 Overview of Turbine
 Concept of Governing System
 Functioning of EHC Circuits
 Turbine Start Up Procedure
 TSI & TSC System
 Turbine Protection System
Ext.
No
Source Of Extraction Destination Equipments
1 13th stage of HPT HPH-8
2 CRH HPH-7
3 3rd stage of IPT HPH-6 *
3 3rd stage of IPT TDBFP
4 6th stage of IPT DEAERATOR
5 8th stage of IPT LPH-4
6 11th stage of IPT LPH-3
7 2nd stage of LPT LPH-2
8 4th stage of LPT LPH-1
Turbine Extractions
 Turbine: HPT, IPT, LPT1 and LPT2
 Turbine Bearings: 08
 Generator / Exciter Bearings: 04
 Turbine Stop Valves: 04 (HPSV-1&2, IPSV-1&2)
 Turbine Control Valves: 08 (4 HPCV & 4 IPCV)
 CRH Check Valves: 02 ( With Bypass lines for warm up)
 Motor driven Shut Off valve in non-stabilized oil line to
Check Valve
 Motor driven warm up Shut Off valves for HPCV-3 & 4
 Governing Box
 Motor operated Control Gear to generate resetting /
protection oil & control oil for S.V./ Summators
 Two Manual trip devices
 Two Over Speed Governor Slide valves (110 % & 111 %)
 Two Remote Trip Solenoids
 Slide Valve for ATT with two solenoids
 Combination of throttle & nozzle governing
 IP Turbine has throttle governing – all four control
valves open simultaneously
 HP Turbine has nozzle governing – all four control
valves open in preset sequence
 Resetting of Turbine is done by Control Gear operation
 Operation of Stop & Control Valves and CRH Check
Valves are done by spring type hydraulic servomotors
 Servomotors are closed by spring action during loss of
oil pressure
 HPT control valves open only after achieving preset load
(12% of 660 MW)
 Opening time of control valve is 1.5 sec
 Closing time of Stop valve in case of operation of
protection is 0.3 sec
 Turbine maximum speed is restricted to 108% in case of
generator disconnected from grid
 Over speed protection system stops steam supply in
HPC in < 0.5s
 Speed Controller Droop is adjustable from 2.5% to 8%
(with dead band of 0.04%)
 Stabilized oil pressure of 50 Ksc is supplied to Control
Gear
 The control gear (AE001) is moved from closed position
(0 degree) to open position (90 deg)
 Oil is first supplied to reset the over speed governor slide
valves
 Subsequently Protection Oil is generated and supplied
to protection devices
 Finally, Control Oil for Stop Valves servomotors &
Control Oil for EHC-summators are generated
 Control Oil pressure in S.V. servomotor moves up slide valve,
providing Header Pressure Oil under the piston for S.V. opening
 Header Pressure Oil is supplied to C.V. valve servomotors via
locking pilot valve & traction/bush arrangements. Opening of C.V.
is governed by Control Oil from EHC-Summator
 During loss of Header Pressure Oil, the servomotors are closed by
spring action
 During loss of Control Oil pressure, Bush & Traction of Pilot valve
travels up shutting off head pressure oil supply to C.V.
servomotors, resulting control valve closing
 During S.V. ATT, bush & Traction do not travel up due to slide valve
downward movement by ATT motor
EHC comprises of following controllers:
1. Speed Controller
2. Pressure Controller
3. Load Controller
4. Position Controller
 EHC can be kept in Manual / Auto Mode as per
operator’s choice
 Manual mode can be selected only when Generator is
connected to grid
 In Manual Mode, operator can directly open / close the
control valves
 Controllers can be selected in auto mode through P.B
provided on operators console or through interlocks
 Controller output in auto mode depends on set point and
actual value
Logic-1
Speed
Set Point
R
L
Speed Set
Point = 0
Rate Logic
Logic - 2
Actual Speed
(Mv3)
+
-
Speed
Controller
O/P
Logic 1: Turbine protection operated / 2v4 stop valves closed / 2v3 speed
measuring channels faulty / Deviation between actual speed and set point
during run-up exceeded allowable value*
Logic 2: Speed gradient is controlled by minimum of TSE margin &
gradient from selected Start up curve, given by the Turbine Manufacturer
Contd….
Rolling Speed Gradient Curve
Speed gradients as per Manufacturer’s start up curve are as follows:
Rolling Condition Target Speed Preset Time Min. Halt Time
Cold Startup
( > 72 H )
3 - 500 rpm 150 sec 300 sec
1200 rpm* 550 sec 300 sec
3000 rpm 630 sec --------
Between 36H – 72H
3 - 500 rpm 75 sec 120 sec
3000 rpm 240 sec --------
Between 8H – 36H 3 - 3000 rpm 360 sec --------
Between 2H – 8H
3 - 3000 rpm 300 sec --------
 Speed Controller will be switched on automatically in
