Integrating fuel cell systems in critical industrial processes
1. Main Headquarters: 120 Water Street, Suite 350, North Andover, MA 01845 With offices in: NY, ME, TX, CA, OR www.ers-inc.com
ASSESSMENT OF FUEL CELL
APPLICATIONS FOR CRITICAL
INDUSTRIAL PROCESSES
presented by
Dan Birleanu
ENERGY & RESOURCE SOLUTIONS
2. īą Power Quality and Critical Applications
īą Premium Power Equipment
īą Overview of Fuel Cell Technology
īą Fuel Cells Current Challenges
īą Feasibility Assessment Methodology
īą Case Study: Semiconductor Crystal Growth Facility
īą Conclusions
ASSESSMENT OF FUEL CELL APPLICATIONS
FOR CRITICAL INDUSTRIAL PROCESSES
6/9/2014 2
3. īą High Voltage Spikes and Surges
īą Low Voltage Electrical Noise
īą Harmonics
īą Voltage Fluctuations
īą Power Outages and Interruptions
POWER QUALITY AND CRITICAL
APPLICATIONS
4. īą Medical Treatment Facilities
īą Advanced Manufacturing Facilities
īą Communication and Data Centers
īą High-Security Facilities
īą Remote Sites
īą Air Traffic Control Facilities
POWER QUALITY AND CRITICAL
APPLICATIONS (CONT.)
5. īą Requirements
ī Availability: Respond in Milliseconds without
Significant Distortions
ī Reliability: 99.999âĻ%
ī Maintainability: Easily Accessible while
Maintaining Availability
īą Technologies
ī Energy Storage: Batteries, Flywheel, Super-
capacitors, Super-conducting Magnetic Energy
Storage (SMES), Compressed Air Storage (CAES)
ī Back-up Power: Generator Sets, Micro-turbines,
Small Gas Turbines, Fuel Cells.
PREMIUM POWER EQUIPMENT
6. PAFC PEMFC MCFC SOFC
Size Range 100-200 kW 3-250 kW 250 kW - 10 MW 1 kW - 10 MW
Fuel H ydrogen, Natural
Gas, Landfill Gas,
Digester Gas, Propane
Natural Gas,
H ydrogen, Propane,
Diesel
Natural Gas,
H ydrogen
Natural Gas, H ydrogen,
Landfill Gas, Fuel Oil
Capacity 0.1-0.3 W/cm2
0.6-0.8 W/cm2
0.1-0.2 W/cm2
0.3-0.5 W/cm2
Efficiency 36-42% 30-40% 45-55% 45-60%
Environment Nearly zero emissions
(when running on H 2)
Nearly zero emissions
(when running on H 2)
Nearly zero emissions
(when running on H 2)
Nearly zero emissions
(when running on H 2)
Other
Features
Cogeneration (H ot
Water)
Cogeneration (H ot
Water)
Cogeneration (H ot
Water or Steam)
Cogeneration (H ot
Water or Steam)
Estimative
Cost
$4,000 per kW $5,000 per kW $2,000-$4,000 per
kW
$1,300 per kW (Desired)
Commercial
Status
Available Pre-commercial Pre-commercial Pre-commercial
Strengths Quiet
Low Emissions
H igh Efficiency
Proven Reliability
Quiet
Low Emissions
H igh Efficiency
Quiet
Low Emissions
H igh Efficiency
Quiet
Low Emissions
H igh Efficiency
Weaknesses H igh Cost H igh Cost
Need to Demonstrate
Limited Field Test
Experience
H igh Cost
Need to Demonstrate
H igh Cost
Need to Demonstrate
OVERVIEW OF FUEL CELL
TECHNOLOGY
7. PAFC ī§ī Reduction of manufacturing and operating costs
ī§ī Further improved durability and reliability
ī§ī Reducing space requirements
ī§ī Improving heat recovery potentials
ī§ī Staying economically competitive with other fuel cell technologies as they mature
PEMFC ī§ī Reduction of manufacturing and operating costs
ī§ī Understanding the influences of operating conditions
ī§ī Understanding transient load response
ī§ī Improve fuel processing to accommodate different type of fuels
ī§ī Improve cold-start
ī§ī Catalyst loading
MCFC ī§ī Reduction of manufacturing and operating costs
ī§ī Reducing the rate of cathode dissolution
ī§ī Improve retention of the electrolyte
ī§ī Improving resistance to catalyst poisoning
SOFC ī§ī Reduction of manufacturing and operating costs
ī§ī Identifying configurations that require less stringent material purity specifications
ī§ī Use of less exotic alloys, which is directly related to the high operating temperature
ī§ī Maintenance of seals and manifolds under severe thermal stresses
FUEL CELLS CURRENT
CHALLENGES
8. īą Description of the Operation and Need for Premium Power
ī Applicable End Uses and Equipment
ī Utility Usage
ī Outage and Low Power Quality History
ī Technical Impacts of Downtime
ī Cost Impacts of Outage and Low Power Quality Incidents
ī Capital Project Financing and Investment Requirements
īą Assessment of Power Quality
ī Critical Equipment Service Lines
ī Tolerance Range of Critical Equipment
ī Impact Assessment of Power Quality
FEASIBILITY ASSESSMENT METHODOLOGY
9. īą Assessment of Economic Losses Associated with Power
Reliability and Power Quality Problems
ī Estimates of Economic Impacts
ī Technical and Economic Scenarios
īą Research and Review of the Premium Power Systems
Technical Options
ī Review of Premium Power Systems
ī Considered Technologies: Features and Advantages
īą Preliminary Technical and Economic Screening of Options
ī Simplified Estimates of Energy Impacts
ī Simplified Estimates of Costs
ī Simplified Estimates of Economic Impacts
FEASIBILITY ASSESSMENT METHODOLOGY
(CONT.)
