PMP EXAM
SAMPLE Q & A
A project manager meets with a customer for initial discussions about an upcoming project. At
the end of the meeting, the customer asks the project manager for a rough estimate of the
project duration. Based on her experience with three similar projects, the project manager
provides an estimate of 8-10 months.
What estimation technique does the project manager use?
A. Expert judgment
B. Three-point estimating
C. Analogous estimating
D. Bottom-up estimating
HINT: Identify the estimating technique that compares a project to a previous, similar project.
Question
The correct answer is C
The project manager is using historical duration information from comparable projects to
estimate the duration of a future project. This gross value estimating approach is called
analogous estimating and is frequently used to provide a ballpark figure when there is a limited
amount of detailed information available about the project.
Answer
All our questions are updated to the latest 
A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.


Stop by at free.pm-exam-simulator.com/ and try the
PM Exam Simulator free for 7 days.


We are a trusted and experienced education provider.

Free PMP Sample Q & A

  • 1.
  • 2.
    A project managermeets with a customer for initial discussions about an upcoming project. At the end of the meeting, the customer asks the project manager for a rough estimate of the project duration. Based on her experience with three similar projects, the project manager provides an estimate of 8-10 months. What estimation technique does the project manager use? A. Expert judgment B. Three-point estimating C. Analogous estimating D. Bottom-up estimating HINT: Identify the estimating technique that compares a project to a previous, similar project. Question
  • 3.
    The correct answeris C The project manager is using historical duration information from comparable projects to estimate the duration of a future project. This gross value estimating approach is called analogous estimating and is frequently used to provide a ballpark figure when there is a limited amount of detailed information available about the project. Answer
  • 4.
    All our questionsare updated to the latest  A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days. We are a trusted and experienced education provider.