case generator breaker opens (with Turbine controller
on auto) or Turbine trips
 Turbine speed measurement is be done by using 3
sensors (eddy current type)
 The mean* of the three sensors is taken as actual
speed
 Incase of one sensor fault, maximum of rest two
sensors will come in service
 Incase of two sensor fault, Turbine trip signal is
generated to trip the turbine
 Speed Ref Tracking:
After Synchronization, with other controller in service,
the speed controller tracks the actual speed between
49HZ to 51HZ (adjustable)
 Islanding Mode:
If actual speed exceeds speed reference by a preset
limit under Generator Breaker in closed condition,
Islanding mode occurs – Transferring Turbine to Speed
Control mode
 Load Control On: Load Controller will be switched on
automatically if Turbine controller is kept on auto and
connected to the grid under “Turbine Latched” condition.
 Load Control Off: Load controller will be switched off
under following conditions:
1. Manual control mode is switched on
2. The Generator has disconnected from the grid
3. The grid frequency has gone beyond allowable limits
4. Load Measurement faulty (2/3 sensors faulty)
5. M.S. Pres. measurement faulty (2V3 sensors faulty)
6. Unit is in Pressure Control mode
Load Ref
R
L Delay Element
Max.Load Lim. Min.Load Lim.
Correction
C.K.T
Freq. Corr
Press. Corr
Fast
Tracking
Actual Load
+
-
O/P
Logic - 4
5
6
STOP
3
2
1
Logic-1: CMC ON, when load ref. will come from CMC circuit, where TSC
Margin calculation controls the gradient
Logic-2: The Load reference tracks actual load for bump less transfer
once it is connected to the grid.
Contd…
Logic-3: Load Reference will be stopped under the following
Conditions:
1. TSC Margin is less than permissible value*
2. The difference between the actual and reference value is
not in allowable range
Logic-4: Maximum and minimum load set points, set by the Operator
Logic-5: External Frequency Influence ON - actual frequency will be
tracked at a predefined delayed rate, with an adjustable droop to
help in loading and unloading of the machine within a band of
frequency
Contd…
Logic – 6: The Pressure correction is divided into two Parts:
1. Before the “HPC On” is generated, the pressure
correction will be calculated with R.H. pressure
2.After “HPC On” is generated, the pressure correction
will be calculated with M.S pressure
HPC On: The point at which the HP Control Valves starts Opening
(12% of full load)
Load Measurement: Three Transducers with mean* value selection
Incase of one of the transducer failed, maximum of rest two.will be
selected
 Pressure Control is switched ON by the operator or
automatically through Turbine Control on auto when HPC
is in operation
 Pressure Controller is automatically deactivated under the
following conditions:
1. GCB Open
2. The frequency is more than allowable value*
3. M.S. pressure transducers failed (2V3)
4. Manual Control switched on
5. Load control is On
6. HPC is out of operation
• M.S. pressure set point is dictated by Boiler Master
• Limitation of pressure drop to impermissible value is ensured by
minimum pressure controller
• Limitation of pressure rise to impermissible value is ensured by a
protective control stage maximum steam pressure controller, which
comes into operation through maximum value selector
Adder Block
M. S. Pr. Set Point
Actual Pr. Value +
-
PI
Controller
MIN
Minimum Pr.
Controller
MAX
Control Stage Max
Pr. Controller
O/P
• A PI controller is used to generate the signal to the current amplifiers
through Limiter
• Command to HP control valves extends under “HPC ON” condition
• Loss of current signal to I/H Converter results in closing of the C.V.
MV2
Posn. F/B - 1
Posn. F/B - 2
Control Signal From TC
+
- PI
+
+
MIN
Limiter
O/P- (0-150mA)
Biasing Current 0.8 to 1A
TO I/H
CONVERTOR
 I/H Converters control the opening and closing of the
corresponding control valves
 Individual I/H converters get command from Turbine
controller
 50 Ksc Header Pressure Oil holds the piston (2) up
against spring action
 As the slide valve (1) moves as per I/H converter, 35 Ksc
control oil output is regulated for C.V. servomotor
operation
 When 50 KSC Governing oil pressure collapses, piston
(2) travels down due to spring action – thus draining the
oil line of C.V. servomotor
 Start Turbine rolling with Speed Control on from barring
speed to 500 rpm
 After achieving desired criteria, raise speed set point to 1200
