SlideShare a Scribd company logo
International Journal of Electrical and Computer Engineering (IJECE)
Vol. 7, No. 2, April 2017, pp. 729~740
ISSN: 2088-8708, DOI: 10.11591/ijece.v7i2.pp729-740  729
Journal homepage: http://iaesjournal.com/online/index.php/IJECE
Generator Assessment of Hydro Power Station Adequacy after
Reconstruction from Classical to HIS SF6 Substation
Srete Nikolovski1
, Goran Slipac2
, Emir Alibašić3
1
Faculty of Electrical Engineering, Computer Science and Information Technology, University of Osijek, Croatia
2
Croatian National Grid Company- HEP Inc., Zagreb, Croatia
3
ZZO Tuzla Kanton, Tuzla, Bosnia and Herzegovina
Article Info ABSTRACT
Article history:
Received Dec 9, 2016
Revised Mar 12, 2017
Accepted Mar 26, 2017
Reliability analysis of substations and generator assessment of power plant
stations are very important elements in a design and maintenance process.
This paper presents a generator adequacy assessment of a classical “H”
scheme for an open conventional substation, which is often used, and a new
HIS - High Integrated Switchgear with SF6 gas isolation. Generator
adequacy indices of both types of classical and HIS switchgear were
compared and the results showed a high level of reliability and availability of
the HIS presented substation. The input data were the annual reports of
Croatian TSO-Transmission System Operator (HOPS) and statistics of
operation events of Croatian National Electricity (HEP Inc.). For the HIS
substation, the input reliability data were used from relevant international
literature since only few of HIS substations are installed in Croatia. The
generator is modelled with a three-state Markov state space model and Monte
Carlo simulations were used for the generator assessment analysis. Adequacy
indices LOLP and EDNS were obtained using DIgSILENT software.
Keyword:
Adequacy indices
Classical substation
Computer simulation
Generator adequacy
High integrated SF6 substation
Markov state spece model
Monte Carlo simulation,
Copyright © 2017 Institute of Advanced Engineering and Science.
All rights reserved.
Corresponding Author:
Srete Nikolovski,
Faculty of Electrical Engineering,
Computer Science and Information Technology Osijek,
J.J. Strossmayer University of Osijek,
K. Trpimira 2 B, 31000 Osijek, Croatia.
Email: srete.nikolovski@etfos.hr
1. INTRODUCTION
During the analysis of the composite transmission system network reliability, it is generally not
enough to view the switchgears solely as network junction points, and thereby omit the influence of
individual switchgear components on the reliability of the system as a whole. Every switchgear configuration
has a significant impact on the occurrence of power line outages and consequently on the entire system
reliability [1], [2]. This especially concerns the multiple power line failures which considerably depend on
switchgear failures [3], [4]. The paper analyzes switchgear reliability using Mont Carlo, the loss of one
consumer and generator adequacy assessment using Monte Carlo simulation [5]. The basic definitions related
to modelling failures from a switchgear are as follows:
a. Switchgear components: transformers, circuit breakers, disconnectors and busbars; surge arresters, current
and load measuring transformers are usually omitted. The protection system is generally not taken into the
account;
b. Switchgear availability: the probability of presence of a corresponding electrical connection between
switchgear busbars from a HV to LV side;
c. Passive failure: unavailability is reduced to the faulty component (it does not cause a triping of
protection). It should be noted that the definitions of active and passive failures vary from an author to
author;
IJECE ISSN: 2088-8708 
Generator Assessment of Hydro Power Station Adequacy after Reconstruction from … (Srete Nikolovski)
730
d. Switching-off disabled: normally switched-on circuit breaker unable to switch-off upon demand;
e. Switching-on disabled: normally switched-off circuit breaker unable to switch-on upon demand;
f. Maintenance: a planned activity aiming at improving the condition of a component. It can be postponed if
required by switchgear conditions.
Generator adequacy assessment is a part of dependability evaluation (reliability, availability,
maintainability, and safety) [6]. The analysis is performed for the events of the first level of coincidence
which is a forced failure or switching-off of one component. The paper deals with the generator adequacy
assessment connected on a substation using a computer software. The load in a substation is modelled with a
load duration curve which is then modelled with different load states considered in the generator assessment
analysis using Monte Carlo simulation [7-8]. The paper includes the generator assessment analysis using a
sequential Monte Carlo simulation module in DIgSILENT Power factory software [9].
2. MARKOV STATE SPACE MODEL FOR BUSBARS AND TRANSFORMERS WITHIN THE
SWITCHGEAR
Busbars and transformers, as renewable components, with regard to reliability of supply, can have
two different states – they are either available or unavailable. A two-states component model is the most
oftenly used model since it gives the best description of the continuous operation of a component. It is
presented in Figure 1.
Figure 1. Model of a component with two states
Symbols:
1 - operation state of a component;
2 - component in a failure state;
 - component failure intensity;
 - component repair intensity.
Probability of being in a state 1 and 2 is:



1P



2P (1)
Frequency of being in a state 1 and 2 is defined as follows:




 11 Pf




 22 Pf (2)
3. MODEL OF A SYSTEM WITH TWO COMPONENTS
The model presented in Figure 2 shows the state of two different components - each component can
be either ready to operate or not ready to operate (a coincidence of a transformer and busbar failure).
 ISSN:2088-8708
IJECE Vol. 7, No. 2, April 2017 : 729–740
731
Figure 2. Model of two components with four states
This model is applied during the analysis of switchgear failures for transformer and busbar failure
coincidence. The basic premise of all considerations is that the possibility that two or more events take place
simultaneously is ruled out. Consequently, the possibilities of direct transitions between states 1 and 4, i.e. 2
and 3 within the model are ruled out.
Symbols:
A - first component; B – second component;
1 – components A and B in operation;
2 – component A faulty and B in operation;
3 – component A working and B faulty;
4 - components A and B faulty;
1and 1 - failure and repair intensity of component A;
2 and 2 - failure and repair intensity of component B.
Stationary system solutions, i.e. stationary probabilities of the states are:
))(())(())(())(( 2211
21
4
2211
21
3
2211
21
2
2211
21
1















 PPPP (3)
Since it had been shown earlier that the expressions:







 NA ; present stationary availability, that is,
unavailability of one component, the stationary probabilities of the states in the case of two-components
system can be expressed as follows:
214213212211 ;;; NNPNAPANPAAP  (4)
According to the model of a system with two different components, the frequency of an individual
state can be determined either as a product of the state probability and the sum of intensity of abandoning that
identical state, or as a product of the sum of intensity of entering the state and the probability of a state that is
being abandoned. Frequencies are equal regardless of being observed from a perspective of exits or from a
perspective of entrances. According to that, frequencies of states are as follows:
122121212144
122121212133
122121212122
122121212111
)()(
)()(
)()(
)()(
NfNfNNPf
AfNfNAPf
NfAfANPf
AfAfAAPf








(5)
4. MODEL OF COMPONENT WITH MAINTENANCE
Switchgear components count as renewable components and their maintenance (planned repair) is
carried out periodically. Maintenance of switchgear components increases their reliability and availability
AB
1
AB
2
1
AB
3
AB
4
1
2
2 2 2
1
2
IJECE ISSN: 2088-8708 
Generator Assessment of Hydro Power Station Adequacy after Reconstruction from … (Srete Nikolovski)
732
because the tendency of growth of failure intensity function is being reduced and maintained at a sufficiently
low constant value. Figure 3 shows the Markov state space model of a component with maintenance. It is
presumed that the planned repair of a component will not be performed when a component is not functional,
and upon finishing the repair, a component is again ready for the operation.
Figure 3. Model of component with maintenance
Symbols:
1- component in operation;
2- component A blocked;
3- component A under repair;
R and R - intensity of repair and repair completion of component A;
K and K - intensity of malfunction and repair of component A.
Stationary system solutions, i.e. stationary probabilities of the states are:
KRRKRK
KR
KRRKRK
RK
KRRKRK
RK
PPP











 321 (6)
Based on the earlier considerations, it follows that state “1“denotes component availability, state “2”
denotes a failure-induced component unavailability, and state “3” component unavailability due to repair:
RK NPNPAP  321 ;; (7)
Frequencies of failure and repair states are:
KRRKRK
KRR
rR
KRRKRK
RKK
KK
PPf
PPf










313
212
(8)
5. FAILURE COINCIDENCE MODEL WITH PLANNED MAINTENANCE
Preventive maintenance is conducted in order to keep the frequency of component failures at the
lowest possible level. However, when these coincide with failures of other components in the system, the
number of system failures may be increased. Thus, if possible, preventive maintenance and repairs should be
conducted when they would not have negative effects on the system. It is generally considered that once the
repair has been initiated, it has to be finished. Figure 4 shows a case of failure coincidence with the planned
maintenance. If the possibility of a transition from state “3” into state “4” is removed, then the request that
the repair cannot be initiated in state “3” is accepted, i.e. during the failure state of the other component.
However, if state “4” does not represent the system failure state, that transition is allowed and the failure and
repair processes are independent. The probabilities of being in certain states in case the transition from state
A
1
A
2

AR
3
R
R

 ISSN:2088-8708
IJECE Vol. 7, No. 2, April 2017 : 729–740
733
“3” into state “4” is allowed, since state “4” does not represent the system failure state are as follows:
))((
;
))((
))((
;
))((
43
21
BKBKARAR
BKAR
BKBKARAR
ARBK
BKBKARAR
BKAR
BKBKARAR
BKAR
PP
PP
















(9)
Figure 4. Failure coincidence model of the planned maintenance and repair with failure
Symbols:
1 - components A and B in operation;
2 - component A in repair and B in operation;
3 - component A in operation and B in failure;
4 - component A in repair and B in failure;
AR - component A repair intensity;
AR - component A repair intensity;
BK - component B failure intensity;
BK - component B repair intensity;
R - component repair intensity.
However, if state “4” also means system failure, the transition from state “3” into state “4” is not
allowed, which means that the frequency of repair of the first component in the third and fourth system
equation has a zero value ( ). In that case, the values are:
(10)
AR
*
 0
 
 
 
 BKARBKARBKARARBKBK
BKBKAR
BKARBKARBKARARBKBK
BKARBKARARBK
BKARBKARBKARARBKBK
BKARBKAR
BKARBKARBKARARBKBK
BKARBKBKAR
P
P
P
P



















