WHAT HAPPENS
IN -BETWEEN
IS THE
MANAGEMENT
STAGE I
PROPOSED ROUTE SURVEY
 After studying the SOW from the client .
It is important to survey the project route and take
note of the terrain.
 The use of GPS and knowledge of it with other
mapping
software is an hedge in this stage
IT IS ALL ABOUT
COMPLING WITH
PROCESS
..it has start and end
It begins with
SURVEY of the
PROPOSED ROUTE
STAGE II
DRAFTING AND DRAWING OF
THE SURVEY
IN AUTO-CAD FORMAT
MH 1 MH 2 IN
MH 3
IN
MH 5 OUT
MH 4 OUT
MH 6 MH 7
STAGE III
TRENCHING
YOU CAN CALL IT
DIGGING, REMOVAL OF
THE TERRAIN SUFARCE
TO A GIVEN DEPTH
ASPHALT CUTTING, CONCRETE
BREAKING, THRUST BORING, PAVE
STONES, SWAMP AREAS, BRIGDE
CROSSING are some of the terrain to
work with during
TRENCHING
STAGE IV : CONCRETE WORK
casting of MANHOLE and ROUTE MARKER
Manhole are the concrete junction box site at given interval on the project route
THIS CAN BE CONSTRUCTED ON SITE (IN-SITU)
OR
CAST IN THE PROJECT EQUIPMENT LOCATED (PRE-CAST)
Route marker are the short pillars erected along the fiber route to indicate the
presence of underground telecom facilities
STAGE V
DUCTING & COUPLING
Laying of
(PVC Polyvinyl chloride) (HDPE: High density polyethene) & GI Pipe
WHAT IS COUPLING
JOINING OF DUCTS TOGETHER FOR CONTINUITY
PVC COUPLING
PVC (Polyvinyl chloride)COUPLING INVOLVE SETTING
THE FEMALE SIDE OF THE PIPE AGAINST THE MALE SIDE
SUB-DUCT COUPLING
THE SUB-DUCT KNOWN AS HDPE (High Density
Polyethylene) VARY IN SIZES 33/40mm. It is uniform
in size. Unlike PVC, it does not have male and female
sides. joining requires a special coupler
and techniques
STAGE VI
BACKFILLING
&
REINSTATEMENT
This term refers to the returns of the excavated soil to the trench. Warning tape is
required here before total backfilling. Reinstatement only takes place where
major terrain such as asphalt cutting and concrete breaking take place
STAGE VII
FIBER WORK
FIBER PULLING : HAND PULLING OR BLOWING
It involve inserting of the fiber
optics cable into the sub-duct
from manhole to manhole to the
end of the cable drum or
cassette.
Equipment such as the calibration rope, stager,
hand and blowing machine can be deployed
to achieve this stage
STAGE VIII
FIBER CABLE
TERMINATION
Connectorization and splicing
STAGE IX : TESTING
INSERTION LOSS TEST AND OTDR TEST
VISUAL FAULT LOCATOR
OLTS
OTDR
STAGE X
DOCUMENTATION OF THE TEST RESULT, AS- BUILT DRAWING
For all your
fiber Optics certification
training
in
Nigeria
visit
www.imtfiber.com
and
www.imtcomputer.net

Fiber Optic project implemetation procedure

  • 2.
  • 3.
    STAGE I PROPOSED ROUTESURVEY  After studying the SOW from the client . It is important to survey the project route and take note of the terrain.  The use of GPS and knowledge of it with other mapping software is an hedge in this stage
  • 4.
    IT IS ALLABOUT COMPLING WITH PROCESS ..it has start and end
  • 5.
    It begins with SURVEYof the PROPOSED ROUTE
  • 6.
    STAGE II DRAFTING ANDDRAWING OF THE SURVEY IN AUTO-CAD FORMAT MH 1 MH 2 IN MH 3 IN MH 5 OUT MH 4 OUT MH 6 MH 7
  • 7.
  • 8.
    YOU CAN CALLIT DIGGING, REMOVAL OF THE TERRAIN SUFARCE TO A GIVEN DEPTH
  • 9.
    ASPHALT CUTTING, CONCRETE BREAKING,THRUST BORING, PAVE STONES, SWAMP AREAS, BRIGDE CROSSING are some of the terrain to work with during TRENCHING
  • 10.
    STAGE IV :CONCRETE WORK casting of MANHOLE and ROUTE MARKER Manhole are the concrete junction box site at given interval on the project route THIS CAN BE CONSTRUCTED ON SITE (IN-SITU) OR CAST IN THE PROJECT EQUIPMENT LOCATED (PRE-CAST) Route marker are the short pillars erected along the fiber route to indicate the presence of underground telecom facilities
  • 11.
    STAGE V DUCTING &COUPLING Laying of (PVC Polyvinyl chloride) (HDPE: High density polyethene) & GI Pipe
  • 12.
    WHAT IS COUPLING JOININGOF DUCTS TOGETHER FOR CONTINUITY
  • 13.
    PVC COUPLING PVC (Polyvinylchloride)COUPLING INVOLVE SETTING THE FEMALE SIDE OF THE PIPE AGAINST THE MALE SIDE
  • 14.
    SUB-DUCT COUPLING THE SUB-DUCTKNOWN AS HDPE (High Density Polyethylene) VARY IN SIZES 33/40mm. It is uniform in size. Unlike PVC, it does not have male and female sides. joining requires a special coupler and techniques
  • 15.
    STAGE VI BACKFILLING & REINSTATEMENT This termrefers to the returns of the excavated soil to the trench. Warning tape is required here before total backfilling. Reinstatement only takes place where major terrain such as asphalt cutting and concrete breaking take place
  • 16.
    STAGE VII FIBER WORK FIBERPULLING : HAND PULLING OR BLOWING
  • 17.
    It involve insertingof the fiber optics cable into the sub-duct from manhole to manhole to the end of the cable drum or cassette.
  • 18.
    Equipment such asthe calibration rope, stager, hand and blowing machine can be deployed to achieve this stage
  • 19.
  • 20.
    STAGE IX :TESTING INSERTION LOSS TEST AND OTDR TEST VISUAL FAULT LOCATOR OLTS OTDR
  • 21.
    STAGE X DOCUMENTATION OFTHE TEST RESULT, AS- BUILT DRAWING
  • 22.
    For all your fiberOptics certification training in Nigeria visit www.imtfiber.com and www.imtcomputer.net