rpm* and subsequently to 3000 rpm
 After synchronization Load Controller gets switched On –
raise load > 80MW when “HPC ON” signal is generated
 Turbine Pressure Control will be automatically switched On
 After HPCV demand crosses 80%, switch ON Position
controller to hold 80% as the o/p to control valves for raising
pressure to rated value
 Switch ON Pres. Controller to raise load to rated value
 Switch ON Load Control after load reaches the rated value
START UP CURVES OF TURBINE AFTER SHUTDOWN OF THE UNIT
 To – S.H Live steam temperature.
 Trh – R.H steam temperature
 Po – S.H outlet steam pressure
 Prh – R.H. steam pressure
 Go – Electrical Load of TG
 Ne – Live steam flow from boiler
 N – Turbine rotor speed
 A – Steam Admission
 B – Synchronization
 C – HPC switch on
 D – HPCV open with 20% Throttle reserve & Loading with
constant HPCV position & HP heaters charged
 E – HPCV no-3 opening. Throttle pressure reduced
 F – Full Load
START UP CURVES OF TURBINE AFTER SHUTDOWN OF THE UNIT
START UP CURVES OF TURBINE AFTER SHUTDOWN OF THE UNIT
 Turbo Generator consists of 12 bearings – 8 for Turbine
& 2 for Generator & 2 for Exciter
 For Bearing no. 1-10, abs. brg. vibration is measured in
3 components (Horizontal, Vertical & Horizontal axial)
 For Bearing no. 11 & 12, abs. brg. vibration is measured
in 2 components (Horizontal & Vertical)
 Absolute shell vibration is measured for all the bearings
in 2 components (Horizontal & Vertical)
 Rotor Relative Vibration is measured in all the bearings in
2 components
 Absolute Rotor Vibration is derived from Absolute Bearing
Shell Vibration and Rotor Relative Vibration for all the
bearings
 Axial Shift measurement is done in Bearing no. 3
 Eccentricity measurement is done in Bearing no. 1
 Turbine Speed sensors and Key phasor are Installed in
Bearing no. 1
Turbovisory Instruments
Brg. No. Abs. Brg. Vib. Abs.Shel
Vib.
(2Comp)
Rel.Rotor
Vib.
(2 Comp)
Ang. Dis.
Brg.
Shell
(2 Comp)
Casing
Exp.
Rotor
Exp.
3 Comp 2 cmp
1 Y N Y Y N Y (HPC) Y
2 Y N Y Y N
3 Y N Y Y N
4 Y N Y Y Y Y (IPC) Y
5 Y N Y Y Y
6 Y N Y Y Y Y (LPC-1) Y
7 Y N Y Y Y
8 Y N Y Y Y Y (LPC-2) Y
9 Y N Y Y Y
10 Y N Y Y N
11 N Y Y Y N
12 N Y Y Y N
Turbovisory Instruments
 The Stress Margin of the Turbine is
calculated by measuring the temperatures of
following components:
1. HPC Rotor and Outer Casing
2. IPC Rotor and Outer Casing
3. 2 HP Stop Valves
4. 2 IP Stop Valves
5. 4 HP Control Valves
6. 4 IP Control Valves
Turbine protection system consists of Two
Independent channels, each operating the
corresponding solenoid (220V DC) to trip the Turbine
in case of actuation of remote protection
Hydraulic Protection: Apart from the Electrical Trip,
Turbine is equipped with the following Hydraulic
Protections:
1. Local Manual Trip (1V2)
2. Over speed Trip #1 at 110% of rated speed
3. Over speed Trip #2 at 111% of rated speed
4. Governing oil pressure < 20 Ksc
Contd..
Contd…
 Axial shift Very High (2V3) [-1.7mm, +1.2mm]
 Turbine bearing vibration : Very High (2V10 including X &
Y directions)* >11.2mm/sec (Td=2 sec)
 Lube oil tank level very Low (2V3)* Td=3sec (Arming with
two stop valves open)
 Lub oil pressure Very Low (2V3) < 0.3 Ksc; Td =3 sec
(Arming with two stop valves open)
 Condenser pressure Very High (2V3) > - 0.7ksc
(Arming with condenser press < 0.15 ksc Abs)
Contd..
Turbine Protection System
 M.S. temp Very Low (2V3) < 470 deg C (arming > 512
deg C)*
 M.S. temp Very High (2V3) > 565 deg C*
 HRH temp Very Low (2V3) < 500deg C (arming > 535
deg C)*
 HRH temp Very High (2V3) > 593deg C*
 HPT outlet temperature Very High (2V4) > 420 deg C
Contd…
 Gen seal oil level of any seal oil tank Very Low (2V3)* <
0 mm;Td=15 sec (Arming with any two stop valves
open)
 All Generator seal oil pumps OFF (3V3)* Td: 9 sec
(Arming with any two stop valves open)
 Generator Stator winding flow Very Low (2v3) < 17.3
m3/hr; Td =120 sec (Arming with any two stop valves
open)
 Generator hot gas coolers flow Very LOW (2V3)* :
<180m3/hr; Td=300sec(Arming with any two stop
valves open)
 Generator cooler hot gas temp. Very High(2V4) > 85
deg (Td = 300sec
Contd…
 MFT operated: (2V3)
 Deareator level Very High (2V3) > 3400 mm*
 HP heater level protection operated (2V3)*
 Generator Electrical protection operated (2V3)
 Turbine over speed protection operated (114%)
 Turbine Controller failure protection operated (2V3)
Contd…
SIPAT 660 MW Turbo- Governing & Protection System.ppt