)()(
)()(
)(
)()(
)(
)()(
)(
4
3
2
1
AB
1
ARB
2
AR
AB
3
ARB
4
AR
AR
BK BK BK
AR
BK
IJECE ISSN: 2088-8708 
Generator Assessment of Hydro Power Station Adequacy after Reconstruction from … (Srete Nikolovski)
734
Since the most common frequencies of the component repair and maintenance are significantly
higher than the respective frequencies of entering into those states, i.e. the multiple products of very small
values can be disregarded, the near solution values (10) are:
(11)
The frequency of the system failure, (failure and repair coincidence state) which also means the failure of the
system, is:
(12)
The mean time of failure coincidence with the planned maintenance and repair is:
(13)
6. GENERATOR MODEL WITH A DERATED STATE
Figure 5 shows the model of the component with the derated state (reduced capacity). It is assumed
that the transition of the component to the derated state from the forced outage is not allowed because it is
believed that during its stay in the forced outage, the repair is performed and that component is ready for the
operation with the rated capacity.
Figure 5. Generator model with one derated state
Symbols:
1 component A in operation;
2 component Ader1
in operation with the derated state;
3 component A in failure;
component A intensity of the derated state;
1der component A intensity of departure from the derated state;
 component A failure rate;
 component A repair rate:
The probabilities of being in a certain state are:


111
1
1
derderder
der
P




111
1
2
derderder
der
P


,
1
3
1 1 1
derP
der der der

     

 
(14)
)(
;;;1 4321
BKARAR
BKAR
BK
BK
AR
AR
PPPP









AR
BKAR
BKAR
BKARAR
BKAR
BKARPf





 )(
)(
)(44
BKAR
k
f
P
T


1
4
4
der1
der1
der1
1der
 ISSN:2088-8708
IJECE Vol. 7, No. 2, April 2017 : 729–740
735
The frequencies of generator states are:



111
11
312111
)(
)(
derderder
derder
derder PPPf


 (15)



111
11
12112
derderder
derder
derder PPf

 (16)



111
1
313
derderder
der
PPf

 (17)
The mean time of generators states:
 

11
1
1
1
derf
P
T ,
12
2
2
1
derf
P
T

 ,

1
3
3
3 
f
P
T (18)
7. DESCRIPTION OF A HYDRO POWER PLANT SUBSTATION
7.1. Basic Characteristics of the Previous Switchgear
It is placed at the level of 183,5 m in the narrow area between the engine room facility and building
entrance at the end of diversion channel [12]. The switchgear is in “H“ scheme with five feeders, two block
transformer feeders, each equipped with a circuit breaker, disconnectors, current measuring transformers and
surge arresters, two outgoing feeders equipped with outgoing disconnectors only, section feeder with a
diagonally placed disconnector for the connection between blocks, i.e. transmission lines. It is dimensioned
for short circuit power of 3500 MVA. The switchgear is connected to the Nedeljanec substation by 110 kV
double transmission line (Al/Fe 240/40 mm2
). Considering that outgoing feeders do not have circuit breakers
installed, distance protection in a hydro power plant works at the switching off of the circuit breaker in a
block transformer feeder and the circuit breaker in the outgoing feeder of Nedeljanec substation which in this
way represents distant busbars of this switchgear. Switchgear equipment is nearly 30 years old, except for the
new SF6 circuit breakers produced by “ABB” and installed four years ago in a place of the old pneumatic
circuit breakers 3P 123 type, produced by “Končar d.d“. The whole equipment is installed on the iron stands
made from steel pipes and profile, coated with anticorrosive paint, fixed to a concrete base with anchor bolts.
The connection of the devices is done by wires (Al/Fe 240/40 mm2
), i.e. AlMg  70 mm pipes. A busbar
system is carried out by wires attached above the devices by using double tension insulator strings with seven
glass insulators, type U 160 BS, on each of them. Busbars are attached to “T” portals made from welded iron
profiles. The classical 110 kV switchgear is designed for the outdoor use and shown in Figure 6.
Figure 6. Existing classical 110 kV switchgear
The 110 kV transmission line connections from Nedeljanec substation is carried out by the
attachment to the southern busbar portal. Block transformers with transmission ratio of 10,5/121 kV, vector
group Yd5, power 2×50 MVA, are placed at the level of 176 m, between the engine room facility and the
dam. They are connected to generator terminals by copper profile busbars. Although rationally placed in
IJECE ISSN: 2088-8708 
Generator Assessment of Hydro Power Station Adequacy after Reconstruction from … (Srete Nikolovski)
736
relation to the generator, due to an inadequately constructed oil pit, they are an ecological threat for the
environment in case of disasters since there is a possibility of transformer oil spill into the Drava river. Also,
in case of failure of a transformer with a tank crack, there is a possibility of flaming oil spreading onto the
generator and other equipment. The analysis of the outage caused by failures at the hydro electrical power
plant in the period from 2009 to 2013 shows the loss of supply of approximately 5 TWh of electrical energy,
out of which 82% are block transformer failures due to lightning strikes. Considering the age of the
equipment (about 30 years old), which is near the end of its life span, the stated manipulative possibilities and
operating conditions of the network, as well as the work safety at the hydro electrical power plant which
generates 100 MVA of electrical power, it is evident that it is necessary to reconstruct and modernize 110 kV
switchgear by replacing the old equipment and expanding the switchgear to a scheme that would enable
flexible manipulation without operation interruptions. Figure 7 shows single line scheme of the present
classical and the new HIS switchgear
Figure 7. Single line scheme of the present classical and the new HIS switchgear
7.2. Description of the new SF6 High Integrated Switchgear
The new metal enclosed SF6 gas insulated switchgear, high integrated for the outdoor installation
(HIS) at the new location will be installed on the concrete laminated foundation. The switchgear will be
constructed for the outdoor installation along with the appropriate treatment of the external surfaces, which
enables the installation in open spaces exposed to the atmospheric conditions and solar radiation. The
switchgear constructed in the “H” scheme form will consist of three-poled enclosed busbars, two busbar
measuring feeders, one section/coupling feeder, two transformer feeders and two outgoing feeders. The
switchgear will be connected to the network and transformers by the overhead connectors Al 300 mm2
. A
block transformer is connected to the current measuring transformers by means of Cu pipes  32 × 2 mm.
The designed switchgear satisfies the following minimum demands - modular performance of manufacture
completed mounting groups with the possibility of subsequent extension by means of upgrade by additional
fields, sections, busbars, circuit breakers, disconnectors and other components without unnecessary
dismounting of the equipment's main parts. The switchgear should secure the highest possible security for the
workers and others around the switchgear surrounding area under normal operating conditions and during
failures (short circuit). In accordance with the conditions at the installation location, the switchgear will be
sized for the insulation degree 123 Si 230/550 and will have the following rated values and technical
characteristics shown in Table 1. Figure 9 presents the 110 kV SIEMENS SF6 switchgear.
Figure 9. SIEMENS HIS SF6 switchgear
110 KV-S1
110
k
V
110 KV S2
110
k
V
10 KV HIS1
10
kV
10 KV HIS2
10
kV
110 KV NED S2 110
k
V
10 KV S1
10
kV
BUS-10 KV S2
10
kV
HE VARARZDIN A HE VARARZDIN B
10 KV S A
10
kV
10 KV S B
10
kV
HE VARARZDIN A1
CABLE_A
HE VARARZDIN B1
CABLE_B
TRAFO-A TRAFO - B
HE-NEDELJANEC 1 HE-NEDELJANEC 2
110 KV NED S1
110
k
V
110 KV S1 HIS
110
k
V
110 KV S2 HIS
110
k
V
TRAFO-A1 TRAFO-B1
110 KV NED S2_A
110
k
V
110 KV NED S1_A
110
k
V
HE-NEDELJANEC 11 HE-NEDELJANEC 21
NEDELJANEC 1 NEDELJANEC 2
HIS
SUBSTATION
CLASSICAL
SUBSTATION
 ISSN:2088-8708
IJECE Vol. 7, No. 2, April 2017 : 729–740
737
Table 1. Technical characteristics of new HIS switchgear
Rated voltage 110 kV
Network maximum voltage 123 kV
Rated frequency 50 Hz
Rated withstand voltage of 50 Hz 1 min:
between phases and toward ground
275 kV
110 kV neutral point earthing Direct earthing
Rated withstand surge voltage of 1,2/50s:
between phases and toward ground
between opened circuit breaker contacts
between opened disconnector contacts
550 kV
550 kV
650 kV
Rated permanent current at 40°C:
busbars
outgoing and transformer feeders
2500 A
1250 A
Rated short term withstand current 1 s 40 kA
8. RESULTS OF THE GENERATOR ADEQUACY SIMULATION
The simulation was performed in the program package of DIgSILENT with the power flow
calculation [12] for the period of 1 year. The load on the 110 kV side of the power transmission line
Nedeljanec is displayed by the annual curve of duration presented in Figure 10. Also, 110 kV busbar outages
were considered within the load Nedeljanec.
Figure 10. The curve of load duration Nedeljanec
The input data for HIS was used from [12], and for the existing switchgear from the statistics of the
plant events HOPS from [13]. The input data for generators in the hydro power plant are given in Table 2.
After the generator assessment analysis is performed using Monte Carlo simulation for 100 000 runs, the
generator adequacy indices are shown in Figure 11.
Figure 11. Total available capacity, available dispatch capacity, grid total demand and total reserve
generation
IJECE ISSN: 2088-8708 
Generator Assessment of Hydro Power Station Adequacy after Reconstruction from … (Srete Nikolovski)
738
Table 2. Input data for generators
Year Working state
(h)
Derated state
(h)
Maintenance
(h)
Failure state
(h)
Sum of hours
(h)
2010 5535 2418 793 14 8760
2011 5884 2024 850 2 8760
2012 5834 1980 946 0 8760
2013 6490 1481 651 138 8760
Average 6030,8 1823,6 862,8 42,8 8760
Figure 12 shows monte Carlo simulation process for Classical switchgear, minimal, average and
maximum values of LOLP and EDNS indices
Figure 12. Monte Carlo simulation process for Classical switchgear, minimal, average and maximum
values of LOLP and EDNS indices
In Tables 4 and 5, results for Monte Carlo simulations of generator adequacy indices for both cases,
classical and HIS switchgear are presented.
Table 4. HIS switchgear generator adequacy indices
Loss of Load Probability Expected Demand Not Supplied
Average(LOLP)
(%)
Confidence Levels
Lower Upper
Average (EDNS)
(MW)
Confidence Levels
0.21700 0.19279 0.24121 | 0.011 0.010 0.012
Table 5. Classical switchgear generator adequacy indices
Loss of Load Probability Expected Demand Not Supplied
Average (LOLP)
(%)
Confidence Levels
Lower Upper
Average (EDNS)
(MW)
Confidence Levels
0.27300 0.24586 0.30014 0.015 0.013 0.016
The difference in adequacy indices of the new SF6 gas insulated High Integrated Switchgear in
relation to the standard existing switchgear for the outdoor usage is obvious. This can only be one of the
advantages and additional criteria for choosing the HIS and justifying the reconstruction.
1.000E+58.000E+46.000E+44.000E+42.000E+41.000E+0 [-]
12.00
8.00
4.00
0.00
-4.00
-8.00
Summary Grid: Loss of Load Probability (Unconstrained), Average in %
Summary Grid: Loss of Load Probability (Unconstrained), Lower confidence limit in %
Summary Grid: Loss of Load Probability (Unconstrained), Upper confidence limit in %
1.000E+58.000E+46.000E+44.000E+42.000E+41.000E+0 [-]
0.08
0.06
0.04
0.02
-0.00
-0.02
Summary Grid: Demand Not Supplied (Unconstrained), Average in MW
Summary Grid: Demand Not Supplied (Unconstrained), Lower confidence limit in MW
Summary Grid: Demand Not Supplied (Unconstrained), Upper confidence limit in MW
Convergence Date: 10/15/2016
Annex: /1
DIgSILENT
 ISSN:2088-8708
IJECE Vol. 7, No. 2, April 2017 : 729–740
739
9. CONCLUSION
This paper presents the generator adequacy assessment connected to 110 kV/10 kV switchgear in
the hydro power plant, particularly of the present switchgear for the outdoor use, as well as the new SF6 HIS-
High Integrated Switchgear. Markov space-state method was used, together with the generator assessment
Monte Carlo simulation using DIgSILENT software. Monte Carlo generator assessment is also performed in
consideration to the generator three states model (in work, derated state and in outage). All outage data are
taken from the statistics of the plant events for the four years period of time, form 2009 to 2013 year, from
HEP d.d.. The information on the equipment and switchgear elements outages has been statisticaly processed.
For the new switchgear in the “H” scheme, which was conducted in the HIS SF6 technology, outage data are
taken from the relevant literature statistics. All relevant adequacy generator assessment indices of the
switchgear have been computed. The generator adequacy indices of the HIS are far better than the standard
switchgear for the outdoor use, which of course, aside from other advantages, can be crucial in transition to
the High Integrated Switchgears.
REFERENCES
[1] D. Koval, A. Chowdhury, Assessment of Transmission-Line Common-Mode, Station-Originated, and Fault-Type
Forced-Outage Rates, IEEE Transactions on Industry application, Vol. 46, No. 1. Nov. 2001.
[2] R. Billinton, T.K.P. Medicherla, Station Originated Multiple Outages in the Reliability Analysis of a Composite
Generation and Transmission System, IEEE Transaction on PAS, Vol. 100. No.8. Oct. 1981.
[3] R. Billinton, P.K. Vohra, S. Kumar, Effect of Station originated outages in a composite system adequacy evaluation
of The IEEE Reliability test system, IEEE Transaction on PAS, Vol. 104. No.10. Oct. 1985.
[4] R. Billinton, R.N. Allan “Reliability Evaluation of Power Systems”, 2nd Edition, Publisher Plenum Press, New
York, USA, 1996.
[5] R. Billinton, W. Li, Reliability assessment of electric power systems using Monte Carlo methods, Publisher,
Plenum Press, New York and London, 1994.
[6] M. B. Hamouda, M. N. Lakhoua, L. El Amraoui, Dependability Evaluation and Supervision in Thermal Power
Plants, International Journal of Electrical and Computer Engineering (IJECE), Vol. 5, No 5. Oct. 2015.
[7] J. Nahman, Modeling simultaneous outages for Bulk-power system reliability analysis, IEEE Trans on Reliability,
Vol. R-34, No. 5. Nov. 1985.
[8] J. Nahman, M. Grahovac, Load modeling for generating capacity reliability evaluation using frequency and
duration method, IEE Proceeding-C, Vol. 139, No. 6, Nov. 1992.
[9] DIgSILENT PowerFactory 15, User Manual, Gomaringen 2014.
[10] SIEMENS i EXOR “Electrical project of reconstruction of substation 110 kV i 35 kV in HE”, 2005.
[11] T.M. Chan, F. Heil, D. Kopejkova “Report on the second international survey on high voltage gas isolated
substation service experience”, CIGRE, Paris, WG, 1998K. Karsai, D. Kerenyi, L. Kiss „Large Power
Transformers“, Oxford 1987.
[12] Croatian Transmission System Operator, HOPS d.o.o Zagreb “Operational Events Statistics for 2013”, Zagreb,
2014 S. D. Bole, “Mitigation of Inrush Current in Transformer”, International Journal of Innovative Technology
and Exploring Engineering (IJITEE), ISSN: 2278-3075, Volume-3, Issue-7, Dec. 2013.
BIOGRAPHIES OF AUTHORS
Srete Nikolovski, PhD.MSc.El.Eng. (IEEE M’1995, SM’2005) was born in Belgrade on
October 1, 1954. He obtained his BSc degree (1978) and MSc degree (1989), in electrical
engineering at the Faculty of Electrical Engineering, University of Belgrade and his PhD degree
from the Faculty of Electrical and Computing, University of Zagreb, Croatia in 1993. He is
currently a Full Professor at the Department of Power Engineering at the Faculty of Electrical
Engineering, Computer Science and Information Technology, J. J. Strossmayer University of
Osijek, Croatia. His main interests are power system protection, power system analysis and
reliability. He has published 200 technical papers in international journals and proceedings. He is
a Senior Member of IEEE Reliability Society, PES Society and the Croatian CIGRE.
Goran Slipac, PhD.El.Eng, was born in Travnik, on February 25 1960. He obtained his diploma
degree in 1983 in field of Electrical Power Engineering from the Faculty of Electrical
Engineering and Computing, University of Zagreb and a master degree in the field of on the
same Faculty. During 1994-2001 he attended training courses in Argonne, USA, in the field of
Generation Expansion Planning and Energy Demand Analysis. He was a Manager of Corporate
Development Department in HEP Inc. (Croatian Electricity Utility) and a Director of HEP
Renewables company. He is currently employed as an Advisor of HEP Inc. Management Board.
He is the former chairman of the Study Committee C1 Croatian CIGRE. His main interests are
power system analysis and generation expansion planning.
IJECE ISSN: 2088-8708 
Generator Assessment of Hydro Power Station Adequacy after Reconstruction from … (Srete Nikolovski)
740
Emir Alibašić, Dipl.El.Ing., was born in Tuzla on March 12, 1982. He obtained his BCs degree
(2007) in Tuzla in field of Electrical engineering at the Faculty of Electrical Engineering,
University of Tuzla. Currently he is a PhD student at Faculty of Electrical Engineering, J.J.
Strossmayer University of Osijek, Croatia. His main interests are power transmission lines and
optimization of electrical energy transmission. He wass employed at UMEL-
DALEKOVODMONTAZA Tuzla on the position of design and maintenance of objects up to
400 kV and currently is owner INFORM Agency for the development of software applications.
Currently he works as ITC manager at ZZO TK.

