The relatively new concept of #EarnedSchedule explained by Whizible PMP as a part of the #projectmanagementtraining series. Useful for #projectmanagers and PMO. Also useful for PMP exam as per PMBOK version 6
2. Developed by Walt Lipke, 2003
Included in PMI’s Practice Standard for EVM,
2011
Included in PMI’s PMBOK (6th edition), 2017
Extension to Earned Value Methodology (EVM)
Uses EVM data such as PV & EV.
3. Overcome known shortcomings of EVM
schedule indicators – SV & SPI.
◦ SV concludes at $0 variance and SPI at 1.00 at the
end of project, irrespective of whether the project
finished late or ahead of schedule.
Better predictive ability than EVM schedule
indicators throughout the entire project life.
Provide basis for performing schedule
analysis.
4.
5. To understand how to calculate ES, lets look at an
example. Here is some sample data showing
cumulative values of EV & PV in cost units.
Graphically, ES can be computed by projecting EV
at status period onto PV curve and then taking X-
intercept of this projection, as shown before.
Period
(AT)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
EVcum
95 180 470 770 1065 1315 1610 1900 2150 2275 2425 2555 2695 2770 2823
PVcum
105 200 515 845 1175 1475 1805 2135 2435 2665 2760 2823
10. Cost based Schedule Performance Index: SPI
◦ Reverts to 1.0 at the end of project
0.905 0.900
0.913 0.911 0.906
0.892 0.892 0.890 0.883
0.854
0.879
0.905
0.955
0.981
1.000
0.750
0.800
0.850
0.900
0.950
1.000
1.050
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Schedule Performance Index (Cost based)
SPI = EV/PV
11. Time based Independent Estimate At Completion: IEAC(t)
12. To complete Schedule Performance Index: TSPI
◦ Similar to cost based - To Complete Performance Index
(TCPI)
1.01 1.02 1.02 1.03 1.05 1.09 1.12 1.18
1.32
1.77
3.03
0.50
1.00
1.50
2.00
2.50
3.00
3.50
1 2 3 4 5 6 7 8 9 10 11
To complete Schedule Performance Index
TSPI = (PD-ES)/(PD-AT)
13. E S is derived from existing E V M data
Provides time-based schedule indicators
E S Indicators do not fail for late finish
projects
Schedule prediction is more accurate than
prediction by cost based schedule indicators.
14. With Whizible’s upcoming EVM/ES Analytics Tool,
EVM data can be analyzed to get deeper insights into
the health of a project than traditional EVM analysis
Whizible’s EVM/ES Analytics tool can be used at
project and/or task level where EVM data is available.
Summary data such as periodic & cumulative ES,
SV(t); indicators such as SPI(t) & TSPI; estimates like
IEAC & IECD, and charts are available to be made part
of periodic monitoring and reports.
With these charts & indices, project managers can see
trends in the estimated completion date and cost,
and decide when re-baselining may be appropriate.
15. Whizible is an integrated solution to manage
a projectized service business.
To know more about Whizible, please
Visit: https://www.whizible.com/
Email: info@whizible.com