SlideShare a Scribd company logo
AUX. SUPPLY
The service voltage which we are adopted in RSTPS are 11KV,
6.6KV , 415V 3PH AC supply and 240V 1PH AC supply.
11KV for Stage 2/3 MDBFPs.
6.6KV for station/unit HT auxiliaries like BFP s (stage-I), Mills,
ID/FD/ PA fans, CEPS, CW, RW Pumps & IAC/PAC etc.
415V for station aux like BAHP/FALP, Service water pumps,
unit aux like Seal Air fan, Lube oil pumps, AC seal oil pumps
and Centrifuge etc.
240V supply for lighting and welding.
These supplies are fed through the different switchgears
What are switchgears?
The equipment which normally fall in this category are:
Circuit Breakers
Isolators
Load break switches
Earth switches
Switch fuse units etc.
The switchgears are fed through different transformers
Transformer
Generator Transformer
Tie Transformer
The generator is connected to this transformer by means of bus ducts. This
transformer is used to step up the generating voltage of 18 / 21 KV to 400 KV .
This transformer is provided OFAF cooling and Off load tap changer.
There are total 4 No. of Tie Transformers are provided for feeding supply for
internal requirements. It steps down 400 KV to 33KV This transformer is
provided OFAF cooling and Off load tap changer.
Station Transformer
The station transformer is required to feed power to the auxiliaries
during start-ups, and C- auxiliaries when unit is in service.,
This transformer is normally rated for initial auxiliary load
requirements of unit.
It is provided with On load tap changer to cater to the fluctuating
voltage of the grid.
Unit Auxiliary Transformer
The UAT draws its power from the main bus duct-connecting
Generator to the GT. The total KVA capacity of unit Auxiliary
transformer require can be determined by assuming 0.85 power factor
and 0,9 efficiency for total load with a safe margin of 20%. It is
provided with On load tap changer to cater to the fluctuating voltage
of the grid.
Transformers
BREAKER
TRANSFORMER
ISOLATOR
SWITCH CUM
FUSE UNIT
FUSE
CONTACT
400 KV LINE
33 KV LINE
11 KV LINE
6.6 KV LINE
415 V LINE
220 DC LINE
5
SYMBOLS
33KV SWITCHGEAR
UNIT # 1
GEN
400 KV BUS # 2
400 KV BUS # 1
ST # 6
ST # 3 ST #
4
ST #
5
TIE # 1
75 MVA
400/33 KV
SEC # A SEC # B
SEC # C SEC # D SEC # E ~
~
GT # 5
21/400 KVTIE # 2
75 MVA
400/ 33 KV
TIE # 3
100MVA
400/ 33
KV
6
TIE # 4
100 MVA
400/ 33 KV
~
~
GT # 1
240 MVA
18/400 KV
UNIT # 5
GEN
ST # 1 ST # 2 ST #7
SEC #F
TIE # 2
400/33 Kv
75 MVA
TIE # 1
400/33 Kv
75 MVA
spare
WTP-2
CW-1
ST-1
CHPAUG-1
ST-6
COL-3
SWYD-1
TIETOSEC-F
COL-2
WTP-1
CW-2
ST-2
CHPAUG-2
CONST-2
TIETOSEC–E
SWYD-2
SEC-A SEC-BB/C
33 KV STAGE-I SWITCHGEAR
7
33 KV
MERRYLIN-
GERRIN
MAKE SF6
SHSLURRYLTG
TIETO1CW1
UNITSWGR-1B
UNITSWGR-2B
AIRCOMP-A
FOLTG
CHP-B
ASS-1
DAETP-1
UNITSWGR–3A
SPARE
UNITSWGR–1A
DAETP-2
UNITSWGR–2A
ST –1
33 / 6.6 KV
19 / 25 / 31.5 MVA
ST –2
33 / 6.6 KV
19 / 25 / 31.5 MVA
STLT-4
6.6 / 0.433
1.65 MVA
STLT-3
6.6 / 0.433
1.65 MVA
STLT-1
6.6 / 0.433
1.65 MVA
STLT-2
6.6 / 0.433
1.65 MVA
AIRCOMP
SWGR-B
CHP-A
ASXMER-2
UNITSWGR-3B
6.6 KV STATION SWITCHGEAR
B/C
1S1/2S1
B/C
1S2 / 2S2
1S1
1S2
2S1 2S2
ASHXMER-3
STN LT SWGR - 1 STN LT SWGR - 2
SEC-A SEC-B SEC-A SEC-B
8
NOTE: ALL SECTIONS HAVE BUS
VTS
LINE PT PANELS ARE
AVAILABLE IN 1S1 & 2S2
6.6 KV STATION SWITCHGEAR
INCOMER FROM STATION TRANSFORMER
PROTECTIONS
 Remote trip
 Local trip
 Mech.trip
 Elect.trips from
• E/F Relay
• IDMT O/C: R,Y,B phases.
INTERLOCKS
 Station transformer HT breaker
trip.
 Trips when Incomer from station
transformer and buscoupler is
ON in service position with trip
selection in this incomer.
PERMISSIVES
 
• 33 KV side charged.
• No elect trip from 
•  E/F Relay
•  IDMT  O/C: R,Y,B phases.
•No elect trip from Buscoupler.
• No Continuous close command
 
64
6.6 KV STATION SWITCHGEAR
BUSCOUPLER
PROTECTIONS
 Remote trip
 Local trip
 Mech.trip
 Elect.trips from
• E/F Relay
• IDMT O/C: R,Y,B
phases.
INTERLOCKS
• Trips when both
Incomers from station
transformer are ON in
service position with trip
selection in buscoupler..
PERMISSIVES
• No elect trip from 
• E/F Relay
•  IDMT  O/C: R,Y,B phases.
•No elect trip from Incomer from station 
transformer
• No Continuous close command
 
 
65
6.6 KV UNIT SWGR # A
6.6 KV UNIT SWGR # B
UT # A
25 MVA
18/6.6KV
6.6KV UNIT SWITCHGEAR
∼
200MW GEN
400KV BUS # 1
400KV BUS # 2
UT # B
25 MVA
18/6.6KV
FROM 1S2 / 1S2 / 1S1
(UNITS 1 / 2 / 3 )
FROM 2S1 / 2S1 / 2S2
(UNITS 1 / 2 / 3 )
GT
18 / 400 KV
240 MVA
14
6.6 KV UNIT SWITCHGEAR.
TIE INCOMER FROM STATION SWGR.
 
PROTECTIONS
 Remote trip
 Local trip
 Mech.trip
 Elect.trips from
• E/F Relay CTU 12(64)
• IDMT O/C Relay – R,Y,B phases
INTERLOCKS
 Breaker trips when UAT incomer is ON
in service position.
 Breaker closes on auto from command.
from GRP.
PERMISSIVES
 
• No elect trip from 
•  E/F Relay CTU 12(64)
•IDMT  O/C Relay – R,Y,B 
phases
• No elect trip from UAT incomer.
• upstream Isolator / breaker in service 
/ closed
• No Continuous close command
 
57
6.6 KV UNIT SWITCHGEAR.
INCOMER FROM UNIT TRANSFORMER
PROTECTIONS
 Local trip
 Mech.trip
 Remote trip
 Elect.trips from
 E/F Relay (51) -CDG
• IDMT O/C: R,Y,B, phases.
 Trip from GRP
INTERLOCKS
 Breaker trips when TIE incomer is
ON in service position
PERMISSIVES
 
• No elect trip from 
• E/F Relay (51) -CDG
• IDMT O/C:  R,Y,B, phases.
•Unit synchronised. 
•No elect trip from TIE incomer.
• No Continuous close command
 
