..."I see eyes in my soup": How Delivery Hero implemented the safety system for ...
"I see eyes in my soup": How Delivery Hero implemented the safety system for ...
 
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
 
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
 
Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native Applications
 
ICT role in 21st century education and its challenges
ICT role in 21st century education and its challengesICT role in 21st century education and its challenges
ICT role in 21st century education and its challenges
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
 
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot ModelMcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot Model
 
Artificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyArtificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : Uncertainty
 
Six Myths about Ontologies: The Basics of Formal Ontology
Six Myths about Ontologies: The Basics of Formal OntologySix Myths about Ontologies: The Basics of Formal Ontology
Six Myths about Ontologies: The Basics of Formal Ontology
 
FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024
 
DEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
DEV meet-up UiPath Document Understanding May 7 2024 AmsterdamDEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
DEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
 

Hanford Waste Treatment Plant completes fifth concrete wall elevation for largest facility

  • 1. November 16, 2011 Hanford Waste Treatment Plant completes fifth concrete wall elevation for largest facility MEDIA CONTACTS: Suzanne Heaston, Bechtel National, Inc., (509) 371-2329 Carrie Meyer, Department of Energy, (509) 372-0810 Richland, Wash. -- Last week, crews at the Hanford Waste Treatment Plant, also known as the “Vit Plant,” finished installing the Pretreatment Facility’s fifth elevation of concrete walls. The fifth elevation reaches 96 feet at the top. To place the final walls, crews used a specialized concrete pumping truck with an extendable arm that reaches approximately 200 feet vertically or horizontally. The Pretreatment Facility, the largest of the Vit Plant’s four major nuclear facilities, comprises six elevated concrete sections and more than 113,000 cubic yards of concrete. Work on the sixth and final elevation is already in progress, and only four small wall sections remain before all concrete walls in the Pretreatment Facility are complete. When complete, the building’s walls will reach a total height of 109 feet. Steel columns and roof trusses will extend beyond the walls to an overall height of 120 feet. (Photo 1 of 3) (continued)
  • 2. (Photo 2 of 3) (Photo 3 of 3) Bechtel National, Inc. is designing and building the world’s largest radioactive waste treatment plant for the U.S. Department of Energy at the Hanford Site in southeastern Washington state. The $12.2 billion Waste Treatment and Immobilization Plant, also known as the “Vit Plant,” will immobilize the radioactive liquid waste currently stored in 177 underground tanks using a process called “vitrification.” (continued)
  • 3. Vitrification involves blending the waste with molten glass and heating it to high temperatures. The mixture is then poured into stainless steel canisters. In this glass form, the waste is stable and impervious to the environment, and its radioactivity will dissipate over hundreds to thousands of years. The Vit Plant will cover 65 acres with four nuclear facilities -- Pretreatment, Low-Activity Waste Vitrification, High-Level Waste Vitrification and Analytical Laboratory -- as well as operations and maintenance buildings, utilities and office space. Construction of the Vit Plant began in 2001 and is more than 60 percent complete. The project is scheduled to complete construction in 2016; will reach commissioning in 2019 and achieve full operations in 2022. NR11-20 ###