More Related Content

What's hot

ENHANCING RELIABILITY BY RECONFIGURATION OF POWER DISTRIBUTION SYSTEMS CONSID...
ENHANCING RELIABILITY BY RECONFIGURATION OF POWER DISTRIBUTION SYSTEMS CONSID...ENHANCING RELIABILITY BY RECONFIGURATION OF POWER DISTRIBUTION SYSTEMS CONSID...
ENHANCING RELIABILITY BY RECONFIGURATION OF POWER DISTRIBUTION SYSTEMS CONSID...
Suganthi Thangaraj
 
Online diagnosis of supercapacitors using extended Kalman filter combined wit...
Online diagnosis of supercapacitors using extended Kalman filter combined wit...Online diagnosis of supercapacitors using extended Kalman filter combined wit...
Online diagnosis of supercapacitors using extended Kalman filter combined wit...
International Journal of Power Electronics and Drive Systems
 
Impact of hybrid FACTS devices on the stability of the Kenyan power system
Impact of hybrid FACTS devices on the stability of the Kenyan power system Impact of hybrid FACTS devices on the stability of the Kenyan power system
Impact of hybrid FACTS devices on the stability of the Kenyan power system
IJECEIAES
 
Fault Ride-Through capability of DSTATCOM for Distributed Wind Generation System
Fault Ride-Through capability of DSTATCOM for Distributed Wind Generation SystemFault Ride-Through capability of DSTATCOM for Distributed Wind Generation System
Fault Ride-Through capability of DSTATCOM for Distributed Wind Generation System
IJPEDS-IAES
 
Dynamic model of zeta converter with full state
Dynamic model of zeta converter with full stateDynamic model of zeta converter with full state
Dynamic model of zeta converter with full state
eSAT Publishing House
 
Harmonic stability analysis of multi-paralleled 3-phase PV inverters tied to ...
Harmonic stability analysis of multi-paralleled 3-phase PV inverters tied to ...Harmonic stability analysis of multi-paralleled 3-phase PV inverters tied to ...
Harmonic stability analysis of multi-paralleled 3-phase PV inverters tied to ...
International Journal of Power Electronics and Drive Systems
 
Modular Approach to Implement Model Predictive Control on Three Phase Voltage...
Modular Approach to Implement Model Predictive Control on Three Phase Voltage...Modular Approach to Implement Model Predictive Control on Three Phase Voltage...
Modular Approach to Implement Model Predictive Control on Three Phase Voltage...
International Journal of Power Electronics and Drive Systems
 
V044145150
V044145150V044145150
V044145150
IJERA Editor
 
Single Phase PV Grid-Connected in Smart Household Energy System with Anticipa...
Single Phase PV Grid-Connected in Smart Household Energy System with Anticipa...Single Phase PV Grid-Connected in Smart Household Energy System with Anticipa...
Single Phase PV Grid-Connected in Smart Household Energy System with Anticipa...
IJPEDS-IAES
 
Power Flow Analysis of Island Business District 33KV Distribution Grid System...
Power Flow Analysis of Island Business District 33KV Distribution Grid System...Power Flow Analysis of Island Business District 33KV Distribution Grid System...
Power Flow Analysis of Island Business District 33KV Distribution Grid System...
IJERA Editor
 
ترجمه مقاله انگلیسی
ترجمه مقاله انگلیسیترجمه مقاله انگلیسی
ترجمه مقاله انگلیسی
alighobyshavi
 
Ar36263268
Ar36263268Ar36263268
Ar36263268
IJERA Editor
 
Speed Conrol of Separately Excited dc Motor using Fuzzy Technique
Speed Conrol of Separately Excited dc Motor using Fuzzy TechniqueSpeed Conrol of Separately Excited dc Motor using Fuzzy Technique
Speed Conrol of Separately Excited dc Motor using Fuzzy Technique
IDES Editor
 