 
58
6.6 KV,
ASEA MAKE
MOCB,
CW-I,
COMP-1,
RAW WATER
P/H
6.6 KV STAGE-2,
SIEMENS MAKE,
VACUUM CB
6.6 KV ABB,SF6,LWTP TRFR 1&2
SEC-A
IAC-1
UNIT LIGHTING XFMR
BFP-C
BFP-A
PA FANS A,C AND E
MILLS A,C AND E
CEP-A
FD-B
ID-B
UAT-A
ESP-A
SEC-B
BFP-C
BFP-B
PA FANS B,D AND F
MILLS B,D AND F
CEP-B
FD-A
ID-A
UAT-B
ESP-B
UNIT-1
SEC-A
IAC-3
UNIT LIGHTING 
XFMR
BFP-C
BFP-A
PA FANS A,C AND E
MILLS A,C AND E
CEP-A
FD-A
ID-A
UAT-A
ESP-A
SEC-B
BFP-C
BFP-B
PA FANS B,D AND F
MILLS B,D AND F
CEP-B
FD-B
ID-B
UAT-B
ESP-B
UNIT-2
SEC-A
UNIT LIGHTING 
XFMR
BFP-C
BFP-A
PA FANS A,C AND E
MILLS A,C AND E
CEP-A
FD-A
ID-A
UAT-A
ESP-A
SEC-B
BFP-C
BFP-B
PA FANS B,D AND F
MILLS B,D AND F
CEP-B
FD-B
ID-B
UAT-B
ESP-B
UNIT-3
6.6 KV UNIT SWITCHGEAR
15
HT MOTOR FEEDER
PERMISSIVES
 No elect trip from
 (i) E/F Relay
 (ii) Inst O/C Relay: R, Y,B Phases
 (iii) Lockout rotor
 (iv) Differential protection
 IDMT O/C: R, B phases.
 Overload
 EPB released
 Process permissive
 No Continuous close command
PROTECTIONS
 Local trip
 Remote trip
 Mech.trip
 EPB Pressed.
 Elect.trips from
• E/F Relay
• Inst O/C Relay R, Y,B Phases
 Lockout rotor
 Differential protection
 Overload.
 Process trips.
INTERLOCKS:
 Bus under voltage trip
63
TRANSFORMER HT SIDE FEEDER
PERMISSIVES
 No Elect trip from
 E/F Relay
 IDMT O/C Relay (51) R, Y, B Phases (or)
differential protection..
 Inst O/C Relay (50)
 R-Phase
 Y-Phase
 B-Phase
 Wdg.temp high
 Transformer oil temp. high
 Bucholtz trip
 No Continuous close command
PROTECTIONS
 Local trip
 Mech.trip
 Remote trip
 Elect.trips from
 E/F Relay
 IDMT O/C Relay (51) R, Y, B Phases
(or) differential protection..
 Inst O/C Relay (50)
 R-Phase
 Y-Phase
 B-Phase
 Transformer oil temp. high
 Wdg. temp. high
 Buchholtz trip
THIS IS APPLICABLE TO ESP, UAT , unit ltg, FO ltg, Ash slurry ltg, StationLT , CT LT, WTP LT, switchyard LT, ASH
SLURRY TRANSFORMERS HT SIDE BREAKER
62
UAT - A
6.6 / .433 KV
1.6 MVA
TGMCC–A
TGMCC–C
BMCC–A
BVDDC–A
TGMCC–B
TGMCC–D
BMCC–B
BVDDC–B
SEC-A SEC-BB/C
415V UNIT LT SWITCHGEAR 
 
UAT - B
6.6 / .433 KV
1.6 MVA
SPARE
SPARE
EMCC
From DG Set
EQUIPMENTS
CHARGERS
EMERGENCY
LTG
UPSALT
SOURCE
PAFANFLOP
MCC
EQUIPMENTS:
TGOP
TURNING GEAR MOTOR
VEF-B
SCANNER AIR FAN-A
APH-A AUX DRIVE
APH-B AUX DRIVE
CHARGERS:
FLOAT MAIN
BOOST CHARGER
UPS CHARGER-A
FROM
UNIT SWGR - A
FROM
UNIT SWGR - B
16
DG SWITCHGEAR
DG SET – 2
625 KVA
DG SET – 1
625 KVA
415 V LT BUS
TOUNIT–1EMCC
TOUNIT–2EMCC
TOUNIT–3EMCC
TOSWYD
25
PERMISSIVES
1 No Elect. trips from
Inst.O/C relay R,Y,B-phases
E/F relay
1 Upstream breaker closed in
service position.
3 No Continuous close command.
4 No Elect. trip from BUS COUPLER
5 Breaker panel door closed
UNIT LT SWITCHGEAR
INCOMER A &B
PROTECTIONS
01 Local trip
02 Remote trip
03 Mech trip
04 Inst O/C trip R,Y,B-phase
E/F relay
INTERLOCKS
01 Trips on Upstream breaker off.
02 Trips on breaker panel door open.
59
PERMISSIVES
1 No Elect. trips from
Inst.O/C. R, Y, B -phases
Earth Fault
2 No Elect. trips from
INCOMER - A
INCOMER - B
3 No Continuous close command.
4 Breaker panel door closed
UNIT LT SWITCHGEAR
BUS COUPLER
PROTECTIONS
1 Local trip
2 Remote trip
3 Mech trip
4 Electrical trips
Inst.O/C. R, Y, B -phases
Earth Fault
INTERLOCKS
01 Trips when Both incomers are ON and
in service position
02 Trips on breaker panel door open.
61
UNIT LT SWITCHGEAR
FEEDER (BMCC, BVDDC, TG MCC)
PROTECTIONS
 
1 Mech trip
2 Local trip                                  
               
2 Overload trip
3 Short circuit trip.
 
INTERLOCKS
 1 Upstream breaker OFF. 
2 Trips on breaker panel door 
open.                          
 PERMISSIVES                                  
                         
