IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE)
e-ISSN: 2278-1684,p-ISSN: 2320-334X, Volume 12, Issue 1 Ver. II (Jan- Feb. 2015), PP 57-65
www.iosrjournals.org
DOI: 10.9790/1684-12125765 www.iosrjournals.org 57 | Page
Evaluation of Total Quality Management Implementation as
Engineering Practices in Jordanian Construction Projects
Jumah M.Th. Al-Dulaimy1
, Faithy Alkhazraji2
, Rami H. ALHadeethi3
,
Jamal O. Sameer4
1Department of planning, Education Ministry , Al-anbar, Iraq
2Isra University ,Amman, Jordan
3Al-hashimya University,Amman, Jordan
4Universiti Tenaga Nasional, Kuala Lumpur, Malaysia
Abstract:The construction sector is one of the most important business fields in Jordan and this sector is
suffering from many problems in Management and quality. Total quality management (TQM) process is
considered as a modern system in the field of quality.
The purpose of this paper is to evaluate TQM implementation as engineering practices in different construction
projects phases. In order to achieve this objective, literature review has been carried out to identify the two
main factors influencing the implementation of TQM factors in the construction process: (continuous
improvement, customer satisfaction) .
And by examining the four ISO 9001-2008 requirements to achieve important TQM factors in construction
process. In this study, the data was collected by a questionnaire survey, the survey analyzed by statistical
software SPSS.
More than 204 questionnaire forms were distributed, 177 was responded which was represented 86 % of the
total spread questionnaire forms, the respondents were engineers only(Civil, Mechanical, Electrical and
Architectural).
By analyses of results, the study showed that TQM implementation level in all construction projects phases was
moderate in Jordanian construction process.
Key words: Total quality management, ISO 9001-2008,Customer Satisfaction, Continues Improvement.
I. Introduction:
The main attention of total quality management (TQM) and its application in construction projects to
establishment of high-quality facilities and Raise the performance level in construction Process.TQM appears to
be a very important concept which is difficult to summarize in a short definition. TQM is a process lead by
senior management to obtain involvement of all employees in the continuous improvement of the performance
of all activities.
Therefore, this studyevaluated the two main TQM factors in construction project (customer satisfaction
and continuous improvement) by examining the apply of four ISO 9001-2008 requirement during different
project phases.
Because of instability in the Middle East, especially wars in Iraq, Syria, Lebanon, Palestine, has
resulted in an increased immigration percentage in the recent years to Jordan. This big number of people has
increased the demand to develop the country infrastructure, in addition to the necessary needs such as, houses,
hospitals, hotels, schools and entertainment places. So it's important to adopt TQM concept which affecting
positively on the entire construction industry and company reputations, with a result that caused a rapid rise in
the quality scale to the highest level (Bani Ismail,2012).
Despite the international adoption of the TQM concept, it has not been developed within the Arab area
, as a result from the lack of basic knowledge of TQM and low level of organization’ readiness for
change(Haffar,2010).
II. Literature Review:
TQM is one of most important techniques to improve quality, which many organizations and
companies are using to reach success. thewide implementation for TQMall through the world in different sectors
andindustries. The positive results appeared in these sectorsandindustries because of TQM implementation
(Bhat and Rajashekhar, 2009).
The purpose or function of TQM is to provide a high quality product to the customers, in turn increase
the productivity also customer satisfaction ,furthermore decrease the cost With lower price anda higher quality
Evaluation of Total Quality Management Implementation as Engineering Practices in ….
DOI: 10.9790/1684-12125765 www.iosrjournals.org 58 | Page
product, TQM is approach of managing different industries to improve the quality of product (Kumar, et al.,
2011).
And its show Establish strategic goals, mission and vision based on the concept of TQM and bind all
parties together including subcontractors of these goals. The Organizations need to follow continuous
improvement while maintaining a long-term Perspective. The improvement will have to be made both in the
processes and the organizational system in order to make the TQM program successful(Al-Tayeb Mustafa,2008)
(TQM) Total quality management is defined as both a management of quality philosophy and group of
guiding principles that promoteculture in organizations and all members participation in organization aiming to
achieve longtermsuccessprocess through continuous improvement and customer satisfaction of products, and the
benefits for all society members (Juran et al., 1999; Rampersad, 2001;Besterfield et al., 2003)
III. Definitions of Total Quality Management
The Asian Institute of Technology (AIT), define TQM as “a philosophy that strengthens and support
the culture to foster continuous organizational improvement through integrated, systematic, consistent and
reliable effort involving everything and everyone, focusing primarily on total satisfaction of internal and
external customers, where employees work together in teams with process ownership, guided by a committed
top management, which takes a practical participation” (Nukulchai,2003).
Also, according to the British Quality Association defines TQM as “an all-agreement business
management philosophy focusing on completely fulfilling customer requirements with a maximum of
effectiveness and efficiency" (Wessel, 2004).
According the previous definitions, define the TQM as a philosophy but the different point of view.
British Standard(BS) described the TQM as the management philosophy aimed to achieve organization
objectives. While, the (AIT), defined the TQM as the philosophy aiming to satisfy the customers.
Out of above definitions, aneasy definition of TQM is a get-together of external and internal customer
requirements, and the difference between quality and TQM is that the quality expression generally focuses on a
temporary process.
In construction project for example, in order to achieve a good strength for concrete according to the
specifications, the concrete should be cured by water for(3-4)days, to reached for the required quality, so this is
a temporary process, while TQM is a long term process and adopts a strategic dimension, to lead each financial,
production, marketing and managerial plan in the path which support the strategic dimension. From the previous
definitions, the researcher conclusion was that the definition of TQM is an old concept, but in last years it
appears as an official job.
Basics of TQM Principles in construction projects:
The concept of TQM is modern in construction projects. It was only applied to industrial projects, the
construction companies in the United States applied (TQM) after the noticed the great success of industrial
companies by the application of the concept of TQM which is based on the achieving the basic principles:
customer satisfaction, continuous improvement. These principles will be defined and clarified and how they will
be applied in construction projects. (Gamld D. Oberlender 2000,)
Customer Satisfaction:
The basic function of the construction industry is to provide customers projects, facilities and services
ready to use, and meet their requirements. Any construction company must be completed its work at a
competitive cost to guarantee continuous work. TQM is a management philosophy based on identifying
customer needs and requirements exactly and work to make suitable environment and working conditions
suitable to achieve the needs and requirements at the lowest possible cost, by quality control at every stage of
the construction process. While the construction project is an idea to close out and ready for use, this quality of
the final product will be satisfy the customer needs.
Continues Improvement:
To Continues Improvement we have to:
-Continuous improvement for current methods and procedures and to keep existed improvements during the
product processing control.
-Concentrate on achieving technological development in construction and engineering process during innovation
and creation.
The construction project consists of a group of activities so we want to develop, innovate and create in each
activity to achieve quality and fulfill customer satisfaction.
During each activity implementation we have to reduce gap between the customer requirements and
current status, during the use of problem analysis process by using Deming cycle "Plan-do-check-act", which its
Evaluation of Total Quality Management Implementation as Engineering Practices in ….
DOI: 10.9790/1684-12125765 www.iosrjournals.org 59 | Page
considered as a procedure for continuous improvement by concentrate on correction procedure and defect
prevention.
Deming cycle contain four process Occur every time and constantly repeated and apply it in each
process as show in Figure(1),and Table (1) show Eight steps for each Deming cycle process .
Figure (1)Eight steps for each Deming cycle process
Table (1) shows Eight steps for each Deming cycle process .
-Identify the problem and improvement aim.
-Analyze the current status
-Determine the root causes and its affect
-Develop plans for corrective works
Plan
-Apply the plan and its implementation.Do
-Document the implementation plan result to compare it with main plan aim.Check
-Create the criteria for the necessary steps to avoid problem repeated
-Reprocess and take in consecration rest of problems or suitable improvement in the next
plan stage.
Act
ISO 9001-2008
ISO 9001:2008 it’s the last version sets out the criteria for a quality management system and conceder
only standard in the family that can be certified. It can be used by large or smallorganization, regardless of its
field of activity.
Moreover, the ISO 9001:2008 is implemented by over one million companies and organizations in over 170
countries (ISO technical committee.2008)
There are four ISO 9001-2008 requirements to Achieve TQM important factors in construction projects. (The
continuous improvement and customer satisfaction) as shown in Figure (2):(International standard ISO 9001,
2008).
1. Management responsibility.