IRJET- Optimal Control of Multilevel Inverter to Minimize Harmonic Distortion...
IRJET- Optimal Control of Multilevel Inverter to Minimize Harmonic Distortion...IRJET- Optimal Control of Multilevel Inverter to Minimize Harmonic Distortion...
IRJET- Optimal Control of Multilevel Inverter to Minimize Harmonic Distortion...
IRJET Journal
 
K010418290
K010418290K010418290
K010418290
IOSR Journals
 
Comparative Study of Three Phase Grid Connected Photovoltaic Inverter Using P...
Comparative Study of Three Phase Grid Connected Photovoltaic Inverter Using P...Comparative Study of Three Phase Grid Connected Photovoltaic Inverter Using P...
Comparative Study of Three Phase Grid Connected Photovoltaic Inverter Using P...
IJPEDS-IAES
 
IRJET- STATCOM Enabled Modified iUPQC Controller
IRJET- STATCOM Enabled Modified iUPQC ControllerIRJET- STATCOM Enabled Modified iUPQC Controller
IRJET- STATCOM Enabled Modified iUPQC Controller
IRJET Journal
 
Fractional Order PID Controlled Interleaved Boost converter Fed Shunt Active ...
Fractional Order PID Controlled Interleaved Boost converter Fed Shunt Active ...Fractional Order PID Controlled Interleaved Boost converter Fed Shunt Active ...
Fractional Order PID Controlled Interleaved Boost converter Fed Shunt Active ...
International Journal of Power Electronics and Drive Systems
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
IJERD Editor
 
Welcome to International Journal of Engineering Research and Development (IJERD)
Welcome to International Journal of Engineering Research and Development (IJERD)Welcome to International Journal of Engineering Research and Development (IJERD)
Welcome to International Journal of Engineering Research and Development (IJERD)
IJERD Editor
 

What's hot (20)

ENHANCING RELIABILITY BY RECONFIGURATION OF POWER DISTRIBUTION SYSTEMS CONSID...
ENHANCING RELIABILITY BY RECONFIGURATION OF POWER DISTRIBUTION SYSTEMS CONSID...ENHANCING RELIABILITY BY RECONFIGURATION OF POWER DISTRIBUTION SYSTEMS CONSID...
ENHANCING RELIABILITY BY RECONFIGURATION OF POWER DISTRIBUTION SYSTEMS CONSID...
 
Online diagnosis of supercapacitors using extended Kalman filter combined wit...
Online diagnosis of supercapacitors using extended Kalman filter combined wit...Online diagnosis of supercapacitors using extended Kalman filter combined wit...
Online diagnosis of supercapacitors using extended Kalman filter combined wit...
 
Impact of hybrid FACTS devices on the stability of the Kenyan power system
Impact of hybrid FACTS devices on the stability of the Kenyan power system Impact of hybrid FACTS devices on the stability of the Kenyan power system
Impact of hybrid FACTS devices on the stability of the Kenyan power system
 
Fault Ride-Through capability of DSTATCOM for Distributed Wind Generation System
Fault Ride-Through capability of DSTATCOM for Distributed Wind Generation SystemFault Ride-Through capability of DSTATCOM for Distributed Wind Generation System
Fault Ride-Through capability of DSTATCOM for Distributed Wind Generation System
 
Dynamic model of zeta converter with full state
Dynamic model of zeta converter with full stateDynamic model of zeta converter with full state
Dynamic model of zeta converter with full state
 
Harmonic stability analysis of multi-paralleled 3-phase PV inverters tied to ...
Harmonic stability analysis of multi-paralleled 3-phase PV inverters tied to ...Harmonic stability analysis of multi-paralleled 3-phase PV inverters tied to ...
Harmonic stability analysis of multi-paralleled 3-phase PV inverters tied to ...
 
Modular Approach to Implement Model Predictive Control on Three Phase Voltage...
Modular Approach to Implement Model Predictive Control on Three Phase Voltage...Modular Approach to Implement Model Predictive Control on Three Phase Voltage...
Modular Approach to Implement Model Predictive Control on Three Phase Voltage...
 
V044145150
V044145150V044145150
V044145150
 
Single Phase PV Grid-Connected in Smart Household Energy System with Anticipa...
Single Phase PV Grid-Connected in Smart Household Energy System with Anticipa...Single Phase PV Grid-Connected in Smart Household Energy System with Anticipa...
Single Phase PV Grid-Connected in Smart Household Energy System with Anticipa...
 
Power Flow Analysis of Island Business District 33KV Distribution Grid System...
Power Flow Analysis of Island Business District 33KV Distribution Grid System...Power Flow Analysis of Island Business District 33KV Distribution Grid System...
Power Flow Analysis of Island Business District 33KV Distribution Grid System...
 
ترجمه مقاله انگلیسی
ترجمه مقاله انگلیسیترجمه مقاله انگلیسی
ترجمه مقاله انگلیسی
 
Ar36263268
Ar36263268Ar36263268
Ar36263268
 
Speed Conrol of Separately Excited dc Motor using Fuzzy Technique
Speed Conrol of Separately Excited dc Motor using Fuzzy TechniqueSpeed Conrol of Separately Excited dc Motor using Fuzzy Technique
Speed Conrol of Separately Excited dc Motor using Fuzzy Technique
 
IRJET- Optimal Control of Multilevel Inverter to Minimize Harmonic Distortion...
IRJET- Optimal Control of Multilevel Inverter to Minimize Harmonic Distortion...IRJET- Optimal Control of Multilevel Inverter to Minimize Harmonic Distortion...
IRJET- Optimal Control of Multilevel Inverter to Minimize Harmonic Distortion...
 
K010418290
K010418290K010418290
K010418290
 
Comparative Study of Three Phase Grid Connected Photovoltaic Inverter Using P...
Comparative Study of Three Phase Grid Connected Photovoltaic Inverter Using P...Comparative Study of Three Phase Grid Connected Photovoltaic Inverter Using P...
Comparative Study of Three Phase Grid Connected Photovoltaic Inverter Using P...
 
IRJET- STATCOM Enabled Modified iUPQC Controller
IRJET- STATCOM Enabled Modified iUPQC ControllerIRJET- STATCOM Enabled Modified iUPQC Controller
IRJET- STATCOM Enabled Modified iUPQC Controller
 
Fractional Order PID Controlled Interleaved Boost converter Fed Shunt Active ...
Fractional Order PID Controlled Interleaved Boost converter Fed Shunt Active ...Fractional Order PID Controlled Interleaved Boost converter Fed Shunt Active ...
Fractional Order PID Controlled Interleaved Boost converter Fed Shunt Active ...
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
 
Welcome to International Journal of Engineering Research and Development (IJERD)
Welcome to International Journal of Engineering Research and Development (IJERD)Welcome to International Journal of Engineering Research and Development (IJERD)
Welcome to International Journal of Engineering Research and Development (IJERD)
 

Similar to Generator Assessment of Hydro Power Station Adequacy after Reconstruction from Classical to HIS SF6 Substation

IRJET-Power Flow & Voltage Stability Analysis using MATLAB
IRJET-Power Flow & Voltage Stability Analysis using MATLAB IRJET-Power Flow & Voltage Stability Analysis using MATLAB
IRJET-Power Flow & Voltage Stability Analysis using MATLAB
IRJET Journal
 
Power Flow & Voltage Stability Analysis using MATLAB
Power Flow & Voltage Stability Analysis using MATLAB Power Flow & Voltage Stability Analysis using MATLAB
Power Flow & Voltage Stability Analysis using MATLAB
IRJET Journal
 
Selective localization of capacitor banks considering stability aspects in po...
Selective localization of capacitor banks considering stability aspects in po...Selective localization of capacitor banks considering stability aspects in po...
Selective localization of capacitor banks considering stability aspects in po...
IAEME Publication
 
20120140502013
2012014050201320120140502013
20120140502013
IAEME Publication
 
LOAD SHEDDING DESIGN FOR AN INDUSTRIAL COGENERATION SYSTEM
LOAD SHEDDING DESIGN FOR AN INDUSTRIAL COGENERATION SYSTEMLOAD SHEDDING DESIGN FOR AN INDUSTRIAL COGENERATION SYSTEM
LOAD SHEDDING DESIGN FOR AN INDUSTRIAL COGENERATION SYSTEM
ELELIJ
 
Steady state stability analysis and enhancement of three machine nine bus pow...
Steady state stability analysis and enhancement of three machine nine bus pow...Steady state stability analysis and enhancement of three machine nine bus pow...
Steady state stability analysis and enhancement of three machine nine bus pow...
eSAT Journals
 
International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)
IJERD Editor
 
Reliability Analysis of a 3-Machine Power Station Using State Space Approach
Reliability Analysis of a 3-Machine Power Station Using State Space ApproachReliability Analysis of a 3-Machine Power Station Using State Space Approach
Reliability Analysis of a 3-Machine Power Station Using State Space Approach
IJERA Editor
 
Aircraft Electrical Power Generation & Distribution System Units Through an A...
Aircraft Electrical Power Generation & Distribution System Units Through an A...Aircraft Electrical Power Generation & Distribution System Units Through an A...
Aircraft Electrical Power Generation & Distribution System Units Through an A...
IJMTST Journal
 
Performance analysis of a single phase ac voltage controller under induction ...
Performance analysis of a single phase ac voltage controller under induction ...Performance analysis of a single phase ac voltage controller under induction ...
Performance analysis of a single phase ac voltage controller under induction ...
eSAT Publishing House
 
Switched DC Sources Based Novel Multilevel Inverter
Switched DC Sources Based Novel Multilevel InverterSwitched DC Sources Based Novel Multilevel Inverter
Switched DC Sources Based Novel Multilevel Inverter
IRJET Journal
 
Fuzzy Logic based Maximum Power Point Tracker in Photovoltaic Cell
Fuzzy Logic based Maximum Power Point Tracker in Photovoltaic CellFuzzy Logic based Maximum Power Point Tracker in Photovoltaic Cell
Fuzzy Logic based Maximum Power Point Tracker in Photovoltaic Cell
International Journal of Science and Research (IJSR)
 
PSO based Direct Power Control for a Multifunctional Grid Connected Photovolt...
PSO based Direct Power Control for a Multifunctional Grid Connected Photovolt...PSO based Direct Power Control for a Multifunctional Grid Connected Photovolt...
PSO based Direct Power Control for a Multifunctional Grid Connected Photovolt...
International Journal of Power Electronics and Drive Systems
 
IRJET- PI Controller based Shunt Connected Three Phase Active Power Filter
IRJET- PI Controller based Shunt Connected Three Phase Active Power FilterIRJET- PI Controller based Shunt Connected Three Phase Active Power Filter
IRJET- PI Controller based Shunt Connected Three Phase Active Power Filter
IRJET Journal
 