1     No Elect. trips from Inst.O/C 
relay   R,Y,B-phases 
2 No Continuous close command.
3 Breaker panel door closed
60
415V BOILER MCC
SEC - A SEC - B
SEC-A
MILLS A,C,E LUB OIL PUMPS
-GRAVIMETRIC FEEDERS A,C,E
-PA FANS A,C,E ISOLATING DAMPERS
-ROTARY FEEDERS C,D,E,F,G,H
-LP DOSING-A
-HP DOSING-A
-SEAL AIR FAN-B
-SH STAGE-I LHS AND RHS SPRAY BLOCK V/VS
-AUX PRDS V/V F036
-HPBYPASS OSU-1
-SOOT BLOWER CABINET SUPPLY
-D/A HIGH LEVEL CONTROL BYPASS V/V F046
-CG-A,C
APH-A MAIN MOTOR
SEC-B
MILLS B,D,F LUB OIL PUMPS
-GRAVIMETRIC FEEDERS B,D,F
-PA FANS B,D,F ISOLATING DAMPERS
-ROTARY FEEDERS A,B, I,J,K,L,M,N,O,P
-LP DOSING-B
-HP DOSING-B
-SEAL AIR FAN-A
-SH STAGE-II LHS AND RHS SPRAY BLOCK V/VS
-AUX PRDS INLET V/V F002 AND TIE V/V F010
-HPBYPASS OSU-2
-BOILER DEWATERING CABINET SUPPLY
-CRT MAKE UP CONTROL BYPASS V/V F047
-CG-B,D
-APH-B MAIN MOTOR
-SCANNER AIR FAN-B
-ECO INLET V/V F002
-UPS CHARGER -B
FROM UNIT LT
SWGR-A
FROM UNIT LT
SWGR-B
400 A
400 A
400 A
17
415V BOILER VDDC
SEC - A SEC - B
SEC-A
-START UP VENT F027
-AUX STEAM TO SCAPH-B INLET,OUTLET AND
REGULATING /VS F020, F022, F023
-ECO RECIR V/V F005
-FRS 30% INLET AND OUTLET V/VS
-BUNKER GATES A,C,E
-ESP PASS I AND II INLET AND OUTLET DAMPERS
ID-B INLET AND OUTLET DAMPERS
-AUX STEAM TO D/A PREHEATING V/V F046
-SH HEADER VENTS F690,F680 AND F682
-RHS MAIN STEAM STOP V/V F030
CBD ISO V/V F012
-AUX STEAM TO SCAPH-A INLET,OUTLET AND
REGULATING /VS F024, F026, F027
-EBD V/VS F017 AND F018
SEC-B
-RH VENT F710
-SH HEADER VENTS F700,F698,F692
-FRS 100% RHS AND MIDDLE INLET AND
OUTLET V/VS
-BUNKER GATES B,D,F
-ESP PASS III AND IV INLET AND OUTLET
DAMPERS
-ID-A INLET AND OUTLET DAMPERS
-LHS MAIN STEAM STOP V/V F040
-RH ATTEMPERATION BLOCK V/V F095
FROM UNIT LT
SWGR-A
FROM UNIT LT
SWGR-B
400 A
250 A
250 A
18
415V TGMCC - A
FROM UNIT LT
SWGR-A
TIE FROM / TO
TGMCC-D
BFP-A,B,C DISCHARGE V/VS AND INTEGRAL BYPASS V/VS
BFP-A,B,C LUB OIL PUMPS
TURBINE SIDE MS STOP V/VS F007 AND F008
MOT CLEAN OIL PUMP AND DIRTY OIL PUMP
CRH DRAIN V/VS F764,F766,F767,F765
LPH-1 INLET,OUTLET AND BYPASS V/VS F020,F021 AND F022
TURBINE AOP
CEP A AND B DISCHARGE V/VS
LP BYPASS DRAIN V/VS F762 AND F763
LP BYPASS OSU 1 AND 2
GSEB A AND B
AUX PRDS OSU
200 A250 A
19
415V TGMCC - B
FROM UNIT LT
SWGR-B
TIE FROM / TO
TGMCC-C
VEF-A
ESVS AND IVS SEAT DRAINS
HP TURBINE DRAIN V/VS
SEAL STEAM FEED V/V(F001),SHUT OFF V/V(F003) AND
UNLOADING V/V(F004) AND BYPASS V/V(F002)
TURBINE PREWARMING V/V F005
CPU INLET AND OUTLET V/V
ARP RELAY CABINET
MOT CENTRIFUGE SUPPLY
UNIT BATTERY CHARGER FLOAT(SB)
800 A 400 A
20
415V TGMCC - C
TIE FROM/TO
TGMCC-B
FROM UNIT LT
SWGR-A
-SEAL OIL PANEL SUPPLY
-BUS DUCT PRESSURISATION AND HOT AIR BLOWING
SUPPLY
-EXCITATION PANLEL SUPPLY
-GT COOLER S/B SUPPLY
-UT-B COOLER MAIN SUPPLY
-UT-A COOLER S/B SUPPLY
-TURBINE SIDE DEWATERING PUMPS PANEL
-EXCITATION THYRISTOR FANS AUX SUPPLY
-EXCITATION FIELD FLASHING SUPPLY
MULSIFIER SYSTEM(MOT AND ROT)
400 A800 A
21
415V TGMCC - D
TIE FROM / TO
TGMCC-A
FROM UNIT LT
SWGR-B
•AUX STEAM TO SEAL STEAM CONTROL BYPASS V/V
•UT-A COOLER MAIN SUPPLY
•UT-B COOLER S/B SUPPLY
•ALL EJECTORS AIR AND STEAM SIDE V/VS
•ALL HEATERS EXTRACTION STEAM BLOCK V/VS
•HRH LINE DRAINS,MS LINE DRAINS,CRH LINE DRAINS
•GT COOLER MAIN SUPPLY
•HPH 5 AND 6 INLET,OUTLET AND BYPASS V/VS
•TURBINE LUB OIL TEMP CONTROL V/V F023
•HP FLASH TANK ATTEMPERATION V/V F033
•LP BYPASS LINE DRAIN V/V F726,F727
•CPU FLOW CONTROL BYPASS V/V
•EXHAUST HOOD SPRAY BYPASS V/V F020
•CW PASS A AND B INLET AND OUTLET V/VS
•VACUUM BREAKER V/V
•D/A VENT V/V
•ALL HEATERS NORMAL AND ALTERNATE DRIP
CONTROL BYPASS V/VS
•CONDENSER MIN RECIRCULATION V/V BYPASS V/V
•HOTWELL LEVEL CONTROL V/V BYPASS V/V
•HOTWELL MAKE UP BYPASS V/V F043
200 A
250 A
22
VENTILLATION MCC
AWU C&D BLOWERS AND PUMPS SUPPLY
TG ROOF EXTRACTORS(5 NOS)
C&I DOCK HOUSE
DAS ROOM A/C PACKAGE UNIT
EXHAUST AIR FANS
-VENTILLATION MCC ROOM(2 NOS)
-D/A ROOF EXTRACTORS(2 NOS)
-UNIT BATTERY ROOM(2 NOS)
-BUNKER LEVEL DUST EXTACTION FANS(5 NOS)
AIR WASHER MCC
AWU A AND B BLOWERS AND PUMPS
ARCW PUMPS A AND B
FROM STN
LT SWGR
FROM STN
LT SWGR
630 A
400 A
23
415V ESP SWITCHGEAR
BOARD-A
BOARD-B
ESP PASS I AND II FIELDS
ESP PASS I AND II AUX SUPPLY
ESP ZERO FIELD AND AUX PANEL
ESP A/C
ESP A/C PACKAGE UNIT
ESP PASS III AND IV FIELDS
ESP PASS III AND IV AUX SUPPLY
APH FIRE DETECTOR
WELDING SUPPLY(SPARE)
ESP TRF-A
6.6/.433 KV
1.25 MVA
ESP TRF-B
6.6/.433 KV
1.25 MVA
FROM UNIT
SWGR-A
FROM UNIT
SWGR-B
BC
24
DC SYSTEM OF RAMAGUNDAM
 TO OPERATE FROM BATTERIES
FOR ATLEAST 60 MINUTES
FOLLOWING COMPLETE FAILURE
OF ALL AC SUPPLIES
 TO OPERATE FROM BATTERIES
FOR ATLEAST 10 HRS FOLLOWING
FAILURE OF ALL BATTERY
CHARGERS
DC LOADS
 INSTRUMENTS
 INDICATIONS, ANNUNCIATIONS &
ALARMS
 SWITCHGEAR CLOSING & TRIPPING
 CONTROLS,PROCTECTION &
INTERLOCKS
 TELECOMMUNICATIONS
 PLCC & PA SYSTEM
 DC LIGHTING
 DC DRIVES
DC SYSTEM
 BATTERY CHARGERS [TWO/THREE]
 BATTERY BANKS [ONE/TWO]
 DC DISTRIBUTION BOARDS [ONE/TWO]
 DC FUSE BOARDS
 UN EARTHED SYSTEM
 CHARGER TROUBLE, DC EARTH FAULT
AND DC VOLTAGE ABNORMAL ALARMS
IN UCB
220 V UNIT DCDB
BOOST CHARGER BATTERY BANK FLOAT MAIN FLOAT S/B
ELECTROMAGNETIC
BOARD-1
TIEFEEDER
LOGICDB
DCLTG
A ELECTROMAGNETIC
BOARD-2
220 V DCDB
500 A
X
SW4 SW3
SW4 SW4
•CONTACTOR X OPENS ON
BOOST CHARGER ON
TIE FEEDERS TO UNITS:
UNIT- 1: FROM UNIT –2 DCDB
FROM SWYD DCDB SEC-1
UNIT-2 : FROM UNIT – 1 DCDB
FROM UNIT- 3 DCDB
UNIT- 3 : FROM UNIT- 2 DCDB
DCEOPSTARTER
PANLE
DCSEALOILPANEL
26
UNIT-1
A: DC SOURCES FOR
6.6 KV UNIT SWGR A AND B MAIN
415 UNIT SWGR - A AND B
EMCC I/C-1 & EMCC I/C –2
6.6 KV STN SWGR 1S1 AND 1S2 MAIN
6.6 KV STN SWGR 2S1 AND 2S2 MAIN
415 STN SWGR - 1A AND 1B MAIN
415 STN SWGR - 2A AND 2B MAIN
UNIT-1 MLDB
AIR COMPRESSOR ANNUNCIATION PANEL
6.6 KV COMRESSOR SWGR 1
DG SWGR PANEL-2
ESP SWGR
INTERCOM EMERGENCY SUPPLY
UNIT-2
A: DC SOURCES FOR
6.6 KV UNIT SWGR A AND B MAIN
415 UNIT SWGR - A AND B
6.6 KV UNIT SWGR – 3A & 3B STANDBY
6.6 KV UNIT SWGR – 1A & 1B STANDBY
415 UNIT SWGR - 3A AND 3 B STANDBY
EMCC I/C-1
EMCC I/C –2
ESP SWGR
DC FUSE BOARD – 1
-UCR AC
-STN LT 1 & 2
-STN SWGR IS1 & 2S1
-CSSAEP
DC FUSE BOARD – 2
-STN LT 3 & 4
-STN SWGR IS2 & 2S2
-UNIT – 1 LT SWGR
- DG SWGR
INTERCOM EMERGENCY SUPPLY
UNIT-3
A: DC SOURCES FOR
6.6 KV UNIT SWGR A AND B MAIN
415 UNIT SWGR - A AND B
6.6 KV UNIT SWGR – 2A & 2B STANDBY
415 V UNIT SWGR – 2A & 2B STANDBY
EMCC I/C-1
EMCC I/C –2
ESP SWGR
INTERCOM EMERGENCY SUPPLY
220 V UNIT DCDB SUPPLY DISTRIBUTION
27
ASH SLURRY LT SWITCHGEAR
AS TRF-1
6.6 / .433 KV
1.6 / 2 MVA
SPARE-3NOS
H2PLANTMCC
ASSERIES-1
ASSERIES-2
FOUNLOADING
MCC
ASSERIES-3
CANTEEN
SUPPLY
ASMCC
SERVIVE
WATERMCC
SEC-A B/C--2B/C-1
AS TRF-3
6.6 / .433 KV
1.6 / 2 MVA
SPARE
CHIMNEYMCC-1
PRESSUREPARTS
MAINTWORKSHOP
CHIMNEYMCC-2
SEALWATER
PUMP-3
FOPRESSURISING
MCC
SPARE
ASSERIES4
ASSEIRS-5
H2PLANTMCC
AS TRF-2
6.6 / .433 KV
1.6 / 2 MVA
SEC-C
SEC-B
FROM 1S1 FROM 2S1
FROM 2S2
CANTEENSUPPLY
30
6.6 KV CW SWITCHGEAR
1CW2
2CW2
2CW11CW1
B/C
B/C
CTLTXFMER-1
AW&FFXFMER-1
CWP/P-1
CWP/P-2
SPARE
RAWWATER
SWGRSEC-A
CWP/P-5
CWP/P-6
LWTPXFMR-1
DMERVICE
XFMER-1(STAGE-II)
CTLTXFMER-3
WAGONTIPPLER
XFMER-1
WAGONTIPPLER
XFMER-2
CWP/P-3
CWP/P-4
DMERVICEXFMER-2
STAGE-II
CTLTXFMER-4
CTLTXFMER-2
CWP/P-7
AW&FFXFMER-2
TIETORAWWATER
SWGRSEC-B
CTLTGXFMER
RAWWATER
P/P-6
RAWWATER
P/P-3
CW XFMER-1
33 /6.6/6.6 KV
20/25 MVA
CW XFMER-2
33 /6.6/6.6 KV
20/25 MVA
FROM 33 KV SWGR
SEC-A
FROM 33 KV SWGR
SEC-B
TIEFROM
2S1SWGR
BUSVT
BUSVT
BUSVT
BUSVT
LWTPXFMR-2
37
NOTE: ALL SECTIONS HAVE LINE PT CUBICLES
6.6 KV CW1 / CW2 / WTP SWITCHGEAR
BUSCOUPLER
 