2. Resource management.
3. Product realization.
Each of The four ISO(9001-2008)requirements includes a number of elements
4. Measurement, analysis and improvement.
Evaluation of Total Quality Management Implementation as Engineering Practices in ….
DOI: 10.9790/1684-12125765 www.iosrjournals.org 60 | Page
Figure (2)
Questionnaire design
Questions in a questionnaire were formulated based on the literature review as main sources to get the
initial form of questionnaire; the Figure ( 3 ) shows the questionnaire development process.
Figure (3) Questionnaire design
Results of factor analysis:
The result of the output obtained in this research could be presented as followed:The items in the
survey were made on a five points likert scale where 5 implied strongly agree, and 1 Indicated the respondent
strongly disagree with the statements. The item of the questionnaire was conducted by using SPSS package
version 16.0 to detect the factor structure in the variable and Table ( 2 ) show the mean, Standard deviation and
Skewnessvalues for all project phases:
Contract documentDesignStudy
SkSdMSkSdMSkSdMSt. Dis.
-0.220.823.15-0.120.693.17-0.020.643.33M.R
0.040.723.160.050.763.24-0.040.723.13R.M
-0.180.813.18-0.270.773.38-0.200.553.48P.R
-0.100.743.25-0.440.753.38-0.090.813.03M&A
-0.050.703.19-0.290.613.29-0.110.553.24Overall
Evaluation of Total Quality Management Implementation as Engineering Practices in ….
DOI: 10.9790/1684-12125765 www.iosrjournals.org 61 | Page
Close outImplementationContractor Selection
SkSdMSkSdMSkSdMSt. Dis.
-0.210.833.21-0.160.683.130.200.792.86M.R
0.390.753.14-0.090.733.090.210.743.17R.M
-0.070.843.19-0.360.753.26-0.250.703.27P.R
-0.181.013.150.090.663.000.180.693.27M&A
0.090.753.17-0.180.633.120.300.553.14Overall
Table ( 2 ) Statically descriptive for different project phases
Evaluation of TQM Implantation as engineering practice
The stages were divided in the questionnaire to six phases. In addition to that, the classifications for
mean values in the upcoming Tables will be based on the following criteria as suggested by researcher as shown
in Table (3):
Table (3) Evaluation level
Category Weak Moderate High
Mean < 3 3 – 4 <4
TQM factors were then analyzed according to six construction projects phases as in the following:
- Study phase
conclude from Figure(4) that all mean values are moderate in all ISO requirments (management
responsibility and product realization) but in resources management there are two values under the mean (weak
evaluation) ,at which There was a shortage in work invironmental analysis and resources procurement.
In (Measurement and alanlyisis) there was no study review and check by any neutral part.
Figure(4)Current state of TQM in study Phase
In general the overall TQM implementation factors in study phase is moderate.
3.9.2 Design phase
According to Figure(5), that all mean values are moderate in all ISO requirments (resources
management, product realization and measurement and analysis ) but in Management Responsibility there are
three values under the mean (weak evaluation) at which insufficient responsibility and Authorization ,lack
communucation and design change approval.
Evaluation of Total Quality Management Implementation as Engineering Practices in ….
DOI: 10.9790/1684-12125765 www.iosrjournals.org 62 | Page
Figure(5) Current state of TQM in designphase.
In general the overall TQM implementation factors in design phase is moderate.
3.9.3 Contract documentsphase
According to Figure(6), that all mean values are moderate in all ISO requirements (management
responsibility,resources management, product realization and measurement and analysis).
Figure(6)Current state of TQM in contractdocumentsphase
In general the overall TQM implementation factors in contract documants phase are moderate
Contractor selection phase
According to Figure(7) that all mean values are moderate in all ISO requirments (resources
management, product realization and measurement and analysis) but in management responsibility there are
three values under the mean (weak evaluation) at which the contractor was sellected according to financial
categories rather than experience and insufficient responsibility and Authorization .
Evaluation of Total Quality Management Implementation as Engineering Practices in ….
DOI: 10.9790/1684-12125765 www.iosrjournals.org 63 | Page
Figure(7)Current state of TQM in contractor selection phase
In general the overall TQM implementation factors in contractor sellection phase is moderate.
Implementation phase
conclude from Figure(8),that overall mean value for management responsibility is moderate but four
values are considered (weak) due to improper cash flow, no detailed project's budget , lack of communication
among project parties and lack of commitment inproject duration.That overall mean value for resources
management is moderate but there are five values considered (weak) mean value. Such as poor raw material
quality ,there is no technical staff,inappropriate labor wages ,shortage in site mobilization and poor safety
procedures.The overall mean value for product realization is moderate but there is one low value(weak)at which
no control and analysis for construction test.The overall mean value for measurement and analysis has a
moderate mean value but there are two values with low mean value (weak) at which there is a lack in check and
test to diagnose the defects ,and no preventive procedures .
Evaluation of Total Quality Management Implementation as Engineering Practices in ….
DOI: 10.9790/1684-12125765 www.iosrjournals.org 64 | Page
Figure(8) Current state of TQM in implementation Phase
In general the overall TQM implementation factors in implementation phase is moderate.
Close out phase
According to Figure (9) that all mean values are moderate in all ISO requirements (management
responsibility, product realization and measurement and analysis) but resources management has one value
under the mean (weak evaluation) at which the there is a lack in staff training.
Figure(9) Current state of TQM in close outphase
In general the overall TQM implementation factors in close out phase is moderate.
IV. Conclusion:
1) TQM factors applied in the Jordanian construction projects are classified as a moderate level because some
of (four ISO requirement) in the project phases are weak.
2) In study phase found that there a huge weakness in the analysis of work environment, there is no third or
other neutral part are checking the Study, and the owner satisfaction is adopting as criterion of effective
performance criteria in quality management system.
3) In design phase there is a big weakness because of authorizing some responsibilities and authorities from
top Management to the designer to ensure work efficiency, also lack in coordination between the owner and
designer will affect the project completion according to the requirements, but the designdocumentswere
clear and suitable for requirements.
4) Contract documents phase was the best among the different phases, where the documents are approved
before concluding the contract; also take advantage of previous contracts to develop the final form of the
contract.
5) There is a large shortage of management responsibility in contractor selection phase, found that the
contractor selection was not according to experience, efficiency and price , contractor select was according
to the lowest total price only, but the feature of this phase is there are a third party to resolving disputes if
there.
6) The implementation phase was the worst among the other phases where :
a) There is huge weakness in the four ISO requirements to apply TQM factors application in this phase.
b) Also found that no interest of using high quality raw materials.
c) There is no enough coordinate to information exchange and Periodic meetings between the project parties
(owner, designer and executer).
d) The working staff wagesare not appropriate with the assigned to it works to ensure quality, also weakness in
health and safety standards in the projects.
e) Weak in monitoring and analyzing construction tests to measure the conformity with the specifications and
lack in the preventive procedures to guarantee avoiding the no confirm occurring.
Evaluation of Total Quality Management Implementation as Engineering Practices in ….
DOI: 10.9790/1684-12125765 www.iosrjournals.org 65 | Page
7) In close out phase the training sessions are not available for the working staff to improve their
qualifications, there is a concern to make the contractor to repair the diagnosed defects before the facility
occupied, impose discounts when found nonconforming product for the owner requirements.
Refrence
[1]. Bani Ismail, Loiy (2012), An evaluation of the implementation of Total Quality Management (TQM) within the construction sector
in the United Kingdom and Jordan, Doctoral thesis, University of Huddersfield
[2]. Haffar, Mohamed (2010),The Influence of Organizational Culture on Total QualityManagement Implementation in Syrian Public
Manufacturing Organizations, BrunelUniversity.
[3]. Bhat, K.S. and J. Rajashekhar, 2009. " An empirical study of barriers to TQM implementation in Indianindustries", The TQM
Magazine, 21(3): 261-272.
[4]. Das, A., V. Kumar and U. Kumar, 2011. "The role of leadership competencies for implementing TQM(Anempirical study in Thai
manufacturing industry) ", International Journal of Quality & Reliability Management,28(2): 195-219.
[5]. Al-Tayeb ,Mustafa (2008), Critical Success Factors of TQM Implementation on Construction Projects in Gaza Strip. Master thesis,
The Islamic University – Gaza.
[6]. Nukulchai, W. K. (2003), Towards Total Quality Management in Higher Education: The Experience of Asian Institute of
Technology. Asian Institute of Technology.
[7]. Wessel,G, and Burcher,P.(2004), Six Sigma for Small and Medium-Sized Enterprises. The TQM Magazine, volume 16 No.4,
pp.264 - 272.
[8]. Oberlender, Garold D. (2000),PROJECT MANAGEMENT FOR ENGINEERING AND CONSTRUCTION..Oklahoma State
University.
[9]. Juran, J. and Godfrey, A. (eds.) (1999). Juran’s Quality Handbook, 5th edition. New York: McGraw-Hill.
[10]. Rampersad, H. (2001). Total Quality Management: an Executive Guide to Continuous Improvement. New York: Springer.
[11]. Besterfield, D., Besterfield-Michna, C., Nesterfield, G. and Besterfirld-Sccre, M. (2003). Total Quality Management, 3rd Edition.
New Jersey: Prentice Hall.
[12]. Internet Articles based on print sourceISO technical committee, (2008), (TC) ISO/TC 176, sub-committee, from web site:
http://www.iso.org/iso/iso_9000