Convergence Problems Of Contingency Analysis In Electrical Power Transmission...
Convergence Problems Of Contingency Analysis In Electrical Power Transmission...Convergence Problems Of Contingency Analysis In Electrical Power Transmission...
Convergence Problems Of Contingency Analysis In Electrical Power Transmission...
CSCJournals
 
Work Portfolio
Work PortfolioWork Portfolio
Work Portfolio
Shashwat Shekhar
 
Reactive power aspects in reliability assessment of power systems
Reactive power aspects in reliability assessment of power systemsReactive power aspects in reliability assessment of power systems
Reactive power aspects in reliability assessment of power systems
IAEME Publication
 
Transient stability analysis on a multi machine system in psat
Transient stability analysis on a multi machine system in psatTransient stability analysis on a multi machine system in psat
Transient stability analysis on a multi machine system in psat
eSAT Journals
 
International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)
inventionjournals
 
Application and Comparison Between the Conventional Methods and PSO Method fo...
Application and Comparison Between the Conventional Methods and PSO Method fo...Application and Comparison Between the Conventional Methods and PSO Method fo...
Application and Comparison Between the Conventional Methods and PSO Method fo...
International Journal of Power Electronics and Drive Systems
 

Similar to Generator Assessment of Hydro Power Station Adequacy after Reconstruction from Classical to HIS SF6 Substation (20)

IRJET-Power Flow & Voltage Stability Analysis using MATLAB
IRJET-Power Flow & Voltage Stability Analysis using MATLAB IRJET-Power Flow & Voltage Stability Analysis using MATLAB
IRJET-Power Flow & Voltage Stability Analysis using MATLAB
 
Power Flow & Voltage Stability Analysis using MATLAB
Power Flow & Voltage Stability Analysis using MATLAB Power Flow & Voltage Stability Analysis using MATLAB
Power Flow & Voltage Stability Analysis using MATLAB
 
Selective localization of capacitor banks considering stability aspects in po...
Selective localization of capacitor banks considering stability aspects in po...Selective localization of capacitor banks considering stability aspects in po...
Selective localization of capacitor banks considering stability aspects in po...
 
20120140502013
2012014050201320120140502013
20120140502013
 
LOAD SHEDDING DESIGN FOR AN INDUSTRIAL COGENERATION SYSTEM
LOAD SHEDDING DESIGN FOR AN INDUSTRIAL COGENERATION SYSTEMLOAD SHEDDING DESIGN FOR AN INDUSTRIAL COGENERATION SYSTEM
LOAD SHEDDING DESIGN FOR AN INDUSTRIAL COGENERATION SYSTEM
 
Steady state stability analysis and enhancement of three machine nine bus pow...
Steady state stability analysis and enhancement of three machine nine bus pow...Steady state stability analysis and enhancement of three machine nine bus pow...
Steady state stability analysis and enhancement of three machine nine bus pow...
 
International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)
 
Reliability Analysis of a 3-Machine Power Station Using State Space Approach
Reliability Analysis of a 3-Machine Power Station Using State Space ApproachReliability Analysis of a 3-Machine Power Station Using State Space Approach
Reliability Analysis of a 3-Machine Power Station Using State Space Approach
 
Aircraft Electrical Power Generation & Distribution System Units Through an A...
Aircraft Electrical Power Generation & Distribution System Units Through an A...Aircraft Electrical Power Generation & Distribution System Units Through an A...
Aircraft Electrical Power Generation & Distribution System Units Through an A...
 
Performance analysis of a single phase ac voltage controller under induction ...
Performance analysis of a single phase ac voltage controller under induction ...Performance analysis of a single phase ac voltage controller under induction ...
Performance analysis of a single phase ac voltage controller under induction ...
 
Switched DC Sources Based Novel Multilevel Inverter
Switched DC Sources Based Novel Multilevel InverterSwitched DC Sources Based Novel Multilevel Inverter
Switched DC Sources Based Novel Multilevel Inverter
 
Fuzzy Logic based Maximum Power Point Tracker in Photovoltaic Cell
Fuzzy Logic based Maximum Power Point Tracker in Photovoltaic CellFuzzy Logic based Maximum Power Point Tracker in Photovoltaic Cell
Fuzzy Logic based Maximum Power Point Tracker in Photovoltaic Cell
 
PSO based Direct Power Control for a Multifunctional Grid Connected Photovolt...
PSO based Direct Power Control for a Multifunctional Grid Connected Photovolt...PSO based Direct Power Control for a Multifunctional Grid Connected Photovolt...
PSO based Direct Power Control for a Multifunctional Grid Connected Photovolt...
 
IRJET- PI Controller based Shunt Connected Three Phase Active Power Filter
IRJET- PI Controller based Shunt Connected Three Phase Active Power FilterIRJET- PI Controller based Shunt Connected Three Phase Active Power Filter
IRJET- PI Controller based Shunt Connected Three Phase Active Power Filter
 
Convergence Problems Of Contingency Analysis In Electrical Power Transmission...
Convergence Problems Of Contingency Analysis In Electrical Power Transmission...Convergence Problems Of Contingency Analysis In Electrical Power Transmission...
Convergence Problems Of Contingency Analysis In Electrical Power Transmission...
 
Work Portfolio
Work PortfolioWork Portfolio
Work Portfolio
 
Reactive power aspects in reliability assessment of power systems
Reactive power aspects in reliability assessment of power systemsReactive power aspects in reliability assessment of power systems
Reactive power aspects in reliability assessment of power systems
 
Transient stability analysis on a multi machine system in psat
Transient stability analysis on a multi machine system in psatTransient stability analysis on a multi machine system in psat
Transient stability analysis on a multi machine system in psat
 
International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)
 
Application and Comparison Between the Conventional Methods and PSO Method fo...
Application and Comparison Between the Conventional Methods and PSO Method fo...Application and Comparison Between the Conventional Methods and PSO Method fo...
Application and Comparison Between the Conventional Methods and PSO Method fo...
 

More from IJECEIAES

Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
IJECEIAES
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
IJECEIAES
 
Neural network optimizer of proportional-integral-differential controller par...
Neural network optimizer of proportional-integral-differential controller par...Neural network optimizer of proportional-integral-differential controller par...
Neural network optimizer of proportional-integral-differential controller par...
IJECEIAES
 
An improved modulation technique suitable for a three level flying capacitor ...
An improved modulation technique suitable for a three level flying capacitor ...An improved modulation technique suitable for a three level flying capacitor ...
An improved modulation technique suitable for a three level flying capacitor ...
IJECEIAES
 
A review on features and methods of potential fishing zone
A review on features and methods of potential fishing zoneA review on features and methods of potential fishing zone
A review on features and methods of potential fishing zone
IJECEIAES
 
Electrical signal interference minimization using appropriate core material f...
Electrical signal interference minimization using appropriate core material f...Electrical signal interference minimization using appropriate core material f...
Electrical signal interference minimization using appropriate core material f...
IJECEIAES
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
IJECEIAES
 
Bibliometric analysis highlighting the role of women in addressing climate ch...
Bibliometric analysis highlighting the role of women in addressing climate ch...Bibliometric analysis highlighting the role of women in addressing climate ch...
Bibliometric analysis highlighting the role of women in addressing climate ch...
IJECEIAES
 
Voltage and frequency control of microgrid in presence of micro-turbine inter...
Voltage and frequency control of microgrid in presence of micro-turbine inter...Voltage and frequency control of microgrid in presence of micro-turbine inter...
Voltage and frequency control of microgrid in presence of micro-turbine inter...
IJECEIAES
 
Enhancing battery system identification: nonlinear autoregressive modeling fo...
Enhancing battery system identification: nonlinear autoregressive modeling fo...Enhancing battery system identification: nonlinear autoregressive modeling fo...
Enhancing battery system identification: nonlinear autoregressive modeling fo...
IJECEIAES
 
Smart grid deployment: from a bibliometric analysis to a survey
Smart grid deployment: from a bibliometric analysis to a surveySmart grid deployment: from a bibliometric analysis to a survey
Smart grid deployment: from a bibliometric analysis to a survey
IJECEIAES
 
Use of analytical hierarchy process for selecting and prioritizing islanding ...
Use of analytical hierarchy process for selecting and prioritizing islanding ...Use of analytical hierarchy process for selecting and prioritizing islanding ...
Use of analytical hierarchy process for selecting and prioritizing islanding ...
IJECEIAES
 
Enhancing of single-stage grid-connected photovoltaic system using fuzzy logi...
Enhancing of single-stage grid-connected photovoltaic system using fuzzy logi...Enhancing of single-stage grid-connected photovoltaic system using fuzzy logi...
Enhancing of single-stage grid-connected photovoltaic system using fuzzy logi...
IJECEIAES
 
Enhancing photovoltaic system maximum power point tracking with fuzzy logic-b...
Enhancing photovoltaic system maximum power point tracking with fuzzy logic-b...Enhancing photovoltaic system maximum power point tracking with fuzzy logic-b...
Enhancing photovoltaic system maximum power point tracking with fuzzy logic-b...
IJECEIAES
 
Adaptive synchronous sliding control for a robot manipulator based on neural ...
Adaptive synchronous sliding control for a robot manipulator based on neural ...Adaptive synchronous sliding control for a robot manipulator based on neural ...
Adaptive synchronous sliding control for a robot manipulator based on neural ...
IJECEIAES
 
Remote field-programmable gate array laboratory for signal acquisition and de...
Remote field-programmable gate array laboratory for signal acquisition and de...Remote field-programmable gate array laboratory for signal acquisition and de...
Remote field-programmable gate array laboratory for signal acquisition and de...
IJECEIAES
 
Detecting and resolving feature envy through automated machine learning and m...
Detecting and resolving feature envy through automated machine learning and m...Detecting and resolving feature envy through automated machine learning and m...
Detecting and resolving feature envy through automated machine learning and m...
IJECEIAES
 
Smart monitoring technique for solar cell systems using internet of things ba...
Smart monitoring technique for solar cell systems using internet of things ba...Smart monitoring technique for solar cell systems using internet of things ba...
Smart monitoring technique for solar cell systems using internet of things ba...
IJECEIAES
 
An efficient security framework for intrusion detection and prevention in int...
An efficient security framework for intrusion detection and prevention in int...An efficient security framework for intrusion detection and prevention in int...
An efficient security framework for intrusion detection and prevention in int...
IJECEIAES
 

More from IJECEIAES (20)

Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
 
Neural network optimizer of proportional-integral-differential controller par...
Neural network optimizer of proportional-integral-differential controller par...Neural network optimizer of proportional-integral-differential controller par...
Neural network optimizer of proportional-integral-differential controller par...
 