 PROTECTIONS
 
 Remote trip
 Local trip 
 Mech.trip 
 Elect.trips from 
• E/F Relay
•   IDMT  O/C: R,Y,B phases.  
 INTERLOCKS
• Trips when both Incomers are ON 
in service position with trip 
selection in buscoupler.
• Closes  on auto if the following 
conditions are satisfied.
 Any incomer trip and No 
fault on this section
 Bus under voltage operated
 Buscoupler selection in 
auto
PERMISSIVES
• No elect trip from
• E/F Relay
• IDMT O/C: R,Y,B phases.
•No elect trip from any of the Incomers.
• No Continuous close command
67
CLARIFIEDWATERPUMP-7 FROM 33 KV SWGR SEC-A
6.6 KV WTP SWITCHGEAR
SEC-A SEC-B
FROM 33 KV SWGR SEC-B
CLARIFIEDWATERPUMP-1
CLARIFIEDWATERPUMP-3
CLARIFIEDWATERPUMP-5
WTPLTXFMR-1
SATCOMXFMR-1
CLARIFIEDWATERPUMP-6
CLARIFIEDWATERPUMP-4
CLARIFIEDWATERPUMP-2
WTPLTXFMR-2
SATCOMXFMR-2
B/C
WTP XFMR-1
33 / 6.9 KV
5 MVA
WTP XFMR-2
33 / 6.9 KV
5 MVA
BUSVT
BUSVT
SPARE
44
NOTE: BOTH SECTIONS HAVE LINE PT CUBICLES
Indicates breaker in open condition
Indicates breaker in close condition
closed
B/C 2
open
Col I Col II Col IIIRDM I RDM II
From SEC F Sec B Sec A
#1 #2 #3
NEW COLONY SWITCHGEAR AS ON 25/05/05
B/C 1
All
Transformers
are 4MVA
THANK
YOU

More Related Content

What's hot

Electrical distribution system
Electrical distribution system Electrical distribution system
Electrical distribution system
Ankush Bharti
 
Design considerations of electrical installations
Design considerations of electrical installationsDesign considerations of electrical installations
Design considerations of electrical installations
vishalgohel12195
 
Electrical wiring system - and estimation
Electrical wiring system -  and estimation Electrical wiring system -  and estimation
Electrical wiring system - and estimation
Mahfuz Sikder
 
Presentation on substations
Presentation on substationsPresentation on substations
Presentation on substations
vishalgohel12195
 
Basics of electrical control panel
Basics of electrical control panelBasics of electrical control panel
Basics of electrical control panel
CHACKOCHEN MATHEW
 
Electrical System Design
Electrical System Design Electrical System Design
VARIABLE REFRIGERANT FLOW(VRF) ppt
VARIABLE REFRIGERANT FLOW(VRF)  pptVARIABLE REFRIGERANT FLOW(VRF)  ppt
VARIABLE REFRIGERANT FLOW(VRF) ppt
Ezhil Raj s
 
Electrical maintenance
Electrical maintenanceElectrical maintenance
Electrical maintenance
Carl Tim Lapinig
 
Electrical Installation PPT (Basic Electrical Engineering)
Electrical Installation PPT (Basic Electrical Engineering)Electrical Installation PPT (Basic Electrical Engineering)
Electrical Installation PPT (Basic Electrical Engineering)
Dhrumil Maniar
 
Circuit protection devices perfect ppt
Circuit protection devices perfect ppt Circuit protection devices perfect ppt
Circuit protection devices perfect ppt
vikram rajpurohit
 
Electrical Power substation
Electrical Power substationElectrical Power substation
Electrical Power substation
Emran Ali
 
Electric substation
Electric substation Electric substation
Electric substation
ANNU KUMAR
 
Energy efficient hvac
Energy efficient hvac Energy efficient hvac
Overhead line work ppt
Overhead line work pptOverhead line work ppt
Overhead line work ppt
Demsew Mitiku
 
Electrical protective devices ec
Electrical protective devices ecElectrical protective devices ec
Electrical protective devices ec
trg12345
 
Relay and switchgear protection
Relay and switchgear protectionRelay and switchgear protection
Relay and switchgear protectionBinit Das
 
Chapter 4 electrical-auxiliary_systems
Chapter 4 electrical-auxiliary_systemsChapter 4 electrical-auxiliary_systems
Chapter 4 electrical-auxiliary_systems
Jothimanikkam Somasundaram
 
Different types of Transformers used in Generating Station
Different types of Transformers used in Generating StationDifferent types of Transformers used in Generating Station
Different types of Transformers used in Generating Station
Vasanthan Ravichandran
 
Unit 01 electrical wiring diagrams
Unit 01 electrical wiring diagramsUnit 01 electrical wiring diagrams
Unit 01 electrical wiring diagrams
Parneet Chowdhary
 

What's hot (20)

Electrical distribution system
Electrical distribution system Electrical distribution system
Electrical distribution system
 
Air conditioning system
Air conditioning systemAir conditioning system
Air conditioning system
 
Design considerations of electrical installations
Design considerations of electrical installationsDesign considerations of electrical installations
Design considerations of electrical installations
 
Electrical wiring system - and estimation
Electrical wiring system -  and estimation Electrical wiring system -  and estimation
Electrical wiring system - and estimation
 
Presentation on substations
Presentation on substationsPresentation on substations
Presentation on substations
 
Basics of electrical control panel
Basics of electrical control panelBasics of electrical control panel
Basics of electrical control panel
 
Electrical System Design
Electrical System Design Electrical System Design
Electrical System Design
 
VARIABLE REFRIGERANT FLOW(VRF) ppt
VARIABLE REFRIGERANT FLOW(VRF)  pptVARIABLE REFRIGERANT FLOW(VRF)  ppt
VARIABLE REFRIGERANT FLOW(VRF) ppt
 
Electrical maintenance
Electrical maintenanceElectrical maintenance
Electrical maintenance
 
Electrical Installation PPT (Basic Electrical Engineering)
Electrical Installation PPT (Basic Electrical Engineering)Electrical Installation PPT (Basic Electrical Engineering)
Electrical Installation PPT (Basic Electrical Engineering)
 
Circuit protection devices perfect ppt
Circuit protection devices perfect ppt Circuit protection devices perfect ppt
Circuit protection devices perfect ppt
 
Electrical Power substation
Electrical Power substationElectrical Power substation
Electrical Power substation
 
Electric substation
Electric substation Electric substation
Electric substation
 
Energy efficient hvac
Energy efficient hvac Energy efficient hvac
Energy efficient hvac
 
Overhead line work ppt
Overhead line work pptOverhead line work ppt
Overhead line work ppt
 
Electrical protective devices ec
Electrical protective devices ecElectrical protective devices ec
Electrical protective devices ec
 
Relay and switchgear protection
Relay and switchgear protectionRelay and switchgear protection
Relay and switchgear protection
 
Chapter 4 electrical-auxiliary_systems
Chapter 4 electrical-auxiliary_systemsChapter 4 electrical-auxiliary_systems
Chapter 4 electrical-auxiliary_systems
 
Different types of Transformers used in Generating Station
Different types of Transformers used in Generating StationDifferent types of Transformers used in Generating Station
Different types of Transformers used in Generating Station
 
Unit 01 electrical wiring diagrams
Unit 01 electrical wiring diagramsUnit 01 electrical wiring diagrams
Unit 01 electrical wiring diagrams
 

Viewers also liked

EE6502 Microprocessor & Microcontroller Regulation 2013
EE6502 Microprocessor & Microcontroller Regulation 2013EE6502 Microprocessor & Microcontroller Regulation 2013
EE6502 Microprocessor & Microcontroller Regulation 2013
Velalar College of Engineering and Technology
 
2 input output dan internal memori
2 input output dan internal memori2 input output dan internal memori
2 input output dan internal memori
Simon Patabang
 
EE6711 Power System Simulation Lab manual
EE6711 Power System Simulation Lab manualEE6711 Power System Simulation Lab manual
EE6711 Power System Simulation Lab manual
Velalar College of Engineering and Technology
 
8085 alp programs
8085 alp programs8085 alp programs
Principles of management
Principles of management Principles of management
Control systems (II-EEE)
Control systems (II-EEE)Control systems (II-EEE)
Control systems (II-EEE)
betasam
 
Load shedding problem in Bangladesh
Load shedding problem in BangladeshLoad shedding problem in Bangladesh
Load shedding problem in Bangladesh
usernameleon
 
DISTRIBUTION SYSTEM OPERATION AND CONTROL
DISTRIBUTION SYSTEM OPERATION AND CONTROLDISTRIBUTION SYSTEM OPERATION AND CONTROL
DISTRIBUTION SYSTEM OPERATION AND CONTROL
yohannes feleke
 
12 depresiasi
12 depresiasi12 depresiasi
12 depresiasi
Simon Patabang
 
Dasar kelistrikan
Dasar kelistrikanDasar kelistrikan
Dasar kelistrikan
Zainal Abidin
 
EE2356 Microprocessor and Microcontroller Lab Manuel
EE2356 Microprocessor and Microcontroller Lab ManuelEE2356 Microprocessor and Microcontroller Lab Manuel
EE2356 Microprocessor and Microcontroller Lab Manuel
Velalar College of Engineering and Technology
 
8085 instruction set
8085 instruction set8085 instruction set
Microprocessor interview questions
Microprocessor interview questionsMicroprocessor interview questions
Microprocessor interview questions
Velalar College of Engineering and Technology
 