More Related Content

What's hot

8 relationship and comparison between in jit tqm and tpm a review
8 relationship and comparison between in jit  tqm and tpm  a review8 relationship and comparison between in jit  tqm and tpm  a review
8 relationship and comparison between in jit tqm and tpm a reviewprjpublications
 
Om theoretical assignment group 5
Om  theoretical assignment group 5Om  theoretical assignment group 5
Om theoretical assignment group 5Vandana Kumari
 
Enhancement of the performance of an industry by the application of tqm concepts
Enhancement of the performance of an industry by the application of tqm conceptsEnhancement of the performance of an industry by the application of tqm concepts
Enhancement of the performance of an industry by the application of tqm conceptseSAT Journals
 
Enhancement of the performance of an industry by the
Enhancement of the performance of an industry by theEnhancement of the performance of an industry by the
Enhancement of the performance of an industry by theeSAT Publishing House
 
IRJET- Application of Quality Function Deployment (QFD) in Aluminium Pot Manu...
IRJET- Application of Quality Function Deployment (QFD) in Aluminium Pot Manu...IRJET- Application of Quality Function Deployment (QFD) in Aluminium Pot Manu...
IRJET- Application of Quality Function Deployment (QFD) in Aluminium Pot Manu...IRJET Journal
 
Total Quality Management
Total Quality Management Total Quality Management
Total Quality Management Aneel Raza
 
Implementation and financial accounting of quality training and education
Implementation and financial accounting of quality training and educationImplementation and financial accounting of quality training and education
Implementation and financial accounting of quality training and educationIAEME Publication
 
Total quality management models
Total quality management modelsTotal quality management models
Total quality management modelsMuzo Bacan
 
Study on the Impact of ISO Certification on the Quality Culture of Constructi...
Study on the Impact of ISO Certification on the Quality Culture of Constructi...Study on the Impact of ISO Certification on the Quality Culture of Constructi...
Study on the Impact of ISO Certification on the Quality Culture of Constructi...IRJET Journal
 
IRJET- A Study on Quantification of Factors Affecting the Quality of Construc...
IRJET- A Study on Quantification of Factors Affecting the Quality of Construc...IRJET- A Study on Quantification of Factors Affecting the Quality of Construc...
IRJET- A Study on Quantification of Factors Affecting the Quality of Construc...IRJET Journal
 
Unit-I Introduction
Unit-I  IntroductionUnit-I  Introduction
Unit-I IntroductionDr.Raja R
 
2011-01-01 published journal article hande yilmaz
2011-01-01 published journal article hande yilmaz2011-01-01 published journal article hande yilmaz
2011-01-01 published journal article hande yilmazHANDE YILMAZ
 
A working definition for total quality management (tqm) researchers
A working definition for total quality management (tqm) researchers A working definition for total quality management (tqm) researchers
A working definition for total quality management (tqm) researchers Luong Tien Dat
 
Quality management and performance a review
Quality management and performance a reviewQuality management and performance a review
Quality management and performance a reviewiaemedu
 

What's hot (19)

Socio educational project
Socio educational projectSocio educational project
Socio educational project
 
