SlideShare a Scribd company logo
1 of 22
INDUSTRIAL TRAINING ON
19/09/2022- 24/09/2022
AT 66 kV substation, Alappuzha
TEAM MEMBERS
1. Sharon Shaji
2. Deefuljith Divakaran
3. Janasudhan K
Alappuzha 66kv Substation- In General
66 kV substation Alappuzha is a Substation under KSEB Itd in Alappuzha district.
The ALAPPUZHA 66kV substation is located within the municipal limit of
Alappuzha town at the Eastern side of NH 66 and the Northern side of V.C.N.B
road. This substation mainly feeds almost all the consumers of Alappuzha
Municipality through the 13 (thirteen) 11kV outgoing feeders. In addition to this,
the 66kV Substation at Pathirappally is also normally fed from this substation
through Alappuzha-Pathirappally 6ALPT 66 kV feeder.
Normal supply is taken from 220 kV Substation Punnapra through Punnapra-
Alappuzha 66kV Double Circuit (6PUAL NO. 1 & 2) 66kV feeders. As a standby
source, 66kV supply from 220kV substation, Pallom supply is kept available to
this station through Kuttanadu Substation via Kuttanadu-Alappuzha (6KTAL)
66kV single circuit feeder. The 66kV switch yard of this substation is having 7
(seven) Bays with parallel duplicate bus arrangements.
SINGLE LINE DIAGRAM OF 66 KV
SUBSTATION
66KV FEEDERS
There are four 66Kv feeders in this substation.
 6ALPT 66kV feeder( ALPY-PATHIRAPPALLY 66 kV feeder)
 6 KTAL 66kV feeder (KUTTANAD-ALPY 66kV feeder)
 6 PUAL No.1 66kv feeder(PUNNAPRA-ALPY No.1 66Kvfeeder)
 6 PUAL No.2 66kv feeder(PUNNAPRA-ALPY No.2 66Kvfeeder)
FEEDER BAY - (GENERAL)
The 66 kV feeder bay consists of the following equipments.
 1. Lightening arrester
 2. Potential transformer
 3. Line isolator with Earth switch
 4. Current transformer
 5. SF6 Circuit Breaker
SUBSTATION YARD
POWER TRANSFORMER
 The substation has three nos of Power Transformers.
16 MVA 66/11kV, Transformer no 2 with OLTC (TOSHIBA MAKE)
10 MVA 66/11kV, Transformer no 3 with OLTC (TELK MAKE)
16 MVA, 66/ 11kV, Transformer no 1 with OLTC (TELK MAKE)
All the three transformers are controlled by 1500 MVA, SF6 circuit
breakers(CROMPTON GREAVES MAKE).
 The remote and manual control of the breakers are possible. Since we are having a
double bus system, there are 2 nos 66Kv bus isolators installed for each transformer bay.
 Each transformer bay consist of 2 bus isolators, SF6 circuit breaker (SF6 CB), current
transformer (CT) and lightning arresters (LA).
16 MVA, 66/11kVTransformer with on load
tap changer
MAKE TELK
KVA HV 12500/16000
LV 12500/16000
VOLT HV 66000
LV 11000
AMPERE HV 109/140
LV 657/841
Type of connection Star/star
No of phases 3
Frequency 50 Hz
C&R panel make ALIND
Type of cooling ONAN/ONAF
Impedance voltage 10.19%
Vector group YNyn0
Year of manufacture 2015
No of tap positions 11
Normal tap positions 3
10 MVA, 66/11kVTransformer with on load
tap changer
MAKE TELK
KVA HV 10000
LV 10000
VOLT HV 66000
LV 11000
AMPERE HV 87.6
LV 525
Type of connection Star/star
No of phases 3
Frequency 50 Hz
C&R panel make ALIND
Type of cooling ONAN
Impedance voltage 9.83%
Vector group YNyn0
Year of manufacture 2004
No of tap positions 11
Normal tap positions 3
TRANSFORMER PROTECTION
SCHEMES
1.Differential protection
 It employs differential relay(87).
 It mainly responds to those faults which occur in the differential protection zone of the
transformer, which includes the region between primary and secondary side CTs of the
transformer.
2. Restricted Earth Fault(REF) Protection
 It employs REF(64) relay. It protects the transformer from internal earth fault.
3. Over current and Earth fault Protection
 It employs the relays 51 (Over Current Relay) and 51N (Earth Fault Relay).
 They are used for protection of transformer from external short circuits and excessive
over load.
4.Buccholz Protection Scheme