RES (IV-EEE)
RES (IV-EEE)RES (IV-EEE)
RES (IV-EEE)
betasam
 
8086 alp
8086 alp8086 alp
Instruction set of 8086 Microprocessor
Instruction set of 8086 Microprocessor Instruction set of 8086 Microprocessor
Instruction set of 8086 Microprocessor
Velalar College of Engineering and Technology
 
Design of Electrical Machines Problems & Solutions
Design of Electrical Machines Problems & SolutionsDesign of Electrical Machines Problems & Solutions
Design of Electrical Machines Problems & Solutions
Velalar College of Engineering and Technology
 
6 Divergensi dan CURL
6 Divergensi dan CURL6 Divergensi dan CURL
6 Divergensi dan CURL
Simon Patabang
 

Viewers also liked (20)

Professional Ethics
Professional EthicsProfessional Ethics
Professional Ethics
 
EE6502 Microprocessor & Microcontroller Regulation 2013
EE6502 Microprocessor & Microcontroller Regulation 2013EE6502 Microprocessor & Microcontroller Regulation 2013
EE6502 Microprocessor & Microcontroller Regulation 2013
 
2 input output dan internal memori
2 input output dan internal memori2 input output dan internal memori
2 input output dan internal memori
 
EE6711 Power System Simulation Lab manual
EE6711 Power System Simulation Lab manualEE6711 Power System Simulation Lab manual
EE6711 Power System Simulation Lab manual
 
8085 alp programs
8085 alp programs8085 alp programs
8085 alp programs
 
Principles of management
Principles of management Principles of management
Principles of management
 
Control systems (II-EEE)
Control systems (II-EEE)Control systems (II-EEE)
Control systems (II-EEE)
 
Load shedding problem in Bangladesh
Load shedding problem in BangladeshLoad shedding problem in Bangladesh
Load shedding problem in Bangladesh
 
DISTRIBUTION SYSTEM OPERATION AND CONTROL
DISTRIBUTION SYSTEM OPERATION AND CONTROLDISTRIBUTION SYSTEM OPERATION AND CONTROL
DISTRIBUTION SYSTEM OPERATION AND CONTROL
 
12 depresiasi
12 depresiasi12 depresiasi
12 depresiasi
 
Dasar kelistrikan
Dasar kelistrikanDasar kelistrikan
Dasar kelistrikan
 
EE2356 Microprocessor and Microcontroller Lab Manuel
EE2356 Microprocessor and Microcontroller Lab ManuelEE2356 Microprocessor and Microcontroller Lab Manuel
EE2356 Microprocessor and Microcontroller Lab Manuel
 
8085 instruction set
8085 instruction set8085 instruction set
8085 instruction set
 
Microprocessor interview questions
Microprocessor interview questionsMicroprocessor interview questions
Microprocessor interview questions
 
Fundamentals of substaion
Fundamentals of substaionFundamentals of substaion
Fundamentals of substaion
 
RES (IV-EEE)
RES (IV-EEE)RES (IV-EEE)
RES (IV-EEE)
 
8086 alp
8086 alp8086 alp
8086 alp
 
Instruction set of 8086 Microprocessor
Instruction set of 8086 Microprocessor Instruction set of 8086 Microprocessor
Instruction set of 8086 Microprocessor
 
Design of Electrical Machines Problems & Solutions
Design of Electrical Machines Problems & SolutionsDesign of Electrical Machines Problems & Solutions
Design of Electrical Machines Problems & Solutions
 
6 Divergensi dan CURL
6 Divergensi dan CURL6 Divergensi dan CURL
6 Divergensi dan CURL
 

Similar to ELECTRICAL SYSTEMS

132 kV uppcl
132 kV uppcl132 kV uppcl
132 kV uppcl
Abrar Ahamed
 
ppt on summer training on uppcl
ppt on summer training on uppclppt on summer training on uppcl
ppt on summer training on uppcl
Sunny Daksh
 
Ucn5804 datasheet
Ucn5804 datasheetUcn5804 datasheet
Ucn5804 datasheet
franklinpaiva1000
 
400 Kv Soja
400 Kv Soja400 Kv Soja
400 Kv Soja
chandni shah
 
ppt on industrial training of final year studen from ptcul 132kv substation ...
ppt on industrial training of final year studen  from ptcul 132kv substation ...ppt on industrial training of final year studen  from ptcul 132kv substation ...
ppt on industrial training of final year studen from ptcul 132kv substation ...
surendra rawat
 
industrial training on 132 kv substation
industrial training on 132 kv substationindustrial training on 132 kv substation
industrial training on 132 kv substation
pk130992
 
Advanced motion controls be25a20fac
Advanced motion controls be25a20facAdvanced motion controls be25a20fac
Advanced motion controls be25a20fac
Electromate
 
Transformers in NTPC
Transformers in NTPCTransformers in NTPC
Transformers in NTPC
Sagnik Saha
 
Original Power Supply IC LNK616PG LNK616P LNK616 DIP-7 New
Original Power Supply IC LNK616PG LNK616P LNK616 DIP-7 NewOriginal Power Supply IC LNK616PG LNK616P LNK616 DIP-7 New
Original Power Supply IC LNK616PG LNK616P LNK616 DIP-7 New
AUTHELECTRONIC
 
220 kv gss
220 kv gss220 kv gss
220 kv gss
Dashrath047
 
Gss ppt by kanhaiya
Gss ppt  by kanhaiyaGss ppt  by kanhaiya
Gss ppt by kanhaiya
imkanhaiyalal
 
Original Power Supply IC TNY290PG TNY290P TNY290 DIP-7 New Power Integration
Original Power Supply IC TNY290PG TNY290P TNY290 DIP-7 New Power IntegrationOriginal Power Supply IC TNY290PG TNY290P TNY290 DIP-7 New Power Integration
Original Power Supply IC TNY290PG TNY290P TNY290 DIP-7 New Power Integration
AUTHELECTRONIC
 
gas turbine generator set operation and maintenance
gas turbine generator set operation and maintenancegas turbine generator set operation and maintenance
gas turbine generator set operation and maintenance
AmrSherif54
 
400 kv nelmangala
400 kv nelmangala400 kv nelmangala
400 kv nelmangala
Mayur Dhanaji Rane
 
Thesis grid station 1.pdf
Thesis grid station 1.pdfThesis grid station 1.pdf
Thesis grid station 1.pdf
Rashidali731283
 
Advanced motion controls b25a20fac
Advanced motion controls b25a20facAdvanced motion controls b25a20fac
Advanced motion controls b25a20fac
Electromate
 
400 KV GSS HEERAPURA, JAIPUR
400 KV GSS HEERAPURA, JAIPUR400 KV GSS HEERAPURA, JAIPUR
400 KV GSS HEERAPURA, JAIPUR
sahid raja khan
 
Digital Electronics and Integrated Circuits - Unit 5.pptx
Digital Electronics and Integrated Circuits - Unit 5.pptxDigital Electronics and Integrated Circuits - Unit 5.pptx
Digital Electronics and Integrated Circuits - Unit 5.pptx
Dhivya Ramachandran
 
220kv substation
220kv substation220kv substation
220kv substation
Anbarasu Balakrishnan
 
Presentation (2).pptx
Presentation (2).pptxPresentation (2).pptx
Presentation (2).pptx
TejusManikandan
 

Similar to ELECTRICAL SYSTEMS (20)

132 kV uppcl
132 kV uppcl132 kV uppcl
132 kV uppcl
 
ppt on summer training on uppcl
ppt on summer training on uppclppt on summer training on uppcl
ppt on summer training on uppcl
 
Ucn5804 datasheet
Ucn5804 datasheetUcn5804 datasheet
Ucn5804 datasheet
 
400 Kv Soja
400 Kv Soja400 Kv Soja
400 Kv Soja
 
ppt on industrial training of final year studen from ptcul 132kv substation ...
ppt on industrial training of final year studen  from ptcul 132kv substation ...ppt on industrial training of final year studen  from ptcul 132kv substation ...
ppt on industrial training of final year studen from ptcul 132kv substation ...
 
industrial training on 132 kv substation
industrial training on 132 kv substationindustrial training on 132 kv substation
industrial training on 132 kv substation
 
Advanced motion controls be25a20fac
Advanced motion controls be25a20facAdvanced motion controls be25a20fac
Advanced motion controls be25a20fac
 
Transformers in NTPC
Transformers in NTPCTransformers in NTPC
Transformers in NTPC
 
Original Power Supply IC LNK616PG LNK616P LNK616 DIP-7 New
Original Power Supply IC LNK616PG LNK616P LNK616 DIP-7 NewOriginal Power Supply IC LNK616PG LNK616P LNK616 DIP-7 New
Original Power Supply IC LNK616PG LNK616P LNK616 DIP-7 New
 
220 kv gss
220 kv gss220 kv gss
220 kv gss
 
Gss ppt by kanhaiya
Gss ppt  by kanhaiyaGss ppt  by kanhaiya
Gss ppt by kanhaiya
 
Original Power Supply IC TNY290PG TNY290P TNY290 DIP-7 New Power Integration
Original Power Supply IC TNY290PG TNY290P TNY290 DIP-7 New Power IntegrationOriginal Power Supply IC TNY290PG TNY290P TNY290 DIP-7 New Power Integration
Original Power Supply IC TNY290PG TNY290P TNY290 DIP-7 New Power Integration
 
gas turbine generator set operation and maintenance
gas turbine generator set operation and maintenancegas turbine generator set operation and maintenance
gas turbine generator set operation and maintenance
 