An improved modulation technique suitable for a three level flying capacitor ...
An improved modulation technique suitable for a three level flying capacitor ...An improved modulation technique suitable for a three level flying capacitor ...
An improved modulation technique suitable for a three level flying capacitor ...
 
A review on features and methods of potential fishing zone
A review on features and methods of potential fishing zoneA review on features and methods of potential fishing zone
A review on features and methods of potential fishing zone
 
Electrical signal interference minimization using appropriate core material f...
Electrical signal interference minimization using appropriate core material f...Electrical signal interference minimization using appropriate core material f...
Electrical signal interference minimization using appropriate core material f...
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
 
Bibliometric analysis highlighting the role of women in addressing climate ch...
Bibliometric analysis highlighting the role of women in addressing climate ch...Bibliometric analysis highlighting the role of women in addressing climate ch...
Bibliometric analysis highlighting the role of women in addressing climate ch...
 
Voltage and frequency control of microgrid in presence of micro-turbine inter...
Voltage and frequency control of microgrid in presence of micro-turbine inter...Voltage and frequency control of microgrid in presence of micro-turbine inter...
Voltage and frequency control of microgrid in presence of micro-turbine inter...
 
Enhancing battery system identification: nonlinear autoregressive modeling fo...
Enhancing battery system identification: nonlinear autoregressive modeling fo...Enhancing battery system identification: nonlinear autoregressive modeling fo...
Enhancing battery system identification: nonlinear autoregressive modeling fo...
 
Smart grid deployment: from a bibliometric analysis to a survey
Smart grid deployment: from a bibliometric analysis to a surveySmart grid deployment: from a bibliometric analysis to a survey
Smart grid deployment: from a bibliometric analysis to a survey
 
Use of analytical hierarchy process for selecting and prioritizing islanding ...
Use of analytical hierarchy process for selecting and prioritizing islanding ...Use of analytical hierarchy process for selecting and prioritizing islanding ...
Use of analytical hierarchy process for selecting and prioritizing islanding ...
 
Enhancing of single-stage grid-connected photovoltaic system using fuzzy logi...
Enhancing of single-stage grid-connected photovoltaic system using fuzzy logi...Enhancing of single-stage grid-connected photovoltaic system using fuzzy logi...
Enhancing of single-stage grid-connected photovoltaic system using fuzzy logi...
 
Enhancing photovoltaic system maximum power point tracking with fuzzy logic-b...
Enhancing photovoltaic system maximum power point tracking with fuzzy logic-b...Enhancing photovoltaic system maximum power point tracking with fuzzy logic-b...
Enhancing photovoltaic system maximum power point tracking with fuzzy logic-b...
 
Adaptive synchronous sliding control for a robot manipulator based on neural ...
Adaptive synchronous sliding control for a robot manipulator based on neural ...Adaptive synchronous sliding control for a robot manipulator based on neural ...
Adaptive synchronous sliding control for a robot manipulator based on neural ...
 
Remote field-programmable gate array laboratory for signal acquisition and de...
Remote field-programmable gate array laboratory for signal acquisition and de...Remote field-programmable gate array laboratory for signal acquisition and de...
Remote field-programmable gate array laboratory for signal acquisition and de...
 
Detecting and resolving feature envy through automated machine learning and m...
Detecting and resolving feature envy through automated machine learning and m...Detecting and resolving feature envy through automated machine learning and m...
Detecting and resolving feature envy through automated machine learning and m...
 
Smart monitoring technique for solar cell systems using internet of things ba...
Smart monitoring technique for solar cell systems using internet of things ba...Smart monitoring technique for solar cell systems using internet of things ba...
Smart monitoring technique for solar cell systems using internet of things ba...
 
An efficient security framework for intrusion detection and prevention in int...
An efficient security framework for intrusion detection and prevention in int...An efficient security framework for intrusion detection and prevention in int...
An efficient security framework for intrusion detection and prevention in int...
 

Recently uploaded

Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
mamunhossenbd75
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
wisnuprabawa3
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
heavyhaig
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
Rahul
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
JamalHussainArman
 
2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt
PuktoonEngr
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
ssuser36d3051
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
mahammadsalmanmech
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
University of Maribor
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
VICTOR MAESTRE RAMIREZ
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
NidhalKahouli2
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
gestioneergodomus
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
Mukeshwaran Balu
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
insn4465
 
Wearable antenna for antenna applications
Wearable antenna for antenna applicationsWearable antenna for antenna applications
Wearable antenna for antenna applications
Madhumitha Jayaram
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
Hitesh Mohapatra
 

Recently uploaded (20)

Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
 
2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
 
Wearable antenna for antenna applications
Wearable antenna for antenna applicationsWearable antenna for antenna applications
Wearable antenna for antenna applications
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
 

Generator Assessment of Hydro Power Station Adequacy after Reconstruction from Classical to HIS SF6 Substation