 It employs buccholz relay which is sensitive to the effects of dielectric failure inside the
transformer.
5.Winding temperature and Oil temperature Indicators
 They are precision instruments that monitor the temperature rise of oil and windings.
 They operate the alarm or the circuit breaker when the recorded temperature exceeds a pre-
set value.
IMPORTANT RELAYS IN TRANSFORMER
Name of relay T/F lll T/F ll T/F l
Differential
relay
87, Alind 87, Siemens 87, Alind
Buccholz relay 30A, Alind 30AABB 30AAlind
Master trip
relay
86, Alind 86,ABB 86, Alind
REF relay 64R, Alind 64, Alstom 64, Alstom
Over current
&
Earth fault
relay
50/51 N, 50/51
R,
50/51 B, Alind
-
50/51 N, 50/51
R,
50/51 B, Alind
PT selection
relay
30 B, Alind - 30 B, Alind
DC
supervision
relay
30 C, Alind 80 DC, ABB 30 C, Alind
Directional
numerical
O/C and E/F
relay
-
67/67 N
Siemens
-
OPERATION TO BE CARRIED OUT OF ON
OCCURENCE OF FOLLOWING ALARMS
1. Buccholz alarm
 When the Buccholz alarm rings, accept the alarm and note down the relay and
annunciator indications.
 Inform the matter to the station Engineer.
 Observe the transformer for any abnormal heating or sound.
 Observe if any abnormality is seen on the transformer.
 Switch off and Isolate the transformer after intimating the higher officials...
2. Temperature alarm (oil and winding)
 The oil temperature and winding temperature alarm will be activated when
the temperature of oil or winding exceeds a pre-set value.
 This can be due to some faults inside the transformer such as inter turn
shorts, loose contacts etc. Or due to overload.
 If the cause is overload, make arrangements to reduce the load of the
transformer immediately.
 If the cause is not overload, immediately switch off and isolate the
transformer
 Inform the Station Engineer Inspect the temperature gauge.
 Charge the transformer only after the rectification of the fault.
SF6 CIRCUIT BREAKER
PERMIT TO WORK ON A
TRANSFORMER
1. Confirm that the total load of the Transformer which is under permit to work can be
safely transferred to remaining transformers in service.
2. Switch off 11 KV feeders under the transformer.
3. Switch off, confirm all three ammeter readings are zero & isolate the VCB of incomer
on which permit is to be issued and provide "CAUTION SUPPLY BACK FED" board4.
4. Rack in the VCB of Bus Coupler No I or II and charge its VCB.
5. Charge 11 kV feeders.
6. Switch off the SF6 breaker of transformer and isolate the same from the live buses
(open both bus 18:11 isolators and provide "CAUTION SUPPLY AVAILABLE" board).
7. Switch off AC and DC control supply (if necessary) and check for any supply in the
marshalling box. Provide "PERMIT TO WORK board on TF control panel.
8. Switch off the SF6 breaker of 16MVA transformer 1 and isolate the same from the live
buses (open both bus 1811 isolators and provide CAUTION SUPPLY AVAILABLE"
board), Switch off AC and DC control supply (if necessary) and check for any supply in the
marshalling box. Provide "PERMIT TO WORK board or control panel.18/977.
9. Earth the HVLV&SF6 terminals of the transformer.
10. Fix caution board on every point of switching off and isolation made, encircle the
working area with a caution ribbon and keep the keys, if any in custody, and issue permit to
work and get it signed. Note the points earthed in the permit form along with the number of
earth rods.
11.Monitor the load on the Transformer in service and make arrangements with the
Distribution authorities to limit the load to the admissible maximum load.
SAFETY EQUIPMENT TO BE USED
1. Earth rods
2. Safety belts
3. Ropes and ladders
4. Caution ribbon
5. Safety helmets and safety shoes
6. Tool baskets
7. LV/ HV gloves
8. Chain block
9. Multimeter
RELAY CLASS