8 relationship and comparison between in jit tqm and tpm a review
8 relationship and comparison between in jit  tqm and tpm  a review8 relationship and comparison between in jit  tqm and tpm  a review
8 relationship and comparison between in jit tqm and tpm a review
 
Om theoretical assignment group 5
Om  theoretical assignment group 5Om  theoretical assignment group 5
Om theoretical assignment group 5
 
Enhancement of the performance of an industry by the application of tqm concepts
Enhancement of the performance of an industry by the application of tqm conceptsEnhancement of the performance of an industry by the application of tqm concepts
Enhancement of the performance of an industry by the application of tqm concepts
 
Enhancement of the performance of an industry by the
Enhancement of the performance of an industry by theEnhancement of the performance of an industry by the
Enhancement of the performance of an industry by the
 
Tqm intro
Tqm introTqm intro
Tqm intro
 
IRJET- Application of Quality Function Deployment (QFD) in Aluminium Pot Manu...
IRJET- Application of Quality Function Deployment (QFD) in Aluminium Pot Manu...IRJET- Application of Quality Function Deployment (QFD) in Aluminium Pot Manu...
IRJET- Application of Quality Function Deployment (QFD) in Aluminium Pot Manu...
 
Total Quality Management
Total Quality Management Total Quality Management
Total Quality Management
 
Implementation and financial accounting of quality training and education
Implementation and financial accounting of quality training and educationImplementation and financial accounting of quality training and education
Implementation and financial accounting of quality training and education
 
Baldrige vs deming
Baldrige vs demingBaldrige vs deming
Baldrige vs deming
 
Total quality management models
Total quality management modelsTotal quality management models
Total quality management models
 
5.Achievement of TQM in Organization
5.Achievement of TQM in Organization5.Achievement of TQM in Organization
5.Achievement of TQM in Organization
 
Study on the Impact of ISO Certification on the Quality Culture of Constructi...
Study on the Impact of ISO Certification on the Quality Culture of Constructi...Study on the Impact of ISO Certification on the Quality Culture of Constructi...
Study on the Impact of ISO Certification on the Quality Culture of Constructi...
 
IRJET- A Study on Quantification of Factors Affecting the Quality of Construc...
IRJET- A Study on Quantification of Factors Affecting the Quality of Construc...IRJET- A Study on Quantification of Factors Affecting the Quality of Construc...
IRJET- A Study on Quantification of Factors Affecting the Quality of Construc...
 
Unit-I Introduction
Unit-I  IntroductionUnit-I  Introduction
Unit-I Introduction
 
2011-01-01 published journal article hande yilmaz
2011-01-01 published journal article hande yilmaz2011-01-01 published journal article hande yilmaz
2011-01-01 published journal article hande yilmaz
 
A working definition for total quality management (tqm) researchers
A working definition for total quality management (tqm) researchers A working definition for total quality management (tqm) researchers
A working definition for total quality management (tqm) researchers
 
Quality management and performance a review
Quality management and performance a reviewQuality management and performance a review
Quality management and performance a review
 
hand book
hand bookhand book
hand book
 

Viewers also liked

Simulation of Signals with Field Signal Simulator
Simulation of Signals with Field Signal SimulatorSimulation of Signals with Field Signal Simulator
Simulation of Signals with Field Signal SimulatorIOSR Journals
 
Bandwidth enhancement of rectangular microstrip patch antenna using slots
Bandwidth enhancement of rectangular microstrip patch antenna using slotsBandwidth enhancement of rectangular microstrip patch antenna using slots
Bandwidth enhancement of rectangular microstrip patch antenna using slotsIOSR Journals
 
Identification and Monitoring the Change of Land Use Pattern Using Remote Sen...
Identification and Monitoring the Change of Land Use Pattern Using Remote Sen...Identification and Monitoring the Change of Land Use Pattern Using Remote Sen...
Identification and Monitoring the Change of Land Use Pattern Using Remote Sen...IOSR Journals
 
“Study The Different Parameters of Sewage Treatment With UASB & SBR Technolog...
“Study The Different Parameters of Sewage Treatment With UASB & SBR Technolog...“Study The Different Parameters of Sewage Treatment With UASB & SBR Technolog...
“Study The Different Parameters of Sewage Treatment With UASB & SBR Technolog...IOSR Journals
 
Prevention of Selective Jamming Attacks by Using Packet Hiding Methods
Prevention of Selective Jamming Attacks by Using Packet Hiding MethodsPrevention of Selective Jamming Attacks by Using Packet Hiding Methods
Prevention of Selective Jamming Attacks by Using Packet Hiding MethodsIOSR Journals
 

Viewers also liked (20)

Simulation of Signals with Field Signal Simulator
Simulation of Signals with Field Signal SimulatorSimulation of Signals with Field Signal Simulator
Simulation of Signals with Field Signal Simulator
 
D010111822
D010111822D010111822
D010111822
 
G017375362
G017375362G017375362
G017375362
 
H1802054851
H1802054851H1802054851
H1802054851
 
B017140612
B017140612B017140612
B017140612
 
A017150107
A017150107A017150107
A017150107
 
K0111199101
K0111199101K0111199101
K0111199101
 
Bandwidth enhancement of rectangular microstrip patch antenna using slots
Bandwidth enhancement of rectangular microstrip patch antenna using slotsBandwidth enhancement of rectangular microstrip patch antenna using slots
Bandwidth enhancement of rectangular microstrip patch antenna using slots
 
E1804012536
E1804012536E1804012536
E1804012536
 
H017545662
H017545662H017545662
H017545662
 
Identification and Monitoring the Change of Land Use Pattern Using Remote Sen...
Identification and Monitoring the Change of Land Use Pattern Using Remote Sen...Identification and Monitoring the Change of Land Use Pattern Using Remote Sen...
Identification and Monitoring the Change of Land Use Pattern Using Remote Sen...
 
B1303070716
B1303070716B1303070716
B1303070716
 
“Study The Different Parameters of Sewage Treatment With UASB & SBR Technolog...
“Study The Different Parameters of Sewage Treatment With UASB & SBR Technolog...“Study The Different Parameters of Sewage Treatment With UASB & SBR Technolog...
“Study The Different Parameters of Sewage Treatment With UASB & SBR Technolog...
 