More Related Content

Similar to SIPAT 660 MW Turbo- Governing & Protection System.ppt

Kiln Hydraulic Thrust Device.pdf
Kiln Hydraulic Thrust Device.pdfKiln Hydraulic Thrust Device.pdf
Kiln Hydraulic Thrust Device.pdfHamedMostafa10
 
action-d20dt-repairs-manual.pdf
action-d20dt-repairs-manual.pdfaction-d20dt-repairs-manual.pdf
action-d20dt-repairs-manual.pdfalexgeneral
 
94716008 burner-management-system-et-2008
94716008 burner-management-system-et-200894716008 burner-management-system-et-2008
94716008 burner-management-system-et-2008Mowaten Masry
 
HPLP bypass HPLP bypass HPLP bypass ET 2010.ppt
HPLP bypass HPLP bypass HPLP bypass ET 2010.pptHPLP bypass HPLP bypass HPLP bypass ET 2010.ppt
HPLP bypass HPLP bypass HPLP bypass ET 2010.pptBhaiyaKamalendu1
 
Synchronising the 210MW unit to the 220KV grid
Synchronising the 210MW unit to the 220KV gridSynchronising the 210MW unit to the 220KV grid
Synchronising the 210MW unit to the 220KV gridManohar Tatwawadi
 
Burner Management System ( FSSS).pptx
Burner Management System ( FSSS).pptxBurner Management System ( FSSS).pptx
Burner Management System ( FSSS).pptxManzoorAlam40
 
Operation of hydro power plants
Operation of hydro power plants Operation of hydro power plants
Operation of hydro power plants DINESHPRASAD39
 
Globe core oil purification plant SMM 0.6
Globe core oil purification plant SMM 0.6Globe core oil purification plant SMM 0.6
Globe core oil purification plant SMM 0.6GlobeCore
 
MODELLING CASCADED SPLIT RANGE (CASC-SRC) CONTROLLERS IN ASPEN HYSYS DYNAMICS
MODELLING CASCADED SPLIT RANGE (CASC-SRC) CONTROLLERS IN ASPEN HYSYS DYNAMICSMODELLING CASCADED SPLIT RANGE (CASC-SRC) CONTROLLERS IN ASPEN HYSYS DYNAMICS
MODELLING CASCADED SPLIT RANGE (CASC-SRC) CONTROLLERS IN ASPEN HYSYS DYNAMICSVijay Sarathy
 
INTRODUCTION TO GOVERNING
INTRODUCTION TO GOVERNINGINTRODUCTION TO GOVERNING
INTRODUCTION TO GOVERNINGSURAJ KUMAR
 
Control Philosophy for Smart Water distribution
Control Philosophy for Smart Water distributionControl Philosophy for Smart Water distribution
Control Philosophy for Smart Water distributionRaja Kannan
 
electric pump and 2.6 CLSS Electronics.ppt
electric pump and 2.6 CLSS Electronics.pptelectric pump and 2.6 CLSS Electronics.ppt
electric pump and 2.6 CLSS Electronics.pptdatazaky
 

Similar to SIPAT 660 MW Turbo- Governing & Protection System.ppt (20)

Diesel Fire Pump Controllers
Diesel Fire Pump ControllersDiesel Fire Pump Controllers
Diesel Fire Pump Controllers
 
Hplpbp
HplpbpHplpbp
Hplpbp
 
Kiln Hydraulic Thrust Device.pdf
Kiln Hydraulic Thrust Device.pdfKiln Hydraulic Thrust Device.pdf
Kiln Hydraulic Thrust Device.pdf
 
action-d20dt-repairs-manual.pdf
action-d20dt-repairs-manual.pdfaction-d20dt-repairs-manual.pdf
action-d20dt-repairs-manual.pdf
 
94716008 burner-management-system-et-2008
94716008 burner-management-system-et-200894716008 burner-management-system-et-2008
94716008 burner-management-system-et-2008
 
Steam Boiler Sequence Of Operation
Steam Boiler Sequence Of OperationSteam Boiler Sequence Of Operation
Steam Boiler Sequence Of Operation
 
محاضرة 5
محاضرة 5محاضرة 5
محاضرة 5
 
HPLP bypass HPLP bypass HPLP bypass ET 2010.ppt
HPLP bypass HPLP bypass HPLP bypass ET 2010.pptHPLP bypass HPLP bypass HPLP bypass ET 2010.ppt
HPLP bypass HPLP bypass HPLP bypass ET 2010.ppt
 
Synchronising the 210MW unit to the 220KV grid
Synchronising the 210MW unit to the 220KV gridSynchronising the 210MW unit to the 220KV grid
Synchronising the 210MW unit to the 220KV grid
 
On off controller
On off controllerOn off controller
On off controller
 
BMS FSSS.pptx
BMS FSSS.pptxBMS FSSS.pptx
BMS FSSS.pptx
 
Burner Management System ( FSSS).pptx
Burner Management System ( FSSS).pptxBurner Management System ( FSSS).pptx
Burner Management System ( FSSS).pptx
 
Operation of hydro power plants
Operation of hydro power plants Operation of hydro power plants
Operation of hydro power plants
 
Globe core oil purification plant SMM 0.6
Globe core oil purification plant SMM 0.6Globe core oil purification plant SMM 0.6
Globe core oil purification plant SMM 0.6
 
MODELLING CASCADED SPLIT RANGE (CASC-SRC) CONTROLLERS IN ASPEN HYSYS DYNAMICS
MODELLING CASCADED SPLIT RANGE (CASC-SRC) CONTROLLERS IN ASPEN HYSYS DYNAMICSMODELLING CASCADED SPLIT RANGE (CASC-SRC) CONTROLLERS IN ASPEN HYSYS DYNAMICS
MODELLING CASCADED SPLIT RANGE (CASC-SRC) CONTROLLERS IN ASPEN HYSYS DYNAMICS
 
