This document discusses a waste heat recovery turbine project at a 200 MW diesel engine power plant in Chennai, India. The plant recovers heat from engine exhaust using a heat recovery steam generator and steam turbine to generate 600 kW of additional power. Installed in 2011, the turbine saves $300,000 per year in energy costs and will save $4.5 million over its 15-year lifetime. The project has an payback period of less than 2 years and provides environmental benefits like reduced carbon emissions.