1. The project aims to investigate the feasibility of constructing a
hydroelectric dam from a technical, economic, and social point of
view. The project charter created by the project manager on
behalf of the project sponsor is now approved.
Which of the following processes should be performed next?
A. Develop Project Management Plan
B. Identify Risks
C. Identify Stakeholders
D. Develop Project Charter
HINT: All of the project initiation processes should be completed
before moving on to the planning processes.
QUESTION
2. The correct answer is C.
The Identify Stakeholders process is the process of identifying all
people or organizations impacted by the project and
documenting relevant information regarding their interests,
involvement, and impact on project success. Both the Develop
Project Charter process and the Identify Stakeholders process are
part of the Initiating Process Group which should be completed
before proceeding to the processes in the Planning Process
Group. In this scenario, since the project charter has been
developed and approved, the Identify Stakeholders process
should be performed next.
ANSWER
3. All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge (PMBOK® Guide)
standard.
Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator
free for 7 days.
We are a Project Management Institute (PMI)® Registered Education Provider.