More Related Content

Similar to Presentation (2).pptx

power house training seminar
power house training seminarpower house training seminar
power house training seminarParas kumar
 
132 KV Substation Gajraula.pptx
132 KV Substation Gajraula.pptx132 KV Substation Gajraula.pptx
132 KV Substation Gajraula.pptxAsif682330
 
Anurag Attri.pptx
Anurag Attri.pptxAnurag Attri.pptx
Anurag Attri.pptxAsif682330
 
C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)saurabhVEC
 
Thesis grid station 1.pdf
Thesis grid station 1.pdfThesis grid station 1.pdf
Thesis grid station 1.pdfRashidali731283
 
WBSETCL Subhash Gram 220KV Substation Training Report
WBSETCL Subhash Gram 220KV Substation Training ReportWBSETCL Subhash Gram 220KV Substation Training Report
WBSETCL Subhash Gram 220KV Substation Training ReportArijit Basu
 
Srijan tripathi(220kv gss) ppt
Srijan tripathi(220kv gss) pptSrijan tripathi(220kv gss) ppt
Srijan tripathi(220kv gss) pptsrijan tripathi
 
ppt on summer training on uppcl
ppt on summer training on uppclppt on summer training on uppcl
ppt on summer training on uppclSunny Daksh
 
400kv-Substation-Training-report-Unnao-India.ppt
400kv-Substation-Training-report-Unnao-India.ppt400kv-Substation-Training-report-Unnao-India.ppt
400kv-Substation-Training-report-Unnao-India.pptMarcWorld
 
Power transformer testing and commissioning guidelines r
Power transformer testing and commissioning guidelines rPower transformer testing and commissioning guidelines r
Power transformer testing and commissioning guidelines rAshish Patel
 
Industrial training 220 KV moradabad
Industrial training 220 KV moradabadIndustrial training 220 KV moradabad
Industrial training 220 KV moradabadMONU KUMAR
 
Substation Training presentation
Substation Training presentationSubstation Training presentation
Substation Training presentationKamal Mittal
 
ABB MV Indoor Voltage Transformer : Indoor Cast Resin Voltage Transformer ABB...
ABB MV Indoor Voltage Transformer : Indoor Cast Resin Voltage Transformer ABB...ABB MV Indoor Voltage Transformer : Indoor Cast Resin Voltage Transformer ABB...
ABB MV Indoor Voltage Transformer : Indoor Cast Resin Voltage Transformer ABB...Thorne & Derrick International
 
220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance220 KV Substation Operation & Maintenance
220 KV Substation Operation & MaintenanceHimansu Pradhan
 
INTERNSHIP REPORT-ORIGINAL (Autosaved)
INTERNSHIP REPORT-ORIGINAL (Autosaved)INTERNSHIP REPORT-ORIGINAL (Autosaved)
INTERNSHIP REPORT-ORIGINAL (Autosaved)Asafak Husain
 

Similar to Presentation (2).pptx (20)

power house training seminar
power house training seminarpower house training seminar
power house training seminar
 
INTERFACING.ppt
INTERFACING.pptINTERFACING.ppt
INTERFACING.ppt
 
132 KV Substation Gajraula.pptx
132 KV Substation Gajraula.pptx132 KV Substation Gajraula.pptx
132 KV Substation Gajraula.pptx
 
Anurag Attri.pptx
Anurag Attri.pptxAnurag Attri.pptx
Anurag Attri.pptx
 
C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)
 