400 kv nelmangala
400 kv nelmangala400 kv nelmangala
400 kv nelmangala
 
Thesis grid station 1.pdf
Thesis grid station 1.pdfThesis grid station 1.pdf
Thesis grid station 1.pdf
 
Advanced motion controls b25a20fac
Advanced motion controls b25a20facAdvanced motion controls b25a20fac
Advanced motion controls b25a20fac
 
400 KV GSS HEERAPURA, JAIPUR
400 KV GSS HEERAPURA, JAIPUR400 KV GSS HEERAPURA, JAIPUR
400 KV GSS HEERAPURA, JAIPUR
 
Digital Electronics and Integrated Circuits - Unit 5.pptx
Digital Electronics and Integrated Circuits - Unit 5.pptxDigital Electronics and Integrated Circuits - Unit 5.pptx
Digital Electronics and Integrated Circuits - Unit 5.pptx
 
220kv substation
220kv substation220kv substation
220kv substation
 
Presentation (2).pptx
Presentation (2).pptxPresentation (2).pptx
Presentation (2).pptx
 

ELECTRICAL SYSTEMS

  • 1.
  • 2.
  • 3.
  • 4. AUX. SUPPLY The service voltage which we are adopted in RSTPS are 11KV, 6.6KV , 415V 3PH AC supply and 240V 1PH AC supply. 11KV for Stage 2/3 MDBFPs. 6.6KV for station/unit HT auxiliaries like BFP s (stage-I), Mills, ID/FD/ PA fans, CEPS, CW, RW Pumps & IAC/PAC etc. 415V for station aux like BAHP/FALP, Service water pumps, unit aux like Seal Air fan, Lube oil pumps, AC seal oil pumps and Centrifuge etc. 240V supply for lighting and welding. These supplies are fed through the different switchgears
  • 5. What are switchgears? The equipment which normally fall in this category are: Circuit Breakers Isolators Load break switches Earth switches Switch fuse units etc. The switchgears are fed through different transformers
  • 6. Transformer Generator Transformer Tie Transformer The generator is connected to this transformer by means of bus ducts. This transformer is used to step up the generating voltage of 18 / 21 KV to 400 KV . This transformer is provided OFAF cooling and Off load tap changer. There are total 4 No. of Tie Transformers are provided for feeding supply for internal requirements. It steps down 400 KV to 33KV This transformer is provided OFAF cooling and Off load tap changer.
  • 7. Station Transformer The station transformer is required to feed power to the auxiliaries during start-ups, and C- auxiliaries when unit is in service., This transformer is normally rated for initial auxiliary load requirements of unit. It is provided with On load tap changer to cater to the fluctuating voltage of the grid. Unit Auxiliary Transformer The UAT draws its power from the main bus duct-connecting Generator to the GT. The total KVA capacity of unit Auxiliary transformer require can be determined by assuming 0.85 power factor and 0,9 efficiency for total load with a safe margin of 20%. It is provided with On load tap changer to cater to the fluctuating voltage of the grid. Transformers
  • 8. BREAKER TRANSFORMER ISOLATOR SWITCH CUM FUSE UNIT FUSE CONTACT 400 KV LINE 33 KV LINE 11 KV LINE 6.6 KV LINE 415 V LINE 220 DC LINE 5 SYMBOLS
  • 9. 33KV SWITCHGEAR UNIT # 1 GEN 400 KV BUS # 2 400 KV BUS # 1 ST # 6 ST # 3 ST # 4 ST # 5 TIE # 1 75 MVA 400/33 KV SEC # A SEC # B SEC # C SEC # D SEC # E ~ ~ GT # 5 21/400 KVTIE # 2 75 MVA 400/ 33 KV TIE # 3 100MVA 400/ 33 KV 6 TIE # 4 100 MVA 400/ 33 KV ~ ~ GT # 1 240 MVA 18/400 KV UNIT # 5 GEN ST # 1 ST # 2 ST #7 SEC #F
  • 10.
  • 11. TIE # 2 400/33 Kv 75 MVA TIE # 1 400/33 Kv 75 MVA spare WTP-2 CW-1 ST-1 CHPAUG-1 ST-6 COL-3 SWYD-1 TIETOSEC-F COL-2 WTP-1 CW-2 ST-2 CHPAUG-2 CONST-2 TIETOSEC–E SWYD-2 SEC-A SEC-BB/C 33 KV STAGE-I SWITCHGEAR 7
  • 13. SHSLURRYLTG TIETO1CW1 UNITSWGR-1B UNITSWGR-2B AIRCOMP-A FOLTG CHP-B ASS-1 DAETP-1 UNITSWGR–3A SPARE UNITSWGR–1A DAETP-2 UNITSWGR–2A ST –1 33 / 6.6 KV 19 / 25 / 31.5 MVA ST –2 33 / 6.6 KV 19 / 25 / 31.5 MVA STLT-4 6.6 / 0.433 1.65 MVA STLT-3 6.6 / 0.433 1.65 MVA STLT-1 6.6 / 0.433 1.65 MVA STLT-2 6.6 / 0.433 1.65 MVA AIRCOMP SWGR-B CHP-A ASXMER-2 UNITSWGR-3B 6.6 KV STATION SWITCHGEAR B/C 1S1/2S1 B/C 1S2 / 2S2 1S1 1S2 2S1 2S2 ASHXMER-3 STN LT SWGR - 1 STN LT SWGR - 2 SEC-A SEC-B SEC-A SEC-B 8 NOTE: ALL SECTIONS HAVE BUS VTS LINE PT PANELS ARE AVAILABLE IN 1S1 & 2S2
  • 14. 6.6 KV STATION SWITCHGEAR INCOMER FROM STATION TRANSFORMER PROTECTIONS  Remote trip  Local trip  Mech.trip  Elect.trips from • E/F Relay • IDMT O/C: R,Y,B phases. INTERLOCKS  Station transformer HT breaker trip.  Trips when Incomer from station transformer and buscoupler is ON in service position with trip selection in this incomer. PERMISSIVES   • 33 KV side charged. • No elect trip from  •  E/F Relay •  IDMT  O/C: R,Y,B phases. •No elect trip from Buscoupler. • No Continuous close command   64
  • 15. 6.6 KV STATION SWITCHGEAR BUSCOUPLER PROTECTIONS  Remote trip  Local trip  Mech.trip  Elect.trips from • E/F Relay • IDMT O/C: R,Y,B phases. INTERLOCKS • Trips when both Incomers from station transformer are ON in service position with trip selection in buscoupler.. PERMISSIVES • No elect trip from  • E/F Relay •  IDMT  O/C: R,Y,B phases. •No elect trip from Incomer from station  transformer • No Continuous close command     65
  • 16.
  • 18. 6.6 KV UNIT SWITCHGEAR. TIE INCOMER FROM STATION SWGR.   PROTECTIONS  Remote trip  Local trip  Mech.trip  Elect.trips from • E/F Relay CTU 12(64) • IDMT O/C Relay – R,Y,B phases INTERLOCKS  Breaker trips when UAT incomer is ON in service position.  Breaker closes on auto from command. from GRP. PERMISSIVES   • No elect trip from  •  E/F Relay CTU 12(64) •IDMT  O/C Relay – R,Y,B  phases • No elect trip from UAT incomer. • upstream Isolator / breaker in service  / closed • No Continuous close command   57
  • 19. 6.6 KV UNIT SWITCHGEAR. INCOMER FROM UNIT TRANSFORMER PROTECTIONS  Local trip  Mech.trip  Remote trip  Elect.trips from  E/F Relay (51) -CDG • IDMT O/C: R,Y,B, phases.  Trip from GRP INTERLOCKS  Breaker trips when TIE incomer is ON in service position PERMISSIVES   • No elect trip from  • E/F Relay (51) -CDG • IDMT O/C:  R,Y,B, phases. •Unit synchronised.  •No elect trip from TIE incomer. • No Continuous close command     58