H012225053
H012225053H012225053
H012225053
 
Prevention of Selective Jamming Attacks by Using Packet Hiding Methods
Prevention of Selective Jamming Attacks by Using Packet Hiding MethodsPrevention of Selective Jamming Attacks by Using Packet Hiding Methods
Prevention of Selective Jamming Attacks by Using Packet Hiding Methods
 
G012465564
G012465564G012465564
G012465564
 
B018140813
B018140813B018140813
B018140813
 
D017372538
D017372538D017372538
D017372538
 
M010427686
M010427686M010427686
M010427686
 
U180304130141
U180304130141U180304130141
U180304130141
 

Similar to H012125765

Study on negligence of quality assurance and proposing an effective framework...
Study on negligence of quality assurance and proposing an effective framework...Study on negligence of quality assurance and proposing an effective framework...
Study on negligence of quality assurance and proposing an effective framework...eSAT Journals
 
QUALITY MANAGEMENT PRACTICES OF CONTRACTING FIRMS IN BUILDING PROJECT DELIVERY
QUALITY MANAGEMENT PRACTICES OF CONTRACTING FIRMS IN BUILDING PROJECT DELIVERYQUALITY MANAGEMENT PRACTICES OF CONTRACTING FIRMS IN BUILDING PROJECT DELIVERY
QUALITY MANAGEMENT PRACTICES OF CONTRACTING FIRMS IN BUILDING PROJECT DELIVERYIAEME Publication
 
Implementing total quality management to improve facilities
Implementing total quality management to improve facilitiesImplementing total quality management to improve facilities
Implementing total quality management to improve facilitiesLaukik Raut
 
TQM in Construction Management A Review
TQM in Construction Management A ReviewTQM in Construction Management A Review
TQM in Construction Management A Reviewijtsrd
 
Total quality management practices in construction companies kerala
Total quality management practices in  construction companies keralaTotal quality management practices in  construction companies kerala
Total quality management practices in construction companies keralaIAEME Publication
 
Critical success factors of Total Quality Management implementation in Indian...
Critical success factors of Total Quality Management implementation in Indian...Critical success factors of Total Quality Management implementation in Indian...
Critical success factors of Total Quality Management implementation in Indian...IRJET Journal
 
Quality Management System at Construction Project: A Questionnaire Survey
Quality Management System at Construction Project: A Questionnaire SurveyQuality Management System at Construction Project: A Questionnaire Survey
Quality Management System at Construction Project: A Questionnaire SurveyIJERA Editor
 
IRJET- Total Quality Management based Improvement of Teaching and Learnin...
IRJET-  	  Total Quality Management based Improvement of Teaching and Learnin...IRJET-  	  Total Quality Management based Improvement of Teaching and Learnin...
IRJET- Total Quality Management based Improvement of Teaching and Learnin...IRJET Journal
 
StudyofQualityManagementinConstructionProjects[1].pdf
StudyofQualityManagementinConstructionProjects[1].pdfStudyofQualityManagementinConstructionProjects[1].pdf
StudyofQualityManagementinConstructionProjects[1].pdfssuser4a1ad9
 
IRJET- Construction Quality Management on Site
IRJET-  	  Construction Quality Management on SiteIRJET-  	  Construction Quality Management on Site
IRJET- Construction Quality Management on SiteIRJET Journal
 
TQM: A Quality and Performance Enhancer
TQM: A Quality and Performance EnhancerTQM: A Quality and Performance Enhancer
TQM: A Quality and Performance Enhancerinventy
 
045 INTERGRATING SCN WITH JIT AND TQM
045 INTERGRATING SCN WITH JIT AND TQM 045 INTERGRATING SCN WITH JIT AND TQM
045 INTERGRATING SCN WITH JIT AND TQM Dr Fereidoun Dejahang
 
045 integrating scm with jit and tqm
045 integrating scm with jit and tqm045 integrating scm with jit and tqm
045 integrating scm with jit and tqmdrdej19
 
A project report on TQM by Abhinandan Kumar
A project report on TQM by Abhinandan KumarA project report on TQM by Abhinandan Kumar
A project report on TQM by Abhinandan KumarAbhinandan Kumar
 

Similar to H012125765 (20)

Study on negligence of quality assurance and proposing an effective framework...
Study on negligence of quality assurance and proposing an effective framework...Study on negligence of quality assurance and proposing an effective framework...
Study on negligence of quality assurance and proposing an effective framework...
 
QUALITY MANAGEMENT PRACTICES OF CONTRACTING FIRMS IN BUILDING PROJECT DELIVERY
QUALITY MANAGEMENT PRACTICES OF CONTRACTING FIRMS IN BUILDING PROJECT DELIVERYQUALITY MANAGEMENT PRACTICES OF CONTRACTING FIRMS IN BUILDING PROJECT DELIVERY
QUALITY MANAGEMENT PRACTICES OF CONTRACTING FIRMS IN BUILDING PROJECT DELIVERY
 
Implementing total quality management to improve facilities
Implementing total quality management to improve facilitiesImplementing total quality management to improve facilities
Implementing total quality management to improve facilities
 
120 tqm-constructability-bar chart
120 tqm-constructability-bar chart120 tqm-constructability-bar chart
120 tqm-constructability-bar chart
 
17 1st review
17 1st review17 1st review
17 1st review
 
TQM in Construction Management A Review
TQM in Construction Management A ReviewTQM in Construction Management A Review
TQM in Construction Management A Review
 
Total quality management practices in construction companies kerala
Total quality management practices in  construction companies keralaTotal quality management practices in  construction companies kerala
Total quality management practices in construction companies kerala
 
G037036048
G037036048G037036048
G037036048
 
Critical success factors of Total Quality Management implementation in Indian...
Critical success factors of Total Quality Management implementation in Indian...Critical success factors of Total Quality Management implementation in Indian...
Critical success factors of Total Quality Management implementation in Indian...
 
Au4102342349
Au4102342349Au4102342349
Au4102342349
 
Quality Management System at Construction Project: A Questionnaire Survey
Quality Management System at Construction Project: A Questionnaire SurveyQuality Management System at Construction Project: A Questionnaire Survey
Quality Management System at Construction Project: A Questionnaire Survey
 
IRJET- Total Quality Management based Improvement of Teaching and Learnin...
IRJET-  	  Total Quality Management based Improvement of Teaching and Learnin...IRJET-  	  Total Quality Management based Improvement of Teaching and Learnin...
IRJET- Total Quality Management based Improvement of Teaching and Learnin...
 
StudyofQualityManagementinConstructionProjects[1].pdf
StudyofQualityManagementinConstructionProjects[1].pdfStudyofQualityManagementinConstructionProjects[1].pdf
StudyofQualityManagementinConstructionProjects[1].pdf
 
A project report on TQM
A project report on TQMA project report on TQM
A project report on TQM
 
IRJET- Construction Quality Management on Site
IRJET-  	  Construction Quality Management on SiteIRJET-  	  Construction Quality Management on Site
IRJET- Construction Quality Management on Site
 
TQM: A Quality and Performance Enhancer
TQM: A Quality and Performance EnhancerTQM: A Quality and Performance Enhancer
TQM: A Quality and Performance Enhancer
 
USE OF ANDROID TOOL FOR QUALITY CONSTRUCTION
USE OF ANDROID TOOL FOR QUALITY CONSTRUCTIONUSE OF ANDROID TOOL FOR QUALITY CONSTRUCTION
USE OF ANDROID TOOL FOR QUALITY CONSTRUCTION
 
045 INTERGRATING SCN WITH JIT AND TQM
045 INTERGRATING SCN WITH JIT AND TQM 045 INTERGRATING SCN WITH JIT AND TQM
045 INTERGRATING SCN WITH JIT AND TQM
 