Ashish.pptx
Ashish.pptxAshish.pptx
Ashish.pptx
 
rough.pptx
rough.pptxrough.pptx
rough.pptx
 
Thesis grid station 1.pdf
Thesis grid station 1.pdfThesis grid station 1.pdf
Thesis grid station 1.pdf
 
WBSETCL Subhash Gram 220KV Substation Training Report
WBSETCL Subhash Gram 220KV Substation Training ReportWBSETCL Subhash Gram 220KV Substation Training Report
WBSETCL Subhash Gram 220KV Substation Training Report
 
132 kV uppcl
132 kV uppcl132 kV uppcl
132 kV uppcl
 
Summer Training presentation on 132/33 KV sub-station Minto park, Allahabad
Summer Training presentation on 132/33 KV sub-station Minto park, AllahabadSummer Training presentation on 132/33 KV sub-station Minto park, Allahabad
Summer Training presentation on 132/33 KV sub-station Minto park, Allahabad
 
Srijan tripathi(220kv gss) ppt
Srijan tripathi(220kv gss) pptSrijan tripathi(220kv gss) ppt
Srijan tripathi(220kv gss) ppt
 
ppt on summer training on uppcl
ppt on summer training on uppclppt on summer training on uppcl
ppt on summer training on uppcl
 
400kv-Substation-Training-report-Unnao-India.ppt
400kv-Substation-Training-report-Unnao-India.ppt400kv-Substation-Training-report-Unnao-India.ppt
400kv-Substation-Training-report-Unnao-India.ppt
 
Power transformer testing and commissioning guidelines r
Power transformer testing and commissioning guidelines rPower transformer testing and commissioning guidelines r
Power transformer testing and commissioning guidelines r
 
Industrial training 220 KV moradabad
Industrial training 220 KV moradabadIndustrial training 220 KV moradabad
Industrial training 220 KV moradabad
 
Substation Training presentation
Substation Training presentationSubstation Training presentation
Substation Training presentation
 
ABB MV Indoor Voltage Transformer : Indoor Cast Resin Voltage Transformer ABB...
ABB MV Indoor Voltage Transformer : Indoor Cast Resin Voltage Transformer ABB...ABB MV Indoor Voltage Transformer : Indoor Cast Resin Voltage Transformer ABB...
ABB MV Indoor Voltage Transformer : Indoor Cast Resin Voltage Transformer ABB...
 
220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance
 
INTERNSHIP REPORT-ORIGINAL (Autosaved)
INTERNSHIP REPORT-ORIGINAL (Autosaved)INTERNSHIP REPORT-ORIGINAL (Autosaved)
INTERNSHIP REPORT-ORIGINAL (Autosaved)
 

Recently uploaded

kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadhamedmustafa094
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
Moment Distribution Method For Btech Civil
Moment Distribution Method For Btech CivilMoment Distribution Method For Btech Civil
Moment Distribution Method For Btech CivilVinayVitekari
 
Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxchumtiyababu
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxSCMS School of Architecture
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptNANDHAKUMARA10
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdfAldoGarca30
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdfKamal Acharya
 
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEGEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEselvakumar948
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxMuhammadAsimMuhammad6
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...Amil baba
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...drmkjayanthikannan
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesRAJNEESHKUMAR341697
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiessarkmank1
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwaitjaanualu31
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationBhangaleSonal
 

Recently uploaded (20)

kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal load
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Moment Distribution Method For Btech Civil
Moment Distribution Method For Btech CivilMoment Distribution Method For Btech Civil
Moment Distribution Method For Btech Civil
 
Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptx
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEGEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planes
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 