  • 1. International Journal of Electrical and Computer Engineering (IJECE) Vol. 7, No. 2, April 2017, pp. 729~740 ISSN: 2088-8708, DOI: 10.11591/ijece.v7i2.pp729-740  729 Journal homepage: http://iaesjournal.com/online/index.php/IJECE Generator Assessment of Hydro Power Station Adequacy after Reconstruction from Classical to HIS SF6 Substation Srete Nikolovski1 , Goran Slipac2 , Emir Alibašić3 1 Faculty of Electrical Engineering, Computer Science and Information Technology, University of Osijek, Croatia 2 Croatian National Grid Company- HEP Inc., Zagreb, Croatia 3 ZZO Tuzla Kanton, Tuzla, Bosnia and Herzegovina Article Info ABSTRACT Article history: Received Dec 9, 2016 Revised Mar 12, 2017 Accepted Mar 26, 2017 Reliability analysis of substations and generator assessment of power plant stations are very important elements in a design and maintenance process. This paper presents a generator adequacy assessment of a classical “H” scheme for an open conventional substation, which is often used, and a new HIS - High Integrated Switchgear with SF6 gas isolation. Generator adequacy indices of both types of classical and HIS switchgear were compared and the results showed a high level of reliability and availability of the HIS presented substation. The input data were the annual reports of Croatian TSO-Transmission System Operator (HOPS) and statistics of operation events of Croatian National Electricity (HEP Inc.). For the HIS substation, the input reliability data were used from relevant international literature since only few of HIS substations are installed in Croatia. The generator is modelled with a three-state Markov state space model and Monte Carlo simulations were used for the generator assessment analysis. Adequacy indices LOLP and EDNS were obtained using DIgSILENT software. Keyword: Adequacy indices Classical substation Computer simulation Generator adequacy High integrated SF6 substation Markov state spece model Monte Carlo simulation, Copyright © 2017 Institute of Advanced Engineering and Science. All rights reserved. Corresponding Author: Srete Nikolovski, Faculty of Electrical Engineering, Computer Science and Information Technology Osijek, J.J. Strossmayer University of Osijek, K. Trpimira 2 B, 31000 Osijek, Croatia. Email: srete.nikolovski@etfos.hr 1. INTRODUCTION During the analysis of the composite transmission system network reliability, it is generally not enough to view the switchgears solely as network junction points, and thereby omit the influence of individual switchgear components on the reliability of the system as a whole. Every switchgear configuration has a significant impact on the occurrence of power line outages and consequently on the entire system reliability [1], [2]. This especially concerns the multiple power line failures which considerably depend on switchgear failures [3], [4]. The paper analyzes switchgear reliability using Mont Carlo, the loss of one consumer and generator adequacy assessment using Monte Carlo simulation [5]. The basic definitions related to modelling failures from a switchgear are as follows: a. Switchgear components: transformers, circuit breakers, disconnectors and busbars; surge arresters, current and load measuring transformers are usually omitted. The protection system is generally not taken into the account; b. Switchgear availability: the probability of presence of a corresponding electrical connection between switchgear busbars from a HV to LV side; c. Passive failure: unavailability is reduced to the faulty component (it does not cause a triping of protection). It should be noted that the definitions of active and passive failures vary from an author to author;
  • 2. IJECE ISSN: 2088-8708  Generator Assessment of Hydro Power Station Adequacy after Reconstruction from … (Srete Nikolovski) 730 d. Switching-off disabled: normally switched-on circuit breaker unable to switch-off upon demand; e. Switching-on disabled: normally switched-off circuit breaker unable to switch-on upon demand; f. Maintenance: a planned activity aiming at improving the condition of a component. It can be postponed if required by switchgear conditions. Generator adequacy assessment is a part of dependability evaluation (reliability, availability, maintainability, and safety) [6]. The analysis is performed for the events of the first level of coincidence which is a forced failure or switching-off of one component. The paper deals with the generator adequacy assessment connected on a substation using a computer software. The load in a substation is modelled with a load duration curve which is then modelled with different load states considered in the generator assessment analysis using Monte Carlo simulation [7-8]. The paper includes the generator assessment analysis using a sequential Monte Carlo simulation module in DIgSILENT Power factory software [9]. 2. MARKOV STATE SPACE MODEL FOR BUSBARS AND TRANSFORMERS WITHIN THE SWITCHGEAR Busbars and transformers, as renewable components, with regard to reliability of supply, can have two different states – they are either available or unavailable. A two-states component model is the most oftenly used model since it gives the best description of the continuous operation of a component. It is presented in Figure 1. Figure 1. Model of a component with two states Symbols: 1 - operation state of a component; 2 - component in a failure state;  - component failure intensity;  - component repair intensity. Probability of being in a state 1 and 2 is:    1P    2P (1) Frequency of being in a state 1 and 2 is defined as follows:      11 Pf      22 Pf (2) 3. MODEL OF A SYSTEM WITH TWO COMPONENTS The model presented in Figure 2 shows the state of two different components - each component can be either ready to operate or not ready to operate (a coincidence of a transformer and busbar failure).
  • 3.  ISSN:2088-8708 IJECE Vol. 7, No. 2, April 2017 : 729–740 731 Figure 2. Model of two components with four states This model is applied during the analysis of switchgear failures for transformer and busbar failure coincidence. The basic premise of all considerations is that the possibility that two or more events take place simultaneously is ruled out. Consequently, the possibilities of direct transitions between states 1 and 4, i.e. 2 and 3 within the model are ruled out. Symbols: A - first component; B – second component; 1 – components A and B in operation; 2 – component A faulty and B in operation; 3 – component A working and B faulty; 4 - components A and B faulty; 1and 1 - failure and repair intensity of component A; 2 and 2 - failure and repair intensity of component B. Stationary system solutions, i.e. stationary probabilities of the states are: ))(())(())(())(( 2211 21 4 2211 21 3 2211 21 2 2211 21 1                 PPPP (3) Since it had been shown earlier that the expressions:         NA ; present stationary availability, that is, unavailability of one component, the stationary probabilities of the states in the case of two-components system can be expressed as follows: 214213212211 ;;; NNPNAPANPAAP  (4) According to the model of a system with two different components, the frequency of an individual state can be determined either as a product of the state probability and the sum of intensity of abandoning that identical state, or as a product of the sum of intensity of entering the state and the probability of a state that is being abandoned. Frequencies are equal regardless of being observed from a perspective of exits or from a perspective of entrances. According to that, frequencies of states are as follows: 122121212144 122121212133 122121212122 122121212111 )()( )()( )()( )()( NfNfNNPf AfNfNAPf NfAfANPf AfAfAAPf         (5) 4. MODEL OF COMPONENT WITH MAINTENANCE Switchgear components count as renewable components and their maintenance (planned repair) is carried out periodically. Maintenance of switchgear components increases their reliability and availability AB 1 AB 2 1 AB 3 AB 4 1 2 2 2 2 1 2
  • 4. IJECE ISSN: 2088-8708  Generator Assessment of Hydro Power Station Adequacy after Reconstruction from … (Srete Nikolovski) 732 because the tendency of growth of failure intensity function is being reduced and maintained at a sufficiently low constant value. Figure 3 shows the Markov state space model of a component with maintenance. It is presumed that the planned repair of a component will not be performed when a component is not functional, and upon finishing the repair, a component is again ready for the operation. Figure 3. Model of component with maintenance Symbols: 1- component in operation; 2- component A blocked; 3- component A under repair; R and R - intensity of repair and repair completion of component A; K and K - intensity of malfunction and repair of component A. Stationary system solutions, i.e. stationary probabilities of the states are: KRRKRK KR KRRKRK RK KRRKRK RK PPP             321 (6) Based on the earlier considerations, it follows that state “1“denotes component availability, state “2” denotes a failure-induced component unavailability, and state “3” component unavailability due to repair: RK NPNPAP  321 ;; (7) Frequencies of failure and repair states are: KRRKRK KRR rR KRRKRK RKK KK PPf PPf           313 212 (8) 5. FAILURE COINCIDENCE MODEL WITH PLANNED MAINTENANCE Preventive maintenance is conducted in order to keep the frequency of component failures at the lowest possible level. However, when these coincide with failures of other components in the system, the number of system failures may be increased. Thus, if possible, preventive maintenance and repairs should be conducted when they would not have negative effects on the system. It is generally considered that once the repair has been initiated, it has to be finished. Figure 4 shows a case of failure coincidence with the planned maintenance. If the possibility of a transition from state “3” into state “4” is removed, then the request that the repair cannot be initiated in state “3” is accepted, i.e. during the failure state of the other component. However, if state “4” does not represent the system failure state, that transition is allowed and the failure and repair processes are independent. The probabilities of being in certain states in case the transition from state A 1 A 2  AR 3 R R 
  • 5.  ISSN:2088-8708 IJECE Vol. 7, No. 2, April 2017 : 729–740 733 “3” into state “4” is allowed, since state “4” does not represent the system failure state are as follows: ))(( ; ))(( ))(( ; ))(( 43 21 BKBKARAR BKAR BKBKARAR ARBK BKBKARAR BKAR BKBKARAR BKAR PP PP                 (9) Figure 4. Failure coincidence model of the planned maintenance and repair with failure Symbols: 1 - components A and B in operation; 2 - component A in repair and B in operation; 3 - component A in operation and B in failure; 4 - component A in repair and B in failure; AR - component A repair intensity; AR - component A repair intensity; BK - component B failure intensity; BK - component B repair intensity; R - component repair intensity. However, if state “4” also means system failure, the transition from state “3” into state “4” is not allowed, which means that the frequency of repair of the first component in the third and fourth system equation has a zero value ( ). In that case, the values are: (10) AR *  0        BKARBKARBKARARBKBK BKBKAR BKARBKARBKARARBKBK BKARBKARARBK BKARBKARBKARARBKBK BKARBKAR BKARBKARBKARARBKBK BKARBKBKAR P P P P                    )()( )()( )( )()( )( )()( )( 4 3 2 1 AB 1 ARB 2 AR AB 3 ARB 4 AR AR BK BK BK AR BK
  • 6. IJECE ISSN: 2088-8708  Generator Assessment of Hydro Power Station Adequacy after Reconstruction from … (Srete Nikolovski) 734 Since the most common frequencies of the component repair and maintenance are significantly higher than the respective frequencies of entering into those states, i.e. the multiple products of very small values can be disregarded, the near solution values (10) are: (11) The frequency of the system failure, (failure and repair coincidence state) which also means the failure of the system, is: (12) The mean time of failure coincidence with the planned maintenance and repair is: (13) 6. GENERATOR MODEL WITH A DERATED STATE Figure 5 shows the model of the component with the derated state (reduced capacity). It is assumed that the transition of the component to the derated state from the forced outage is not allowed because it is believed that during its stay in the forced outage, the repair is performed and that component is ready for the operation with the rated capacity. Figure 5. Generator model with one derated state Symbols: 1 component A in operation; 2 component Ader1 in operation with the derated state; 3 component A in failure; component A intensity of the derated state; 1der component A intensity of departure from the derated state;  component A failure rate;  component A repair rate: The probabilities of being in a certain state are:   111 1 1 derderder der P     111 1 2 derderder der P   , 1 3 1 1 1 derP der der der           (14) )( ;;;1 4321 BKARAR BKAR BK BK AR AR PPPP          AR BKAR BKAR BKARAR BKAR BKARPf       )( )( )(44 BKAR k f P T   1 4 4 der1 der1 der1 1der
  • 7.  ISSN:2088-8708 IJECE Vol. 7, No. 2, April 2017 : 729–740 735 The frequencies of generator states are:    111 11 312111 )( )( derderder derder derder PPPf    (15)    111 11 12112 derderder derder derder PPf   (16)    111 1 313 derderder der PPf   (17) The mean time of generators states:    11 1 1 1 derf P T , 12 2 2 1 derf P T   ,  1 3 3 3  f P T (18) 7. DESCRIPTION OF A HYDRO POWER PLANT SUBSTATION 7.1. Basic Characteristics of the Previous Switchgear It is placed at the level of 183,5 m in the narrow area between the engine room facility and building entrance at the end of diversion channel [12]. The switchgear is in “H“ scheme with five feeders, two block transformer feeders, each equipped with a circuit breaker, disconnectors, current measuring transformers and surge arresters, two outgoing feeders equipped with outgoing disconnectors only, section feeder with a diagonally placed disconnector for the connection between blocks, i.e. transmission lines. It is dimensioned for short circuit power of 3500 MVA. The switchgear is connected to the Nedeljanec substation by 110 kV double transmission line (Al/Fe 240/40 mm2 ). Considering that outgoing feeders do not have circuit breakers installed, distance protection in a hydro power plant works at the switching off of the circuit breaker in a block transformer feeder and the circuit breaker in the outgoing feeder of Nedeljanec substation which in this way represents distant busbars of this switchgear. Switchgear equipment is nearly 30 years old, except for the new SF6 circuit breakers produced by “ABB” and installed four years ago in a place of the old pneumatic circuit breakers 3P 123 type, produced by “Končar d.d“. The whole equipment is installed on the iron stands made from steel pipes and profile, coated with anticorrosive paint, fixed to a concrete base with anchor bolts. The connection of the devices is done by wires (Al/Fe 240/40 mm2 ), i.e. AlMg  70 mm pipes. A busbar system is carried out by wires attached above the devices by using double tension insulator strings with seven glass insulators, type U 160 BS, on each of them. Busbars are attached to “T” portals made from welded iron profiles. The classical 110 kV switchgear is designed for the outdoor use and shown in Figure 6. Figure 6. Existing classical 110 kV switchgear The 110 kV transmission line connections from Nedeljanec substation is carried out by the attachment to the southern busbar portal. Block transformers with transmission ratio of 10,5/121 kV, vector group Yd5, power 2×50 MVA, are placed at the level of 176 m, between the engine room facility and the dam. They are connected to generator terminals by copper profile busbars. Although rationally placed in