045 integrating scm with jit and tqm
045 integrating scm with jit and tqm045 integrating scm with jit and tqm
045 integrating scm with jit and tqm
 
A project report on TQM by Abhinandan Kumar
A project report on TQM by Abhinandan KumarA project report on TQM by Abhinandan Kumar
A project report on TQM by Abhinandan Kumar
 

More from IOSR Journals (20)

A011140104
A011140104A011140104
A011140104
 
M0111397100
M0111397100M0111397100
M0111397100
 
L011138596
L011138596L011138596
L011138596
 
K011138084
K011138084K011138084
K011138084
 
J011137479
J011137479J011137479
J011137479
 
I011136673
I011136673I011136673
I011136673
 
G011134454
G011134454G011134454
G011134454
 
H011135565
H011135565H011135565
H011135565
 
F011134043
F011134043F011134043
F011134043
 
E011133639
E011133639E011133639
E011133639
 
D011132635
D011132635D011132635
D011132635
 
C011131925
C011131925C011131925
C011131925
 
B011130918
B011130918B011130918
B011130918
 
A011130108
A011130108A011130108
A011130108
 
I011125160
I011125160I011125160
I011125160
 
H011124050
H011124050H011124050
H011124050
 
G011123539
G011123539G011123539
G011123539
 
F011123134
F011123134F011123134
F011123134
 
E011122530
E011122530E011122530
E011122530
 
D011121524
D011121524D011121524
D011121524
 

Recently uploaded

Hyderabad Call Girls Khairatabad ✨ 7001305949 ✨ Cheap Price Your Budget
Hyderabad Call Girls Khairatabad ✨ 7001305949 ✨ Cheap Price Your BudgetHyderabad Call Girls Khairatabad ✨ 7001305949 ✨ Cheap Price Your Budget
Hyderabad Call Girls Khairatabad ✨ 7001305949 ✨ Cheap Price Your BudgetEnjoy Anytime
 
Key Features Of Token Development (1).pptx
Key  Features Of Token  Development (1).pptxKey  Features Of Token  Development (1).pptx
Key Features Of Token Development (1).pptxLBM Solutions
 
Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxOnBoard
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Alan Dix
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking MenDelhi Call girls
 
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024BookNet Canada
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersThousandEyes
 
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptx
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptxMaking_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptx
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptxnull - The Open Security Community
 
How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?XfilesPro
 
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024BookNet Canada
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesSinan KOZAK
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...HostedbyConfluent
 
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreternaman860154
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationMichael W. Hawkins
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):comworks
 
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Patryk Bandurski
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slidespraypatel2
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsMark Billinghurst
 

Recently uploaded (20)

Hyderabad Call Girls Khairatabad ✨ 7001305949 ✨ Cheap Price Your Budget
Hyderabad Call Girls Khairatabad ✨ 7001305949 ✨ Cheap Price Your BudgetHyderabad Call Girls Khairatabad ✨ 7001305949 ✨ Cheap Price Your Budget
Hyderabad Call Girls Khairatabad ✨ 7001305949 ✨ Cheap Price Your Budget
 
Key Features Of Token Development (1).pptx
Key  Features Of Token  Development (1).pptxKey  Features Of Token  Development (1).pptx
Key Features Of Token Development (1).pptx
 
Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptx
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
 
The transition to renewables in India.pdf
The transition to renewables in India.pdfThe transition to renewables in India.pdf
The transition to renewables in India.pdf
 
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptx
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptxMaking_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptx
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptx
 
How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?
 
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen Frames
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
 
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreter
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):
 
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slides
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR Systems
 