Presentation (2).pptx

  • 1. INDUSTRIAL TRAINING ON 19/09/2022- 24/09/2022 AT 66 kV substation, Alappuzha
  • 2. TEAM MEMBERS 1. Sharon Shaji 2. Deefuljith Divakaran 3. Janasudhan K
  • 3. Alappuzha 66kv Substation- In General 66 kV substation Alappuzha is a Substation under KSEB Itd in Alappuzha district. The ALAPPUZHA 66kV substation is located within the municipal limit of Alappuzha town at the Eastern side of NH 66 and the Northern side of V.C.N.B road. This substation mainly feeds almost all the consumers of Alappuzha Municipality through the 13 (thirteen) 11kV outgoing feeders. In addition to this, the 66kV Substation at Pathirappally is also normally fed from this substation through Alappuzha-Pathirappally 6ALPT 66 kV feeder. Normal supply is taken from 220 kV Substation Punnapra through Punnapra- Alappuzha 66kV Double Circuit (6PUAL NO. 1 & 2) 66kV feeders. As a standby source, 66kV supply from 220kV substation, Pallom supply is kept available to this station through Kuttanadu Substation via Kuttanadu-Alappuzha (6KTAL) 66kV single circuit feeder. The 66kV switch yard of this substation is having 7 (seven) Bays with parallel duplicate bus arrangements.
  • 4. SINGLE LINE DIAGRAM OF 66 KV SUBSTATION
  • 5. 66KV FEEDERS There are four 66Kv feeders in this substation.  6ALPT 66kV feeder( ALPY-PATHIRAPPALLY 66 kV feeder)  6 KTAL 66kV feeder (KUTTANAD-ALPY 66kV feeder)  6 PUAL No.1 66kv feeder(PUNNAPRA-ALPY No.1 66Kvfeeder)  6 PUAL No.2 66kv feeder(PUNNAPRA-ALPY No.2 66Kvfeeder)
  • 6. FEEDER BAY - (GENERAL) The 66 kV feeder bay consists of the following equipments.  1. Lightening arrester  2. Potential transformer  3. Line isolator with Earth switch  4. Current transformer  5. SF6 Circuit Breaker
  • 8. POWER TRANSFORMER  The substation has three nos of Power Transformers. 16 MVA 66/11kV, Transformer no 2 with OLTC (TOSHIBA MAKE) 10 MVA 66/11kV, Transformer no 3 with OLTC (TELK MAKE) 16 MVA, 66/ 11kV, Transformer no 1 with OLTC (TELK MAKE) All the three transformers are controlled by 1500 MVA, SF6 circuit breakers(CROMPTON GREAVES MAKE).  The remote and manual control of the breakers are possible. Since we are having a double bus system, there are 2 nos 66Kv bus isolators installed for each transformer bay.  Each transformer bay consist of 2 bus isolators, SF6 circuit breaker (SF6 CB), current transformer (CT) and lightning arresters (LA).
  • 9. 16 MVA, 66/11kVTransformer with on load tap changer
  • 10. MAKE TELK KVA HV 12500/16000 LV 12500/16000 VOLT HV 66000 LV 11000 AMPERE HV 109/140 LV 657/841 Type of connection Star/star No of phases 3 Frequency 50 Hz C&R panel make ALIND Type of cooling ONAN/ONAF Impedance voltage 10.19% Vector group YNyn0 Year of manufacture 2015 No of tap positions 11 Normal tap positions 3
  • 11. 10 MVA, 66/11kVTransformer with on load tap changer
  • 12. MAKE TELK KVA HV 10000 LV 10000 VOLT HV 66000 LV 11000 AMPERE HV 87.6 LV 525 Type of connection Star/star No of phases 3 Frequency 50 Hz C&R panel make ALIND Type of cooling ONAN Impedance voltage 9.83% Vector group YNyn0 Year of manufacture 2004 No of tap positions 11 Normal tap positions 3
  • 13. TRANSFORMER PROTECTION SCHEMES 1.Differential protection  It employs differential relay(87).  It mainly responds to those faults which occur in the differential protection zone of the transformer, which includes the region between primary and secondary side CTs of the transformer. 2. Restricted Earth Fault(REF) Protection  It employs REF(64) relay. It protects the transformer from internal earth fault. 3. Over current and Earth fault Protection  It employs the relays 51 (Over Current Relay) and 51N (Earth Fault Relay).  They are used for protection of transformer from external short circuits and excessive over load.