Diesel fuel 4_d5_stepiii
Diesel fuel 4_d5_stepiiiDiesel fuel 4_d5_stepiii
Diesel fuel 4_d5_stepiii
 
INTRODUCTION TO GOVERNING
INTRODUCTION TO GOVERNINGINTRODUCTION TO GOVERNING
INTRODUCTION TO GOVERNING
 
Control Philosophy for Smart Water distribution
Control Philosophy for Smart Water distributionControl Philosophy for Smart Water distribution
Control Philosophy for Smart Water distribution
 
J08 d common rail
J08 d common railJ08 d common rail
J08 d common rail
 
electric pump and 2.6 CLSS Electronics.ppt
electric pump and 2.6 CLSS Electronics.pptelectric pump and 2.6 CLSS Electronics.ppt
electric pump and 2.6 CLSS Electronics.ppt
 

More from MarcWorld

CE 533 Chapter 21.pptx
CE 533 Chapter 21.pptxCE 533 Chapter 21.pptx
CE 533 Chapter 21.pptxMarcWorld
 
CE 533 Chapter 15.pptx
CE 533 Chapter 15.pptxCE 533 Chapter 15.pptx
CE 533 Chapter 15.pptxMarcWorld
 
Advanced Control System.ppt
Advanced Control System.pptAdvanced Control System.ppt
Advanced Control System.pptMarcWorld
 
Super-Critical Boiler.ppt
Super-Critical Boiler.pptSuper-Critical Boiler.ppt
Super-Critical Boiler.pptMarcWorld
 
000-Forgings-PPT-Presentation-IMU_Basic_Knowledge_English_final_11-03-14.pdf
000-Forgings-PPT-Presentation-IMU_Basic_Knowledge_English_final_11-03-14.pdf000-Forgings-PPT-Presentation-IMU_Basic_Knowledge_English_final_11-03-14.pdf
000-Forgings-PPT-Presentation-IMU_Basic_Knowledge_English_final_11-03-14.pdfMarcWorld
 
fall00_boone.ppt
fall00_boone.pptfall00_boone.ppt
fall00_boone.pptMarcWorld
 
FACTS-FlexibleACTransmissionSystem.ppt
FACTS-FlexibleACTransmissionSystem.pptFACTS-FlexibleACTransmissionSystem.ppt
FACTS-FlexibleACTransmissionSystem.pptMarcWorld
 
400kv-Substation-Training-report-Unnao-India.ppt
400kv-Substation-Training-report-Unnao-India.ppt400kv-Substation-Training-report-Unnao-India.ppt
400kv-Substation-Training-report-Unnao-India.pptMarcWorld
 
Unburned Carbon versus CO2 Emission-PROMECON-BoilerOptimization.ppt
Unburned Carbon versus CO2 Emission-PROMECON-BoilerOptimization.pptUnburned Carbon versus CO2 Emission-PROMECON-BoilerOptimization.ppt
Unburned Carbon versus CO2 Emission-PROMECON-BoilerOptimization.pptMarcWorld
 
AKE2008H_08Luther_KWK-Subventionsloch_kurz.ppt
AKE2008H_08Luther_KWK-Subventionsloch_kurz.pptAKE2008H_08Luther_KWK-Subventionsloch_kurz.ppt
AKE2008H_08Luther_KWK-Subventionsloch_kurz.pptMarcWorld
 

More from MarcWorld (10)

CE 533 Chapter 21.pptx
CE 533 Chapter 21.pptxCE 533 Chapter 21.pptx
CE 533 Chapter 21.pptx
 
CE 533 Chapter 15.pptx
CE 533 Chapter 15.pptxCE 533 Chapter 15.pptx
CE 533 Chapter 15.pptx
 
Advanced Control System.ppt
Advanced Control System.pptAdvanced Control System.ppt
Advanced Control System.ppt
 
Super-Critical Boiler.ppt
Super-Critical Boiler.pptSuper-Critical Boiler.ppt
Super-Critical Boiler.ppt
 
000-Forgings-PPT-Presentation-IMU_Basic_Knowledge_English_final_11-03-14.pdf
000-Forgings-PPT-Presentation-IMU_Basic_Knowledge_English_final_11-03-14.pdf000-Forgings-PPT-Presentation-IMU_Basic_Knowledge_English_final_11-03-14.pdf
000-Forgings-PPT-Presentation-IMU_Basic_Knowledge_English_final_11-03-14.pdf
 
fall00_boone.ppt
fall00_boone.pptfall00_boone.ppt
fall00_boone.ppt
 
FACTS-FlexibleACTransmissionSystem.ppt
FACTS-FlexibleACTransmissionSystem.pptFACTS-FlexibleACTransmissionSystem.ppt
FACTS-FlexibleACTransmissionSystem.ppt
 
400kv-Substation-Training-report-Unnao-India.ppt
400kv-Substation-Training-report-Unnao-India.ppt400kv-Substation-Training-report-Unnao-India.ppt
400kv-Substation-Training-report-Unnao-India.ppt
 