H012125765

  • 1. IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE) e-ISSN: 2278-1684,p-ISSN: 2320-334X, Volume 12, Issue 1 Ver. II (Jan- Feb. 2015), PP 57-65 www.iosrjournals.org DOI: 10.9790/1684-12125765 www.iosrjournals.org 57 | Page Evaluation of Total Quality Management Implementation as Engineering Practices in Jordanian Construction Projects Jumah M.Th. Al-Dulaimy1 , Faithy Alkhazraji2 , Rami H. ALHadeethi3 , Jamal O. Sameer4 1Department of planning, Education Ministry , Al-anbar, Iraq 2Isra University ,Amman, Jordan 3Al-hashimya University,Amman, Jordan 4Universiti Tenaga Nasional, Kuala Lumpur, Malaysia Abstract:The construction sector is one of the most important business fields in Jordan and this sector is suffering from many problems in Management and quality. Total quality management (TQM) process is considered as a modern system in the field of quality. The purpose of this paper is to evaluate TQM implementation as engineering practices in different construction projects phases. In order to achieve this objective, literature review has been carried out to identify the two main factors influencing the implementation of TQM factors in the construction process: (continuous improvement, customer satisfaction) . And by examining the four ISO 9001-2008 requirements to achieve important TQM factors in construction process. In this study, the data was collected by a questionnaire survey, the survey analyzed by statistical software SPSS. More than 204 questionnaire forms were distributed, 177 was responded which was represented 86 % of the total spread questionnaire forms, the respondents were engineers only(Civil, Mechanical, Electrical and Architectural). By analyses of results, the study showed that TQM implementation level in all construction projects phases was moderate in Jordanian construction process. Key words: Total quality management, ISO 9001-2008,Customer Satisfaction, Continues Improvement. I. Introduction: The main attention of total quality management (TQM) and its application in construction projects to establishment of high-quality facilities and Raise the performance level in construction Process.TQM appears to be a very important concept which is difficult to summarize in a short definition. TQM is a process lead by senior management to obtain involvement of all employees in the continuous improvement of the performance of all activities. Therefore, this studyevaluated the two main TQM factors in construction project (customer satisfaction and continuous improvement) by examining the apply of four ISO 9001-2008 requirement during different project phases. Because of instability in the Middle East, especially wars in Iraq, Syria, Lebanon, Palestine, has resulted in an increased immigration percentage in the recent years to Jordan. This big number of people has increased the demand to develop the country infrastructure, in addition to the necessary needs such as, houses, hospitals, hotels, schools and entertainment places. So it's important to adopt TQM concept which affecting positively on the entire construction industry and company reputations, with a result that caused a rapid rise in the quality scale to the highest level (Bani Ismail,2012). Despite the international adoption of the TQM concept, it has not been developed within the Arab area , as a result from the lack of basic knowledge of TQM and low level of organization’ readiness for change(Haffar,2010). II. Literature Review: TQM is one of most important techniques to improve quality, which many organizations and companies are using to reach success. thewide implementation for TQMall through the world in different sectors andindustries. The positive results appeared in these sectorsandindustries because of TQM implementation (Bhat and Rajashekhar, 2009). The purpose or function of TQM is to provide a high quality product to the customers, in turn increase the productivity also customer satisfaction ,furthermore decrease the cost With lower price anda higher quality
  • 2. Evaluation of Total Quality Management Implementation as Engineering Practices in …. DOI: 10.9790/1684-12125765 www.iosrjournals.org 58 | Page product, TQM is approach of managing different industries to improve the quality of product (Kumar, et al., 2011). And its show Establish strategic goals, mission and vision based on the concept of TQM and bind all parties together including subcontractors of these goals. The Organizations need to follow continuous improvement while maintaining a long-term Perspective. The improvement will have to be made both in the processes and the organizational system in order to make the TQM program successful(Al-Tayeb Mustafa,2008) (TQM) Total quality management is defined as both a management of quality philosophy and group of guiding principles that promoteculture in organizations and all members participation in organization aiming to achieve longtermsuccessprocess through continuous improvement and customer satisfaction of products, and the benefits for all society members (Juran et al., 1999; Rampersad, 2001;Besterfield et al., 2003) III. Definitions of Total Quality Management The Asian Institute of Technology (AIT), define TQM as “a philosophy that strengthens and support the culture to foster continuous organizational improvement through integrated, systematic, consistent and reliable effort involving everything and everyone, focusing primarily on total satisfaction of internal and external customers, where employees work together in teams with process ownership, guided by a committed top management, which takes a practical participation” (Nukulchai,2003). Also, according to the British Quality Association defines TQM as “an all-agreement business management philosophy focusing on completely fulfilling customer requirements with a maximum of effectiveness and efficiency" (Wessel, 2004). According the previous definitions, define the TQM as a philosophy but the different point of view. British Standard(BS) described the TQM as the management philosophy aimed to achieve organization objectives. While, the (AIT), defined the TQM as the philosophy aiming to satisfy the customers. Out of above definitions, aneasy definition of TQM is a get-together of external and internal customer requirements, and the difference between quality and TQM is that the quality expression generally focuses on a temporary process. In construction project for example, in order to achieve a good strength for concrete according to the specifications, the concrete should be cured by water for(3-4)days, to reached for the required quality, so this is a temporary process, while TQM is a long term process and adopts a strategic dimension, to lead each financial, production, marketing and managerial plan in the path which support the strategic dimension. From the previous definitions, the researcher conclusion was that the definition of TQM is an old concept, but in last years it appears as an official job. Basics of TQM Principles in construction projects: The concept of TQM is modern in construction projects. It was only applied to industrial projects, the construction companies in the United States applied (TQM) after the noticed the great success of industrial companies by the application of the concept of TQM which is based on the achieving the basic principles: customer satisfaction, continuous improvement. These principles will be defined and clarified and how they will be applied in construction projects. (Gamld D. Oberlender 2000,) Customer Satisfaction: The basic function of the construction industry is to provide customers projects, facilities and services ready to use, and meet their requirements. Any construction company must be completed its work at a competitive cost to guarantee continuous work. TQM is a management philosophy based on identifying customer needs and requirements exactly and work to make suitable environment and working conditions suitable to achieve the needs and requirements at the lowest possible cost, by quality control at every stage of the construction process. While the construction project is an idea to close out and ready for use, this quality of the final product will be satisfy the customer needs. Continues Improvement: To Continues Improvement we have to: -Continuous improvement for current methods and procedures and to keep existed improvements during the product processing control. -Concentrate on achieving technological development in construction and engineering process during innovation and creation. The construction project consists of a group of activities so we want to develop, innovate and create in each activity to achieve quality and fulfill customer satisfaction. During each activity implementation we have to reduce gap between the customer requirements and current status, during the use of problem analysis process by using Deming cycle "Plan-do-check-act", which its
  • 3. Evaluation of Total Quality Management Implementation as Engineering Practices in …. DOI: 10.9790/1684-12125765 www.iosrjournals.org 59 | Page considered as a procedure for continuous improvement by concentrate on correction procedure and defect prevention. Deming cycle contain four process Occur every time and constantly repeated and apply it in each process as show in Figure(1),and Table (1) show Eight steps for each Deming cycle process . Figure (1)Eight steps for each Deming cycle process Table (1) shows Eight steps for each Deming cycle process . -Identify the problem and improvement aim. -Analyze the current status -Determine the root causes and its affect -Develop plans for corrective works Plan -Apply the plan and its implementation.Do -Document the implementation plan result to compare it with main plan aim.Check -Create the criteria for the necessary steps to avoid problem repeated -Reprocess and take in consecration rest of problems or suitable improvement in the next plan stage. Act ISO 9001-2008 ISO 9001:2008 it’s the last version sets out the criteria for a quality management system and conceder only standard in the family that can be certified. It can be used by large or smallorganization, regardless of its field of activity. Moreover, the ISO 9001:2008 is implemented by over one million companies and organizations in over 170 countries (ISO technical committee.2008) There are four ISO 9001-2008 requirements to Achieve TQM important factors in construction projects. (The continuous improvement and customer satisfaction) as shown in Figure (2):(International standard ISO 9001, 2008). 1. Management responsibility. 2. Resource management. 3. Product realization. Each of The four ISO(9001-2008)requirements includes a number of elements 4. Measurement, analysis and improvement.