  • 21. 6.6 KV STAGE-2, SIEMENS MAKE, VACUUM CB
  • 24. HT MOTOR FEEDER PERMISSIVES  No elect trip from  (i) E/F Relay  (ii) Inst O/C Relay: R, Y,B Phases  (iii) Lockout rotor  (iv) Differential protection  IDMT O/C: R, B phases.  Overload  EPB released  Process permissive  No Continuous close command PROTECTIONS  Local trip  Remote trip  Mech.trip  EPB Pressed.  Elect.trips from • E/F Relay • Inst O/C Relay R, Y,B Phases  Lockout rotor  Differential protection  Overload.  Process trips. INTERLOCKS:  Bus under voltage trip 63
  • 25. TRANSFORMER HT SIDE FEEDER PERMISSIVES  No Elect trip from  E/F Relay  IDMT O/C Relay (51) R, Y, B Phases (or) differential protection..  Inst O/C Relay (50)  R-Phase  Y-Phase  B-Phase  Wdg.temp high  Transformer oil temp. high  Bucholtz trip  No Continuous close command PROTECTIONS  Local trip  Mech.trip  Remote trip  Elect.trips from  E/F Relay  IDMT O/C Relay (51) R, Y, B Phases (or) differential protection..  Inst O/C Relay (50)  R-Phase  Y-Phase  B-Phase  Transformer oil temp. high  Wdg. temp. high  Buchholtz trip THIS IS APPLICABLE TO ESP, UAT , unit ltg, FO ltg, Ash slurry ltg, StationLT , CT LT, WTP LT, switchyard LT, ASH SLURRY TRANSFORMERS HT SIDE BREAKER 62
  • 26. UAT - A 6.6 / .433 KV 1.6 MVA TGMCC–A TGMCC–C BMCC–A BVDDC–A TGMCC–B TGMCC–D BMCC–B BVDDC–B SEC-A SEC-BB/C 415V UNIT LT SWITCHGEAR    UAT - B 6.6 / .433 KV 1.6 MVA SPARE SPARE EMCC From DG Set EQUIPMENTS CHARGERS EMERGENCY LTG UPSALT SOURCE PAFANFLOP MCC EQUIPMENTS: TGOP TURNING GEAR MOTOR VEF-B SCANNER AIR FAN-A APH-A AUX DRIVE APH-B AUX DRIVE CHARGERS: FLOAT MAIN BOOST CHARGER UPS CHARGER-A FROM UNIT SWGR - A FROM UNIT SWGR - B 16
  • 27.
  • 28. DG SWITCHGEAR DG SET – 2 625 KVA DG SET – 1 625 KVA 415 V LT BUS TOUNIT–1EMCC TOUNIT–2EMCC TOUNIT–3EMCC TOSWYD 25
  • 29. PERMISSIVES 1 No Elect. trips from Inst.O/C relay R,Y,B-phases E/F relay 1 Upstream breaker closed in service position. 3 No Continuous close command. 4 No Elect. trip from BUS COUPLER 5 Breaker panel door closed UNIT LT SWITCHGEAR INCOMER A &B PROTECTIONS 01 Local trip 02 Remote trip 03 Mech trip 04 Inst O/C trip R,Y,B-phase E/F relay INTERLOCKS 01 Trips on Upstream breaker off. 02 Trips on breaker panel door open. 59
  • 30. PERMISSIVES 1 No Elect. trips from Inst.O/C. R, Y, B -phases Earth Fault 2 No Elect. trips from INCOMER - A INCOMER - B 3 No Continuous close command. 4 Breaker panel door closed UNIT LT SWITCHGEAR BUS COUPLER PROTECTIONS 1 Local trip 2 Remote trip 3 Mech trip 4 Electrical trips Inst.O/C. R, Y, B -phases Earth Fault INTERLOCKS 01 Trips when Both incomers are ON and in service position 02 Trips on breaker panel door open. 61
  • 31. UNIT LT SWITCHGEAR FEEDER (BMCC, BVDDC, TG MCC) PROTECTIONS   1 Mech trip 2 Local trip                                                   2 Overload trip 3 Short circuit trip.   INTERLOCKS  1 Upstream breaker OFF.  2 Trips on breaker panel door  open.                            PERMISSIVES                                                             1     No Elect. trips from Inst.O/C  relay   R,Y,B-phases  2 No Continuous close command. 3 Breaker panel door closed 60
  • 32. 415V BOILER MCC SEC - A SEC - B SEC-A MILLS A,C,E LUB OIL PUMPS -GRAVIMETRIC FEEDERS A,C,E -PA FANS A,C,E ISOLATING DAMPERS -ROTARY FEEDERS C,D,E,F,G,H -LP DOSING-A -HP DOSING-A -SEAL AIR FAN-B -SH STAGE-I LHS AND RHS SPRAY BLOCK V/VS -AUX PRDS V/V F036 -HPBYPASS OSU-1 -SOOT BLOWER CABINET SUPPLY -D/A HIGH LEVEL CONTROL BYPASS V/V F046 -CG-A,C APH-A MAIN MOTOR SEC-B MILLS B,D,F LUB OIL PUMPS -GRAVIMETRIC FEEDERS B,D,F -PA FANS B,D,F ISOLATING DAMPERS -ROTARY FEEDERS A,B, I,J,K,L,M,N,O,P -LP DOSING-B -HP DOSING-B -SEAL AIR FAN-A -SH STAGE-II LHS AND RHS SPRAY BLOCK V/VS -AUX PRDS INLET V/V F002 AND TIE V/V F010 -HPBYPASS OSU-2 -BOILER DEWATERING CABINET SUPPLY -CRT MAKE UP CONTROL BYPASS V/V F047 -CG-B,D -APH-B MAIN MOTOR -SCANNER AIR FAN-B -ECO INLET V/V F002 -UPS CHARGER -B FROM UNIT LT SWGR-A FROM UNIT LT SWGR-B 400 A 400 A 400 A 17
  • 33. 415V BOILER VDDC SEC - A SEC - B SEC-A -START UP VENT F027 -AUX STEAM TO SCAPH-B INLET,OUTLET AND REGULATING /VS F020, F022, F023 -ECO RECIR V/V F005 -FRS 30% INLET AND OUTLET V/VS -BUNKER GATES A,C,E -ESP PASS I AND II INLET AND OUTLET DAMPERS ID-B INLET AND OUTLET DAMPERS -AUX STEAM TO D/A PREHEATING V/V F046 -SH HEADER VENTS F690,F680 AND F682 -RHS MAIN STEAM STOP V/V F030 CBD ISO V/V F012 -AUX STEAM TO SCAPH-A INLET,OUTLET AND REGULATING /VS F024, F026, F027 -EBD V/VS F017 AND F018 SEC-B -RH VENT F710 -SH HEADER VENTS F700,F698,F692 -FRS 100% RHS AND MIDDLE INLET AND OUTLET V/VS -BUNKER GATES B,D,F -ESP PASS III AND IV INLET AND OUTLET DAMPERS -ID-A INLET AND OUTLET DAMPERS -LHS MAIN STEAM STOP V/V F040 -RH ATTEMPERATION BLOCK V/V F095 FROM UNIT LT SWGR-A FROM UNIT LT SWGR-B 400 A 250 A 250 A 18
  • 34. 415V TGMCC - A FROM UNIT LT SWGR-A TIE FROM / TO TGMCC-D BFP-A,B,C DISCHARGE V/VS AND INTEGRAL BYPASS V/VS BFP-A,B,C LUB OIL PUMPS TURBINE SIDE MS STOP V/VS F007 AND F008 MOT CLEAN OIL PUMP AND DIRTY OIL PUMP CRH DRAIN V/VS F764,F766,F767,F765 LPH-1 INLET,OUTLET AND BYPASS V/VS F020,F021 AND F022 TURBINE AOP CEP A AND B DISCHARGE V/VS LP BYPASS DRAIN V/VS F762 AND F763 LP BYPASS OSU 1 AND 2 GSEB A AND B AUX PRDS OSU 200 A250 A 19
  • 35. 415V TGMCC - B FROM UNIT LT SWGR-B TIE FROM / TO TGMCC-C VEF-A ESVS AND IVS SEAT DRAINS HP TURBINE DRAIN V/VS SEAL STEAM FEED V/V(F001),SHUT OFF V/V(F003) AND UNLOADING V/V(F004) AND BYPASS V/V(F002) TURBINE PREWARMING V/V F005 CPU INLET AND OUTLET V/V ARP RELAY CABINET MOT CENTRIFUGE SUPPLY UNIT BATTERY CHARGER FLOAT(SB) 800 A 400 A 20
  • 36. 415V TGMCC - C TIE FROM/TO TGMCC-B FROM UNIT LT SWGR-A -SEAL OIL PANEL SUPPLY -BUS DUCT PRESSURISATION AND HOT AIR BLOWING SUPPLY -EXCITATION PANLEL SUPPLY -GT COOLER S/B SUPPLY -UT-B COOLER MAIN SUPPLY -UT-A COOLER S/B SUPPLY -TURBINE SIDE DEWATERING PUMPS PANEL -EXCITATION THYRISTOR FANS AUX SUPPLY -EXCITATION FIELD FLASHING SUPPLY MULSIFIER SYSTEM(MOT AND ROT) 400 A800 A 21