Unburned Carbon versus CO2 Emission-PROMECON-BoilerOptimization.ppt
Unburned Carbon versus CO2 Emission-PROMECON-BoilerOptimization.pptUnburned Carbon versus CO2 Emission-PROMECON-BoilerOptimization.ppt
Unburned Carbon versus CO2 Emission-PROMECON-BoilerOptimization.ppt
 
AKE2008H_08Luther_KWK-Subventionsloch_kurz.ppt
AKE2008H_08Luther_KWK-Subventionsloch_kurz.pptAKE2008H_08Luther_KWK-Subventionsloch_kurz.ppt
AKE2008H_08Luther_KWK-Subventionsloch_kurz.ppt
 

Recently uploaded

What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 

Recently uploaded (20)

What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 

SIPAT 660 MW Turbo- Governing & Protection System.ppt

  • 1.
  • 2.  Overview of Turbine  Concept of Governing System  Functioning of EHC Circuits  Turbine Start Up Procedure  TSI & TSC System  Turbine Protection System
  • 3.
  • 4.
  • 5. Ext. No Source Of Extraction Destination Equipments 1 13th stage of HPT HPH-8 2 CRH HPH-7 3 3rd stage of IPT HPH-6 * 3 3rd stage of IPT TDBFP 4 6th stage of IPT DEAERATOR 5 8th stage of IPT LPH-4 6 11th stage of IPT LPH-3 7 2nd stage of LPT LPH-2 8 4th stage of LPT LPH-1 Turbine Extractions
  • 6.  Turbine: HPT, IPT, LPT1 and LPT2  Turbine Bearings: 08  Generator / Exciter Bearings: 04  Turbine Stop Valves: 04 (HPSV-1&2, IPSV-1&2)  Turbine Control Valves: 08 (4 HPCV & 4 IPCV)  CRH Check Valves: 02 ( With Bypass lines for warm up)  Motor driven Shut Off valve in non-stabilized oil line to Check Valve  Motor driven warm up Shut Off valves for HPCV-3 & 4  Governing Box
  • 7.
  • 8.  Motor operated Control Gear to generate resetting / protection oil & control oil for S.V./ Summators  Two Manual trip devices  Two Over Speed Governor Slide valves (110 % & 111 %)  Two Remote Trip Solenoids  Slide Valve for ATT with two solenoids
  • 9.
  • 10.  Combination of throttle & nozzle governing  IP Turbine has throttle governing – all four control valves open simultaneously  HP Turbine has nozzle governing – all four control valves open in preset sequence  Resetting of Turbine is done by Control Gear operation  Operation of Stop & Control Valves and CRH Check Valves are done by spring type hydraulic servomotors  Servomotors are closed by spring action during loss of oil pressure
  • 11.  HPT control valves open only after achieving preset load (12% of 660 MW)  Opening time of control valve is 1.5 sec  Closing time of Stop valve in case of operation of protection is 0.3 sec  Turbine maximum speed is restricted to 108% in case of generator disconnected from grid  Over speed protection system stops steam supply in HPC in < 0.5s  Speed Controller Droop is adjustable from 2.5% to 8% (with dead band of 0.04%)
  • 12.
  • 13.  Stabilized oil pressure of 50 Ksc is supplied to Control Gear  The control gear (AE001) is moved from closed position (0 degree) to open position (90 deg)  Oil is first supplied to reset the over speed governor slide valves  Subsequently Protection Oil is generated and supplied to protection devices  Finally, Control Oil for Stop Valves servomotors & Control Oil for EHC-summators are generated
  • 14.
  • 15.  Control Oil pressure in S.V. servomotor moves up slide valve, providing Header Pressure Oil under the piston for S.V. opening  Header Pressure Oil is supplied to C.V. valve servomotors via locking pilot valve & traction/bush arrangements. Opening of C.V. is governed by Control Oil from EHC-Summator  During loss of Header Pressure Oil, the servomotors are closed by spring action  During loss of Control Oil pressure, Bush & Traction of Pilot valve travels up shutting off head pressure oil supply to C.V. servomotors, resulting control valve closing  During S.V. ATT, bush & Traction do not travel up due to slide valve downward movement by ATT motor
  • 16. EHC comprises of following controllers: 1. Speed Controller 2. Pressure Controller 3. Load Controller 4. Position Controller
  • 17.  EHC can be kept in Manual / Auto Mode as per operator’s choice  Manual mode can be selected only when Generator is connected to grid  In Manual Mode, operator can directly open / close the control valves  Controllers can be selected in auto mode through P.B provided on operators console or through interlocks  Controller output in auto mode depends on set point and actual value
  • 18. Logic-1 Speed Set Point R L Speed Set Point = 0 Rate Logic Logic - 2 Actual Speed (Mv3) + - Speed Controller O/P Logic 1: Turbine protection operated / 2v4 stop valves closed / 2v3 speed measuring channels faulty / Deviation between actual speed and set point during run-up exceeded allowable value* Logic 2: Speed gradient is controlled by minimum of TSE margin & gradient from selected Start up curve, given by the Turbine Manufacturer Contd….