  • 4. Evaluation of Total Quality Management Implementation as Engineering Practices in …. DOI: 10.9790/1684-12125765 www.iosrjournals.org 60 | Page Figure (2) Questionnaire design Questions in a questionnaire were formulated based on the literature review as main sources to get the initial form of questionnaire; the Figure ( 3 ) shows the questionnaire development process. Figure (3) Questionnaire design Results of factor analysis: The result of the output obtained in this research could be presented as followed:The items in the survey were made on a five points likert scale where 5 implied strongly agree, and 1 Indicated the respondent strongly disagree with the statements. The item of the questionnaire was conducted by using SPSS package version 16.0 to detect the factor structure in the variable and Table ( 2 ) show the mean, Standard deviation and Skewnessvalues for all project phases: Contract documentDesignStudy SkSdMSkSdMSkSdMSt. Dis. -0.220.823.15-0.120.693.17-0.020.643.33M.R 0.040.723.160.050.763.24-0.040.723.13R.M -0.180.813.18-0.270.773.38-0.200.553.48P.R -0.100.743.25-0.440.753.38-0.090.813.03M&A -0.050.703.19-0.290.613.29-0.110.553.24Overall
  • 5. Evaluation of Total Quality Management Implementation as Engineering Practices in …. DOI: 10.9790/1684-12125765 www.iosrjournals.org 61 | Page Close outImplementationContractor Selection SkSdMSkSdMSkSdMSt. Dis. -0.210.833.21-0.160.683.130.200.792.86M.R 0.390.753.14-0.090.733.090.210.743.17R.M -0.070.843.19-0.360.753.26-0.250.703.27P.R -0.181.013.150.090.663.000.180.693.27M&A 0.090.753.17-0.180.633.120.300.553.14Overall Table ( 2 ) Statically descriptive for different project phases Evaluation of TQM Implantation as engineering practice The stages were divided in the questionnaire to six phases. In addition to that, the classifications for mean values in the upcoming Tables will be based on the following criteria as suggested by researcher as shown in Table (3): Table (3) Evaluation level Category Weak Moderate High Mean < 3 3 – 4 <4 TQM factors were then analyzed according to six construction projects phases as in the following: - Study phase conclude from Figure(4) that all mean values are moderate in all ISO requirments (management responsibility and product realization) but in resources management there are two values under the mean (weak evaluation) ,at which There was a shortage in work invironmental analysis and resources procurement. In (Measurement and alanlyisis) there was no study review and check by any neutral part. Figure(4)Current state of TQM in study Phase In general the overall TQM implementation factors in study phase is moderate. 3.9.2 Design phase According to Figure(5), that all mean values are moderate in all ISO requirments (resources management, product realization and measurement and analysis ) but in Management Responsibility there are three values under the mean (weak evaluation) at which insufficient responsibility and Authorization ,lack communucation and design change approval.
  • 6. Evaluation of Total Quality Management Implementation as Engineering Practices in …. DOI: 10.9790/1684-12125765 www.iosrjournals.org 62 | Page Figure(5) Current state of TQM in designphase. In general the overall TQM implementation factors in design phase is moderate. 3.9.3 Contract documentsphase According to Figure(6), that all mean values are moderate in all ISO requirements (management responsibility,resources management, product realization and measurement and analysis). Figure(6)Current state of TQM in contractdocumentsphase In general the overall TQM implementation factors in contract documants phase are moderate Contractor selection phase According to Figure(7) that all mean values are moderate in all ISO requirments (resources management, product realization and measurement and analysis) but in management responsibility there are three values under the mean (weak evaluation) at which the contractor was sellected according to financial categories rather than experience and insufficient responsibility and Authorization .
  • 7. Evaluation of Total Quality Management Implementation as Engineering Practices in …. DOI: 10.9790/1684-12125765 www.iosrjournals.org 63 | Page Figure(7)Current state of TQM in contractor selection phase In general the overall TQM implementation factors in contractor sellection phase is moderate. Implementation phase conclude from Figure(8),that overall mean value for management responsibility is moderate but four values are considered (weak) due to improper cash flow, no detailed project's budget , lack of communication among project parties and lack of commitment inproject duration.That overall mean value for resources management is moderate but there are five values considered (weak) mean value. Such as poor raw material quality ,there is no technical staff,inappropriate labor wages ,shortage in site mobilization and poor safety procedures.The overall mean value for product realization is moderate but there is one low value(weak)at which no control and analysis for construction test.The overall mean value for measurement and analysis has a moderate mean value but there are two values with low mean value (weak) at which there is a lack in check and test to diagnose the defects ,and no preventive procedures .
  • 8. Evaluation of Total Quality Management Implementation as Engineering Practices in …. DOI: 10.9790/1684-12125765 www.iosrjournals.org 64 | Page Figure(8) Current state of TQM in implementation Phase In general the overall TQM implementation factors in implementation phase is moderate. Close out phase According to Figure (9) that all mean values are moderate in all ISO requirements (management responsibility, product realization and measurement and analysis) but resources management has one value under the mean (weak evaluation) at which the there is a lack in staff training. Figure(9) Current state of TQM in close outphase In general the overall TQM implementation factors in close out phase is moderate. IV. Conclusion: 1) TQM factors applied in the Jordanian construction projects are classified as a moderate level because some of (four ISO requirement) in the project phases are weak. 2) In study phase found that there a huge weakness in the analysis of work environment, there is no third or other neutral part are checking the Study, and the owner satisfaction is adopting as criterion of effective performance criteria in quality management system. 3) In design phase there is a big weakness because of authorizing some responsibilities and authorities from top Management to the designer to ensure work efficiency, also lack in coordination between the owner and designer will affect the project completion according to the requirements, but the designdocumentswere clear and suitable for requirements. 4) Contract documents phase was the best among the different phases, where the documents are approved before concluding the contract; also take advantage of previous contracts to develop the final form of the contract. 5) There is a large shortage of management responsibility in contractor selection phase, found that the contractor selection was not according to experience, efficiency and price , contractor select was according to the lowest total price only, but the feature of this phase is there are a third party to resolving disputes if there. 6) The implementation phase was the worst among the other phases where : a) There is huge weakness in the four ISO requirements to apply TQM factors application in this phase. b) Also found that no interest of using high quality raw materials. c) There is no enough coordinate to information exchange and Periodic meetings between the project parties (owner, designer and executer). d) The working staff wagesare not appropriate with the assigned to it works to ensure quality, also weakness in health and safety standards in the projects. e) Weak in monitoring and analyzing construction tests to measure the conformity with the specifications and lack in the preventive procedures to guarantee avoiding the no confirm occurring.
  • 9. Evaluation of Total Quality Management Implementation as Engineering Practices in …. DOI: 10.9790/1684-12125765 www.iosrjournals.org 65 | Page 7) In close out phase the training sessions are not available for the working staff to improve their qualifications, there is a concern to make the contractor to repair the diagnosed defects before the facility occupied, impose discounts when found nonconforming product for the owner requirements. Refrence [1]. Bani Ismail, Loiy (2012), An evaluation of the implementation of Total Quality Management (TQM) within the construction sector in the United Kingdom and Jordan, Doctoral thesis, University of Huddersfield [2]. Haffar, Mohamed (2010),The Influence of Organizational Culture on Total QualityManagement Implementation in Syrian Public Manufacturing Organizations, BrunelUniversity. [3]. Bhat, K.S. and J. Rajashekhar, 2009. " An empirical study of barriers to TQM implementation in Indianindustries", The TQM Magazine, 21(3): 261-272. [4]. Das, A., V. Kumar and U. Kumar, 2011. "The role of leadership competencies for implementing TQM(Anempirical study in Thai manufacturing industry) ", International Journal of Quality & Reliability Management,28(2): 195-219. [5]. Al-Tayeb ,Mustafa (2008), Critical Success Factors of TQM Implementation on Construction Projects in Gaza Strip. Master thesis, The Islamic University – Gaza. [6]. Nukulchai, W. K. (2003), Towards Total Quality Management in Higher Education: The Experience of Asian Institute of Technology. Asian Institute of Technology. [7]. Wessel,G, and Burcher,P.(2004), Six Sigma for Small and Medium-Sized Enterprises. The TQM Magazine, volume 16 No.4, pp.264 - 272. [8]. Oberlender, Garold D. (2000),PROJECT MANAGEMENT FOR ENGINEERING AND CONSTRUCTION..Oklahoma State University. [9]. Juran, J. and Godfrey, A. (eds.) (1999). Juran’s Quality Handbook, 5th edition. New York: McGraw-Hill. [10]. Rampersad, H. (2001). Total Quality Management: an Executive Guide to Continuous Improvement. New York: Springer. [11]. Besterfield, D., Besterfield-Michna, C., Nesterfield, G. and Besterfirld-Sccre, M. (2003). Total Quality Management, 3rd Edition. New Jersey: Prentice Hall. [12]. Internet Articles based on print sourceISO technical committee, (2008), (TC) ISO/TC 176, sub-committee, from web site: http://www.iso.org/iso/iso_9000