  • 37. 415V TGMCC - D TIE FROM / TO TGMCC-A FROM UNIT LT SWGR-B •AUX STEAM TO SEAL STEAM CONTROL BYPASS V/V •UT-A COOLER MAIN SUPPLY •UT-B COOLER S/B SUPPLY •ALL EJECTORS AIR AND STEAM SIDE V/VS •ALL HEATERS EXTRACTION STEAM BLOCK V/VS •HRH LINE DRAINS,MS LINE DRAINS,CRH LINE DRAINS •GT COOLER MAIN SUPPLY •HPH 5 AND 6 INLET,OUTLET AND BYPASS V/VS •TURBINE LUB OIL TEMP CONTROL V/V F023 •HP FLASH TANK ATTEMPERATION V/V F033 •LP BYPASS LINE DRAIN V/V F726,F727 •CPU FLOW CONTROL BYPASS V/V •EXHAUST HOOD SPRAY BYPASS V/V F020 •CW PASS A AND B INLET AND OUTLET V/VS •VACUUM BREAKER V/V •D/A VENT V/V •ALL HEATERS NORMAL AND ALTERNATE DRIP CONTROL BYPASS V/VS •CONDENSER MIN RECIRCULATION V/V BYPASS V/V •HOTWELL LEVEL CONTROL V/V BYPASS V/V •HOTWELL MAKE UP BYPASS V/V F043 200 A 250 A 22
  • 38. VENTILLATION MCC AWU C&D BLOWERS AND PUMPS SUPPLY TG ROOF EXTRACTORS(5 NOS) C&I DOCK HOUSE DAS ROOM A/C PACKAGE UNIT EXHAUST AIR FANS -VENTILLATION MCC ROOM(2 NOS) -D/A ROOF EXTRACTORS(2 NOS) -UNIT BATTERY ROOM(2 NOS) -BUNKER LEVEL DUST EXTACTION FANS(5 NOS) AIR WASHER MCC AWU A AND B BLOWERS AND PUMPS ARCW PUMPS A AND B FROM STN LT SWGR FROM STN LT SWGR 630 A 400 A 23
  • 39. 415V ESP SWITCHGEAR BOARD-A BOARD-B ESP PASS I AND II FIELDS ESP PASS I AND II AUX SUPPLY ESP ZERO FIELD AND AUX PANEL ESP A/C ESP A/C PACKAGE UNIT ESP PASS III AND IV FIELDS ESP PASS III AND IV AUX SUPPLY APH FIRE DETECTOR WELDING SUPPLY(SPARE) ESP TRF-A 6.6/.433 KV 1.25 MVA ESP TRF-B 6.6/.433 KV 1.25 MVA FROM UNIT SWGR-A FROM UNIT SWGR-B BC 24
  • 40.
  • 41.
  • 42. DC SYSTEM OF RAMAGUNDAM  TO OPERATE FROM BATTERIES FOR ATLEAST 60 MINUTES FOLLOWING COMPLETE FAILURE OF ALL AC SUPPLIES  TO OPERATE FROM BATTERIES FOR ATLEAST 10 HRS FOLLOWING FAILURE OF ALL BATTERY CHARGERS
  • 43. DC LOADS  INSTRUMENTS  INDICATIONS, ANNUNCIATIONS & ALARMS  SWITCHGEAR CLOSING & TRIPPING  CONTROLS,PROCTECTION & INTERLOCKS  TELECOMMUNICATIONS  PLCC & PA SYSTEM  DC LIGHTING  DC DRIVES
  • 44. DC SYSTEM  BATTERY CHARGERS [TWO/THREE]  BATTERY BANKS [ONE/TWO]  DC DISTRIBUTION BOARDS [ONE/TWO]  DC FUSE BOARDS  UN EARTHED SYSTEM  CHARGER TROUBLE, DC EARTH FAULT AND DC VOLTAGE ABNORMAL ALARMS IN UCB
  • 45. 220 V UNIT DCDB BOOST CHARGER BATTERY BANK FLOAT MAIN FLOAT S/B ELECTROMAGNETIC BOARD-1 TIEFEEDER LOGICDB DCLTG A ELECTROMAGNETIC BOARD-2 220 V DCDB 500 A X SW4 SW3 SW4 SW4 •CONTACTOR X OPENS ON BOOST CHARGER ON TIE FEEDERS TO UNITS: UNIT- 1: FROM UNIT –2 DCDB FROM SWYD DCDB SEC-1 UNIT-2 : FROM UNIT – 1 DCDB FROM UNIT- 3 DCDB UNIT- 3 : FROM UNIT- 2 DCDB DCEOPSTARTER PANLE DCSEALOILPANEL 26
  • 46. UNIT-1 A: DC SOURCES FOR 6.6 KV UNIT SWGR A AND B MAIN 415 UNIT SWGR - A AND B EMCC I/C-1 & EMCC I/C –2 6.6 KV STN SWGR 1S1 AND 1S2 MAIN 6.6 KV STN SWGR 2S1 AND 2S2 MAIN 415 STN SWGR - 1A AND 1B MAIN 415 STN SWGR - 2A AND 2B MAIN UNIT-1 MLDB AIR COMPRESSOR ANNUNCIATION PANEL 6.6 KV COMRESSOR SWGR 1 DG SWGR PANEL-2 ESP SWGR INTERCOM EMERGENCY SUPPLY UNIT-2 A: DC SOURCES FOR 6.6 KV UNIT SWGR A AND B MAIN 415 UNIT SWGR - A AND B 6.6 KV UNIT SWGR – 3A & 3B STANDBY 6.6 KV UNIT SWGR – 1A & 1B STANDBY 415 UNIT SWGR - 3A AND 3 B STANDBY EMCC I/C-1 EMCC I/C –2 ESP SWGR DC FUSE BOARD – 1 -UCR AC -STN LT 1 & 2 -STN SWGR IS1 & 2S1 -CSSAEP DC FUSE BOARD – 2 -STN LT 3 & 4 -STN SWGR IS2 & 2S2 -UNIT – 1 LT SWGR - DG SWGR INTERCOM EMERGENCY SUPPLY UNIT-3 A: DC SOURCES FOR 6.6 KV UNIT SWGR A AND B MAIN 415 UNIT SWGR - A AND B 6.6 KV UNIT SWGR – 2A & 2B STANDBY 415 V UNIT SWGR – 2A & 2B STANDBY EMCC I/C-1 EMCC I/C –2 ESP SWGR INTERCOM EMERGENCY SUPPLY 220 V UNIT DCDB SUPPLY DISTRIBUTION 27
  • 47.
  • 48. ASH SLURRY LT SWITCHGEAR AS TRF-1 6.6 / .433 KV 1.6 / 2 MVA SPARE-3NOS H2PLANTMCC ASSERIES-1 ASSERIES-2 FOUNLOADING MCC ASSERIES-3 CANTEEN SUPPLY ASMCC SERVIVE WATERMCC SEC-A B/C--2B/C-1 AS TRF-3 6.6 / .433 KV 1.6 / 2 MVA SPARE CHIMNEYMCC-1 PRESSUREPARTS MAINTWORKSHOP CHIMNEYMCC-2 SEALWATER PUMP-3 FOPRESSURISING MCC SPARE ASSERIES4 ASSEIRS-5 H2PLANTMCC AS TRF-2 6.6 / .433 KV 1.6 / 2 MVA SEC-C SEC-B FROM 1S1 FROM 2S1 FROM 2S2 CANTEENSUPPLY 30
  • 49. 6.6 KV CW SWITCHGEAR 1CW2 2CW2 2CW11CW1 B/C B/C CTLTXFMER-1 AW&FFXFMER-1 CWP/P-1 CWP/P-2 SPARE RAWWATER SWGRSEC-A CWP/P-5 CWP/P-6 LWTPXFMR-1 DMERVICE XFMER-1(STAGE-II) CTLTXFMER-3 WAGONTIPPLER XFMER-1 WAGONTIPPLER XFMER-2 CWP/P-3 CWP/P-4 DMERVICEXFMER-2 STAGE-II CTLTXFMER-4 CTLTXFMER-2 CWP/P-7 AW&FFXFMER-2 TIETORAWWATER SWGRSEC-B CTLTGXFMER RAWWATER P/P-6 RAWWATER P/P-3 CW XFMER-1 33 /6.6/6.6 KV 20/25 MVA CW XFMER-2 33 /6.6/6.6 KV 20/25 MVA FROM 33 KV SWGR SEC-A FROM 33 KV SWGR SEC-B TIEFROM 2S1SWGR BUSVT BUSVT BUSVT BUSVT LWTPXFMR-2 37 NOTE: ALL SECTIONS HAVE LINE PT CUBICLES
  • 50. 6.6 KV CW1 / CW2 / WTP SWITCHGEAR BUSCOUPLER    PROTECTIONS    Remote trip  Local trip   Mech.trip   Elect.trips from  • E/F Relay •   IDMT  O/C: R,Y,B phases.    INTERLOCKS • Trips when both Incomers are ON  in service position with trip  selection in buscoupler. • Closes  on auto if the following  conditions are satisfied.  Any incomer trip and No  fault on this section  Bus under voltage operated  Buscoupler selection in  auto PERMISSIVES • No elect trip from • E/F Relay • IDMT O/C: R,Y,B phases. •No elect trip from any of the Incomers. • No Continuous close command 67
  • 51. CLARIFIEDWATERPUMP-7 FROM 33 KV SWGR SEC-A 6.6 KV WTP SWITCHGEAR SEC-A SEC-B FROM 33 KV SWGR SEC-B CLARIFIEDWATERPUMP-1 CLARIFIEDWATERPUMP-3 CLARIFIEDWATERPUMP-5 WTPLTXFMR-1 SATCOMXFMR-1 CLARIFIEDWATERPUMP-6 CLARIFIEDWATERPUMP-4 CLARIFIEDWATERPUMP-2 WTPLTXFMR-2 SATCOMXFMR-2 B/C WTP XFMR-1 33 / 6.9 KV 5 MVA WTP XFMR-2 33 / 6.9 KV 5 MVA BUSVT BUSVT SPARE 44 NOTE: BOTH SECTIONS HAVE LINE PT CUBICLES
  • 52.
  • 53. Indicates breaker in open condition Indicates breaker in close condition closed B/C 2 open Col I Col II Col IIIRDM I RDM II From SEC F Sec B Sec A #1 #2 #3 NEW COLONY SWITCHGEAR AS ON 25/05/05 B/C 1 All Transformers are 4MVA