  • 19. Rolling Speed Gradient Curve Speed gradients as per Manufacturer’s start up curve are as follows: Rolling Condition Target Speed Preset Time Min. Halt Time Cold Startup ( > 72 H ) 3 - 500 rpm 150 sec 300 sec 1200 rpm* 550 sec 300 sec 3000 rpm 630 sec -------- Between 36H – 72H 3 - 500 rpm 75 sec 120 sec 3000 rpm 240 sec -------- Between 8H – 36H 3 - 3000 rpm 360 sec -------- Between 2H – 8H 3 - 3000 rpm 300 sec --------
  • 20.  Speed Controller will be switched on automatically in case generator breaker opens (with Turbine controller on auto) or Turbine trips  Turbine speed measurement is be done by using 3 sensors (eddy current type)  The mean* of the three sensors is taken as actual speed  Incase of one sensor fault, maximum of rest two sensors will come in service  Incase of two sensor fault, Turbine trip signal is generated to trip the turbine
  • 21.  Speed Ref Tracking: After Synchronization, with other controller in service, the speed controller tracks the actual speed between 49HZ to 51HZ (adjustable)  Islanding Mode: If actual speed exceeds speed reference by a preset limit under Generator Breaker in closed condition, Islanding mode occurs – Transferring Turbine to Speed Control mode
  • 22.  Load Control On: Load Controller will be switched on automatically if Turbine controller is kept on auto and connected to the grid under “Turbine Latched” condition.  Load Control Off: Load controller will be switched off under following conditions: 1. Manual control mode is switched on 2. The Generator has disconnected from the grid 3. The grid frequency has gone beyond allowable limits 4. Load Measurement faulty (2/3 sensors faulty) 5. M.S. Pres. measurement faulty (2V3 sensors faulty) 6. Unit is in Pressure Control mode
  • 23. Load Ref R L Delay Element Max.Load Lim. Min.Load Lim. Correction C.K.T Freq. Corr Press. Corr Fast Tracking Actual Load + - O/P Logic - 4 5 6 STOP 3 2 1 Logic-1: CMC ON, when load ref. will come from CMC circuit, where TSC Margin calculation controls the gradient Logic-2: The Load reference tracks actual load for bump less transfer once it is connected to the grid. Contd…
  • 24. Logic-3: Load Reference will be stopped under the following Conditions: 1. TSC Margin is less than permissible value* 2. The difference between the actual and reference value is not in allowable range Logic-4: Maximum and minimum load set points, set by the Operator Logic-5: External Frequency Influence ON - actual frequency will be tracked at a predefined delayed rate, with an adjustable droop to help in loading and unloading of the machine within a band of frequency Contd…
  • 25. Logic – 6: The Pressure correction is divided into two Parts: 1. Before the “HPC On” is generated, the pressure correction will be calculated with R.H. pressure 2.After “HPC On” is generated, the pressure correction will be calculated with M.S pressure HPC On: The point at which the HP Control Valves starts Opening (12% of full load) Load Measurement: Three Transducers with mean* value selection Incase of one of the transducer failed, maximum of rest two.will be selected
  • 26.  Pressure Control is switched ON by the operator or automatically through Turbine Control on auto when HPC is in operation  Pressure Controller is automatically deactivated under the following conditions: 1. GCB Open 2. The frequency is more than allowable value* 3. M.S. pressure transducers failed (2V3) 4. Manual Control switched on 5. Load control is On 6. HPC is out of operation
  • 27. • M.S. pressure set point is dictated by Boiler Master • Limitation of pressure drop to impermissible value is ensured by minimum pressure controller • Limitation of pressure rise to impermissible value is ensured by a protective control stage maximum steam pressure controller, which comes into operation through maximum value selector Adder Block M. S. Pr. Set Point Actual Pr. Value + - PI Controller MIN Minimum Pr. Controller MAX Control Stage Max Pr. Controller O/P
  • 28. • A PI controller is used to generate the signal to the current amplifiers through Limiter • Command to HP control valves extends under “HPC ON” condition • Loss of current signal to I/H Converter results in closing of the C.V. MV2 Posn. F/B - 1 Posn. F/B - 2 Control Signal From TC + - PI + + MIN Limiter O/P- (0-150mA) Biasing Current 0.8 to 1A TO I/H CONVERTOR
  • 29.
  • 30.  I/H Converters control the opening and closing of the corresponding control valves  Individual I/H converters get command from Turbine controller  50 Ksc Header Pressure Oil holds the piston (2) up against spring action  As the slide valve (1) moves as per I/H converter, 35 Ksc control oil output is regulated for C.V. servomotor operation  When 50 KSC Governing oil pressure collapses, piston (2) travels down due to spring action – thus draining the oil line of C.V. servomotor