10. īą Preparation of Conceptual Design for Cost-Effective Application
ī Site-Specific Systems Components
ī Desired Location Requirements
ī Detailed Conceptual Design
īą System Cost Estimation
īą Detailed Energy, Environmental and Economic Analyses
ī System Modeling
ī Environmental Impact
ī Life Cycle Cost Analyses
FEASIBILITY ASSESSMENT METHODOLOGY
(CONT.)
11. īą Molecular Beam Epitaxy (MBE) Process
īą Facility Descriptors
ī Demand: 2.5 MW
ī Critical Demand: 1.5 MW
ī Energy Usage: 20 million kWh annually
ī Two Separate Feeding Circuits from the Utility Network
ī UPS Batteries Capacity: 600 kW
ī Emergency Generators Capacity: 1.5 MW
īą Critical Systems
ī Ultra-High Vacuum System
ī Heating System (Crystal Growth Process @ 1,700 F)
ī Cooling System (1,700 Tons)
CASE STUDY: SEMICONDUCTOR CRYSTAL GROWTH FACILITY
12. īą Power Quality Incidents
ī Seven Separate Power Outages in 2001
ī Voltage Sags
ī Over Voltages
īą Impact of Power Quality Incidents
ī Shutdown of Crystal Growth Process
ī Process Resume Takes Several Hours
ī Labor Costs: $50,000 per hour
ī Material Losses: up to $500,000 per hour
CASE STUDY: SEMICONDUCTOR CRYSTAL
GROWTH FACILITY (CONT.)
13. PAFC ī§ī Proven reliability: installations in different locations all over the world with
many hours of successful operation
ī§ī Commercially available in sizes that are attractive for the facility (200 kW)
ī§ī For premium power, requires a reliable source of fuel
ī§ī To make it highly cost-effective, requires cogeneration opportunities - which
may not be present
PEMFC ī§ī Not sufficiently proven for this application
ī§ī Commercially available in sizes too small (maximum 50 kW)
ī§ī For premium power, requires a reliable source of fuel
ī§ī To make it highly cost-effective, requires cogeneration opportunities - which
may not be present
MCFC ī§ī Not sufficiently proven for this application
ī§ī Still in the pre-commercial stage
ī§ī For premium power, requires a reliable source of fuel
ī§ī Can produce steam, which could be used in absorption chillers â would require
chiller replacement
SOFC ī§ī Not sufficiently proven for this application
ī§ī Still in the pre-commercial stage
ī§ī For premium power, requires a reliable source of fuel
ī§ī Can produce steam, which could be used in absorption chillers â would require
chiller replacement
CASE STUDY: SEMICONDUCTOR CRYSTAL
GROWTH FACILITY (CONT.)
14. īą Selected Fuel Cell System: UTC Fuel Cells PC25
ī Rated electrical Capacity: 200 kW/235 kVA
ī Thermal Capacity: 900,000 Btu/h @ 140 F
ī Efficiency (LHV): 37% Electric and 50% Thermal
ī Natural Gas Consumption: 2,100 cu.ft./hour
ī Emissions: <2 ppm CO, <1 ppm NOx, negligible SOx
īą Proposed Premium Power System Characteristics and Cost
ī Integration of the Fuel Cells with the Existing Back-up
System
ī Eight (8) Fuel Cell Units
ī Fuel Cells Will Operate 8,000 hours/year
ī Total Estimated Cost: $9,600,000
CASE STUDY: SEMICONDUCTOR CRYSTAL
GROWTH FACILITY (CONT.)
15. CASE STUDY: SEMICONDUCTOR CRYSTAL
GROWTH FACILITY (CONT.)
0
2
4
6
8
10
12
14
16
$500,000 $750,000 $1,000,000 $1,250,000 $1,500,000 $1,750,000 $2,000,000
Total Annual Cost of Losses Due to Power Quality Issues
PaybackPeriod[years]
Payback Period for the Fuel Cell System vs. Cost of Losses
Average Prices (Northeast): Natural Gas â $6.38/ccf and Electricity â $0.0772/kWh
16. īą PAFC and PEMFC Could Provide Clean and Reliable Power
for Critical Industrial Applications
īą Installation Costs Represent a Considerable Barrier to
Widespread Commercialization of the Available Fuel Cell
Systems
īą Cost-effectiveness of the Large Fuel Cell Based Premium
Power Application Rises in the Probability that Major
Events with High Impact on Companyâs Revenues Occur
īą Very Critical Operations (Communication/Data Centers,
Financial Transaction Operations, High-Tech
Manufacturing Facilities) are the most Suitable Applications
for Future Implementation of These Systems
CONCLUSIONS