  • 14. 4.Buccholz Protection Scheme  It employs buccholz relay which is sensitive to the effects of dielectric failure inside the transformer. 5.Winding temperature and Oil temperature Indicators  They are precision instruments that monitor the temperature rise of oil and windings.  They operate the alarm or the circuit breaker when the recorded temperature exceeds a pre- set value.
  • 15. IMPORTANT RELAYS IN TRANSFORMER Name of relay T/F lll T/F ll T/F l Differential relay 87, Alind 87, Siemens 87, Alind Buccholz relay 30A, Alind 30AABB 30AAlind Master trip relay 86, Alind 86,ABB 86, Alind REF relay 64R, Alind 64, Alstom 64, Alstom Over current & Earth fault relay 50/51 N, 50/51 R, 50/51 B, Alind - 50/51 N, 50/51 R, 50/51 B, Alind PT selection relay 30 B, Alind - 30 B, Alind DC supervision relay 30 C, Alind 80 DC, ABB 30 C, Alind Directional numerical O/C and E/F relay - 67/67 N Siemens -
  • 16. OPERATION TO BE CARRIED OUT OF ON OCCURENCE OF FOLLOWING ALARMS 1. Buccholz alarm  When the Buccholz alarm rings, accept the alarm and note down the relay and annunciator indications.  Inform the matter to the station Engineer.  Observe the transformer for any abnormal heating or sound.  Observe if any abnormality is seen on the transformer.  Switch off and Isolate the transformer after intimating the higher officials...
  • 17. 2. Temperature alarm (oil and winding)  The oil temperature and winding temperature alarm will be activated when the temperature of oil or winding exceeds a pre-set value.  This can be due to some faults inside the transformer such as inter turn shorts, loose contacts etc. Or due to overload.  If the cause is overload, make arrangements to reduce the load of the transformer immediately.  If the cause is not overload, immediately switch off and isolate the transformer  Inform the Station Engineer Inspect the temperature gauge.  Charge the transformer only after the rectification of the fault.
  • 19. PERMIT TO WORK ON A TRANSFORMER 1. Confirm that the total load of the Transformer which is under permit to work can be safely transferred to remaining transformers in service. 2. Switch off 11 KV feeders under the transformer. 3. Switch off, confirm all three ammeter readings are zero & isolate the VCB of incomer on which permit is to be issued and provide "CAUTION SUPPLY BACK FED" board4. 4. Rack in the VCB of Bus Coupler No I or II and charge its VCB. 5. Charge 11 kV feeders. 6. Switch off the SF6 breaker of transformer and isolate the same from the live buses (open both bus 18:11 isolators and provide "CAUTION SUPPLY AVAILABLE" board). 7. Switch off AC and DC control supply (if necessary) and check for any supply in the marshalling box. Provide "PERMIT TO WORK board on TF control panel.
  • 20. 8. Switch off the SF6 breaker of 16MVA transformer 1 and isolate the same from the live buses (open both bus 1811 isolators and provide CAUTION SUPPLY AVAILABLE" board), Switch off AC and DC control supply (if necessary) and check for any supply in the marshalling box. Provide "PERMIT TO WORK board or control panel.18/977. 9. Earth the HVLV&SF6 terminals of the transformer. 10. Fix caution board on every point of switching off and isolation made, encircle the working area with a caution ribbon and keep the keys, if any in custody, and issue permit to work and get it signed. Note the points earthed in the permit form along with the number of earth rods. 11.Monitor the load on the Transformer in service and make arrangements with the Distribution authorities to limit the load to the admissible maximum load.
  • 21. SAFETY EQUIPMENT TO BE USED 1. Earth rods 2. Safety belts 3. Ropes and ladders 4. Caution ribbon 5. Safety helmets and safety shoes 6. Tool baskets 7. LV/ HV gloves 8. Chain block 9. Multimeter