  • 31.
  • 32.  Start Turbine rolling with Speed Control on from barring speed to 500 rpm  After achieving desired criteria, raise speed set point to 1200 rpm* and subsequently to 3000 rpm  After synchronization Load Controller gets switched On – raise load > 80MW when “HPC ON” signal is generated  Turbine Pressure Control will be automatically switched On  After HPCV demand crosses 80%, switch ON Position controller to hold 80% as the o/p to control valves for raising pressure to rated value  Switch ON Pres. Controller to raise load to rated value  Switch ON Load Control after load reaches the rated value
  • 33. START UP CURVES OF TURBINE AFTER SHUTDOWN OF THE UNIT
  • 34.  To – S.H Live steam temperature.  Trh – R.H steam temperature  Po – S.H outlet steam pressure  Prh – R.H. steam pressure  Go – Electrical Load of TG  Ne – Live steam flow from boiler  N – Turbine rotor speed  A – Steam Admission  B – Synchronization  C – HPC switch on  D – HPCV open with 20% Throttle reserve & Loading with constant HPCV position & HP heaters charged  E – HPCV no-3 opening. Throttle pressure reduced  F – Full Load
  • 35. START UP CURVES OF TURBINE AFTER SHUTDOWN OF THE UNIT
  • 36. START UP CURVES OF TURBINE AFTER SHUTDOWN OF THE UNIT
  • 37.
  • 38.  Turbo Generator consists of 12 bearings – 8 for Turbine & 2 for Generator & 2 for Exciter  For Bearing no. 1-10, abs. brg. vibration is measured in 3 components (Horizontal, Vertical & Horizontal axial)  For Bearing no. 11 & 12, abs. brg. vibration is measured in 2 components (Horizontal & Vertical)  Absolute shell vibration is measured for all the bearings in 2 components (Horizontal & Vertical)
  • 39.  Rotor Relative Vibration is measured in all the bearings in 2 components  Absolute Rotor Vibration is derived from Absolute Bearing Shell Vibration and Rotor Relative Vibration for all the bearings  Axial Shift measurement is done in Bearing no. 3  Eccentricity measurement is done in Bearing no. 1  Turbine Speed sensors and Key phasor are Installed in Bearing no. 1 Turbovisory Instruments
  • 40. Brg. No. Abs. Brg. Vib. Abs.Shel Vib. (2Comp) Rel.Rotor Vib. (2 Comp) Ang. Dis. Brg. Shell (2 Comp) Casing Exp. Rotor Exp. 3 Comp 2 cmp 1 Y N Y Y N Y (HPC) Y 2 Y N Y Y N 3 Y N Y Y N 4 Y N Y Y Y Y (IPC) Y 5 Y N Y Y Y 6 Y N Y Y Y Y (LPC-1) Y 7 Y N Y Y Y 8 Y N Y Y Y Y (LPC-2) Y 9 Y N Y Y Y 10 Y N Y Y N 11 N Y Y Y N 12 N Y Y Y N Turbovisory Instruments
  • 41.  The Stress Margin of the Turbine is calculated by measuring the temperatures of following components: 1. HPC Rotor and Outer Casing 2. IPC Rotor and Outer Casing 3. 2 HP Stop Valves 4. 2 IP Stop Valves 5. 4 HP Control Valves 6. 4 IP Control Valves
  • 42.
  • 43. Turbine protection system consists of Two Independent channels, each operating the corresponding solenoid (220V DC) to trip the Turbine in case of actuation of remote protection Hydraulic Protection: Apart from the Electrical Trip, Turbine is equipped with the following Hydraulic Protections: 1. Local Manual Trip (1V2) 2. Over speed Trip #1 at 110% of rated speed 3. Over speed Trip #2 at 111% of rated speed 4. Governing oil pressure < 20 Ksc Contd..
  • 45.  Axial shift Very High (2V3) [-1.7mm, +1.2mm]  Turbine bearing vibration : Very High (2V10 including X & Y directions)* >11.2mm/sec (Td=2 sec)  Lube oil tank level very Low (2V3)* Td=3sec (Arming with two stop valves open)  Lub oil pressure Very Low (2V3) < 0.3 Ksc; Td =3 sec (Arming with two stop valves open)  Condenser pressure Very High (2V3) > - 0.7ksc (Arming with condenser press < 0.15 ksc Abs) Contd.. Turbine Protection System
  • 46.  M.S. temp Very Low (2V3) < 470 deg C (arming > 512 deg C)*  M.S. temp Very High (2V3) > 565 deg C*  HRH temp Very Low (2V3) < 500deg C (arming > 535 deg C)*  HRH temp Very High (2V3) > 593deg C*  HPT outlet temperature Very High (2V4) > 420 deg C Contd…
  • 47.  Gen seal oil level of any seal oil tank Very Low (2V3)* < 0 mm;Td=15 sec (Arming with any two stop valves open)  All Generator seal oil pumps OFF (3V3)* Td: 9 sec (Arming with any two stop valves open)  Generator Stator winding flow Very Low (2v3) < 17.3 m3/hr; Td =120 sec (Arming with any two stop valves open)  Generator hot gas coolers flow Very LOW (2V3)* : <180m3/hr; Td=300sec(Arming with any two stop valves open)  Generator cooler hot gas temp. Very High(2V4) > 85 deg (Td = 300sec Contd…
  • 48.  MFT operated: (2V3)  Deareator level Very High (2V3) > 3400 mm*  HP heater level protection operated (2V3)*  Generator Electrical protection operated (2V3)  Turbine over speed protection operated (114%)  Turbine Controller failure protection operated (2V3) Contd…