  • 8. IJECE ISSN: 2088-8708  Generator Assessment of Hydro Power Station Adequacy after Reconstruction from … (Srete Nikolovski) 736 relation to the generator, due to an inadequately constructed oil pit, they are an ecological threat for the environment in case of disasters since there is a possibility of transformer oil spill into the Drava river. Also, in case of failure of a transformer with a tank crack, there is a possibility of flaming oil spreading onto the generator and other equipment. The analysis of the outage caused by failures at the hydro electrical power plant in the period from 2009 to 2013 shows the loss of supply of approximately 5 TWh of electrical energy, out of which 82% are block transformer failures due to lightning strikes. Considering the age of the equipment (about 30 years old), which is near the end of its life span, the stated manipulative possibilities and operating conditions of the network, as well as the work safety at the hydro electrical power plant which generates 100 MVA of electrical power, it is evident that it is necessary to reconstruct and modernize 110 kV switchgear by replacing the old equipment and expanding the switchgear to a scheme that would enable flexible manipulation without operation interruptions. Figure 7 shows single line scheme of the present classical and the new HIS switchgear Figure 7. Single line scheme of the present classical and the new HIS switchgear 7.2. Description of the new SF6 High Integrated Switchgear The new metal enclosed SF6 gas insulated switchgear, high integrated for the outdoor installation (HIS) at the new location will be installed on the concrete laminated foundation. The switchgear will be constructed for the outdoor installation along with the appropriate treatment of the external surfaces, which enables the installation in open spaces exposed to the atmospheric conditions and solar radiation. The switchgear constructed in the “H” scheme form will consist of three-poled enclosed busbars, two busbar measuring feeders, one section/coupling feeder, two transformer feeders and two outgoing feeders. The switchgear will be connected to the network and transformers by the overhead connectors Al 300 mm2 . A block transformer is connected to the current measuring transformers by means of Cu pipes  32 × 2 mm. The designed switchgear satisfies the following minimum demands - modular performance of manufacture completed mounting groups with the possibility of subsequent extension by means of upgrade by additional fields, sections, busbars, circuit breakers, disconnectors and other components without unnecessary dismounting of the equipment's main parts. The switchgear should secure the highest possible security for the workers and others around the switchgear surrounding area under normal operating conditions and during failures (short circuit). In accordance with the conditions at the installation location, the switchgear will be sized for the insulation degree 123 Si 230/550 and will have the following rated values and technical characteristics shown in Table 1. Figure 9 presents the 110 kV SIEMENS SF6 switchgear. Figure 9. SIEMENS HIS SF6 switchgear 110 KV-S1 110 k V 110 KV S2 110 k V 10 KV HIS1 10 kV 10 KV HIS2 10 kV 110 KV NED S2 110 k V 10 KV S1 10 kV BUS-10 KV S2 10 kV HE VARARZDIN A HE VARARZDIN B 10 KV S A 10 kV 10 KV S B 10 kV HE VARARZDIN A1 CABLE_A HE VARARZDIN B1 CABLE_B TRAFO-A TRAFO - B HE-NEDELJANEC 1 HE-NEDELJANEC 2 110 KV NED S1 110 k V 110 KV S1 HIS 110 k V 110 KV S2 HIS 110 k V TRAFO-A1 TRAFO-B1 110 KV NED S2_A 110 k V 110 KV NED S1_A 110 k V HE-NEDELJANEC 11 HE-NEDELJANEC 21 NEDELJANEC 1 NEDELJANEC 2 HIS SUBSTATION CLASSICAL SUBSTATION
  • 9.  ISSN:2088-8708 IJECE Vol. 7, No. 2, April 2017 : 729–740 737 Table 1. Technical characteristics of new HIS switchgear Rated voltage 110 kV Network maximum voltage 123 kV Rated frequency 50 Hz Rated withstand voltage of 50 Hz 1 min: between phases and toward ground 275 kV 110 kV neutral point earthing Direct earthing Rated withstand surge voltage of 1,2/50s: between phases and toward ground between opened circuit breaker contacts between opened disconnector contacts 550 kV 550 kV 650 kV Rated permanent current at 40°C: busbars outgoing and transformer feeders 2500 A 1250 A Rated short term withstand current 1 s 40 kA 8. RESULTS OF THE GENERATOR ADEQUACY SIMULATION The simulation was performed in the program package of DIgSILENT with the power flow calculation [12] for the period of 1 year. The load on the 110 kV side of the power transmission line Nedeljanec is displayed by the annual curve of duration presented in Figure 10. Also, 110 kV busbar outages were considered within the load Nedeljanec. Figure 10. The curve of load duration Nedeljanec The input data for HIS was used from [12], and for the existing switchgear from the statistics of the plant events HOPS from [13]. The input data for generators in the hydro power plant are given in Table 2. After the generator assessment analysis is performed using Monte Carlo simulation for 100 000 runs, the generator adequacy indices are shown in Figure 11. Figure 11. Total available capacity, available dispatch capacity, grid total demand and total reserve generation
  • 10. IJECE ISSN: 2088-8708  Generator Assessment of Hydro Power Station Adequacy after Reconstruction from … (Srete Nikolovski) 738 Table 2. Input data for generators Year Working state (h) Derated state (h) Maintenance (h) Failure state (h) Sum of hours (h) 2010 5535 2418 793 14 8760 2011 5884 2024 850 2 8760 2012 5834 1980 946 0 8760 2013 6490 1481 651 138 8760 Average 6030,8 1823,6 862,8 42,8 8760 Figure 12 shows monte Carlo simulation process for Classical switchgear, minimal, average and maximum values of LOLP and EDNS indices Figure 12. Monte Carlo simulation process for Classical switchgear, minimal, average and maximum values of LOLP and EDNS indices In Tables 4 and 5, results for Monte Carlo simulations of generator adequacy indices for both cases, classical and HIS switchgear are presented. Table 4. HIS switchgear generator adequacy indices Loss of Load Probability Expected Demand Not Supplied Average(LOLP) (%) Confidence Levels Lower Upper Average (EDNS) (MW) Confidence Levels 0.21700 0.19279 0.24121 | 0.011 0.010 0.012 Table 5. Classical switchgear generator adequacy indices Loss of Load Probability Expected Demand Not Supplied Average (LOLP) (%) Confidence Levels Lower Upper Average (EDNS) (MW) Confidence Levels 0.27300 0.24586 0.30014 0.015 0.013 0.016 The difference in adequacy indices of the new SF6 gas insulated High Integrated Switchgear in relation to the standard existing switchgear for the outdoor usage is obvious. This can only be one of the advantages and additional criteria for choosing the HIS and justifying the reconstruction. 1.000E+58.000E+46.000E+44.000E+42.000E+41.000E+0 [-] 12.00 8.00 4.00 0.00 -4.00 -8.00 Summary Grid: Loss of Load Probability (Unconstrained), Average in % Summary Grid: Loss of Load Probability (Unconstrained), Lower confidence limit in % Summary Grid: Loss of Load Probability (Unconstrained), Upper confidence limit in % 1.000E+58.000E+46.000E+44.000E+42.000E+41.000E+0 [-] 0.08 0.06 0.04 0.02 -0.00 -0.02 Summary Grid: Demand Not Supplied (Unconstrained), Average in MW Summary Grid: Demand Not Supplied (Unconstrained), Lower confidence limit in MW Summary Grid: Demand Not Supplied (Unconstrained), Upper confidence limit in MW Convergence Date: 10/15/2016 Annex: /1 DIgSILENT
  • 11.  ISSN:2088-8708 IJECE Vol. 7, No. 2, April 2017 : 729–740 739 9. CONCLUSION This paper presents the generator adequacy assessment connected to 110 kV/10 kV switchgear in the hydro power plant, particularly of the present switchgear for the outdoor use, as well as the new SF6 HIS- High Integrated Switchgear. Markov space-state method was used, together with the generator assessment Monte Carlo simulation using DIgSILENT software. Monte Carlo generator assessment is also performed in consideration to the generator three states model (in work, derated state and in outage). All outage data are taken from the statistics of the plant events for the four years period of time, form 2009 to 2013 year, from HEP d.d.. The information on the equipment and switchgear elements outages has been statisticaly processed. For the new switchgear in the “H” scheme, which was conducted in the HIS SF6 technology, outage data are taken from the relevant literature statistics. All relevant adequacy generator assessment indices of the switchgear have been computed. The generator adequacy indices of the HIS are far better than the standard switchgear for the outdoor use, which of course, aside from other advantages, can be crucial in transition to the High Integrated Switchgears. REFERENCES [1] D. Koval, A. Chowdhury, Assessment of Transmission-Line Common-Mode, Station-Originated, and Fault-Type Forced-Outage Rates, IEEE Transactions on Industry application, Vol. 46, No. 1. Nov. 2001. [2] R. Billinton, T.K.P. Medicherla, Station Originated Multiple Outages in the Reliability Analysis of a Composite Generation and Transmission System, IEEE Transaction on PAS, Vol. 100. No.8. Oct. 1981. [3] R. Billinton, P.K. Vohra, S. Kumar, Effect of Station originated outages in a composite system adequacy evaluation of The IEEE Reliability test system, IEEE Transaction on PAS, Vol. 104. No.10. Oct. 1985. [4] R. Billinton, R.N. Allan “Reliability Evaluation of Power Systems”, 2nd Edition, Publisher Plenum Press, New York, USA, 1996. [5] R. Billinton, W. Li, Reliability assessment of electric power systems using Monte Carlo methods, Publisher, Plenum Press, New York and London, 1994. [6] M. B. Hamouda, M. N. Lakhoua, L. El Amraoui, Dependability Evaluation and Supervision in Thermal Power Plants, International Journal of Electrical and Computer Engineering (IJECE), Vol. 5, No 5. Oct. 2015. [7] J. Nahman, Modeling simultaneous outages for Bulk-power system reliability analysis, IEEE Trans on Reliability, Vol. R-34, No. 5. Nov. 1985. [8] J. Nahman, M. Grahovac, Load modeling for generating capacity reliability evaluation using frequency and duration method, IEE Proceeding-C, Vol. 139, No. 6, Nov. 1992. [9] DIgSILENT PowerFactory 15, User Manual, Gomaringen 2014. [10] SIEMENS i EXOR “Electrical project of reconstruction of substation 110 kV i 35 kV in HE”, 2005. [11] T.M. Chan, F. Heil, D. Kopejkova “Report on the second international survey on high voltage gas isolated substation service experience”, CIGRE, Paris, WG, 1998K. Karsai, D. Kerenyi, L. Kiss „Large Power Transformers“, Oxford 1987. [12] Croatian Transmission System Operator, HOPS d.o.o Zagreb “Operational Events Statistics for 2013”, Zagreb, 2014 S. D. Bole, “Mitigation of Inrush Current in Transformer”, International Journal of Innovative Technology and Exploring Engineering (IJITEE), ISSN: 2278-3075, Volume-3, Issue-7, Dec. 2013. BIOGRAPHIES OF AUTHORS Srete Nikolovski, PhD.MSc.El.Eng. (IEEE M’1995, SM’2005) was born in Belgrade on October 1, 1954. He obtained his BSc degree (1978) and MSc degree (1989), in electrical engineering at the Faculty of Electrical Engineering, University of Belgrade and his PhD degree from the Faculty of Electrical and Computing, University of Zagreb, Croatia in 1993. He is currently a Full Professor at the Department of Power Engineering at the Faculty of Electrical Engineering, Computer Science and Information Technology, J. J. Strossmayer University of Osijek, Croatia. His main interests are power system protection, power system analysis and reliability. He has published 200 technical papers in international journals and proceedings. He is a Senior Member of IEEE Reliability Society, PES Society and the Croatian CIGRE. Goran Slipac, PhD.El.Eng, was born in Travnik, on February 25 1960. He obtained his diploma degree in 1983 in field of Electrical Power Engineering from the Faculty of Electrical Engineering and Computing, University of Zagreb and a master degree in the field of on the same Faculty. During 1994-2001 he attended training courses in Argonne, USA, in the field of Generation Expansion Planning and Energy Demand Analysis. He was a Manager of Corporate Development Department in HEP Inc. (Croatian Electricity Utility) and a Director of HEP Renewables company. He is currently employed as an Advisor of HEP Inc. Management Board. He is the former chairman of the Study Committee C1 Croatian CIGRE. His main interests are power system analysis and generation expansion planning.
  • 12. IJECE ISSN: 2088-8708  Generator Assessment of Hydro Power Station Adequacy after Reconstruction from … (Srete Nikolovski) 740 Emir Alibašić, Dipl.El.Ing., was born in Tuzla on March 12, 1982. He obtained his BCs degree (2007) in Tuzla in field of Electrical engineering at the Faculty of Electrical Engineering, University of Tuzla. Currently he is a PhD student at Faculty of Electrical Engineering, J.J. Strossmayer University of Osijek, Croatia. His main interests are power transmission lines and optimization of electrical energy transmission. He wass employed at UMEL- DALEKOVODMONTAZA Tuzla on the position of design and maintenance of objects up to 400 kV and currently is owner INFORM Agency for the development of software applications. Currently he works as ITC manager at ZZO TK.